HomeMy WebLinkAboutContract 41560COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS §
COUNTY OF TARRANT §
City Secretary
Contract No. 1-1-k(eon
WHEREAS, the undersigned "Developer" desires to make certain improvements to
an addition to the City of Fort Worth, Texas; and
WHEREAS, the City of Fort Worth, a home -rule municipal corporation situated in
Tarrant, Denton, Parker, and Wise Counties, Texas (the "City"), has approved and desires
to participate in Developer's CFA project described herein (the "Project") in accordance
with this Agreement as presented by the Cost Summary Table and Exhibits hereto and
authorized by City Council via M&C Lea Li ma on D \�s, 2011; and
WHEREAS, the City has requested the undersigned "Developer" to cause, and the
Developer desires to cause, the design, permitting and construction of the Project for which
the City will reimburse the Developer for the City's portion of the work after City's final
acceptance of the project in accordance with the adopted Unit Price Ordinance as provided
by the Policy for the Installation of Community Facilities, Section II, as amended.
Developer:
Company: UT Southwestern Moncrief Cancer Center
Authorized Signatory: John A. Roan
Title: Treasurer
Project Name:
Moncrief Cancer Institute
West Magnolia Avenue
Lot 1 R, Block C-D, Fairlawn Subdivision of the Fields — Welch Addition
Mapsco: 77J Council District: 9
CFA: ,,\1 p_ Ca)o`V
OFFICIAL RECORD
CITY SECRETARY
Ft WORTH, TX
DOE: 6540 City Project No. 01610
1
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and
the Developer do hereby agree as follows:
General Requirements
A. The Policy for the Installation of Community Facilities ("Policy") dated March
2001, approved by the City Council of the City of Fort Worth and subsequently
amended from time to time via a Mayor and Council Communication adopted
by the City Council of the City of Fort Worth, is hereby incorporated into this
Community Facilities Agreement ("CFA") as if copied herein verbatim
Developer agrees to comply with all provisions of said Policy in the
performance of its duties and obligations hereunder and to cause all contractors
hired by Developer to comply with the Policy in connection with the work
performed by said contractors, except as otherwise limited by or provided in
this Agreement.
B. Developer shall provide fmancial security in conformance with paragraph 6,
Section II, of the Policy and recognizes that there shall be no reduction in the
collateral until the Project has been completed and the City has officially
accepted the infrastructure. Developer further acknowledges that said process
requires it to submit an Affidavit of Bills paid signed by its contractor and
consent of Surety signed by its surety to ensure the contractor has paid the
sub -contractor and suppliers in full. Additionally, the contractor will provide
in writing that the contractor has been paid in full for all the services
provided under this contract.
C. Developer agrees to cause the construction of the improvements contemplated
by this Agreement as descnbed on the Exhibits attached hereto and that said
construction shall be completed in a good and workmanlike manner and in
accordance with all City standards and the City -approved construction plans,
specifications and cost estimates provided for the Project and the exhibits
attached hereto.
D. The following checked exhibits are made a part hereof: Water (A) X
Sanitary Sewer (A-1) X ; Paving (B) ; Storm Drain (B-1) ; Street
Lights and Signs (C) .
E The Developer shall award all contracts for the construction of community
facilities in accordance with Section II, paragraph 7 of the Policy and the
contracts for the construction of the public infrastructure shall be administered
in conformance with paragraph 8, Section II, of the Policy.
F. For all infrastructure included in this Agreement for which the Developer
awards construction contract(s), Developer agrees to the following:
i. To employ a construction contractor who is approved by the director of the
depaitiuent having jurisdiction over the infrastructure to be constructed, said
contractor to meet City's requirements for being msured, licensed and
bonded to do work in public streets and/or prequalified to perform
water/waste water construction as the case may be.
ii To require its contractor to furnish to the City a payment and performance
bond in the names of the City and the Developer for one hundred percent
(100%) of the contract price of the infrastructure, and a maintenance bond in
the name of the City for one hundred percent (100%) of the contract price of
the infrastructure for a period of two (2) years insuring the maintenance and
repair of the constructed infrastructure during the term of the maintenance
bond. All bonds to be furnished before work is commenced and to meet the
requirements of Chapter 2253, Texas Government Code.
iii To require the contractor(s) it hires to perform the construction work
contemplated herein to provide insurance equal to or in excess of the
amounts required by the City's standard specifications and contract
documents for developer -awarded infrastructure construction contracts. The
City shall be named as additional insured on all insurance required by said
documents and same will be evidenced on the ACORD Certificate of
Insurance supplied by the contractor's insurance provider and bound in the
construction contract book.
iv. To require its contractor to give 48 hours notice to the City's Construction
Services Division of intent to commence construction so that City inspection
personnel will be available; and to require the contractor to allow the
construction to be subject to inspection at any and all times by City
inspection forces, and not to install or relocate any sanitary sewer, storm
drain, or water pipe unless a responsible City inspector is present and gives
his consent to proceed, and to make such laboratory tests of materials being
used as may be required by the City.
v. To require its contractor to have fully executed contract documents
submitted to the City to schedule a Pre -Construction Meeting. The submittal
should occur no less than 10 workmg days prior to the desired date of the
meeting. No construction will commence without a City -issued Notice to
Proceed to the Developer's contractor.
vi. To delay connections of buildings to service lines of sewer and water mains
constructed under this Agreement until said sewer and water mains and
service lines have been completed to the satisfaction of the Water
Department
G. Developer agrees to provide, at its expense, all engineering drawings and
documents necessary to construct the improvements required by this
Agreement.
H. Developer shall cause the installation or adjustment of the required utilities to
serve the development or to construct the improvements required herein.
I. Unless necessitated by the City's participation in this Agreement, City shall not
be responsible for payment of any costs that may be incurred by Developer in
the relocation of any utilities that are or may be in conflict with any of the
community facilities to be installed hereunder. However, City will be
responsible for the costs of utility relocation necessitated by the City's
participation in this Agreement.
J. Developer hereby releases and agrees to indemnify, defend and hold the City
harmless for any inadequacies in the preliminary plans, specifications and cost
estimates supplied by the Developer for this Agreement.
K. Developer agrees to provide, at its expense, all necessary rights of way and
easements across property owned by Developer and required for the construction
of the current and future improvements provided for by this Agreement.
L The Developer further covenants and agrees to, and by these presents does
hereby, fully indemnify, hold harmless and defend the City, its officers agents
and employees from all suits, actions or claims of any character, whether real
or asserted, brought for or on account of any injuries or damages sustained by
any persons (including death) or to any property, resulting from or in
connection with the construction, design, performance or completion of any
work to be performed by said Developer, his contractors, subcontractors,
officers, agents or employees, or in consequence of any failure to properly
safeguard the work, or on account of any act, intentional or otherwise, neglect
or misconduct of said Developer, his contractors, sub -contractors, officers,
agents or employees.
M The Developer will further require its contractors to indemnify, defend and
hold harmless the City, its officers, agents and employees from and against any
and all claims, suits or causes of action of any nature whatsoever whether real
or asserted, brought for or on account of any injuries or damages to persons or
property, including death, resulting from or in any way connected with the
construction of the infrastructure contemplated herein, whether or not such
iniuries. death or damages are caused. in whole or in Dart. by the
alleged negligence of the City of Fort Worth. its officers, servants, or
employees. Further, Developer will require its contractors to indemnify, and
hold harmless the City for any losses, damages, costs or expenses suffered by
the City or caused as a result of said contractor's failure to complete the work
and construct the improvements in a good and workmanlike manner, free from
defects, in conformance with the Policy, and in accordance with all plans and
specifications and shall cause to be executed and delivered to the City an
indemnity agreement from such contractors on a form to be promulgated by the
City.
N. Upon completion of all work associated with the construction of the
infrastructure and improvements, Developer will assign to the City a non-
exclusive right to enforce the contracts entered into by the Developer with its
contractor along with an assignment of all warranties given by the contractor,
whether express or implied Further, Developer agrees that all contracts with
any contractor shall include provisions granting to the City the right to enforce
such contracts as an express intended third party beneficiary of such contracts.
O. Inspection and material testing fees are required as follows and further
apportioned in the Cost Summary Table below
i. Developer shall pay in cash water and wastewater inspection fees and
material testing fees equal to two percent (2%) for a total of 4% of the
Developer's share of the total construction cost as stated in the construction
contract.
ii Developer shall pay in cash paving and storm drain inspection fees equal to
four percent (4%) and material testing fees equal to two percent (2%) for a
total of 6% of the Developer's share of the total construction cost as stated in
the construction contract.
iii Developer shall pay in cash the total cost of streetlights or if the City is not
installing the streetlights inspection fees equal to four percent (4%) of the
Developer's share of the streetlight construction cost as stated in the
construction contract.
iv. Developer shall pay in cash the total cost of street signs necessary for
Developer's portion of the Project.
