HomeMy WebLinkAboutContract 40959COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS
COUNTY OF TARRANT
City Secretary
Contract No.
WHEREAS. the undersigned "Developer" desires to make certain improvements (refer
to the name of the project at the bottom of the page) an addition to the City of Fort Worth,
Texas; and
WHEREAS, the said Developer has requested the City of Fort Worth. a home -rule
municipal corporation situated in Tarrant, Denton, Parker, and Wise Counties, Texas, hereinafter
called "City", to do certain work in connection With said improvements.
Developer Information:
[Developer Company Name: KB Horne Lone Star Inc.
Authorized Signatory: Don Barri neau
Title: President
Project Naine: Emory Place II — Blocks 3, 9 & 10
Project Location: West of Waterbrook, North of John T. White
Additional Streets: N/A
Plat Case No.: FP- 007-052 Plat Name: Emory Place II
Mapsco: 66T
Council District: 4 City Project No: 01424 I
[To be completed by
Received by:
Date:
CFA: 2009-052 DOE: 6320
OFFICIAL RECORD
CITY SECRETARY
'7 if, WORTH, TX
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and the
Developer do hereby agree as follows:
General Requirements
A. The Policy for the Installation of Community Facilities ("Policy") dated
March 2001, approved by the City Council of the City of Fort Worth and
subsequently amended from time to time via a Mayor and Council
Communication adopted by the City Council of the City of Fort Worth, is
hereby incorporated into this Community Facilities Agreement ("CFA' ) as
if copied herein verbatim. Developer agrees to comply with all provisions
of said Policy in the performance of its duties and obligations hereunder
and to cause all contractors hired by Developer to comply with the Policy
in connection with the work performed by said contractors.
B. Developer shall provide financial security in conformance with paragraph
6, Section II, of the Policy and recognizes that there shall be no reduction
in the collateral until the Project has been completed and the City has
officially accepted the infrastructure. Developer further acknowledges
that said process requires the contractor to submit an Affidavit of Bills
paid signed by its contractor and Consent of Surety signed by its surety
to ensure the contractor has paid the sub -contractor and suppliers in full.
Additionally, the contractor will provide in writing that the contractor
has been paid in full for all the services provided under this contract.
C. Developer agrees to cause the construction of the improvements
contemplated by this Agreement and that said construction shall be
completed in a good and workmanlike manner and in accordance with all
City standards and the City -approved construction plans specifications and
cost estimates provided for the Project and the exhibits attached hereto.
D. The following checked exhibits are made a part hereof: Water (A) X ,
Sewer (A-1) X , Paving (B) X , Storm Drain (B-1) X , Street Lights &
Signs (C) X .
E. The Developer shall award all contracts for the construction of community
facilities in accordance with Section II, paragraph 7 of the Policy and the
contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section II, of the Policy.
Combined CFA final Sept 12, 2008 2
F. For all infrastructure included in this Agreement for which the Developer
awards construction contract(s), Developer agrees to the following:
i. To employ a construction contractor who is approved by the director of
the department having jurisdiction over the infrastructure to be
constructed, said contractor to meet City's requirements for being
insured, licensed and bonded to do work in public streets and/or
prequalified to perform water/waste water construction as the case may
be.
ii. To require its contractor to furnish to the City a payment and
performance bond in the names of the City and the Developer for one
hundred percent (100%) of the contract price of the infrastructure, and a
maintenance bond in the name of the City for one hundred percent
(100%) of the contract price of the infrastructure for a period of two (2)
years insuring the maintenance and repair of the constructed
infrastructure during the term of the maintenance bond. All bonds to be
furnished before work is commenced and to meet the requirements of
Chapter 2253, Texas Government Code.
iii. To require the contractor(s) it hires to perform the construction work
contemplated herein to provide insurance equal to or in excess of the
amounts required by the City's standard specifications and contract
documents for developer -awarded infrastructure construction contracts.
The City shall be named as additional insured on all insurance required
by said documents and same will be evidenced on the ACORD
Certificate of Insurance supplied by the contractor's insurance provider
and bound in the construction contract book.
iv. To require its contractor to give 48 hours notice to the City's
Construction Services Division of intent to commence construction so
that City inspection personnel will be available; and to require the
contractor to allow the construction to be subject to inspection at any
and all times by City inspection forces, and not to install or relocate any
sanitary sewer, storm drain, or water pipe unless a responsible City
inspector is present and gives his consent to proceed, and to make such
laboratory tests of materials being used as may be required by the City.
v. To require its contractor to have fully executed contract documents
submitted to the City to schedule a Pre -Construction Meeting. The
3
submittal should occur no less than 10 working days prior to the desired
date of the meeting. No construction will commence without a City -
issued Notice to Proceed to the Developer's contractor.
vi. To delay connections of buildings to service lines of sewer and water
mains constructed under this Agreement until said sewer and water
mains and service lines have been completed to the satisfaction of the
Water Department.
G. Developer agrees to provide, at its expense, all engineering drawings and
documents necessary to construct the improvements required by this
Agreement.
H. Developer shall cause the installation or adjustment of the required utilities
to serve the development or to construct the improvements required herein.
City shall not be responsible for any costs that may be incurred by
Developer in the. relocation of any utilities that are or may be in conflict
with any of the community facilities to be installed hereunder.
J. Developer hereby releases and agrees to indemnify, defend and hold the
City harmless for any inadequacies in the preliminary plans, specifications
and cost estimates supplied by the Developer for this Agreement.
K. Developer agrees to provide, at its expense, all necessary rights of way and
easements across property owned by Developer and required for the
construction of the current and future improvements provided for by this
Agreement.
L. The Developer further covenants and agrees to, and by these presents does
hereby, fully indemnify, hold harmless and defend the City, its officers,
agents and employees from all suits, actions or claims of any character,
whether real or asserted, brought for or on account of any injuries or
damages sustained by any persons (including death) or to any property,
resulting from or in connection with the construction, design, performance
or completion of any work to be performed by said Developer, his
contractors, subcontractors, officers, agents or employees, or in
consequence of any failure to properly safeguard the work, or on account
of any act, intentional or otherwise, neglect or misconduct of said
DEVELOPER, his contractors, sub -contractors, officers, agents or
employees, whether or not such injuries, death or damages are
caused, in whole or in part, by the alleRed neRlixence of the City of
Combined CFA final Sept 12, 2008 4
Fort Worth, its officers, servants, or employees.
1\4. Developer will further require its contractors to indemnify, defend and
hold harmless the City, its officers, agents and employees from and against
any and all claims, suits or causes of action of any nature whatsoever,
whether real or asserted, brought for or on account of any injuries or
damages to persons or property, including death, resulting from, or in any
way connected with, the construction of the infrastructure contemplated
herein, whether or not such injuries, death or damages are caused, in
whole or in part, by the alleged negligence of the City of Fort
Worth, its officers, servants, or employees. Further, Developer ill require
its contractors to indemnify, and hold harmless the City for any losses,
damages, costs or expenses suffered by the City or caused as a result of
said contractor's failure to complete the work and construct the
improvements in a good and workmanlike manner, free from defects, in
conformance with the Policy, and in accordance with all plans and
specifications and shall cause to be executed and delivered to the City an
indemnity agreement from such contractors on a form to be promulgated
by the City.
N. Upon completion of all work associated with the construction of the
infrastructure and improvements, Developer will assign to the City a non-
exclusive right to enforce the contracts entered into by the Developer with
its contractor along with an assignment of all warranties given by the
contractor, whether express or implied. Further, Developer agrees that all
contracts with any contractor shall include provisions granting to the City
the right to enforce such contracts as an express intended third party
beneficiary of such contracts.
O. Inspection and material testing fees are required as follows:
i. Developer shall pay in cash water and wastewater inspection fees and
material testing fees equal to two percent (2%) for a total of 4% of the
developer's share of the total construction cost as stated in the construction
contract.
ii. Developer shall pay in cash paving and storm drain inspection fees equal
to four percent (4%) and material testing fees equal to two percent (2%)
for a total of 6% of the developer's share of the total construction cost as
stated in the construction contract.
5
iii. Developer shall pay in cash the total cost of streetlights or if the city is
not installing the streetlights, inspection fees equal to four percent (4%) of
the developer s share of the streetlight construction cost as stated in the
construction contract.
iv. Developer shall pay in cash the total cost of street signs.
