STANDARD AGREEMENT FOR ENGINEERING RELATED DESIGN SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home -rule municipality
(the "CITY"), and Kimley-Horn and Associates, Inc., authorized to do business in Texas, (the
"ENGINEER"), for a PROJFC T generally described as: Street Improvements for the
Henderson Street Detour.
Art1cDe I
Scope of Services
A. The Scope of Services is set forth in Attachment A.
Article II
Compensation
A. The ENGINEER's compensation is set forth in Attachment B.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but not
limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
(3) Upon completion of services enumerated in Article I, the final payment of any
balance will be due within 30 days of receipt of the final invoice.
(4) In the event of a disputed or contested billing, only that portion so contested will
be withheld from payment, and the undisputed portion will be paid. The CITY
will exercise reasonableness in contesting any bill or portion thereof. No
interest will accrue on any contested portion of the billing until mutually
resolved.
(5)
If the CITY fails to make payment in full to ENGINEER for billings contested in
good faith within 60 days of the amount due, the ENGINEER may, after giving
7 days' written notice to CITY, suspend services under this AGREEMENT until
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 1 of 14
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
paid in full. In the event of suspension of services, the ENGINEER shall have
no liability to CITY for delays or damages caused the CITY because of such
suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental thereto.
Standard of Care
The standard of care applicable to the ENGINEER's services will be the degree
of skill and diligence normally employed in the State of Texas by professional
engineers or consultants performing the same or similar services at the time
such services are performed.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise the
CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise specified
in Attachment A.
(2) In soils foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive test
points and sample intervals and at locations other than where
observations, exploration, and investigations have been made Because
of the inherent uncertainties in subsurface evaluations, changed or
unanticipated underground conditions may occur that could affect the
total PROJECT cost and/or execution. These conditions and
cost/execution effects are not the responsibility of the ENGINEER
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 2 of 14
D Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in ink
on reproducible mylar sheets and electronic files in .pdf format, or as otherwise
approved by CITY, which shall become the property of the CITY. CITY may
use such drawings in any manner it desires; provided, however, that the
ENGINEER shall not be liable for the use of such drawings for any project other
than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on -site representatives or otherwise, do not make the ENGINEER
or its personnel in any way responsible for those duties that belong to the CITY
and/or the CITY's construction contractors or other entities, and do not relieve
the construction contractors or any other entity of their obligations, duties, and
responsibilities, including, but not limited to, all construction methods, means,
techniques, sequences, and procedures necessary for coordinating and
completing all portions of the construction work in accordance with the Contract
Documents and any health or safety precautions required by such construction
work. The ENGINEER and its personnel have no authority to exercise any
control over any construction contractor or other entity or their employees in
connection with their work or any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the progress
or quality of the completed work on the PROJECT or to determine, in general, if
the work on the PROJECT is being performed in a manner indicating that the
PROJECT, when completed, will be in accordance with the Contract
Documents, nor shall anything in the Contract Documents or the agreement
between CITY and ENGINEER be construed as requiring ENGINEER to make
exhaustive or continuous on -site inspections to discover latent defects in the
work or otherwise check the quality or quantity of the work on the PROJECT. If
the ENGINEER makes on -site observation(s) of a deviation from the Contract
Documents, the ENGINEER shall inform the CITY.
(3)
When professional certification of performance or characteristics of materials,
systems or equipment is reasonably required to perform the services set forth
in the Scope of Services, the ENGINEER shall be entitled to rely upon such
certification to establish materials, systems or equipment and performance
criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance with
Attachment A.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 3 of 14
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation or
maintenance costs' competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate PROJECT
cost or schedule. Therefore, the ENGINEER makes no warranty that the
CITY's actual PROJECT costs, financial aspects, economic feasibility, or
schedules will not vary from the ENGINEER's opinions, analyses,
projections, or estimates.
G Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling and
observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects that the
ENGINEER has made an examination to ascertain how or for what purpose the
construction contractor has used the moneys paid; that title to any of the work,
materials, or equipment has passed to the CITY free and clear of liens, claims,
security interests, or encumbrances; or that there are not other matters at issue
between the CITY and the construction contractor that affect the amount that
should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed The ENGINEER is not responsible for any
errors or omissions in the information from others that is incorporated into the
record drawings.
I. Minority and Woman Business Enterprise (M/WBE) Participation
In accord with City of Fort Worth Ordinance No. 15530, as amended, the City
has goals for the participation of minority business enterprises and woman
business enterprises in City contracts Engineer acknowledges the M/WBE
goal established for this contract and its accepted written commitment to
M/WBE participation. Any misrepresentation of facts (other than a negligent
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 4 of 14
misrepresentation) and/or the commission of fraud by the Engineer may result
in the termination of this Agreement and debarment from participating in City
contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years after
final payment under this contract, have access to and the right to examine and
photocopy any directly pertinent books, documents, papers and records of the
ENGINEER involving transactions relating to this contract. ENGINEER agrees
that the CITY shall have access during normal working hours to all necessary
ENGINEER facilities and shall be provided adequate and appropriate work
space in order to conduct audits in compliance with the provisions of this
section. The CITY shall give ENGINEER reasonable advance notice of
intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the CITY
shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such subconsultant,
involving transactions to the subcontract, and further that the CITY shall have
access during normal working hours to all subconsultant facilities, and shall be
provided adequate and appropriate work space, in order to conduct audits in
compliance with the provisions of this article together with subsection (3)
hereof CITY shall give subconsultant reasonable advance notice of intended
audits.
(3)
ENGINEER and subconsultant agree to photocopy such documents as may be
requested by the CITY. The CITY agrees to reimburse ENGINEER for the cost
of copies at the rate published in the Texas Administrative Code in effect as of
the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain commercial
general liability (CGL) and, if necessary, commercial umbrella insurance
with a limit of not less than $1,000,000.00 per each occurrence with a
$2,000,000.00 aggregate. If such Commercial General Liability insurance
contains a general aggregate limit, it shall apply separately to this
PROJECT or location.
i. The CITY shall be included as an insured under the CGL, using ISO
additional insured endorsement or a substitute providing equivalent
coverage, and under the commercial umbrella if any. This
insurance shall apply as primary insurance with respect to any other
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 5 of 14
insurance or self-insurance programs afforded to the CITY. The
Commercial General Liability insurance policy shall have no
exclusions by endorsements that would alter or nullify:
premises/operations, products/completed operations, contractual,
personal injury, or advertizing injury, which are normally contained
within the policy, unless the CITY approves such exclusions in
writing.
ii ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b Business Auto — the ENGINEER shall maintain business auto liability and, if
necessary, commercial umbrella liability insurance with a limit of not less
than $1,000,000 each accident Such insurance shall cover liability arising
out of "any auto', including owned, hired, and non -owned autos, when said
vehicle is used in the course of the PROJECT. If the engineer owns no
vehicles, coverage for hired or non -owned is acceptable.
ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation —ENGINEER shall maintain workers compensation
and employers liability insurance and, if necessary commercial umbrella
liability insurance with a limit of not less than $100,000.00 each accident for
bodily injury by accident or $100,000.00 each employee for bodily injury by
disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — the ENGINEER shall maintain professional liability a
claims -made policy, with a minimum of $1,000,000.00 per claim and
aggregate The policy shall contain a retroactive date prior to the date of the
contract or the first date of services to be performed, whichever is earlier.
Coverage shall be maintained for a period of 5 years following the
completion of the contract. An annual certificate of insurance specifically
referencing this project shall be submitted to the CITY for each year
following completion of the contract.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 6 of 14
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be delivered to the CITY prior to ENGINEER
proceeding with the PROJECT.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, as its interests may appear. The term CITY shall include
its employees, officers, officials, agents, and volunteers as respects the
contracted services.
c. Certificate(s) of insurance shall document that insurance coverage specified
in this agreement are provided under applicable policies documented
thereon.
d. Any failure on part of the CITY to request required insurance documentation
shall not constitute a waiver of the insurance requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent to
the respective Department Director (by name), City of Fort Worth, 1000
Throckmorton, Fort Worth, Texas 76102
Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength and
solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000 00 that would
change or alter the requirements herein is subject to approval by the CITY
in writing, if coverage is not provided on a first -dollar basis. The CITY, at it
sole discretion, may consent to alternative coverage maintained through
insurance pools or risk retention groups. Dedicated financial resources or
letters of credit may also be acceptable to the CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation in
favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring expense,
to review the ENGINEER's insurance policies including endorsements
thereto and, at the CITY's discretion; the ENGINEER may be required to
provide proof of insurance premium payments.
Lines of coverage, other than Professional Liability underwritten on a
claims -made basis, shall contain a retroactive date coincident with or prior
to the date of the contractual agreement. The certificate of insurance shall
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 7 of 14
state both the retroactive date and that the coverage is claims -made.
k. Coverages, whether written on an occurrence or claims -made basis, shall
be maintained without interruption nor restrictive modification or changes
from date of commencement of the PROJECT until final payment and
termination of any coverage required to be maintained after final payments.
I. The CITY shall not be responsible for the direct payment of any insurance
premiums required by this agreement.
m. Sub consultants and subcontractors to/of the ENGINEER shall be required
by the ENGINEER to maintain the same or reasonably equivalent insurance
coverage as required for the ENGINEER When sub
consultants/subcontractors maintain insurance coverage, ENGINEER shall
provide CITY with documentation thereof on a certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent consultant
and not as a subcontractor, agent, or employee of the CITY.
Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure in
writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing of
any conflicts of interest that develop subsequent to the signing of this contract
and prior to final payment under the contract
Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions of
the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with published
design criteria and/or current engineering practice standards which the
ENGINEER should have been aware of at the time this Agreement was
executed, the ENGINEER shall revise plans and specifications as required, at
its own cost and expense. However, if design changes are required due to the
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 8 of 14
changes in the permitting authorities' published design criteria and/or practice
standards criteria which are published after the date of this Agreement which
the ENGINEER could not have been reasonably aware of, the ENGINEER
shall notify the CITY of such changes and an adjustment in compensation will
be made through an amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City -Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of the
information provided by the CITY.
B Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY s facilities as may be required in connection with
the ENGINEER's services. The CITY will be responsible for all acts of the
CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses required
by local, state, or federal authorities; and land, easements, rights -of -way, and
access necessary for the ENGINEER's services or PROJECT construction.
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches drawings
specifications, proposals, and other documents; obtain advice of an attorney,
insurance counselor, accountant, auditor, bond and financial advisors, and
other consultants as the CITY deems appropriate; and render in writing
decisions required by the CITY in a timely manner in accordance with the
project schedule prepared in accordance with Attachment D.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 9 of 14
E Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior role
in the generation, treatment, storage, or disposition of such materials. In
consideration of the associated risks that may give rise to claims by third
parties or employees of City, City hereby releases ENGINEER from any
damage or liability related to the presence of such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos is a
result of ENGINEER's negligence or if ENGINEER brings such hazardous
substance, contaminant or asbestos onto the project.
G Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of Article
IV E. regarding the ENGINEER's Personnel at Construction Site and
provisions providing contractor indemnification of the CITY and the ENGINEER
for contractor's negligence.
H. Contractor Claims and Third -Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain no
direct action against the ENGINEER, its officers, employees,
and subcontractors, for any claim arising out of, in connection
with, or resulting from the engineering services performed.
Only the CITY will be the beneficiary of any undertaking by the
ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third -party beneficiaries.
(3)
The CITY will include in each agreement it enters into with any other entity or
person regarding the PROJECT a provision that such entity or person shall
have no third -party beneficiary rights under this Agreement.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 10 of 14
(4) Nothing contained in this section V.H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY will ensure that Builders Risk/Installation insurance is maintained at
the replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3)
The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required or
requested assistance to support, prepare, document, bring, defend, or assist in
litigation undertaken or defended by the CITY. In the event CITY requests such
services of the ENGINEER, this AGREEMENT shall be amended or a separate
agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of Services
in this AGREEMENT. If such changes affect the ENGINEER's cost of or time
required for performance of the services, an equitable adjustment will be made
through an amendment to this AGREEMENT with appropriate CITY approval.
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments of
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 11 of 14
service for this PROJECT, whether the PROJECT is completed or not. Reuse,
change, or alteration by the CITY or by others acting through or on behalf of the
CITY of any such instruments of service without the written permission of the
ENGINEER will be at the CITY's sole risk. The CITY shall own the final
designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond the
control of the ENGINEER that prevent ENGINEER s performance of its
obligations hereunder.
D Termination
(1) This AGREEMENT may be terminated only by the City for convenience on
30 days' written notice. This AGREEMENT may be terminated by either the
CITY or the ENGINEER for cause if either party fails substantially to perform
through no fault of the other and does not commence correction of such
nonperformance with in 5 days of written notice and diligently complete the
correction thereafter.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans, specifications
or other forms of ENGINEER'S work product;
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
The time requirements for the ENGINEER'S personnel to document the
work underway at the time of the CITY'S termination for convenience so
that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will submit
to the CITY an itemized statement of all termination expenses The CITY'S
approval will be obtained in wnting prior to proceeding with termination
services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER for
the convenience of the CITY. In the event of such suspension, delay or
interruption, an equitable adjustment in the PROJECT s schedule, commitment
and cost of the ENGINEERs personnel and subcontractors, and ENGINEER's
compensation will be made.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 12 of 14
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify, hold harmless and defend the CITY against
liability for any damage caused by or resulting from an act of negligence,
intentional tort, intellectual property infringement, or failure to pay a
subcontractor or supplier committed by the ENGINEER or ENGINEER's agent,
consultant under contract, or another entity over which the ENGINEER
exercises control.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the prior
written consent of the other party.
H. Interpretation
Limitations on liability and indemnities in this AGREEMENT are business
understandings between the parties and shall apply to all the different theories
of recovery, including breach of contract or warranty, tort including negligence,
stnct or statutory liability, or any other cause of action, except for willful
misconduct or gross negligence for limitations of liability and sole negligence
for indemnification. Parties mean the CITY and the ENGINEER, and their
officers, employees, agents, and subcontractors.
I. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT, its
interpretation and performance, and any other claims related to it. The venue
for any litigation related to this AGREEMENT shall be Tarrant County, Texas.
J. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any reason
to be invalid, illegal, or unenforceable in any respect, such invalidity, illegality,
or unenforceability will not affect any other provision, and this AGREEMENT
shall be construed as if such invalid, illegal, or unenforceable provision had
never been contained herein. Articles V.F. VI B , VI D , VI.F., VIA., and VI.I.
shall survive termination of this AGREEMENT for any cause.
K. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in any
way affect this AGREEMENT and the work hereunder, and shall observe and
comply with all orders, laws ordinances and regulations which may exist or may
be enacted later by governing bodies having jurisdiction or authority for such
enactment. No plea of misunderstanding or ignorance thereof shall be
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 13 of 14
M&C Date:
ATTEST:
Mary J. Kayser -
City Secretary
considered. ENGINFFR agrees to defend, indemnify and hold harmless CITY
and all of its officers, agents and employees from and against all claims or
liability arising out of the violation of any such order, law, ordinance, or
regulation, whether it be by itself or its employees.
Article VII
Attachments, ScheduiUes, and Sugrna ttMres
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, supersedes all prior written or oral understandings, and may only be changed
by a written amendment executed by both parties. The following attachments and schedules
are hereby made a part of this AGREEMENT:
Attachment A - Scope of Services
Attachment B o Compensation
Attachment C e Amendments to Standard Agreement for hngineering Services
Attachment D - Project Schedule
Attachment E - Location Map
Executed and effective this the,c,
.4Q
0 0
ri
Ole o
id nee
e)$
wis-SS.Vu PYJth
,c
0 0 3 0 0 0 eit
t4
'VTY OF FORT WORTH
r) ' L j
y.
aktatta ‘,/
h 0 Dow) 4.3)
44 It IL g)% -Cr
2012.
Fernando Costa
Assistant City Manager
APPROVED AS TO FORM AND LEGALITY APPROVAL RECOMMENDED
B
Douglas Black
Assistant City Attorney
M&C No.: T5t3(
6 -5 laz_
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 11.29.2011
Page 14 of 14
By: .----
Douglas .' . Wiersig, P.E.
Directo Department of
Transportation/Public Wo s
Kimley-Horn and Associates, Inc.
By:
Jeff James
Senior Vice President
OFFICIAL RECORiJ
CITY SECRETARY
FT. WORTH, TX
ATTACHMENT "A"
Scooe for Enaineerina Design Related Services for Street Improvements for the Henderson
Street Detour
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
OBJECTIVE
The objectives of this project are to implement improvements at intersections along the
proposed Henderson Street detour. The proposed improvements will assist in improving
operations at the intersections as a result of the added traffic from the Henderson Street
closure. The improvements include pavement markings, signing, traffic signal modifications,
and signal timing adjustments. The project intersections and the associated improvements
are detailed below:
• Henderson St. at White Settlement Rd.
o Convert eastbound approach to have dual rights and prohibit the through and
left movements.
o Convert northbound approach to have dual left turns, one through lane, and
o ne right -turn lane.
o Remove existing raised median on western leg of intersection to facilitate
n orthbound dual left turns.
o Traffic signal modifications to accommodate proposed improvements.
• Henderson St. at Northside Dr. / University Dr.
o Convert southbound approach to have dual left and dual right turns.
o Modify southbound right -turn channelized island to accommodate the second
right -turn lane.
o Modify signal heads and signing for the southbound approach to accommodate
the proposed dual left turns
o Adjust intersection signal phasing to accommodate proposed improvements.
Henderson St. at Lancaster Ave.
o Restripe eastbound approach to have dual lefts, and one shared through -right
lane.
o Traffic signal modifications to support improvements.
• N. Main St. at Northside Dr.
o Convert existing eastbound shared through -right lane to a dedicated right -turn
only lane.
o Traffic signal modifications to support improvements.
•
• University Dr. at White Settlement Rd.
o Remove existing traffic signal and construct new traffic signal.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 06.19.2010
Page 1 of 14
o Convert southbound approach to have dual left turns, one through lane, and
one shared through -right lane.
o Convert existing northbound shared through -right lane to a dedicated right -turn
lane.
o Convert existing westbound shared through -right lane to a free, dedicated right -
turn lane.
o Increase radius of northeast corner to accommodate more efficient right -turn
movement from the dedicated westbound right -turn lane
• Lancaster Ave. at University Dr.
o Restripe northbound approach to have a left -turn only lane, two through lanes,
and one right -turn only lane.
o Traffic signal modifications to support improvements.
White Settlement Rd.
o Mill, overlay, and restripe the outside westbound and eastbound through lanes
from Henderson St. to University Dr.
• Traffic Signal Timing Adiustments
o Evaluate existing signal timing phasing and split times and recommend
changes to accommodate the proposed detour traffic for the six (6) project
intersections.
•
• N. Commercial St.
o Prepare vacate documents for N. Commercial St. between Henderson St.
and White Settlement Rd
• Lancaster Ave. at Summit
O 7th Street Bridge detour improvements
Task 1.
Task 2.
Task 3.
Task 4.
Task 5.
Task 6.
Task 7.
Task 8.
WORK TO BE PERFORMED
Design Management
Preliminary Design
Final Design
Traffic Signal Timing Adjustments
Bid Phase Services
Construction Phase Services
Survey and Subsurface Utility Engineering Services
TxDOT Driveway Permit
TASK 1. DESIGN MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources ENGINEER will manage the project team,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary to make progress
on the work.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 2 of 14
1.1. Managing the Team
• Lead, manage and direct design team activities
• Ensure quality control is practiced in performance of the work
• Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
• Attend a pre -design project kickoff/chartering meeting with CITY staff to confirm and
clarify scope, understand CITY objectives, and ensure economical and functional
designs that meet CITY requirements
•
Conduct and document monthly project update meetings with CITY Project Manager
• Conduct review meetings with the CITY at the end of the 90% and 99% design
phase
• Conduct and document weekly design team meetings
• Prepare invoices, in accordance with Attachment B to this Standard Agreement and
submit monthly in the format requested by the CITY.
Prepare and submit monthly progress reports in the format provided by the
respective CITY Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule
updates with a schedule narrative monthly, as required in Attachment D to this
Standard Agreement and according to the City of Fort Worth's Schedule Guidance
Document.
•
• Complete Monthly M/WBE Report Form and Final Summary Payment Report Form
at the end of the project.
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design.
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs and make changes necessary to meet
their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub -consultants shall carry readily visible
information identifying the name of the company and the company representative.
DELIVERABLES
A. Meeting summaries with action items
B. Monthly invoices
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 3 of 14
C. Monthly progress reports
D. Baseline design schedule
E Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
F. Monthly M/WBE Report Form and Final Summary Payment Report Form
TASK 2. PRELIMINARY DESIGN (90 PERCENT).
P reliminary plans and specifications shall be submitted to CITY per the approved Project
S chedule
ENGINEER will develop the preliminary design of the infrastructure as follows.
