AN ORDINANCE INCREASING APPROPRIATIONS IN THE WATER & SEWER
COMMERCIAL PAPER FUND IN THE AMOUNT OF $349,600.00, FROM AVAILABLE
FUNDS, FOR THE PURPOSE OF DESIGN OVERSIGHT AND PROJECT MANAGEMENT
SERVICES ON NORTH TARRANT EXPRESS SEGMENT 3A, IH-35W FROM IH-820 TO
IH-30; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE
CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT
HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2019-2020 in the
Budget of the City Manager,there shall also be increasing appropriations in the Water&Sewer Commercial
Paper Fund in the amount of$349,600.00, from available funds, for the purpose of design oversight and
project management services on North Tarrant Express segment 3A, IH-35W from IH-820 to IH-30.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23835-09-2019 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
�.uw�A-
017:21.CDT) �!/ V
Douglas W Black Mary J. Kayser
Sr.Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE:April 7, 2020 FDF?
09
MAYOR AND COUNCIL COMMUNICATION MAP
60NTESEG3AA5-KHA
f 4-_-_-i_r .
1 1 V) NE 820
r MARK IV F 1
05
I
4 IMPROVEMENTS �� — -i —' NORTH TARRANT
EXPRESS SEGMENT 3A
• - - - - - - -ale -' — Y �_ _ 1 _ _
MEACHAM BLVD
IPA
I 1
1
1 i �
? 1 J
{ I li.l
` RD TERMINAL 1 1
!t•
1
1 1 V
t
E LONG AVE 1 1
1
ur
1 I .
1 1 28TH ST
28TH ST. T
p + i IMPROVEMENTS
0.
1 YUCCA AVE '
~r 1
k
fm
e
1 �
1 t E 4TH ST& �
TIELAR ST
-
FORT WORT
rw� � •'yam L r a r.. - 4 1
Apo
City of Fort Worth,Texas
Mayor and Council Communication
DATE: 04/07/20 M&C FILE NUMBER: M&C 20-0165
LOG NAME: 60NTESEG3AA5-KHA
SUBJECT
Authorize Execution of Amendment No.5 in the Amount of$279,600.00 to an Engineering Agreement with Kimley-Hom and Associates,Inc.,for
Design Oversight and Project Management Services on North Tarrant Express Segment 3A,IH-35W from IH-820 to IH-30 Project,Adopt
Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt and Adopt Appropriation Ordinance(COUNCIL
DISTRICTS 2,8 and 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Resolution Expressing Official Intent to Reimburse Expenditures with Proceeds of Future Debt for Design Oversight and
Project Management Services on North Tarrant Express Segment 3A,IH-35W from IH-820 to IH-30 Project;
2. Adopt the attached Appropriation Ordinance increasing estimated receipts and appropriations in the Water&Sewer Commercial Paper
Fund in the amount of$349,600.00 for Design Oversight and Project Management Services on North Tarrant Express Segment 3A, IH-35W
from IH-820 to IH-30 Project;and
3. Authorize execution of Amendment No.5 in the amount of$279,600.00 to City Secretary Contract No.43959,an Engineering Agreement
with Kimley-Hom and Associates, Inc.,for Design Oversight and Project Management Services on North Tarrant Express Segment 3A,IH-
35W from IH-820 to IH-30,for a Total Revised Contract in the Amount of$1,828,000.00 (City Project No.CO2011).
DISCUSSION:
Amendment No.5 will provide additional engineering services to oversee and manage the protection and/or relocation of city water and
wastewater facilities within the IH-35 corridor. In 2019,TxDOT expanded its contract with NTEMP to include improvements to the Mark IV Parkway
and NE Loop 820 Intersection.
The proposed scope of services consists of:
• Project management
• Plan reviews of drawings provided by the contractor or other engineers.
• Design for water main replacement on NW 28t'Street.
• Design for water and sewer main replacement on Mark IV Parkway.
• Construction support services including attend preconstruction meetings,on-site observations,construction progress meetings,and shop
drawing reviews
• Project meetings with the City,stakeholders,contractors,other consultants,and citizens
On June 23,2009,Texas Department of Transportation(TxDOT)entered into a 10-year Agreement with North Tarrant Express Mobility Partners
(NTEMP)to identify and construct highway improvements in the northeastern part of Tarrant County including portions of the 1-35W,1-20,and SH-
183 corridors within the City.On October 23,2012(M&C C-25942)the City Council authorized an Engineering Agreement with Kimley-Horn and
Associates,Inc.,in the amount of$698,700.00 for design oversight and project management services on North Tarrant Express Segment 3A on
IH-35W from IH-820 to IH-30.The Agreement was subsequently revised by Amentment No. 1 for a revised scope at no additional cost,
administratively authorized September 18,2013,Amendment No.2 in the amount of$49,700.00 administratively authorized on July 28,2014,
Amendment No.3 in the amount of$400,000.00 authorized September 29,2015(M&C C-27487)and Amendment No.4 in the amount of
$400,000.00 authorized September 20,2016(M&C C-27935).
In addition to the amendment cost,$70,000.00(Water:$40,000.00;Sewer:$30,000.00)is required for Project Management and inspection.
This project is anticipated to be included in a future revenue bond issue for the Water and Sewer Fund.Available cash within the Water and Sewer
portfolio and the City's portfolio along with the appropriation authority authorized under the Callable Commercial Paper Program(CP)will be used
to provide interim financing for this project until debt is issued.To the extent resources other than the Water and Sewer portfolio are used to
provide interim financing,the Water and Sewer Fund will be charged interest that is equivalent to the overall rate of return being earned by the City
portfolio(currently approximately one-percent annually).Should the City's portfolio not support the liquidity needed to provide an interim short-term
financing source,another funding source will be required,which could mean issuance of securities under the CP Program or earlier issuance of
Water and Sewer revenue bonds than is currently planned.Once debt associated with this project is sold,bond proceeds will be used to reimburse
the Water and Sewer portfolio and the City's portfolio in accordance with the attached Reimbursement Resolution.
The City Council adopted the Water Department's Fiscal Year 2019-2023 Five Year Capital Improvement Plan on September 18,2018.This City
Council adopted plan includes this specific project,with funding identified through the CP program to be reimbursed with future revenue bonds.In
accordance with the provisions of the Financial Management Policy Statement,Staff anticipates presenting revenue-supported debt issuances to
the City Council for consideration within the next three years.This debt must be issued within approximately three years to provide reimbursemen
for these expenses.If that does not occur,the costs will no longer be reimbursable by issuing tax-exempt debt and the funding source will have to
be made whole through budgetary methods.Adoption of this resolution does not obligate the City to sell bonds,but preserves the ability to
reimburse the City from tax-exempt bond proceeds.
The Water and Sewer Commercial Paper Fund includes authority of$150,000,000.00 for the purpose of providing interim funding for Water and
Sewer Capital Projects.After this transfer,the balance will be$31,861,475.00 for future capital projects.Funding for the Design Oversight and
Project Management Services on North Tarrant Express Segment 3A, IH-35W from IH-820 to IH-30 project is as depicted below:
FUND Existing Additional Project Total*
Appropriations Appropriations
Water Capital Fund $2 125,855.00 $0.00 $2,125,855.00
59601
Sewer Capital
Legacy-Fund $602,249.00 $0.00 $602,249.00.00
59607
Water and Sewer $400,000.00 $0.00 $400,000.00
Bond 2015A 53007 _
Water and Sewer $1,655,208.00 $0.00 $1,655,208.00
Bond 2016 56005
W&S Commercial $0.00 $349,600.00 $349,600.00
Paper-Fund 56017
Project Total $4,783,312.00 $349,600.00 $5,132,912.00
*Numbers rounded for presentation
M/WBE OFFICE:Kimley-Horn and Associates,Inc.,is in compliance with the City's BDE Ordinance by committing to five percent SBE
participation on this Amendment No.5.The City's MBE goal on this Amendment is five percent.
The project is located in COUNCIL DISTRICTS 2,8 and 9.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds
will be available in the Water&Sewer Commercial Paper Fund for the design oversight and project management services in the North Tarrant
Express Segment project.Prior to any expenditure being incurred,the Water Department has the responsibility to validate the availability of funds.
Submitted for City Manager's Office by- Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: John Kasavich 8480