HomeMy WebLinkAboutContract 46411-A1 Date:07/24/20 CSC No. 46411-A1
Time:9:31 AM
AMENDMENT No. 1
TO CITY SECRETARY CONTRACT
WREREAIS, the City of Fort Worth (CITY) and Kimley-Horn
and Associates, Inc. , (ENGINEER) made and entered into City
Secretary Contract No. 46411 (the CONTRACT) which was authorized
by M&C C-27174 on the 3rd day of February, 2015 in the amount of
$697, 702 , 00; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
Upper Clear Fork Drainage Basin Parallel Interceptor
Improvements at Various Locations within the Upper Clear
Fork Drainage Basin.
WHEREAS, it has become necessary to execute Amendment
No. 1 to the CONTRACT to include an increased scope of work and
revised fee.
NOWTMREFORE, CITY and ENGINEER, acting herein by and
through their duly authorized representatives, enter into the
following agreement, which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the
additional engineering services specified in a proposal dated
April 21 , 20201 a copy of which is attached hereto and
incorporated herein. The cost to City for the additional design
services to be performed by Engineer totals $22,266, 00 . (Sewer:
56002, WP 33)
2 .
Article II of the CONTRACT is amended to provide for an
increase in the fee to be paid to Engineer for all work and
services performed under the Contract, as amended, so that the
total fee paid by the City for all work and services shall be
an amount of $719, 968 . 00 .
3 .
OFFICIAL RECORD
Page -1- CITY SECRETARY
FT. WORTH, TX
All other provisions of the Contract, which are not
expressly amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a
signatory, below.
APPROVED: ENGINEER
City of Fort Worth Kimley-Horn and Associates, Inc.
ba8�(1 a,d6-22
/
Dana Burghdoff Glenn A. Gary, P.E.
Assistant City Manager Senior Vice-President
DATE: Jul 23,2020 6 _3 _ �DO�
DATE:
APPROVAL RECOMMENDED:
Chrietoeher HaN (J1117,1 Z:000n
Christopher Harder, P.E.
Director, Water Department
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring
all r�',orman and r porting requirements ,
a+,N
LjAA Conlon
Project Manager
APPROVED AS TO FORM AND LEGALITY: M&C: N/A
am- Date: N/A
DB!!(Jul2i""M2 Con
Douglas W. Black
Senior Assistant City Attorney
44.d4U�n��
ATTEST: y�0FORr aad
�o� p�° ° °Op.1G
Pv8 o=d
Pp�* 000
b
Mary J. Kayser 0�4tt nBxAsgp
City Secretary
OFFICIAL RECORD
Page -2-
CITY SECRETARY
FT. WORTH, TX
Kimley >>> Horn
April 21, 2020
Mr. Liam Conlon
Project Manager
City of Fort Worth Water Department
1000 Throckmorton Street
Fort Worth,TX 76102
Re: Upper Clear Fork Drainage Basin Interceptor Improvements
Amendment No. 1 —Additional Construction Phase Services
KHA No. 061018142
City Project No. 02448
Dear Liam:
This is an amendment to a contract between Kimley-Horn and Associates, Inc. and the City of Fort
Worth ("the City")dated 02-13-2015 referred to herein as the"Contract'.
This amendment will provide for Additional Construction Phase Services as indicated below:
CONTRACT TASK 8 — CONSTRUCTION PHASE SERVICES (ONE BID PACKAGE):
(Water$0, Sewer$22,266)
ENGINEER will prepare Construction Phase Services scope of services in accordance with the
Original Contract for the following:
® Review up to 10 Additional Shop Drawings
® Attend up to 6 Additional Progress Meetings or Site Observations, and Prepare Meeting Notes
® Provide clarification for up to 6 Contractor Requests for Information(RFI)
We recommend that the City increase the budget by$22,266 for these additional services_The
following tables summarize our recommended budget revisions, water and sanitary sewer design fees,
and revised contract amount:
Description Water Sewer Total
Task 1-Design Management $0 $0 $0
Task 2—Upper Clear Fork Part 1 (WWMP Project 6)
Conceptual Design(30%) $0 $0 $0
Task 3—Upper Clear Fork Part 2(WWMP Project 8)
Conceptual Design(30%) $0 $0 $0
Task 4—ICAP Conceptual Design(30%) $0 $0 $0
Task 5—ICAP Preliminary Design(60%) $0 $0 $0
Task 6—ICAP Final Design(90%)and Final Construction $0 $0 $0
Documents(100%)
Task 7—Bid Phase Services $0 $0 $0
Task 8—Construction Phase Services(One Bid Package) $0 $22,266 $22,266
Task 9—ROW/Easement Services $0 $0 $0
Task 10—Survey and Subsurface Utility Engineering
Services
$0 $0 $0
Task 11—Permitting Services $0 $0 $0
Total $0 $22,266 $22,266
8011300
Kimley >>> Horn Page 2
The following table summarizes the Fee per Work Phase breakdown.-
Work Phase Water Sewer Total
31 $0 $0 $0
32 $0 $0 $0
33 $0 $22,266 $22,266
51 $0 $0 $0
The following breakdown for water and sewer services is recommended:
Water Fee Sewer Fee Survey Fee Total
Original Contract $0 $656,102 $41,600 $697,702
Amendment No.1 $0 $22,266 $0 $22,266
Total $0 $678,368 $41,600 $719,968
The following table summarizes our recommended budget revisions and shows the revised contract
amount:
Original Contract Amend No.1 Revised Contract
Task 1 $31,919 $0 $31,919
Task 2 $100,536 $0 $100,536
Task 3 $93,420 $0 $93,420
Task 4 $70,358 $0 $70,358
Task 5 $122,497 $0 $122,497
Task 6 $115.079 $0 $115,079
Task 7 $19,746 $0 $19,746
Task 8 $41,078 $22,266 $63,344
Task 9 $7,443 $0 $7,443
Task 10 $58,804 $0 $58,804
Task 11 $36,822 $0 $36,822
Total Project $697,702 $22,266 $719,968
We appreciate the opportunity to be of continued service to the City. Please contact us if we need to
provide any further information.
Very truly yours,
KIMLEY-HORN AND ASSOCIATES, INC
Glenn A. Gary, P.E.
Sr.Vice President
GAG/jck
K 1F74'G_Uohues461018142-Upper_Clear_Fork_SWPPPOST_NTPWmendmenl-Nd-1\Amendmerd-No I.doc