2.1 Traffic Signal Short Report for University Dr. at White Settlement Rd.
2.1.1 Data Collection
•
•
The ENGINEER may obtain hard copies of record drawings from the CITY. The
record drawings should include but not be limited to the proposed roadway plans,
right-of-way information, and utility plans. If available, the CITY will furnish the
ENGINEER electronic copies of the CAD files of the existing record drawings or
proposed construction plans.
• The ENGINEER will utilize the topographic survey for a base file. The
ENGINEER will field verify the accuracy of the survey files based on franchise
utility locates performed by DIG-TESS.
• The ENGINEER will meet with the CITY in the field to discuss the electric
service, communications, vehicle detection and Opticom requirements at the
intersection. All existing and proposed utilities, pavement widths, lane
configurations, and traffic control devices will be determined based on field
observations, the record drawings provided by the CITY, and franchise utility
locates.
2.1.2 Capacity Analysis
• The ENGINEER will perform a capacity analysis indicating level of service for
each movement at the intersection. The capacity analysis will be completed
using the SynchroTM analysis software.
The ENGINEER will recommend the appropriate traffic signal phasing for the
intersection with consideration for the capabilities of current CITY controller
hardware and software operation functions
2.1.3 Short Report document shall include the following:
• Existing and/or projected traffic volumes;
• Discussion of existing and proposed conditions;
• Capacity analysis results;
• Photo -log of intersection approaches;
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 4 of 14
• Recommendations for signal design, phasing, operations, illumination, and
pedestrian accommodations, including a preliminary layout with cabinet, pole,
and service placements; and
• Address any unusual conditions and provide recommendations to resolve these
conditions
DELIVERABLES
A. Documentation of key design decisions
B. Draft Short Report
2.2. Development of Preliminary Design Drawings and Specifications shall include the
following:
• Traffic Control Plan for the proposed improvements including all construction
signage and pavement markings which will be in accordance with the latest edition
of the Texas Manual on Uniform Traffic Control Devices.
• SUE plan drawings for the intersection of University Dr. at White Settlement Rd.
only.
• Intersection layout sheets including ROW lines horizontal alignments, utilities,
existing traffic signal equipment curbs, sidewalks, driveways, lane dimensions
and arrows, and existing and proposed contours (0.25' intervals)
• Preliminary mill and overlay layout sheets for White Settlement Rd., from
Henderson St. to University Dr.
• Preliminary roadway and traffic signal details to include curbs, curb expansion
joints, driveways, sidewalks, traffic signal details, and pavement details.
• Preliminary signing, pavement marking, and signal layouts.
Prepare vacate documents for N. Commercial St. between Henderson St. and
White Settlement Rd
Removal plans will be developed to address any removals needed to
accommodate the proposed improvements.
• Separate removal plans will also be developed to address removal of any of the
proposed improvements at the conclusion of the Henderson St. detour.
•
•
2.4. Constructability Review
• Prior to the 90 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
2.4. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and government agencies to determine the
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 5 of 14
approximate location of above and underground utilities, and other facilities
(current and future) that have an impact or influence on the project ENGINEER
will design CITY facilities to avoid or minimize conflicts with existing utilities and
where known and possible consider potential future utilities in designs.
The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
ASSUMPTIONS
• The CITY will provide the ENGINEER with recent traffic counts at the project
intersections.
• The ENGINEER will determine the pedestrian and ADA requirements for the
intersection of University Dr. at White Settlement Rd
• Prior to preparing base plan sheets or conducting field site visits, the ENGINEER
will schedule franchise utility locates (DIG-TESS) at the project intersections
• The ENGINEER shall submit one (1) PDF and two (2) 8.5" x 11" paper copies of
the draft short report to the CITY.
• The ENGINEER will incorporate review comments and submit a final "short
report' to the CITY (one (1) PDF electronic copy and two (2) 8.5 x 11" paper
copies)
• Five (5) sets of 11" x 17" size plans will be delivered for the 90% design.
• Five (5) sets of specifications will be delivered for the 60% design.
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in Buzzsaw.
• The CITY's front end and technical specifications will be used. The ENGINEER
shall supplement the technical specifications if needed.
• Two (2) sets of full size drawings will be delivered for Utility Clearance.
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design plans.
DELIVERABLES
A. Traffic Signal Short Report
B Preliminary Design drawings and specifications
C. Utility Clearance drawings
D. Estimates of probable construction cost
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 6 of 14
TASK 3. FINAL DESIGN CONSTRUCTION DOCUMENTS (100 PERCENT).
• Upon approval of the Preliminary plans, ENGINEER will prepare construction plans
as follows.
• Final draft construction plans (99%) and specifications shall be submitted to CITY
per the approved Project Schedule
• Following a 99% construction plan review meeting with the CITY, the ENGINEER
shall submit Final Plans (100%) to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered
in State of Texas.
•
The ENGINEER shall submit a final design estimate of probable construction cost
with both the 99% and 100% design packages. This estimate shall use ONLY
standard CITY bid items
ASSUMPTIONS
• Five (5) sets of 11" x 17" size drawings and five (5) specifications will be delivered for
the 99% Design package.
• A DWF file for the 99% Design will be created from design CAD drawings and will be
uploaded to the project folder in Buzzsaw.
• Ten (10) sets of 11" x 17" size drawings and ten (10) specifications will be delivered
for the 100% Design package.
• A DWF file for the 100 % Design will be created from design CAD drawings and will
be uploaded to the project folder in Buzzsaw
DELIVERABLES
A. 99% construction plans and specifications.
B. 100% construction plans and specifications.
C. Detailed estimates of probable construction costs including summaries of bid items
and quantities using the CITY's standard bid items and format
D. Original cover mylar for the signatures of authorized CITY officials.
TASK 4. TRAFFIC SIGNAL TIMING ADJUSTMENTS.
• ENGINEER will assist the CITY in determining traffic signal phasing and split
changes needed to accommodate the additional traffic at each of the six (6) project
intersections as a result of the detour. The ENGINEER will utilize any available
SynchroTM files to perform this task.
• ENGINEER will take the projected traffic volumes from the detour and add these to
the existing counts in the SynchroTM files. Lane geometries will also be updated in
the SynchroTM files to reflect the proposed improvements. New timing parameters
and phasing will be developed.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 7 of 14
• ENGINEER will assist the CITY with the inputting of the new timing parameters into
the lap top for field implementation.
• ENGINEER will assist the CITY with fine tuning of the timing during the first week of
the Henderson St. detour.
TASK 5. BID PHASE SERVICES
ENGINEER will support the bid phase of the project as follows.
5.1. Bid Support
• The ENGINEER shall upload all plans and contract documents onto Buzzsaw for
access to potential bidders.
•
Contract documents shall be uploaded in a .xls file.
• Unit Price Proposal documents are to be created utilizing CFW Bidtools only
and combined in a specified spreadsheet workbook, Bid Proposal Worksheet
Template, and will be populated and configured so that all pages are
complete and the Summary Worksheet(s) in the workbook detail and
automatically summarize the totals from the inserted Unit Price Proposal
document worksheets.
