NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Sanitary Sewer to Serve Nationwide Trailers
City Project No.: 101487
Improvement Type(s): Water ❑ Sewer
Original Contract Price: $134,459.50
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $134,459.50
� s Aug 19,2020
Contractor Date
Project Manager/Official Secretary
Title
Wildstone Construction, LLC
Company Name
`-5-Z 'A�'�'��
Steven Aguirre(Aug 20,200 Aug20f 2020
07:47 CDT) b
Project Inspector Date
Mitch Holmes(Aug 21,202013:43 CDT) Aug 21,2020
Project Manager Date
Laurie Lewis
Laurie Lewis(Aug 21,202014:07 CDT) Aug 21,2020
CFA Manager Date
471>a&.271 ZGL4�� Aug 22,2020
Dana Burghdoff(Aug 22,20 09:30 CDT, _
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT.WORTH, TX
Notice of Project Completion
Project Name: Sanitary Sewer to Serve Nationwide Trailers
City Project No.: 101487
City's Attachments
Final Pay Estimate
Change Order(s): ❑ Yes ® N/A
Pipe Report: ® Yes ❑ N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 39 CD Days Charged: 508
Work Start Date: 3/18/2019 Work Complete Date: 8/6/2020
Page 2of2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name SANITARY SEWER TO SERVE NATIONWIDE TRAILERS
Contract Limits
Project Type SANITRY SEWER
City Project Numbers 101487
DOE Number 4870
Estimate Number 1 Payment Number 1 For Period Ending 8/7/2020
CD
City Secretary Contract Number Contract Time 3ED
Contract Date Days Charged to Date 508
Project Manager NA Contract is 100.00 Complete
Contractor WILDSTONE CONSTRUCTION
P O BOX 164429
FORT WORTH, TX 76161
Inspectors CORDOVA / AGUIRRE,S
Monday,August 10,2020 Page 1 of 4
City Project Numbers 101487 DOE Number 4870
Contract Name SANITARY SEWER TO SERVE NATIONWIDE TRAILERS Estimate Number 1
Contract Limits Payment Number 1
Project Type SANITRY SEWER For Period Ending 8/7/2020
Project Funding
UNTI L•SANITARY SEWER IMPROVEMENTS
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 8'SEWER PIPE(SDR-26) 516 LF $132.00 $68,112.00 516 $68,112.00
2 IMPORTED EMBEDMENTBACKFILL 6.5 CY $320.00 $2,080.00 6.5 $2,080.00
3 4'MANHOLE 4 EA $5,900.00 $23,600.00 4 $23,600.00
4 4'EXTRA DEPTH MANHOLE 15.4 CF $350.00 $5,390.00 15.4 $5,390.00
5 CONCRETE COLLAR MANHOLE LID 4 EA $400.00 $1,600.00 4 $1,600.00
6 MANHOLE VACUUM TESTING 4 EA $250.00 $1,000.00 4 $1,000.00
7 Y WIDE ASPHALT PVMT REPAIR, 160 LF $74.00 $11,840.00 160 $11,840.00
RESIDENTIAL
8 BARRIER FREE RAMP TYPE P-1 1 EA $6,000.00 $6,000.00 1 $6,000.00
9 FIRE LANE MARKING 30 LF $20.00 $600.00 30 $600.00
10 POST CCTV INSPECTION 521 LF $1.50 $781.50 521 $781.50
11 TRENCH SAFETY 521 LF $2.00 $1,042.00 521 $1,042.00
12 CONSTRUCTION STAKING 1 LS $532.00 $532.00 1 $532.00
13 AS-BUILT SURVEY POST CONSTRUCTION 1 LS $532.00 $532.00 1 $532.00
14 TRAFFIC CONTROL 0.5 MO $7,350.00 $3,675.00 0.5 $3,675.00
15 EROSION CONTROL 1 LS $7,675.00 $7,675.00 1 $7,675.00
--------------------------------------
Sub-Total of Previous Unit $134,459.50 $134,459.50
--------------------------------------
Monday,August 10,2020 Page 2 of 4
City Project Numbers 101487 DOE Number 4870
Contract Name SANITARY SEWER TO SERVE NATIONWIDE TRAILERS Estimate Number 1
Contract Limits Payment Number 1
Project Type SANITRY SEWER For Period Ending 8/7/2020
Project Funding
Contract Information Summary
Original Contract Amount $134,459.50
Chanize Orders
Total Contract Price $134,459.50
Total Cost of Work Completed $134,459.50
Less %Retained $0.00
Net Earned $134,459.50
Earned This Period $134,459.50
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $134,459.50
Monday,August 10,2020 Page 3 of 4
City Project Numbers 101487 DOE Number 4870
Contract Name SANITARY SEWER TO SERVE NATIONWIDE TRAILERS Estimate Number 1
Contract Limits Payment Number 1
Project Type SANITRY SEWER For Period Ending 8/7/2020
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors CORDOVA / AGUIRRE,S Contract Date
Contractor WILDSTONE CONSTRUCTION Contract Time 39 CD
P O BOX 164429 Days Charged to Date 508 CD
FORT WORTH, TX 76161 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $134,459.50
Less %Retained $0.00
Net Earned $134,459.50
Earned This Period $134,459.50
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $134,459.50
Monday,August 10,2020 Page 4 of 4
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
August 7, 2020
Wildstone Construction, LLC.
12850 HWY 287
Fort Worth,Tx. 76052
RE: Acceptance Letter
Project Name: Sewer Improvements to Serve Nationwide Trailers
Project Type: Sewer
City Project No.: 101487
To Whom It May Concern:
On August 6, 2020 a final inspection was made on the subject project. There were no punch list items
identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on August 6, 2020,
which is the date of the final inspection and will extend of two (2) years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
(817)392-8306.
Sincerely,
Mitch Holmes(Aug 21,202013:43 CDT)
Mitchell Holmes, Project Manager
Cc: Steven Aguirre, Inspector
Ron Cordova, Inspection Supervisor
Edward Davila, Senior Inspector
Victor Tornero, Program Manager
Baird, Hampton & Brown,INC., Consultant
Wildstone Construction, LLC, Contractor
NWT 2850,LLC, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev.08/20/19
IL-DST E
CONSTRUCTIO LLC
AFFIDAVIT
STATE OF Texas
COUNTY OF Tarrant
Before me,the undersigned authority, a notary public in the state and county
aforesaid,on this day personally appeared John Kolb, President of Wildstone Construction, LLC,
known to me to be a credible person,who being by me duly sworn, upon his oath deposed and
said;
That all persons,firms,associations, corporations,or other organizations furnishing
labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth has been
paid in full;
That there are no claims pending for personal injury and/or property damages;
On Contract described as:
Sanitary Sewer to Serve Nationwide Trailers—CPN: 101487
BY
J n kolb/President
Subs ribed swo before me on t s#te 19th day of August 2020.
Notary Public
Tarrant,Texas
4. ••0� April D Seleska
_,1 My Commission Expires
05!0912022
ID No 129813932
12850Highway 287 Office: 817-847-8660
Fort Worth,TX 76052 Fax: 817-847-8019
I
CONSENT OF
SURETY COMPANY
TO FINAL PAYMENT Bond #8253-03-71
Project: Sanitary Sewer to Serve Nationwide Trailers
To(Owner):
City of Fort Worth, Texas and
NWT 2850, LLC
200 Texas Street Contract For: See above
Ft Worth,TX 76102
Contract Date:
Contractor:
Wildstone Construction,LLC
In accordance with the provision of the Contract between the Owner and the Contractor as
defined above,the Federal Insurance Company
202B Hall's Mill Road
Whitehouse Station,NJ 08889
,
on bond of Wildstone Construction,LLC Surety Company,
12850 Hwy 287
Ft Worth,TX 76052
,Contractor
hereby approves of the final payment to the contractor and agrees that final payment to the
contractor shall not relieve the Surety Company of any of its obligations to the
City of Fort Worth,Texas and NWT 2850,LLC
200 Texas Street
Ft Worth,TX 76102
,Owner
as set forth in the said Surety Company's bond.
IN WITNESS WHEREOF,
the Surety Company has hereunto set its hand this 18'h day of August,2020.
Federal Insurance Company
Witness:
Roberta H. Erb,Attorney-in-Fact
Power of Attorney
Federal Insurance Company I Vigilant Insurance Company I Pacific Indemnity Company
Westchester Fire Insurance Company I ACE American Insurance Company
Know All by These Presents, that FEDERAL INSURANCE COMPANY, an Indiana corporation,VIGILANT INSURANCE COMPANY, a New York corporation,PACIFIC
INDEMNITY COMPANY, a Wisconsin corporation, WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY corporations of the
Commonwealth of Pennsylvania, do each hereby constitute and appoint Bennett Brown, W. Lawrence Brown, Roberta H. Erb, Steven M. Tucker and
TracyTucker of Fort Worth,Texas---------------------------------------------------------------------------------------------------------------------------------------------------
each as their true and lawful AttomeyAn-Fact to execute under such designation in their names and to affix their corporate seals to and deliver for and on their behalf as surety
thereon or otherwise,bonds and undertakings and other writings obligatory in the nature thereof(other than bail bonds)given or executed in the course of business,and any
instruments amending or altering the same,and consents to the modification or alteration of any instrument referred to in said bonds or obligations.
In Witness Whereof, said FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY,PACIFIC INDEMNITY COMPANY,WESTCHESTER FIRE INSURANCE
COMPANY and ACE AMERICAN INSURANCE COMPANY have each executed and attested these presents and affixed their corporate seals on this 7t h day of November,2019.
Dawn M.Chloros.Assistant Secretary Stephen M.Haney,Vice President
STATE OF NEW JERSEY
County of Hunterdon SS.
On this 7th day of November,2019,before me,a Notary Public of New Jersey,personally came Dawn M.Chloros and Stephen M Haney,to me known to be Assistant Secretary and
Vice President,respectively, of FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE INSURANCE
COMPANY and ACE AMERICAN INSURANCE COMPANY,the companies which executed the foregoing Power of Attorney,and the said Dawn M.Chloros and Stephen M.Haney,
being by me duly sworn,severally and each for herself and himself did depose and say that they are Assistant Secretary and Vice President,respectively,of FEDERAL INSURANCE
COMPANY,VIGILANT INSURANCE COMPANY,PACIFIC INDEMNITY COMPANY,WESTCHESTER FIRE INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY and
know the corporate seals thereof,that the seals affixed to the foregoing Power of Attorney are such corporate seals and were thereto affixed by authority of said Companies;and
that their signatures as such officers were duly affixed and subscribed by like authority.
Notarial Seal
T�Ah KATHERINE J.ADELAAR
r a NOTARY PUBLIC OF NEW JERSEY
b No.231868b
Pt1BLfC CpatVn439f0n,Expires JutY 16,2024 Norary Ptettic
fER`�
CERTIFICATION
Resolutions adopted by the Boards of Directors of FEDERAL INSURANCE COMPANY,VIGILANT INSURANCE COMPANY,and PACIFIC INDEMNITY COMPANY on August 30,2016;
WESTCHESTER FIRE INSURANCE COMPANY on December 11,2006;and ACE AMERICAN INSURANCE COMPANY on March 20,2009:
-RESed into in theLVED,that following authorizations relate to the execution,for and on behalf of the company,of bonds,underraldngs,recognivances,contracts and other written commitments of the Com
enter
ordinary course of business(each a`Written Commitment"); pany
(1) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized to execute any Written Commitment for and on behalf of the Company,under the
seal of the Company or otherwise.
(2) Each duly appointed attomey-in-fad of the Company is hereby authorized to execute any Written Commitment for and on behalf of the Company,under the seal of the Company or
otherwise,to the extent that such action is authorized by the grant of powers provided for in such persons written appointment as such attorney-in-fact
(3) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized,for and on behalf of the Company,to appoint in writing any person the attorney-
in-fact of the Company with full power and authority to execute,for and on behalf of the Company,under the seal of the Company or otherwise,such Written Commitments of the
Company as may be specified in such written appointment,which specification may be by general type or class of Written Commitments or by specification of one or more particular
Written Commitments.
(4) Each of the Chairman,the President and the Vice Presidents of the Company is hereby authorized,for and on behalf of the Company,to delegate in writing to any other officer of the
Company the authority to execute,for and on behalf of the Company,under the Company s seal or otherwise,such Written Commitments of the Company as are specified in such
written delegation,which specification may be by general type or class of Written Commitments or by specification of one or more particular Written Commitments.
(5) The signature of any officer or other person executing any Written Commitment or appointment or delegation pursuant to this Resolution,and the seal of the Company,may be affixed by
facsimile on such Written Commitment or written appointment or delegation.
FURTHER RESOLVED,that the foregoing Resolution shall not be deemed to be an exclusive statement of the powers and authority of officers,employees and other persons to act for and on behalf of
the Company,and such Resolution shall not limit or otherwise affect the exercise of any such power or authority otherwise validly granted or vested."
L Dawn lit Chloros, Assistant Secretary of FEDERAL INSURANCE COMPANY, VIGILANT INSURANCE COMPANY, PACIFIC INDEMNITY COMPANY, WESTCHESTER FIRE
INSURANCE COMPANY and ACE AMERICAN INSURANCE COMPANY(the"Companies")do hereby certify that
(i) the foregoing Resolutions adopted by the Board of Directors of the Companies are true,correct and in full force and effect,
(ii) the foregoing Power of Attorney is true,correct and in full force and effect
Given under my hand and seals of said Companies at Whitehouse Station,M,this 18th day of August, 2020.
A 14 �t tom— •SilA1/1�
v Dawn A9.Chloros,Assistant Secra[ar?
IN THE EVENT YOU WISH TO VERIFY THE AUTHENTICITY OF THIS BOND OR NOTIFY US OF ANY OTHER MATTER,PLEASE CONTACT US AT:
T Je hone(908)903-3493 Fax(908)903-3656 a-mail:surety@chubb.com
Combined:FED-VIG-PI-WFIC-AAIC(rev.11-19)