P. COMPLETION WITHIN 2 YEARS
i. The City's obligation to participate (exclusive of front foot charges) in the
cost of the community facilities shall terminate if the facilities are not
completed within two (2) years; provided, however, if construction of the
community facilities has started within the two year period, the Developer
may request that the CFA be extended for one year. If the community
facilities are not completed within such extension period, there will be no
further obligation of the City to participate. City participation in a CFA shall
be subject to the availability of City funds and approval by the Fort Worth
City Council, as evidenced by M&C C- 64L-.-`n r3, approved
ii. Nothing contained herein is intended to limit the Developer's obligations
under the Policy, this Agreement, its financial guarantee, its agreement
with its contractor or other related agreements.
iii. The City may utilize the Developer's financial guarantee submitted for this
Agreement to cause the completion of the construction of the community
facilities if at the end of two (2) years from the date of this Agreement the
community facilities have not been completed and accepted.
iv. The City may utilize the Developer's financial guarantee to cause the
completion of the construction of the community facilities or to cause the
payment of costs for construction of same before the expiration of two (2)
years if the Developer breaches this Agreement, becomes insolvent or fails to
pay costs of construction and the financial guarantee is not a Completion
Agreement. If the financial guarantee is a Completion Agreement and the
Developer s contractors and/or suppliers are not paid for the costs of supplies
and/or construction, the contractors and/or suppliers may put a lien upon
the property which is the subject of the Completion Agreement.
Q. CITY PARTICIPATION
i. The costs stated herein may be based upon construction estimates rather
than actual cost. The City's portion of inspection and material testing
fees are directly allocated to the City's accounts for charges and does not
reimburse the Water Inspection and Material Testing Fees to the
developer. The City's participation estimate shall be based upon unity
prices contained in City of Fort Worth Ordinance No. 19192 (or by
public bid). The City's cost participation shall be in an amount not to
exceed $42,872.19 ("Participation' ), but the reimbursement of the
Participation (excluding inspection and material testing fees) is not a
lump sum amount and may be less than stated above depending upon
actual quantities from the Notice of Project Completion package (`Green
Sheet') and unit prices from the construction contracts document and
Green Sheet but not to exceed the unit pnces contained in the City of
Fort Worth Ordinance No. 19192;
Cost Summary Sheet
City Participation cost break downs City pays difference between 8"/12" for 576' of
waterline and 10' of 8" waterline, 8" gate valve and fire hydrants.
A. Water and Sewer Construction
1. Water
2. Sewer
Construction Cost Sub -Total
B. 25% Contingency
Construction Cost Total
Construction Fees*
C. Inspection Fee (2%)
D. Material Testing Fee (2%)
Construction Fees Sub -Total
Total Water and Sewer Project Cost
Developer's Cost
79,108.40
215,193.60
294,302.00
City's Cost Total Cost
$
$
$
73,575.50 $
367,877.50 $
32,978.60
32,978.60
$ 112,087.00
$ 215,193.60
$ 327,280.60
8,244.65 $ 81,820.15
41,223.25 $ 409,100.75
$ 7,357.55 $ 824.47
$ 7,357.55 $ 824.47
$ 14,715.10 $ 1,648.94
$ 382,592.60 $ 42,872.19
$ 8,182.02
$ 8,182.02
$ 16,364.03
$ 425,464.78
Note: Fittings, trench safety, traffic control and pavement repair is calculated as a
percentage (12-8)/12=33%.
The Checked Must be Included as Attachments to this Agreement
Included Attachment
X Location Map
X Exhibit A: Water Improvements
X Exhibit A-1: Sanitary Sewer Improvements
X Cost Estimate
(Remainder of the page intentionally left blank)
IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed in
quadruplicate in its name and on its behalf by its Assistant City Manager, attested by its City Secretary,
with the corporate seal of the City affixed, and said Developer has executed this instrument in
at Fort Worth, Texas this dayof ilAC0-4-tice , 2011.
quadruplicate,
CITY OF FORT WORTH: DEVELOPER:
UT Southwestern Moncrief Cancer Center
‘7-74.*0••••gd Ct.