• Plan Sets are to be uploaded to Buzzsaw in two formats, .pdf and .dwf files.
The .pdf will consist of one file of the entire plan set The .dwf will consist of
individual files one for each plan sheet, and will be numbered and named in
a manner similar to that of the plan set index.
• The ENGINEER shall sell contract documents and maintain a plan holders list on
Buzzsaw from documents sold and from Contractor's uploaded Plan Holder
Registrations in Buzzsaw.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
project's Buzzsaw folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidders questions and requests, in the form of
addenda The ENGINEER shall upload all approved addenda onto Buzzsaw and
mail addenda to all plan holders
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid opening in support of the CITY.
• Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation is to be uploaded into the project s Bid Responses folder on Buzzsaw.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 8 of 14
• Incorporate all addenda into the contract documents and issue conformed sets.
5.2 Mylar Drawings
• The ENGINEER shall submit a set of sealed conformed mylar drawings for
record storage
• Record Drawings shall also be submitted as an Adobe Acrobat PDF format
(version 6.0 or higher) file and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set Each PDF and DWF file shall contain all associated sheets
of the particular plan set Singular PDF and DWF files for each sheet of a
plan set will not be accepted. PDF and DWF files shall conform to naming
conventions as follows:
I. TPW file name example — "W-1956_org47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "_org' designating the file is
of an original plan set, ` 47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667_org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36 ' shall be the total number
of sheets in this file.
Example: X-12755_orgl8.pdf
Both PDF and DWF files shall be uploaded to the project's Record Drawing folder
in Buzzsaw.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number (817) 392 8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
ASSUMPTIONS
• The project will be bid by the CITY.
• The project will be bid only once and awarded to one contractor.
• Fifteen (15) sets of construction documents will be sold to and made available on
Buzzsaw for plan holders and/or given to plan viewing rooms.
• Fifteen (15) sets of construction documents will be printed and made available for
purchase by plan holders and/or given to plan viewing rooms.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 9 of 14
• Five (5) sets of 11" x 17" size plans and specifications (conformed, if applicable)
will be delivered to the CITY.
• PDF and DWF files will be uploaded to Buzzsaw.
• 1 copy full size (22" x 34") mylar plans (conformed, if applicable) will be delivered
to the CITY.
DELIVERABLES
A. Addenda
B. Bid tabulations
C. Recommendation of award
D. Construction documents (conformed, if applicable)
E Conformed mylar plans
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1 Construction Support
• The ENGINEER shall attend the preconstruction conference.
• The ENGINEER shall visit the project site at requested intervals as construction
proceeds to observe and report on progress.
• The ENGINEER shall review shop drawings, samples and other submittals
submitted by the contractor for general conformance with the design concepts and
general compliance with the requirements of the contract for construction. Such
review shall not relieve the Contractor from its responsibility for performance in
accordance with the contract for construction, nor is such review a guarantee that
the work covered by the shop drawings samples and submittals is free of errors,
inconsistencies or omissions. The ENGINEER shall log and track all shop
drawings, samples and other submittals in Buzzsaw.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents review change orders, and make
recommendations as to the acceptability of the work.
• The ENGINEER shall attend the `Final" project walk through and assist with
preparation of final punch list.
6.2 ASSUMPTIONS
• Three (3) site visits are assumed.
• Two (2) submittal reviews are assumed.
• Three (3) RFI's are assumed.
• One (1) Change Order is assumed.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 10 of 14
DELIVERABLES
A. Response to Contractor's Request for Information
B. Review of Change Orders
C. Review of shop drawings
D. Final Punch List items
TASK 7. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES
ENGINEER will provide survey support as follows.
7.1. Design Survey
• ENGINEER will perform field surveys at the six (6) project intersections to collect
horizontal and vertical elevations and other information needed by ENGINEER in
design and preparation of plans for the project. Information gathered during the
survey shall include topographic data, elevations of all sanitary and adjacent
storm sewers, rim/invert elevations, location of buried utilities, structures, trees
(measure caliper, identify overall canopy, and have qualified arborist identify
species of trees), and other features relevant to the final plan sheets Existing
drainage at intersections will be verified by field surveys. Spot elevations will be
shown on intersection layouts with cross slope to fit intersecting grade lines
• The minimum survey information to be provided on the plans shall include the
following:
A Project Control Sheet showing ALL Control Points, used or set while
gathering data Generally on a scale of not less than 1:400
The following information about each Control Point,
a. Identified (Existing. CITY Monument #8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a
referred bearing base. Z coordinate on CITY Datum only.
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South
curb line of North Side Drive at the East end of radius at the Southeast
corner of North Side Drive and North Main Street).
Coordinates on all P.C.'s, P.T.'s, P.I. s, Manholes, Valves, etc., in the
same coordinate system, as the Control.
No less than two horizontal bench marks, per line or location.
Bearings given on all proposed centerlines, or baselines.
Station equations relating utilities to paving, when appropriate.
7.2. Subsurface Utility Engineering
Provide Subsurface Utility Engineering (SUE) to Quality Level B at the intersection of
White Settlement Rd. and University Dr. only as described below. The SUE shall be
performed in accordance with Cl/ASCE 38-02.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 11 of 14
Quality Level D
• Conduct appropriate investigations (e.g., owner records, County/CITY records,
personal interviews, visual inspections, etc.), to help identify utility owners that
may have facilities within the project limits or that may be affected by the project.
• Collect applicable records (e.g., utility owner base maps, "as built' or record
drawings, permit records, field notes, geographic information system data, oral
histories, etc) on the existence and approximate location of existing involved
utilities.
• Review records for: evidence or indication of additional available records;
duplicate or conflicting information; need for clarification
• Develop SUE plan sheets and transfer information on all involved utilities to
appropriate design plan sheets electronic files and/or other documents as
required. Exercise professional judgment to resolve conflicting information. For
information depicted, indicate: utility type and ownership; date of depiction;
quality level(s); end points of any utility data; line status (e.g , active, abandoned,
out of service); line size and condition; number of jointly buried cables; and
encasement.
Quality Level C (includes tasks as described for Quality Level D)
• Identify surface features, from project topographic data and from field
observations, that are surface appurtenances of subsurface utilities.
• Include survey and correlation of aerial or ground -mounted utility facilities in
Quality Level C tasks.
• Survey surface features of subsurface utility facilities or systems, if such features
have not already been surveyed by a professional surveyor If previously
surveyed, check survey data for accuracy and completeness.
• The survey shall also include (in addition to subsurface utility features visible at
the ground surface): determination of invert elevations of any manholes and
vaults; sketches showing interior dimensions and line connections of such
manholes and vaults; any surface markings denoting subsurface utilities,
furnished by utility owners for design purposes
• Exercise professional judgment to correlate data from different sources, and to
resolve conflicting information.
• Update (or prepare) plan sheets, electronic files, and/or other documents to
reflect the integration of Quality Level D and Quality Level C information.
• Recommend follow-up investigations (e.g., additional surveys, consultation with
utility owners, etc.) as may be needed to further resolve discrepancies.
