HomeMy WebLinkAboutContract 52483-A2 CSC No. 52483-A2
AMENDMENT No.2
TO CITY SECRETARY CONTRACT No. 52483
WHEREAS, the City of Fort Worth (CITY) and Halff
Associates, Inc. , (ENGINEER) , made and entered into City Secretary
Contract No. 52483, (the CONTRACT) , which was authorized by M&C No.
C-29147 on the 11 day of June, 2019 in the amount of $ 930, 000 . 00
(Nine hundred and Thirty Thousand Dollars) ; and
WHEREAS, the CONTRACT involves engineering services for
the following project:
CentrePort Trail Phase I and Phase II Project; and
WHEREAS, it has become necessary to execute Amendment No. 2 to
the CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through
their duly authorized representatives, enter into the following
agreement, which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the
additional engineering services specified in a scope of services
proposal, a copy of which is attached hereto and incorporated herein
(Attachment A) . The cost to City for the additional design
services to be performed by Engineer totals $37,000. 00 (see attached
Funding Breakdown Sheet, page 3) .
2 .
Article II of the CONTRACT is amended to provide for an increase
in the fee to be paid to Engineer for all work and services performed
under the Contract, as amended, so that the total fee paid by the City
for all work and services shall be an amount of $994,000. 00.
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
City of Fort Worth OFFICIAL RECORD
Professional Services Agreement Amendment Template CITY SECRETARY
CFW Official Release 9/19/2017
Page 1 of 3 FT. WORTH, TX
APPROVED:
City of Fort Worth ENGINEER
1 Halff Associates, Inc.
Valerie Washington(Sep 1,2020 22:41 CDT)
Valerie Washington fjvid Buchanan
Assistant City Manager Director of Landscape Architecture
DATE: Sep 1, 2020 DATE: August 21, 2020
APPROVAL RECOMMENDED:
Richard Zavala(Aug 26,2020 21:22 CDT)
Richard Zavala
Director, Park & Recreation Department
DATE: Aug 26, 2020
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements .
Jing Yang
Project Manager
APPROVED AS TO FORM AND LEGALITY:
M&C: N&C
DBlack(Sep 1,20201721CDT) Date: Sep 1, 2020
Douglas W. Black
Assistant City Attorney
4p444UQ�
ATTEST: -poF F°Rroaa
° 9�0
d-0 0-00
Ov0 g=4
MaIPV� Date
`° Sep 2, 2020
add v
�n�pspb
Mary J. Kayser
City Secretary
City of Fort Worth OFFICIAL RECORD
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017 Page 2 of 3 CITY SECRETARY
FT. WORTH, TX
FUNDING BREAKDOWN SHEET
AMENDMENT No. 1
TO CITY SECRETARY CONTRACT No. 52483
DEPARTMENT FUND-ACCOUNT-CENTER AMOUNT
PARD 31001-5330500-0800450-100082-5030 $37, 000 . 00
City of Fort Worth
Professional Services Agreement Amendment Template
CFW Official Release 9/19/2017
Page 3 of 3
ATTACHMENT A
ONE 1201 North Bowser Road
■■■ HALFF Richardson,Texas 75081
■■■ (214)346-6200
Fax(214)739-0095
ADDITIONAL SERVICES CONFIRMATION
To: Jing Yang Date: July 24, 2020
From: Laura Johnson AVO: 34838.001
Email: LJohnson@halff.com Project: CentrePort Phase I
VIA: email
The scope of services provided below are a continuation of the scope of services stated in the Standard Form of
Agreement dated July 2, 2019 between The City of Fort Worth (CLIENT)and Halff Associates (CONSULTANT)for
CentrePort Trail— Phase 1. The specific H&H services provided as part of this amendment are as follows:
Additional Services
The Phase I H&H budget of$5,000 mainly only covered the cost of limited internal analysis and did not include the
development and submittal of reports to TxDOT and the City of Ft. Worth. The following is a summary of the
additional services requested for the effort that has exceeded the original scope.
• Data collection including topographic contours and land use for the unnamed tributary H&H study. Includes
development of the terrain to extract HEC-RAS cross section geometry.
• Development and QA/QC of the hydrology study for the unnamed tributary.
• Development and QA/QC of the hydraulic study for the unnamed tributary.
• Development and QA/QC of a TxDOT format report to submit to TxDOT for review. Includes coordination
and time to address TxDOT's comments.
• Development and QA/QC of a floodplain study report to request a floodplain permit from the City of Ft.
Worth. Includes City forms and developing additional exhibits not included in the TxDOT report as required
to document the floodplain study methodology. Includes coordination and time to address the City's
comments.
To perform these additional services, Halff is requesting a lump sum fee of$32,000.00 for the H&H work and
coordination/management and communication with the H&H team.
Additional Services total: $32,000.00
We request your signature below to confirm the scope and fee. If the scope and/or fee is not acceptable, please
notify us immediately.
CITY OF FORT WORTH HALFF ASSOCIATES INC.
By: By:
(Print name)
Title: Title:
Signature: Signature:
Date: Date:
ONE 1201 North Bowser Road
MEN HALFF Richardson,Texas
75081
(214)346-6200-6200
Fax(214)739-0095
ADDITIONAL SERVICES CONFIRMATION
To: Jing Yang Date: August 11, 2020
From: Laura Johnson AVO: 34838.001
Email: LJohnson@halff.com Project: CentrePort Phase II
VIA: email
The scope of services provided below are a continuation of the scope of services stated in the Standard Form of
Agreement dated July 2, 2019 between The City of Fort Worth (CLIENT)and Halff Associates (CONSULTANT)for
CentrePort Trail— Phase 11. The specific JPCentre services provided as part of this amendment are as follows:
Additional Services
This additional service is for the work performed on the added JPCentre 8' trail connection from Phase I to Phase
11.A connection study was sent to the CLIENT on March 10th, an exhibit was sent on April 215t and 30% Schematic
Design sheets with cost estimate were sent on June 12th. This effort culminated on June 25, 2020 with JP Morgan
abandoning idea of an 8' width connector trail to the CentrePort Phase 11 trail. For this additional service, Halff is
requesting a lump sum fee of$5,000.00.
Additional Services total: $5,000.00
We request your signature below to confirm the scope and fee. If the scope and/or fee is not acceptable, please
notify us immediately.
CITY OF FORT WORTH HALFF ASSOCIATES INC.
By: By:
(Print name)
Title: Title:
Signature: Signature:
Date: Date: