HomeMy WebLinkAboutContract 52228-A1 CSC No. 52228-A1 AMENDMENT No.1 TO CITY SECRETARY CONTRACT NO. 52228 WHEREAS, the City of Fort Worth ("CITY") and Parkhill, Smith & Cooper Inc. d/b/a Schrickel Rollins/ PSC, ("ENGINEER") made and entered into City Secretary Contract No. 52228, ("CONTRACT") which was authorized on the 26th day of April, 2019 in the amount of$398,732.00; and WHEREAS, the CONTRACT involves engineering services for the following project: Trail Gap Connections; and WHEREAS, it has become necessary to execute Amendment No. 1 to the CONTRACT to include an increased scope of work and revised fee. NOW THEREFORE, CITY and ENGINEER, acting herein by and through their duly authorized representatives, enter into the following agreement, which amends the CONTRACT: 1. Article I of the CONTRACT is amended to expand the Scope of Services to be provided by ENGINEER as specified in Attachment A.1 which is attached hereto and incorporated herein. 2. Article II of the CONTRACT is amended to increase the Compensation to be paid to ENGINEER as specified in Attachment B.1 which is attached hereto and incorporated herein. The cost to CITY for the additional engineering related professional services to be performed by ENGINEER by this amendment totals the amount up to $85,241.00. (See Funding Breakdown Sheet attached hereto.) The ENGINEER's compensation for all engineering related professional services under the CONTRACT, as amended, shall be in the amount up to $483,973.00 (Four Hundred Eighty-three Thousand Nine Hundred Seventy-three Dollars). 3. Attachment D Project Schedule of the CONTRACT is amended to establish the Schedule for completion of all engineering related professional services by ENGINEER as specified in Attachment D.1 which is attached hereto and incorporated herein. 4. All other provisions of the CONTRACT, which are not expressly amended herein, shall remain in full force and effect. OFFICIAL RECORD CITY SECRETARY Amendment No.1 to City Secretary Contract No.52228 Trail Gap Connections-CFW Project No.101632 FT. WORTH, TX Page 1 of 3 Duly executed by each party's designated representative to be effective on the date subscribed by the CITY's designated Assistant City Manager. BY: BY: CITY OF FORT WORTH ENGINEER Parkhill, Smith & Cooper Inc. d/b/a Schrickel Rollins/ PSC Vt^l Valerie Washington(Ju128,2020 09:30 CDT) Valerie Washington Assistant City Manager Victor W. Baxter Date: Jul 28, 2020 (Signatory's Printed Name) Director of Landscape Architecture and Planning Business Development (Signatory's Printed Title) Date: Jul 22, 2020 APPROVAL RECOMMENDED: Agy1w Cheek By: David Creek(Jul 24,202014:12 CDT) Richard Zavala, Director Park& Recreation Department 'Im DC DC Contract Compliance Manager By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Dwight Taylor Project Manager OFFICIAL RECORD CITY SECRETARY Amendment No.1 to City Secretary Contract No.52228 Trail Gap Connections-CFW Project No.101632 FT. WORTH, TX Page 2 of 3 APPROVED AS TO FORM AND LEGALITY �l NC/�GO.LOLD DBlack(Jul 28,2020 07:29 CDT) By: Douglas W. Black Senior Assistant City Attorney �44nnn� a� FORrQua F......0.* � ®ti o ATTEST: ��o o=� $�*o00 *� Form 1295 No: n/a 000000000 M&C No: n/a Mary J. Kayser RAa City Secretary Rp M&C Date: n/a OFFICIAL RECORD CITY SECRETARY Amendment No.1 to City Secretary Contract No.52228 Trail Gap Connections-CFW Project No.101632 FT. WORTH, TX Page 3 of 3 Attachment A.1 Scope of Services Amendment No. 1 to City Secretary Contract No.52228 Trail Gap Connections Attachment A Scope of Services of the CONTRACT is amended as defined below. (i)Below BASIC SERVICES Task C description, add the following: D. Final Design (100%/Sealed Construction Document Levels) ENGINEER shall perform the following tasks: Based on CITY's review of the ENGINEER's 90% Construction Document Level and input and guidance from CITY, prepare final design documents (plans, cost opinion, and specifications at 100%/Sealed construction document level submittals)as described below for the following trail gap connections: ■ Buck Sansom Park to Marine Creek Lake Trail — segment from the existing trail located in the northeast corner of Buck Sansom Park to the existing trail located just northwest of the trailhead parking area at the southeast corner of Marine Creek Lake, measuring approximately 1.3 miles in length (excluding 1-820 interchange as defined in ENGINEER's 90%Construction Document level plans) ■ Arcadia Trail Park South to