HomeMy WebLinkAboutContract 53916-PM1CSC No. 53916-PM1
RCVD 08/20/2020
00 00 10- 1
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 1 of 5
CITY OF FORT WORTH North City Addition Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049
Revised September 1, 2015
SECTION 00 00 10 1
TABLE OF CONTENTS 2
DEVELOPER AWARDED PROJECTS 3
4
Division 00 - General Conditions 5
00 11 13 Invitation to Bidders 6
00 21 13 Instructions to Bidders 7
00 41 00 Bid Form 8
00 42 43 Proposal Form Unit Price 9
00 43 13 Bid Bond 10
00 45 11 Bidders Prequalification’s 11
00 45 12 Prequalification Statement 12
00 45 13 Bidder Prequalification Application 13
00 45 26 Contractor Compliance with Workers' Compensation Law 14
00 45 40 Minority Business Enterprise Goal 15
00 52 43 Agreement 16
00 61 25 Certificate of Insurance 17
00 62 13 Performance Bond 18
00 62 14 Payment Bond 19
00 62 19 Maintenance Bond 20
00 72 00 General Conditions 21
00 73 00 Supplementary Conditions 22
00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded 23
Projects 24
25
Division 01 - General Requirements 26
01 11 00 Summary of Work 27
01 25 00 Substitution Procedures 28
01 31 19 Preconstruction Meeting 29
01 31 20 Project Meetings 30
01 32 16 Construction Progress Schedule 31
01 32 33 Preconstruction Video 32
01 33 00 Submittals 33
01 35 13 Special Project Procedures 34
01 45 23 Testing and Inspection Services 35
01 50 00 Temporary Facilities and Controls 36
01 55 26 Street Use Permit and Modifications to Traffic Control 37
01 57 13 Storm Water Pollution Prevention Plan 38
01 58 13 Temporary Project Signage 39
01 60 00 Product Requirements 40
01 66 00 Product Storage and Handling Requirements 41
01 70 00 Mobilization and Remobilization 42
01 71 23 Construction Staking 43
01 74 23 Cleaning 44
01 77 19 Closeout Requirements 45
01 78 23 Operation and Maintenance Data 46
01 78 39 Project Record Documents 47
48
00 00 10- 2
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 2 of 5
CITY OF FORT WORTH North City Addition Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049
Revised September 1, 2015
Technical Specifications which have been modified by the Engineer specifically for this 1
Project; hard copies are included in the Project’s Contract Documents 2
3
Division 02 - Existing Conditions 4
NONE 5
6
Division 03 - Concrete 7
NONE 8
9
Division 26 - Electrical 10
NONE 11
12
Division 31 - Earthwork 13
NONE 14
15
Division 32 - Exterior Improvements 16
NONE 17
18
Division 33 - Utilities 19
NONE 20
21
Division 34 - Transportation 22
NONE 23
24
25
Technical Specifications listed below are included for this Project by reference and can be 26
viewed/downloaded from the City’s Buzzsaw site at: 27
28
htps://projectpoint.buzzsaw.com/client/fortworthgov/Resources/02%20-29
%20Construction%20Documents/Specifications 30
31
32
Division 02 - Existing Conditions 33
02 41 13 Selective Site Demolition 34
02 41 14 Utility Removal/Abandonment 35
02 41 15 Paving Removal 36
37
Division 03 - Concrete 38
03 30 00 Cast-In-Place Concrete 39
03 34 13 Controlled Low Strength Material (CLSM) 40
03 34 16 Concrete Base Material for Trench Repair 41
03 80 00 Modifications to Existing Concrete Structures 42
43
Division 26 - Electrical 44
26 05 00 Common Work Results for Electrical 45
26 05 10 Demolition for Electrical Systems 46
26 05 33 Raceway and Boxes for Electrical Systems 47
26 05 43 Underground Ducts and Raceways for Electrical Systems 48
26 05 50 Communications Multi-Duct Conduit 49
50
00 00 10- 3
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 3 of 5
CITY OF FORT WORTH North City Addition Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049
Revised September 1, 2015
Division 31 - Earthwork 1
31 10 00 Site Clearing 2
31 23 16 Unclassified Excavation 3
31 23 23 Borrow 4
31 24 00 Embankments 5
31 25 00 Erosion and Sediment Control 6
31 36 00 Gabions 7
31 37 00 Riprap 8
9
Division 32 - Exterior Improvements 10
32 01 17 Permanent Asphalt Paving Repair 11
32 01 18 Temporary Asphalt Paving Repair 12
32 01 29 Concrete Paving Repair 13
32 11 23 Flexible Base Courses 14
32 11 29 Lime Treated Base Courses 15
32 11 33 Cement Treated Base Courses 16
32 11 37 Liquid Treated Soil Stabilizer 17
32 12 16 Asphalt Paving 18
32 12 73 Asphalt Paving Crack Sealants 19
32 13 13 Concrete Paving 20
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 21
32 13 73 Concrete Paving Joint Sealants 22
32 14 16 Brick Unit Paving 23
32 16 13 Concrete Curb and Gutters and Valley Gutters 24
32 17 23 Pavement Markings 25
32 17 25 Curb Address Painting 26
32 31 13 Chain Link Fences and Gates 27
32 31 26 Wire Fences and Gates 28
32 31 29 Wood Fences and Gates 29
32 32 13 Cast-in-Place Concrete Retaining Walls 30
32 91 19 Topsoil Placement and Finishing of Parkways 31
32 92 13 Hydro-Mulching, Seeding, and Sodding 32
32 93 43 Trees and Shrubs 33
34
Division 33 - Utilities 35
33 01 30 Sewer and Manhole Testing 36
33 01 31 Closed Circuit Television (CCTV) Inspection 37
33 03 10 Bypass Pumping of Existing Sewer Systems 38
33 04 10 Joint Bonding and Electrical Isolation 39
33 04 11 Corrosion Control Test Stations 40
33 04 12 Magnesium Anode Cathodic Protection System 41
33 04 30 Temporary Water Services 42
33 04 40 Cleaning and Acceptance Testing of Water Mains 43
33 04 50 Cleaning of Sewer Mains 44
33 05 10 Utility Trench Excavation, Embedment, and Backfill 45
33 05 12 Water Line Lowering 46
33 05 13 Frame, Cover and Grade Rings 47
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 48
33 05 16 Concrete Water Vaults 49
33 05 17 Concrete Collars 50
00 00 10- 4
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 4 of 5
CITY OF FORT WORTH North City Addition Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049
Revised September 1, 2015
33 05 20 Auger Boring 1
33 05 21 Tunnel Liner Plate 2
33 05 22 Steel Casing Pipe 3
33 05 23 Hand Tunneling 4
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 5
33 05 26 Utility Markers/Locators 6
33 05 30 Exploratory Excavation for Existing Utilities 7
33 11 05 Bolts, Nuts, and Gaskets 8
33 11 10 Ductile Iron Pipe 9
33 11 11 Ductile Iron Fittings 10
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11
33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12
33 11 14 Buried Steel Pipe and Fittings 13
33 11 15 Pre-stressed Concrete Cylinder Pipe 14
33 12 10 Water Services 1-inch to 2-inch 15
33 12 11 Large Water Meters 16
33 12 20 Resilient Seated Gate Valve 17
33 12 21 AWWA Rubber-Seated Butterfly Valves 18
33 12 25 Connection to Existing Water Mains 19
33 12 30 Combination Air Valve Assemblies for Potable Water Systems 20
33 12 40 Dry-Barrel Fire Hydrants 21
33 12 50 Water Sample Stations 22
33 12 60 Blow-off Valves 23
33 31 12 Cured in Place Pipe (CIPP) 24
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 25
33 31 15 HDPE Pipe For Sanitary Sewers (Gravity and Force Mains) 26
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 27
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 28
33 31 22 Sanitary Sewer Slip Lining 29
33 31 23 Sanitary Sewer Pipe Enlargement 30
33 31 50 Sanitary Sewer Service Connections and Service Line 31
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 32
33 39 10 Cast-in-Place Concrete Manholes 33
33 39 20 Precast Concrete Manholes 34
33 39 30 Fiberglass Manholes 35
33 39 40 Wastewater Access Chamber (WAC) 36
33 39 60 Epoxy Liners for Sanitary Sewer Structures 37
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 38
33 41 11 HDPE Storm Sewer Pipe 39
33 46 00 Sub drainage 40
33 46 01 Slotted Storm Drains 41
33 46 02 Trench Drains 42
33 49 10 Cast-in-Place Manholes and Junction Boxes 43
33 49 20 Curb and Drop Inlets 44
33 49 40 Storm Drainage Headwalls and Wingwalls 45
46
Division 34 – Transportation 47
34 41 10 Traffic Signals 48
34 41 10.01 Attachment A – Controller Cabinet 49
34 41 10.02 Attachment B – Controller Specification 50
00 00 10- 5
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 5 of 5
CITY OF FORT WORTH North City Addition Phase 1
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102049
Revised September 1, 2015
34 41 10.03 Attachment C – Software Specification 1
34 41 11 Temporary Traffic Signals 2
34 41 13 Removing Traffic Signals 3
34 41 15 Rectangular Rapid Flashing Beacon 4
34 41 16 Pedestrian Hybrid Signal 5
34 41 20 Roadway Illumination Assemblies 6
34 41 20.01 Arterial LED Roadway Luminaires 7
34 41 20.02 Freeway LED Roadway Luminaires 8
34 41 20.03 Residential LED Roadway Luminaires 9
34 41 30 Aluminum Signs 10
34 41 50 Single-Mode Fiber Optic Cable 11
34 71 13 Traffic Control 12
13
Appendix 14
GC-4.01 Availability of Lands 15
GC-4.02 Subsurface and Physical Conditions 16
GC-4.04 Underground Facilities 17
GC-4.06 Hazardous Environmental Condition at Site 18
GC-6.06.D Minority and Women Owned Business Enterprise Compliance 19
GC-6.07 Wage Rates 20
GC-6.09 Permits and Utilities 21
GC-6.24 Nondiscrimination 22
GR-01 60 00 Product Requirements 23
24
END OF SECTION 25
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
004243
DAP -RID PROPOSAL
Page I of
Bidder's Application
Project Item Information
Bidder's Proposal
Bid'is'Item
Description
Specification Section
Unit of
Bid
Unit Price
Bid Value
No.
No.
Measure
Quantity
UNIT
I:
WATER
IMPROVEMENTS
1
3312.0001
Fire Hydrant Assembly
331240
EA
6
__ $4,463.00
11
$26,778_00
2 --
3312.0117
--
_ Connect toEx 4 12" Water -Mad n
-
33
- --
12
25
EA
2
$3,235.50
$6,471.00
3
3312.3105
Cut In Tee & Gate Valve
331220
EA
1
247.00
$5 247.00
_
4
3305.1102
_12"
16" Steel Encasement not Open Cut
33
12
_
25 _ _ _
LF
69
_$5
_ $175.00
_
$12 075.00
5
9999.0004
Bore for 12" Water Pipe
33
12
_
25
LF
69
$175.00
._ $12,075.00
6
3312.3005
12" Gate Valve -
33
12
20
EA
12
_. $2,407.00
- $28,884.00
...__..—
7
3312.3003
- -- -----_. ----
8" Gale Valve
33
1-2-2-0
EA
3
$1,460.00
-, $4,380A0
___..
8
3312.3002
_ . _-.
_-
._... -
6" Gate Valve
_..
33
33
1220
EA _
6
,. _
_ $1,140.00
$61840.00
9
3312.2201
_
2" Water Service
33
12
20
EA
3
$1,651.00
$4 953.00
10
3312.2103
1 1/2" Water Service
33
12
20
EA
3
$2 158
00
$6,474.00
11
3311.0441
12 Water Pipe
33
11
10s 33 11 12
LF
2818
$43.12
$121 512.00
12
3311.0241
8" Water Pipe
33
11
10, 33 11 12
LF
45
-
$35.00
$11575.00
13 -
3311.0141
6" Water Pipe
33
11
10, 33 11 12
LF
108
$29.00
$3 132.00
14
3305.0109
Trench Safety
33 05
10
LF
_ 2971
$1.00
$2,971.00
15
3311.0001
Ductile Iron Water Fittings w/Restraint
33
11
105 33 11 12
TON
2.5
$8,030.80
$20,077.00
16
17
18
19.__-
20._.__
21
CITY OP PORT WORTH
STANDARD CONSTRUCTION SPECfPICATION DOCUMENTS -DEVELOPER A\YARDED PROTECTS
Pam, Version September 1, 2015 2000G- 004243_RiJ Proposal DAP ReviuJ 04.16.20
004243
DAP -HID PROPOSAL
Page 2 or
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
Description
SpeciOcation Section
Unitof
Bid
Unit Price
Bid Value
No.
No.
Measure
Quantity
UNIT II: SANITARY SEWER
IMPROVEMENTS
1
3331.4115 8" Sewer Pipe
33 11 10,33 31 123
LF
30
$36.00
_ _$1,080.00
_ __
2
----
333L4119 8" DIP Sewer Plpe
--- ---
3311 10
LF
73
$62.00
$4,526 00
_
3
3339.1001. 4 Manhole
32 39 -M 33 39 20
EA
2
00
_
$12,052.00
3339.100_4 4' Sha_Ilow_Manhole
33 39 10, 33 39 20
EA
1
_$6,026
$6,026.00
,.
$69026.00
_ _4 _
5
3339.1101- 5'Manhole --
33 39 10, 33 39 20
EA
1
_ _ _
$9,814.00
$9,814.00
6
9999.0001 to Ex. Mild w/external drop
00 00 00
EA
1
$8,250.00
_ $8 250,00
__ _
7
_Connect
9999.0002 Connect totx7mfi
0o o0 00
EA
1
$3,690.00
$3,690.00
8
3305.0113 Trench Water Stop -
330515
EA
2
$1,595.00
$3,190.00
_
9
3339.0001Epoxy Manhole Liner
333960
VF
65
$482.22
$31,344.30
10
-_. _...---3
3301.0_101 Manhole Vacuum Testing--- _
- --__.
33 01 30
EA
4
_..
$100.00
_. $400.00
_
11
35.0 ii concrete Encasement
30
33 06 10
CY
2
$54.00
$108.00
12
3301.0002Posl-Giant Inspection
3301 31
-
LF
103
$1.00
$103.00
13
3305.0109 Trench Safety
33 05 10
LF
103
$1.00
$103.00
14
15
16
17
18
19
20
21
22
23
24
2-5
26
27
28
29
31
32
33
34
35
...... ...... __.. _..
... ____
_..
36 __
37
39
40
41
42
43
44
45
46
47___.
CITY OF FORT
WORTH
STANDARD CONSTRUCTION
SPECIFICATION DOCUMENTS -DEVELOPER AWARDED PROJECTS
Foun Version
Seplember 1, 2015
20006
- 0042 43_Hid Poapool
DAP Revised 04.16.20
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
004243
DAP-HIDPROPOSAL
Page 3 of
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
Description
Specification Section
Unit of
Bid
Unit Price
Bid Value
No.
No.
Measure
Quantity
TOTAL UNIT It: SANITARY SEWER
IMPROVEMENTc
$80,686.30
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIPICATION DOCUMENTS -DEVELOPER AIVARDF,D PROJECTS
Porm Version September I, 2015 20006- 004243 Hid Proposel_DAP Revised 04.16.20
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
004243
DAP-BIDPROPOSAL
Pap 4 of 6
Bidder's Application
Project
Item Infomration
Bidder's Proposal
Bidlist Item
Description
Specification Section
Unit of
Bid
Unit Price
Bid Value
No.
No.
Measure
Quantity
UNIT III:. DRAINAGE
IMPROVEMENTS
10
LF
343
_ $148.00
_ $50,764,.,00
1
3341.0_402
42" RCP, Class III
3341
2
_
3341.0302
30" RCP, Class III
_
33 41
16 -
_
LF
_ _
64
$96.00
_
$6144.00
3
9-13T01—
Connect to Ex. Storm
00 00
EA
1
$2 263,00
3137.0102
Rock Rip Rap - Dry
�1100
31 3700
SY
40
,$2,263.00
$108.00
$4,320.00
_ _4
5
_
3349.0002
_
5' Storm Junction Box
33 49
10
EA
3
_ _
U1723.00
_
$203169,00
6
3349.1009
42" Flared Headwall, One
Pipe -
33 49
40
EA
1
_ $5 623,00
$5,623.00
7
3305.6109
Trench Safety
33 05
10 1
LF
407
$1.00
_ $407.00
9
16
11
12
13
14
15
16
17
18
19
26
21
22
23
24
25
26
27
28
29
36
31
32
33
34
35
36
37
.._
38
40
41
42
43
_...
44
45
TOTAL
UNIT
III: DRAINAGE
IMPROVEMENT
$8900.001
CITY OP PORT \NORTH
STANDARD CONSTRUCTION SPECIPICATION DOCUMENTS - DEVELOPER A\YARDED PROJECTS
Porm Version September 1, 2015
20006- 00 42 43 Bid Proposal_DAP Revised 04.16.20
SECTION 00 42 43
Developer Awarded Projects - PROPOSAL FORM
UNIT PRICE BID
004243
In PROPOSAL
PROPOSAL
Page 5 of
Bidder's Application
Project Item Information
Bidder's Proposal
Bidlist Item
Description
Specification Section
Unit of
Bid
Unit Price
Bid Value
No.
No.
Measure
Quantity
UNIT
IV: PAVING
IMPROVEMENTS
1
0241.1000
Remove Conc. Pvmt.
024115
SY
265
$27.00
$7,155.00
2
0241.0100
Remove Conc. Sidewalk
0241
_
13
SY
..
