HomeMy WebLinkAboutContract 53013-AR1 FORT WORTH. City of Fort Worth CSC No.53013-AR1
'111� Construction Allowance Request
Project Name Everman Pkwy Concrete Rehabilitation Project City Sec# 1 53013
Client Project#(s)l 102102
Project Everman Pkwy Concrete Rehabilitation Project.
Description
Contractor Makou,Inc. City Inspector Matt Cain
Funding Allocation Account TPW Totals Select Day
T e
Original Contract Amount $930,790.00 $930,790.00
Extras to Date
Credits to Date
Current Contract Amount $930,790.00 $930,790.00
Amount of Proposed Allocation $41,964.00 $41,964.00
Original Allowance Available for Allocation 50.000.00 $50,000.00
Allowance Funds Previously Allocated $0.00
Remaining Funds Available for this Allocation $50,000.00 $50,000.00
JUSTIFICATION(REASONS)FOR CHANGE ORDER
IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST,THE CONTRACTOR SHALL:Furnish all labor and material as per attached proposed
Construction Allowance Request(with attachments)to the Construction Allowance Request:This construction allowance is for the installation of TxDOT PR11 pedestrian
handrail on Everman Parkway,Marlene Drive,Michael Drive and Christopher Drive.The handrails are required to protect people from a potential fall hazard while using the
newly installed sidewalk adjacent to a culvert over a creek at these four locations within the limits of this project.Staff considers this unit price reasonable after comparing it
to another recently bid item of similar work and it is approximately 35%lower.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
Contractor's Company Name Contractor Name tract Signature bate
Ins Irw24on Supervisor Pate Pro-ect Maniager/P7ogram Manager Date
33 9 231C,
Assistant Dir r(Dept) Date Director,Contracring Department(Dept) Date
Assistant City Attorney Date Assistant City Manager Date
Council Action if required)
M&C Number M&C Date Approved
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX
City of Fort Worth
Construction Allowance Additions
Project Name I Everman Pkwy Concrete Rehabilitation Project City Sec# 53013
Client Project# 1 102102
Contractor Makou,Inc. Inspector �— Matt Cain
ADDITIONS
y Unit UnitCost Total
New Install PeUes;Tn—an Handrail-TXDOT
ew Remove and dispose existing handrail TP -0 S 50. 0
TPW 41,964.00
Sub Total AdclitEn—s ,9 .00
Change Order Additions Page 1 of 1
FORT WORTH City of Fort worth
vl--- Construction Allowance Deletions
Project Name Everman Pkwy Concrete Rehabilitation Project City Sec# 53013
Client Project# 102102
Contractor Makou,Inc. Inspector Matt Cain
ITEMS TO BE REDUCED AND CREDITED TOWARD CONSTRUCTION ALLOWANCE
Unit Unit Cost ota
TPW
Sub Total Deletions 0
Change Order Deletions Page 1 of 1
MISBE Breakdown for this Construction Allowance
M/SBE Sub Type of Service Amount for this CO
Total
Previous Construction Allowance
CO# DATE AMOUNT
Total $0.00
10/5/2020 BIM 360 Document Management
13 AUTODESK BIM 360 fortworthgov>102102-Everman Parkway Concrete Rehabilitation Project- A TI
•:: Document Management FOLDERS REVIEWS TRANSMITTALS ISSUES
Reviews > Review detail
CLOSED #14 Construction Allowance Approval Workflow
Export Report - This review is closed.
Name^ Description Version Markup Comments PROGRESS
Construction Allowance_Everman Pkwy_Rev.pdf -- V3 0 No comme
Initiator Initial Review n
Quote_Handrail_Everman Pkwy.pdf -- V3 0 No comme TI Tarigul Islam Sep 25,4:03 PM
<tariqu Lisla m @fortworthtexas.gov>
Submitted to Reviewer 1
Reviewer 1 Initial Review 1 n
JP Jeffrey Perrigo Sep 28,8:10 AM
<ieffrey.perrigo @fortworthtexas.gov>
Submitted to Reviewer 2
Reviewer Initial Review 2
LZ Lane Zarate Sep 28,9:05 AM
<la ne.za rate@fortworthtexas.gov>
Submitted to Reviewer 3
Approved
Reviewer3 Initial Review3 n
LP Lauren Prieur Sep 28,10:51 AM
<la u ren.prieu r@fortworthtexas.gov>
Submitted to Reviewer 4
Reviewer 4 Initial Review 4
WJ William Johnson Sep 28,1131 AM
<willia m.ioh nsan @fortworthtexas.gov>
Submitted to Reviewer 5
Reviewer Initial Reviews n
DID Douglas Black Oct 2,5:07 PM
<doug.black@fortworthtexas.gov>
Submitted to Approver
Approved
Approver Final Review n
DB Dana Burghdoff Oct 2,5:52 PM
<dana.bu rg hdoff@fortworthtexas.gov>
OFFICIAL RECORD Review ended
CITY SECRETARY Review dosed
FT.WORTH, TX
https://docs.b360.autodesk.com/projects/52d7e5c7-ca93-4d32-aO35-d7d832e6aOcO/reviews/e6el2967-a3a4-42d6-9872-7fe0cc467d8f 1/1
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract,including
ensuring all performance and reporting requirements.