P. COMPLETION WITHIN 2 YEARS
i. The City's obligation to participate (exclusive of front foot charges) in
the cost of the community facilities shall terminate if the facilities are
not completed within two (2) years; provided, however, if construction
of the community facilities has started within the two year period, the
developer may request that the CFA be extended for one year If the
community facilities are not completed within such extension period,
there will be no further obligation of the City to participate. City
participation in a CFA shall be subject to the availability of City funds
and approval by the Fort Worth City Council.
ii. Nothing contained herein is intended to limit the Developer's
obligations under the Policy, this Agreement, its financial guarantee,
its agreement with its contractor or other related agreements.
iii. The City may utilize the Developer's financial guarantee submitted for
this Agreement to cause the completion of the construction of the
community facilities if at the end of two (2) years from the date of this
Agreement the community facilities have not been completed and
accepted.
iv. The City may utilize the Developer's financial guarantee to cause the
completion of the construction of the community facilities or to cause
the payment of costs for construction of same before the expiration of
two (2) years if the Developer breaches this Agreement, becomes
insolvent or fails to pay costs of construction and the financial guarantee
is not a Completion Agreement. If the financial guarantee is a
Completion Agreement and the Developer's contractors and/or suppliers
are not paid for the costs of supplies and/or construction, the contractors
and/or suppliers may put a lien upon the property which is the subject of
the Completion Agreement.
Combined CFA final Sept 12, 2008 6
Cost Summary Sheet
Project Name: Emory Place II
CFA No.: 2009-052
DOE No.: 6320
An Engineer's Estimate of Probable Cost is acceptable. However, the construction contract
price will ultimately determine the amount of CFA fees and financial guarantee. The bid price
and any additional CFA payments will be required prior to scheduling a pre -construction
meeting.
An itemized estimate corresponding to each project -specific exhibit is required to support the
following information.
Items
A. Water and Sewer Construction
1. Water Construction
2. Sewer Construction
Water and Sewer Construction Total
B. TPW Construction
1. Street
2. Storm Drain
3. Street Lights - Installed by Developer
TPW Construction Cost Sub -Total
Total Construction Cost (excluding the fees):
Construction Fees:
C. Water/Sewer Inspection Fee (2%)
D. Water/Sewer Material Testing Fee (2%)
Sub -Total for Water Construction Fees
E. TPW Inspection Fee (4%)
F. TPW Material Testing (2%)
G. Street Light Inspsection Cost
H. Street Light Materials - Poles & Arms
H. Street Signs Installation Cost
Sub -Total for TPW Construction Fees
Total Construction Fees:
Financial Guarantee Options, choose one
Developer's Cost
$
85,171.90
99,733.00
184,904.90
$
230.014.00
120,340.00
12,320.00
$
362,674.00
$
547,578.90
$
$
$
3,698.10
3,698.10
7,396.20
14,014.16
7,007.08
729.30
5,912.62
1,225.00
28,888.16
36,284.36
(4)gq,413,c.
Amount
Choice
(ck one)
Bond
= 100%0
$ —? 547,578.90
X
Completion
Agreement
= 100%
/
Holds
Plat
$ 547,578.90
Cash
Escrow
Water/Sanitary
Sewer=
125%
$ 231,131.13
Cash
Escrow
Paving/Storm
Drain
r= 125%
_
$ 453,342.50
IN TESTIMONY WHEREOF, the City of Fort -Worth has caused this instrument to be
executed in quadruplicate in its name and on its behalf by its Assistant City Manager, attested
by its City Secretary, with the corporate seal of the City affixed, and said Developer has
executed this instrument in quadruplicate, at Fort Worth,Texas this 1 �' day
p
of 0 20 tab .
CITY OF FORT WORTH - Recommended by:
Water Department
Wendy Chi- ► bulal. EMBA, P.E.
Development Engineering Manger
Approved as to Form & Jiegal ity:
An J: nsey
Assistant ity Attorney
ATTEST:
Marty Hendri
City Secretary
ATTEST
Transportation & Public Works Department
Director
Approved by City Manager's Office
Fernando Costa
Assistant City Manager
0
rib.
41,9
sQe.9000000 icy
‘ti`lb earl girt; '691
,
v
i
TO REQUIRED I
KB Home Lone Star Inc.
