Loading...
HomeMy WebLinkAboutContract 43542-CO1 (2)FORT WORTH® Cott' of '_trtVkimrrtth Change order Request Project Name BNSF Railway Track Installation / Alliance Airport Runway Extension Client Project #(s)I E.534596 Project Description Qwest Utility Relocation Contractor Qwest Communications Company, LLC City Project Mgr.I Ruseena Johnson Dept. Original Contract Amount Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date !Amount of Proposed Change Order Revised Contract Amount Original Funds Available for Change Orders Remaining Funds Available for this CO Additional Funding (if necessary) Aviation $1,274,844.51 $0.00 $0.00 $0.00 $1,274,844.51 $159,069.00 $1,433,913.51 $0.00 $159,069.00 i i Change Order # City Inspector f�1�r COMUACT CHANGE ORDERS to DATE (INCLUDING THIS ONE) AS % OF ORIGINAL CONTRACT JUSTIFICATION (REASONS) FOR CHANGE ORDER 1 -2-fl4 tr City Sec # L4?�-Itik i Date I 11/14/2012 Totals Select Day Type $1,274,844.51 $1,274,844.51 $159,069.00 $1,433,913.51 $0.00 $159,069.00 I 12.48% I i Net increase to include 2,000 ft Rock Directional Bore (estimated) and 30,000 ft exta trench depth (up to Eft) due to construction shedule adds $159,068.68. The estimate is based on preliminary engineering. ri 11(f): (2011 -010710 10 144(ard a Ind AL t Olt; 0 Mei I' Kay;W9 gNTS ro 8 000 cf ?pY � moo®0 te jl i1i \ 1C 11il ;l C iJ is i{,' it ;���� t) it l_ '�c . .. �1 ., t_ lit. l; LJ1 It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. L Contractor's Company Name Contractor (Name) Qwest Communications Company, LLC I Pieter Poll Inspector/Inspection Supervisor na Assistant Director (Dept) Date t Signature Date Project Manager/Program Manager Date Director, Contracting Department (Dept) ty Manager Date 11/14/2012 IL Date \\POil Date r214-ct ate // 21 /. 4 Council Action (if required) i MC Number -25-1* cy M&C Date Approved I uni 11-27-12 P03:49 IN Qwest NNS OSP Project Cost Summary Job Site / Work Location Project Name Project Location Cost Detail of OSP, FOC and Splicing Material Cost (Qwest Supplied) OSP Materials Splice Materials Fiber Optic Cable (FOC) BNSF FAA Relocation Haslet / FT. Worth, TX Quantity UOM 72,000 it Total Material Cost (Qwest) Shipping on Materials & FOC Shipping 600 m Total Shipping Cost Taxes on Materials & FOC Taxes on Materials and FOC Total Tax Cost External Labor Costs External OSP Construction Costs (Labor & All Remaining Materials) External Splicing Costs Engl.: 'rig and Inspection Costs - If Other Fees Including Permit & Right of Way Costs Railroad ROW fees Private ROW fees Miensllaneots ROW fees BNSF Coordinater O,vest Splicing 0 0 0 Internal Labor & Flagging Costs Field Support Construction Field Operations Construction Support Field Support Engineering & Permitting Field Support Splicing (from SFP) Field Operations Splicing Support (from SFP) Testing & Acceptance Support (from SFP) Fiber Planning Project Analysts CAD Fiberbase Fiber Leasing/Contracts Railroad Flagging Total Estimated Construction Cost Total External Costs Total Other Fees 500 120 20 60 24 60 100 24 24 hrs hrs hrs hrs hrs hrs hrs hrs hrs his hrs days Total Internal Support & Flagging Costs Estimated Cost 4,855.00 1,650.00 115,200.00 121,505.00 810.00 810.00 9,112.87 9,112.87 820,036.43 13,248.00 200,220.00 1,043,404.43 0.00 0.00 0.00 30,000.00 0.00 0.00 000 0.00 30,000.00 39,000.00 7,570.80 0.00 1,58000 3,765.40 0.00 1,872.00 4,680.00 7,800.00 1,872.00 1,872.00 0.00 70,012.20 Change Revised Estimate -4,855.00 -1,850.00 0.00 0.00 -472.88 178,790.75 -13,248.00 -1,660.00 0.00 0.00 0.00 0.00 20,000.00 0.00 0.00 0.00 0.00 -7,570.80 0.00 -1,560.00 -3,785.40 0.00 0.00 0.00 -3,120.00 0.00 0.00 0.00 0.00 0.00 