Fernando Costa
Assistant City Manager
Recommended by:
Transportation & Public Works Department
N/A
William A. Verkest, P.E.
Director
Water Department
Wendy Chi -
Water Dev
79/
bulal, EMBA, P.E.
pment Engineering Manager
Approved as to Form & Legality:
10, ct,
Marcia Wise
etn. Assistant City Attorney
ATTEST:
Marty Hendrix
City Secretary
Authorization:
M&C:
Date:
11
•
A. Roan, Treasurer
frank Crumb, Director
4
„cse-$04.-ttittirtrti
,cr• f0387*
• *000000004fr
0� k
T 4 04 ,'9
',Attawieti9
OFFICIAL RECORD I
CITY SECRETARY �
ft WORTH, TX
1
c
o.
OirsL.
0) O
O per.
CO
N 0
C
F0RTW�RTH UT Southwestern Moncrief Cancer Center
WATERWater Map
i
Vs) 7-
j•,
C c
r=■■e g
`° *VAC 16
CV)
• _ v
mm
a)
c• Ow
W
0
CD 0
om
C
a
ous
�.
O C
U
t 0•
8
>+ c
a
0
o to
Et Tti
Q. ID
c
m
rna
,
IL o
Legend
OS DALE
12" Waterline
r
1i!■id SET FL =EV A
•1 I0111111111111f♦Oil`.
4 11.110111.1 OE MI MO
sw1 OM a InMMI_■r
Wing MINOM
r11.1laNMil Ell
It�MIm
Emma no mi •No so cm mi IN m
MI —t■�MO SI MI 1
NI IS MI NO air
as au or ow
aim
--- ti
! `-•.
hOSEDAL.E
a
■irk `��ti
d �; L'R.WII lKI
■
IIIIIiiii 4 - »iI ,,f;
III11m Ia1�11. �•' —•
IIIIIillll!fl '
ai1111i11u111u iI
iuui Y1u1111l r •{
,.04111111110, .41111111,,J E ,�
111�!illl r��' :' II��IIIItI' E____
■I�•��lr ,�- /Itltt� IIIIIIIRir�l�irll
Irj i,JIIIIWIt'llr'glill■1■ 11111 1���1
imps' i nsri ,11111I1�' ti I•IL
"ter ti111�aIiii .! MIut'Jir,n Imwal
n ,1111111Ci:r1InN11p at1u1uIFlii�i' n . nal
�SIIIIII!�1�• ;1;u;Itu1 i1IIIrl1r IIIIfl
. eli arnii.■uIII__�,. IIIHP!I
r ■I■■--i
1i weir 1k11:zi
111111111111NEMP;WiErililr-=5:
1 14t=.7—.Au"1/41/26ll1/4,r1.1.■tililL. LII�L �—ir
i.�" �. rJ L t
FIJI_111
I1 ■m■
111 111
a:OE? VIM
rel: 't 4.1
cp
3
0
73
0
L
0
c�
1
m
3
ao
m
co
0
d)
ca
m
L
m
0
co
ccn
n
m
as
3
.D
S
mD
rei
3
A
N
O
O
0
3,500
7,000 10,500 14,000
Feet
NAD_1983 StatePlane rexas_North Central_FIPS 4202_Feet 1 inch equals 7000 feet
3 Pipe - Sewer - 21-Inch PVC (All Depth) - Install (BID-00287)
4 Manhole - Std. 4-Foot Dia. (to 6-Foot Depth) - Install (BID-00213)
Manhole - Std. 4-Foot Dia. Added Depth (over 6-Foot Depth)
Install (BID-00214)
Manhole - Drop - Std. 4-Foot Dia. (to 6-Foot Depth) - Install (BID-
00207)
Manhole - Drop - Std. 4-Foot Dia. - Added Depth (over 6-foot Depth)
Install (BID-00208)
8 Collar - Manhole - 32-Inch - Frame & Cover -- Install (BID-00198)
Pavement Repair - 2-Inch Min HMAC (STR-028) Permanent Install
(BID-00443)
10 Inspection - Post Construction Cleaning & TV - Study (BID-00201)
ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST
IITEM I DESCRIPTION
QTY/UNIT I I PRICE
INSTALLATION OF 12" WATER LINE IN OLEANDER STREET (FROM JENNINGS TO ST. LOUIS)
1 Cut and Plug Unused Water Services 9 EA $
2 Irrigation Service-2 Inch - Tap to Main - Install (BID-00755)