NvAti-%
Prin' me: assrf rots Print Name: Don Bamneatl
Title: O.inawti #f tett".4/0 4cQyj,,,Tit1e: President
Combined CFA final Sept 12, 2008
8
OFFICIAL RECORD
CITY SECRETARY
Ft WORTH, TX
Check items associated with the project being undertaken; checked items must be
included as Attachments to this Agreement
Included
AL
Attachment
Location Map
Exhibit A: Water Improvements
Water Estimate
Exhibit A-1: Sewer Improvements
Sewer Estimate
Exhibit B: Paving Improvements
Paving Estimate
Exhibit B-1: Storm Dram Improvements
Storm Drain Estimate
Exhibit C: Street Lights and Signs Improvements
Street Lights and Signs Estimate j
(Remainder of Page Intentionally Left Blank)
9
VICINITY MAP
NOT TO SCALE
•
•
— ——...... /
r_.
1
11
it
1
IF
iI
19
1
18 /
17
i
16
.1I
/1
/
•
• 1
•
•
•
15
ti
>-
4 C
1I
1
13
12
•
21
/
10
22
F.H.
r
31
32 33 ‘`"34
8 WA TER � \�
I ,
30
29
1
;Ira
23\\
24
28
8" WATER
25
KNCHT ISLAV LN.__—___
•
\
tQ
\
8
11
•
12
6
13 ,.
°o 5
14
4+J1
4
(S
15
3
16
2
17
\ 8" Wt
•
•
•
•
•
•
PATE 4:• ENGINEERS7
8150 BROOKRIVER DRIVE
SUITE S-700
DALLAS, TEXAS, 75247
PH. (214) 357-2981
FAX (214) 357-29B5
JOB NO. 109401302
TffR
18 —
SYLVAN INEAR0W5 DR.
\
15
14
ti 13
N.
12
7.
•
9 1 22 '---fir
8
1
—/1 ]'
4 t•
/
49
/
/
I
rk
`^
w
`1
•
\
1 I•
1—
/3
T •
5 U 1 r,t _
J V
/ \ ' I \
4 ,'�7 _ % �\
/ ( I \
1 / v
3 ,i' __ \ 1
/ ,v 1
\\ 1
1
1
F.H.
i
GLADE OAKI3 DR.
8
IS so
7_ 6
1
fast . as _raimom.
z
rr,
`�—wIrnER
r—
._
-,,,--/ �
r' rook TRICE
_IIO1 � LVERY `.
/
` '
. -
1— ----1 Ii
— � �
-`l n
T.—KuanN^_
/Whta nLL,I.
._h
��.
/.di'�I►__
SITE
PNOERSO
1----�r \ �'/-I
L
N
a ai - x
1
l�/
eErlrnodo
L uoR�_, 21
-- —
a
lv
VOL,JCL, 6.5:..-c•C, Pr -42
rrr)1
♦I
I
•
OHS T RD
) ifl$
FP-007-052
DOE # 6320
WATER MAP #: 2090-400W & 2084-400W
SANITARY SEWER MAP #: 2090-400S & 2084-400S
VICINITY MAP
N .T.S.
CITY OF FORT WORTH, TX
WATER DEPARTMENT
EMORY PLACE
OVERALL WATER LAYOUT
PROJECT NO.
WATER: P265-604150142483
SEWER: P275-704130142483
SHEET
EXHIBIT A
EXHIBIT A PEI It: 109401302
CONSTRUCTION COST ESTIMATE
PROJECT NAME: EmoryPlacell
PHASE:
FILE NAME: 109401302
DESCRIPTION
ACREAGE:
DATE
DATE PREP:
UNIT
ASWATER DISTRIBUTION SYSTEM
8" P.V.C. WATERLINE LF
11.45
27-Jul-10
27-Jul-10
BY:
CHECKED:
REVISED:
APPROXIMATE
QUANTITY PRICE
2,242
$19.00
RP
BD
TOTAL
AMOUNT
$42,598.00
6" P.V.C. WATERLINE
8" GATE VALVE & BOX
8"X8" WET CONNECTION W/ SOLID SLEEVE
CAST IRON FITTINGS
FIRE HYDRANT ASSEMBLY
LF
EA
EA
TN
37
6
2
1
$17.00
$950.00
$2,000.00
$2,500.00
EA
2
$2,000.00
$629.00
$5,700.00
$4,000.00
$1,375.00
$4,000.00
1' WATER SRV
TESTING
EA
LS
61
2,242
$400.00
$24,400.00
$1.00
$2 242.00
TRENCH SAFETY
LS
TOTAL WATER DISTRIBUTION SYSTEM
2,279
$0.10
$227.90
$85,1':71.90
MATERIAL TESTING FEES
PERCENT
2.0%
$85,171.90
$1,703.44
INSPECTION FEES
PERCENT
2.0%
$85,171.90
$1,703.44
TOTAL WATER DISTRIBUTION SYSTEM FEES
PATE ENGINEERS, INC. 1 of 6
1
$3,406.88
J1
C:1Documents and Settings\RustyP.PATE01\Desktop\CFA ESTIMATES.XLS,
EXHIBIT A
•
r °o
1D
22
23
33
KNICI-IT ISLAND us.
