HomeMy WebLinkAboutContract 41592-CO1 DiIsTRIs TIOl N:
.
"w'HFFE_FtLE CITE OF FORT WORTH w ICTIJO W01,
CANARY-CONSTR HA,:jG
PINK-PROJECT MAq L - - E ORDER REQUEST
GOLDENROD_ T
CHANCE ORDER.NO. DATE PROJECT NO,
December 6,I x.011 City Project P275-701.30001 8683
00186
PROJECT DESC TION: Village Creel.WRF Modifications to Bar Screen Bldg. 3 and CITY SECRETARY CONTRACT NCB,
Junction Box Rehabilitation 41592
ORIGINAL CONTRACT AMOUNT............................................ 737 ,345.0
EXTRAS TO DATE............................................... 0.00 JEAN 10 9 2012
CREDITS TO,DATE......... .......... 0.00 TER DEPARTMENT
WA
COTTR.ACT COST TO DATE..........................................................................................,................................................................... 7,179-145.00
AMOUNT OF PROPOSED CHANGE ORDER....................r.................................................................................................................$ 1,6603195.70:
REVISED CONTRACT AMOUNT........w...............................,,..................................... ..........,.._.....,... 9 039 540.70
���
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS................................... ...���:.��" ........................ 221,000.00
.
ADDITIONAL FUNDING 1F'NECESSARY)............................... ............................ H]D,.. ..... .................. 1 R� 660 95.70
�
REMAINrNG FUNDS AVAILABLE FOR CHANGE ORDER...................................... .....................................I........................... 22 1_1000.00
IN ACCORDANCE WITH THIS CHANGE ORDER,THE CONTRACTOR SHALL: rnodi /change the contract as shown below to provide a cornpletel
Functional,and operational plant.These changes are as listed below. Further descriptions and Cost Breakdowns are;attached.
C R-002 MODIFICATIONS TO BY-PASS PUMPING SET ----------------------------- -------_- ------- -------...-------------------$41 X697.70
The Contractor shall modify the installed pwnping set up to accommodate plant operations.. Hydraulic restrictions drough the existing Bar
Screen Building No. 2 and the detritors require the use of more primary clarifiers to achieve the required pumping capacity of 150 IMGD. This
modified set up rewires additional piping to reach the designated discharge point. The Contractor hass provided a cost of$41,697.70 for this
work and requested no additional time,
CMR-005 REROUTE 39-rNCH DRAIN LINE----__-- ---------------------------------------------------------------------------------------------$601355.00
The Contractor shall reroute the 39-inch drain line in conflict with the tunnel to tern-.nate to a new manhole at the tunnel. The drain line was
not shoA,,n on the contract plans. The Contractor has provided a cost of$6'0 355.00 for this work and requested no additional time.
PCM-002 REPLACEMENT OF 96-INCH PIPELINE TO BAR SCREEN BLDG 3 ------------------------------__ ------------_--------$1,55 143.00
The Contractor shall replace the existing 96-inch plant influent line from Junction.Box 4B to the Bar Screen Building No'. 311 install a manhole
at the deflection point and turil el under the levee. When the pipe was taken out of service during the scheduled shutdo 94 ' ' ected and
found to be in a severel y p p deteriorated condition. This is an optimal time to replace the pipe since this line is critical iand the
.
by-pass pumping was already set up.. The Contractor has provided a cost of$1,558,143.00 for this work and req e idar
days.
TOT COST FOR CHANGE ORDER N"C. 1 ------------------------------------------------ -- -------- -_ ..-_-___--.-_.�__.___� -
1-140
'���_-__ ��. _ � X70 The Revised Substantial Completion date for the contract is,June 04 2012. µ
10 AY
understood ., Chang order by the contractor constitutes an accor� 1ti� in u or all
It is and oad and t� reed that the acceptance of this
costs arising out off,or incidental to,the Change order. �
ORIGINAL CONTRACT TIME A DMONA.L APPROVED TIME To DATE APPROVED CONTRACT TIME To DATE ADDITIONAL TIME FOR THIS CHANGE ORDER
360 Calendar Days None 360 Calendar Days 60 Calendar Days.
CONTRACTOR DATE FIELD ENGINEER DATE
Arlo Contra ti�a g Services Inc. ArrT P obinson,PE,CDM 4d, •
"I.SEI. DATE D CT4'IMANACaINCa DEFT. DATE
elene a 01 �.
D oR d rPF, DATE CI TT 1E DATE
drew r b6r Ass t Director t - t 7—, 3. 1
CIT1,' NAGE .— DATE COUNCIL ACTION(IF REQUIRED). � "�� DATE
Fernando Cosh Assistant Manager
11.311
APPROVED DISAPPROVED,�D OTHER
..
`N�
N—12
" ° h ti
City of Fort Worth, Texas
f% 0 N
Mayor an ounce unc ion
RINNOWN
COUNCIL ACTION: Approved on 12/6/20111
DATE: Tuesday, December 06, 2011 REFERENCE NO'.. C-25339
LOG, NAME,-, 6101ARK CHANGE ORDER 1 BARSC�RE,E,N3
SUBJECT:
Authorize Execution of Change Order N'o.1 to City Secretary Contract No. 41591,2 in the, Amount of
$1,660,195.70 for a Total Contract Amount of $9,039,540.70 with Ark Contracting Services LLC, for the
I
Modlificati'on,s to Bar Screen Bulilding, 3 and Junction Box Rehabilitation at Village Creek Water Reclama,tion
Facility (ALA. COUNCIL DISTRICTS)
RECOMMENDATION:
It is recommended that the City Council authorize execution of Change Order No. 1 to a construction
contract with Ark Contracting Services LL1C, in the amount of$11,6601,195:.70 for the Modifications, to Bar
Screen Building 3 and Junction Box Rehabilitation at Village Creek Water Reclamation Facility, increasing
the total contract cost to $9,,039,540.701.
DISCUSSION:
On January 25, 20111 (M&C C-24719) City Council authorized a construction contract with Ark Contracting
Services, LLC, for$7,379,345-00 for the Modifications to Bar Screen Building 3 and Junction Box
Rehabilitation at Village Creek Water Reclamation Facility.
During the construction of Junction Box 4-B it became apparent that the 96-inch influent line is severely
deteriorated, making it difficult to, complete the connection to the new work and revealing a serious
weakness in the City's critical infrastructure. A thorough inspection of the pipe condition, including a laser
procedure to determine the remaining pipe thickness found that the crown of the pipe is severely corroded
and subject to failure.
The original pipe wall thickness was 9-314-inches. Approximately 50 percent of the pipeline thickness has
been lost to corrosion and in some locations less than two inches crown thickness remains. This line was
installed in 1975 and was considered industry standard at that time. The portion of the pipe proposed to
be replaced is located downstream of a junction structure with turbulent flow conditions, which facilitates
the release of hydrogen sulfide gas from the wastewater. The hydrogen sulfide gas reacts with the
moisture in the pipe and corrodes the concrete. The concrete pipe is proposed to be replaced in this
Change Order No. 1 with a fiberglass pipe, which is resistant to the corrosive effects of hydrogen su!lf'ide
gas.
Bypass pumping is currently set up for the project and will be necessary for replacement of the 96-inch
influent line. Replacing the line under this contract may save the City more than $2,000,000 in bypass
pumping costs should it have to be completed under a separate contract at another time,
This proposed Change Order No. 1 will compensate the Contractor for replacement of 883 linear feet..of
96-inch pipe, tunneling under the levee, installation of'a new access manhol'e, and for the necessary
bypass pumping services to keep the work area dry. The contractor has requested an additional 60
Logname.- 60ARK CHANGE ORDER I BARSCREEN3, Page I of 2
calendar days to comp!l�etel the work.
1
Other work proposed, to be completed under this change order No. includes:!
• the installation of a 39-inch manhole to resolve an underground conflict,
• contract modifications to non-intrusive valve actuators,
• additional length of bypass pumping hose required to meet plant operating constraints, and
• the fabrication of additional stainless steel wiire plate for Bar,Screen Building 3 influent, channel at
flume 7.
Malcolm Pirnie, Inc., the design engineer and Camp Dresser & McKee, Inc., the construction manager
have reviewed the costs, consider them to be fair and reasonable and recommend approval. City Staff
concurs, with the recomimendations.
MWBE - Ark Contracting Services LLC, agrees to maintain its initial M/WBE commitment of 22 percent
that it made on the original contract and extend and maintain that same M[WBE commitment of 22 percent
to this first change order. Therefore Ark, Contracting Services LLC, remains in compliance with the City's
M/WBE Oirdinanice and attes,ts, to its colm�m�itrnein�t by its signature, on the Acceptance of Previous M/WBE
Commitment form executed by an authorized representative of its company.
The Village Creek Water Reclamation Facility is located in COUNCIL DISTRICT 5 and serves ALL
COUNCIL DISTRICTS.
FISCAL INFORMATION 1 CERTIF...1-CATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Sewer Capital Projects Fund.
FUND CENTERS:
TO Fund/Account/Centers FROM Fund/Account/Centers
P258 541200 701300018680 $1.660,195.70
,CERTIFICATIONS.-
Submitted for City Manager's Offic Fernando Costa (6122)
Orig.,inat,'I'ng-Der)artment Head S. Frank Crumb (82,97)
1 a,delene, R,afalko (812,15)
Adldlfio�nall (information Cont Ctact
u-
........__.......... ........
ATTACHMENTS- " -
1 6 Ark Chan geOrder 1 Barscreen3 FAR.r)df (CFW Internal)
2,. 60A,R,K CHANGE ORDER 1 BA,RSCREEN3 MWBE-I)df (CFW Internal)
3. 610ARK CHANGE ORDER 1 BIAR,SCREEN3 REVISED Mapp ,,,,f tPublic)
................. .............. ..............
4. (CFW Internal)
Logname: 60ARK CHANGE ORDER I BARSCREEN3 Page 2 of 2