Loading...
HomeMy WebLinkAboutContract 54116-CO1 CSC No.54116-COI FOn-F City of Fort Worth `— Change Order Bequest Project Name: Contract 2014 WSM-A,Part 3 City Sec No.: 1 54116 Project No.(s); 56002.0500430-001780 DOE No. N/A Clty Proj.No.: 102695 Project Description: Water/Sewer replacements and pavement rehabilitation on Oscar Ave,,NE 35th St.,N.Sylvania Ave.,Akers Ave., i Morning Glory Ave.,W.Lotus Ave.,Bluebonnet Ave.,and Carnation Ave. Contractor: Woody Contractors,Inc Change Order# 0 Date: r 9/22/2020 City Project Mgr.1 Leon Wilson City Inspector: I Esteban Mortloya Jr, j Phone Number; 817-392-2387 Phone Number; 817-319-6452 Dept, Water Sewer Paving 'totals Contract Thne (Ca ender days Original Contract Amount $2,311,332.70 $785,946.51 $856,286.67 $3,953,565.78 400 Extras to Date Credits to Date Pending Change Orders(In M&C Process) Contract Cost to Date $2,311,332.70 $785,946.51 $856,286.67 $3,953,565.78 400 Amount of Proposed Change Order $0.00 $0.00 $0.00 $0.00 Revised Contract Amount $2,311,332.70 $785,946.51 $856,286.57 $3,953,665.78 400 Original Funds Available for Change Orders $115,567.00 $39,297.00 $0.00 $164,864.00 Remaining Funds Available for this CO Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT MAXALLOWABLECONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $4,941,957.23 JUSTIFICATION(REASONS)FOR CHANGE ORDER Change Order No.1 will provide Imported select fill necessary for trench backrill to replace unsuitable natural material that was encountered during water main installation. It Is understood and agreed that file acceptance of Ills Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or Incidental to,the above Change Order, Contractor's Company Name Contractor Name SgnIractor Signature Date Woody Contractors,Inc Troy Woody —a0 Inspector Date Proj t Mana Dale -t2 .11 9/23/20 20 24. Ireclor Water Dep Dale Con ruction Supervisor TPW Dept) Date 2- Sep Assistant City Attorney Date Assistant Cj y manager Date o kISep 24 2020 , Sep 25,2020 Council Action If Required M&C Number N/A M&C Dale Approved NIA OFFICIAL RECORD CITY SECRETARY FT.WORTH,TX 1F(D> r WoP. rnaj City of Fort Worth Change Order Additionq Project Name Contract 2014 WSM-A,Part 3 City Sec No.; 54116 Project No.(s): 56002-0600430.001780 DOE No, N/A City Proj,No.: 102695 Project Water/Sewer replacements and pavement rehabilitation on Oscar Ave.,NE 35th St.,N.Sylvania Ave.,Akers Ave., i Description Morning Glory Ave,,W,Lotus Ave.,Bluebonnet Ave.,and Carnation Ave. Contractor Woody Contractors,Inc Change Order:= Date: 9/22/2020 City Project Mgr. Leon Wilson City Inspector FEstebanMontoyaJr. ADDITIONS 1'f -15ERIMPTION DEPT Qt Unit Unit Cost Total 63 Imported select fill for trench backFill Water 300.00 CY $35.00 $10,500.00 Water $10,500.00 Sewer Paving Page 2 of 4 Additions Sub Total $10,500.00 r (c), -r MV0 n TI1l City of Fort Worth Change Ordor Deletions Project Name Conlract 2014 WSM-A,Part 3 City Sec No.: 54116 Project No.(s): 56002-0600430-001780 DOE No. N/A City Proj.No.: 102695 Project Description Water/Sewer replacements and pavement rehabllilation on Oscar Ave.,NE 351h St.,N.Sylvania Ave.,Akers Ave., Morning Glory Ave.,W.Lotus Ave.,Bluebonnet Ave.,and Carnation Ave. Contractor F Woody Contractors,Inc Change Order: F 71Date 9/22/2020 City Project Mgr. I Leon Wilson City Inspector. FEeban Montoya Jr. DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total 62 Water Construction Allowance Water 0.13 LS $80,000,00 $10,500.00 f i 47 t I i i i I it I it I Water $10,600.00 Sewer Paving Page 3 of 4 Deletions Sub Total 1$10,500,00 i i i MMOU Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 i Previous Change Orders Co# ._ DATE AMOUNT I I l; i I --_ -------- Total J --- -- $0.00 l { I Page 4 of 4 Contract Compliance Manager By signing I aelmowledge that I am the person responsible for the monitoring and administration of this contract,including ensuring aR pai ornrance and reporting requirements, Signature j i Leon Wilson, Jr. Name of Bmployee Project Manager P��v'saII°0TDE4 4UQTitle 'FOR), �ab-=a°F °°�°vmoo °o ATTEST: ° 4,�d dd A`�o4p 2 Owd last,j�A �QQaaaoo r Ronald P.Gonzales(Sep 25,202010' DT) Mary J, Kayser City Secretary OFFICIAL RECORD CITY SECRETARY FT.WORTH,TX