2
M.H
3
2
•
CLAD
OAK.
DR.
9
S
7O
9
6
5
4
PATE u ENGINEERS
—002726
8150 BROOKRIVER DRIVE
SUITE S-700
DALLAS, TEXAS, 75247
PH. 214 357-2981
FAX 214 357-2955
JOB NO. 109401302
34
•
77
�f
M174
14)
II
-7
�.-- WMER
In
fJdrk
/ ��.yrook
N
TRICE
�f
LOVIEiY
f 4 l
l
`� <'
r S' EASTFRR
/ KUH��
--
CB JOHN T IT -�
yp.1 T R�
-.\ )/
SITE -
AND�R30 EL_�
'_ -:' 'o
— -_'7ED - LIE 0 .
_
o�
A1 3 _=
—, Lo,
,_,
nV isc. 721,C47
--L/OHNi T NHI- RB
1�
FP-007-052
DOE # 6320
WATER MAP #: 2090-400W & 2084-400W
SANITARY SEWER MAP #: 2090-400S & 2084-400S
VICINITY MAP
LEGEND
•
EXISTING SS
PROPOSED SS
EXISTING EX. M.H.
PROPOSED EX. M.H,
CITY OF FORT WORTH, TX
WATER DEPARTMENT
EMORY PLACE
OVERALL SANITARY SEWER LAYOUT
PROJECT NO.
WATER: P265-604150142483
SEWER: P275-704130142483
SHEET
EXHIBIT A-1
EXHIBIT A-1 PEI it: 109401302
CONSTRUCTION COST ESTIMATE
PROJECT NAME: Emory Place II ACREAGE: 11.45 BY:
P H A S E: D A T E: 27 Jul-10 CHECKED:
FILE NAME: 109401302 DATE PREP: 27 Jul-10 REVISED:
DESCRIPTION
B.SANITARY SEWER SYSTEM
8' SDR-35 P.V.C. PIPES-8')
8SDR-35 P.V.C. PIPE (8'-10')
8' SDR-26 P.V.C. PIPE (10' 12')
8" SDR-26 P.V.C. PIPE (12' 14')
APPROXIMATE UNIT
UNIT QUANTITY PRICE
LF
LF
929
249
$20.00
$22.00
LF
LF
690
70
RP
BD
$23.00
$24.00
TOTAL
AMOUNT
$18, 580.00
$5,478.00
$15,870.00
$1,680.00
8" SDR-26 P.V.C. PIPE (10' 12') W/ CONC ENCASE
4' DIAMETER MANHOLE
LF
EA
60
8
50.00
$2,500.00
$3,000.00
$20,000.00
4' DIAMETER DROP MANHOLE
EA
1
$2,800.00
$2,800.00
EX1 RA DEPTH 4' SS MH
VF
26
$130.00
$3,380.00
CLAY DAM
EA
4
$50.00
CONNECT TO EXIST. S.S. LINE
EA 2
$300.00
$200.00
$600.00
TRENCH SAFETY
LF
1,938 $1.00
$1, 938.00
MANHOLE VACCUUM TESTING
EA
9 $50.00
$450.00
SS TESTING & TV LF 1,938 $1.50
4" SDR-26 P.V.C. SERVICE EA 30 $400.00
4" SDR-35 P.V.C. SERVICE EA 31 $350.00
$2,907.00
$12,000.00
$10, 850.00
TOTAL SANITARY SEWER SYSTEM
$99,733,00
MATERIAL TESTING FEES PERCENT
2.0% $99,733.00 $1,994.66
INSPECTION FEES PERCENT 2.0% $99,733.00 $1,994.66
TOTAL SANITARY SEWER SYSTEM FEES
PATE ENGINEERS, INC. 2 of 6
1
$3,989.32
1
1
C:\Documents and Settings\RuslyP.PATF01\Desktop\CFA FSTIMATFS.XLS,
EXHIBIT Al
X
a
5
L
•
DIJ7
an9la 2
O r
21 22
10
32
3
L__
30
29
28
23
24
25
KNIGHT ISLAND LN.