• Provide Quality Level C to identify overhead utilities on the project and provide
the overhead utility information on the SUE plan sheets
Level B (includes tasks as described for Quality Level C)
• Select and apply appropriate surface geophysical method(s) to search for and
detect subsurface utilities within the project limits and/or to trace a particular
utility line or system
• Based on an interpretation of data, mark the indications of utilities on the ground
surface for subsequent survey Utilize paint or other method acceptable for
marking of lines.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 12 of 14
• Unless otherwise directed, mark centerline of single -conduit lines, and outside
edges of multi -conduit systems
• Resolve differences between designated utilities and utility records and surveyed
appurtenances
• Recommend additional measures to resolve differences if they still exist.
Recommendations may include additional or different surface geophysical
methods, exploratory excavation, or upgrade to Quality Level A data.
• As an alternative to the physical marking of lines, the ENGINEER may, with
CITY's approval, utilize other means of data collection, storage, retrieval, and
reduction, that enables the correlation of surface geophysical data to the project's
survey control.
DELIVERABLES
A. Copies of field survey data and notes signed and sealed by a licensed surveyor.
B. Drawing of the project layout with dimensions and coordinate list.
C. SUE plan drawings sealed by a professional engineer registered in the State of
Texas.
TASK 8. TxDOT DRIVEWAY PERMITTING.
ENGINEER will provide permitting support for the CITY to obtain any and all agreements
and/or permits normally required for a project of this size and type, as follows.
8.1. Texas Department of Transportation (TxDOT) Permit
• Meet, negotiate and coordinate to obtain approval of the agency issuing the
agreement and/or permits
• Completing all forms/applications necessary.
• Submitting forms/applications for CITY and TxDOT review
• Submitting revised forms for agency review
• Responding to agency comments and requests
ASSUMPTIONS
• TxDOT will allow this project to be constructed through the driveway permit
process.
• Permit preparation will begin after approval of the Preliminary Design.
• One (1) meeting is assumed with TxDOT for the driveway permit.
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services
described in the tasks above. However, ENGINEER can provide these services, if
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 13 of 14
needed, upon the CITY's written request Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be
agreed upon in writing by both parties before the services are performed. These
additional services include the following:
• ROW/Easement services.
• Negotiation of easements or property acquisition.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre -qualification, bid protests, bid rejection
and re -bidding of the contract for construction.
• Construction management and inspection services
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Performance of miscellaneous and supplemental services related to the project
as requested by the CITY.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 08.27.2010
Page 14 of 14
ATTACHMENT B
COMPENSATION
Design Services for
Street Imarovements for the Henderson Street Detour
City Project No. 00144
Lump Sum Project
1. Compensation
A. The ENGINEER shall be compensated a total lump sum fee of $132,000.00 as
summarized in Exhibit B 1 — Engineer Invoice and Section IV — Summary of Total
Project Fees. The total lump sum fee shall be considered full compensation for
the services described in Attachment A, including all labor materials, supplies,
and equipment necessary to deliver the services.
B. The ENGINEER shall be paid monthly payments as described in Section II Method of Payment.
II. Method of Payment
A. Partial payment shall be made to the ENGINEER monthly upon City's approval of
an invoice prepared and submitted by the ENGINEER in the format and including
content as presented in Exhibit B-1, Progress Reports as required in item III. of
this Attachment B, and Schedule as required in Attachment D to this Agreement.
The estimated current physical percent complete as required on the invoice shall
be calculated from the progress schedule as required in Attachment D to this
Standard Agreement and according to the current version of the City of Fort
Worth's Schedule Guidance Document.
C. The cumulative sum of such monthly partial fee payments shall not exceed the
total current project budget including all approved Amendments.
Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER
I11. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department monthly progress reports and
schedules in the format required by the City.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19.2010
Page 1 of 3
B-1
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm Primary Responsibility
P rime Consultant
Kimley-Horn and Project management, design
Associates, Inc.
P roposed M/WBE Sub -Consultants
Gorrondona &
Fee Amount
$90,775.00
Topographic survey and Level $41,225.00
Associates, Inc. B SUE
N on-M/WBE Consultants
Project Number & Name
00144 - Street Improvements for the
Henderson Street Detour
TOTAL $132,000.00
Total Fee
$132, 000.00
M/WBE Fee
$41, 225.00
100%
M/WBE %
31.2%
City M/WBE Goal = 31% Consultant Committed Goal = 31 %
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19,2010
Page 2 of 3
B-2
EXHIBIT "B-1"
LEVEL OF EFFORT SPREADSHEET
(Supplement to Attachment B)
Insert the level of effort spreadsheet following this page.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19,2010
Page 3 of 3
x Description
Rate
4Q?ment
,e Team
. eam Meetings
in-wfiip ,ttQps and Reporting
're- es) p oordination Meeting
Month)x.-Proj(ect U{tdate Meetings
Design Submittal review Meetings
.4 Prepare Baseline Schedule
Prepare Monthly Progress Reports with
1.2.5 Schedule
1.2.6 Prepare Monthly MWBE Reports
1.2.7 Invoicing
2.0 PrefiminaryOes(p (80 Percen(f
2.1 Traffic Signal Short Report
2.2 Preliminafy Design Drawings
2.3 Constructability review
2.4 Utilij Clearance
2.5 Traffic Control Plan
2.6 Proiect Decision Lqq
2.7 Construction Estimate
3.0 rinafDesign
3.1 (Final Draft (99%) Construction Plans and
Specifications
3.2 (Final (100%)�rIgs anq py;ifi ng
3.3 IProjec Decision Logs §§ ° and 0o%)
4.0 Traffic Sipa' rlmfnq Adjustmen(s
4.1 Riming Adjustments
4.2 IFine runirag,
5.0
5.1
5.1.1
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
Bid Phase
Bid Support
Sell Contract Documents and Maintain
Plan Holders List
Issue Addenda
Attend Pre -bid Conference
Attend Bid Openinp
Tabulate Bids and'Recommend Award
Issue Conformed Ca-q(i9.) Q s pwwp1;s
6.0 epns;ructioQ Phan geryces
6.1 Construction Support
6.1.1 I Attend Preconstruction Conference
_ 6.1.2 1 Project Site Visits
6.1.3 1 Submittal Review
Request for Information/Change Order
_ 6.1.4 Review
6.1.5 I Final Walk Through and Punch List
7.0 ISurve
_ 7.1 IDesi n Survey
_ 7.2 'Level SUE
7.3 IN. Commercial Vacation Document
8.0 Permitting
8.1 TxDOT
e
Totals
Sr. Project
Manager
$19C
4
28
1
25
2
1
1
Level of Effort Spreadsheet
ASK/HOUR BREAKDOWN
Design Services for
Street Improvements for the Henderson Street Detour
Citv Proiect No, 00144
Project
Manager
$155
22
2
4
3
4
41
11
21
11
11
61
4
4�
2
1
101 20,
6
41
12,
2
10
0
15
51
Project
Engineer
$115
104
15
80
5
2
37J
25
101
21
Labor hours)
if
EIT
CADD
S90
0
245
220
25
50
201
5
20
10
6'
2
2
1
1
24
3
91
41
4
41
4
4
20
10
4
0
0
0
165
0
0 0
10
10'
Administrative Total Labor
Cost
$75
1
6 $4,620
$310
$1,380
$465
$620
$620
$155
$460
2 $305
0
0
0j
335
15;
$305
$51,235
$2,535
$42,925
$620
$310
$4,230
$230
$385
$16,255
$11,340
$4,685
$230
$6,355,
$3,455'
$2,900
$2,065
$3801
$380
$310
$310
$380
$305
J
$3,720
$465
$1,395'
$620
$620
$620
$465
$155,
$155
$155,
$1,620
$1,620'
$86,335
Expense
Subconsultant
MWBE Non-MWBE
$0 $0
$0
$0
Travel
Office
Expense/
Reproduction
Total Expense Task Sub Total
Cost
0 $
$50
$50
$100'.
soj $0 $701
$50
$50
$0
$701
$0
$0
$0
$100
$100
$0
$41,225
$0
$0
$0
$01
$41,225
$Oj
$0.