3 Irrigation Service-2 Inch Copper - Install (BID-00753)
4 Water Service-2 Inch - Tap to Main - Install (BID-00767)
5 Water Service-2 Inch Copper '- Install (BID-00763)
Pipe-Pressure-8 Inch PVC - Install (BID-00616)
6 Pipe-Pressure-12 Inch PVC - Install (BID-00591)
Pipe-Pressure-8 Inch PVC - Install (BID-00618) (Connection at
Oleander and May)
8 Valve-12 Inch -Gate- wNalve Box - Install (BID-00717)
9 Valve-8 Inch -Gate- wNalve Box - Install (BID-00749)
10 Fire Hydrant Assembly w/ 6" Gate Valve Install (BID-00546)
11 Pipe Fittings for < Than 16 Inch DI (BID-00568)
12 Trench Safety System 5 Foot Depth - Install (BID-00372)
13 Traffic Control for Utilities - Install (BID-00181)
14 Pipe -Grout -Non -Shrink-- Install (BID-00224)
Pavement Repair-2 Inch Min HMAC (STR-028) Permanent Install
(BID-00443)
TOTAL
7
15
ITEM
DESCRIPTION
1
35
1
35
35
576
EA
LF
EA
LF
LF
LF
800.00
866.00
32.00
866.00
32.00
30.00
38.00
10 LF $ 30.00
8
2
3
4.30
641
586
3.2
EA $ 1,587.00
EA $ 935.00
EA $ 2,360.00
Ton $ 3,600.00
LF $ 1.00
LF $ 15.00
CY $ 110.00
641 LF $ 48.00
I QUANTITYI UNIT I PRICE
AMOUNT I
7,200,00
866.00
1,120.00
866.00
1,120.00
1,050.00
21,888.00
300.00
12,696.00
1,870,00
7,080.00
15,480, 00
641.00
8,790.00
352.00
$ 30,768.00
$ 112,087.00
I AMOUNT
INSTALLATION OF 21" SANITARY SEWER LINE IN MAGNOLIA, JENNINGS, AND OLEANDER STREET
1 Sewer Servie-4 Inch - Install (BID-00354) 18 LF $ 26.00 $
2 Cut and Plug Unused Sanitary Sewer Services 9 EA $ 800.00 $
5
6
7
9
16
11 Inspection - Pre Construction Cleaning & TV - Study (BID-00202)
12 Manhole -Vacuum Test - Services (BID-00217)
13 Portable Changeable Message Sign
14 Pipe -Grout -Non -Shrink- Install (BID-00224)
15 Trench Safety System 5 Foot Depth - Install (BID-00372)
Traffic Control for Utilities - Install (Plans require TX Registered
Engineer's Seal) (BID-00181)
TOTAL
986 LF $ 125.00 $
5 EA $ 2,340.00 $
13.7 VF $ 148.00 $
2 EA $ 3,020.00 $
9 VF $ 257.00 $
7 EA $ 39.00 $
1,004 LF $ 39.00 $
979 LF $ 2.00 $
1,154 LF $ 3.00 $
7 EA $ 104.00 $
7 DAYS $ 85.00 $
3 CY $ 110.00 $
986 LF $ 1.00 $
979 LF $ 15.00 $
468.00
7,200.00
123,250.00
11,700.00
2,027.60
6,040.00
2,313.00
273.00
39,156.00
1,958.00
3,462.00
728,00
595.00
352.00
986.00
14,685.00
215,193.60
2009076_Moncrief Cancer Institute_11-0214_13DM
Page 1 of 1
EXIS7ING 18"—
WATER LINE
EX-12"-W
—W-
4y
co
i W
rPROPOSED 12"
WATER LINE
PROPOSED FIRE
EXIS77NG 6"—
WATER LINE
EXIS77NG FIRE I I"DRANT
TO BE REMOVE[' AND
SALVAGED TO P'/ 7 PROPOSED 8'-
1.
I (--PROPOSED 12" WATER LINE
Y W. OLEANDER STREET
WATER LINE
ra'---, , 1
////L
/ /
-CO� / /
w
/ /
JXlSfNG� 3/4" ME � TO BE
,REMOV�� AND AAi.V.'4GED TO
/CITY. SERVICE TO 9F CUT
BIND PLL't4 /A/T MAIN.
/ /
3 / EXIS77NG/
, / BUILDING /
-
gym'-. EXISTING 3/4" NETER TO BE
/,REMOVED AI'1h •iALVAGED TO
CITY. SERVleE TO BE CUT
— ,AND PLUGB'L' ,1T MAIN.
OX /RR1G//A;7O, SERVICE AND
28
/1-2" DOME'),C WATER SERVCE
/AND BOX /
,1.-8" FIRE •R6rCE
� ro
/
/
REMOVED
CITY. SER�'1
AND PLU
4" METER TO BE
D SALVAGED 7O
TO BE CUT
AT MAIN.
11
EXIS771sY 1 12"
WATER LINE
l
X-12"-WL' EX-12"-W EX-12"-W
REMOVE AND SALVAGE EX. FIRE HYDRA
INSTALL NEW F7RE HYDRANT.
PROPOSED WATER LINE
EXIS77NG WATER LINE
EXIS77NG F7RE HYDRANT
PROPOSED F7RE HYDRANT
PROPOSED WATER METER
EXIS77NG WATER METER
PROPOSED FIRE
HYDRANT
•4
W
C 6"
WATER LINE
PROPOSED 12"
WATER LINE
EXIS77NG FIRE HYDRANT
TO BE REMOVED AND
SALVAGED TO CITY
LOT 1 R, BLOCK
C—D
FAIRLA WN
SUBDIVISION
OF FIELDS —WELCH
ADDITION
EXIS77NG 3/4" METER TO BE
REMOVED AND SALVAGED TO
CITY. SERVICE TO BE CUT
AND PLUGGED AT MAIN.
EX1S71NG 6" WATER LINE
TO BE ABANDONED AND
GROUTED IN PLACE
c
': EXI677NG 3/1"
,, TO BE REMOVED
SALVAGED T9 1
SET» NCE TO BE
AN) PLUGGED 4
- MAN.
T.
0
EX-12"-W
T
W
48'
v /
EX-� 2' W
W. MAGNOLIA AVENUE
40
w
EXHIBIT "A"
WATER LINE EXHIBIT
MONCRIEF CANCER CENTER
EXIS7ING 8"
WATER LINE
\--EXISTING 8"
WATER LINE
GRAPHIC SCALE
50 100 200
( IN FEET )
1 inch = 100 ft.
DUNAWA
550 Baby Avenue • Sulte 400 • Fat Worth. Texas 76107
Tel:817.335.1121 • Fax 817.335.7437
(DREG. F-1114)
SS-„9-x3
SS-„9-X3
CONNECT TO Eh 1S7/NG
16" LAN. SEWER
(M-23AR)
M „9 X3
—SSemompluggm
•
SS-„91-X3
it
PROPOSED 1" )
Nl9I-Or atwtK ( EX- 1860J L t -ft VAIVIJ4; EX-18"-W
SS ss fit ss
1f 1 I/1
1-6" SAN. SEWER SERVICE W/ \\\\XNkilibisPkX
PROPOSED 4' DIA. SSMH \ CONNECT To EXISVr
\\\\\-\\\\\ SAN. SEWER (L-2104R) \
EXIST. 4' SSMH ABANDON
AND GROUT IN PLAX
N SS
E;41 774IG 6" SANITARY
SE TO BE ABANDONED\•
Alp GROUTED IN PLACE \\\\\\\\\\\\\\\\\c
(1—J j
EXIS77NG
BUILDING
RE
OF
15 T\
EX:STING 8" SANITARY
SEVER TO BE ABANDONED
AND GROUTED IN PLACE
(L-264R)
XIS7ING 16" SANITARY
WER TO BE ABANDONED
U c4vuu iWU In `FZHCt
8
EX-6"-W
REMOVE AND DISPOSE
OF 4" SSMH
m—TwWST.. 4' SSMH ABANDON
wm X AIV GROUT IN PLACE
llr'
EXI n i 6"
SE OBE ABANDONED �t?"