GLADE OAKS DR.
33
1
34
SYLVAN
MEADOWS DR.
15
14
13
12
11
10
9
8
7
6
4
2.
PATE ENGINEERS
—002726
B150 BROOKRIVER DRIVE
SUITE S-700
DALLAS, TEXAS, 75247
PH. (214) 357-2981
FAX (214) 357-2985
JOB NO. 109401302
Laaana-
I tar, II
11 1
/1
aa-n
ra
au
r-r IC
c02 0c1
n
- -, ✓
/ !— *INTER
/ a
��
/Swdybrook
Park
TRICE
o
Kill
i �
/ / L
/1R
I �, �s1�RN
� � o
�µ'hit6�
/i\v" /�l"
4\ SITS �Rso
a:
�� /
Hs
��
-JOHN T WHI RD
1211,1101
VICINITY MAP
N_T.S_
FP-007-052
EMORY PLACE
OVERALL STREET LAYOUT
PROJECT NO_
D.O.E. # 6320
STREET & STORM DRAIN
PLAN FILE NO. W-1581
SHEET
EXHIBIT B
EXHIBIT B PEI it: 109401302
CONSTRUCTION COST ESTIMATE
PROJECT NAME: EmoryPlacell ACREAGE:
PHASE: DATE:
FILE NAME: 109401302 DATE PREP:
DESCRIPTION
D.STREET PAVING
6' LIME STAB SUBGRADE
7' REINFORCED CONCRETE PAVEMENT
11.45
27-Jul-10
27-Jul-10
BY: RP
CHECKED: BD
REVISED:
APPROXIMATE UNIT
UNIT QUANTITY PRICE
TOTAL
AMOUNT
SY 7,480 $2.50 $18,700.00
SY 7,030
25.80 $181,374.00
HYDRATED LIME (30#)
3000 PSI SIDEWALK
REMOVE EX DRIVE
TN 112 $150.00 $16,800 00
SF 1700 $3.00 $5,100.00
SY 35 $20.00 $700.00
7" CURB LF 47 $20.00
940.00
BARRIER FREE RAMPS
EA 4 $1,000.00 $4,000.00
REMOVE BARRICADE
EA 2 $200.00 $400.00
TRAFFIC CONTROL LS 1 $2,000.00 $2,000.00
TOTAL STREET PAVING
230,014,00
MATERIAL TESTING FEES
INSPECTION FEES
PERCENT 2.0% $230,014.00 $4,600.28
PERCENT 4.0% $230,014.00 $9,200.56
TOTAL STREET PAVING FEES
PATE ENGINEERS, INC. 3 of 6
1
$13,800.84
1
1
C:IDocuments and Setangs\RustyP.PATF011Desktop\CFA FSTIMATES.XI. S,
EXI!I13II B
9
A
F
3
2 x2" D.I.
2'x2' D.I.
2'x2' D.I.
2'x2' D.
2.x2' D,l,
2'x2' D.I,
15
14
13
12
TIT
Q
2'x2' al.
2'x2' D.I.
2'x2' al.
2'x2' D,l,+
'+ 1
,
Z31
L
I+Co 30
1 101 0.
29
21x2' D.l,�l
Li
iI 28
1
23 24
SD-,49
25
rely
9
15' C.I.
10
8
11
7
12
6
13
5
14
4
15
3
16
2
17
18
sac
PATE •u ENGINEERS
8150 BROOKRIVER DRIVE
SUITE S-700
DALLAS, TEXAS, 75247
PH. (214) 357-2981
FAX (214) 357-2985
JOB NO. 109401302
GLADE OAKS DR.
