HomeMy WebLinkAboutContract 51038-R1 CSC No. 51038-R1
CITY OF FORT WORTH
FIRST RENEWAL OF AGREEMENT
WHEREAS, the City of Fort Worth, ("City"), and Hach Company, authorized to do
business in Texas ("Contractor"), entered into that certain ORIGINAL AGREEMENT (City
Secretary # 51038, M&C P-12204) for the PROJECT generally described as: Citywide
Wastewater Collection System Flow Monitoring; and
WHEREAS, the ORIGINAL AGREEMENT may be renewed up to three times as
provided by M&C P-12204; and
WHEREAS, The City and Contractor desire to renew the ORIGINAL AGREEMENT for
an additional term at the same price, said FIRST RENEWAL is available in the budget of the
Water and Sewer Capital Projects Fund, as appropriated in Ordinance# 22393-09-2016.
NOW, THEREFORE, it is agreed by the City and Contractor as follows:
Article I
The Scope of Services as set forth in the ORIGINAL AGREEMENT has not changed.
Article II
The Contractor's compensation shall be in the amount up to $132,000.00. The Term of
this renewal agreement shall be for one year, effective as of the effective date or the expenditure
of the funding, whichever occurs first.
Article III
There are no other changes to any other terms or 'conditions of the ORIGINAL
AGREEMENT.
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
First Renewal of Agreement City Secretary No. 51038
Hach Company Page I o f2
EXECUTED by each party's duly authorized representative and EFFECTIVE as of the date
subscribed by the City's designated City Manager.
City of Fort Worth Hach Company
Aw&whw a
DanaDana Burg 2020� LC'Ll1i �
Dana Burghdoff Meghan Cozzens
Assistant City Manager Program Manager
DATE: Sep 23,2020 DATE: 6/18/2020
APPROVAL RECOMMENDED:
Christopher Hard (Sep22,202012:47CDT)
Chris Harder, P.E.
Director, Water Department
APPROVED AS TO FORM AND LEGALITY:
p�� M&C: P-12204
: 1 1=o:-=d" Date: June 5, 2018
Mack(Sep 23,2020 12:21 CDT)
Douglas W. Black
Sr. Assistant City Attorney
Contract Compliance Manager
By signing I acknowledge that I am the person responsible for the monitoring and administration
ofthis contract, including ensuring all performance and rep01 iing requirements.
John Kasavich, P.E.
Project Manager
444o�a���
Qp FORr�oa�
ATTEST: �
J' 0
duo o�'.�°o
for Ronald P.Gonzales P v go=d
_p29,20201327CDT) PpQlf o00 00�c�a
ne
Maly J. Kayser ��an xA54pp
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
First Renewal of Agreement City Secretary No. 51038
Hach Company Page 2 o f2
HACH COMPANY 1 5600 Lindbergh Drive I PO Box 389 1 Loveland.Colorado 80539 1 P 970.669.3050 1 F 970.669.2932 I hach.com
June 18,2020
ATTN: John Kasavich, P.E.
Project Manager
City of Fort Worth Water Department
200 Texas Street
Fort Worth,TX 76102
RE: Contract FIRST RENEWAL
Hach Flow Monitoring Service for a Citywide Collection System
Temporary Flow Monitoring Project
City Secretary Contract No. 51038
Mr. Kasavich,
Please find attached Contract FIRST RENEWAL to the Hach Flow Monitoring Service for a Citywide
Collection System Temporary Flow Monitoring Project. This renewal request specifically addresses the
project narrative elements summarized below.
BACKGROUND
Hach Company was contracted in July 2018 and started monitoring ten (10) locations within the City of
Fort Worth's wastewater collection system in September 2018. Five (5) additional sites were installed
during the Fall of 2019 (Amendment No. 1). The monitoring contract includes data management,
reporting, maintenance, and calibrations.
FIRST RENEWAL: Addresses the solicitation of the following flow monitoring services funding amount of
$132,000 for the above referenced project.
• Desire to exercise the FIRST RENEWAL outlined in the original contract to extend the project for
one year at the current pricing. This request seeks additional funding for the above referenced
Professional Services Agreement contract value($440,000)for utilized to monitorthe fifteen(15)
locations through Fall 2021.
Under the FIRST RENEWAL request, Hach Company has integrated the estimated costs noted above by
project task shown in the table below.
Page 11
HACH COMPANY 1 5600 Lindbergh Drive I PO Box 389 1 Loveland,Colorado 80539 1 P 970.669.3050 1 F 970,669.2932 1 teach com
Item No. Description Unit of Unit Price Value
Measure Quantity
Flow Meter Unit with Non-Contact AV Sensor(includes
5 a Doppler Radar Velocity sensor or laser velocity sensor EA 0
with an ultrasonic depth sensor)and pressure depth $11,100.00 $0.00
sensor
Initial Flow Meter Installations(Includes initial site
6 calibration,coordination with the telemetry service EA 0
provider,and a final confirmation inspection within 7 $900.00 $0.00
days of installation)
Meter Site Maintenance as Required Including
Scheduled Calibrations(bi-weekly for the first 60 days
7 and then quarterly thereafter)—Monthly Servicing Fee MO 180 $600.00 $108,000.00
(per meter,up to 20 meters)
Additional Meter Site Maintenance and Calibration Site
Visits for Use as Directed/Authorized by the City
(related to additional calibration requested beyond
8 specified in the scope and related to telemetry-related EA 15 $500.00 $7,500.00
manual collects above and beyond regularly scheduled
site calibration and meter maintenance visits),Not for
Use for Regular Calibration and Maintenance visits
Flow Meter Removal(Includes final site calibrations,
9 meter cleanup and servicing and recalibration of meter EA 15 $100.00 $1,500.00
and probes prior to redeployment)
Flow Meter Redeployment Fee(includes meter site
investigations,documentation,and site selections;
installation,miscellaneous field supplies associated
10 with new installation,initial site calibration, EA 15 $900.00 $4,500.00
communications check(s)and a final confirmation
inspection to start the clock on the metering period
for that site)
Additional Data Management,Analysis and Reporting
BA#1 Monthly Data Mangement,Analysis,and Reporting Fee M0 60
(per meter,up to 20 meters)as noted in Section 30.0 $175.00 $10,500.00
"Scope of Work"
Total $132,000.00
For your convenience, a summary of the total project fees are as follows:
Contract Item Fee
Original Contract Amount $326,000.00
Amendment No. 1 $114,000.00
First Renewal $132,000.00
Amended Contract Value $572,000.00
Page 12 o
I
HACH COMPANY 1 5600 Lindbergh Drive I PO Box 389 1 Loveland.Colorado 80539 1 P 970.669.3050 1 F 970.669.2932 1 har_h.com
Please do not hesitate to contact us should you have questions or need any additional background
information concerning this matter. Thank you for your time and consideration.
Sincerely,
Cody Jeanneret
DDS Project Manager
CC: Meghan Cozzens, Program Manager, Hach Company
Richard Delgadillo, Divisional Sales Manager, Hach Company
Jim Caruso, Corporate Account Manager, Hach Company
o