HomeMy WebLinkAboutContract 52329-CO3 CSC No.52329-CO3 FORT WORTH, City of Fort Worth Change Order Request Project Namel 2018 CIP Concrete Restoration-Contract 5 City Sec# 52329 Client Project#(s) CPH#101570 Project Description Replacement of damaged concrete panels. Contractorl Omega Contracting Inc. Change Order# 0 Date 7/23/2020 City Project Mgr.I Maged Zaki City Inspector Brian McGill Dept. Water TPW Contract Time Totals WD Original Contract Amount $0.00 $1,618,196.00 $1,618,196.00 360 Extras to Date $31,900.00 $18,000.00 $49,900.00 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $31,900.00 $1,636,196.00 $1,668,096.00 360 No to ADD&DEL Tabs to Enter CO Backup $0.00 $0.00 15 Revised Contract Amount $31,900.00 $1,636,196.00 $1,668,096.00 375 Original Funds Available for Change Orders $0.00 Remaining Funds Available for this CO $0.00 $0.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.080% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,022,745.00 JUSTIFICATION(REASONS)FOR CHANGE ORDER This change order is required to add 15 days to the project duration due to the additional traffic control adjustments around Tx-183 HWY exits on W.Vickery Blvd.Those additional adjustments were needed to secure safe routs and work:zones. It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The PfojecUProg ram Manager signing below acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and reporting requirements. Contractor's.Company Name Cofttrac or ame r t Signature Date Omega Contracting Inc. a/7; '74 le-!A 1 y X7 Inspectodlttspection Supervisor Date Project Manager/Prograrn Manager Date liAl� Aug 4,2020 ge4zaw Aug4,2020 Assistant Director Dept Date Director,Contracting Department Dept Date Pam* Aug 4,2020 Aug 5,2020 N Assistant City Attorney Date `Assistant City Manager Date Aug 6,2020 Aug 6,2020 Council Action if require" M&C Number M&C Date Approved OFFICIAL RECORD CITY SECRETARY Change Order Additions Page 1 of 4 FT. WORTH, TX FORTWOR111 City of Fort Worth --1- Change Order Additions Project Name 2010 CIP Concrete Restoration-Contract 5 City Sec# 52329 Client Project# CPN#101570 Project Description FRPplaocmpnt of damaged concrete panels. Contractor Omega Contracting Inc. Change Order# F-3 Date 7123/2020 City Project Mgr. Maged Zaki City Inspector FB,,n McGill AUDITIONS y unit Units c a f Water 0.00 TPW Sub Total Additions Change Order Additions Page 2 of 4 FORTWORTH City of Fort Worth llv�— Change Order Deletions Project Name 2018 CIP Concrete Restoration-Contract 5 City Sec# 52329 Client Projecl# CPN#101570 Project Description Replacement of damaged concrete panels. Contractor Omega Contracting Inc. Change Order# 0 Date 7l2312020 City Project Mgr. Maged Zaki City Inspector Brian McGill DELETIONS y Unit Units oa Water $0.00 TPW $0.00 Sub Totalollons Change Order Additions Page 3 of 4 MIWBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO NIA Total $0.00 Previous Change Orders CO# DATE AMOUNT None Total $0.00 Change Order Additions Page 4 of 4 Contract Compliance Manager: By signing, I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requiremee ts. cO cl��J�/� Maged Zaki Professional Engineer. 4.opvonp cps�f oRr�°9$ �a ATTEST: c�a aid oaa*ooQ o00*�a �y�, y�,a,� Oaan nEXA`-+odOp Mary J.Kayser City Secretary OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX