HomeMy WebLinkAboutContract 49826-FP1 FORTWORTH
CSC No. 49826-FP1
WATER DEPARTMENT
ENGINEERING AND FISCAL SERVICES �(165-W
NOTICE OF PROJECT COMPLETION
DOE. Ne: N/A
Regarding contract 49826 for Slope Stabilization Sewer Mains M-280B and M-338B as required by the Water
Department as approved by City Council on 9/26/17 through M&C C-28407 the Director of the Water Department,
upon the recommendation of the Sr. Capital Projects Officer, Capital Projects Delivery,Water Department,has accepted
the project as complete.
Original Contract Prices: $1,867,535.80
Amount of Approved Change Orders: $8,800.00 Ns 1
Revised Contract Amount: $1,876,335.80
Total Cost Work Completed: $449,365.80
Less Deductions:
Liquidated Damages: Days @$650.00/Day
Other Deductions(see comments):
Total Deduction Amount: $0.00
Total Cost Work Completed: $449,365.80
Less Previous Payments: $426,897.51
Final Payment Due $22,468.29
o il � > a 1c, 1124 /20
Recommended for Acceptance Date
Assistant Director, Water Department
Christopher ep�16:08CDTG� Sep 30, 2020
Accepted Date
Director, Water Department
Dana�a & hd—eCDT) Sep 30, 2020
City Manager Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Project Name: Slope Stabilization Sewer Mains M-280B and M-338B DOE. NQ: N/A
Comments:
C) 11- /�,�'-W
Csq
City Project Numbers 100520 DOE Number 0007
Contract Name Slope Stabilization Sewer Mains M-280-B and M-338-B Estimate Number 3
Contract Limits Payment Number 3
Project Type Sewer For Period Ending 8/30/2018
Project Funding
Project Manager Deeter City Secretary Contract Number 49826
Inspectors Johnson / Johnson Contract Date 9/26/2017
Contractor HUMPHREY&MORTON CONSTRUCTION COMP Contract Time 240 CD
5136 VESTA FARLEY Days Charged to Date 64 CD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
+ 2 22,Q(as Z-1
Total Cost of Work Completed $449,365.80
Less 0 %Retained $0.00
Net Earned $449,365.80
Earned This Period $22,468.29
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $426,897.51
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $22,468.29
Monday,August 03,2020 Page 4 of 4
FORT WORTH
1 �
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name Slope Stabilization Sewer Mains M-280-B and M-338-B
Contract Limits
Project Type Sewer
City Project Numbers 100520
DOE Number 0007
Estimate Number 3 Payment Number 3 For Period Ending 8/30/2018
CD
City Secretary Contract Number 49826 Contract Time 24(FD
Contract Date 9/26/2017 Days Charged to Date 64
Project Manager Deeter Contract is 24.000 Complete
Contractor HUMPHREY&MORTON CONSTRUCTION COMP
5136 VESTA FARLEY
FORT WORTH, TX 76119
Inspectors Johnson / Johnson
Monday,August 03,2020 Page 1 of 4
City Project Numbers 100520 DOE Number 0007
Contract Name Slope Stabilization Sewer Mains M-280-B and M-338-B Estimate Number 3
Contract Limits Payment Number 3
Project Type Sewer For Period Ending 8/30/2018
Project Funding
Sewer
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
-------- ---------- — — ----- --- -- -
1 3123.0101 Unclassified Excavation b 13300 CY $28.09 $373,597.00 11970 $336,237.30
2 3124.0101 Embankment by Plan 5250 CY $28.32 $148,680.00
3 9999.000124"Secant Piles 680 VF $172.00 $116,960.00 132.25 $22,747.00
4 9999.0002 36"Secant Piles 1270 VF $376.00 $477,520.00
5 9999.0003 Concrete Coping 190 CY $533.00 $101,270.00
6 3136.0104 Twisted Gabion Mattresses 1000 CY $350.00 $350,000.00
7 3291.0100 Topsoil(6-inch) 600 CY $16.17 $9,702.00
8 3292.0400 Seeding,Hydromulch(Scor 3220 SY $3.68 $11,849.60
9 3292.0500 Seeding,Soil Retention B 3220 SY $3.26 $10,497.20
10 3293.0102 Plant 2"Tree(Cotton Woo 260 EA $633.00 $164,580.00
11 3125.0101 SWPPP >1 acre I LS $12,122.00 $12,122.00
12 9999.0004 Construction Survey 1 LS $3,595.00 $3,595.00
