NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Watersbend South Phase 1 D
City Project No.: 101975
Improvement Type(s): Water ® Sewer
Original Contract Price: $426,646.00
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $426,646.00
CesarmGa da(Jul20,202008:24CDT) Ju120,2020
Contractor Date
Superintendent
Title
Conatser construction
Company Name
MAAUIW CAWW�
Manuel Chatman(Jul 20,202009:11 CDT) Jul 20,2020
Project I-n�sppeecttoor� Date
' 1�'A
FRED EHIA—(Ju120,202010:45 CDC Ju120 f2020
Project Manager Date
Laurie Lewis(Jul 20,202013:35 CDT) Ju120,2020
CFA Manager Date
0444,LuNgA&6o
Dana Burghdoff( 20,20 3:38CDT) Ju120,2020
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name:Watersbend South Phase 1 D
City Project No.: 101975
City's Attachments
Final Pay Estimate
Change Order(s): ❑ Yes ® N/A
Pipe Report: ® Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 130 CD Days Charged: 130
Work Start Date: 10/10/2019 Work Complete Date: 7/7/2020
Page 2of2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name WATERSBEND SOUTH PHASE 11)
Contract Limits
Project Type WATER&SEWER
City Project Numbers 101975
DOE Number 1019
Estimate Number 1 Payment Number 1 For Period Ending 2/17/2020
W
City Secretary Contract Number 52682 Contract Time 13@V
Contract Date Days Charged to Date 130
Project Manager NA Contract is 100.00 Complete
Contractor CONATSER CONSTRUCTION TxLP
5327 WICHITA ST
FORT WORTH, TX 76119
Inspectors MILLER,W / CHATMAN,M
Friday,July 17,2020 Page 1 of 4
City Project Numbers 101975 DOE Number 1019
Contract Name WATERSBEND SOUTH PHASE 1D Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 2/17/2020
Project Funding
WATER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8"PVC WATER PIPE 2875 LF $32.00 $92,000.00 2875 $92,000.00
2 8"GATE VALVE 4 EA $1,250.00 $5,000.00 4 $5,000.00
3 STD.FIRE HYDRANT ASSEMBLY W/6"GATE 4 EA $4,200.00 $16,800.00 4 $16,800.00
VALVE&VALVE BOX
4 DUCTILE IRON WATER FITTINGS 0.4 TN $4,500.00 $1,800.00 0.4 $1,800.00
W/RESTRAINT
5 TRENCH SAFETY 2875 LF $1.00 $2,875.00 2875 $2,875.00
6 1"DOMESTIC WATER SERVICES 92 EA $950.00 $87,400.00 92 $87,400.00
7 CONNECT TO EXISTING 8"W.L.STUB-OUT 4 EA $1,000.00 $4,000.00 4 $4,000.00
--------------------------------------
Sub-Total of Previous Unit $209,875.00 $209,875.00
--------------------------------------
SEWER
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
8 8"SDR-26 PVC SEWER PIPE 2656 LF $38.00 $100,928.00 2656 $100,928.00
9 SDR-26 4"SEWER SERVICES 92 EA $650.00 $59,800.00 92 $59,800.00
10 4'STD DIA.MANHOLE 9 EA $4,000.00 $36,000.00 9 $36,000.00
11 8"PVC SANITARY SEWER PIPE W/CSS 100 LF $48.00 $4,800.00 100 $4,800.00
BACKFILL
12 TRENCH SAFETY 2656 LF $1.00 $2,656.00 2656 $2,656.00
13 POST-CCTV INSPECTION 2656 LF $2.00 $5,312.00 2656 $5,312.00
14 4'EXTRA DEPTH MANHOLE 13 VF $175.00 $2,275.00 13 $2,275.00
15 TRENCH WATER STOPS 4 EA $500.00 $2,000.00 4 $2,000.00
16 CONNECT TO EXISTING 8"SEWER 3 EA $1,000.00 $3,000.00 3 $3,000.00
--------------------------------------
Sub-Total of Previous Unit $216,771.00 $216,771.00
--------------------------------------
Friday,July 17,2020 Page 2 of 4
City Project Numbers 101975 DOE Number 1019
Contract Name WATERSBEND SOUTH PHASE 1D Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 2/17/2020
Project Funding
Contract Information Summary
Original Contract Amount $426,646.00