115,200.00 810.00 8,840.00 1,006,727.18 0.00 198,560.00 0.00 0.00 000 30,000.00 20,000.00 0.00 000 0.00 39,000.00 0.00 0.00 0.00 0.00 0.00 1,872.00 4,680.00 4,680.00 1,872.00 1,872.00 0.00 1, 274, 844.51 159,068.68 1, 433, 913.18 Summery BNSF Affiance Airport Ertenvm ne282-14-12C0x!s 11/152012 City of Fort Worth, Texas Mayor and ouncil ommunication COUNCIL ACTION: Approved on 11/6/2012 DATE• Tuesday, November 06, 2012 LOG NAME: 55AFW RWY EXT UTILITY RELOC QWEST C01 SUBJECT: Authorize Execution of Change Order No. 1 to City Secretary Contract No 43542 with Qwest Communications Company, LLC d/b/a CenturyLink QCC, in the Amount of $159,069 00 for Relocation of Gas Pipelines Along John Day and Keller Haslet Roads as Part of the Runway Extension Project at Fort Worth Alliance Airport for a Revised Total Cost of $1,433,913.51 (COUNCIL DISTRICT 2) REFERENCE NO.: **C-25954 RECOMMENDATION. It is recommended that the City Council authorize execution of Change Order No. 1 to City Secretary Contract No. 43542 with Qwest Communications Company, LLC d/b/a CenturyLink QCC in the amount of $159,069.00 for relocation of gas pipelines along John Day and Keller Haslet Roads as part of the Runway Extension Project at Fort Worth Alliance Airport for a revised total cost of $1,433,913 51. DISCUSSION: On March 20, 2012, (M&C C-25511) the City Council authorized the City Manager to execute a construction reimbursement Agreement with Qwest Communications Company, LLC d/b/a CenturyLink QCC (Qwest), in the amount of $1,274,844.51 for the relocation of 12.5 miles of fiber optic lines as part of the Runway Extension Project at Fort Worth Alliance Airport. Change Order No. 1 is to authorize Qwest to complete additional directional bore in rock and extra trenching below the normal 48 inch depth to match the new elevation prior to others cutting grade as part of the Alliance Runway Extension project. This change order will increase the reimbursement amount by $159,069.00 for a revised reimbursement amount of $1,433,913.51. The Qwest utility facilities will be relocated by Qwest and Qwest will be reimbursed for the agreed upon amount. This Contract, including its change orders, is specifically exempted from competitive bidding requirements. M/WBE - A waiver for the goal for MBE/SBE subcontracting requirements was requested by the Aviation Department and approved by the M/WBE Office because the purchase of goods and services is from sources where subcontracting or supplier opportunities are negligible. Federal Aviation Administration funds from Alliance Runway Extension Grants will be used for this Project. Existing land credits that remain from the original land donation for Alliance Airport will be used for the City's 10 percent in -kind match This project is located in COUNCIL DISTRICT 2. FISCAL INFORMATION / CERTIFICATION: The Financial Management Services Director certifies that funds are available, as appropriated, in the Logname: 55AFW RWY EXT UTILITY RELOC_QWEST CO1 Page 1 of 2 current capital budget of the Airports Grant Fund. FUND CENTERS: TO Fund/Account/Centers FROM Fund/Account/Centers CR14 539120 055218339700 $159,069.00 CERTIFICATIONS: Submitted for City Manager's office bY: Fernando Costa (6122) Originatinq Department Head: Bill Welstead (5402) Ruseena Johnson (5407) Additional Information Contact: Patrick Buckley (2443) ATTACHMENTS 1. 00960 Project Mgp.pdf (Public) 2. 960 U-tility FAR 05521833900 9-12 . df (CFW Internal) 3. Funds availab€lit - M&C 55AFW RWY IT T UTILITY. df (CFW Internal) 4. Owest Comminieations LLC dba Centu Link OCC Waiver. df (CFW Internal) Logname: 5 5AFW RVVY EXT UTILITY RELOC_QWEST COI Page 2 of 2