STATE OF TEXAS § CONTRACT NO. ` j TI" L
§ Renewal and Amendment of Interlocal Agreement Court
Order No. 110472
COUNTY OF TARRANT § Project: Harley
BACKGROUND
1. Tarrant County (��COUNTY'J and the City of Fort Worth ("CITY' entered
into an Agreement approved by Tarrant County Commissioners Court
Order No. 110472, for the cooperative funding of improvements to Harley
Street ("Project' as described in the 2006 Tarrant County Bond Program,
2. The Project is not complete and the COUNTY and the CITY desire to
renew the Agreement for the 2014 Fiscal Year.
Therefore, the COUNTY and CITY agree to the following
1. The COUNTY and the CITY renew the Agreement for the COUNTY's 2014
Fiscal Year with the Agreement to expire September 30, 2014 or the
completion of the Project as determined by the COUNTY, whichever
occurs sooner.
2. The COUNTY and CITY agree to amend the costs as shown in the revised
--I payment schedules.
pFF�C1A� RECOORD All terms and conditions of the original Agreement as amended remain in
CITY SECRETARY
FT. WORTH, TX effect except to the extent modified by this Renewal.
•
�P' OVED on this day the �Z- day of , 20/YJF by
Tarrant County,
W 44
TARRANT COUNTY
STATE OF TEXAS
County Judge
Commissioners Court Order No. ��7,�,3�
t1t11 • - • � NH
�ltt
WIN
nature
tiF
�.. J���,".. •.r7xjiit12
APPROVED AS TO FORM AND
Interlocal Agreement Transportation Bond 2006-2007
(2 .0 3.13 Page 1
ti
MaAMALIMMIK&M-1iF
*By law, the District Attorneys Office may only approve contracts for its clients. We reviewed this
document from our client's legal perspective. Other parties may not rely on this approval. Instead, those
parties should seek contract review from independent counsel.
CERTIFICATIOI�I OF A l/AILABLE FUNDS
��SS367. 6�
Certification of Funds Available as follows:
Fiscal year ending September 30, 2007
Fiscal year ending September 30, 2008
Fiscal year ending September 30, 2009
Fiscal year ending September 30, 2010
Fiscal year ending September 30, 2011
Fiscal year ending September 30, 2012
Fiscal year ending September 30, 2013
Fiscal year ending September 30, 201�
IN THE AMOUNT OF
0
0
0
0
0
$2,858,285.83
$3551367.67�,
All future years funding is contingent on future debt issuance
and renewal %J this contract
Fiscal year ending September 30, 2015
Fiscal year ending September 30, 2016
Auditor's Office
0
$3,213,653.50
Interlocal Agreement Transportation Bond 2006-2007 Page 2
ATTACHMENT A
Project Information
City: City of Fort Worth
Project Name. Construction of Harley Street from University to Montgomery
Proposed Project Schedule
*
Design:
ROW Acquisition:
Utility Relocation:
Construction:
Start Date
Jul-2010
May-2011
Feb-2012
Duration (mo)
12
6
End Date *
Jul-2011
Nov-2011
21 Nov-2013
COUNTY payments by completed phase are contingent upon the COUNTY'S
reasonable determination that the work regarding the project phase for which payment
is expected is successfully completed, as determined by the COUNTY. COUNTY
plans to issue debt for all phases of this project, therefore payment remains contingent
on debt issuance in accordance with applicable law.
Once Construction commences, COUNTY payment shall be made by fiscal quarter
prorated over the life of the construction but contingent upon reasonable progress in
construction as may be determined by the COUNTY.
Proposed County Payment by Phase
Design. $
ROW Acquisition: $
Utility Relocation: $
Construction: $3,213,653.50
County Funding
Total: $3,213,653.50
Proposed County Payment by Calendar Quarter (SUBJECT TO CHANGE)
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$2,858,285.83
$
$
$355,367.67
$
$
$
$
$
$
$
$
$
$
$
$
Interlocal Agreement Transportation Bond 2006-2007
Page 3
M&C Review
Page 1 of 2
official site of the City of Fort Worth, Texas
FORT WORTH
DATE:
CODE:
SUBJECT:
COUNCIL ACTION: Approved on 12/3/2013
12/3/2013 REFERENCE
NO.:
C TYPE
C-26578
NON -
CONSENT
LOG NAME:
PUBLIC
HEARING:
20RENEWAL TARRANT
COUNTY ILA FUNDING
AGRMT FY 2014
NO
Authorize Renewal of Five Interlocal Agreements with Tarrant County for the Construction
Costs to Realign Harley Avenue Between University Drive and Montgomery Street in a
Revised Amount of $3,213,653.50, for the Construction of Summer Creek Drive in the
Amount of $500 000.00, for Reconstruction of East Rosedale Street from US 287, West of
Miller Avenue in the Amount of $7,994,000.00, for the Reconstruction of East Rosedale
Street Near the Texas Wesleyan Campus in the Amount of $375,000.00, and for
Improvements to Ten Traffic Signals Along State Highway 183 in the Amount of
$108,000.00 (COUNCIL DISTRICTS 4, 6, 7, 8, and 9)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the renewal of the Interlocal Agreement with Tarrant County, Texas for the construction
project to realign Harley Avenue between University Drive and Montgomery Street, City Secretary
Contract No. 41877 in a revised amount of $3,213 653.50;
2. Authorize the renewal of the Interlocal Agreement with Tarrant County Texas for the construction
of Summer Creek Drive, City Secretary Contract No. 43321 in the amount of $500,000.00.
