HomeMy WebLinkAboutContract 50436-CO2 CSC No. 50436-CO2
FORTWORTH City of Fort Worth
Change Order Request
ProjectNamef VCWRF Miscellaneous Switchgear Improvements City Sec# 1 50436
Client Project#(s)l City Project#CO2648
Projec Village Creek Water Reclamation Facility(VCWRF)-Miscellaneous Switchgear and MCC improvements for Primary
Descriptio Treatment Area
Contractorl Texsun Electrical Contractors, Inc. Change Order# 0 Date L 9/9/2020
City Project Mgr.1 Farida Goderya,PE City Inspector Nathan gray/Mike Hill
Dept. Water Totals Select Day Type
Original Contract Amount 10,765,692.00 10,765,692.00 548
Extras to Date $48,279.68 $48,279.68 302
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $10,813,971.68 $10,813,971.68 850
Amoumt of Proposed Change Order 0.00 60
Revised Contract Amount 10,813,971.68 10,813,971.68 910
Original Funds Available for Change Orders $0.00
Remaining Funds Available for this CO $0.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.45%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $13,457,115.00
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Staff concurs with the contractor's request for 60 additional calendar days on the project for the time it took to fabricate-change
two canopy structures and other related work adjustments, due to Covid-19 pandemic.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor(Name) _ (contract signature Date
Texsun Electrical Contractors, Inc. Steve Milled Doug Moulder 1 7 T3 2
t--ir--
lnspectorhnspection Supervisor Date Project Manager/Program Manager Date
Nathan Gray/Puneet Gupta,PE(GAIJ Farida Goderya Farida Goderya,PE � z< 9/25/2020
Assistant Director(Dept) I Date Director,Contracting Department(Dept) Date
Tony Sholola,PE p& s h 0 w IC, 2.5- 2_0 Chris Harder,PE I-141-k ` �' Sep 28,2020
Assistant City Attorney Date Assistant City Manager Date
Doug Blac4 � Sep 29,2020 Dana Burghdofl°. ., Sep29,2020
Council Action(if required)
M&C Number N/A M&C Date Approved OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
�TEXSUN
CLECTRICAL
NTRAC-IORS INC
9/23/2020
City of Ft. Worth Water Department.
1000 Throckmorton St.
Fort Worth,TX
76102
Attn: Farida Goderya
Re: Village Creek Water Reclamation Facility Miscellaneous Switchgear Replacement
Subject: Letter of Delays
Farida, we are requesting the date for f inal completion be adjusted 60 additional days from the
date stated in CO 1. The additional days requested are based on the following list of work
items that have caused delays in the project schedule.
New final completion date: September 30, 2020.
Delays:
1. Shop fabrication delays of canopy structurers.
2. Work adjustments due to recent Covid-19 pandemic.
Thank you,
Steve Miller
Texsun Electrical Contractors
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration ofthis contract, including
ensuring all performance andreporting requirements.
Signature
Farida Goderya, PhD,PE
Name of Employee
Senior Project Manager
Title ap44adIl�
,cyo1........4aa
p�'� °°Rp
P�'o old
oo
=v
�EXASap�d
'for Ronald P.Gonzales(Sep 30,2020 08:38 CDT)