100
_
$10,00
$1,000.00
3
3213
0301
4 Conc. Sidewalk (w Wide)
32
13 20
SF
100
$13,20
$1,320.00
4
_
3471.00o1
TraNic Control I
--
34
--- -
71 13
_
MO
2
---
--
$3,000,00
__
$6,000.00
_ _
5
_ _
3201,0616
Conc. Pvmt. Repair
-
32
1129
SY _
_ 265
..$72
00
._
$19
080.00
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
_
35-
36
37
38
39
40
41
43
4-4
_.
45
I
TOTAL
UNIT
IV: PAVING
IMPROV
EMENT.Sli
$3055.00
CITY OP FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS
rams Version September I, 2015
20006- 004243 Bid Pmposal_DAP Revised 04.16.20
UNIT PRICE BID
SECTION vu 42 4a
Developer Awarded Projects - PROPOSAL FORM
Pr Ject Item information
004243
DAP -HID PROPOSAL
PagetioT6
Bidder's Application
Bidde>'s Proposal
IBidlNo.
Item) Description I Specification No. Section I Measure I Quantity Bid I Unit Price ( Bid Value
N
UNIT I: WATER IMPROVEMENTS
UNIT II: SANITARY SEWER IMPROVEMENTS
UNIT III: DRAINAGE IMPROVEMENTS
UNIT IV: PAVING IMPROVEMENTS
This Bid is submitted by the entity named below:
BIDDER:
Wright Construction Company
601NP, Wall St
Grapevine, TX 76051
Contractor agrees to complete WORK [or FINAL ACCEPTANCE within
CONTRACT comroenees to run as provided in the General Conditions.
Total Construction Bid
BY:
TITLE:
DATE: sj /;zq iU
END OF SECTION
59 . working drys after the date when the
CITY OP FORT WORTH
STANDARD CONSTRUCTION SPECIPICATION DOCUMENTS - DHVHLOPER AWARDGD PROIF.CTS
Pamr Version September I, 2015
20006- 004243_Hid Proposal_DAP Revised 04.16.20
00 45 11 - 1
BIDDERS PREQUALIFICATIONS
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised April 2, 2014
Landmark Quebec Addition
102418
SECTION 00 45 11
BIDDERS PREQUALIFICATIONS
1. Summary. All contractors are required to be prequalified by the City prior to submitting
bids. To be eligible to bid the contractor must submit Section 00 45 12, Prequalification
Statement for the work type(s) listed with their Bid. Any contractor or subcontractor who is
not prequalified for the work type(s) listed must submit Section 00 45 13, Bidder
Prequalification Application in accordance with the requirements below.
The prequalification process will establish a bid limit based on a technical evaluation and
financial analysis of the contractor. The information must be submitted seven (7) days prior
to the date of the opening of bids. For example, a contractor wishing to submit bids on
projects to be opened on the 7th of April must file the information by the 31st day of March
in order to bid on these projects. In order to expedite and facilitate the approval of a Bidder’s
Prequalification Application, the following must accompany the submission.
a. A complete set of audited or reviewed financial statements.
(1) Classified Balance Sheet
(2) Income Statement
(3) Statement of Cash Flows
(4) Statement of Retained Earnings
(5) Notes to the Financial Statements, if any
b. A certified copy of the firm’s organizational documents (Corporate Charter, Articles
of Incorporation, Articles of Organization, Certificate of Formation, LLC
Regulations, Certificate of Limited Partnership Agreement).
c. A completed Bidder Prequalification Application.
(1) The firm’s Texas Taxpayer Identification Number as issued by the Texas
Comptroller of Public Accounts. To obtain a Texas Taxpayer Identification
number visit the Texas Comptroller of Public Accounts online at the
following web address www.window.state.tx.us/taxpermit/ and fill out the
application to apply for your Texas tax ID.
(2) The firm’s e-mail address and fax number.
(3) The firm’s DUNS number as issued by Dun & Bradstreet. This number
is used by the City for required reporting on Federal Aid projects. The DUNS
number may be obtained at www.dnb.com.
d. Resumes reflecting the construction experience of the principles of the firm for firms
submitting their initial prequalification. These resumes should include the size and
scope of the work performed.
e. Other information as requested by the City.
2. Prequalification Requirements
a. Financial Statements. Financial statement submission must be provided in
accordance with the following:
(1) The City requires that the original Financial Statement or a certified copy
be submitted for consideration.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised April 2, 2014
Landmark Quebec Addition
102418
00 45 11 - 2
BIDDERS PREQUALIFICATIONS
Page 2 of 3
(2) To be satisfactory, the financial statements must be audited or reviewed
by an independent, certified public accounting firm registered and in
good standing in any state. Current Texas statues also require that
accounting firms performing audits or reviews on business entities within
the State of Texas be properly licensed or registered with the Texas State
Board of Public Accountancy.
(3) The accounting firm should state in the audit report or review whether
the contractor is an individual, corporation, or limited liability company.
(4) Financial Statements must be presented in U.S. dollars at the current rate
of exchange of the Balance Sheet date.
(5) The City will not recognize any certified public accountant as
independent who is not, in fact, independent.
(6) The accountant’s opinion on the financial statements of the contracting
company should state that the audit or review has been conducted in
accordance with auditing standards generally accepted in the United
States of America. This must be stated in the accounting firm’s opinion.
It should: (1) express an unqualified opinion, or (2) express a qualified
opinion on the statements taken as a whole.
(7) The City reserves the right to require a new statement at any time.
(8) The financial statement must be prepared as of the last day of any month,
not more than one year old and must be on file with the City 16 months
thereafter, in accordance with Paragraph 1.
(9) The City will determine a contractor’s bidding capacity for the purposes
of awarding contracts. Bidding capacity is determined by multiplying the
positive net working capital (working capital = current assets – current
liabilities) by a factor of 10. Only those statements reflecting a positive
net working capital position will be considered satisfactory for
prequalification purposes.
(10) In the case that a bidding date falls within the time a new financial
statement is being prepared, the previous statement shall be updated with
proper verification.
b. Bidder Prequalification Application. A Bidder Prequalification Application must be
submitted along with audited or reviewed financial statements by firms wishing to be
eligible to bid on all classes of construction and maintenance projects. Incomplete
Applications will be rejected.
(1) In those schedules where there is nothing to report, the notation of
“None” or “N/A” should be inserted.
(2) A minimum of five (5) references of related work must be provided.
(3) Submission of an equipment schedule which indicates equipment under
the control of the Contractor and which is related to the type of work for
which the Contactor is seeking prequalification. The schedule must
include the manufacturer, model and general common description of
each piece of equipment. Abbreviations or means of describing
equipment other than provided above will not be accepted.
3. Eligibility to Bid
a. The City shall be the sole judge as to a contractor’s prequalification.
b. The City may reject, suspend, or modify any prequalification for failure by the
contractor to demonstrate acceptable financial ability or performance.
c. The City will issue a letter as to the status of the prequalification approval.
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS
Revised April 2, 2014
Landmark Quebec Addition
102418
00 45 11 - 3
BIDDERS PREQUALIFICATIONS
Page 3 of 3
d. If a contractor has a valid prequalification letter, the contractor will be eligible to bid
the prequalified work types until the expiration date stated in the letter.
END OF SECTION
00 45 12
OAP MQUALIFICATION STATEMENT
Page I or t
SECTION 00 4512
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Major We
Tyne" box provide the complete major work We and actual description as provided by the Watei
Department for water and sewer and TPW for paying,,
Major Work Type
Contractor/Subcontractor Company Name
Prequalification
Expiration Date
Water, Sewer Paving &
Wright Construction Co Inc.
Drainage Improvements to
Serve Lonestar Business Park
Water Dist. - 12" Din. & Smaller
Wright Construction Co., Inc.
4/30/2021
Sewer Collection System - 8" Din. & Son
[let Wright Construction Co., Inc.
4/30/2021
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
BIDDER:
Wright Construction Co Inc. BY: David retry
601 W. Wall Street
Grapevine, Texas 76051
(Signature)
TITLE: (fact. f��eSic2ary j
DATE: (1 4 f a o
END OF SECTION
CITY OF FOflT WORTH
STANDARD CONSTRUCTION PREQUALIFICATIONSTRTEMENT— DEVELOPER AWARDED PROTECTS
004512_Prequalificatlon Statement 2015 DAP
Form Version September 1, 2015
004526-1
CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
Page 1 of 1
1 SECTION 00 45 26
2 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW
3 Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it
4 provides worker's compensation insurance coverage for all of its employees employed on City
5 Project No.102418, Contractor further certifies that, pursuant to Texas Labor Code, Section
6 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with
7 worker's compensation coverage.
9 CONTRACTOR:
10 Wright Construction Co Inc. By:
11 (Please Print) �
12
13 601 W. Wall Street Signature: ....... � _->. — '
14 Address
15
16 Grapevine, Texas 76051 Title: vi C-f pre }" d ems% r
17 City/State/Zip (Please Print)
18
19
20 THE STATE OF TEXAS §
21
22 COUNTY OF TARRANT §
23
24 BEFORE ME, the.undersigned authority, on this day personally appeared
known to me to be the person whose name is
26 subscribed to the foregoing instrument, and acknowledged to me that he/she executed the
27 same as the act and deed of i, i� �7f - , I for the purposes and
28 consideration therein expressed and in the capacity therein stated.
29
30 GIVEN UNDER MY HAND AND SEAL OF OFFICE this ' day of
32
33
34 iis���``°�� Deb Donaldson j
_;� Notary Public, State of Texas/j,A
35 :� Comm. Expires0l/24/2021 Notary Public in and for the State of Texas
9�0:� Notary lD 11970986
36 END OF SECTION
CITY OF FORT WORTH Landmark Quebec Addition
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS 202428
Revised April 2, 2014
00 52 43 - 1
Developer Awarded Project Agreement
Page 1 of 4
CITY OF FORT WORTH Landmark Quebec Addition
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS 102418
Revised June 16, 2016
SECTION 00 52 43 1
AGREEMENT 2
3
THIS AGREEMENT, authorized on _May 21, 2020_is made by and between the Developer, 4
(LONESTAR COMMERCE CENTER I, LLC), authorized to do business in Texas (“Developer”) , and 5
__The Conlan Company_____, authorized to do business in Texas, acting by and through its duly 6
authorized representative, (“Contractor”). 7
Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree 8
as follows: 9
Article 1. WORK 10
Contractor shall complete all Work as specified or indicated in the Contract Documents for the 11
Project identified herein. 12
Article 2. PROJECT 13
The project for which the Work under the Contract Documents may be the whole or only a part 14
is generally described as follows: 15
Lonestar Business Park 16
102418 17
Article 3. CONTRACT TIME 18
3.1 Time is of the essence. 19
All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 20
Documents are of the essence to this Contract. 21
3.2 Final Acceptance. 22
The Work will be complete for Final Acceptance within _76__ calendar days after the date 23
when the Contract Time commences to run as provided in Paragraph 12.04 of the 24
Standard City Conditions of the Construction Contract for Developer Awarded Projects. 25
3.3 Liquidated damages 26
Contractor recognizes that time is of the essence of this Agreement and that Developer 27
will suffer financial loss if the Work is not completed within the times specified in 28
Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 29
of the Standard City Conditions of the Construction Contract for Developer Awarded 30
Projects. The Contractor also recognizes the delays, expense and difficulties involved in 31
proving in a legal proceeding the actual loss suffered by the Developer if the Work is not 32
completed on time. Accordingly, instead of requiring any such proof , Contractor agrees 33
that as liquidated damages for delay (but not as a penalty), Contractor shall pay 34
Developer _Five Hundred _ Dollars ($_500.00 ) for each day that expires after the time 35
specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of 36
Acceptance. 37
Article 4. CONTRACT PRICE 38
Developer agrees to pay Contractor for performance of the Work in accordance with the 39
Contract Documents an amount in current funds of _ Four Hundred Sixty Eight Thousand and 40
Three hundred Seventy Five Dollars ($_468,375.30_). 41
Article 5. CONTRACT DOCUMENTS 42
5.1 CONTENTS: 43
A. The Contract Documents which comprise the entire agreement between Developer 44
and Contractor concerning the Work consist of the following: 45
005243-2
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
Developer Awarded Project Agreement
Page 2 of 4
1.
This Agreement.
2.
Attachments to this Agreement:
a. Bid Form (As provided by Developer)
1) Proposal Farm (DAP Version)
2) Prequalification Statement
3) State and Federal documents (project specific)
b. Insurance ACORD Form(s)
c. Payment Bond (DAP Version)-
d. Performance Bond (DAP Version)
e. Maintenance Bond (DAP Version)
f. Power of Attorney for the Bonds
g. Worker's Compensation Affidavit
h. MBE and/or SBE Commitment Form (If required)
3.
Standard City General Conditions of the Construction Contract
for Developer
Awarded Projects.
4.
Supplementary Conditions.
5.
Specifications specifically made a part of the Contract Documents
by attachment
or, if not attached, as incorporated by reference and described in
the Table of
Contents of the Project's Contract Documents.
6.
Drawings,
7.
Addenda,
8.
Documentation submitted by Contractor prior to Notice of Award.
9.
The following which may be delivered or issued after the Effective Date of the
Agreement and, if issued, become an incorporated part of
the Contract
Documents:
a. Notice to Proceed.
b. Field Orders.
c. Chadge Orders.
d. Letter of Final Acceptance.
CITY OF FORT WORTH Landmark quebec Addition
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS— DEVELOPER AWARDED PROJECTS 102418
Revised June 16, 2016
006243-3
Developer Awarded Project Agreement
Page 3 of 4
77
Article 6. INDEMNIFICATION
78
6.1
Contractor covenants and agrees to indemnify, hold harmless and defend, at its own
79
expense, the city, its officers, servants and employees, from and against any and all
80
claims arising out of, or alleged to arise out of, the work and services to be performed by
81
the contractor, its officers, agents, employees, subcontractors, licenses or invitees under
82
this contract. This indemnification provision is specifically intended to operate and be
83
effective even if it is alleged or proven that all or some of the damages being sought
84
were caused in whole or in part, by any act, omission or negligence of the city. This
85
indemnity provision is intended to include, without limitation, indemnity for costs,
86
expenses and legal fees incurred by the city in defending against such claims and causes
87
of actions.
88
89
6.2
Contractor covenants and agrees to indemnify and hold harmless, at its own expense,
90
the city, its officers, servants and employees, from and against any and all loss, damage
91
or destruction of property of the city, arising out of, or alleged to arise out of, the work
92
and services to be performed by the contractor, its officers, agents, employees,
93
subcontractors, licensees or invitees under this contract. This indemnification provision
94
is specifically intended to operate and be effective even if it is alleged or proven that all
95
or some of the damages being sought were caused, in whole or in part, by any act,
96
omission or negligence of the city.
97
98
Article 7. MISCELLANEOUS
99
7A
Terms,
100
Terms used in this Agreement are defined in Article 1 of the Standard City Conditions of
101
the Construction Contract for Developer Awarded Projects.
102
7.2
Assignment of Contract.
103
This Agreement, including all of the Contract Documents may not be assigned by the
104
Contractor without the advanced' express written consent of the Developer.
105
7.3
Successors and Assigns.
106
Developer and Contractor each binds itself, its partners, successors, assigns and legal
107
representatives to the other party hereto, in respect to all covenants, agreements and
108
obligations contained in the Contract Documents,
109
7.4
Severability,
110
Any provision or part of the Contract Documents held to be unconstitutional, void or
111
unenforceable by a court of competent jurisdiction shall be deemed stricken, and all
112
remaining provisions shall continue to be valid and binding upon DEVELOPER and
113
CONTRACTOR,
114
7.5
Governing Law and Venue.
115
This Agreement, including all of the Contract Documents is performable in the State of
116
Texas. Venue shall be Tarrant County, Texas, or the United States District Court for the
117
Northern District of Texas, Fort Worth Division,
118
119
7.6
Authority to Sign.
120
Contractor shall attach evidence of authority to sign Agreement, if other than duly
121
authorized signatory of the Contractor.
CITY OF FORT WORTH Landmark Que6ecAddi[ion
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS 102415
Revised tune 16, 2016
006243-4
Developer Awarded Project Agreement
Page 4 of 4
122
123 IN WITNESS WHEREOF, Developer and Contractor have executed this Agreement in multiple
124 counterparts.
125
126 This Agreement is effective as of the last date signed by the Parties ("Effective Date").
127
Contractor:
The Conlan Company
Company Name:
By,
Ignature)
Benjamin Bratcher
(Printed Name)
Title: Senior Project Manager
Address:
1501 LB1 Freeway, Suite 550
City/State/Zip:
Farmers Branch, Texas 75234
Date
Developer:
Lonestar Commerce Center 1, LLC
Company name:
By. 214
r .__-M
f (Signat re)
r
Curt Hefner
(Printed Name)
Address:
750 N. Saint Paul Street, Suite 1350
City/State/Zip:
Dallas. Texas 75201
r
Date
CITY OF FORT W ORTH Landmark Quebec Additlan
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS —DEVELOPER AWARDED PROJECTS 102418
Revised June 16, 2016
00 62 13 - 1
PERFORMANCE BOND
Page 1 of 2
CITY OF FORT WORTH Landmark Quebec Addition
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS 102418
Revised January 31, 2012
SECTION 00 62 13 1
PERFORMANCE BOND 2
3
THE STATE OF TEXAS § BOND NUMBER: 30090314 4
§ KNOW ALL BY THESE PRESENTS: 5
COUNTY OF TARRANT § 6
7
That we, The Conlan Company, known as “Principal” herein and Continental Casualty 8
Company, a corporate surety(sureties, if more than one) duly authorized to do business in the 9
State of Texas, known as “Surety” herein (whether one or more), are held and firmly bound unto 10
the Developer, Lonestar Commerce Center, LLC, 750 North Saint Paul Street, Dallas, TX 75201, 11
authorized to do business in Texas (“Developer”) and the City of Fort Worth, a Texas municipal 12
corporation (“City”), in the penal sum of Four-Hundred Sixty – Eight Thousand Three-Hundred 13
and Seventy-Five Dollars and Thirty cents ($468,375.30), lawful money of the United States, to 14
be paid in Fort Worth, Tarrant County, Texas for the payment of which sum well and truly to be 15
made jointly unto the Developer and the City as dual obligees, we bind ourselves, our heirs, 16
executors, administrators, successors and assigns, jointly and severally, firmly by these presents. 17
WHEREAS, Developer and City have entered into an Agreement for the construction of 18
community facilities in the City of Fort Worth by and through a Community Facilities Agreement, 19
CFA Number CFA20-0032 and 20
WHEREAS, the Principal has entered into a certain written contract with the Developer awarded 21
the 21 day of May, 2020, which Contract is hereby referred to and made a part hereof for all 22
purposes as if fully set forth herein, to furnish all materials, equipment labor and other 23
accessories defined by law, in the prosecution of the Work, including any Change Orders, as 24
provided for in said Contract designated as Water and Sanitary Sewer Improvements to Serve 25
Landmark Quebec Addition. 26
NOW, THEREFORE, the condition of this obligation is such that if the said Principal shall 27
faithfully perform it obligations under the Contract and shall in all respects duly and faithfully 28
perform the Work, including Change Orders, under the Contract, according to the plans, 29
specifications, and contract documents therein referred to, and as well during any period of 30
extension of the Contract that may be granted on the part of the Developer and/or City, then 31
this obligation shall be and become null and void, otherwise to remain in full force and effect. 32
PROVIDED FURTHER, that if any legal action be filed on this Bond, venue shall lie in 33
Tarrant County, Texas or the United States District Court for the Northern District of Texas, Fort 34
Worth Division. 35
This bond is made and executed in compliance with the provisions of Chapter 2253 of 36
the Texas Government Code, as amended, and all liabilities on this bond shall be determined in 37
accordance with the provisions of said statue. 38
00 62 13 - 2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
PERFORMANCE BOND
Page 2 of 2
IN WITNESS WHEREOF, the Principal and the Surety have SIGNED and SEALED this
instrument by duly authorized agents and officers on this the day of
20
PRINCIPAL: The Conlan Company
a P"k�_
Nitness as to Principal
Nitn s as to Surety
Jam s H. Vaughan, V/
BY:A_/�.
Signature
Name and Title .�`�•.•'`••"'•:�'0y''.
��.• °oaPaN ?�
Address: 1800 Parkway Place, Suitd1010
Marietta, Georgia 30067_ SEAL
SURETY: �`.,� • •.•�� ••,. ��.
Continental Casualtv Com M07
BY:
Signature
Felisa H. Vaughan, Attorney -in -Fact
Name and Title
Address: McGriff Insurance Services, Inc.
3100 Royal Blvd. South
Alpharetta, GA 30022
Telephone Number: (770) 664-6818
*Note: If signed by an officer of the Surety Company, there must be on file a certified extract
from the by-laws showing that this person has authority to sign such obligation. If
Surety's physical address is different from its mailing address, both must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Landmark Quebec Addition
102418
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY -IN -FACT
Know All Men By These Presents, That Continental Casually Company, an Illinois insurance company, National Fire Insurance Company of
Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company (herein called
"the CNA Companies"), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois,
and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint
Travis G Huffines, Brian E Madden, Deborah B Sasser, Brittany L Triplett, Fedsa H Vaughan, Individually
of Alpharetta, GA, their true and ]awful Attomey(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their
behalf bonds, undertakings and other obligatory instruments of similar nature
- In Unlimited Amounts -
and to bind them [hereby as fully and to the same extent as if such instruments were slgned by a duly authorized officer of their insurance companies and
all the acts of said Attorney, pursuant to the authority hereby given Is hereby ratified and confirmed.
This Power of Attorney is made and ezecutedpursuant [o and by authority of the By -Law and Reso]utions, printed on the reverse hereof, duly
adopted, as indicated, by the Boards of Directors of the insurance companies.
In Witness Whereof, the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto
affixed on this 30th day of March, 2020.
�6A9Uq(rY �� INSURgyc `oMvpPr o<yF,
OOPPOPATE L � `PCOePa
i T 1t _�W�ry iuisoi i.
R� SEAL Y
Continental Casualty Company
National Fire Insurance Company of Hartford
American Ca Ity Company of Re ding, Pennsylvania
Paul T. Bruflat'Kee President
State of South Dakota, County of Minnehaha, as:
On this 30th day of March, 2020, before me personally came Paul T. Bruflat to me known, who, being by me duly sworn, did depose and say: [hat
he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company,
National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a
Pennsylvania insurance company described in and which executed the above instrument; that he knows the seals of said insurance companies; that the.
sealsaffixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said
insurance companies and that he signed his. name thereto pursuant to like authority, and acknowledges same to be the act and deed of said insurance
companies.
�i, J. MOHR �L! • IIII ��
My Commission Expires June 23, 2021 J. Mohr v Notary Public
CERTIFICATE
I, D. Johnson, Assistant Secretary of Continental Casualty any, an Illinois insurance company, National Fire Insurance Company of Hartford,
an Illinois insurance company, and American Casualty Company ofReading, Pennsylvania, a Pennsylvania insurance company do hereby certify that the.
Power of Attorney herein above set forth is. still in force; and further certify chat the By -Law and Resolution of the Board of Directors of the insurance
companies printed on the reverse hereof is still in force. In testimony whereof I have hereunto subscribed my name and affixed the seal of the said
insurance companies this day of , 2020,
P� GAS Uq<)J-
0
pOPP011AiE
F
�U
SEAL
1891
Form F6853-4/2012
CDU,vpnr o<Continental Casualty Company
'roe National Fire Insurance Company of Hartford
5 `PpasroNiira A American Casualty Company of Reading, Pennsylvania
t 1U19 7I. f�
`sky •
D. Johnson Assistant Secretary
Go to www.cnasurety.com > Owner /Obligee Services > Validate Bond Coverage, If you want to verify hood authenticity.
Authorizing By -Laws and Resolutions
ADOPTED BY THEBOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution may adopted by the Board of Directors of the Company at a
meeting held on May 12, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific cum a, agreements and instruments. an behalf of the
Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign wilt be
provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attomey is signed by Paul T. Bruflat, Vtce President, who has been authorized pursuant la the above resolution to execute power of attorneys on
behalf of Continental Casualty Company.
This Power of Attomey is signed and sealed by facsimile under and by the authority of the Pollowing Resolution adopted by the Boars of Directors of the Company by
unanimous written consent dated the 25" day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition. to being provided in original, hard copy forma[, may be provided vie facsimile or
otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of any Authorized Officer
shall he valid and binding on the Company. "
ADOPTED BV THE BOARD OF DIRECTORS OF NATIONAL FIRE INSURANCE COMPANY OF HARTFORD:
This Power of Attomey is made and executed pursuant to and by authority of the foflowing resolution duly adopted by the Board of Directors of the Company by
unanimous written consent dated May IO2 1995:
"RESOLVED: 'that any Senior or Group Vice President may authorize an officer m sign specific documents, agreements and instruments on hetrelfof the
Campany provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sigo will he
provided in writing by the Senior or Group Vim President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T: Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on
behalf of National Fire Insurance Company of Hartford.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by
unanimous written consent dated the 25'" day of Aprfl, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, hoods, undertakings and other ob0gatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may he provided via facsimile or
otherwise in an eleetrmric format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorised Officer
shall be valid and binding on the Company. "
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING, PENNSYLVANIA:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company by
unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the
Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be
provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on
behalf of American Casualty Company of Reading, Paansylvania.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by
unanimous written consent dated the 250 day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Hoard of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, lianas, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time; the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via facsimile or
otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of any Authorized Officer
shall be valid and binding on the Company. "
00 62 14 - 1
PAYMENT BOND
Page 1 of 2
CITY OF FORT WORTH Landmark Quebec Addition
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS 102418
Revised January 31, 2012
SECTION 00 62 14 1
PAYMENT BOND 2
3
THE STATE OF TEXAS § 4
§ KNOW ALL BY THESE PRESENTS: 5
COUNTY OF TARRANT § 6
That we, The Conlan Company, known as “Principal” herein, and Continental Casualty 7
Company, a corporate surety ( or sureties if more than one), duly authorized to do business in 8
the State of Texas, known as “Surety” herein (whether one or more), are held and firmly bound 9
unto the Developer, Lonestar Commerce Center, LLC, 750 North Saint Paul Street, Dallas, Texas, 10
authorized to do business in Texas “(Developer”), and the City of Fort Worth, a Texas municipal 11
corporation (“City”), in the penal sum of Four-Hundred Sixty - Eight Thousand Three - Hundred 12
and Seventy-Five Dollars and Thirty cents ($ 468,375.30), lawful money of the United States, to 13
be paid in Fort Worth, Tarrant County, Texas, for the payment of which sum well and truly be 14
made jointly unto the Developer and the City as dual obligees, we bind ourselves, our heirs, 15
executors, administrators, successors and assigns, jointly and severally, firmly by these presents: 16
WHEREAS, Developer and City have entered into an Agreement for the construction of 17
community facilities in the City of Fort Worth, by and through a Community Facilities 18
Agreement, CFA Number CFA20-0032 and 19
WHEREAS, Principal has entered into a certain written Contract with Developer, 20
awarded the 21 day of May, 2020, which Contract is hereby referred to and made a part hereof 21
for all purposes as if fully set forth herein, to furnish all materials, equipment, labor and other 22
accessories as defined by law, in the prosecution of the Work as provided for in said Contract 23
and designated as North City Addition Phase 1. 24
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if Principal shall 25
pay all monies owing to any (and all) payment bond beneficiary (as defined in Chapter 2253 of 26
the Texas Government Code, as amended) in the prosecution of the Work under the Contract, 27
then this obligation shall be and become null and void; otherwise to remain in full force and 28
effect. 29
This bond is made and executed in compliance with the provisions of Chapter 2253 of 30
the Texas Government Code, as amended, and all liabilities on this bond shall be determined in 31
accordance with the provisions of said statute. 32
IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED this 33
instrument by duly authorized agents and officers on this the 21 day of May, 2020. 34
35
006214-2
1
2
3
4
5
6
7
8
(Princ/pal) Secretary "
Witness as to Principal
PAYMENTBOND
Page 2 of 2
PRINCIPAL: The Conlan Company
Signature
/kKFvwy I2 7tAZpi U, P'2C'5)o&/UT
Name and Title
••%GONLAN Cp''b.
Address: 1800 Parkway Place, Suit quosesee
PO :v
_ Marietta, Georgia 3006E G OP
be
SEAL
SURETY: • CFORWI '
Continental Casualty Company '--;987,,,,,, „tP
ATTEST: /�4 / 8Y:
(Surety) Brian E. Madden
Alit ss as to Surety es H. V ghan, Jr.
a v//
Name and Title Felisa H, Vaughan
Attorney -in -Fact
Address: McGriff Insurance Services: Inc.
3100 ROVaIBIvd,$OUth
Alpharetta, Georgia 30022
Telephone Number: (7701 664-6818
Note:
If signed
by an officer of the Surety, there must
be on file a certified extract from the
bylaws
showing
that this person has authority to sign
such obligation. If Surety's physical
address
is different
from its mailing address, both must be
provided.
The date of the bond shall not be prior to the date the Contract is awarded.
END OF SECTION.
CITY OF FORT WORTH
STANDARD CITI CONDITIONS —DEVELOPER AWARDED PROlECrS
Revised January 31, 2012
Landmark Quebec Addition
10241g
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY -IN -FACT
Know All Men By These Presents, That Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of
Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company (herein called
"the CNA Companies"), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois,
and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint
Travis G Hufflnes, Brian E Madden, Deborah B Sasser, Brittany L Triplett, Felisa H Vaughan, Individually
of Alpharetta, GA, their true and lawful Attomey(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their
behalf bonds, undertakings and other obligatory instruments of similar nature
- In Unlimited Amounts -
and to bind them [hereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of their insurance companies and
all the acts of said Attorney, pursuant to the authority hereby given is hereby ratified and confirmed.
This Power of Attorney is made and executed pursuant to and by authority of the By -Law and Resolutions, printed on the reverse hereof, duly
adopted, as indicated, by the Boards of Directors of the insurance companies.
In
Witness Whereof, the-0NA Companies have caused
these presents to be signed
by their Vice President and their corporate seals to be hereto
affixed
on this 30th day of March, 2020,
USEAL
�o�uAU>� 1NSURq,� yy��cvnNroA;t,
J9i c:'• HA R7F •
Continental Casualty Company
National Fire Insurance Company of Hartford
American Ca ]ty Company of Re ding, Pennsylvania
Yaul T. Bruflat Ace President
State of South Dakota, County of Minnehaha, as:
On this 30th day of March, 202Q, before me personally came Paul T. Bruflat to me known, who, being by me duly sworn, did depose and say: that
he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company,
National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a
Pennsylvania insurance company described in and which executed the above instrument; that he knows the seals of said insurance companies; that the
seals affixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said
insurance companies and that he signed his name thereto pursuant to like authority, and acknowledges same to be the act and deed of said insurance
companies.
e1$xIN! rtN0.Ulain
WINMhYw/r///�Mi'
My Commission Expires June 23, 2021 L Mohr Notary Public
CERTIFICATE
1, D. Johnson, Assistant Secretary of Continental Casualty any, an Illinois insurance company, National Pire Insurance Company of Hartford,
an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company do hereby certifythat the
Power ofAttorney herein above set Forth is still in force, and further certify that the By -Law and Resolution of the Board of Directors of the insurance
companies printed on the reverse hereof is still in force. In testimony whereof I have hereunto subscribed my name and affixed the, sea] of the said
insurance companies this day of , 2020.
a, pnSOAtpy � 10SUR4� ANY M,t,
ponPeaAre O^ $ Ypr,99PO9gT�
o 1eisoi''�a�
u SEAL t ,p
1891 HAIIIii •
Form F6853-4/2012
Continental Casualty Company
National Fire Insurance Company of Hartford
American Casualty Company of Reading, Pennsylvania
<0�0 0 j 6 V��
.Johnson Assistant Secretary
Go to www.cnasuretv.com > Owner /Obligee Services > Validate Band Coverage, if you want to verify bond authenticity.
Authorizing By -Laws and Resolutions
ADOPTED BY THE BOARD Or DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company at a
meeting held on May 12, 19951
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the
Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be
provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective,"
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on
behalf of Continental Casualty Company.
This Power of Attorney is signed and scaled by facsimile under and by the authority of the following Resolution adopted by the Baud of Directors of the Company by
unanimous written consent dated the 25's day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being. provided in original, hard copy format, may he provided via facsimile or
otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer
shall he valid and binding on the Company. "
ADOPTED BY THE BOARD OF Dll2HCTORS OP NATIONAL FIRE W SURANCE COMPANY OP HARTFORD:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company by
unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the
Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be
provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on
behalf of National Fire Insurance Company of Hartford.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by
unanimous written consent dated the 251s day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via facsimile or
otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer
shalt be valid and binding on the Company, "
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING, PENNSYLVAMA:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the Company by
unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the
Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will be
provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on
behalf of American Casualty Company of Reading, Pennsylvania.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by
unanimous written consent dated the 256 day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers; in addition to being provided in original, hard copy format, may be provided via facsimile or
otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of my Authorized Officer
shall be valid and binding on the Company. "
00 62 19 - 1
MAINTENANCE BOND
Page 1 of 4
CITY OF FORT WORTH Landmark Quebec Addition
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS 102418
Revised January 31, 2012
SECTION 00 62 19 1
MAINTENANCE BOND 2
3
THE STATE OF TEXAS § BOND NUMBER: 30090315 4
§ KNOW ALL BY THESE PRESENTS: 5
COUNTY OF TARRANT § 6
That we, The Conlan Company, known as “Principal” herein and Continental Casualty 7
Company, a corporate surety (sureties, if more than one), duly authorized to do business in the 8
State of Texas, known as “Surety” herein (whether one or more), are held and firmly bound unto 9
the Developer, Lonestar Commerce Center, LLC, 750 North Saint Paul Street, Dallas, Texas 10
75201, authorized to do business in Texas (“Developer”) and the City of Fort Worth, a Texas 11
municipal corporation (“City”), in the sum of Four-Hundred Sixty – Eight Thousand Three 12
Hundred and Seven-Five Dollars and Thirty cents ($468,375.30), lawful money of the United 13
States, to be paid in Fort Worth, Tarrant County, Texas, for payment of which sum well and truly 14
be made jointly unto the Developer and the City as dual obligees and their successors, we bind 15
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, 16
firmly by these presents. 17
18
WHEREAS, Developer and City have entered into an Agreement for the construction of 19
community facilities in the City of Fort Worth by and through a Community Facilities Agreement, 20
CFA Number CFA20-0032and 21
WHEREAS, the Principal has entered into a certain written contract with the Developer 22
awarded the 21 day of May, 2020, which Contract is hereby referred to and a made part hereof 23
for all purposes as if fully set forth herein, to furnish all materials, equipment labor and other 24
accessories as defined by law, in the prosecution of the Work, including any Work resulting from 25
a duly authorized Change Order (collectively herein, the “Work”) as provided for in said Contract 26
and designated as Water and Sanitary Sewer Improvement to Landmark Quebec Addition; and 27
28
WHEREAS, Principal binds itself to use such materials and to so construct the Work in 29
accordance with the plans, specifications and Contract Documents that the Work is and will 30
006219-2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
MAINTENANCE BOND
Page 2 of 3
WHEREAS, Principal binds itself to use such materials and to so construct the Work in
accordance
with the plans,
specifications and Contract
Documents that the Work is
and
will
remain free
from defects in
materials or workmanship
for and during the period of
two
(2) years
after the date of Final Acceptance of the Work by the City ("Maintenance Period"); and
WHEREAS, Principal binds itself to repair or reconstruct the Work in whole or in part upon
receiving notice from the Developer and/or City of the need thereof at any time within the
Maintenance Period.
NOW THEREFORE, the condition of this obligation is such that if Principal shall remedy
any defective Work, for which timely notice was provided by Developer or City, to a completion
satisfactory to the City, then this obligation shall become null and void; otherwise to remain in
full force and effect.
PROVIDED, HOWEVER, if Principal shall fail so to repair or reconstruct any timely
noticed defective Work, it is agreed that the Developer or City may cause any and all such
defective Work to be repaired and/or reconstructed with all associated costs thereof being
borne by the Principal and the Surety under this Maintenance Bond; and
PROVIDED FURTHER, that if
any legal action be filed
on
this Bond,
venue shall lie in
Tarrant County, Texas or the United
States District Court for
the
Northern
District of Texas, Fort
Worth Division; and
PROVIDED FURTHER, that this obligation shall be continuous in nature and successive
recoveries maybe had hereon for successive breaches.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS— DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Landmark Quebec Addition
102418
006219-3
1
2
3
4
5
6
7
8
9
10
11
12
MAINTENANCE BOND
Page 3 of 3
IN WITNESS WHEREOF, the Principal and Surety have each SIGNED and SEALED this
instrument by duly authorized agents and officers on this the day of
.20
ec�
" u�L
Witness as to Principal
ATTEST:
r E-
(Suretyf Brian E. Madden
Witn ss as to Surety
/,
Ja es H. Vaughan,
PRINCIPAL:
The Conlan Company
BY: !�
Signature
X�//K) le-70K�111J EAT
Name and Title %'tAUW CO,R�-'''�
•
SEAL:=
°
SURETY: '110a„1987 ls »����`���,.
Continental Casualty Company
4/
4,101
BY: 0 -
Signature
Address: 1800 Parkway Place, Suite 1
Marietta, Georgia 30067
Felisa H. Vaughan, Attorney -in -Fact
Name and Title
Address: McGriff Insurance Services, Ift,
3100 Royal Blvd. South
Alpharetta, Georgia 30022
Telephone Number: (770) 664-6818
Note: If signed by an officer of the Surety, there must be on file a certified extract from the
bylaws showing that this person has authority to sign such obligation. If Surety's physical
address is different from its mailing address, bath must be provided.
The date of the bond shall not be prior to the date the Contract is awarded.
END OF SECTION
CITY OF FORT WORTH
STANDARD CITY CONDITIONS — DEVELOPER AWARDED PROJECTS
Revised January 31, 2012
Landmark Quebec Addition
102418
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY -IN -FACT
Know All Men By These Presents, That Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of
Hartford, an Illinois insurance company, and American Casualty Company of Reading; Pennsylvania, a Pennsylvania insurance company (herein called
"the CNA Companies'), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois,
and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint
Travis G HufYlnes, Brian E Madden, Deborah H Sasser, Brittany L Triplett, Fensa H Yanghan, Individually
of Alpharetta, GA, their true and lawful Attomey(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their
behalf bonds, undertakings and other obligatory instruments of similar nature
In Unlimited Amounts -
and to
bind them thereby as
fully and
to
the
same eaten[ as if such insWments were signed by a duly authorized officer of their insurance companies and
all the
acts of said Attorney,
pursuant
to
the
authority hereby given is hereby ratified and confirmed.
This Power of Attomey is made and executed pursuant to and by authority ofhe By -Law and Resolutions, printed on the reverse hereof, duly
adopted, as indicated, by the Boards of Directors of the insurance companies.
In Witness Whereof, the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto
affixed on this 30th day of March, 2020,
�GASt/q<Ty 1NSURq IL F ��Avpav gAy0,
f(
U000F:1P0AAr&
a�1a0AiPsueiagI.tr0 �
L y
& HAW* s •
Continental Casualty Company
National Fire Insurance Company of Hartford
American Callty Company of Re ding, Pennsylvania
Paul T. Bmflat ce President
State of South Dakota, County of Minnehaha, ss:
On this 30th day of March, 2020, before me personally came Paul T. Bmflat to me known, who, being by me duly sworn, did depose and say: that
he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company;
National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a
Pennsylvania insurance company described in and which executed the above instmment; that he knows the seals of said insurance companies; that the
seals affixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said
insurance companies and that he signed his name thereto pursuant to like authority,nod acknowledges same to be the act and deed of said insurance
companies.
�aourm WOTA�
My Commission Expires June 23, 2021 J. Mohr Notary Public
CERTIFICATE
I, D. Johnson, Assistant Secretary of Continental Casualty any, an Illinoisinsurance company, National Fire Insurance Company of Hartford,
an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company do hereby certify that the
Power of Attorney herein above set forth is still in force, and further certify that the By -Law and Resolution of the Board of Directors of the insurance
companies printed on the reverse hereof is still in force.. In testimony whereof I have hereunto subscribed my name and affixed the seal of the said
insurance companies this day of 120206
�OAS llgtTy � 1NSU114yc pxr Pe,�
F- GQPP: PAif °�, y $ �NCOA11
z �'ZvyG'I3 'J r2 soi �'
Y, SEAL
ta97. � XARtf� •
Joi
Form F68534/2012
Continental Casualty Company
National Fue Insurance Company of Hartford
American Casualty Company of Reading, Pennsylvania
<00C 0 j O;V��
.Johnson Ir Assistant Secretary
Go to www.cnasurety.com > Owner /Obligee Services > Validate Bond Coverage, if you want to verify bond authenticity.
Authorizing By -Laws and Resolutions
ADOPTED BY THE BOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duty adopted by the Board of Directors of the Company at a
meeting held on May 12, 1995:
"RESOLVED: That any can at or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on hehalf of the
Company provided that the time of such authorized officer and a description of the documents, agreements or instruments that such officer may sign will he
provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attamey is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution [o execute power ofettomeys on
behalf of Continental Casualty Company.
Phis Power of Attamey is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Hoard ofDirectors of the Company by
unanimous written consent dated the 25" day of April, 2012:
"Whereas,. the bylaws afthe Company or specific resolution of the Board ofDirecmrs has authorized various officers (the "Authorized Officers")to execute
various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be proviied via facsimile ar
otherwise in not electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer
shall be valid and binding on the Company. "
ADOPTED BY TBE BOARD OF DIRECTORS OF NATIONAL F[RE INSURANCE COMPANY OF HARTFORD:
This. Power of Attomey is made and executed pursuant tc and 6y authority of the following resolution duly adopted by the Hoard of Directors of the Company by
unanimous written consent dated May 10, 1995:
"RESOLVED: 'Chat any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the
Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that sue h officer may sign will be
provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This
Power of Attomey is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attameys on
behalf of Nafional Fire Insurance Company of Hartford.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the fallowing Resolution adopted by the Board of Directors of the Company by
unmrimouswritten consent dated the 25" day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, herd copy format, may be provided vie facsimile or
otherwise in an electronic format (collectively, "Elcelronic Signaures"); Now therefore be it resolved: that the Electronic Signature of any Authorized Officer
shall be valid and binding on the Company. "
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING„ PENNSYLVANIA:
This Power of Attorney is made and executed pursuant to and by authority of the fo0owing resolution duly adopted by the Board of Directors of Ore Company by
unanimous written consent doled May 10,.1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of the
Company provided that the name of such euthptized officer and a description pf the documents, agreements or insWments that such officer may sign will be
provided inwriting by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of attorneys on
behalf of American Casualty Company of Reading, Pennsylvania,
'this Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the Company by
unanhnaus written consent dated the 25"day of April, 2012:
"Whereas, the bylaws of Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers")to execute
various policies, bonds; undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via facsimile or
otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore he it resolved: that the Electronic Signature of any Authorized Officer
shall be valitl and binding on the Company. "
This page has been left blank intentionally.
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
CONTRACTOR’S BLANKET ADDITIONAL INSURED ENDORSEMENT –
FORM A
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
Policy Number Agency Number Policy Effective Date
Policy Expiration Date Date Account Number
Named Insured Agency Issuing Company
1. a. SECTION II - WHO IS AN INSURED is amended to add as an additional insured any person or
organization:
(1) Whom you are required to add as an additional insured on this policy under a written contract or
written agreement relating to your business; or
(2) Who is named as an additional insured under this policy on a certificate of insurance.
b. The written contract, written agreement, or certificate of insurance must:
(1) Require additional insured status for a time period during the term of this policy; and
(2) Be executed prior to the "bodily injury", "property damage", or "personal and advertising injury"
leading to a claim under this policy.
c. If, however:
(1) “Your work” began under a letter of intent or work order; and
(2) The letter of intent or work order led to a written contract or written agreement within 30 days of
beginning such work; and
(3) Your customer’s customary contracts require persons or organizations to be named as additional
insureds;
we will provide additional insured status as specified in this endorsement.
2. The insurance provided under this endorsement is limited as follows:
a. That person or organization is an additional insured only with respect to liability caused, in whole or in
part, by:
(1) Premises you:
(a) Own;
(b) Rent;
(c) Lease; or
(d) Occupy;
(2) Ongoing operations performed by you or on your behalf. Ongoing operations does not apply to
“bodily injury” or “property damage” occurring after:
Includes copyrighted material of Insurance Services Office, Inc.
CG 70 48 10 15 Pages 1 of 4
CPP205094112 01/01/2020
01/01/2021
The Conlan Company
(a) All work to be performed by you or on your behalf for the additional insured(s) at the site of the
covered operations is complete, including related materials, parts or equipment (other than
service, maintenance or repairs); or
(b) That portion of “your work” out of which the injury or damage arises is put to its intended use by
any person or organization other than another contractor working for a principal as a part of the
same project.
(3) Completed operations coverage, but only if:
(a) The written contract, written agreement, or certificate of insurance requires completed
operations coverage or “your work” coverage; and
(b) This coverage part provides coverage for “bodily injury” or “property damage” included within
the “products-completed operations hazard”.
However, the insurance afforded to such additional insured only applies to the extent permitted by law.
b. If the written contract, written agreement, or certificate of insurance:
(1) Requires “arising out of” language; or
(2) Requires you to provide additional insured coverage to that person or organization by the use of
either or both of the following:
(a) Additional Insured – Owners, Lessees or Contractors – Scheduled Person Or Organization
endorsement CG 20 10 10 01; or
(b) Additional Insured – Owners, Lessees or Contractors – Completed Operations endorsement CG
20 37 10 01;
then the phrase “caused, in whole or in part, by” in paragraph 2.a. above is replaced by “arising out of”.
c. If the written contract, written agreement, or certificate of insurance requires you to provide additional
insured coverage to that person or organization by the use of:
(1) Additional Insured – Owners, Lessees or Contractors – Scheduled Person Or Organization
endorsement CG 20 10 07 04 or CG 20 10 04 13; or
(2) Additional Insured – Owners, Lessees or Contractors – Completed Operations endorsement CG 20
37 07 04 or CG 20 37 04 13; or
(3) Both those endorsements with either of those edition dates; or
(4) Either or both of the following:
(a) Additional Insured – Owners, Lessees or Contractors – Scheduled Person Or Organization
endorsement CG 20 10 without an edition date specified; or
(b) Additional Insured – Owners, Lessees or Contractors – Completed Operations endorsement CG
20 37 without an edition date specified;
then paragraph 2.a. above applies.
d. Premises, as respects paragraph 2.a.(1) above, include common or public areas about such premises if
so required in the written contract or written agreement.
e. Additional insured status provided under paragraphs 2.a.(1)(b) or 2.a.(1)(c) above does not extend
beyond the end of a premises lease or rental agreement.
f. The limits of insurance that apply to the additional insured are the least of those specified in the:
(1) Written contract;
(2) Written agreement;
(3) Certificate of insurance; or
(4) Declarations of this policy.
The limits of insurance are inclusive of and not in addition to the limits of insurance shown in the
Declarations.
Includes copyrighted material of Insurance Services Office, Inc.
Page 2 of 4 CG 70 48 10 15
g. The insurance provided to the additional insured does not apply to "bodily injury", "property damage", or
"personal and advertising injury" arising out of an architect’s, engineer’s, or surveyor’s rendering of, or
failure to render, any professional services, including but not limited to:
(1) The preparing, approving, or failing to prepare or approve:
(a) Maps;
(b) Drawings;
(c) Opinions;
(d) Reports;
(e) Surveys;
(f) Change orders;
(g) Design specifications; and
(2) Supervisory, inspection, or engineering services.
h. SECTION IV – COMMERCIAL GENERAL LIABILITY CONDITIONS, paragraph 4. Other Insurance is
deleted and replaced with the following:
4. Other Insurance.
Coverage provided by this endorsement is excess over any other valid and collectible insurance
available to the additional insured whether:
a. Primary;
b. Excess;
c. Contingent; or
d. On any other basis;
but if the written contract, written agreement, or certificate of insurance requires primary and non-
contributory coverage, this insurance will be primary and non-contributory relative to other insurance
available to the additional insured which covers that person or organization as a Named Insured, and
we will not share with that other insurance.
i. If the written contract, written agreement, or certificate of insurance as outlined above requires additional
insured status by use of CG 20 10 11 85, then the coverage provided under this CG 70 48 endorsement
does not apply except for paragraph 2.h. Other Insurance. Additional insured status is limited to that
provided by CG 20 10 11 85 shown below and paragraph 2.h. Other Insurance shown above.
ADDITIONAL INSURED - OWNERS, LESSEES OR
CONTRACTORS (FORM B)
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART.
SCHEDULE
Name of Person or Organization: Blanket Where Required by Written Contract, Agreement, or
Certificate of Insurance that the terms of CG 20 10 11 85 apply
(If no entry appears above, information required to complete this endorsement will be shown in the
Declarations as applicable to this endorsement.)
WHO IS AN INSURED (Section II) is amended to include as an insured the person or organization shown
in the Schedule, but only with respect to liability arising out of "your work" for that insured by or for you.
CG 20 10 11 85 Copyright, Insurance Services Office, Inc., 1984
Includes copyrighted material of Insurance Services Office, Inc.
CG 70 48 10 15 Pages 3 of 4
j. The insurance provided by this endorsement does not apply to any premises or work for which the
person or organization is specifically listed as an additional insured on another endorsement attached to
this policy.
Includes copyrighted material of Insurance Services Office, Inc.
Page 4 of 4 CG 70 48 10 15
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
CONTRACTORS GENERAL LIABILITY EXTENSION ENDORSEMENT
This endorsement modifies insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE FORM
Under SECTION I - COVERAGE A. BODILY INJURY AND PROPERTY DAMAGE LIABILITY, paragraph 2.
EXCLUSIONS, provisions 1. through 6. of this endorsement amend the policy as follows:
1. LIQUOR LIABILITY
Exclusion c. Liquor Liability is deleted.
2. NONOWNED WATERCRAFT AND NONOWNED AIRCRAFT (HIRED, RENTED OR LOANED WITH PAID
CREW)
Exclusion g. Aircraft, Auto or Watercraft, paragraph (2)is deleted and replaced with the following:
(2) A watercraft you do not own that is:
(a) Less than 51 feet long; and
(b) Not being used to carry persons or property for a charge;
Exclusion g. Aircraft, Auto or Watercraft, paragraph (6) is added as follows:
(6) An aircraft that you do not own that is:
(a) Hired;
(b) Rented; or
(c) Loaned to you;
with paid crew for a period of five (5) consecutive days or less.
Paragraph (6) does not apply if the insured has any other insurance for “bodily injury or “property
damage” liability for such aircraft, whether such other insurance is primary, excess, contingent or on any
other basis.
3. PREMISES ALIENATED
A. Exclusion j. Damage to Property, paragraph (2) is deleted.
B. The following paragraph is also deleted from Exclusion j. Damage to Property:
Paragraph (2) of this exclusion does not apply if the premises are “your work” and were never occupied,
rented or held for rental by you.
4. PROPERTY DAMAGE LIABILITY - ELEVATORS AND SIDETRACK AGREEMENTS
A. Exclusion j. Damage to Property, paragraphs (3), (4), and (6) do not apply to the use of elevators.
B. Exclusion k. Damage to Your Product does not apply to:
1. The use of elevators; or
2. Liability assumed under a sidetrack agreement.
5. PROPERTY DAMAGE LIABILITY - BORROWED EQUIPMENT
A. Exclusion j. Damage to Property, paragraph (4) does not apply to "property damage" to borrowed
equipment while at a jobsite and not being used to perform operations.
Includes copyrighted material of Insurance Services Office, Inc.
CG 70 49 11 09 Page 1 of 10
B. With respect to any one borrowed equipment item, provision 5.A. above does not apply to "property
damage" that exceeds $25,000 per occurrence or $25,000 annual aggregate.
6. PRODUCT RECALL EXPENSE
A.Exclusion n. Recall Of Products, Work Or Impaired Property does not apply to “product recall
expenses” that you incur for the “covered recall” of “your product”. This exception to the exclusion does
not apply to “product recall expenses” resulting from:
1. Failure of any products to accomplish their intended purpose;
2. Breach of warranties of fitness, quality, durability or performance;
3. Loss of customer approval or any cost incurred to regain customer approval;
4. Redistribution or replacement of “your product”, which has been recalled, by like products or
substitutes;
5. Caprice or whim of the insured;
6. A condition likely to cause loss, about which any insured knew or had reason to know at the
inception of this insurance;
7. Asbestos, including loss, damage or clean up resulting from asbestos or asbestos containing
materials;
8. Recall of “your product(s)” that have no known or suspected defect solely because a known or
suspected defect in another of “your product(s)” has been found.
B.Under SECTION III – LIMITS OF INSURANCE, paragraph 3. is replaced in its entirety as follows and
paragraph 8. is added:
3. The Products-Completed Operations Aggregate Limit is the most we will pay for the sum of:
a. Damages under COVERAGE A BODILY INJURY AND PROPERTY DAMAGE LIABILITY
because of “bodily injury” and “property damage” included in the “products-completed
operations hazard” and
b. “Product recall expenses”.
8. Subject to paragraph 5.above, $25,000 is the most we will pay for all “product recall expenses”
arising out of the same defect or deficiency.
The insurance afforded by provisions 1. through 6. of this endorsement is excess over any valid and collectible
insurance (including any deductible) available to the insured whether primary, excess or contingent, and SECTION
IV.,paragraph 4. Other Insurance is changed accordingly.
7. BLANKET CONTRACTUAL LIABILITY – RAILROADS
When a written contract or written agreement requires Contractual Liability - Railroads, the definition of
"insured contract" in Section V - Definitions is replaced by the following with respect to operations performed
for, or affecting, a railroad:
9. "Insured Contract" means:
a. A contract for a lease of premises. However, that portion of the contract for a lease of premises that
indemnifies any person or organization for damage by fire to premises while rented to you or
temporarily occupied by you with permission of the owner is not an "insured contract";
b. A sidetrack agreement;
c. Any easement or license agreement;
d. An obligation, as required by ordinance, to indemnify a municipality, except in connection with work
for a municipality;
Includes copyrighted material of Insurance Services Office, Inc.
Page 2 of 10 CG 70 49 11 09
e. An elevator maintenance agreement;
f. That part of any other contract or agreement pertaining to your business (including an
indemnification of a municipality in connection with work performed for a municipality) under which
you assume the tort liability of another party to pay for "bodily injury" or "property damage" to a third
person or organization. Tort liability means a liability that would be imposed by law in the absence of
any contract or agreement.
Paragraph f. does not include that part of any contract or agreement:
(1) That indemnifies an architect, engineer or surveyor for injury or damage arising out of:
(a) Preparing, approving or failing to prepare or approve maps, shop drawings, opinions,
reports, surveys, field orders, change orders or drawings and specifications; or
(b) Giving directions or instructions, or failing to give them;
(2) Under which the insured, if an architect, engineer or surveyor, assumes liability for an injury or
damage arising out of the insured's rendering or failure to render professional services,
including those listed in Paragraph (1) above and supervisory, inspection, architectural or
engineering activities.
8. CONTRACTUAL LIABILITY - PERSONAL AND ADVERTISING INJURY
Under SECTION 1 - COVERAGE B., paragraph 2. Exclusions, paragraph e. Contractual Liability is deleted.
9. SUPPLEMENTARY PAYMENTS
Under SECTION I - SUPPLEMENTARY PAYMENTS - COVERAGES A AND B, paragraphs 1.b. and 1.d. are
deleted and replaced with the following:
b. Up to $2,500 for cost of bail bonds required because of accidents or traffic law violations arising out of the
use of any vehicle to which the Bodily Injury Liability Coverage applies. We do not have to furnish these
bonds.
d. All reasonable expenses incurred by the insured at our request to assist us in the investigation or defense
of the claim or “suit”, including actual loss of earnings up to $500 a day because of time off from work.
10. BROADENED WHO IS AN INSURED
SECTION II - WHO IS AN INSURED is deleted and replaced with the following:
1. If you are designated in the Declarations as:
a. An individual, you and your spouse are insureds, but only with respect to the conduct of a business
of which you are the sole owner.
b. A partnership or joint venture, you are an insured. Your members, your partners, and their spouses
are also insureds, but only with respect to the conduct of your business.
c. A limited liability company, you are an insured. Your members are also insureds, but only with
respect to the conduct of your business. Your managers are insureds, but only with respect to their
duties as your managers.
d. An organization other than a partnership, joint venture or limited liability company, you are an
insured. Your "executive officers" and directors are insureds, but only with respect to their duties as
your officers or directors. Your stockholders are also insureds, but only with respect to their liability
as stockholders.
e. A trust, you are an insured. Your trustees are also insureds, but only with respect to their duties as
trustees.
Includes copyrighted material of Insurance Services Office, Inc.
CG 70 49 11 09 Page 3 of 10
2. Each of the following is also an insured:
a. Your “volunteer workers” only while performing duties related to the conduct of your business, or
your "employees," other than either your "executive officers," (if you are an organization other than a
partnership, joint venture or limited liability company) or your managers (if you are a limited liability
company), but only for acts within the scope of their employment by you or while performing duties
related to the conduct of your business. However, none of these "employees" or “volunteer workers”
are insured for:
(1) "Bodily injury" or "personal and advertising injury":
(a) To you, to your partners or members (if you are a partnership or joint venture), to your
members (if you are a limited liability company), to a co-"employee" while in the course of
his or her employment or performing duties related to the conduct of your business, or to
your other “volunteer workers” while performing duties related to the conduct of your
business;
(b) To the spouse, child, parent, brother or sister of that co-"employee" or “volunteer worker”
as a consequence of paragraph (1)(a) above;
(c) For which there is any obligation to share damages with or repay someone else who must
pay damages because of the injury described in paragraphs (1)(a) or (b) above; or
(d) Arising out of his or her providing or failing to provide professional health care services
except as provided in provision 11. of this endorsement.
Paragraphs (1)(a), (1)(b) and (1)(c) above do not apply to your “employees” who are:
(i) Managers;
(ii) Supervisors;
(iii) Directors; or
(iv) Officers;
with respect to “bodily injury” to a co-“employee”.
(2) "Property damage" to property:
(a) Owned, occupied or used by;
(b) Rented to, in the care, custody or control of, or over which physical control is being
exercised for any purpose by
you, any of your "employees," “volunteer workers”, any partner or member (if you are a
partnership or joint venture), or any member (if you are a limited liability company).
b. Any person (other than your "employee" or “volunteer worker”), or any organization while acting as
your real estate manager.
c. Any person or organization having proper temporary custody of your property if you die, but only;
(1) With respect to liability arising out of the maintenance or use of that property; and
(2) Until your legal representative has been appointed.
d. Your legal representative if you die, but only with respect to duties as such. That representative will
have all your rights and duties under this Coverage Form.
e. Your subsidiaries if:
(1) They are legally incorporated entities; and
(2) You own more than 50% of the voting stock in such subsidiaries as of the effective date of this
policy.
Includes copyrighted material of Insurance Services Office, Inc.
Page 4 of 10 CG 70 49 11 09
If such subsidiaries are not shown in the Declarations, you must report them to us within 180 days of
the inception of your original policy.
f.(1) Any person or organization, other than an architect, engineer or surveyor, required to be named
as an additional insured in a "work contract", letter of intent or work order. However, such
person or organization shall be an additional insured only with respect to covered "bodily injury,"
"property damage," and "personal and advertising injury" arising out of “your work" under that
"work contract", letter of intent or work order.
(2) We will provide additional insured coverage to such person or organization only:
(a) for a period of 30 days after the effective date of the applicable "work contract", letter of
intent or work order; or
(b) until the end of the policy term in effect at the inception of the applicable “work contract”,
letter of intent or work order;
whichever is earlier.
(3) Coverage provided under this paragraph f. is excess over any other valid and collectible
insurance available to the additional insured whether primary, excess, contingent, or on any
other basis unless the “work contract”, letter of intent or work order requires this insurance be
primary, in which case this insurance will be primary without contribution from such other
insurance available to the additional insured.
(4) This paragraph f. does not apply if form CG 70 48, Contractors Blanket Additional Insured
Endorsement, is attached to the policy.
g.Any person or organization to whom you are obligated by virtue of a written contract to provide
insurance such as is afforded by this policy, but only with respect to liability arising out of the
maintenance or use of that part of any premises leased to you, including common or public areas
about such premises if so required in the contract.
However, no such person or organization is an insured with respect to:
(1) Any "occurrence" that takes place after you cease to occupy those premises; or
(2) Structural alterations, new construction or demolition operations performed by or on behalf of
such person or organization.
h. Any state or political subdivision but only as respects legal liability incurred by the state or political
subdivision solely because it has issued a permit with respect to operations performed by you or on
your behalf.
However, no state or political subdivision is an insured with respect to:
(1) "Bodily injury", "property damage", and "personal and advertising injury" arising out of
operations performed for the state or municipality; or
(2) "Bodily injury" or "property damage" included within the "products-completed operations
hazard."
i. Any person or organization who is the lessor of equipment leased to you to whom you are obligated
by virtue of a written contact to provide insurance such as is afforded by this policy, but only with
respect to their liability arising out of the maintenance, operation or use of such equipment by you or
a subcontractor on your behalf with your permission and under your supervision.
However, no such person or organization is an insured with respect to any "occurrence" that takes
place after the equipment lease expires.
j. Any architect, engineer, or surveyor engaged by you but only with respect to liability arising out of
your premises or "your work."
Includes copyrighted material of Insurance Services Office, Inc.
CG 70 49 11 09 Page 5 of 10
However, no architect, engineer, or surveyor is an insured with respect to "bodily injury," "property
damage," or "personal and advertising injury" arising out of the rendering of or the failure to render
any professional services by or for you, including:
(1) The preparing, approving, or failing to prepare or approve maps, drawings, opinions, reports,
surveys, change orders, designs or specifications; or
(2) Supervisory, inspection, or engineering services.
This paragraph j. does not apply if form CG 70 48, Contractors Blanket Additional Insured
Endorsement, is attached to the policy.
k. Any manager, owner, lessor, mortgagee, assignee or receiver of premises, including land leased to
you, but only with respect to liability arising out of the ownership, maintenance or use of that part of
the premises or land leased to you.
However, no such person or organization is an insured with respect to:
(1) Any "occurrence" that takes place after you cease to occupy that premises, or cease to lease
the land; or
(2) Structural alteration, new construction or demolition operations performed by or on behalf of that
person or organization.
3. Any organization you newly acquire or form, other than a partnership, joint venture or limited liability
company and over which you maintain ownership or majority interest, will qualify as a Named Insured if
there is no other similar insurance available to that organization. However:
a. Coverage under this provision is afforded until the end of the policy period.
b. Coverage A does not apply to "bodily injury" or "property damage" that occurred before you acquired
or formed the organization.
c. Coverage B does not apply to "personal and advertising injury" arising out of an offense committed
before you acquired or formed the organization.
d. Coverage A does not apply to “product recall expense” arising out of any withdrawal or recall that
occurred before you acquired or formed the organization.
4. Any person or organization (referred to below as vendor) with whom you agreed, because of a written
contract or agreement to provide insurance is an insured, but only with respect to "bodily injury" or
"property damage" arising out of "your products" that are distributed or sold in the regular course of the
vendor's business.
However, no such person or organization is an insured with respect to:
a."Bodily injury" or "property damage" for which the vendor is obligated to pay damages by reason of
the assumption of liability in a contract or agreement. This exclusion does not apply to liability for
damages that the vendor would have in the absence of the contract or agreement.
b. Any express warranty unauthorized by you;
c. Any physical or chemical change in “your product” made intentionally by the vendor;
d. Repackaging, except when unpacked solely for the purpose of inspection, demonstration, testing, or
the substitution of parts under instructions from the manufacturer, and then repackaged in the
original container;
e. Any failure to make such inspections, adjustments, tests or servicing as the vendor has agreed to
make or normally undertakes to make in the usual course of business, in connection with the
distribution or sale of “your products”;
f. Demonstration, installation, servicing or repair operations, except such operations performed at the
vendor's premises in connection with the sale of “your product”;
Includes copyrighted material of Insurance Services Office, Inc.
Page 6 of 10 CG 70 49 11 09
g. “Your products” which, after distribution or sale by you, have been labeled or relabeled or used as a
container, part or ingredient of any other thing or substance by or for the vendor.
h. “Bodily injury” or “property damage” arising out of the sole negligence of the vendor for its own acts
or omissions or those of its employees or anyone else acting on its behalf. However, this exclusion
does not apply to:
(1) The exceptions contained in subparagraphs d. or f.; or
(2) Such inspections, adjustments, tests or servicing as the vendor has agreed to make or normally
undertakes to make in the usual course of business, in connection with the distribution or sale of
the products.
This insurance does not apply to any insured person or organization from which you have acquired “your
products”, or any ingredient, part, or container, entering into, accompanying or containing “your products”.
No person or organization is an insured with respect to the conduct of any current or past partnership, joint
venture or limited liability company that is not shown as a Named Insured in the Declarations.
11. INCIDENTAL MALPRACTICE LIABILITY
As respects provision 10., SECTION II - WHO IS AN INSURED, paragraph 2.a.(1)(d) does not apply to any
nurse, emergency medical technician or paramedic employed by you to provide medical or paramedical
services, provided that you are not engaged in the business or occupation of providing such services, and your
“employee” does not have any other insurance that would also cover claims arising under this provision,
whether the other insurance is primary, excess, contingent or on any other basis.
Under SECTION III - LIMITS OF INSURANCE, provisions 12. through 14. of this endorsement amend the policy as
follows:
12. AGGREGATE LIMITS PER PROJECT
The General Aggregate Limit applies separately to each of your construction projects away from premises
owned by or rented to you.
13. INCREASED MEDICAL PAYMENTS LIMIT AND REPORTING PERIOD
A.The requirement under SECTION I - COVERAGE C MEDICAL PAYMENTS that expenses be incurred
and reported to us within one year of the date of the accident is changed to three years.
B.SECTION III - LIMITS OF INSURANCE, paragraph 7., the Medical Expense Limit, is subject to all of the
terms of SECTION III - LIMITS OF INSURANCE and is the greater of:
1. $10,000; or
2. The amount shown in the Declarations for Medical Expense Limit.
C. This provision 13. does not apply if COVERAGE C MEDICAL PAYMENTS is excluded either by the
provisions of the Coverage Form or by endorsement.
14. DAMAGE TO PREMISES RENTED TO YOU – SPECIFIC PERILS
A.The word fire is changed to "specific perils" where it appears in:
1.The last paragraph of SECTION I – COVERAGE A, paragraph 2. Exclusions;
2. SECTION IV, paragraph 4.b. Excess Insurance.
B. The Limits of Insurance shown in the Declarations will apply to all damage proximately caused by the
same event, whether such damage results from a "specific peril" or any combination of "specific perils."
C. The Damage To Premises Rented To You Limit described in SECTION III - LIMITS OF INSURANCE,
paragraph 6., is replaced by a new limit, which is the greater of:
1. $1,000,000; or
Includes copyrighted material of Insurance Services Office, Inc.
CG 70 49 11 09 Page 7 of 10
2. The amount shown in the Declarations for Damage To Premises Rented To You Limit.
D. This provision 14.does not apply if the Damage To Premises Rented To You Limit of SECTION I -
COVERAGE A is excluded either by the provisions of the Coverage Form or by endorsement.
Under SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, provisions 15. through 17. of this
endorsement amend the policy as follows:
15. KNOWLEDGE OF OCCURRENCE
Under 2. Duties In The Event Of Occurrence, Offense, Claim, Or Suit, paragraph a. is deleted and replaced
and paragraphs e.and f. are added as follows:
a.You must see to it that we are notified as soon as practicable of an "occurrence" or an offense, regardless
of the amount, which may result in a claim. Knowledge of an "occurrence" or an offense by your
“employee(s)” shall not, in itself, constitute knowledge to you unless one of your partners, members,
“executive officers”, directors, or managers has knowledge of the "occurrence" or offense. To the extent
possible, notice should include:
(1) How, when and where the "occurrence" or offense took place;
(2) The names and addresses of any injured persons and witnesses; and
(3) The nature and location of any injury or damage arising out of the "occurrence" or offense.
e. If you report an “occurrence” to your workers compensation carrier that develops into a liability claim for
which coverage is provided by the Coverage Form, failure to report such an “occurrence” to us at the time
of the “occurrence” shall not be deemed a violation of paragraphs a., b., and c.above. However, you
shall give written notice of this “occurrence” to us as soon you become aware that this “occurrence” may
be a liability claim rather than a workers compensation claim.
f.You must see to it that the following are done in the event of an actual or anticipated “covered recall” that
may result in “product recall expense”:
(1) Give us prompt notice of any discovery or notification that “your product” must be withdrawn or
recalled. Include a description of “your product” and the reason for the withdrawal or recall;
(2) Cease any further release, shipment, consignment or any other method of distribution of like or
similar products until it has been determined that all such products are free from defects that could
be a cause of loss under the insurance.
16. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS
Paragraph 6. Representations is deleted and replaced with the following:
6. Representations
By accepting this policy, you agree:
a. The statements in the Declarations are accurate and complete;
b. Those statements are based upon representations you made to us;
c. We have issued this policy in reliance upon your representations; and
d. This policy is void in any case of fraud by you as it relates to this policy or any claim under this
policy.
We will not deny coverage under this coverage part if you unintentionally fail to disclose all hazards
existing as of the inception date of this policy. You must report to us any knowledge of an error or
omission in the description of any premises or operations intended to be covered by the Coverage Form
as soon as practicable after its discovery. However, this provision does not affect our right to collect
additional premium or exercise our right of cancellation or nonrenewal.
Includes copyrighted material of Insurance Services Office, Inc.
Page 8 of 10 CG 70 49 11 09
17. TRANSFER OF RIGHTS (BLANKET WAIVER OF SUBROGATION)
Paragraph 8. Transfer of Rights Of Recovery Against Others To Us is deleted and replaced with the
following:
8. If the insured has rights to recover all or part of any payment we have made under this Coverage Form,
those rights are transferred to us. The insured must do nothing after loss to impair them. At our request,
the insured will bring "suit" or transfer those rights to us and help us enforce them. However, if the
insured has waived rights to recover through a written contract, or if "your work" was commenced under a
letter of intent or work order, subject to a subsequent reduction to writing with customers whose
customary contracts require a waiver, we waive any right of recovery we may have under this Coverage
Form.
18. EXTENDED NOTICE OF CANCELLATION AND NONRENEWAL
Paragraph 2.b.of A. Cancellation of the COMMON POLICY CONDITIONS is deleted and replaced with the
following:
b. 60 days before the effective date of the cancellation if we cancel for any other reason.
Under SECTION IV – COMMERCIAL GENERAL LIABILITY CONDITIONS, Paragraph 9. When We Do Not
Renew is deleted and replaced with the following:
9. When We Do Not Renew
If we decide not to renew this Coverage Part, we will mail or deliver to the first Named Insured shown in
the Declarations written notice of the nonrenewal not less than 60 days before the expiration date.
If notice is mailed, proof of mailing will be sufficient proof of notice.
19. MOBILE EQUIPMENT REDEFINED
Under SECTION V - DEFINITIONS, paragraph 12. "Mobile equipment", paragraph f. (1) does not apply to self-
propelled vehicles of less than 1,000 pounds gross vehicle weight.
20. DEFINITIONS
1. SECTION V – DEFINITIONS, paragraph 4. “Coverage territory” is replaced by the following definition:
“Coverage territory” means anywhere in the world with respect to liability arising out of “bodily injury,”
“property damage,” or “personal and advertising injury,” including “personal and advertising injury”
offenses that take place through the Internet or similar electronic means of communication provided the
insured’s responsibility to pay damages is determined in a settlement to which we agree or in a “suit” on
the merits, in the United States of America (including its territories and possessions), Puerto Rico and
Canada.
2. SECTION V – DEFINITIONS is amended by the addition of the following definitions:
“Covered recall” means a recall made necessary because you or a government body has determined that
a known or suspected defect, deficiency, inadequacy, or dangerous condition in “your product” has
resulted or will result in “bodily injury” or “property damage”.
“Product Recall expenses" mean only reasonable and necessary extra costs, which result from or are
related to the recall or withdrawal of “your product” for:
a. Telephone and telegraphic communication, radio or television announcements, computer time and
newspaper advertising;
b. Stationery, envelopes, production of announcements and postage or facsimiles;
c. Remuneration paid to regular employees for necessary overtime or authorized travel expense;
d. Temporary hiring by you or by agents designated by you of persons, other than your regular
employees, to perform necessary tasks;
Includes copyrighted material of Insurance Services Office, Inc.
CG 70 49 11 09 Page 9 of 10
e. Rental of necessary additional warehouse or storage space;
f. Packaging of or transportation or shipping of defective products to the location you designate; and
g. Disposal of “your products” that cannot be reused. Disposal expenses do not include:
(1) Expenses that exceed the original cost of the materials incurred to manufacture or process such
product; and
(2) Expenses that exceed the cost of normal trash discarding or disposal, except as are necessary
to avoid “bodily injury” or “property damage”.
"Specific Perils" means fire; lightning; explosion; windstorm or hail; smoke; aircraft or vehicles; riot or civil
commotion; vandalism; leakage from fire extinguishing equipment; weight of snow, ice or sleet; or "water
damage".
"Water damage" means accidental discharge or leakage of water or steam as the direct result of the
breaking or cracking of any part of a system or appliance containing water or steam.
"Work contract" means a written agreement between you and one or more parties for work to be
performed by you or on your behalf.
Includes copyrighted material of Insurance Services Office, Inc.
Page 10 of 10 CG 70 49 11 09
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADVANTAGE
COMMERCIAL AUTOMOBILE BROAD FORM ENDORSEMENT
This endorsement modifies insurance provided under the
BUSINESS AUTO COVERAGE FORM
With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless
modified by the endorsement.
The premium for this endorsement is $ INCLUDED
1. EXTENDED CANCELLATION CONDITION
COMMON POLICY CONDITIONS -CANCELLATION, Paragraph A.2. is replaced by the following:
2. We may cancel this policy by mailing or delivering to the first Named Insured written notice of
cancellation at least:
a. 10 days before the effective date of cancellation if we cancel for nonpayment of premium; or
b. 60 days before the effective date of cancellation if we cancel for any other reason.
2. BROADFORMINSURED
SECTION II -LIABILITY COVERAGE A.1. WHO IS AN INSURED is amended by the addition of the
following:
d. Any organization you newly acquire or form, other than a partnership, joint venture or limited liability
company, and over which you maintain ownership or a majority interest, will qualify as a Named Insured.
However.
(1) Coverage under this provision is afforded only until the end of the policy period;
(2) Coverage does not apply to "accidents" or "loss" that occurred before you acquired or formed the
organization; and
(3) Coverage does not apply to an organization that is an "insured" under any other policy or would be
an "insured" but for its termination or the exhausting of its limit of insurance.
e. Any "employee" of yours using:
(1) A covered "auto" you do not own, hire or borrow, or a covered "auto" not owned by the "employee"
or a member of his or her household, while performing duties related to the conduct of your
business or your personal affairs; or
(2) An "auto" hired or rented under a contract or agreement in that "employee's" name, with your
permission, while performing duties related to the conduct of your business. However, your
"employee" does not qualify as an insured under this paragraph (2) while using a covered "auto"
rented from you or from any member of the "employee's" household.
f. Your members, if you are a limited liability company, while using a covered "auto" you do not own, hire,
or borrow. while performing duties related to the conduct of your business or your personal affairs.
g. Any person or organization with whom you agree in a written contract, written agreement or permit, to
provide insurance such as is afforded under this policy, but only with respect to your covered "autos".
This provision does not apply:
(1) Unless the written contract or agreement is executed or the permit is issued prior to the "bodily
injury" or "property damage";
lnclud€s copyrighted materia~ of Insurance Services Office, Inc.
CA 71 15 11 09 Page 1 of 5
The Conlan Company
CA2050943120
(2) To any person or organization included as an insured by an endorsement or in the Declarations; or
(3) To any lessor of "autos" unless:
(a) The lease agreement requires you to provide direct primary insurance for the lessor;
(b) The "auto" is leased without a driver; and
(c) The lease had not expired.
Leased "autos" covered under this provision will be considered covered "autos" you own and not covered
"autos" you hire.
h. Any legally incorporated organization or subsidiary in which you own more than 50% of the voting stock
on the effective date of this endorsement.
This provision does not apply to "bodily injury" or "property damage" for which an "insured" is also an
insured under any other automobile policy or would be an insured under such a policy, but for its
termination or the exhaustion of its limits of insurance, unless such policy was written to apply
specifically in excess of this policy.
3. COVERAGE EXTENSIONS-SUPPLEMENTARY PAYMENTS
Under SECTION II-LIABILITY COVERAGE, A.2.a. Supplementary Payments, paragraphs (2) and (4) are
deleted and replaced with the following:
(2) Up to $2500 for the cost of bail bonds (including bonds for related traffic law violations) required because
of an "accident" we cover. We do not have to furnish these bonds.
(4) All reasonable expenses incurred by the "insured" at our request, including actual loss of earnings up to
$500 a day because of time off from work.
4. AMENDED FELLOW EMPLOYEE EXCLUSION
SECTION II -LIABILITY COVERAGE, B. EXCLUSIONS, paragraph 5. Fellow Employee is deleted and
replaced by the following:
5. Fellow Employee
"Bodily injury" to:
a. Any fellow "employee" of the "insured" arising out of and in the course of the fellow "employee's"
employment or while performing duties related to the conduct of your business. However, this
exclusion does not apply to your "employees" that are officers, managers, supervisors or above.
Coverage is excess over any other collectible insurance.
b. The spouse, child, parent, brother or sister of that fellow "employee" as a consequence of
paragraph a. above.
5. HIRED AUTO PHYSICAL DAMAGE COVERAGE AND LOSS OF USE EXPENSE
A. Under SECTION Ill -PHYSICAL DAMAGE COVERAGE, A. COVERAGE, the following is added:
If any of your owned covered "autos" are covered for Physical Damage, we will provide Physical Damage
coverage to "autos" that you or your "employees" hire or borrow, under your name or the "employee's"
name, for the purpose of doing your work. We will provide coverage equal to the broadest physical
damage coverage applicable to any covered "auto" shown in the Declarations, Item Three, Schedule of
Covered Autos You Own, or on any endorsements amending this schedule.
B. Under SECTION Ill -PHYSICAL DAMAGE COVERAGE, A.4. COVERAGE EXTENSIONS, paragraph
b. Loss of Use Expenses is deleted and replaced with the following:
b. Loss Of Use Expenses
Page 2 of 5
For Hired Auto Physical Damage, we will pay expenses for which an "insured" becomes legally
responsible to pay for loss of use of a vehicle rented or hired without a driver, under a written rental
contract or agreement. We will pay for loss of use expenses if caused by:
Includes copyrighted material of Insurance Services Office, Inc.
CA711511 09
(1) Other than collision, only if the Declarations indicate that Comprehensive Coverage is provided
for any covered "auto";
(2) Specified Causes of Loss, only if the Declarations indicate that Specified Causes Of Loss
Coverage is provided for any covered "auto"; or
(3) Collision, only if the Declarations indicate that Collision Coverage is provided for any covered
"auto".
However, the most we will pay for any expenses for loss of use is $30 per day, to a maximum of
$2,000.
C. Under SECTION IV-BUSINESS AUTO CONDITIONS, paragraph 5.b. Other Insurance is deleted and
replaced by the following:
b. For Hired Auto Physical Damage Coverage, the following are deemed to be covered "autos" you own:
1. Any covered "auto" you lease, hire, rent or borrow; and
2. Any covered "auto" hired or rented by your "employee" under a contract in that individual
"employee's" name, with your permission, while performing duties related to the conduct of your
business.
However, any "auto" that is leased, hired, rented or borrowed with a driver is not a covered "auto",
nor is any "auto" you hire from any of your "employees", partners (if you are a partnership),
members (if you are a limited liability company), or members of their households.
6. LOAN OR LEASE GAP COVERAGE
Under SECTION Ill -PHYSICAL DAMAGE COVERAGE, A. COVERAGE, the following is added:
If a covered "auto" is owned or leased and if we provide Physical Damage Coverage on it, we will pay, in the
event of a covered total "loss", any unpaid amount due on the lease or loan for a covered "auto", less:
(a) The amount paid under the Physical Damage Coverage Section of the policy; and
(b) Any:
(1) Overdue lease or loan payments including penalties, interest or other charges resulting from
overdue payments at the time of the "loss";
(2) Financial penalties imposed under a lease for excessive use, abnormal wear and tear or high
mileage;
(3) Costs for extended warranties, Credit Life Insurance, Health, Accident or Disability Insurance
purchased with the loan or lease;
(4) Security deposits not refunded by a lessor; and
(5) Carry-over balances from previous loans or leases.
7. RENTAL REIMBURSEMENT
SECTION Ill -PHYSICAL DAMAGE COVERAGE, A. COVERAGE, paragraph 4. Coverage Extensions is
deleted and replaced by the following:
4. Coverage Extensions
(a) We will pay up to $75 per day to a maximum of $2000 for transportation expense incurred by you
because of covered "loss". We will pay only for those covered "autos" for which you carry Collision
Coverage or either Comprehensive Coverage or Specified Causes of Loss Coverage. We will pay
for transportation expenses incurred during the period beginning 24 hours after the covered "loss"
and ending, regardless of the policy's expiration, when the covered "auto" is returned to use or we
pay for its "loss". This coverage is in addition to the otherwise applicable coverage you have on a
covered "auto". No deductibles apply to this coverage.
(b) This coverage does not apply while there is a spare or reserve "auto" available to you for your
operation.
Includes copyrighted material of Insurance Services Office, Inc.
CA 71 15 11 09 Page 3 of 5
8. AIRBAG COVERAGE
SECTION Ill -PHYSICAL DAMAGE, B. EXCLUSIONS, Paragraph 3. is deleted and replaced by the
following:
We will not pay for "loss" caused by or resulting from any of the following unless caused by other "loss" that is
covered by this insurance:
a. Wear and tear, freezing, mechanical or electrical breakdown. However, this exclusion does not include
the discharge of an airbag.
b. Blowouts, punctures or other road damage to tires.
9. GLASS REPAIR-WAIVER OF DEDUCTIBLE
SECTION Ill-PHYSICAL DAMAGE COVERAGE, D. DEDUCTIBLE is amended to add the following:
No deductible applies to glass damage if the glass is repaired rather than replaced.
10. COLLISION COVERAGE-WAIVER OF DEDUCTIBLE
SECTION Ill -PHYSICAL DAMAGE COVERAGE, D. DEDUCTIBLE is amended to add the following:
When there is a "loss" to your covered "auto" insured for Collision Coverage, no deductible will apply if the
"loss" was caused by a collision with another "auto" insured by us.
11. KNOWLEDGE OF ACCIDENT
SECTION IV-BUSINESS AUTO CONDITIONS, A. LOSS CONDITIONS, 2. DUTIES IN THE EVENT OF
ACCIDENT, CLAIM, SUIT OR LOSS, paragraph a. is deleted and replaced by the following:
a. You must see to it that we are notified as soon as practicable of an "accident", claim, "suit" or "loss".
Knowledge of an "accident", claim, "suit" or "loss" by your "employees" shall not, in itself, constitute
knowledge to you unless one of your partners, executive officers, directors, managers, or members (if
you are a limited liability company) has knowledge of the "accident", claim, "suit" or "loss". Notice should
include:
(1) How, when and where the "accident" or "loss" occurred;
(2) The "insured's" name and address; and
(3) To the extent possible, the names and addresses of any injured persons and witnesses.
12. TRANSFER OF RIGHTS (BLANKET WAIVER OF SUBROGATION)
SECTION IV-BUSINESS AUTO CONDITIONS A.5. TRANSFER OF RIGHTS OF RECOVERY AGAINST
OTHERS TO US is deleted and replaced by the following:
If any person or organization to or for whom we make payment under this Coverage Form has rights to
recover damages from another, those rights are transferred to us. That person or organization must do
everything necessary to secure our rights and must do nothing after "accident" or "loss" to impair them.
However, if the insured has waived rights to recover through a written contract, or if your work was
commenced under a letter of intent or work order, subject to a subsequent reduction in writing with customers
whose customary contracts require a waiver, we waive any right of recovery we may have under this
Coverage Form.
13. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS
SECTION IV-BUSINESS AUTO CONDITIONS, B. GENERAL CONDITIONS, 2. CONCEALMENT,
MISREPRESENTATION OR FRAUD is amended by the addition of the following:
We will not deny coverage under this Coverage Form if you unintentionally fail to disclose all hazards existing
as of the inception date of this policy. You must report to us any knowledge of an error or omission in your
representations as soon as practicable after its discovery. This provision does not affect our right to collect
additional premium or exercise our right of cancellation or non-renewal.
Includes copyrighted material of Insurance Services Office, Inc.
Page 4 of 5 CA 71 15 11 09
14. BLANKET COVERAGE FOR CERTAIN OPERATIONS IN CONNECTION WITH RAILROADS
When required by written contract or written agreement, the definition of "insured contract" is amended as
follows:
The exception contained in paragraph H.3. relating to construction or demolition operations on or within
50 feet of a railroad; and
Paragraph H.a.
are deleted with respect to the use of a covered "auto" in operations for, or affecting, a railroad.
Includes copyrighted material of Insurance Services Office, Inc.
CA 7115 11 09 Page 5 of 5
This page has been left blank intentionally.
The Conlan Company WC2050942140
This page has been left blank intentionally.
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 – Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 – Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 – Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 – Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contractor’s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 – Contractor’s Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and “Or-Equals” ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 – Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 – City’s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on City’s Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 – City’s Observation Status During Construction ........................................................................... 27
8.01 City’s Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 – Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 – Completion .................................................................................................................................. 32
12.01 Contractor’s Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 – Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 – Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos—Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day – A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw – City’s on-line, electronic document management and collaboration system.
5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract—The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents—Those items that make up the contract and which must include the
Agreement, and it’s attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non-Resident Bidder
iii. Prequalification Statement
c. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l. Supplementary Conditions
m. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project’s Contract Documents
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor—The individual or entity with whom Developer has entered into the Agreement.
11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer – An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings—That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer—The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
16. Final Inspection – Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements—A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone—A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non-Participating Change Order—A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order—A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans – See definition of Drawings.
24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor’s plan to accomplish the Work within the Contract Time.
25. Project—The Work to be performed under the Contract Documents.
26. Project Representative—The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting – An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples—Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications—That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions – That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor—An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent – The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions—That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
41. Work—The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non-Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City’s written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or
the word “Supply,” or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 2 – PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City’s written interpretation or clarification.
ARTICLE 4 – BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor’s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. The certificate of insurance shall document the City, an as “Additional Insured” on all
liability policies.
2. The Contractor’s general liability insurance shall include a, “per project” or “per location”,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor’s obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage’s and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor’s insurance.
4.04 Contractor’s Insurance
A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers’ Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers’ compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor’s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U”
coverage’s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”,
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor’s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: ____________________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a “Right of Entry Agreement” with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor’s use of private and/or construction access roads crossing said railroad company’s
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor’s operations and work cross, occupy, or touch railroad property:
a. General Aggregate: _____________________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : _____________________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad company’s right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company’s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company’s property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor’s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor’s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City’s written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or “or-equal” item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an “or-equal” item, in which
case review and approval of the proposed item may, in City’s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City’s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor’s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or
“or-equal” at Contractor’s expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City’s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City’s determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor’s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor’s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City’s safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any,
with which City’s employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor’s designated safety representative at the Site.
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City’s review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City’s Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City’s review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City’s review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor’s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor’s warranty and guarantee.
B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor’s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor’s obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor’s responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional’s written approval when
submitted to City.
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City’s
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 6 – OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City’s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City’s employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor’s Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor’s Work except for latent defects in the work provided by others.
ARTICLE 7 – CITY’S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City’s Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor’s failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7.03 Compliance with Safety Program
While at the Site, City’s employees and representatives shall comply with the specific applicable
requirements of Contractor’s safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City’s Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City’s representative during construction are
set forth in the Contract Documents.
A. City’s Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor’s executed Work. Based on
information obtained during such visits and observations, City’s Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City’s Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City’s Project Representative’s visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City’s Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City’s Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City’s Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City’s written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 – CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor’s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to
perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City’s special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor’s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City’s written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor’s obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor’s services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants,
employees, and City’s other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City’s rights and remedies under this
Paragraph 11.09.
ARTICLE 12 – COMPLETION
12.01 Contractor’s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor’s
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 – SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 – MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
SECTION 01 31 19
PRECONSTRUCTION MEETING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Provisions for the preconstruction meeting to be held prior to the start of Work to
clarify construction contract administration procedures
B. Deviations from this City of Fort Worth Standard Specification
1. No construction schedule required unless requested by the City.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Attend preconstruction meeting.
2. Representatives of Contractor, subcontractors and suppliers attending meetings
shall be qualified and authorized to act on behalf of the entity each represents.
3. Meeting administered by City may be tape recorded.
a. If recorded, tapes will be used to prepare minutes and retained by City for
future reference.
B. Preconstruction Meeting
1. A preconstruction meeting will be held within 14 days after the delivery of the
distribution package to the City.
a. The meeting will be scheduled and administered by the City.
2. The Project Representative will preside at the meeting, prepare the notes of the
meeting and distribute copies of same to all participants who so request by fully
completing the attendance form to be circulated at the beginning of the meeting.
3. Attendance shall include:
a. Developer and Consultant
b. Contractor's project manager
c. Contractor's superintendent
d. Any subcontractor or supplier representatives whom the Contractor may desire
to invite or the City may request
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor’s work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
i. Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
l. Insurance Renewals
m. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre-Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City’s representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
jj. Questions or Comments
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
[Insert Project Name]
[Insert Project Number]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 32 33 - 1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
SECTION 01 32 33
PRECONSTRUCTION VIDEO
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the
vicinity of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
SECTION 01 33 00
DAP SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General methods and requirements of submissions applicable to the following
Work-related submittals:
a. Shop Drawings
b. Product Data (including Standard Product List submittals)
c. Samples
d. Mock Ups
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Notify the City in writing, at the time of submittal, of any deviations in the
submittals from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently in advance of
performing the related Work or other applicable activities, or within the time
specified in the individual Work Sections, of the Specifications.
b. Contractor is responsible such that the installation will not be delayed by
processing times including, but not limited to:
a) Disapproval and resubmittal (if required)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
g) Similar sequenced activities
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
01 33 00 - 2
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other
contractor.
B. Submittal Numbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
1. Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) “By this submittal, I hereby represent that I have determined and verified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
2. The Project title and number
3. Contractor identification
4. The names of:
a. Contractor
b. Supplier
c. Manufacturer
5. Identification of the product, with the Specification Section number, page and
paragraph(s)
6. Field dimensions, clearly identified as such
7. Relation to adjacent or critical features of the Work or materials
8. Applicable standards, such as ASTM or Federal Specification numbers
9. Identification by highlighting of deviations from Contract Documents
10. Identification by highlighting of revisions on resubmittals
11. An 8-inch x 3-inch blank space for Contractor and City stamps
F. Shop Drawings
1. As specified in individual Work Sections includes, but is not necessarily limited to:
a. Custom-prepared data such as fabrication and erection/installation (working)
drawings
b. Scheduled information
c. Setting diagrams
d. Actual shopwork manufacturing instructions
e. Custom templates
f. Special wiring diagrams
g. Coordination drawings
h. Individual system or equipment inspection and test reports including:
1) Performance curves and certifications
i. As applicable to the Work
2. Details
a. Relation of the various parts to the main members and lines of the structure
b. Where correct fabrication of the Work depends upon field measurements
1) Provide such measurements and note on the drawings prior to submitting
for approval.
G. Product Data
1. For submittals of product data for products included on the City’s Standard Product
List, clearly identify each item selected for use on the Project.
2. For submittals of product data for products not included on the City’s Standard
Product List, submittal data may include, but is not necessarily limited to:
a. Standard prepared data for manufactured products (sometimes referred to as
catalog data)
1) Such as the manufacturer's product specification and installation
instructions
2) Availability of colors and patterns
3) Manufacturer's printed statements of compliances and applicability
4) Roughing-in diagrams and templates
5) Catalog cuts
6) Product photographs
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
7) Standard wiring diagrams
8) Printed performance curves and operational-range diagrams
9) Production or quality control inspection and test reports and certifications
10) Mill reports
11) Product operating and maintenance instructions and recommended
spare-parts listing and printed product warranties
12) As applicable to the Work
H. Samples
1. As specified in individual Sections, include, but are not necessarily limited to:
a. Physical examples of the Work such as:
1) Sections of manufactured or fabricated Work
2) Small cuts or containers of materials
3) Complete units of repetitively used products color/texture/pattern swatches
and range sets
4) Specimens for coordination of visual effect
5) Graphic symbols and units of Work to be used by the City for independent
inspection and testing, as applicable to the Work
I. Do not start Work requiring a shop drawing, sample or product data nor any material to
be fabricated or installed prior to the approval or qualified approval of such item.
1. Fabrication performed, materials purchased or on-site construction accomplished
which does not conform to approved shop drawings and data is at the Contractor's
risk.
2. The City will not be liable for any expense or delay due to corrections or remedies
required to accomplish conformity.
3. Complete project Work, materials, fabrication, and installations in conformance
with approved shop drawings, applicable samples, and product data.
J. Submittal Distribution
1. Electronic Distribution
a. Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another external FTP site approved by the
City.
b. Shop Drawings
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
b) If Contractor requires more than 1 hard copy of Shop Drawings
returned, Contractor shall submit more than the number of copies listed
above.
c. Product Data
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved
product data and samples, where required, to the job site file and elsewhere as
directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance
with the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City
does not relieve the Contractor from his/her responsibility with regard to the
fulfillment of the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the
Work with all other associated work and trades, for selecting fabrication processes,
for techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest of
the City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an
exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
comments on the submittal.
a) When returned under this code the Contractor may release the
equipment and/or material for manufacture.
b. Code 2
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c. Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to require a
resubmittal of the package.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non-conforming items that were noted.
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance.
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Handled in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor’s risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City’s
expense.
1) All subsequent reviews will be performed at times convenient to the City
and at the Contractor's expense, based on the City's or City
Representative’s then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City.
c. The need for more than 1 resubmission or any other delay in obtaining City's
review of submittals, will not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City’s
discretion.
b. Submittals deemed by the City to be not complete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a list or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents, then written notice must be
provided thereof to the Developer at least 7 Calendar Days prior to release for
manufacture.
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
9. When the shop drawings have been completed to the satisfaction of the City, the
Contractor may carry out the construction in accordance therewith and no further
changes therein except upon written instructions from the City.
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
following receipt of submittal by the City.
L. Mock ups
1. Mock Up units as specified in individual Sections, include, but are not necessarily
limited to, complete units of the standard of acceptance for that type of Work to be
used on the Project. Remove at the completion of the Work or when directed.
M. Qualifications
1. If specifically required in other Sections of these Specifications, submit a P.E.
Certification for each item required.
N. Request for Information (RFI)
1. Contractor Request for additional information
a. Clarification or interpretation of the contract documents
b. When the Contractor believes there is a conflict between Contract Documents
c. When the Contractor believes there is a conflict between the Drawings and
Specifications
1) Identify the conflict and request clarification
2. Sufficient information shall be attached to permit a written response without further
information.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
SECTION 01 31 19
PRECONSTRUCTION MEETING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Provisions for the preconstruction meeting to be held prior to the start of Work to
clarify construction contract administration procedures
B. Deviations from this City of Fort Worth Standard Specification
1. No construction schedule required unless requested by the City.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Attend preconstruction meeting.
2. Representatives of Contractor, subcontractors and suppliers attending meetings
shall be qualified and authorized to act on behalf of the entity each represents.
3. Meeting administered by City may be tape recorded.
a. If recorded, tapes will be used to prepare minutes and retained by City for
future reference.
B. Preconstruction Meeting
1. A preconstruction meeting will be held within 14 days after the delivery of the
distribution package to the City.
a. The meeting will be scheduled and administered by the City.
2. The Project Representative will preside at the meeting, prepare the notes of the
meeting and distribute copies of same to all participants who so request by fully
completing the attendance form to be circulated at the beginning of the meeting.
3. Attendance shall include:
a. Developer and Consultant
b. Contractor's project manager
c. Contractor's superintendent
d. Any subcontractor or supplier representatives whom the Contractor may desire
to invite or the City may request
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor’s work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
i. Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
l. Insurance Renewals
m. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre-Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City’s representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
jj. Questions or Comments
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
[Insert Project Name]
[Insert Project Number]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 32 33 - 1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
SECTION 01 32 33
PRECONSTRUCTION VIDEO
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the
vicinity of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
SECTION 01 33 00
DAP SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General methods and requirements of submissions applicable to the following
Work-related submittals:
a. Shop Drawings
b. Product Data (including Standard Product List submittals)
c. Samples
d. Mock Ups
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Notify the City in writing, at the time of submittal, of any deviations in the
submittals from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently in advance of
performing the related Work or other applicable activities, or within the time
specified in the individual Work Sections, of the Specifications.
b. Contractor is responsible such that the installation will not be delayed by
processing times including, but not limited to:
a) Disapproval and resubmittal (if required)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
g) Similar sequenced activities
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
01 33 00 - 2
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other
contractor.
B. Submittal Numbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
1. Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) “By this submittal, I hereby represent that I have determined and verified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
2. The Project title and number
3. Contractor identification
4. The names of:
a. Contractor
b. Supplier
c. Manufacturer
5. Identification of the product, with the Specification Section number, page and
paragraph(s)
6. Field dimensions, clearly identified as such
7. Relation to adjacent or critical features of the Work or materials
8. Applicable standards, such as ASTM or Federal Specification numbers
9. Identification by highlighting of deviations from Contract Documents
10. Identification by highlighting of revisions on resubmittals
11. An 8-inch x 3-inch blank space for Contractor and City stamps
F. Shop Drawings
1. As specified in individual Work Sections includes, but is not necessarily limited to:
a. Custom-prepared data such as fabrication and erection/installation (working)
drawings
b. Scheduled information
c. Setting diagrams
d. Actual shopwork manufacturing instructions
e. Custom templates
f. Special wiring diagrams
g. Coordination drawings
h. Individual system or equipment inspection and test reports including:
1) Performance curves and certifications
i. As applicable to the Work
2. Details
a. Relation of the various parts to the main members and lines of the structure
b. Where correct fabrication of the Work depends upon field measurements
1) Provide such measurements and note on the drawings prior to submitting
for approval.
G. Product Data
1. For submittals of product data for products included on the City’s Standard Product
List, clearly identify each item selected for use on the Project.
2. For submittals of product data for products not included on the City’s Standard
Product List, submittal data may include, but is not necessarily limited to:
a. Standard prepared data for manufactured products (sometimes referred to as
catalog data)
1) Such as the manufacturer's product specification and installation
instructions
2) Availability of colors and patterns
3) Manufacturer's printed statements of compliances and applicability
4) Roughing-in diagrams and templates
5) Catalog cuts
6) Product photographs
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
7) Standard wiring diagrams
8) Printed performance curves and operational-range diagrams
9) Production or quality control inspection and test reports and certifications
10) Mill reports
11) Product operating and maintenance instructions and recommended
spare-parts listing and printed product warranties
12) As applicable to the Work
H. Samples
1. As specified in individual Sections, include, but are not necessarily limited to:
a. Physical examples of the Work such as:
1) Sections of manufactured or fabricated Work
2) Small cuts or containers of materials
3) Complete units of repetitively used products color/texture/pattern swatches
and range sets
4) Specimens for coordination of visual effect
5) Graphic symbols and units of Work to be used by the City for independent
inspection and testing, as applicable to the Work
I. Do not start Work requiring a shop drawing, sample or product data nor any material to
be fabricated or installed prior to the approval or qualified approval of such item.
1. Fabrication performed, materials purchased or on-site construction accomplished
which does not conform to approved shop drawings and data is at the Contractor's
risk.
2. The City will not be liable for any expense or delay due to corrections or remedies
required to accomplish conformity.
3. Complete project Work, materials, fabrication, and installations in conformance
with approved shop drawings, applicable samples, and product data.
J. Submittal Distribution
1. Electronic Distribution
a. Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another external FTP site approved by the
City.
b. Shop Drawings
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
b) If Contractor requires more than 1 hard copy of Shop Drawings
returned, Contractor shall submit more than the number of copies listed
above.
c. Product Data
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved
product data and samples, where required, to the job site file and elsewhere as
directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance
with the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City
does not relieve the Contractor from his/her responsibility with regard to the
fulfillment of the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the
Work with all other associated work and trades, for selecting fabrication processes,
for techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest of
the City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an
exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
comments on the submittal.
a) When returned under this code the Contractor may release the
equipment and/or material for manufacture.
b. Code 2
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c. Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to require a
resubmittal of the package.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non-conforming items that were noted.
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance.
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Handled in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor’s risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City’s
expense.
1) All subsequent reviews will be performed at times convenient to the City
and at the Contractor's expense, based on the City's or City
Representative’s then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City.
c. The need for more than 1 resubmission or any other delay in obtaining City's
review of submittals, will not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City’s
discretion.
b. Submittals deemed by the City to be not complete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a list or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents, then written notice must be
provided thereof to the Developer at least 7 Calendar Days prior to release for
manufacture.
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
9. When the shop drawings have been completed to the satisfaction of the City, the
Contractor may carry out the construction in accordance therewith and no further
changes therein except upon written instructions from the City.
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
following receipt of submittal by the City.
L. Mock ups
1. Mock Up units as specified in individual Sections, include, but are not necessarily
limited to, complete units of the standard of acceptance for that type of Work to be
used on the Project. Remove at the completion of the Work or when directed.
M. Qualifications
1. If specifically required in other Sections of these Specifications, submit a P.E.
Certification for each item required.
N. Request for Information (RFI)
1. Contractor Request for additional information
a. Clarification or interpretation of the contract documents
b. When the Contractor believes there is a conflict between Contract Documents
c. When the Contractor believes there is a conflict between the Drawings and
Specifications
1) Identify the conflict and request clarification
2. Sufficient information shall be attached to permit a written response without further
information.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
01 45 23 - 1
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another form of distribution approved
by the City.
01 45 23 - 2
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised August 30, 2013
Landmark Quebec Addition
102418
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City’s Project Representative
4. Provide City’s Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised July 1, 2011
Landmark Quebec Addition
102418
SECTION 01 55 26
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative procedures for:
a. Street Use Permit
b. Modification of approved traffic control
c. Removal of Street Signs
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 34 71 13 – Traffic Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES
A. Reference Standards
1. Reference standards cited in this specification refer to the current reference standard
published at the time of the latest revision date logged at the end of this
specification, unless a date is specifically cited.
2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
1.4 ADMINISTRATIVE REQUIREMENTS
A. Traffic Control
1. General
a. When traffic control plans are included in the Drawings, provide Traffic
Control in accordance with Drawings and Section 34 71 13.
b. When traffic control plans are not included in the Drawings, prepare traffic
control plans in accordance with Section 34 71 13 and submit to City for
review.
1) Allow minimum 10 working days for review of proposed Traffic Control.
B. Street Use Permit
1. Prior to installation of Traffic Control, a City Street Use Permit is required.
a. To obtain Street Use Permit, submit Traffic Control Plans to City
Transportation and Public Works Department.
01 55 26 - 2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised July 1, 2011
Landmark Quebec Addition
102418
1) Allow a minimum of 5 working days for permit review.
2) Contractor’s responsibility to coordinate review of Traffic Control plans for
Street Use Permit, such that construction is not delayed.
C. Modification to Approved Traffic Control
1. Prior to installation traffic control:
a. Submit revised traffic control plans to City Department Transportation and
Public Works Department.
1) Revise Traffic Control plans in accordance with Section 34 71 13.
2) Allow minimum 5 working days for review of revised Traffic Control.
3) It is the Contractor’s responsibility to coordinate review of Traffic Control
plans for Street Use Permit, such that construction is not delayed.
D. Removal of Street Sign
1. If it is determined that a street sign must be removed for construction, then contact
City Transportation and Public Works Department, Signs and Markings Division to
remove the sign.
E. Temporary Signage
1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
requirements of the latest edition of the Texas Manual on Uniform Traffic Control
Devices (MUTCD).
2. Install temporary sign before the removal of permanent sign.
3. When construction is complete, to the extent that the permanent sign can be
reinstalled, contact the City Transportation and Public Works Department, Signs
and Markings Division, to reinstall the permanent sign.
F. Traffic Control Standards
1. Traffic Control Standards can be found on the City’s Buzzsaw website.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
01 55 26 - 3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised July 1, 2011
Landmark Quebec Addition
102418
Revision Log
DATE NAME SUMMARY OF CHANGE
01 71 23 - 1
DAP CONSTRUCTION STAKING AND SURVEY
Page 1 of 4
CITY OF FORT WORTH Lonestar Business Park
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418
Revised April 7, 2014
SECTION 01 71 23 1
CONSTRUCTION STAKING AND SURVEY 2
PART 1 - GENERAL 3
1.1 SUMMARY 4
A. Section Includes: 5
1. Requirements for construction staking and construction survey 6
B. Deviations from this City of Fort Worth Standard Specification 7
1. None. 8
C. Related Specification Sections include, but are not necessarily limited to: 9
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10
2. Division 1 – General Requirements 11
1.2 PRICE AND PAYMENT PROCEDURES 12
A. Measurement and Payment 13
1. Construction Staking 14
a. Measurement 15
1) This Item is considered subsidiary to the various Items bid. 16
b. Payment 17
1) The work performed and the materials furnished in accordance with this 18
Item are subsidiary to the various Items bid and no other compensation will 19
be allowed. 20
2. Construction Survey 21
a. Measurement 22
1) This Item is considered subsidiary to the various Items bid. 23
b. Payment 24
1) The work performed and the materials furnished in accordance with this 25
Item are subsidiary to the various Items bid and no other compensation will 26
be allowed. 27
1.3 REFERENCES [NOT USED] 28
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 29
1.5 SUBMITTALS 30
A. Submittals, if required, shall be in accordance with Section 01 33 00. 31
B. All submittals shall be approved by the City prior to delivery. 32
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS 33
A. Certificates 34
1. Provide certificate certifying that elevations and locations of improvements are in 35
conformance or non-conformance with requirements of the Contract Documents. 36
a. Certificate must be sealed by a registered professional land surveyor in the 37
State of Texas. 38
01 71 23 - 2
DAP CONSTRUCTION STAKING AND SURVEY
Page 2 of 4
CITY OF FORT WORTH Lonestar Business Park
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418
Revised April 7, 2014
B. Field Quality Control Submittals 1
1. Documentation verifying accuracy of field engineering work. 2
1.7 CLOSEOUT SUBMITTALS [NOT USED] 3
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4
1.9 QUALITY ASSURANCE 5
A. Construction Staking 6
1. Construction staking will be performed by the City. 7
2. Coordination 8
a. Contact City’s Project Representative at least 2 weeks in advance for 9
scheduling of Construction Staking. 10
b. It is the Contractor’s responsibility to coordinate staking such that construction 11
activities are not delayed or negatively impacted. 12
3. General 13
a. Contractor is responsible for preserving and maintaining stakes furnished by 14
City. 15
b. If in the opinion of the City, a sufficient number of stakes or markings have 16
been lost, destroyed or disturbed, by Contractor’s neglect, such that the 17
contracted Work cannot take place, then the Contractor will be required to pay 18
the City for new staking with a 25 percent markup. The cost for staking will be 19
deducted from the payment due to the Contractor for the Project. 20
B. Construction Survey 21
1. Construction Survey will be performed by the City. 22
2. Coordination 23
a. Contractor to verify that control data established in the design survey remains 24
intact. 25
b. Coordinate with the City prior to field investigation to determine which 26
horizontal and vertical control data will be required for construction survey. 27
c. It is the Contractor’s responsibility to coordinate Construction Survey such that 28
construction activities are not delayed or negatively impacted. 29
d. Notify City if any control data needs to be restored or replaced due to damage 30
caused during construction operations. 31
1) City shall perform replacements and/or restorations. 32
3. General 33
a. Construction survey will be performed in order to maintain complete and 34
accurate logs of control and survey work as it progresses for Project Records. 35
b. The Contractor will need to ensure coordination is maintained with the City to 36
perform construction survey to obtain construction features, including but not 37
limited to the following: 38
1) All Utility Lines 39
a) Rim and flowline elevations and coordinates for each manhole or 40
junction structure 41
2) Water Lines 42
a) Top of pipe elevations and coordinates for waterlines at the following 43
locations: 44
(1) Every 250 linear feet 45
01 71 23 - 3
DAP CONSTRUCTION STAKING AND SURVEY
Page 3 of 4
CITY OF FORT WORTH Lonestar Business Park
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418
Revised April 7, 2014
(2) Horizontal and vertical points of inflection, curvature, etc. (All 1
Fittings) 2
(3) Cathodic protection test stations 3
(4) Sampling stations 4
(5) Meter boxes/vaults (All sizes) 5
(6) Fire lines 6
(7) Fire hydrants 7
(8) Gate valves 8
(9) Plugs, stubouts, dead-end lines 9
(10) Air Release valves (Manhole rim and vent pipe) 10
(11) Blow off valves (Manhole rim and valve lid) 11
(12) Pressure plane valves 12
(13) Cleaning wyes 13
(14) Casing pipe (each end) 14
b) Storm Sewer 15
(1) Top of pipe elevations and coordinates at the following locations: 16
(a) Every 250 linear feet 17
(b) Horizontal and vertical points of inflection, curvature, etc. 18
c) Sanitary Sewer 19
(1) Top of pipe elevations and coordinates for sanitary sewer lines at 20
the following locations: 21
(a) Every 250 linear feet 22
(b) Horizontal and vertical points of inflection, curvature, etc. 23
(c) Cleanouts 24
c. Construction survey will be performed in order to maintain complete and 25
accurate logs of control and survey work associated with meeting or exceeding 26
the line and grade required by these Specifications. 27
d. The Contractor will need to ensure coordination is maintained with the City to 28
perform construction survey and to verify control data, including but not 29
limited to the following: 30
1) Established benchmarks and control points provided for the Contractor’s 31
use are accurate 32
2) Benchmarks were used to furnish and maintain all reference lines and 33
grades for tunneling 34
3) Lines and grades were used to establish the location of the pipe 35
4) Submit to the City copies of field notes used to establish all lines and 36
grades and allow the City to check guidance system setup prior to 37
beginning each tunneling drive. 38
5) Provide access for the City to verify the guidance system and the line and 39
grade of the carrier pipe on a daily basis. 40
6) The Contractor remains fully responsible for the accuracy of the work and 41
the correction of it, as required. 42
7) Monitor line and grade continuously during construction. 43
8) Record deviation with respect to design line and grade once at each pipe 44
joint and submit daily records to City. 45
9) If the installation does not meet the specified tolerances, immediately notify 46
the City and correct the installation in accordance with the Contract 47
Documents. 48
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 49
01 71 23 - 4
DAP CONSTRUCTION STAKING AND SURVEY
Page 4 of 4
CITY OF FORT WORTH Lonestar Business Park
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Project Number: 102418
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED] 1
1.12 WARRANTY [NOT USED] 2
PART 2 - PRODUCTS [NOT USED] 3
PART 3 - EXECUTION 4
3.1 INSTALLERS [NOT USED] 5
3.2 EXAMINATION [NOT USED] 6
3.3 PREPARATION [NOT USED] 7
3.4 APPLICATION 8
3.5 REPAIR / RESTORATION [NOT USED] 9
3.6 RE-INSTALLATION [NOT USED] 10
3.7 FIELD [OR] SITE QUALITY CONTROL 11
A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the 12
City in accordance with this Specification. 13
B. Do not change or relocate stakes or control data without approval from the City. 14
3.8 SYSTEM STARTUP [NOT USED] 15
3.9 ADJUSTING [NOT USED] 16
3.10 CLEANING [NOT USED] 17
3.11 CLOSEOUT ACTIVITIES [NOT USED] 18
3.12 PROTECTION [NOT USED] 19
3.13 MAINTENANCE [NOT USED] 20
3.14 ATTACHMENTS [NOT USED] 21
END OF SECTION 22
23
Revision Log
DATE NAME SUMMARY OF CHANGE
24
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
SECTION 01 77 19
CLOSEOUT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for closing out a contract
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Guarantees, Bonds and Affidavits
1. No application for final payment will be accepted until all guarantees, bonds,
certificates, licenses and affidavits required for Work or equipment as specified are
satisfactorily filed with the City.
B. Release of Liens or Claims
1. No application for final payment will be accepted until satisfactory evidence of
release of liens has been submitted to the City.
1.5 SUBMITTALS
A. Submit all required documentation to City’s Project Representative.
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 CLOSEOUT PROCEDURE
A. Prior to requesting Final Inspection, submit:
1. Project Record Documents in accordance with Section 01 78 39
2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
01 74 23.
C. Final Inspection
1. After final cleaning, provide notice to the City Project Representative that the Work
is completed.
a. The City will make an initial Final Inspection with the Contractor present.
b. Upon completion of this inspection, the City will notify the Contractor, in
writing within 10 business days, of any particulars in which this inspection
reveals that the Work is defective or incomplete.
2. Upon receiving written notice from the City, immediately undertake the Work
required to remedy deficiencies and complete the Work to the satisfaction of the
City.
3. Upon completion of Work associated with the items listed in the City's written
notice, inform the City, that the required Work has been completed. Upon receipt
of this notice, the City, in the presence of the Contractor, will make a subsequent
Final Inspection of the project.
4. Provide all special accessories required to place each item of equipment in full
operation. These special accessory items include, but are not limited to:
a. Specified spare parts
b. Adequate oil and grease as required for the first lubrication of the equipment
c. Initial fill up of all chemical tanks and fuel tanks
d. Light bulbs
e. Fuses
f. Vault keys
g. Handwheels
h. Other expendable items as required for initial start-up and operation of all
equipment
D. Notice of Project Completion
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
1. Once the City Project Representative finds the Work subsequent to Final Inspection
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
E. Supporting Documentation
1. Coordinate with the City Project Representative to complete the following
additional forms:
a. Final Payment Request
b. Statement of Contract Time
c. Affidavit of Payment and Release of Liens
d. Consent of Surety to Final Payment
e. Pipe Report (if required)
f. Contractor’s Evaluation of City
g. Performance Evaluation of Contractor
F. Letter of Final Acceptance
1. Upon review and acceptance of Notice of Project Completion and Supporting
Documentation, in accordance with General Conditions, City will issue Letter of
Final Acceptance and release the Final Payment Request for payment.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 78 23 - 1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
SECTION 01 78 23
OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Product data and related information appropriate for City's maintenance and
operation of products furnished under Contract
2. Such products may include, but are not limited to:
a. Traffic Controllers
b. Irrigation Controllers (to be operated by the City)
c. Butterfly Valves
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Schedule
1. Submit manuals in final form to the City within 30 calendar days of product
shipment to the project site.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
approved by the City prior to delivery.
1.6 INFORMATIONAL SUBMITTALS
A. Submittal Form
1. Prepare data in form of an instructional manual for use by City personnel.
2. Format
a. Size: 8 ½ inches x 11 inches
b. Paper
1) 40 pound minimum, white, for typed pages
2) Holes reinforced with plastic, cloth or metal
c. Text: Manufacturer’s printed data, or neatly typewritten
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
d. Drawings
1) Provide reinforced punched binder tab, bind in with text
2) Reduce larger drawings and fold to size of text pages.
e. Provide fly-leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
f. Cover
1) Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS".
2) List:
a) Title of Project
b) Identity of separate structure as applicable
c) Identity of general subject matter covered in the manual
3. Binders
a. Commercial quality 3-ring binders with durable and cleanable plastic covers
b. When multiple binders are used, correlate the data into related consistent
groupings.
4. If available, provide an electronic form of the O&M Manual.
B. Manual Content
1. Neatly typewritten table of contents for each volume, arranged in systematic order
a. Contractor, name of responsible principal, address and telephone number
b. A list of each product required to be included, indexed to content of the volume
c. List, with each product:
1) The name, address and telephone number of the subcontractor or installer
2) A list of each product required to be included, indexed to content of the
volume
3) Identify area of responsibility of each
4) Local source of supply for parts and replacement
d. Identify each product by product name and other identifying symbols as set
forth in Contract Documents.
2. Product Data
a. Include only those sheets which are pertinent to the specific product.
b. Annotate each sheet to:
1) Clearly identify specific product or part installed
2) Clearly identify data applicable to installation
3) Delete references to inapplicable information
3. Drawings
a. Supplement product data with drawings as necessary to clearly illustrate:
1) Relations of component parts of equipment and systems
2) Control and flow diagrams
b. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation.
c. Do not use Project Record Drawings as maintenance drawings.
4. Written text, as required to supplement product data for the particular installation:
a. Organize in consistent format under separate headings for different procedures.
b. Provide logical sequence of instructions of each procedure.
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
5. Copy of each warranty, bond and service contract issued
a. Provide information sheet for City personnel giving:
1) Proper procedures in event of failure
2) Instances which might affect validity of warranties or bonds
C. Manual for Materials and Finishes
1. Submit 5 copies of complete manual in final form.
2. Content, for architectural products, applied materials and finishes:
a. Manufacturer's data, giving full information on products
1) Catalog number, size, composition
2) Color and texture designations
3) Information required for reordering special manufactured products
b. Instructions for care and maintenance
1) Manufacturer's recommendation for types of cleaning agents and methods
2) Cautions against cleaning agents and methods which are detrimental to
product
3) Recommended schedule for cleaning and maintenance
3. Content, for moisture protection and weather exposure products:
a. Manufacturer's data, giving full information on products
1) Applicable standards
2) Chemical composition
3) Details of installation
b. Instructions for inspection, maintenance and repair
D. Manual for Equipment and Systems
1. Submit 5 copies of complete manual in final form.
2. Content, for each unit of equipment and system, as appropriate:
a. Description of unit and component parts
1) Function, normal operating characteristics and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Operating procedures
1) Start-up, break-in, routine and normal operating instructions
2) Regulation, control, stopping, shut-down and emergency instructions
3) Summer and winter operating instructions
4) Special operating instructions
c. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Alignment, adjusting and checking
d. Servicing and lubrication schedule
1) List of lubricants required
e. Manufacturer's printed operating and maintenance instructions
f. Description of sequence of operation by control manufacturer
1) Predicted life of parts subject to wear
2) Items recommended to be stocked as spare parts
g. As installed control diagrams by controls manufacturer
h. Each contractor's coordination drawings
1) As installed color coded piping diagrams
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
i. Charts of valve tag numbers, with location and function of each valve
j. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
k. Other data as required under pertinent Sections of Specifications
3. Content, for each electric and electronic system, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Circuit directories of panelboards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d. Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Adjustment and checking
f. Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h. Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Provide operation and maintenance data by personnel with the following criteria:
1. Trained and experienced in maintenance and operation of described products
2. Skilled as technical writer to the extent required to communicate essential data
3. Skilled as draftsman competent to prepare required drawings
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 – title of section removed
4/7/2014 M.Domenech Revised for DAP Application
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
SECTION 01 78 39
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Work associated with the documenting the project and recording changes to project
documents, including:
a. Record Drawings
b. Water Meter Service Reports
c. Sanitary Sewer Service Reports
d. Large Water Meter Reports
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS
A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
City’s Project Representative.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Accuracy of Records
1. Thoroughly coordinate changes within the Record Documents, making adequate
and proper entries on each page of Specifications and each sheet of Drawings and
other Documents where such entry is required to show the change properly.
2. Accuracy of records shall be such that future search for items shown in the Contract
Documents may rely reasonably on information obtained from the approved Project
Record Documents.
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
3. To facilitate accuracy of records, make entries within 24 hours after receipt of
information that the change has occurred.
4. Provide factual information regarding all aspects of the Work, both concealed and
visible, to enable future modification of the Work to proceed without lengthy and
expensive site measurement, investigation and examination.
1.10 STORAGE AND HANDLING
A. Storage and Handling Requirements
1. Maintain the job set of Record Documents completely protected from deterioration
and from loss and damage until completion of the Work and transfer of all recorded
data to the final Project Record Documents.
2. In the event of loss of recorded data, use means necessary to again secure the data
to the City's approval.
a. In such case, provide replacements to the standards originally required by the
Contract Documents.
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED]
2.2 RECORD DOCUMENTS
A. Job set
1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
charge to the Contractor, 1 complete set of all Documents comprising the Contract.
B. Final Record Documents
1. At a time nearing the completion of the Work and prior to Final Inspection, provide
the City 1 complete set of all Final Record Drawings in the Contract.
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 MAINTENANCE DOCUMENTS
A. Maintenance of Job Set
1. Immediately upon receipt of the job set, identify each of the Documents with the
title, "RECORD DOCUMENTS - JOB SET".
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
2. Preservation
a. Considering the Contract completion time, the probable number of occasions
upon which the job set must be taken out for new entries and for examination,
and the conditions under which these activities will be performed, devise a
suitable method for protecting the job set.
b. Do not use the job set for any purpose except entry of new data and for review
by the City, until start of transfer of data to final Project Record Documents.
c. Maintain the job set at the site of work.
3. Coordination with Construction Survey
a. At a minimum clearly mark any deviations from Contract Documents
associated with installation of the infrastructure.
4. Making entries on Drawings
a. Record any deviations from Contract Documents.
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
change by graphic line and note as required.
c. Date all entries.
d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
e. In the event of overlapping changes, use different colors for the overlapping
changes.
5. Conversion of schematic layouts
a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
ducts, and similar items, are shown schematically and are not intended to
portray precise physical layout.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) However, design of future modifications of the facility may require
accurate information as to the final physical layout of items which are
shown only schematically on the Drawings.
b. Show on the job set of Record Drawings, by dimension accurate to within 1
inch, the centerline of each run of items.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
ceiling plenum", "exposed", and the like).
3) Make all identification sufficiently descriptive that it may be related
reliably to the Specifications.
c. The City may waive the requirements for conversion of schematic layouts
where, in the City's judgment, conversion serves no useful purpose. However,
do not rely upon waivers being issued except as specifically issued in writing
by the City.
B. Final Project Record Documents
1. Transfer of data to Drawings
a. Carefully transfer change data shown on the job set of Record Drawings to the
corresponding final documents, coordinating the changes as required.
b. Clearly indicate at each affected detail and other Drawing a full description of
changes made during construction, and the actual location of items.
c. Call attention to each entry by drawing a "cloud" around the area or areas
affected.
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
CITY OF FORT WORTH
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS
Revised April 7, 2014
Landmark Quebec Addition
102418
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to other Documents
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy of that
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE