HomeMy WebLinkAboutContract 53959-A1 CSC No. 53959-A1
AMENDMENT No. 1
TO CITY SECRETARY CONTRACT No. 53959
WHEREAS, the City of Fort Worth (CITY) and Teague Nall and Perkins,
Inc. , (ENGINEER) , made and entered into City Secretary Contract No. 53959,
(the CONTRACT) , which was authorized by M&C No. 20-0386 on the 16 day of
June, 2020 in the amount of $ 144, 000 . 00 (One hundred Forty-Four Thousand
Dollars) ; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Sycamore Park Phase I Project; and
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1 .
Article I of the CONTRACT is amended to include the additional
engineering services specified in a scope of services proposal, a copy of
which is attached hereto and incorporated herein (Attachment A) . The
cost to City for the additional design services to be performed by
Engineer totals $80,000. 00 (Attachment B) .
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $224,000. 00.
3 .
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
City of Fort Worth
Professional Services Agreement Amendment Template OFFICIAL RECORD
CFW Official Release 9/19/2017
Page 1 of CITY SECRETARY
FT. WORTH, TX
APPROVED:
City of Fort Worth ENGINEER
Teague Nall and Perkins, Inc.
Digitally signed by William H.Smith
William H. Smith DN.C=US,t,CN=tilliam Scot O=TNP,
OU=LA Dept.,CN=William H.Smith
Valerie Washington(Oct 7,202017:25 CDT) Date:2M.10.0817-42-07-OSOP
Valerie Washington Willian H. Smith, ASLA
Assistant+City Manager Director of Landscape Architecture
DATE: Oc` 7, 2020 DATE: October 6, 2020
APPROVAL RECOMMENDED:
Richard Zavala(Oct 7,bo 14:18 CDT)
Richard Zavala
Director, Park & Recreation Department
DATE: Oct 7, 2020
Contract Compliance Manager:
By signing, I acknowledge that I am the person responsible for the
monitoring and administration of this contract, including ensuring all
performance and reporting requirements .
Jing Yang
Project Manager
APPROVED AS TO FORM AND LEGALITY:
M&C: N&C
DBlack(Oct 7,202017:23 CDT) Date.
Oct 7 2020
Douglas W. Black
Assistant City Attorney
4.0440pn��
10,
C�pORr�Oa�
ATTEST: p 0
Pia*00000,00000
000*�
P. ���:� aQQ� Oct 8 2020
or Ronald P.GOnzales(Oct ,202008:44CDT) Date'
Mary J. Kayser
City Secretary
City of Fort Worth
Professional Services Agreement Amendment Template OFFICIAL RECORD
CFW Official Release 9/19/2017
Page 2of3 CITY SECRETARY
FT. WORTH, TX
Attachment A
Mtn
p www.tnpinc-corn
September 23, 2020 engineers
surveyors
landswpe architects
Mrs. Jing Yang TEXAS
FORT
City of Fort Worth DENTONORTH
Parks & Recreation Department ALLEN
311 W Tenth Street HEATH
CYPRESS
Fort Worth, Texas 76102 SUGAR LAND
GEORGIA
Re: Fee Proposal for Contract Amendment No. 1 —
BLAIRSVILLE
Sycamore Park Improvements, Phase 1
City of Fort Worth Project No. 102014
(TNP Project No. FTW 20157)
Dear Mrs. Yang:
Teague Nall and Perkins, Inc. is submitting this fee Amendment for the above referenced contract
based on additional services requested. The following is a brief description and cost for the
additional services to be provided on this project:
I. Playground and Trails
Per the Sycamore Park master plan, the City has identified available funds for the
construction of the trail improvements and the playground on the southside of Vickery
Boulevard. The trail improvements will consist of trails around the playground, replacing
trails north of the creek, and along the planned parking lot and drive improvements south of
the creek. TNP will provide surveying, engineering and landscape services for the additional
design,and will utilize sub consultants for the geotechnical and subsurface utility designation.
II. Fee Proposal for Contract Amendment No. 1: $ 80,000
TNP proposes a total fee of$80,000 to accomplish the scope of services. A breakdown of
the fee is included in Attachment B-1.
Summary of Contract Fee:
Original Contract Amount: $ 144,000
Amendment No. 1 $ 80,000
Revised Contract Amount $ 224,000
III. Project Schedule
The anticipated duration of the additional design services is 3 months. See Attachment D-1
Project Schedule.
TNP Firm ^ Registrations
xa Board of Professional Engineers and Land Surveyors I Engineering Firm No.F-230 I Surveying Firm No. 10011600 10194381 10011601
Georgia Board aF PraFessional Engineers Firm No.PEP007431 I Texas Board aF Architectural Examiners Firm No.BR 2673
IV. M/WBE Utilization:
This amendment includes work effort for our certified SBE subconsultant partners. With this
amendment, the overall M/SBE participation will be 8%which is in line with the City's M/SBE
goal of 8%.
Thank you for consideration of this contract amendment request. If you have any questions,
please do not hesitate to call us.
Sincerely,
TEAGUE NALL AND PERKINS, INC.
Bill Smith, RLA
Director of Landscape Architecture Services, Associate
Scott A. Gibson, P.E.
Team Leader, Associate
Attachments: 1)Attachment B Compensation
Attachment B
Compensation
The services for Contract Amendment No. 1 shall be provided for a total lump sum fee of
$80,000 (Eighty Thousand Dollars). The overall fee total shown shall not be exceeded
without prior written authorization from the CITY.
Payment for the services described in Contract Amendment No. 1 shall be invoiced to
the CITY on a monthly basis, based upon percentage completed for each task. Below is
a fee breakdown by task for the services described in Attachment A Scope of Services:
Sycamore Park Phase I Development - Trails and Playground
Task Fee
Professional Services
1. Coordination/Management/Communication $ 6,225.00
2. Data Review/Site Visit/Base Map $ 15,175.00
3. Geotechnical Services $ 2,100.00
4. Engineering Services $ 34,420.00
5. Landscape Design Services $ 17,760.00
6. State Accessibility Plan Review $ 0
7. Bid and Construction Administration $ 4,320.00
Total Fee for Services $80,000.00
Attachment B-1 Compensation
Sycamore Park Phase I Development
Date:09.23.2020
Page 1 of 1
10/2/2020 Attachment C
CITY OF FORT WORTH
CONTRACT COMPLIANCE MEMORANDUM
AMENDMENT
THIS FORM MUST BE ATTACHED TO THE ROUTING "M & C" BEFORE LAW
DEPARTMENT AND CITY MANAGER APPROVAL
To: Department Project Manager
From: Office of Business Equity
Date: October 2, 2020
In the Amount of: $80,000.00 PACS-102014
DOE/Project No.
Project/Bid: Amendment #1 - Design of Sycamore Park Phase I
Development
1. Compliance with the City's Business Diversity Enterprise (BDE) Ordinance has
been achieved by the following method:
TEAGUE NALL AND PERKINS, INC. is in compliance with the City's BDE
Ordinance by committing to 8% SBE participation on this amendment. The City's
SBE goal on this amendment is 8%.