3. Authorize the renewal of the Interlocal Agreement with Tarrant County, Texas for the
reconstruction of East Rosedale Street from US 287 to west of Miller Avenue, City Secretary Contract
No. 44514 in the amount of $7,994,000 00;
4. Authorize the renewal of the Interlocal Agreement with Tarrant County, Texas for the
reconstruction of East Rosedale Street near the Texas Wesleyan Campus City Secretary Contract
No. 44513 in the amount of $375,000.00; and
5. Authorize the renewal of the Interlocal Agreement with Tarrant County, Texas for the
improvements to ten traffic signals along State Highway 183 City Secretary Contract 44498 in the
amount of $108,000.00.
DISCUSSION:
The renewal of these Interlocal Agreements are required to maintain Tarrant County's funding
obligation in the new Fiscal Year.
HARLEY AVENUE
On March 22, 2011, the City Council authorized (M&C C 24801) City Secretary Contract No. 41877,
an Interlocal Agreement with Tarrant County for County funding participation in an amount not to
exceed $4,500,000.00 for construction. This value of $4,500 000.00 was based on an as -built cost
estimate before advertisement for construction.
In 2012, Staff revised the project cost based on construction bids; the revised Tarrant County funding
participation for construction of Harley Avenue is $3,213 653.50. The City will own and maintain the
roadway after construction is complete. This renewal adjusts the amount and timing of the payments
to better coincide with actual project delivery.
http://apps.cfwnet org/council_packet/mc_review.asp7ID=19198&councildate=12/3/2013 5/7/2014
M&C Review Page 2 of 2
SUMMER CREEK DRIVE
On April 17, 2012, the City Council authorized (M&C C-25564), City Secretary Contract No. 43321,
an Interlocal Agreement with Tarrant County for cost participation and accepted Tarrant County's
contribution in the amount of $500,000.00 to partner in funding the project. This renewal adjusts the
timing of the payments to better coincide with actual project delivery.
RECONSTRUCTION OF EAST ROSEDALE STREET
On September 25, 2012, the City Council authorized (M&C C-25881), City Secretary Contract No.
44514 an Interlocal Agreement with Tarrant County for County funding participation in an amount not
to exceed $7,994,000.00 for the reconstruction of East Rosedale from US 287 to west of Miller
Avenue. This renewal makes no adjustments to the original Agreement.
RECONSTRUCTION OF EAST ROSEDALE STREET — TWU CAMPUS
On September 25, 2012, the City Council authorized (M&C C-25866), City Secretary Contract No.
44513 an Interlocal Agreement with Tarrant County for County funding participation in an amount not
to exceed $375,000.00 for the reconstruction of East Rosedale Street from Nashville Avenue to
Collard Street. This renewal adjusts the timing of payments to coincide with actual project delivery.
IMPROVEMENT TO TRAFFIC SIGNALS ON SH 183
On September 14, 2010, the City Council authorized (M&C G-17050), City Secretary Contract No.
44498 an Interlocal Agreement with Tarrant County for the County funding participation in an amount
not to exceed $108 000.00 for traffic signal improvements on SH-183. This renewal makes no
adjustments but keeps the Agreement current.
These projects are located in COUNCIL DISTRICTS 4, 6, 7, 8, and 9, Mapsco 56M, 74W, 75H, 76E,
77L, 78K, 78M, 102E, and 102R.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that this action will not increase the total
appropriations of City Funds.
TO Fund/Account/Centers FROM Fund/Account/Centers
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Douglas W. Wiersig (7801)
Additional Information Contact: Jim Walker (8009)
ATTACHMENTS
Map ILA Harley Ave.pdf
Map ILA SH 183 pdf
Map Rosedale Street at Texas Wesleyan.pdf
Map Rosedale Street From US 287.pdf
Map Rosedale to Miller Avenue.pdf
http://apps.cfwnet.org/council_packet/mc_review.asp?ID=19198&councildate=12/3/2013 5/7/2014