J
32 33
re
1
Yi
34 I
SA5I.
55 .33
VAN'MEADOWS DR.
14
13
12
I
11
10
9
8
7
6
r
1 26 55'
RQ
--
1
1
12
1/111117 I rS OIEG
'1/0' 50655. ; 4
1R1 ijyC-----�.J�.,RAy�O�
AA7Z__
';/-
,T.WIN7ER N
}III/
v/ lY
----
tic
--1/2,Ab,00k TRICE
o « 01
d
m
KCome,
JOHN T, R G —
�`
\�'� /\��
--
/.
SITE '!
ANDERSOrr•j..
—
�_—
i...,
w es. ; , �wr i� a
I
\.
'r/c,
s I 0-o---'
,
34 ✓'--1 `a-.
i/CURIE_I
/JBRENIIVDLIQ C._..Y- __ � t_
n .4.,_....,-----
� �'V4pN6Ri"'-
JOdN T NH RD
12Rao
VICINITY MAP
FP-007-052
EMORY PLACE
OVERALL STORM SEWER LAYOUT
PROJECT NO,
D.O.E. # 6320
STREET & STORM DRAIN
PLAN FILE NO. W-1581
SHEET
EXHIBIT 9-1
EXHIBIT B-1 PEI #: 109401302
CONSTRUCTION COST ESTIMATE
PROJECT NAME EmoryPlacell ACREAGE
PHASE: DATE:
FILE NAME: 109401302 DATE PREP:
DESCRIPTION
C.STORM SEWER SYSTEM
21" RCP
24" RCP
30" RCP
36" RCP
11.45
27 Jul-10
27-Jul-10
APPROXIMATE
UNIT QUANTITY
BY: RP
CHECKED: BD
REVISED:
UNIT
PRICE
TOTAL
AMOUNT
LF 55 $42.00 $2,310.00
LF 290 $45.00 $13,050.00
LF 384 $52.00
LF 92 $65.00
24" HDPE
2'x2 DROP INLET
LF
EA
$19,968.00
$5,980.00
977 $42.00 $41,034.00
11
$1, 500.00
10' STD CURB INLET
EA
2
$2,000.00
$16,500.00
$4,000.00
15' STD CURB INLET
4' SQ MANHOLE
EA
2
$3,000.00 $6,000.00
EA
1
$2,500.00
2,500.00
5' SQ MANHOLE
EA
2
$3,200.00
$6,400.00
TRENCH SAFETY LF
1,798
$1.00 $1,798.00
REMOVE EX DROP INLET & CONNECT
EA
1
$800.00
$800.00
TOTAL STORM SEWER SYSTEM
20,340,00
MATERIAL TESTING FEES
PERCENT 2.0% $120,340.00 $2,406.80
INSPECTION FEES
PERCENT 4.0% $120,340.00 $4,813.60
TOTAL STORM SEWER SYSTEM FEES
PATE ENGINEERS, INC. 4 of 6
I
$7,220.40
C:1Documenis and Settings\RustyP.PATF011Desktop\CFA FSTIMATFS.XI S,
EXI lIBIT 131
V_
21
22
23
t
32 1 33
31
L__
30
e1
29
24
25
19
18
17
16
15
14
1
13
12
11
U
10
KNIGHT ISLAND La
9
10
6
11
12
6
13
N
4
1
1
SYLVAN MEADOWS DR.
15
14
13
12
11
10
9
27
8
27,
7
6
5
14
4
15
3
16
2
17
18
O
0
GLADE OAKS DR. T
4
10
/..Et CAv.
IS IS
OM MD S
1
Y �
PATE •) ENGINEERS
TBPE F-002726
8150 BROOKRIVER DRIVE
SUITE S-700
DALLAS, TEXAS, 75247
PH. (214) 357-2981
FAX (214) 357-2985
JOB NO, 109401302
G
C>r fir a1E/
1ri r
a4MD
YekTER
0 r .
L
��
' _, a
r
tJ F
T( KU& j
J 1C "1-;.---
o e"�IIT. ff
7
,\
SITE
ANDpaSOM11 E.
LIE o
G Q
..�
I�C 1$
,-__.4 � .
a Uvbddgl�--�oKr�7
l L�I n L�` -I r41I�NdA1!- '
1QHb T fiHITE RD
'7-* 120,rr
WALT
,_ 5656, Pa_ 4
T .. ..
VICINITY MAP
LEGEND
EXISTING STREET LIGHT
PROPOSED STREET LIGHT
N.T.S.
FP-007-052
EMORY PLACE
STREET LIGHTS LAYOUT
PROJECT NO.
D.O.E. #
STREET & STORM DRAIN
PLAN FILE NO. W-1581
SHEET
EXHIBIT C
PROJECT NAME:
PHASE:
FILE NAME:
DESCRIPTION
E,STREET LIGHTS
POLE & ARMS INSTALLATION
EXHIBIT C PEI #: 109401302
CONSTRUCTION COST ESTIMATE
Emory Place II
ACREAGE
DATE:
109401302 DATE PREP:
UNIT
EA
11.45
27 Jul-10
27 Jul-10
APPROXIMATE
QUANTITY
7
BY:
CHECKED:
REVISED:
UNIT
PRICE
$1,500.00
RP
BD
TOTAL
AMOUNT
$10,500.00
2" PVC SCH 40 CONDUIT
LF
140
$8.00
$1,120.00
118 CONDUCTOR 4 WIRES
LF
140
$5.00
$700.00
TOTAL STREET LIGHTS
TOTAL STREET LIGHTS FEES
STREET LIGHTS PURCHASE FROM THE CITY
POLE & ARMS MATERIALS FA 7
STREET LIGHTS PURCHASE FROM THE CITY
PATE ENGINEERS, INC. 5 of 6
$844.66
$12,320.00
1
$492.80
$5,912.62
I
$5,912.62
C:IDocuments and Settings\RustyP,PATF011Desktop\CFA FSTIMATFS.XI S,
EXI IIBIT C
'ADO/T(tt1
19
18
1
17
1
16
15
14
13
21
fY
5-
22
23
31
L
32 \ 33
30
29
24
28
25
KNIGHT ISLAND LN,
9
10
8
11
7
12
6
13 O
5
14
4
15
3
16
2
17
18
GLADE OAKS DR.
3
1
4
Y
SYLVAN (MEADOWS DR.
15
14
13
12
11
25
10
9
8
7
6
4
7
3
2
OL A1t OAKS
9
8
7O
6
5
4
PATE 4;• ENGINEERS
-002726
8150 BROOKRIVER DRIVE
SUITE S-700
DALLAS, TEXAS, 75247
PH. 214 357-2981
FAX 214 357-2985
JOB N0. 109401302
3I2
77,
� , � a
?Mo<
tl_
/
RELar4E+M
/��1ram'
!`�!1I!lRiii
A..) ---,
,I
— r teaWiT7EC
r
KU6W7 _L.
-1/0
�7
111
itG h-�
Co'mMry cill
dOhR{IT. R
�7 if
1 SITE�4 _
ADaR300,1 ctL.
/�
SO
t////
1 -c 31 8
r—Ay
:_
I �i
iJ_r'-- '� ,. �BReit) "' UuntLa 1 . , , l �
` . ' youimOzr
-5'O `r;rc n;c rij 50
n
Ass-
T WHE RD
>Igo
VICINITY MAP
LEGEND
PROPOSED STREET SIGN
N.T.S.
FP-007-052
EMORY PLACE
SIGNS LAYOUT
PROJECT NO.
D.O.E. # 6320
STREET & STORM DRAIN
PLAN FILE NO. W-1581
SHEET
EXHIBIT C- I
EXHIBIT C-1 PEI tt: 109401302
CONSTRUCTION COST ESTIMATE
PROJECT NAME Emory Place ll ACREAGE 11.45 BY: RP
PHASE: D A T E: 27 Jul-10 CHECKED BD
E I L E NAME: 109401302 DATE PREP: 27 Jul-10 REVISED:
DESCRIPTION
F STREET SIGNS
STREET SIGN
APPROXIMATE UNIT
UNIT QUANTITY PRICE
EA
TOTAL
AMOUNT
$245.00 $1,225.00
TOTAL STREET SIGNS
PATE ENGINEERS, INC. 6 of 6
1225.00 I'
C:1Documents and Settings \RustyP.PATF011Desktop\CFA FSTIMATFS.XLS,
EXHIBIT Cl