Tariqul Islam / T-", tf'G (�
Name of Employee/Signature
Project Manager
Title
❑ This form is N/A as No City Funds are associated with this Contract
Printed Name Signature
a F FOR���0
G�,°0000
�a
Pvoo 0
o
ATTEST: °o*'°�ocollllo *�
ysj- Rona P. aNCZ46Y �01 nEXASoa
or Ronald P.Gonzales(W ,202010AT CDT)
Mary J.Kayser,City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH, TX
MAKOU Inc.
Construction Company
7100 S. Cooper St www.makoiLinc.com
Suite # 15. DUNS # 03 679 1092
Arlington, TX 76001 MBE/HUB/SB
Tele. 817-798-5426 Fax 817-494-0404
EVERMAN PARKWAY HAND RAILING
CT&S proposal PRl RAILING $ 111/lf
MAKOU INC OH/P 10% $ 11.10/lf
--------------------
TOTAL $ 122.10/lf
Removal of Disposal of Hand Rail on Marlene Dr $450.00
Let us know if you have any question
SINCERELY
MAQSOOD KHAN
PRINCIPAL
MAKOU Inc.
6204 Parkside Dr. Arlington, TX 76001
makouinc(c,gmail.com 1 817-798-5426
Construction - Metal Technology £t Steel
Quality Metal Work
D/M/WBE
www.ctands.com
Brad Berland - Sales/Est
0: 972-554-9629 F: 972-438-9828 Cell: 972-890-6928
PROPOSAL # 1779
Date: 8/18/2020
Proposal For: City of Fort Worth . Everman Parkway
C.T. and S. Metalwork's. Proposes to furnish all Material, Shop Drawings and
Labor for the following:
1.Modified PRl railing
All railing will be galvanized
Fabrication and installation
$111/foot. If this is shipped and installed all at once.
Additional trips will have a charge of$800
Any and all grounding requirements are excluded
Payment Terms: Net 30 Days on all Invoices
Retainage to be 10% of fabrication only & paid in full thirty (30) days
after completion of punch list.
Materials for proiect will be billed upon receipt and payment shall be due within 30
days
�� ��a srrstrr
'' ♦1513 Maryland Drive ♦ Irving,Texas 75061 ♦ (972)554-9629 ♦ Fax(972)438-9828
Fabrication progress billings will be billed no later than the 25th day of the month for
the previous month and shall be due within 30 days
This is a steel bid only, any foundation or concrete work is excluded
All anchor bolts requiring to be poured in place will be supplied by CT&S but placed in
concrete by others
STANDARD EXCLUSIONS & QUALIFICATIONS:
Engineering and Calculations unless otherwise specified
Cost of material testing or inspection, costs of shop and field labor
testing by others.
All flagging and lane closures by others
General Contractor to provide all traffic and pedestrian control,
including fences, barricades and flagmen
Bid does not include performance bond or LOC
General Contractor to provide all permits
Drawings must be approved by the customer prior to fabrication.
Schedule must be approved by General Contractor prior to fabrication
Bid based on forty (40) hour work week.
C.T.& S. Metalworks is not responsible for fall protection of personnel other than its
own workers.
Fabrication of steel to be per AISC Code of Standard Practice.
If the General Contractor fails to make payments when due, or its
financial ability to make payments becomes impaired, C. T. & S. Metalworks.,
may suspend all work during the continuance of either situation.
This proposal is valid for a period of thirty (30) days from this date only. General
Contractor accepts in writing the above proposal, all exclusions, terms conditions and
qualifications. In turn C. T. & S., Metalworks. agrees to perform the described.
WRITTEN ACCEPTANCE OF THIS PROPOSAL SHALL BE NECESSARY FOR THIS TO
BECOME A BINDING CONTRACT FOR BOTH PARTIES.
sb` er$u;fb
0♦1513 Maryland Drive ♦ Irving,Texas 75061 �... ♦ (972)554-9629 ♦ Fax(972)438-9828 % ""