$o'
1
$0,
$
$701
$250'
4,620
$0
$310
$0
$1,380
$0
$465
$0
$620
50
$620
$0
$155
$0
$460
50
$305
$0
$50
$0
$305
$51,285
$2,535
$50'
$42,975
50
$620
$0
$310
$0
$4,230
50
$230
50
$100
$50
$385
$16,355
$11,390
$50
$0
$70,
$0'
$4,735
$230
$6,425
$3,455
$70
$100
$2,970
$2,165
$1001
$480
50
$380
$0
$310
$0
$310
$0
$380
$0
$305
$0
$3,720
$0
$465
$0
$1,395
$0,
$620
$0
$620
50
$41,225
528,875,
$9,000
$0'
50
$620
$41,690
$29,030
$9,155
$3,5.05
$1,620,
$1,620
$41,545
Project Summary
Total Hours
Total Labor
Total Expense
MWBE Subconsultant
Non-MWBE Subconsultant
10% Sub Markup
MWBE Participation
Total Project Cost
$127,880
714
$86/335
$41 545
$41,225
$0
$4/ 120
31.2%
$132,000
City of Fort Worth, Texas
Attachment B - Level of Effort Supplement
PMO Official Release Date: 5.19.2010
1of1
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
Street Improvements for the Henderson Street Detour
City Project No. 00144
No changes to the Standard Agreement.
City of Fort Worth, Texas
Attachment C
PMO Release Date 05 19 2010
Page I of I
Consulting Contract Schedule Specifications
City of Fort Worth Capital Improvement Program
Attachment D m Proiect Schedule
FORT
, WORTH
This PROTECT requires a Tier 2 schedule as defined herein and in the Citiy's Schedule Guidance
Document.
D1. CONSULTING SERVICES SCHEDULE DEVELOPMENT: The CONSULTANT shall
prepare schedules for consulting services that meet the requirements described in this
specification, showing by Critical Path Method (CPM) the planned sequence and timing of
the Work associated with the Agreement. All submittals shall be submitted in PDF format,
and schedule files shall also be submitted in native file format (i.e. file formats associated
with the scheduling software). The approved scheduling software systems for creating the
schedule files are:
Primavera (Version 6.1 or later or approved by CITY)
Primavera Contractor (Version 6.1 or later or approved by CITY)
Microsoft Project (Version 2003/2007 or later or approved by CITY)(PHASING OUT)
D2 BASELINE CONSULTING SERVICES SCHEDULE: Following notice -to -proceed, the
CONSULTANT shall develop, submit and review the draft detailed baseline consulting
services schedule with the CITY to demonstrate the CONSULTANT'S understanding of the
Agreement requirements and approach for performing the work. The CONSULTANT will
prepare the final detailed baseline consulting services schedule based on CITY comments, if
any, and submit to the CITY no later than the submittal of the first project invoice.
The following guidelines shall be adhered to in preparing the baseline schedule, and as
described in further detail in the CITY's Schedule Guidance Document.
a. The scope shall be subdivided by work breakdown structure (WBS) representing the
tasks, subtasks, and activities associated with delivering the work.
b. The schedule shall accurately describe the major work activities, key milestones, and
dependencies/relationships as appropriate to the work.
c. The schedule should include appropriate meetings, review periods, critical decision
points, including third party utility dependencies and reviewing agencies.
D3. PROGRESS CONSULTING SERVICES SCHEDULE: The CONSULTANT shall prepare
and submit monthly to the CITY for approval the updated schedule in accordance with D1
and D2 and the CITY's Schedule Guidance Document inclusive. As the Work progresses,
the CONSULTANT shall enter into the schedule and record actual progress as described in
the CITY's Schedule Guidance Document.
The updated schedule submittal shall also include a concise schedule narrative that
highlights the following, if appropriate and applicable:
•
•
•
Changes in the critical path,
Expected schedule changes,
Potential delays,
Opportunities to expedite the schedule,
Coordination issues the CITY should be aware of or can assist with,
City of Fort Worth, Texas
Attachment D
PMO Release Date: 02.15.2011
Page 1 of 2
• Other schedule - related issues that the CONSULTANT wishes to communicate to the
CITY.
D4. PERFORMANCE AND CONSULTING SERVICES SCHEDULE: If the work
accomplished falls behind that scheduled due to factors within the CONSULTANT's
control, the CONSULTANT shall take such action as necessary to improve the progress of
the Work. In addition, the CITY may require the CONSULTANT to submit a revised
schedule demonstrating the proposed plan to make up the delay in schedule progress and
to ensure completion of the Work within the allotted Agreement time.
D5. SCHEDULE TIERS SPECIAL INSTRUCTIONS•
The requirements for the schedule are determined based on the nature and needs of the
project. The schedule tier for this project is stated at the top of this document.
CONSULTANT shall submit each schedule relying on the CITY's current Schedule
Guidance Document.
D6. SCHEDULE SUBMITTAL AND PAYMENT:
As stated in III.A.(1). of the Agreement, CONSULTANT shall provide the information
required by Attachment D. CONSULTANT's monthly invoices will not be accepted and
processed for payment without monthly schedule updates that are submitted in the time
and manner required by Attachment D and the CITY's current Schedule Guidance
Document.