Arcadia Trail Park North—segment from the existing trail just northeast of the intersection of Seneca Drive and Truxton Court to the northwest corner of the intersection of N. Beach Street and Thompson Road, measuring approximately 0.5 miles in length Final design for all improvements shall follow current CITY standard designs and specifications unless otherwise approved in writing by CITY,as follows: ■ All proposed improvements shall be consistently referenced in all documents with regard to pay item number and pay item name (whether on plan documents, in specification documents, or in estimate documents). ■ All pay item numbers, names, and specifications shall correspond to CITY standard number, name, and specification for the item if CITY has one(use 'CIVIL'version first, if not one,then use 'PAR'version). ■ If CITY does not have a standard number, name, and specification for a particular item, then the pay item number, name, and specification for that item shall correspond to TOOT standard number, name, and specification for the item, if TOOT has one. Attachment A.1 Scope of Services-Amendment No.1 to City Secretary Contract No.52228 Trail Gap Connections—City of Fort Worth Project No.101632 Page 1 of 4 ■ If TOOT does not have a standard number, name, and specification for a particular item, then the pay item number, name, and specification for that item shall correspond to another widely accepted standard number,name,and specification for the item, if a widely accepted standard exists. ■ If another widely accepted standard number, name, and specification for a particular item one does not exist, then a custom pay item number, name, and specification shall be created by ENGINEER. ENGINEER shall, at request of CITY at any time throughout the project, transmit to CITY electronic copies of ENGINEER work product components including but not limited to data, photos, images,text, designs, cost opinions, etc.for project-related use by CITY including but not limited to project budgeting, coordination, communication, bidding, etc. This requirement shall include but not be limited to ENGINEER's transmittal of electronic files of drawings to CITY's designated project folder system. 1) Final Design Plans The final design plans shall be suitable for use and submitted in both 22 inch x 34 inch (full-size) and 11 inch x 17 inch (half size)format with black and white line work(and with full-color aerial photo background which can be turned on or off as requested by CITY). The minimum text font size shall be 12 point on full-size sheets and 6 point on half-size sheets. Both full-size and half-size sheet plan and detail views shall be to standard engineer or architect scale(for example: 1 inch=30 feet full-size/1 inch=60 feet half-size for plans; 1/4 inch = 1 foot full size and 1/8 inch = 1 foot half size for details). All plan submittals (full-size and half-size, hardcopy and electronic pdf) shall be true to feet per inch scales indicated on the plans. The plan sets shall be submitted in both full-size and half-size formats with three (3) hardcopies in each size, bound with a solid black heavy paper binder strip on left side and with an electronic pdf in each size. The content and organization of the all final design submittals shall be based on the requirements for the ENGINEER's 90% Construction Document Level plans and all additional necessary structural design plans, details, cost opinion, and specifications related to the Arcadia Trail improvements in the vicinity of the north edge of the residential property at 8165 Keechi Creek Court(Park Glen Addition Block 124 Lot 51). The final design plans shall include, at a minimum, the following in the sheet formats provided by CITY and in the order shown below: Attachment A.1 Scope of Services-Amendment No.1 to city secretary Contract No.52228 Trail Gap Connections—City of Fort Worth Project No.101632 Page 2 of 4 A) Cover B) General Notes C) Summary of Quantities D) Key Map(with match lines and references to plan and detail sheets) E) Typical Sections F) Plans and Details (number of plan sheets as required for legibility and scalability in both full-size and half-size sheet format) 2) Final Design Cost Opinion The final design opinion of probable construction cost shall be based on the ENGINEER's plans and on unit prices current at the time of the cost opinion preparation. The cost opinion shall be submitted in 8%inch x 11 inch portrait format, printed on one side,three (3) hardcopies and an electronic pdf. 3) Final Design Specifications The final design specifications shall include all project applicable construction specification sections for the project. The CITY shall provide ENGINEER with CITY's electronic standard technical specification sections as well as with CITY's electronic standard front-end non-technical section documents including: cover, table of contents, general conditions,general requirements, and appendix. ENGINEER shall complete fill-in of all applicable blanks in the front-end non-technical specification sections with CITY input and guidance. The specifications shall be submitted in electronic version (in both MS Word and pdf formats) and in hardcopy version in 8 % inch x 11 inch portrait format, black and white, unbound, printed on one side. ENGINEER shall submit three (3) hardcopy versions and an electronic version at both the 100% construction document level submittal and the sealed construction document level submittal. 4) Final Design CITY Reviews and Meetings Throughout the final design phase, ENGINEER shall attend online meetings (WebEx or similar online videoconference) with the CITY to discuss the CITY's review comments, to obtain CITY input and guidance, to coordinate with other CITY departments regarding compliance with CITY reviews and approvals,etc. These meetings are anticipated to occur one to two times in a given week to ensure timely project coordination and progress of the work. Attachment A.1 Scope of Services-Amendment No.1 to City Secretary Contract No.52228 Trail Gap Connections—City of Fort Worth Project No.101632 Page 3 of 4 (H)Below SPECIAL SERVICES Task B—Contingency Services, item h., add the following: i. review of ENGINEER'S final design plans for compliance with Texas Accessibility Standards(TAS) and registration of each trail connection project(Buck Sansom to Marine Creek segment and Arcadia Trail Park segment) with Texas Department of Licensing and Regulation (TDLR) j. hydraulics and hydrology/flood studies k. environmental studies I. bid phase assistance (meetings, addenda, bid tabulation/evaluation,etc.) m. construction phase assistance (meetings,submittal review,site visits, etc.) Attachment A.1 Scope of Services-Amendment No.1 to city secretary Contract No.52228 Trail Gap Connections—City of Fort Worth Project No.101632 Page 4 of 4 Attachment B.1 Compensation Amendment No. 1 to City Secretary Contract No.52228 Trail Gap Connections Attachment B Compensation of the CONTRACT is amended as defined below. (i) The first paragraph first sentence is amended as follows: The services and expenses described in Attachment A Scope of Services, as amended by Attachment A.1, shall be provided by the ENGINEER for a total fee not to exceed $483,973 (Four Hundred Eighty-three Thousand Nine Hundred Seventy-three Dollars)without prior written authorization from CITY. (ii)Below I. Basic Services, add the following new subtask and fee amount: D. Final Design (100%/Sealed CD Level) (lump sum) $ 55,741 (iii)Below I. Basic Services, increase the Basic Services Subtotal fee amount by$55,741 as follows: Basic Services Subtotal $ 316,413 (iv)Below 11. Special Services, increase the Subtask B—Contingency Services fee amount by$29,500 as follows: B. Special Service—Contingency Services(lump sum) $ 84,500 (v)Below 11. Special Services, increase the Special Services Subtotal fee amount by$29,500 as follows: Special Services Subtotal $ 167,560 (vi)Increase the Total Fee for Services amount by$85,241 as follows: Total Fee for Services $483,973 Attachment 8.1 Compensation-Amendment No.1 to City Secretary Contract No.52228 Trail Gap Connections—City of Fort Worth Project No.101632 Page 1 of 1 Attachment D.1 Project Schedule Amendment No. 1 to City Secretary Contract No.52228 Trail Gap Connections Attachment D Project Schedule of the CONTRACT is amended as defined below. (i) The first paragraph first sentence is amended as follows: The CITY anticipates ENGINEER'S completion of the services described in Attachment A Scope of Services,as amended by Attachment A.1,within eight (8) weeks of ENGINEER'S receipt of notice-to-proceed with services described in Attachment A.1 from CITY. (H)Below 1. Basic Services, add the following subtask and duration: D. Final Design (100%/Sealed CD Level) 8 weeks Attachment D.1 Project Schedule-Amendment No.1 to City Secretary Contract No.52228 Trail Gap Connections—City of Fort Worth Project No.101632 Page 1 of 1