Chanize Orders
Total Contract Price $426,646.00
Total Cost of Work Completed $426,646.00
Less %Retained $0.00
Net Earned $426,646.00
Earned This Period $426,646.00
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $426,646.00
Friday,July 17,2020 Page 3 of 4
City Project Numbers 101975 DOE Number 1019
Contract Name WATERSBEND SOUTH PHASE 1D Estimate Number 1
Contract Limits Payment Number 1
Project Type WATER&SEWER For Period Ending 2/17/2020
Project Funding
Project Manager NA City Secretary Contract Number 52682
Inspectors MILLER,W / CHATMAN,M Contract Date
Contractor CONATSER CONSTRUCTION TxLP Contract Time 130 W
5327 WICHITA ST Days Charged to Date 130 W
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $426,646.00
Less %Retained $0.00
Net Earned $426,646.00
Earned This Period $426,646.00
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $426,646.00
Friday,July 17,2020 Page 4 of 4
FORTWORTH
TRANSPORTATION AND PUBLIC WORKS
PIPE REPORT FOR:
PROJECT NAME: Watersbend South Phase I
PROJECT NUMBER: 101975
DOE NUMBER: N/A
WATER
PIPE LAID SIZE TYPE OF PIPE LF
WATER 8" PVC 2,875
FIRE HYDRANTS: 4 VALVES(16"OR LARGER)
PIPE ABANDONED SIZE TYPE OF PIPE LF
611
DENSITIES: Yes
NEW SERVICES: 92(1") Copper 92ea.
SEWER
PIPE LAID SIZE TYPE OF PIPE LF
SEWER 8" SDR-26 PVC 2,656
PIPE ABANDONED SIZE TYPE OF PIPE LF
DENSITIES: Yes
NEW SERVICES: 4" SDR-26 PVC 92 ea.
4' DIP 9ea.
TRANSPORTATION AND PUBLIC WORKS
The Ciry of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
(817) 392-7941 •Fax: (817) 392-7845
FORT WORTH rev 03/05/07
TRANSPORTATION &PUBLIC WORKS
STATEMENT OF CONTRACT TIME
STATEMENT NO.: N/A
NAME OF PROJECT: Watersbend South Phase I
PROJECT NO.: 101975 CONTRACTOR: Conatser
DOE NO.: 1975
PERIOD FROM:10/10/19 TO: 07/07/20
WORK ORDER EFFECTIVE:10/10/2020 CONTRACT TIME: 130 O WD(1 CD
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED CREDITED MONTH CHARGED CREDITED
DURING DURING
1. 16.
2. 17.
3. 18.
4. 19.
5. 20.
6. 21.
7. 22.
8. 23.
9. 24.
10. 25.
11. 26.
12. 27.
13. 28.
14. 29.
15. 30.
31.
SAT' ' 'SUN RAIN TOO WET' OTHERS UTILITIES DAYS TOTAL
&HOLIDAYS &TOO COLD RELOCATIONS CHARGED DAYS
THIS
PERIOD
PREVIOUS
PERIOD
TOTALS
TO DATE
*REMARKS:
July 17, 2020
INSPECTOR DATE
ENGINEERING DEPARTMENT
The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TX 76012-6311
(817) 392-7941 •Fax: (817) 392-7845
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
July 10, 2020
Conatser Construction TX, L.P.
5327 Wichita Street
Fort Worth,TX 76119
RE: Acceptance Letter
Project Name: Watersbend South Phase 1D
Project Type:Water, Sewer
City Project No.: 101975
To Whom It May Concern:
On June 24, 2020 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on July 7, 2020. The final inspection and
the corrected punch list items indicate that the work meets the City of Fort Worth specifications and is
therefore accepted by the City. The warranty period will start on July 10,2020,which is the date of the
punch list completion and will extend of two(2)years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
817.392.8424.
Sincerely,
zam
(_
FRED EHIA(Jul 20,202010:45 CDT)
Fred Ehia, Project Manager
Cc: Manuel Chatman, Inspector
Wade Miller, Inspection Supervisor
Emanuel Nieto,Senior Inspector
Victor Tonero, Program Manager
Goodwin & Marshall Inc., Consultant
Conatser Construction TX L.P., Contractor
Forestar, Developer
File