City of Fort Worth, Texas
Attachment D
PMO Release Date. 02.15 2011
Page 2 of 2
4
5
6
7
8
9
Worth City Project No. 00144
Improvements for Henderson St. Detour
me Duration Start Finish Predecessors .bruary 2012 I March 2012 April 2012 1 May 2012 June 2012 July 2012 I August 2012 I September 2012 October 2012 I November 2012 _ I December 2012 Ja uary 2013 I February 2013
2/5 2/1 2/192/28`, 3/413/1113/1$3/2j 4/1 4/8 4/1514/224/29 5/6 5/13r5/205/27J6/3 /1d6/17i6/2417/1 17/8I7/1517/2217/2918/5I8/1218/198/26I 9/219/9I9/16I9/2319/3d10/7).0/14.0/2i0/2 11/4j.1/1i1/1W2 12/2;12/42/1 .2/2j2/3(1/6I1/13;1/2d1/27: 2/3 2/102/17i2/2
e to Proceed
- Design Management
1.1- Managing the Team
1.2 - Communications and Reporting
Pre -Design Kick off Meeting
Monthly Project Meeting #1
Monthly Project Meeting #2
Monthly Project Meeting #3
Invoicing, Status Updates, MWBE
10 2 - Preliminary Design
11 2.1- Traffic Signal Short Report
12 2.2 - Preliminary Design
13 2.3 - Constructability Review
14 2.4 - Utility Clearance
15 2.5 - City Review
16 3 - Final Design and Construction Documents
17 3.1- Prepare 99% plans, specs, estimate
18
19
20
21
22
3.2 - 99% Review Meeting
3.3 - Prepare Final plans, specs, contract docs
4 - Traffic Signal Timing Adjustments
4.1- Timing Plan adjustments
4.2 - In -Field Fine Tuning
23 5 - Bid Phase and M&C Approval
24 6 - Construction
25 7 - Topographic Survey
26 8 - TxDOT Permit
Date: Wed 2/22/12
Task
Split
Milestone
1 day Mon 4/2/12 Mon 4/2/12
172 days Tue 4/3/12Ved 11/28/121
172 days Tue 4/3/12Ved 11/28/121
172 days Tue 4/3/12Ved 11/28/121
1 day Tue 4/3/12 Tue 4/3/121
1 day Tue 5/1/12 Tue 5/1/12
1 day Mon 6/4/12 Mon 6/4/12
1 day Mon 7/2/12 Mon 7/2/12
172 days Tue 4/3/12Ved 11/28/121
80 days Tue 4/3/12 Mon 7/23/121
35 days Tue 4/3/12 Mon 5/21/121
40 days Tue 5/8/12 Mon 7/2/12 25
1 day Tue 7/3/12 Tue 7/3/12 12
5 days Tue 7/3/12 Mon 7/9/1212
15 days Tue 7/3/12 Mon 7/23/1212
16 days Tue 7/24/12 Tue 8/14/1213
10 days Tue 7/24/12 Mon 8/6/1215
1 day Tue 8/7/12 Tue 8/7/12 17
5 days Wed 8/8/12 Tue 8/14/1218
177 days Tue 5/22/12Wed 1/23/13
10 days Tue 5/22/12 Mon 6/4/12 11
5 days Thu 1/17/13 Wed 1/23/13
80 days Wed 8/15/12 Tue 12/4/1219
50 days Wed 12/5/12 Tue 2/12/13 23
25 days Tue 4/3/12 Mon 5/7/12 1
30 days Tue 7/3/12 Mon 8/13/1212
1
i
41
II
1
Iiiimiiiiiiiii Summary II it External Milestone O Inactive Summary V ) Manual Summary Rollun
Project Summary C' '.) Inactive Task r 1 Manual Task F' „] Manual Summary
O External Tasks t — a Inactive Milestone Duration -only Start -only
1 11
Finish-nnly 1
J Deadline 3
Progress �—
kommi
Page 1
ata\PPP\PRE.NiP\Attochmanlj
lo. N. \FLWJAarkobnq\For
73
0
0
0
Rockwood
Park
nw pod
nor 'al
etery
r
r' iv
Texas
Science
rater
sops
Park
AVE
x
cc
0
;RESTLINE
Hebrew SHOTT
Cemetery
SITE MAP
STREET IMPROVEMENTS FOR THE
HENDERSON ST. DETOUR
F24�RTH
MAPSCO 62—Q, 62—T, 62—W, 62—Y, 76—A, 76—C, 76—D
DAGGETT
BROADWAY
el
MAIN ST. (B287) AT
NORTHSIDE DR.
Tr
r HENDERSON ST. (SH 199) AT
NORTHSIDE DR./UNIVERSITY DR.
RVIS I 1
PROPOSED HENDERSON
STREET BRIDGE
UNIVERSITY DR. AT
WHITE SETTLEMENT RD.
HENDERSON ST. (SH 199) AT
WHITE SETTLEMENT RD.
W. LANCASTER AVE. AT
UNIVERSITY DR.
HENDERSON ST. (SH 199)
AT W. LANCASTER AVE.
W. LANCASTER AVE. AT
BROADWSUMMIT AVE.
Copyright 2011 City of Fort Worth. Unauthorized reproduction is a violation of applicable laws. This product is for
informational purposes and may not have been prepared for or be suitable for legal, engineering, or surveying
purposes. It does not represent an on —the —ground survey and represents only the approximate relative location of
property boundaries. The City of Fort Worth assumes no responsibility for the accuracy of said data.
City of Fort Worth, Texas
Mayor and ouncil ommunication
COUNCIL ACTION: Approved on 6/5/2012
DATE Tuesday, June 05, 2012
LOG NAME: 20TRV LOCAL STREET IMPROVEMENTS
SUBJECT:
REFERENCE NO.: **C-25631
Authorize Execution of an Engineering Services Agreement with Kimley-Horn and Associates, Inc., in the
Amount of $132,000.00 for the Design of Local Street and Intersection Improvements to Support the
Henderson Street Bridge Detour (COUNCIL DISTRICTS 2, 7 and 9)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of an Engineering Services Agreement
with Kimley-Horn and Associates, Inc., in the amount not to exceed $132,000.00 for the design of local
street and intersection improvements to support the Henderson Street Bridge Detour by utilizing
$132 000.00 from the 2008 Bond Program to provide for street improvements of several intersections.
DISCUSSION
This Agreement is for design services associated with providing local street improvements to intersections
along the proposed detour route of the Henderson Street Bridge Project. The 2008 Bond Program
included funds for the project design.
Kimley-Horn and Associates, inc., has submitted a proposal to provide the final design plans and
construction specifications and contract documents for a fee not to exceed $132.000 00. Staff considers
this fee to be fair and reasonable for the scope of services to be performed.
Kimley-Horn and Associates, Inc., is in compliance with the City's M/WBE Ordinance by committing to 31
percent M/WBE participation. The City's goal on this project is 31 percent.
This project is located in COUNCIL DISTRICTS 2, 7 and 9, Mapsco 62Q, 62T, 62W, 62Y, 76A, 76C, and
76D.
FISCAL INFORMATION / CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Street Improvements 2008 Fund.
FUND CENTERS:
TO Fund/Account/Centers FROM Fund/Account/Centers
C204 531200 209260014430 $132.000.00
CERTIFICATIONS:
Submitted for City Manager's Office by:
Originating Department Head:
Fernando Costa (6122)
Douglas W. Wiersig (7801)
Logname: 20TRV LOCAL STREET IMPROVEMENTS Page 1 of 2
Additional Information Contact: Patrick Buckley (2443)
ATTACHMENTS
1. 0014 FAR- 00014.pdf (CFW Internal)
2. Attachment E Vicinity Map.pdf (Public)
3. C204 Available Funds.pdf (CFW Internal)
4. FAR 14 KH Design Local Street. pdf (CFW Internal)
5. MWBE Contract Compliance Memo TRV Street Improvement for Henderson Detour KH.pdf (CFW
Internal)
Logname: 20TRV LOCAL STREET IMPROVEMENTS Page 2 of 2