AN GR-'U7ED IN PLACE
Q X (L—f 15)
w x
m
ty
rV ir% �,, �E ' IB-B=-3AfVPFi4RY
�R
1'1" SSMH
SSMH
OPOSED 21"
NITARY SEWER
REMOVE AND DISPOSE OF
EXIST. 8" SANITARY SEWER
(L-2104R)
INSTALL 4' SSMH
CONNECT TO EXISTING 16"
SAN. SEWER (M-23AR)
REMOVE AND DISPOSE
OF 4' SSMH
EX-6EX-6"-W
1-
LOT 1 R, BLOCK
C—D
FAIRLA WN
SUBDIVISION
OF FIELDS— WFI C -I
ADDI TION
[EMOVED
EXISTING 10' SANITARY
SEWER
XIST. SANIDRY SEWER
ERVICES TO BE / !/
EuivigAvigam
PROPOSED SANITARY SEWER
EXISTING SANITARY SEWER
EXIS77NG SANITARY SEWER MANHOLE
PROPOSED SANITARY SEWER MANHOLE
EX 10" SS
EX-10"-S
EX-/
r
041
EX-18"-W
Ex 16" SS
X 6' W
EX 6"-SS
EX 8" W
EXHIBIT "A-1"
SEWER LINE EXHIBIT
MONCRIEF CANCER CENTER
GRAPHIC SCALE
50 100 200
( IN FEET )
1 inch = 100 ft.
DU
550 Belay Avenue • Suite 400 • Fort Worth, Texas 76107
Tel: 817.335.1121 • Foz 817.335.7437
(D(REG. F-1114)
M&C Review
COUNCIL ACTION: Approved on 1/25/2011
DATE: 1/25/2011 REFERENCE NO.: **C-24702 LOG NAME'
CODE& C TYPE:
PUBLIC
HEARING:
SUBJECT: Approve Community Facilities Agreement in the Amount of $42,872.19 with UT
S outhwestern Moncrief Cancer Center for Construction of Water and Sewer Services to
S erve UT Southwestern Moncrief Cancer Center Located in Fort Worth with City
P articipation (COUNCIL DISTRICT 9)
Page 1 of 2
Official site of the City of Fort Worth, Texas
FORT WORTH
60MONCRIEF CANCER
CENTER
CONSENT
NO
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute a Community
Facilities Agreement in the amount of $42,872.19 with UT Southwestern Moncrief Cancer Center for
the installation of water and sanitary sewer services to serve UT Southwestern Moncrief Cancer
Center, a development, located in Fort Worth with City participation.
DISCUSSION:
UT Southwestern Moncrief Cancer Center, the developer of UT Southwestern Moncrief Cancer
Center, has executed a proposed contract for community facilities to serve a development located in
Fort Worth, (see attached map).
The total cost for water and sewer improvements for this development is $425,358.19. There will be
City participation to increase pipe capacity in development area. The Developer and City estimated
costs for water and sewer improvements are subject to construction inspection fees.
A. Water and Sewer Construction Developer's Cost
1. Water
2. Sewer
Construction Cost Sub -Total
Contingency 25 percent
Total Water and Sewer
Construction
Construction Fees:
B. Inspection Fee (two
percent)
C. Material Testing Fee (two
percent)
Construction Fees Sub -Total
Total Water and Sewer
Project Cost
This development is located in COUNCIL DISTRICT 9.
$ 82,039.40
$ 212,180.60
$ 294,220.00
$ 73,555.00
$ 367,775.00 $
7,355.50 $
7,355.50
14,711.00
382,486.00
City's Cost
32,978.60 $
32,978.60
8,244.65
41,223.25
824.47 $
824.47 $
1,648.94 $
42,872.19 $
Total Cost
115,018.00
212,180.60
327,198.60
81,799.65
408,998.25
8,179.97
8,179.97
16,359.94
425,358.19
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Water Capital Project Fund.
rnhtml:file://C•\Documents and Settings\knightj\Local Settings\Temporary Internet Files\OLK298\Moncrie... 01/26/2011
M&C Review Page 2 of 2
TO Fund/Account/Centers FROM Fund/Account/Centers
P265 539140 609150161083 $411223.25
P265 531350 609150161085
P265 531200 609150161084
Submitted for City Manaaer's Office bv: Fernando Costa (6122)
Oriainatina Department Head: S. Frank Crumb (8207)
Additional Information Contact: Viesha Kaminska (8428)
ATTACHMENTS
Exhibit A Water.pdf
Exhibit A-1 Sewer.odf
Moncrief Cancer Center CFA Exhibit water.pdf
$824.47
$824.47
mhtnil:file://C:\Documents and Settings\knightj\Local Settings\Temporary Internet Files\OLK298\Moncrie... 01/26/2011