13 9999.0005 Construction Staking 1 LS $11,163.00 $11,163.00 0.5 $5,581.50
14 9999.0006 Construction Allowance(CO#1) 0 LS $65,000.00 $0.00
15 9999.0007 Archeological Monitoring(CO#1) 18 Da $1,100.00 $19,800.00 18 $19,800.00
C16 Archeological Digging and Identifying 1 LS $65,000.00 $65,000.00 1 $65,000.00
Artifacts(CO#1)
Sub-Total of Previous Unit $1,876,335.80 $449,365.80
Monday,August 03,2020 Page 2 of 4
City Project Numbers 100520 DOE Number 0007
Contract Name Slope Stabilization Sewer Mains M-280-B and M-338-B Estimate Number 3
Contract Limits Payment Number 3
Project Type Sewer For Period Ending 8/30/2018
Project Funding
Contract Information Summary
Original Conti-act Amount $1,867,535.80
Chamze Orders
Change Order Number 1 $8,800.00
Total Contract Price $1,876,335.80
( % Date 8/3/2020 Total Cost of Work Completed $449,365.80
Contr c orl Less 0 %Retained $0.00
(�^3
Date Net Earned $449,365.80
Inspection Supervisor Earned This Period $22,468.29
T OAJ 5,�J 1.11,01 Gi,L(�I Z-c> Retainage This Period $0.00
Date Less Liquidated Damages
Project Manager
NIA/� Days @ /Day $0.00
`tl A Date LessPavement Deficiency $0.00
MAs tt Director/TPW �/ / Less Penalty $0.00
/ �'� Sep 30,2020 Less Previous Payment $426,397.51
Christopher Hard (Sep 29,202016:08 CDT) Date y
Director/Contracting Department Plus Material on Hand Less 15% $0.00
Balance Due This Payment $22,468.29
Monday,August 03,2020 Page 3 of 4
FORTWORTH rev 03/05/07
WATER ENGINEERING & FISCAL SERVICES
FINAL STATEMENT OF CONTRACT TIME
FINAL STATEMENT NO.:3
NAME OF PROJECT: Slope Stabilization Sewer Mains M-280-B and M-338-B
PROJECT NO.: 100520 CONTRACTOR: Humphrey&Morton Const.
CITY PROJECT 100520
PERIOD FROM:06/25/18 TO: 08/03/20 FINAL INSPECTION DATE: 8/30/2018
WORK ORDER EFFECTIVE:6/25/2018 CONTRACT TIME: 240 0 WD* CD
DAY OF DAYS REASON FOR DAYS DAY OF DAYS REASON FOR DAYS
MONTH CHARGED CREDITED MONTH CHARGED CREDITED
DURING DURING
1. 16.
2. 17.
3. 18.
4. 19.
5. 20.
6. 21.
7. 22.
8• 23.
9. 24.
10. 25.
11. 26.
12. 27.
13. 28.
14. 29.
15. 30.
31.
SAT,SUN, RAIN,TOO WET, UTILITIES DAYS TOTAL
&HOLIDAYS &TOO COLD RELOCATIONS OTHERS CHARGED DAYS
THIS
PERIOD 0 0
PREVIOUS
PERIOD 64 64
TOTALS
TO DATE 64 64
*REMARKS:
i
8/3/2020
CONT CT R DATE INSP CTOR DATE
Capital Projects Deli-very,Water Department
The City of Fort\North•1000 Throckmorton Street•Fort Worth,TZ 76012-6311
(817)392-4477•Fax:(817)392-8460
FORTWORTH REV:02/22/07
Capital Projects Delivery,Water Department
CONTRACTOR'S EVALUATION OF CITY
I) PROJECT INFORMATION Date: 3-Aug-20
Name ofContraclor Project Name
Humphrey&Morton Construction Co. Slope Stabilization Sewer Mains M-280-B and M-338-B
6Vater Engineering Inspector Project Manager
David Johnson Tony Sholola
DOE Number Project Difficulty Type of Contract
Q Simple Q Routine QQ Complex ❑ water ❑� waste water ❑Storm Drainage ❑ Pavement
Initial Contract Amoum Final Cauract Amount
�Sl,867,535.80 $1,876,335.80
II)PERFORMANCE EVALUATION
0-Inadequate 1 -Deficient 2-Standard 3 -Good 4-Excellent
ELEMENT RATING ELEMENT RATING
(0-4) (0-4)
INSPECTION EVALUATION PLANS&SPECIFICATIONS
1 Availability of Inspector 4 1 Accuracy of Plans to Existing Conditions 4
2 Knowledge of Inspector 4 2 Clarity&Sufficiency of Details 4
3 Accuracy of Measured Quantities 4 3 Applicability of Specifications 4
4 Display Of Professionalism 4 4 Accuracy of Plan Quantities 4
5 Citizen Complaint Resolution 4 PROJECT MANAGER EVALUATION
6 Performance-Setting up Valve Crews, Labs 1 4 1 Knowledge And/Or Problem Resolution 4
ADMINISTRATION 2 Availability of Project Manager 4
l Change Order Processing Time 4 13 Communication 4
2 Timliness of Contractor Payments 4 4 Resolution of Utility Conflicts 4
3 Bid Opening to Pre-Con Meeting Timeframe 4
III)COMMENTS&SIGNATURES
COMMENTS
Signature Contractor
Signature Inspector &-L,41V
Signature Inspector's Supervisor
INSPECTOR'S COMMENTS
Capital Projects Delivery,Water Department
The City of Fort Worth• 1000 Throckmorton Street•Fort Worth,TL 76012-6311
(817)392-4477 •Fax:(817)392-8460
FORTWORTHREV:02/20/07
Capital Projects Delivery,Water Department
PERFORMANCE EVALUATION OF CONTRACTOR
n CONTRACTOR&PROJECT DATA
Name of Contractor Project Nance
Hmphrey&Morton Construction Co. Slope Stabilization Sewer Mains M-208-B and M-338-B
6Pater Engineering Inspector DOE Number
David Johnson N/A
IPater Engineering Luspector Project 11anager
❑Water [Z Waste Water ❑Storm Drainage ❑ Pavement Tony Sholola
Initial Contract Amount Project Difficulty
$1,867,535.80 Q Simple Q Routine Complex
Final Contract Amount Date
$1,876,335.80 8/3/2020
In PERFORMANCE EVALUATION
0-Inadequate 1-Deficient 2-Standard 3-Good 4-Excellent
ELEMENT WEIGHT(x) APPLICABLE(Y/N) RATING(0-4) MAX SCORE SCORE
1 Submission of Documents 2 Y 3 8 6
2 Public Notifications 5 Y 4 20 20
3 Plans on Site 5 Y 4 20 20
4 Field Supervision 15 Y 4 60 60
5 Work Performed 15 Y 4 60 60
6 Finished Product 15 N
7 Job Site Safety 15 Y 4 60 60
8 Traffic Control Maintenance 15 Y 4 60 60
9 Daily Clean Up 5 Y 4 20 20
10 Citizen's Complaint Resolution 5 Y 4 20 1 20
11 Property Restoration 5 N
12 After Hours Response 5 N
13 Project Completion 5 N
TOTAL ELEMENT SCORE(A) 326
BONUS PONTS(25 Maximum)(B)
TOTAL SCORE(TS) 326
III)CONTRACTOR'S RATING
Maximum Score(MS)=448 or sum of applicable element score maximums which= 328
Rating([TS/MS]r 100%) 326 / 328 = 99%
Performance Category Excellent
<20%=Inadequate 20%to<40%=Deficient 40%to<60%=Standard 60%to<80%=Good >80%=B.i-cellent
Inspector's Comments(INCLUDING EXPLANATION OF BONUS POINTS AWARDED)
Signature Inspector Signature Contractor _
Signature Inspector's Supervisor I
CONTRACTOR'S COMMENTS
Capital Projects Delivery,Water Department
The City of Fort Worth• 1000 Throckmorton Street•Fort North,TX 76012-6311
(817)392-4477•Fax: (817)392-8460
FORT WORTH
September 24,2020
Humphrey&Morton Construction Company
5136 Vesta Farley
Fort Worth,TX 76119
Re:Acceptance Letter
Project Name: Slope Stabilization Sewer Mains M-280B and M-338B
Project Type: Sewer
Project Ns: 100520
D.O.E.Ns: N/A
Contract Ns: 49826 Dated: 9/26/2017
Gentleman:
On March 23,2020 a final inspection was made on the subject project. There were no punch list items identified
at the time. The final inspection indicates that the work meets the City of Fort Worth specifications and is
therefore accepted by the City. The warranty period will start on March 23,2020,which is the date of final
inspection and will extend for (2)years in accordance with the Contract Documents.
If you have any questions concerning this letter of acceptance,please feel free to contact me at(817) 392-6054
Yours Truly,
Tony Sholola,P.E.,Assistant Director Water Department
MP /
cc: Chris Harder,P.E.,Director,Water Department
Laura Wilson,P.E.,Deputy Director,Water Department
Captain Michael Skains,Fire Department
Roger Hauser,Field Operations Superintendent,Water Department
Bill Lundvall,Field Operations Superintendent,Waste Water Department
Tony Sholola,P.E.,Project Manager
Brian Darby,P.E. Deotte Consulting,Consultant
Humphrey&Morton Construction, Contractor
David Johnson,Inspection Supervisor,Water Engineering and Fiscal Services
David Johnson,Inspector,Water Engineering and Fiscal Services
File
WATER DEPARTMENT
ENGINEERING AND FISCAL SERVICES
THE CITY OF FORT WORTH * 1000 THROCKMORTON STREET * FORT WORTH, TEXAS 76102
817-392-8240 * FAx 817-392-8195
Cp Printed on recycled paper