HomeMy WebLinkAboutContract 52483-A1 AMENDMENT No.1 CSC No. 52483-A1
TO CITY SECRETARY CONTRACT No. 52483
WHEREAS, the City of Fort Worth (CITY) and Halff Associates,
Inc. , (ENGINEER) , made and entered into City Secretary Contract No. 52483,
(the CONTRACT) , which was authorized by M&C No. C-29147 on the 11 day of
June, 2019 in the amount of $ 930, 000. 00 (Nine hundred and Thirty
Thousand Dollars) ; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
CentrePort Trail Phase I and Phase II Project; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a scope of services proposal, a copy of
which is attached hereto and incorporated herein (Attachment A) . The
cost to City for the additional design services to be performed by
Engineer totals $27,000. 00 (see attached Funding Breakdown Sheet, page 3) .
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $957,000. 00.
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
City of Fort Worth --— — — —"
Professional Services Agreement Amendment Template c �, ;,,,
CFW Official Release 9/19/2017 RECEIVED F'M F i'f�'0AL u\'��� LIP,
Page 1 of 3 JUN 3 O ZOZO
CnYOFFORTWORTH
CITY SECRERRY
APPROVED:
City of Fort Worth ENGINEER
Halff Associates, Inc.
Ikjd�—
Valerie Washington(Jun 23,202013:09 CDT)
Valerie Washington David Buchanan
Assistant City Manager Director of Landscape Architecture
DATE: Jun 23, 2020 DATE: Jun 17, 2020
APPROVAL RECOMMENDED:
Dgvid Conk
David Creek(Jun 17,2020 16:01 CDT)
David Creek
Acting Director, Park & Recreation Department
DATE: Jun 17, 2020
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements .
Jing Yang
Project Manager
APPROVED AS TO FORM AND LEGALITY:
M&C: N&C
Zkiil- -lin
Mack(Jun 23,202013:04 CDT) Date. Jun 23, 2020
Douglas W. Black
Assistant City Attorney
ATTEST:
Date. Jun 23, 2020
a'l^�•, ;
Mary J. Kayser '
City Secretary3yf '
1
City of Fort Worth
Professional Services Agreement Amendment Template OFFICIAL RECORD
CFW Official Release 9/19/2017
Page 2 of 3 CITY SECRETARY
FT. WORTH,TX
FUNDING BREAKDOWN SHEET
AMENDMENT No. 1
TO CITY SECRETARY CONTRACT No. 52483
DEPARTMENT FUND-ACCOUNT-CENTER AMOUNT
PARD 31001-5330500-0800450-100082-5030 $27, 000 . 00
City of Fort Worth
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017
Page 3 of 3
MEN
NNE HALFF N ATTACHMENT A Richardson,
North Bowser Road
Richardson,Texas 75081
■ . (214)346-6200
Fax(214)739-0095
ADDITIONAL SERVICES CONFIRMATION
To: Jing Yang Date: June 11, 2020
From: Laura Johnson AVO: 34838.001
Email: LJohnson@halff.com Project: CentrePort Phase I
VIA: email
The City of Fort Worth (CLIENT) has asked Halff Associates (CONSULTANT) to prepare construction
documentation services and design services for CentrePort Trail Phase I beyond the services provided in the
agreement dated July 2, 2019. The scope of services provided below are a continuation of the scope of services
stated in the Standard Form of Agreement dated July 2, 2019. The specific services provided as part of this
amendment are as follows:
Additional Services
Regarding Phase I, an archeological survey is recommended and is not currently included in our scope. TxDOT
Environmental has concurred with the recommendation of doing the archeological survey.
Per our scope of work, Halff is tasked with completing an Archeological Background Study (ABS) in accordance
with Section 106 of the National Historic Preservation Act,Texas Antiquities Code, and the Health and Safety Code.
Before the ABS can be submitted to TxDOT, our licensed archeologist conducts the background study based on
desktop resources and the proposed design, then presents a recommendation on any further work needed. The
report is then submitted for TxDOT's review and comment/concurrence. Because this was submitted through the
TxDOT Dropbox, I have attached the background study for your reference. A survey that includes shovel testing
only was recommended in the areas as shown in the Archeological Background Study (see Figure 7) for the
following reasons:
• There are previously identified archeological sites within the project area.
• Based on a review of FEMA floodplain and TxDOT Potential Archeological Liability data, Holocene-age
deposits are likely to occur within the project area (see Figures 3 and 4 in the ABS). These are present
where the project area intersects or parallels alluvial terraces of natural waterways.
• A historically reliable water source, the West Fork Trinity River, is within 500 feet of the project area. Three
associated tributaries cross the project area.
• The USGS topographic map indicates the project area south of the Trinity Railway Express contains
uplands overlooking a perennial waterway which is considered a landform with high potential for human
occupation.
• The areas of high potential have not been previously surveyed.
• These portions proposed for surveying have either a high or moderate potential for Holocene-age deposits
(see Figure 3 in the ABS).
As mentioned, due to the nature of the construction activities taking place, only an evaluation for shallow deposits
using shovel testing is recommended. No excavation for an evaluation of deep deposits is proposed.
MEN 1201 North Bowser Road
M Richardson,Texas 75081
E. HALFF (214)346-6200
Fax(214)739-0095
Below is the cost estimate for the archeological survey for CentrePort Trail Phase I:
To perform these additional services, Halff is requesting a lump sum fee of$14,000.00.
Additional Services total: $14,000.00
We request your signature below to confirm the scope and fee. If the scope and/or fee is not acceptable, please
notify us immediately.
CITY OF FORT WORTH HALFF ASSOCIATES INC.
By: By:
(Print name)
Title: Title:
Signature: Signature:
Date: Date:
MEN 1201 North Bowser Road
■■■ HALFF N Richardson,Texas 75081
■ . (214)346-6200
Fax(214)739-0095
ADDITIONAL SERVICES CONFIRMATION
To: Jing Yang Date: June 11, 2020
From: Laura Johnson AVO: 34838.001
Email: LJohnson@halff.com Project: CentrePort Trail- Phase I
VIA: email
The scope of services provided below are a continuation of the scope of services stated in the Standard Form of
Agreement dated July 2, 2019 between The City of Fort Worth (CLIENT)and Halff Associates (CONSULTANT)for
CentrePort Trail— Phase 1. The specific geotechnical services provided as part of this amendment are as follows:
Additional Services
I. Access to remaining borings
A. All the Phase I borings have been drilled by Alliance Geotechnical Group (AGG)except for seven
borings, RW-10 thru RW-16. Due to heavy spring rains,ATV tracking and multiple repairs to the rock
dam creek crossing, borings RW-11 thru RW16 will require access through DART/TRE's parking lot
and required a track mounted drilling rig. The path that AGG had been using for the other Phase I
borings cannot be accessed even with a lightly loaded track due to very soft and wet conditions. AGG
had to repair a rock dam creek crossing several times. To access to the remaining borings through
the DART/TRE parking lot, AGG will remove one metal beam guard rail post and rail in order to gain
access. They will temporarily hang the guard rail in place during the field work and when they are
finished with their work, they will put the post and guard rail back in place.
II. Stability Analyses
A. When AGG developed the proposal for the CentrePort Phase I investigation, they knew about the
short retaining walls but did not know about the steep embankment slopes beyond the short walls.
Therefore, they did not include any direct shear and/or CU Triaxial testing (which are required for
stability analyses). They did not include time for slope stability analyses in the original scope of
services. Based upon the current plans, AGG recommends that slope stability analyses be performed
for a few of the retaining wall conditions.
To perform these additional services, Halff is requesting a lump sum fee of$13,000.00 for Halff's coordination
with Alliance Geotechnical Services and the geotechnical work by AGG.
Additional Services total: $13,000.00
We request your signature below to confirm the scope and fee. If the scope and/or fee is not acceptable, please
notify us immediately.
CITY OF FORT WORTH HALFF ASSOCIATES INC.
By: By:
(Print name)
Title: Title:
Signature: Signature:
Date: Date: