HomeMy WebLinkAboutOrdinance 24441-09-2020 Ordinance No. 24441-09-2020
AN ORDINANCE INCREASING ESTIMATED RECEIPTS AND APPROPRIATIONS IN THE
WATER AND SEWER CAPITAL PROJECTS FUND IN THE AMOUNT OF $5,520,240.00,
TRANSFERRED FROM AVAILABLE FUNDS IN THE WATER AND SEWER FUND, FOR
THE PURPOSE OF FUNDING THE 2019 WATER LINE AND SANITARY SEWER
REPLACEMENT WSM-A PROJECT; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL
ORDINANCES IN CONFLICT HEREWITH;AND PROVIDING AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2019-2020 in the
Budget of the City Manager,there shall also be increased estimated receipts and appropriations in the Water
and Sewer Capital Projects Fund in the amount of $5,520,240.00, transferred from available funds in the
Water and Sewer Fund, for the purpose of funding the 2019 Water Line and Sanitary Sewer Replacement
WSM-A project.
SECTION 2.
That should any portion, section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction, such decision, opinion or judgment shall in no way impair
the remaining portions, sections, or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 23835-09-2019 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations, in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY:
for Ronald P. Gonzales
Mack(Sep 28,2020 09:07 CDT) for Ronald P.Gonzales(Sep 28,2020 09:31 CDT)
Douglas W Black Mary J. Kayser
Sr Assistant City Attorney City Secretary
ADOPTED AND EFFECTIVE: September 22, 2020
�XAS.
r 7 r �r• I ti � f.1�li
40 old,
f
; AWOL
yl. w
4 1 A l �I+w I O �# F
�'0jai
1
.,
.-
elk JL
ANN
r
44
t ry 4i - J x F
MAYOR AND COUNCIL COMMUNICATION MAP
602019WSMA-GRATEX
wWACO,WAY�
.' WRIPLEY-WAY- ` a 411DRTH 7
CARDIFF AV -
-WILTON DR�
F r O • U O
r D, LL
b J
CHEDLAAVE 4
1NHEELM( DR ;I f
BARGE R
47
% +++SSSyyyJ}}}III{{{rrr k
BALROA DR
Pk
.I ---q�.fir - "'3`• � ���T� � r* �4 .� `�
�0RT WORT y �. TA
$L 2020
• A
�-+fit ��e� _ � '� ��" '*�i - ' S Imo►
+ ^ot
am
A .Mop
y
Ar op Is
e
7"f 44
J �F
�.� .ee
'" -0000
dit
ii
-. rl s� t
IV or
t.. : mail
rcy��
• All,
y L - I rl +y. w
Sal
�itpo
+
,
FFLP
Ir A Pw
w 1
• 'r p
L . ' 0
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 09/22/20 M&C FILE NUMBER: M&C 20-0708
LOG NAME: 602019WSMA-GRATEX
SUBJECT
(CD 6 and CD 9)Authorize Execution of a Contract with Gra-Tex Utilities, Inc.,in the Amount of$4,781,325.85,for the 2019 Water Line and
Sanitary Sewer Replacement-A Project,and Adopt Appropriation Ordinance
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the execution of a contract with Gra-Tex Utilities, Inc.,in the amount of$4,781,325.85,for the 2019 Water Line&Sanitary Sewer
Replacement-A project;and
2. Adopt the attached Appropriation Ordinance increasing receipts and appropriations in the Water&Sewer Capital Projects fund in the
amount of$5,520,240.00 for the 2019 Water Line and Sanitary Sewer Replacement-A project(City Project No. 102168)transferred from
available funds within the Water&Sewer fund.
DISCUSSION:
This Mayor and Council Communication is to authorize a construction contract for the replacement of deteriorated water and/or sanitary sewer
mains as indicated on the following streets,alley and easements:
Street From To Scope of
Work
Merida Avenue West Cantey McPherson Water
Street Avenue
Lubbock Avenue West Cantey McPherson Water/Sewer
Street Avenue
McPherson Lubbock Avenue Sandage Avenue Water
Avenue
West Bowie Merida Avenue Sandage Avenue Water
Street ] I -
Wabash Avenue West Cantey Street Park Hill Drive Water
Rogers Avenue W.Biddison Street BenbrookWater
Boulevard
Lamesa Place Rogers Avenue Benbrook Water/Sewer
Boulevard
Chedlea Avenue Kingswood Drive Wallingford Drive Water/Sewer
Alley
between West
Cantey Street Greene Avenue Parmer Avenue Sewer
and Princeton
Street
Alley between
Merida Avenue West Cantey McPherson Sewer
and Sandage Street Avenue
Avenue _
Alley North of Biddison 46 feet north,then
Biddison Street Street/Bluebonnet northeasterly 120 Sewer
Circle Intersection feet
Biddison
Biddison Street Street/Bluebonnet 180 feet east Sewer
Circle Intersection
W.Biddison South University
Bluebonnet Circle Street/Bluebonnet Drive/Bluebonnet Sewer
Circle Intersection Circle Intersection
South University South University
Drive Drive/Bluebonnet 190 feet north Sewer
Circle Intersection
In conjunction with replacement of the water mains,all connecting lead service lines will be removed and replaced.There are a total of 64 identified
lead service lines that will be replaced as part of this contract.
The project was advertised for bids on July 2 and July 9,2020 in the Fort Worth Star-Telegram.On August 6,2020,the following bids were
received:
Bidder Amount Time of Completion
Gra-Tex Utilities, Inc. $4,781,325.85 630 Calendar Days
Woody Contractors, Inc. $5,259,057.1511
Jackson Construction,Ltd. $6,554,777.00
In addition to the contract amount,$595,473.00(Water:$299,586.00;Sewer:$295,887.00)is required for project management,material testing
and inspection,and$143,441.15(Water:$72,108.70;Sewer:$71,332.45)is provided for project contingencies.
The sanitary sewer component of this project is part of the Water Department's Sanitary Sewer Overflow Initiative Program.
This project will have no impact on the Water Department's operating budget when completed.
Appropriations for the 2019 Water Line&Sanitary Sewer Replacement(WSM-A)project are as depicted below:
Existing Additional
Fund Project Total*
Appropriations Appropriations
Water&Sewer
Capital Projects $294,941.00 $5,520,240.00$5,815,181.00
Fund 56002
Project Total $294,941.00 $5,520,240:0 $5,815,181.00
*Numbers rounded for presentation purposes.
Office of Business Diversity:Gra-Tex Utilities, Inc.,is in compliance with the City's BDE Ordinance by committing to nine percent MBE
participation.The City's MBE goal on this project is seven percent.
The project is located in COUNCIL DISTRICTS 6 and 9.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that funds are currently available in the Water&Sewer fund and upon approval of the above recommendations
and adoption of the attached appropriation ordinance,funds will be available in the current capital budget,as appropriated,in the W&S Capital
Projects fund for the WSM-A project.Prior to any expenditure being incurred,the Water Department has the responsibility to validate the
availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: Chris Harder 5020
Additional Information Contact: Suby Varughese 7803