HomeMy WebLinkAboutContract 53487-PM1CSC No . 53487-PM1
00 00 10- 1
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 1 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 2, 2014
SECTION 00 00 10
TABLE OF CONTENTS
DEVELOPER AWARDED PROJECTS
Division 00 - General Conditions
00 11 13 Invitation to Bidders
00 21 13 Instructions to Bidders
00 41 00 Bid Form
00 42 43 Proposal Form Unit Price
00 43 13 Bid Bond
00 45 11 Bidders Prequalification’s
00 45 12 Prequalification Statement
00 45 13 Bidder Prequalification Application
00 45 26 Contractor Compliance with Workers' Compensation Law
00 45 40 Minority Business Enterprise Goal
00 52 43 Agreement
00 61 25 Certificate of Insurance
00 62 13 Performance Bond
00 62 14 Payment Bond
00 62 19 Maintenance Bond
00 72 00 General Conditions
00 73 00 Supplementary Conditions
00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded
Projects
Division 01 - General Requirements
01 11 00 Summary of Work
01 25 00 Substitution Procedures
01 31 19 Preconstruction Meeting
01 31 20 Project Meetings
01 32 16 Construction Progress Schedule
01 32 33 Preconstruction Video
01 33 00 Submittals
01 35 13 Special Project Procedures
01 45 23 Testing and Inspection Services
01 50 00 Temporary Facilities and Controls
01 55 26 Street Use Permit and Modifications to Traffic Control
01 57 13 Storm Water Pollution Prevention Plan
01 58 13 Temporary Project Signage
01 60 00 Product Requirements
01 66 00 Product Storage and Handling Requirements
01 70 00 Mobilization and Remobilization
01 71 23 Construction Staking
01 74 23 Cleaning
01 77 19 Closeout Requirements
01 78 23 Operation and Maintenance Data
01 78 39 Project Record Documents
00 00 10- 2
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 2 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 2, 2014
Technical Specifications listed below are included for this Project by reference and can be
viewed/downloaded from the City’s Buzzsaw site at:
htps://projectpoint.buzzsaw.com/client/fortworthgov/Resources/02%20-
%20Construction%20Documents/Specifications
Division 02 - Existing Conditions
02 41 13 Selective Site Demolition
02 41 14 Utility Removal/Abandonment
02 41 15 Paving Removal
Division 03 - Concrete
03 30 00 Cast-In-Place Concrete
03 34 13 Controlled Low Strength Material (CLSM)
03 34 16 Concrete Base Material for Trench Repair
03 80 00 Modifications to Existing Concrete Structures
Division 26 - Electrical
26 05 00 Common Work Results for Electrical
26 05 10 Demolition for Electrical Systems
26 05 33 Raceway and Boxes for Electrical Systems
26 05 43 Underground Ducts and Raceways for Electrical Systems
Division 31 - Earthwork
31 10 00 Site Clearing
31 23 16 Unclassified Excavation
31 23 23 Borrow
31 24 00 Embankments
31 25 00 Erosion and Sediment Control
31 36 00 Gabions
31 37 00 Riprap
Division 32 - Exterior Improvements
32 01 17 Permanent Asphalt Paving Repair
32 01 18 Temporary Asphalt Paving Repair
32 01 29 Concrete Paving Repair
32 11 23 Flexible Base Courses
32 11 29 Lime Treated Base Courses
32 11 33 Cement Treated Base Courses
32 12 16 Asphalt Paving
32 12 73 Asphalt Paving Crack Sealants
32 13 13 Concrete Paving
32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps
32 13 73 Concrete Paving Joint Sealants
32 14 16 Brick Unit Paving
32 16 13 Concrete Curb and Gutters and Valley Gutters
32 17 23 Pavement Markings
32 31 13 Chain Link Fences and Gates
00 00 10- 3
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 3 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 2, 2014
Division 33 - Utilities
33 01 30 Sewer and Manhole Testing
33 01 31 Closed Circuit Television (CCTV) Inspection
33 03 10 Bypass Pumping of Existing Sewer Systems
33 04 10 Joint Bonding and Electrical Isolation
33 04 11 Corrosion Control Test Stations
33 04 12 Magnesium Anode Cathodic Protection System
33 04 30 Temporary Water Services
33 04 40 Cleaning and Acceptance Testing of Water Mains
33 05 10 Utility Trench Excavation, Embedment, and Backfill
33 05 12 Water Line Lowering
33 05 13 Frame, Cover and Grade Rings
33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade
33 05 16 Concrete Water Vaults
33 05 17 Concrete Collars
33 05 20 Auger Boring
33 05 21 Tunnel Liner Plate
33 05 22 Steel Casing Pipe
33 05 23 Hand Tunneling
33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate
33 05 26 Utility Markers/Locators
33 05 30 Exploratory Excavation for Existing Utilities
33 11 10 Ductile Iron Pipe
33 11 11 Ductile Iron Fittings
33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe
33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type
33 11 14 Buried Steel Pipe and Fittings
33 11 15 Pre-stressed Concrete Cylinder Pipe
33 12 10 Water Services 1-inch to 2-inch
33 12 11 Large Water Meters
33 12 20 Resilient Seated Gate Valve
33 12 21 AWWA Rubber-Seated Butterfly Valves
33 12 25 Connection to Existing Water Mains
33 12 30 Combination Air Valve Assemblies for Potable Water Systems
33 12 40 Dry-Barrel Fire Hydrants
33 12 50 Water Sample Stations
33 12 60 Blow-off Valves
33 31 12 Cured in Place Pipe (CIPP)
33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers
33 31 15 HDPE Pipe For Sanitary Sewers (Gravity and Force Mains)
33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe
33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe
33 31 22 Sanitary Sewer Slip Lining
33 31 23 Sanitary Sewer Pipe Enlargement
33 31 50 Sanitary Sewer Service Connections and Service Line
33 31 70 Combination Air Valve for Sanitary Sewer Force Mains
33 39 10 Cast-in-Place Concrete Manholes
33 39 20 Precast Concrete Manholes
33 39 30 Fiberglass Manholes
33 39 40 Wastewater Access Chamber (WAC)
00 00 10- 4
TABLE OF CONTENTS FOR DEVELOPER AWARDED PROJECTS
Page 4 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 2, 2014
33 39 60 Epoxy Liners for Sanitary Sewer Structures
33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts
33 41 11 HDPE Storm Sewer Pipe
33 46 00 Sub drainage
33 46 01 Slotted Storm Drains
33 46 02 Trench Drains
33 49 10 Cast-in-Place Manholes and Junction Boxes
33 49 20 Curb and Drop Inlets
33 49 40 Storm Drainage Headwalls and Wingwalls
Division 34 - Transportation
34 41 10 Traffic Signals
34 41 13 Removing Traffic Signals
34 41 20 Roadway Illumination Assemblies
34 41 30 Aluminum Signs
34 71 13 Traffic Control
Appendix
GC-4.01 Availability of Lands
GC-4.02 Subsurface and Physical Conditions
GC-4.04 Underground Facilities
GC-4.06 Hazardous Environmental Condition at Site
GC-6.06.D Minority and Women Owned Business Enterprise Compliance
GC-6.07 Wage Rates
GC-6.09 Permits and Utilities
GC-6.24 Nondiscrimination
GR-01 60 00 Product Requirements
END OF SECTION
DIVISION 00
GENERAL CONDITIONS
UTILITIES,
PAVING
&
LIGHTING
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
00 45 12
DAP PREQUALIFICATION STATEMENT
Page 1 of 1
SECTION 00 4512
DAP — PREQUALIFICATION STATEMENT
Each Bidder is required to complete the information below by identifying the prequalified contractors
and/or subcontractors whom they intend to utilize for the major work type(s) listed. In the "Major Work
Type" box provide the complete major work type and actual description as provided by the Water
Department for water and sewer and TPW for paving
Major Work Type
Contractor/Subcontractor Company Name
Prequalification
Expiration Date
Water and Wastewater New
Development, Rehabilitation and
Conatser Construction TX, L.P.
n
Redevelopment Open Cut
(all sizes)
Concrete/Reconstruction
(Unlimited)
Conatser Construction TX, L.P.
1 20 21
Roadway and Pedestrian
Lighting
Conatser Construction TX, L.P.
'dl /2021
The undersigned hereby certifies that the contractors and/or subcontractors described in the table above
are currently prequalified for the work types listed.
BIDDER
Conatser Construction TX, L.P. BY:
5327 Wichita Street
Ft. Worth, TX 76119
q%Ignature)
NAME/TITLE: Brock Huggins / President
DATE:
END OF SECTION
CRY OF FORT WORTH
STANDARD CONSTRUCTION PREQUALIFICATION STATEMENT— DEVELOPER AWARDED PROJECTS
Statement
Farm Verslon September 1, 2015
Heritage Trace Parkway, city#102139
DO 45 12—Prequal
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
Daniel C. Bartok
Chief Executive Officer
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
8/11/2020
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
DocuSign Envelope ID: 2295C614-8C5D-4A26-BF69-82960CFA3674
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS
OF THE CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
STANDARD CITY CONDITIONS OF THE
CONSTRUCTION CONTRACT
FOR DEVELOPER AWARDED PROJECTS
TABLE OF CONTENTS
Page
Article 1 – Definitions and Terminology .......................................................................................................... 1
1.01 Defined Terms ............................................................................................................................... 1
1.02 Terminology .................................................................................................................................. 5
Article 2 – Preliminary Matters ......................................................................................................................... 6
2.01 Before Starting Construction ........................................................................................................ 6
2.02 Preconstruction Conference .......................................................................................................... 6
2.03 Public Meeting .............................................................................................................................. 6
Article 3 – Contract Documents and Amending ............................................................................................... 6
3.01 Reference Standards ..................................................................................................................... 6
3.02 Amending and Supplementing Contract Documents .................................................................. 6
Article 4 – Bonds and Insurance ....................................................................................................................... 7
4.01 Licensed Sureties and Insurers ..................................................................................................... 7
4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7
4.03 Certificates of Insurance ............................................................................................................... 7
4.04 Contractor’s Insurance .................................................................................................................. 9
4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12
Article 5 – Contractor’s Responsibilities ........................................................................................................ 12
5.01 Supervision and Superintendent ................................................................................................. 12
5.02 Labor; Working Hours ................................................................................................................ 13
5.03 Services, Materials, and Equipment ........................................................................................... 13
5.04 Project Schedule .......................................................................................................................... 14
5.05 Substitutes and “Or-Equals” ....................................................................................................... 14
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16
5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16
5.08 Wage Rates.................................................................................................................................. 18
5.09 Patent Fees and Royalties ........................................................................................................... 19
5.10 Laws and Regulations ................................................................................................................. 19
5.11 Use of Site and Other Areas ....................................................................................................... 19
5.12 Record Documents ...................................................................................................................... 20
5.13 Safety and Protection .................................................................................................................. 21
5.14 Safety Representative ................................................................................................................. 21
5.15 Hazard Communication Programs ............................................................................................. 22
5.16 Submittals .................................................................................................................................... 22
5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.18 Indemnification ........................................................................................................................... 24
5.19 Delegation of Professional Design Services .............................................................................. 24
5.20 Right to Audit: ............................................................................................................................ 25
5.21 Nondiscrimination....................................................................................................................... 25
Article 6 – Other Work at the Site ................................................................................................................... 26
6.01 Related Work at Site ................................................................................................................... 26
Article 7 – City’s Responsibilities................................................................................................................... 26
7.01 Inspections, Tests, and Approvals .............................................................................................. 26
7.02 Limitations on City’s Responsibilities ....................................................................................... 26
7.03 Compliance with Safety Program ............................................................................................... 27
Article 8 – City’s Observation Status During Construction ........................................................................... 27
8.01 City’s Project Representative ..................................................................................................... 27
8.02 Authorized Variations in Work .................................................................................................. 27
8.03 Rejecting Defective Work .......................................................................................................... 27
8.04 Determinations for Work Performed .......................................................................................... 28
Article 9 – Changes in the Work ..................................................................................................................... 28
9.01 Authorized Changes in the Work ............................................................................................... 28
9.02 Notification to Surety .................................................................................................................. 28
Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28
10.01 Change of Contract Price ............................................................................................................ 28
10.02 Change of Contract Time............................................................................................................ 28
10.03 Delays .......................................................................................................................................... 28
Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29
11.01 Notice of Defects ........................................................................................................................ 29
11.02 Access to Work ........................................................................................................................... 29
11.03 Tests and Inspections .................................................................................................................. 29
11.04 Uncovering Work ....................................................................................................................... 30
11.05 City May Stop the Work ............................................................................................................. 30
11.06 Correction or Removal of Defective Work ................................................................................ 30
11.07 Correction Period ........................................................................................................................ 30
11.08 City May Correct Defective Work ............................................................................................. 31
Article 12 – Completion .................................................................................................................................. 32
12.01 Contractor’s Warranty of Title ................................................................................................... 32
12.02 Partial Utilization ........................................................................................................................ 32
12.03 Final Inspection ........................................................................................................................... 32
12.04 Final Acceptance ......................................................................................................................... 33
Article 13 – Suspension of Work .................................................................................................................... 33
13.01 City May Suspend Work ............................................................................................................ 33
Article 14 – Miscellaneous .............................................................................................................................. 34
14.01 Giving Notice .............................................................................................................................. 34
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.02 Computation of Times ................................................................................................................ 34
14.03 Cumulative Remedies ................................................................................................................. 34
14.04 Survival of Obligations ............................................................................................................... 35
14.05 Headings ...................................................................................................................................... 35
00 73 10- 1
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 1 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 1 – DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in these General Conditions or in other Contract Documents, the terms listed
below have the meanings indicated which are applicable to both the singular and plural thereof,
and words denoting gender shall include the masculine, feminine and neuter. Said terms are
generally capitalized or written in italics, but not always. When used in a context consistent with
the definition of a listed-defined term, the term shall have a meaning as defined below whether
capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial
capital letters in the Contract Documents include references to identified articles and paragraphs,
and the titles of other documents or forms.
1. Agreement - The written instrument which is evidence of the agreement between Developer
and Contractor covering the Work
2. Asbestos—Any material that contains more than one percent asbestos and is friable or is
releasing asbestos fibers into the air above current action levels established by the United
States Occupational Safety and Health Administration.
3. Business Day – A business day is defined as a day that the City conducts normal business,
generally Monday through Friday, except for federal or state holidays observed by the City.
4. Buzzsaw – City’s on-line, electronic document management and collaboration system.
5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight.
6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by,
its governing body through its City Manager, his designee, or agents authorized pursuant to
its duly authorized charter on his behalf.
7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City
for the Construction of one or more following public facilities within the City public right-of-
way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs.
A CFA may include private facilities within the right-of-way dedicated as private right-of-
way or easement on a recorded plat.
8. Contract—The entire and integrated written document incorporating the Contract
Documents between the Developer, Contractor, and/or City concerning the Work. The
Contract supersedes prior negotiations, representations, or agreements, whether written or
oral.
9. Contract Documents—Those items that make up the contract and which must include the
Agreement, and it’s attachments such as standard construction specifications, standard City
Conditions, other general conditions of the Developer, including:
a. An Agreement
00 73 10- 2
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 2 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
b. Attachments to the Agreement
i. Bid Form
ii. Vendor Compliance with State Law Non-Resident Bidder
iii. Prequalification Statement
c. Current Prevailing Wage Rates Table (if required by City)
d. Insurance Accord Form
e. Payment Bond
f. Performance Bond
g. Maintenance Bond
h. Power of Attorney for Bonds
i. Workers Compensation Affidavit
j. MWBE Commitment Form( If required by City)
k. General Conditions
l. Supplementary Conditions
m. The Standard City Conditions
n. Specifications specifically made part of the Contract Documents by attachment, if
not attached, as incorporated by reference and described in the Table of Contents of
the Project’s Contract Documents
o. Drawings
p. Documentation submitted by contractor prior to Notice of Award.
q. The following which may be delivered or issued after the effective date if the
Agreement and, if issued become an incorporated part of the Contract Documents
i. Notice to Proceed
ii. Field Orders
iii. Change Orders
iv. Letters of Final Acceptance
r. Approved Submittals, other Contractor submittals, and the reports and drawings of
subsurface and physical conditions are not Contract Documents.
10. Contractor—The individual or entity with whom Developer has entered into the Agreement.
11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day.
12. Developer – An individual or entity that desires to make certain improvements within the
City of Fort Worth
13. Drawings—That part of the Contract Documents prepared or approved by Engineer which
graphically shows the scope, extent, and character of the Work to be performed by
Contractor. Submittals are not Drawings as so defined.
14. Engineer—The licensed professional engineer or engineering firm registered in the State of
Texas performing professional services for the Developer.
15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor
that the Work specified in the Contract Documents has been completed to the satisfaction of
the City.
00 73 10- 3
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 3 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
16. Final Inspection – Inspection carried out by the City to verify that the Contractor has
completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in
conformance with the Contract Documents.
17. General Requirements—A part of the Contract Documents between the Developer and a
Contractor.
18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes,
and orders of any and all governmental bodies, agencies, authorities, and courts having
jurisdiction.
19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or
personal property.
20. Milestone—A principal event specified in the Contract Documents relating to an
intermediate Contract Time prior to Final Acceptance of the Work.
21. Non-Participating Change Order—A document, which is prepared for and reviewed by the
City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
22. Participating Change Order—A document, which is prepared for and approved by the City,
which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or
revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on
or after the Effective Date of the Agreement.
23. Plans – See definition of Drawings.
24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with
the General Requirements, describing the sequence and duration of the activities comprising
the Contractor’s plan to accomplish the Work within the Contract Time.
25. Project—The Work to be performed under the Contract Documents.
26. Project Representative—The authorized representative of the City who will be assigned to
the Site.
27. Public Meeting – An announced meeting conducted by the Developer to facilitate public
participation and to assist the public in gaining an informed view of the Project.
28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday
thru Friday (excluding legal holidays).
29. Samples—Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by which such
portion of the Work will be judged.
00 73 10- 4
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 4 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required
submittals and the time requirements to support scheduled performance of related
construction activities.
31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or
Developer upon which the Work is to be performed, including rights-of-way, permits, and
easements for access thereto, and such other lands furnished by City or Developer which are
designated for the use of Contractor.
32. Specifications—That part of the Contract Documents consisting of written requirements for
materials, equipment, systems, standards and workmanship as applied to the Work, and
certain administrative requirements and procedural matters applicable thereto.
Specifications may be specifically made a part of the Contract Documents by attachment or,
if not attached, may be incorporated by reference as indicated in the Table of Contents
(Division 00 00 00) of each Project.
33. Standard City Conditions – That part of the Contract Documents setting forth requirements
of the City.
34. Subcontractor—An individual or entity having a direct contract with Contractor or with any
other Subcontractor for the performance of a part of the Work at the Site.
35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information
which are specifically prepared or assembled by or for Contractor and submitted by
Contractor to illustrate some portion of the Work.
36. Superintendent – The representative of the Contractor who is available at all times and able
to receive instructions from the City and/or Developer and to act for the Contractor.
37. Supplementary Conditions—That part of the Contract Documents which amends or
supplements the General Conditions.
38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having
a direct contract with Contractor or with any Subcontractor to furnish materials or
equipment to be incorporated in the Work by Contractor or Subcontractor.
39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires,
manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any
encasements containing such facilities, including but not limited to, those that convey
electricity, gases, steam, liquid petroleum products, telephone or other communications,
cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or
other control systems.
40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday,
Sunday or legal holiday, as approved in advance by the City.
00 73 10- 5
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 5 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
41. Work—The entire construction or the various separately identifiable parts thereof required
to be provided under the Contract Documents. Work includes and is the result of performing
or providing all labor, services, and documentation necessary to produce such construction
including any Participating Change Order, Non-Participating Change Order, or Field
Order, and furnishing, installing, and incorporating all materials and equipment into such
construction, all as required by the Contract Documents.
42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or
legal holidays authorized by the City for contract purposes, in which weather or other
conditions not under the control of the Contractor will permit the performance of the
principal unit of work underway for a continuous period of not less than 7 hours between 7
a.m. and 6 p.m.
1.02 Terminology
A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in
the Bidding Requirements or Contract Documents, have the indicated meaning.
B. Defective:
1. The word “defective,” when modifying the word “Work,” refers to Work that is
unsatisfactory, faulty, or deficient in that it:
a. does not conform to the Contract Documents; or
b. does not meet the requirements of any applicable inspection, reference standard, test, or
approval referred to in the Contract Documents; or
c. has been damaged prior to City’s written acceptance.
C. Furnish, Install, Perform, Provide:
1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or
the word “Supply,” or any combination or similar directive or usage thereof, shall mean
furnishing and incorporating in the Work including all necessary labor, materials, equipment,
and everything necessary to perform the Work indicated, unless specifically limited in the
context used.
D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known
technical or construction industry or trade meaning are used in the Contract Documents in
accordance with such recognized meaning.
00 73 10- 6
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 6 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 2 – PRELIMINARY MATTERS
2.01 Before Starting Construction
Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting
the Work. New schedules will be submitted to City when Participating Change Orders or Non-
Participating Change Orders occur.
2.02 Preconstruction Conference
Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as
specified in the Contract Documents.
2.03 Public Meeting
Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor
attending the Public Meeting as scheduled by the City.
ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING
3.01 Reference Standards
A. Standards, Specifications, Codes, Laws, and Regulations
1. Reference to standards, specifications, manuals, or codes of any technical society,
organization, or association, or to Laws or Regulations, whether such reference be specific or
by implication, shall mean the standard, specification, manual, code, or Laws or Regulations
in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there
were no Bids), except as may be otherwise specifically stated in the Contract Documents.
2. No provision or instruction shall be effective to assign to City, or any of its officers,
directors, members, partners, employees, agents, consultants, or subcontractors, any duty or
authority to supervise or direct the performance of the Work or any duty or authority to
undertake responsibility inconsistent with the provisions of the Contract Documents.
3.02 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide for additions, deletions, and revisions in
the Work or to modify the terms and conditions thereof by a Participating Change Order or a
Non-Participating Change Order.
B. The requirements of the Contract Documents may be supplemented, and minor variations and
deviations in the Work not involving a change in Contract Price or Contract Time, may be
authorized, by one or more of the following ways:
1. A Field Order;
00 73 10- 7
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 7 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or
2. City’s written interpretation or clarification.
ARTICLE 4 – BONDS AND INSURANCE
4.01 Licensed Sureties and Insurers
All bonds and insurance required by the Contract Documents to be purchased and maintained by
Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized
in the State of Texas to issue bonds or insurance policies for the limits and coverage so required.
Such surety and insurance companies shall also meet such additional requirements and qualifications
as may be provided Section 4.04.
4.02 Performance, Payment, and Maintenance Bonds
A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in
accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount
equal to the Contract Price as security for the faithful performance and payment of all of
Contractor’s obligations under the Contract Documents.
B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount
equal to the Contract Price as security to protect the City against any defects in any portion of the
Work described in the Contract Documents. Maintenance bonds shall remain in effect for two
(2) years after the date of Final Acceptance by the City.
C. All bonds shall be in the form prescribed by the Contract Documents except as provided
otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list
of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and
as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial
Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed
by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney
which shall show that it is effective on the date the agent or attorney-in-fact signed each bond.
D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in the State of Texas or it ceases to meet the requirements of
Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event
giving rise to such notification, provide another bond and surety, both of which shall comply
with the requirements of Paragraphs 4.01 and 4.02.C.
4.03 Certificates of Insurance
Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee
identified in these Standard City Conditions certificates of insurance (and other evidence of
insurance requested by City or any other additional insured) which Contractor is required to
purchase and maintain.
00 73 10- 8
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 8 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. The certificate of insurance shall document the City, an as “Additional Insured” on all
liability policies.
2. The Contractor’s general liability insurance shall include a, “per project” or “per location”,
endorsement, which shall be identified in the certificate of insurance provided to the City.
3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the
insured, be complete in its entirety, and show complete insurance carrier names as listed in
the current A.M. Best Property & Casualty Guide
4. The insurers for all policies must be licensed and/or approved to do business in the State of
Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-:
VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial
strength and solvency to the satisfaction of Risk Management. If the rating is below that
required, written approval of City is required.
5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor
of the City. In addition, the Contractor agrees to waive all rights of subrogation against the
Engineer (if applicable), and each additional insured identified in these Standard City
Conditions. Failure of the City to demand such certificates or other evidence of full
compliance with the insurance requirements or failure of the City to identify a deficiency
from evidence that is provided shall not be construed as a waiver of Contractor’s obligation
to maintain such lines of insurance coverage.
6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess
Liability insurance for any differences is required. Excess Liability shall follow form of the
primary coverage.
7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If
coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with
or prior to the date of the effective date of the agreement and the certificate of insurance shall
state that the coverage is claims-made and the retroactive date. The insurance coverage shall
be maintained for the duration of the Contract and for three (3) years following Final
Acceptance provided under the Contract Documents or for the warranty period, whichever is
longer. An annual certificate of insurance submitted to the City shall evidence such
insurance coverage.
8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the
required lines of coverage, nor decrease the limits of said coverage unless such endorsements
are approved in writing by the City. In the event a Contract has been bid or executed and the
exclusions are determined to be unacceptable or the City desires additional insurance
coverage, and the City desires the contractor/engineer to obtain such coverage, the contract
price shall be adjusted by the cost of the premium for such additional coverage plus 10%.
9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance
coverage shall be approved by the City in regards to asset value and stockholders' equity. In
00 73 10- 9
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 9 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
lieu of traditional insurance, alternative coverage maintained through insurance pools or risk
retention groups, must also be approved by City.
10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a
first-dollar basis, must be acceptable to and approved by the City.
11. City, at its sole discretion, reserves the right to review the insurance requirements and to
make reasonable adjustments to insurance coverage’s and their limits when deemed
necessary and prudent by the City based upon changes in statutory law, court decision or the
claims history of the industry as well as of the contracting party to the City. The City shall
be required to provide prior notice of 90 days, and the insurance adjustments shall be
incorporated into the Work by Change Order.
12. City shall be entitled, upon written request and without expense, to receive copies of policies
and endorsements thereto and may make any reasonable requests for deletion or revision or
modifications of particular policy terms, conditions, limitations, or exclusions necessary to
conform the policy and endorsements to the requirements of the Contract. Deletions,
revisions, or modifications shall not be required where policy provisions are established by
law or regulations binding upon either party or the underwriter on any such policies.
13. City shall not be responsible for the direct payment of insurance premium costs for
Contractor’s insurance.
4.04 Contractor’s Insurance
A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such
insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’
Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for
Employers’ Liability as is appropriate for the Work being performed and as will provide
protection from claims set forth below which may arise out of or result from Contractor’s
performance of the Work and Contractor’s other obligations under the Contract Documents,
whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly
or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts
any of them may be liable:
1. claims under workers’ compensation, disability benefits, and other similar employee benefit
acts;
2. claims for damages because of bodily injury, occupational sickness or disease, or death of
Contractor’s employees.
3. The limits of liability for the insurance shall provide the following coverages for not less
than the following amounts or greater where required by Laws and Regulations
a. Statutory limits
b. Employer's liability
00 73 10- 10
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 10 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $100,000 each accident/occurrence
2) $100,000 Disease - each employee
3) $500,000 Disease - policy limit
B. Commercial General Liability. Coverage shall include but not be limited to covering liability
(bodily injury or property damage) arising from: premises/operations, independent contractors,
products/completed operations, personal injury, and liability under an insured contract. Insurance
shall be provided on an occurrence basis, and as comprehensive as the current Insurance
Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the City. The Commercial General
Liability policy, shall have no exclusions by endorsements that would alter of nullify
premises/operations, products/completed operations, contractual, personal injury, or advertising
injury, which are normally contained with the policy, unless the City approves such exclusions
in writing.
1. For construction projects that present a substantial completed operation exposure, the City
may require the contractor to maintain completed operations coverage for a minimum of no
less than three (3) years following the completion of the project
2. Contractor's Liability Insurance under this Section which shall be on a per project basis
covering the Contractor with minimum limits of:
a. $1,000,000 each occurrence
b. $2,000,000 aggregate limit
3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance)
making the General Aggregate Limits apply separately to each job site.
4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U”
coverage’s. Verification of such coverage must be shown in the Remarks Article of the
Certificate of Insurance.
C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”,
defined as autos owned, hired and non-owned and provide indemnity for claims for damages
because bodily injury or death of any person and or property damage arising out of the work,
maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone
for whose acts any of them may be liable.
1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in
an amount not less than the following amounts:
a. Automobile Liability - a commercial business policy shall provide coverage on "Any
Auto", defined as autos owned, hired and non-owned.
00 73 10- 11
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 11 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1) $1,000,000 each accident on a combined single limit basis. Split limits are
acceptable if limits are at least:
2) $250,000 Bodily Injury per person
3) $500,000 Bodily Injury per accident /
4) $100,000 Property Damage
D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of
railroad right-of-way, the Contractor shall comply with the following requirements:
1. The Contractor’s construction activities will require its employees, agents, subcontractors,
equipment, and material deliveries to cross railroad properties and tracks owned and
operated by: ____________________________________________________________
Write the name of the railroad company. (If none, then write none)
2. The Contractor shall conduct its operations on railroad properties in such a manner as not to
interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use
or operation of its/their trains or other property. Such operations on railroad properties may
require that Contractor to execute a “Right of Entry Agreement” with the particular railroad
company or companies involved, and to this end the Contractor should satisfy itself as to the
requirements of each railroad company and be prepared to execute the right-of-entry (if any)
required by a railroad company. The requirements specified herein likewise relate to the
Contractor’s use of private and/or construction access roads crossing said railroad company’s
properties.
3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions
shall provide coverage for not less than the following amounts, issued by companies
satisfactory to the City and to the Railroad Company for a term that continues for so long as
the Contractor’s operations and work cross, occupy, or touch railroad property:
a. General Aggregate: _____________________________________
Enter limits provided by Railroad Company (If none, write none)
b. Each Occurrence: : _____________________________________
Enter limits provided by Railroad Company (If none, write none)
4. With respect to the above outlined insurance requirements, the following shall govern:
a. Where a single railroad company is involved, the Contractor shall provide one insurance
policy in the name of the railroad company. However, if more than one grade separation
or at-grade crossing is affected by the Project at entirely separate locations on the line or
lines of the same railroad company, separate coverage may be required, each in the
amount stated above.
b. Where more than one railroad company is operating on the same right-of-way or where
several railroad companies are involved and operated on their own separate rights-of-
00 73 10- 12
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 12 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
way, the Contractor may be required to provide separate insurance policies in the name
of each railroad company.
c. If, in addition to a grade separation or an at-grade crossing, other work or activity is
proposed on a railroad company’s right-of-way at a location entirely separate from the
grade separation or at-grade crossing, insurance coverage for this work must be included
in the policy covering the grade separation.
d. If no grade separation is involved but other work is proposed on a railroad company’s
right-of-way, all such other work may be covered in a single policy for that railroad, even
though the work may be at two or more separate locations.
5. No work or activities on a railroad company’s property to be performed by the Contractor
shall be commenced until the Contractor has furnished the City with an original policy or
policies of the insurance for each railroad company named, as required above. All such
insurance must be approved by the City and each affected Railroad Company prior to the
Contractor’s beginning work.
6. The insurance specified above must be carried until all Work to be performed on the railroad
right-of-way has been completed and the grade crossing, if any, is no longer used by the
Contractor. In addition, insurance must be carried during all maintenance and/or repair work
performed in the railroad right-of-way. Such insurance must name the railroad company as
the insured, together with any tenant or lessee of the railroad company operating over tracks
involved in the Project.
E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation
or other loss of insurance coverage. Contractor shall stop work until replacement insurance has
been procured. There shall be no time credit for days not worked pursuant to this section.
4.05 Acceptance of Bonds and Insurance; Option to Replace
If City has any objection to the coverage afforded by or other provisions of the bonds or insurance
required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis
of non-conformance with the Contract Documents, the Developer and City shall so notify the
Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence
requested). Contractor shall provide to the City such additional information in respect of insurance
provided as the Developer or City may reasonably request. If Contractor does not purchase or
maintain all of the bonds and insurance required by the Contract Documents, the Developer or City
shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure
to maintain prior to any change in the required coverage.
ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES
5.01 Supervision and Superintendent
A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting
such attention thereto and applying such skills and expertise as may be necessary to perform the
00 73 10- 13
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 13 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Work in accordance with the Contract Documents. Contractor shall be solely responsible for the
means, methods, techniques, sequences, and procedures of construction.
B. At all times during the progress of the Work, Contractor shall assign a competent, English-
speaking, Superintendent who shall not be replaced without written notice to City. The
Superintendent will be Contractor’s representative at the Site and shall have authority to act on
behalf of Contractor. All communication given to or received from the Superintendent shall be
binding on Contractor.
C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of
construction.
5.02 Labor; Working Hours
A. Contractor shall provide competent, suitably qualified personnel to perform construction as
required by the Contract Documents. Contractor shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or protection of persons or the Work or property at
the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work
at the Site shall be performed during Regular Working Hours. Contractor will not permit the
performance of Work beyond Regular Working Hours or for Weekend Working Hours without
City’s written consent (which will not be unreasonably withheld). Written request (by letter or
electronic communication) to perform Work:
1. for beyond Regular Working Hours request must be made by noon at least two (2) Business
Days prior
2. for Weekend Working Hours request must be made by noon of the preceding Thursday
3. for legal holidays request must be made by noon two Business Days prior to the legal
holiday.
5.03 Services, Materials, and Equipment
A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities, and all other facilities and incidentals necessary for the
performance, Contractor required testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into the Work shall be as specified or, if not specified,
shall be of good quality and new, except as otherwise provided in the Contract Documents. All
special warranties and guarantees required by the Specifications shall expressly run to the benefit
of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of
required tests) as to the source, kind, and quality of materials and equipment.
00 73 10- 14
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 14 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed,
connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of
the applicable Supplier, except as otherwise may be provided in the Contract Documents.
5.04 Project Schedule
A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01
and the General Requirements as it may be adjusted from time to time as provided below.
1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and
the General Requirements) proposed adjustments in the Project Schedule.
2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be
submitted in accordance with the requirements of Article 9. Adjustments in Contract Time
for projects with City participation shall be made by participating change orders.
5.05 Substitutes and “Or-Equals”
A. Whenever an item of material or equipment is specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the specification or
description is intended to establish the type, function, appearance, and quality required. Unless
the specification or description contains or is followed by words reading that no like, equivalent,
or “or-equal” item or no substitution is permitted, other items of material or equipment of other
Suppliers may be submitted to City for review under the circumstances described below.
1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and sufficiently similar so that no change in
related Work will be required, it may be considered by City as an “or-equal” item, in which
case review and approval of the proposed item may, in City’s sole discretion, be
accomplished without compliance with some or all of the requirements for approval of
proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of
material or equipment will be considered functionally equal to an item so named if:
a. City determines that:
1) it is at least equal in materials of construction, quality, durability, appearance,
strength, and design characteristics;
2) it will reliably perform at least equally well the function and achieve the results
imposed by the design concept of the completed Project as a functioning whole; and
3) it has a proven record of performance and availability of responsive service; and
b. Contractor certifies that, if approved and incorporated into the Work:
1) there will be no increase in cost to the City or increase in Contract Time; and
00 73 10- 15
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 15 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2) it will conform substantially to the detailed requirements of the item named in the
Contract Documents.
2. Substitute Items:
a. If in City’s sole discretion an item of material or equipment proposed by Contractor does
not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a
proposed substitute item.
b. Contractor shall submit sufficient information as provided below to allow City to
determine if the item of material or equipment proposed is essentially equivalent to that
named and an acceptable substitute therefor. Requests for review of proposed substitute
items of material or equipment will not be accepted by City from anyone other than
Contractor.
c. Contractor shall make written application to City for review of a proposed substitute item
of material or equipment that Contractor seeks to furnish or use. The application shall
comply with Section 01 25 00 and:
1) shall certify that the proposed substitute item will:
i. perform adequately the functions and achieve the results called for by the general
design;
ii. be similar in substance to that specified;
iii. be suited to the same use as that specified; and
2) will state:
i. the extent, if any, to which the use of the proposed substitute item will prejudice
Contractor’s achievement of final completion on time;
ii. whether use of the proposed substitute item in the Work will require a change in
any of the Contract Documents (or in the provisions of any other direct contract
with City for other work on the Project) to adapt the design to the proposed
substitute item;
iii. whether incorporation or use of the proposed substitute item in connection with
the Work is subject to payment of any license fee or royalty; and
3) will identify:
i. all variations of the proposed substitute item from that specified;
ii. available engineering, sales, maintenance, repair, and replacement services; and
00 73 10- 16
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 16 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
4) shall contain an itemized estimate of all costs or credits that will result directly or
indirectly from use of such substitute item, including costs of redesign and Damage
Claims of other contractors affected by any resulting change.
B. Substitute Construction Methods or Procedures: If a specific means, method, technique,
sequence, or procedure of construction is expressly required by the Contract Documents,
Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure
of construction approved by City. Contractor shall submit sufficient information to allow City, in
City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly
called for by the Contract Documents. Contractor shall make written application to City for
review in the same manner as those provided in Paragraph 5.05.A.2.
C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require
Contractor to furnish additional data about the proposed substitute. City will be the sole judge of
acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review
is complete, which will be evidenced by a Change Order in the case of a substitute and an
accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination.
D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special
performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall
indemnify and hold harmless City and anyone directly or indirectly employed by them from and
against any and all claims, damages, losses and expenses (including attorneys fees) arising out
of the use of substituted materials or equipment.
E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or
submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City
approves a substitute so proposed or submitted by Contractor, Contractor may be required to
reimburse City for evaluating each such proposed substitute. Contractor may also be required to
reimburse City for the charges for making changes in the Contract Documents.
F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or
“or-equal” at Contractor’s expense.
G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute
shall be incorporated to the Contract by Participating Change Order.
5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors)
A. The Contractor and any subcontractors are required to be prequalified for the work types
requiring pre-qualification
5.07 Concerning Subcontractors, Suppliers, and Others
A. Minority and Women Owned Business Enterprise Compliance:
00 73 10- 17
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 17 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Required for this Contract.
(Check this box if there is any City Participation)
Not Required for this Contract.
It is City policy to ensure the full and equitable participation by Minority and Women Business
Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the
Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent
of the City’s MWBE Ordinance (as amended) by the following:
1. Contractor shall, upon request by City, provide complete and accurate information regarding
actual work performed by a MWBE on the Contract and payment therefor.
2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without
written consent of the City. Any unjustified change or deletion shall be a material breach of
Contract and may result in debarment in accordance with the procedures outlined in the
Ordinance.
3. Contractor shall, upon request by City, allow an audit and/or examination of any books,
records, or files in the possession of the Contractor that will substantiate the actual work
performed by an MWBE. Material misrepresentation of any nature will be grounds for
termination of the Contract. Any such misrepresentation may be grounds for disqualification
of Contractor to bid on future contracts with the City for a period of not less than three years.
B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors,
Suppliers, and other individuals or entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract
Documents:
1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity
any contractual relationship between City and any such Subcontractor, Supplier or other
individual or entity; nor
2. shall create any obligation on the part of City to pay or to see to the payment of any moneys
due any such Subcontractor, Supplier, or other individual or entity except as may otherwise
be required by Laws and Regulations.
C. Contractor shall be solely responsible for scheduling and coordinating the Work of
Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the
Work under a direct or indirect contract with Contractor.
D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing
any of the Work shall communicate with City through Contractor.
E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an
appropriate agreement between Contractor and the Subcontractor or Supplier which specifically
binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract
00 73 10- 18
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 18 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents, Contractor shall provide City contract numbers and reference numbers to the
Subcontractors and/or Suppliers.
5.08 Wage Rates
Required for this Contract.
Not Required for this Contract.
A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of
Chapter 2258, Texas Government Code (as amended), including the payment of not less than the
rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in
accordance with Chapter 2258. Such prevailing wage rates are included in these Contract
Documents.
B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage
shall, upon demand made by the City, pay to the City $60 for each worker employed for each
calendar day or part of the day that the worker is paid less than the prevailing wage rates
stipulated in these contract documents. This penalty shall be retained by the City to offset its
administrative costs, pursuant to Texas Government Code 2258.023.
C. Complaints of Violations and City Determination of Good Cause. On receipt of information,
including a complaint by a worker, concerning an alleged violation of 2258.023, Texas
Government Code, by a Contractor or Subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether
good cause exists to believe that the violation occurred. The City shall notify in writing the
Contractor or Subcontractor and any affected worker of its initial determination. Upon the
City’s determination that there is good cause to believe the Contractor or Subcontractor has
violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or
claimants as the difference between wages paid and wages due under the prevailing wage rates,
such amounts being subtracted from successive progress payments pending a final determination
of the violation.
D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of
Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected
worker, shall be submitted to binding arbitration in accordance with the Texas General
Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any
affected worker does not resolve the issue by agreement before the 15th day after the date the
City makes its initial determination pursuant to Paragraph C above. If the persons required to
arbitrate under this section do not agree on an arbitrator before the 11th day after the date that
arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is
final and binding on all parties and may be enforced in any court of competent jurisdiction.
E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3)
years following the date of acceptance of the work, maintain records that show (i) the name and
00 73 10- 19
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 19 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
occupation of each worker employed by the Contractor in the construction of the Work provided
for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be
open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right
to Audit, shall pertain to this inspection.
F. Progress Payments. With each progress payment or payroll period, whichever is less, the
Contractor shall submit an affidavit stating that the Contractor has complied with the
requirements of Chapter 2258, Texas Government Code.
G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at
all times.
H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall
otherwise require all of its Subcontractors to comply with Paragraphs A through G above.
5.09 Patent Fees and Royalties
A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold
harmless City, from and against all claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and other professionals and all court
or arbitration or other dispute resolution costs) arising out of or relating to any infringement of
patent rights or copyrights incident to the use in the performance of the Work or resulting from
the incorporation in the Work of any invention, design, process, product, or device not specified
in the Contract Documents.
5.10 Laws and Regulations
A. Contractor shall give all notices required by and shall comply with all Laws and Regulations
applicable to the performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s
compliance with any Laws or Regulations.
B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws
or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such Work.
However, it shall not be Contractor’s responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of
Contractor’s obligations under Paragraph 3.01.
5.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas:
1. Contractor shall confine construction equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas permitted by Laws and Regulations, and
shall not unreasonably encumber the Site and other areas with construction equipment or
00 73 10- 20
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 20 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
other materials or equipment. Contractor shall assume full responsibility for any damage to
any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is
carrying on operations in a portion of a street, right-of-way, or easement greater than is
necessary for proper execution of the Work, the City may require the Contractor to finish the
section on which operations are in progress before work is commenced on any additional
area of the Site.
3. Should any Damage Claim be made by any such owner or occupant because of the
performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim.
4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and
against all claims, costs, losses, and damages arising out of or relating to any claim or
action, legal or equitable, brought by any such owner or occupant against City.
B. Removal of Debris During Performance of the Work: During the progress of the Work
Contractor shall keep the Site and other areas free from accumulations of waste materials,
rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other
debris shall conform to applicable Laws and Regulations.
C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the
clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the
Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as
the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the
written notice (by letter or electronic communication), and shall be entitled to recover its cost in
doing so. The City may withhold Final Acceptance until clean-up is complete and cost are
recovered.
D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and
the Work and make it ready for utilization by City or adjacent property owner. At the completion
of the Work Contractor shall remove from the Site all tools, appliances, construction equipment
and machinery, and surplus materials and shall restore to original condition or better all property
disturbed by the Work.
E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded
in any manner that will endanger the structure, nor shall Contractor subject any part of the Work
or adjacent property to stresses or pressures that will endanger it.
5.12 Record Documents
A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor
and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change
Orders, Field Orders, and written interpretations and clarifications in good order and annotated
to show changes made during construction. These record documents together with all approved
00 73 10- 21
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 21 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Samples and a counterpart of all accepted Submittals will be available to City for reference.
Upon completion of the Work, these record documents, any operation and maintenance manuals,
and Submittals will be delivered to City prior to Final Inspection. Contractor shall include
accurate locations for buried and imbedded items.
5.13 Safety and Protection
A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Such responsibility does not relieve
Subcontractors of their responsibility for the safety of persons or property in the performance of
their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall
take all necessary precautions for the safety of, and shall provide the necessary protection to
prevent damage, injury or loss to:
1. all persons on the Site or who may be affected by the Work;
2. all the Work and materials and equipment to be incorporated therein, whether in storage on
or off the Site; and
3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities, and Underground Facilities not designated for
removal, relocation, or replacement in the course of construction.
B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of
persons or property, or to the protection of persons or property from damage, injury, or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall
notify owners of adjacent property and of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate with them in the protection,
removal, relocation, and replacement of their property.
C. Contractor shall comply with the applicable requirements of City’s safety programs, if any.
D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any,
with which City’s employees and representatives must comply while at the Site.
E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused,
directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any
other individual or entity directly or indirectly employed by any of them to perform any of the
Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor.
F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue
until such time as all the Work is completed and City has accepted the Work.
5.14 Safety Representative
Contractor shall inform City in writing of Contractor’s designated safety representative at the Site.
00 73 10- 22
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 22 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
5.15 Hazard Communication Programs
Contractor shall be responsible for coordinating any exchange of material safety data sheets or other
hazard communication information required to be made available to or exchanged between or
among employers in accordance with Laws or Regulations.
5.16 Submittals
A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal
will be identified as required by City.
1. Submit number of copies specified in the General Requirements.
2. Data shown on the Submittals will be complete with respect to quantities, dimensions,
specified performance and design criteria, materials, and similar data to show City the
services, materials, and equipment Contractor proposes to provide and to enable City to
review the information for the limited purposes required by Paragraph 5.16.C.
3. Submittals submitted as herein provided by Contractor and reviewed by City for
conformance with the design concept shall be executed in conformity with the Contract
Documents unless otherwise required by City.
4. When Submittals are submitted for the purpose of showing the installation in greater detail,
their review shall not excuse Contractor from requirements shown on the Drawings and
Specifications.
5. For-Information-Only submittals upon which the City is not expected to conduct review or
take responsive action may be so identified in the Contract Documents.
6. Submit required number of Samples specified in the Specifications.
7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as City may require to enable City to review the
submittal for the limited purposes required by Paragraph 5.16.C.
B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any
related Work performed prior to City’s review and acceptance of the pertinent submittal will be
at the sole expense and responsibility of Contractor.
C. City’s Review:
1. City will provide timely review of required Submittals in accordance with the Schedule of
Submittals acceptable to City. City’s review and acceptance will be only to determine if the
items covered by the submittals will, after installation or incorporation in the Work, conform
to the information given in the Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole as indicated by the Contract
Documents.
00 73 10- 23
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 23 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular means, method, technique, sequence,
or procedure of construction is specifically and expressly called for by the Contract
Documents) or to safety precautions or programs incident thereto. The review and
acceptance of a separate item as such will not indicate approval of the assembly in which the
item functions.
3. City’s review and acceptance shall not relieve Contractor from responsibility for any
variation from the requirements of the Contract Documents unless Contractor has complied
with the requirements of Section 01 33 00 and City has given written acceptance of each
such variation by specific written notation thereof incorporated in or accompanying the
Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for
complying with the requirements of the Contract Documents.
5.17 Contractor’s General Warranty and Guarantee
A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract
Documents and will not be defective. City and its officers, directors, members, partners,
employees, agents, consultants, and subcontractors shall be entitled to rely on representation of
Contractor’s warranty and guarantee.
B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or operation by persons other than Contractor,
Subcontractors, Suppliers, or any other individual or entity for whom Contractor is
responsible; or
2. normal wear and tear under normal usage.
C. Contractor’s obligation to perform and complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will constitute an acceptance of Work that is
not in accordance with the Contract Documents or a release of Contractor’s obligation to
perform the Work in accordance with the Contract Documents:
1. observations by City;
2. recommendation or payment by City or Developer of any progress or final payment;
3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by
City;
4. use or occupancy of the Work or any part thereof by City;
5. any review and acceptance of a Submittal by City;
6. any inspection, test, or approval by others; or
00 73 10- 24
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 24 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7. any correction of defective Work by City.
D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to
other work or property resulting therefrom which shall appear within a period of two (2) years
from the date of Final Acceptance of the Work unless a longer period is specified and shall
furnish a good and sufficient maintenance bond, complying with the requirements of Article
4.02.B. The City will give notice of observed defects with reasonable promptness.
5.18 Indemnification
A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the
City, its officers, servants and employees, from and against any and all claims arising out of, or
alleged to arise out of, the work and services to be performed by the Contractor, its officers,
agents, employees, subcontractors, licenses or invitees under this Contract. THIS
INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE
AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME
OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY
ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is
intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by
the City in defending against such claims and causes of actions.
B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its
officers, servants and employees, from and against any and all loss, damage or destruction of
property of the City, arising out of, or alleged to arise out of, the work and services to be
performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees
under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY
INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR
PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE
CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF
THE CITY.
5.19 Delegation of Professional Design Services
A. Contractor will not be required to provide professional design services unless such services are
specifically required by the Contract Documents for a portion of the Work or unless such
services are required to carry out Contractor’s responsibilities for construction means, methods,
techniques, sequences and procedures.
B. If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of Contractor by the Contract Documents, City
will specify all performance and design criteria that such services must satisfy. Contractor shall
cause such services or certifications to be provided by a properly licensed professional, whose
signature and seal shall appear on all drawings, calculations, specifications, certifications, and
Submittals prepared by such professional. Submittals related to the Work designed or certified
by such professional, if prepared by others, shall bear such professional’s written approval when
submitted to City.
00 73 10- 25
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 25 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals, provided City has specified
to Contractor performance and design criteria that such services must satisfy.
D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design
drawings will be only for the limited purpose of checking for conformance with performance
and design criteria given and the design concept expressed in the Contract Documents. City’s
review and acceptance of Submittals (except design calculations and design drawings) will be
only for the purpose stated in Paragraph 5.16.C.
5.20 Right to Audit:
A. The City reserves the right to audit all projects utilizing City funds
B. The Contractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of the Contractor involving transactions relating
to this Contract. Contractor agrees that the City shall have access during Regular Working Hours
to all necessary Contractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this Paragraph. The City shall
give Contractor reasonable advance notice of intended audits.
C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that
the subcontractor agrees that the City shall, until the expiration of three (3) years after final
payment under this Contract, have access to and the right to examine and photocopy any directly
pertinent books, documents, papers, and records of such Subcontractor, involving transactions to
the subcontract, and further, that City shall have access during Regular Working Hours to all
Subcontractor facilities, and shall be provided adequate and appropriate work space in order to
conduct audits in compliance with the provisions of this Paragraph. The City shall give
Subcontractor reasonable advance notice of intended audits.
D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate
published in the Texas Administrative Code in effect as of the time copying is performed.
5.21 Nondiscrimination
A. The City is responsible for operating Public Transportation Programs and implementing transit-
related projects, which are funded in part with Federal financial assistance awarded by the U.S.
Department of Transportation and the Federal Transit Administration (FTA), without
discriminating against any person in the United States on the basis of race, color, or national
origin.
B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of
the Act and the Regulations as further defined in the Supplementary Conditions for any project
receiving Federal assistance.
00 73 10- 26
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 26 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 6 – OTHER WORK AT THE SITE
6.01 Related Work at Site
A. City may perform other work related to the Project at the Site with City’s employees, or other
City contractors, or through other direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Contract Documents, then written notice
thereof will be given to Contractor prior to starting any such other work; and
B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility
owner, and City, if City is performing other work with City’s employees or other City
contractors, proper and safe access to the Site, provide a reasonable opportunity for the
introduction and storage of materials and equipment and the execution of such other work, and
properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of
the Work that may be required to properly connect or otherwise make its several parts come
together and properly integrate with such other work. Contractor shall not endanger any work of
others by cutting, excavating, or otherwise altering such work; provided, however, that
Contractor may cut or alter others' work with the written consent of City and the others whose
work will be affected.
C. If the proper execution or results of any part of Contractor’s Work depends upon work
performed by others under this Article 7, Contractor shall inspect such other work and promptly
report to City in writing any delays, defects, or deficiencies in such other work that render it
unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s
failure to so report will constitute an acceptance of such other work as fit and proper for
integration with Contractor’s Work except for latent defects in the work provided by others.
ARTICLE 7 – CITY’S RESPONSIBILITIES
7.01 Inspections, Tests, and Approvals
City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph
11.03.
7.02 Limitations on City’s Responsibilities
A. The City shall not supervise, direct, or have control or authority over, nor be responsible for,
Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any failure of Contractor to comply with Laws
and Regulations applicable to the performance of the Work. City will not be responsible for
Contractor’s failure to perform the Work in accordance with the Contract Documents.
B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13.
00 73 10- 27
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 27 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
7.03 Compliance with Safety Program
While at the Site, City’s employees and representatives shall comply with the specific applicable
requirements of Contractor’s safety programs of which City has been informed pursuant to
Paragraph 5.13.
ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION
8.01 City’s Project Representative
City will provide one or more Project Representative(s) during the construction period. The duties
and responsibilities and the limitations of authority of City’s representative during construction are
set forth in the Contract Documents.
A. City’s Project Representative will make visits to the Site at intervals appropriate to the various
stages of construction as City deems necessary in order to observe the progress that has been
made and the quality of the various aspects of Contractor’s executed Work. Based on
information obtained during such visits and observations, City’s Project Representative will
determine, in general, if the Work is proceeding in accordance with the Contract Documents.
City’s Project Representative will not be required to make exhaustive or continuous inspections
on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts
will be directed toward providing City a greater degree of confidence that the completed Work
will conform generally to the Contract Documents.
B. City’s Project Representative’s visits and observations are subject to all the limitations on
authority and responsibility in the Contract Documents.
8.02 Authorized Variations in Work
City’s Project Representative may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are compatible with the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be accomplished by a Field Order and will be
binding on City Developer, and also on Contractor, who shall perform the Work involved promptly.
8.03 Rejecting Defective Work
City will have authority to reject Work which City’s Project Representative believes to be defective,
or will not produce a completed Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed Project as a functioning whole as
indicated by the Contract Documents. City will have authority to conduct special inspection or
testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or
completed.
00 73 10- 28
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 28 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
8.04 Determinations for Work Performed
Contractor will determine the actual quantities and classifications of Work performed. City’s Project
Representative will review with Contractor the preliminary determinations on such matters before
rendering a written recommendation. City’s written decision will be final (except as modified to
reflect changed factual conditions or more accurate data).
ARTICLE 9 – CHANGES IN THE WORK
9.01 Authorized Changes in the Work
A. Without invalidating the Contract and without notice to any surety, City may, at any time or
from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall
promptly proceed with the Work involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise specifically provided). Extra Work
shall be memorialized by a Participating Change Order which may or may not precede an order
of Extra work.
B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a
project with City participation, a Field Order may be issued by the City.
9.02 Notification to Surety
If the provisions of any bond require notice to be given to a surety of any change affecting the
general scope of the Work or the provisions of the Contract Documents (including, but not limited
to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s
responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the
effect of any such change.
ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME
10.01 Change of Contract Price
A. The Contract Price may only be changed by a Participating Change Order for projects with City
participation.
10.02 Change of Contract Time
A. The Contract Time may only be changed by a Participating Change Order for projects with City
participation.
10.03 Delays
A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or
damages (including but not limited to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or anticipated project.
00 73 10- 29
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 29 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
11.01 Notice of Defects
Notice of all defective Work of which City has actual knowledge will be given to Contractor.
Defective Work may be rejected, corrected, or accepted as provided in this Article 13.
11.02 Access to Work
City, independent testing laboratories, and governmental agencies with jurisdictional interests will
have access to the Site and the Work at reasonable times for their observation, inspection, and
testing. Contractor shall provide them proper and safe conditions for such access and advise them of
Contractor’s safety procedures and programs so that they may comply therewith as applicable.
11.03 Tests and Inspections
A. Contractor shall give City timely notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required
inspections or tests.
B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any
of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full
responsibility for arranging and obtaining such independent inspections, tests, retests or
approvals, pay all costs in connection therewith, and furnish City the required certificates of
inspection or approval; excepting, however, those fees specifically identified in the
Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR)
inspections, which shall be paid as described in the Supplementary Conditions.
C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection
with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or
equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment
submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work.
Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by
City.
D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to
perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by
City.
1. City will coordinate such Testing to the extent possible, with Contractor;
2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other
similar negative result, the Contractor shall be responsible for paying for any and all retests.
Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative
result and require a retest.
00 73 10- 30
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 30 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the
Testing Lab by Contractor. City will forward all invoices for retests to
Developer/Contractor.
4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance
until the Testing Lab is Paid
E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by
Contractor without written concurrence of City, Contractor shall, if requested by City, uncover
such Work for observation.
11.04 Uncovering Work
A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it
must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s
expense.
11.05 City May Stop the Work
If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials
or equipment, or fails to perform the Work in such a way that the completed Work will conform to
the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until
the cause for such order has been eliminated; however, this right of City to stop the Work shall not
give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any
Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent
of any of them.
11.06 Correction or Removal of Defective Work
A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to
an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has
been rejected by City, remove it from the Project and replace it with Work that is not defective.
Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not
limited to all fees and charges of engineers, architects, attorneys, and other professionals and all
court or arbitration or other dispute resolution costs) arising out of or relating to such correction
or removal (including but not limited to all costs of repair or replacement of work of others).
Failure to require the removal of any defective Work shall not constitute acceptance of such
Work.
B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07,
Contractor shall take no action that would void or otherwise impair City’s special warranty and
guarantee, if any, on said Work.
11.07 Correction Period
A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may
be prescribed by the terms of any applicable special guarantee required by the Contract
00 73 10- 31
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 31 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
Documents), any Work is found to be defective, or if the repair of any damages to the land or
areas made available for Contractor’s use by City or permitted by Laws and Regulations as
contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without
cost to City and in accordance with City’s written instructions:
1. repair such defective land or areas; or
2. correct such defective Work; or
3. if the defective Work has been rejected by City, remove it from the Project and replace it
with Work that is not defective, and
4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work
of others or other land or areas resulting therefrom.
B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an
emergency where delay would cause serious risk of loss or damage, City may have the defective
Work corrected or repaired or may have the rejected Work removed and replaced. All claims,
costs, losses, and damages (including but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or other dispute resolution costs)
arising out of or relating to such correction or repair or such removal and replacement (including
but not limited to all costs of repair or replacement of work of others) will be paid by Contractor.
C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or
removed and replaced under this Paragraph 11.07, the correction period hereunder with respect
to such Work may be required to be extended for an additional period of one year after the end
of the initial correction period. City shall provide 30 days written notice to Contractor and
Developer should such additional warranty coverage be required. Contractor’s obligations under
this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this
Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any
applicable statute of limitation or repose.
11.08 City May Correct Defective Work
A. If Contractor fails within a reasonable time after written notice from City to correct defective
Work, or to remove and replace rejected Work as required by City in accordance with Paragraph
11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents,
or if Contractor fails to comply with any other provision of the Contract Documents, City may,
after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such
deficiency.
B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed
expeditiously. In connection with such corrective or remedial action, City may exclude
Contractor from all or part of the Site, take possession of all or part of the Work and suspend
Contractor’s services related thereto, and incorporate in the Work all materials and equipment
incorporated in the Work, stored at the Site or for which City has paid Contractor but which are
00 73 10- 32
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 32 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants,
employees, and City’s other contractors, access to the Site to enable City to exercise the rights
and remedies under this Paragraph.
C. All claims, costs, losses, and damages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and all court or other dispute resolution
costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph
13.09 will be charged against Contractor, and a Change Order will be issued incorporating the
necessary revisions in the Contract Documents with respect to the Work; and City shall be
entitled to an appropriate decrease in the Contract Price.
D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the
performance of the Work attributable to the exercise of City’s rights and remedies under this
Paragraph 11.09.
ARTICLE 12 – COMPLETION
12.01 Contractor’s Warranty of Title
Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any
Application for Payment will pass to City no later than the time of Final Acceptance and shall be
free and clear of all Liens.
12.02 Partial Utilization
A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed
part of the Work which has specifically been identified in the Contract Documents, or which
City, determines constitutes a separately functioning and usable part of the Work that can be
used by City for its intended purpose without significant interference with Contractor’s
performance of the remainder of the Work. City at any time may notify Contractor in writing to
permit City to use or occupy any such part of the Work which City determines to be ready for its
intended use, subject to the following conditions:
1. Contractor at any time may notify City in writing that Contractor considers any such part of
the Work ready for its intended use.
2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and
Contractor shall make an inspection of that part of the Work to determine its status of
completion. If City does not consider that part of the Work to be substantially complete, City
will notify Contractor in writing giving the reasons therefor.
3. Partial Utilization will not constitute Final Acceptance by City.
12.03 Final Inspection
A. Upon written notice from Contractor that the entire Work is complete in accordance with the
Contract Documents:
00 73 10- 33
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 33 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
1. within 10 days, City will schedule a Final Inspection with Contractor.
2. City will notify Contractor in writing of all particulars in which this inspection reveals that
the Work is incomplete or defective. Contractor shall immediately take such measures as are
necessary to complete such Work or remedy such deficiencies.
12.04 Final Acceptance
A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the
Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction
of the following:
1. All documentation called for in the Contract Documents, including but not limited to the
evidence of insurance required by Paragraph 5.03;
2. consent of the surety, if any, to Final Acceptance;
3. a list of all pending or released Damage Claims against City that Contractor believes are
unsettled; and
4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to
City) of all Lien rights arising out of or Liens filed in connection with the Work.
5. after all Damage Claims have been resolved:
a. directly by the Contractor or;
b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s
insurance provider for resolution.
6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or
other requirements of the Contract Documents which specifically continue thereafter.
ARTICLE 13 – SUSPENSION OF WORK
13.01 City May Suspend Work
A. At any time and without cause, City may suspend the Work or any portion thereof by written
notice to Contractor and which may fix the date on which Work will be resumed. Contractor
shall resume the Work on the date so fixed. During temporary suspension of the Work covered
by these Contract Documents, for any reason, the City will stop contract time on City
participation projects.
B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the
control of and without the fault or negligence of the Contractor, and should it be determined by
mutual consent of the Contractor and City that a solution to allow construction to proceed is not
00 73 10- 34
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 34 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
available within a reasonable period of time, Contractor may request an extension in Contract
Time, directly attributable to any such suspension.
C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall
store all materials in such a manner that they will not obstruct or impede the public unnecessarily
nor become damaged in any way, and he shall take every precaution to prevent damage or
deterioration of the work performed; he shall provide suitable drainage about the work, and erect
temporary structures where necessary.
ARTICLE 14 – MISCELLANEOUS
14.01 Giving Notice
A. Whenever any provision of the Contract Documents requires the giving of written notice, it will
be deemed to have been validly given if:
1. delivered in person to the individual or to a member of the firm or to an officer of the
corporation for whom it is intended; or
2. delivered at or sent by registered or certified mail, postage prepaid, to the last business
address known to the giver of the notice.
B. Business address changes must be promptly made in writing to the other party.
C. Whenever the Contract Documents specifies giving notice by electronic means such electronic
notice shall be deemed sufficient upon confirmation of receipt by the receiving party.
14.02 Computation of Times
When any period of time is referred to in the Contract Documents by days, it will be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on a
Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last
day of the period.
14.03 Cumulative Remedies
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto are in addition to, and are not to be construed in any way as
a limitation of, any rights and remedies available to any or all of them which are otherwise imposed
or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the
Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically
in the Contract Documents in connection with each particular duty, obligation, right, and remedy to
which they apply.
00 73 10- 35
Standard City Conditions Of The Construction Contract For Developer Awarded Projects
Page 35 of 35
CITY OF FORT WORTH
STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS
Revised: January 10, 2013
14.04 Survival of Obligations
All representations, indemnifications, warranties, and guarantees made in, required by, or given in
accordance with the Contract Documents, as well as all continuing obligations indicated in the
Contract Documents, will survive final payment, completion, and acceptance of the Work or
termination or completion of the Contract or termination of the services of Contractor.
14.05 Headings
Article and paragraph headings are inserted for convenience only and do not constitute parts of these
General Conditions.
DIVISION 01
GENERAL REQUIREMENTS
01 11 00 - 1
DAP SUMMARY OF WORK
Page 1 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects City Project #102139
Revised December 20, 2012
SECTION 01 11 00
SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Summary of Work to be performed in accordance with the Contract Documents
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract
2. Division 1 - General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Work Covered by Contract Documents
1. Work is to include furnishing all labor, materials, and equipment, and performing
all Work necessary for this construction project as detailed in the Drawings and
Specifications.
B. Subsidiary Work
1. Any and all Work specifically governed by documentary requirements for the
project, such as conditions imposed by the Drawings or Contract Documents in
which no specific item for bid has been provided for in the Proposal and the item is
not a typical unit bid item included on the standard bid item list, then the item shall
be considered as a subsidiary item of Work, the cost of which shall be included in
the price bid in the Proposal for various bid items.
C. Use of Premises
1. Coordinate uses of premises under direction of the City.
2. Assume full responsibility for protection and safekeeping of materials and
equipment stored on the Site.
3. Use and occupy only portions of the public streets and alleys, or other public places
or other rights-of-way as provided for in the ordinances of the City, as shown in the
Contract Documents, or as may be specifically authorized in writing by the City.
a. A reasonable amount of tools, materials, and equipment for construction
purposes may be stored in such space, but no more than is necessary to avoid
delay in the construction operations.
01 11 00 - 2
DAP SUMMARY OF WORK
Page 2 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects City Project #102139
Revised December 20, 2012
b. Excavated and waste materials shall be stored in such a way as not to interfere
with the use of spaces that may be designated to be left free and unobstructed
and so as not to inconvenience occupants of adjacent property.
c. If the street is occupied by railroad tracks, the Work shall be carried on in such
manner as not to interfere with the operation of the railroad.
1) All Work shall be in accordance with railroad requirements set forth in
Division 0 as well as the railroad permit.
D. Work within Easements
1. Do not enter upon private property for any purpose without having previously
obtained permission from the owner of such property.
2. Do not store equipment or material on private property unless and until the
specified approval of the property owner has been secured in writing by the
Contractor and a copy furnished to the City.
3. Unless specifically provided otherwise, clear all rights-of-way or easements of
obstructions which must be removed to make possible proper prosecution of the
Work as a part of the project construction operations.
4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants,
lawns, fences, culverts, curbing, and all other types of structures or improvements,
to all water, sewer, and gas lines, to all conduits, overhead pole lines, or
appurtenances thereof, including the construction of temporary fences and to all
other public or private property adjacent to the Work.
5. Notify the proper representatives of the owners or occupants of the public or private
lands of interest in lands which might be affected by the Work.
a. Such notice shall be made at least 48 hours in advance of the beginning of the
Work.
b. Notices shall be applicable to both public and private utility companies and any
corporation, company, individual, or other, either as owners or occupants,
whose land or interest in land might be affected by the Work.
c. Be responsible for all damage or injury to property of any character resulting
from any act, omission, neglect, or misconduct in the manner or method or
execution of the Work, or at any time due to defective work, material, or
equipment.
6. Fence
a. Restore all fences encountered and removed during construction of the Project
to the original or a better than original condition.
b. Erect temporary fencing in place of the fencing removed whenever the Work is
not in progress and when the site is vacated overnight, and/or at all times to
provide site security.
c. The cost for all fence work within easements, including removal, temporary
closures and replacement, shall be subsidiary to the various items bid in the
project proposal, unless a bid item is specifically provided in the proposal.
01 11 00 - 3
DAP SUMMARY OF WORK
Page 3 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects City Project #102139
Revised December 20, 2012
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 25 00 - 1
DAP SUBSTITUTION PROCEDURES
Page 1 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for requesting the approval of substitution of a product that is not
equivalent to a product which is specified by descriptive or performance criteria or
defined by reference to 1 or more of the following:
a. Name of manufacturer
b. Name of vendor
c. Trade name
d. Catalog number
2. Substitutions are not "or-equals".
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid. No
separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Request for Substitution - General
1. Within 30 days after award of Contract (unless noted otherwise), the City will
consider formal requests from Contractor for substitution of products in place of
those specified.
2. Certain types of equipment and kinds of material are described in Specifications by
means of references to names of manufacturers and vendors, trade names, or catalog
numbers.
a. When this method of specifying is used, it is not intended to exclude from
consideration other products bearing other manufacturer's or vendor's names,
trade names, or catalog numbers, provided said products are "or-equals," as
determined by City.
3. Other types of equipment and kinds of material may be acceptable substitutions
under the following conditions:
a. Or-equals are unavailable due to strike, discontinued production of products
meeting specified requirements, or other factors beyond control of Contractor;
or,
01 25 00 - 2
DAP SUBSTITUTION PROCEDURES
Page 2 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
b. Contractor proposes a cost and/or time reduction incentive to the City.
1.5 SUBMITTALS
A. See Request for Substitution Form (attached)
B. Procedure for Requesting Substitution
1. Substitution shall be considered only:
a. After award of Contract
b. Under the conditions stated herein
2. Submit 3 copies of each written request for substitution, including:
a. Documentation
1) Complete data substantiating compliance of proposed substitution with
Contract Documents
2) Data relating to changes in construction schedule, when a reduction is
proposed
3) Data relating to changes in cost
b. For products
1) Product identification
a) Manufacturer's name
b) Telephone number and representative contact name
c) Specification Section or Drawing reference of originally specified
product, including discrete name or tag number assigned to original
product in the Contract Documents
2) Manufacturer's literature clearly marked to show compliance of proposed
product with Contract Documents
3) Itemized comparison of original and proposed product addressing product
characteristics including, but not necessarily limited to:
a) Size
b) Composition or materials of construction
c) Weight
d) Electrical or mechanical requirements
4) Product experience
a) Location of past projects utilizing product
b) Name and telephone number of persons associated with referenced
projects knowledgeable concerning proposed product
c) Available field data and reports associated with proposed product
5) Samples
a) Provide at request of City.
b) Samples become the property of the City.
c. For construction methods:
1) Detailed description of proposed method
2) Illustration drawings
C. Approval or Rejection
1. Written approval or rejection of substitution given by the City
2. City reserves the right to require proposed product to comply with color and pattern
of specified product if necessary to secure design intent.
3. In the event the substitution is approved, if a reduction in cost or time results, it will
be documented by Change Order.
01 25 00 - 3
DAP SUBSTITUTION PROCEDURES
Page 3 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
4. Substitution will be rejected if:
a. Submittal is not through the Contractor with his stamp of approval
b. Request is not made in accordance with this Specification Section
c. In the Developer’s opinion, acceptance will require substantial revision of the
original design
d. In the City’s or Developer’s opinion, substitution will not perform adequately
the function consistent with the design intent
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. In making request for substitution or in using an approved product, the Contractor
represents that the Contractor:
1. Has investigated proposed product, and has determined that it is adequate or
superior in all respects to that specified, and that it will perform function for which it
is intended
2. Will provide same guarantee for substitute item as for product specified
3. Will coordinate installation of accepted substitution into Work, to include building
modifications if necessary, making such changes as may be required for Work to be
complete in all respects
4. Waives all claims for additional costs related to substitution which subsequently
arise
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 25 00 - 4
DAP SUBSTITUTION PROCEDURES
Page 4 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
EXHIBIT A
REQUEST FOR SUBSTITUTION FORM:
TO:
PROJECT: DATE:
We hereby submit for your consideration the following product instead of the specified item for
the above project:
SECTION PARAGRAPH SPECIFIED ITEM
Proposed Substitution:
Reason for Substitution:
Include complete information on changes to Drawings and/or Specifications which proposed
substitution will require for its proper installation.
Fill in Blanks Below:
A. Will the undersigned contractor pay for changes to the building design, including engineering
and detailing costs caused by the requested substitution?
B. What effect does substitution have on other trades?
C. Differences between proposed substitution and specified item?
D. Differences in product cost or product delivery time?
E. Manufacturer's guarantees of the proposed and specified items are:
Equal Better (explain on attachment)
The undersigned states that the function, appearance and quality are equivalent or superior to the
specified item.
Submitted By: For Use by City
Signature Recommended Recommended
as noted
Firm Not recommended Received late
Address By
Date
Date Remarks
Telephone
For Use by City:
Approved Rejected
City Date
01 31 19 - 1
DAP PRECONSTRUCTION MEETING
Page 1 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
SECTION 01 31 19
PRECONSTRUCTION MEETING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Provisions for the preconstruction meeting to be held prior to the start of Work to
clarify construction contract administration procedures
B. Deviations from this City of Fort Worth Standard Specification
1. No construction schedule required unless requested by the City.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Attend preconstruction meeting.
2. Representatives of Contractor, subcontractors and suppliers attending meetings
shall be qualified and authorized to act on behalf of the entity each represents.
3. Meeting administered by City may be tape recorded.
a. If recorded, tapes will be used to prepare minutes and retained by City for
future reference.
B. Preconstruction Meeting
1. A preconstruction meeting will be held within 14 days after the delivery of the
distribution package to the City.
a. The meeting will be scheduled and administered by the City.
2. The Project Representative will preside at the meeting, prepare the notes of the
meeting and distribute copies of same to all participants who so request by fully
completing the attendance form to be circulated at the beginning of the meeting.
3. Attendance shall include:
a. Developer and Consultant
b. Contractor's project manager
c. Contractor's superintendent
d. Any subcontractor or supplier representatives whom the Contractor may desire
to invite or the City may request
01 31 19 - 2
DAP PRECONSTRUCTION MEETING
Page 2 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
e. Other City representatives
f. Others as appropriate
4. Preliminary Agenda may include:
a. Introduction of Project Personnel
b. General Description of Project
c. Status of right-of-way, utility clearances, easements or other pertinent permits
d. Contractor’s work plan and schedule
e. Contract Time
f. Notice to Proceed
g. Construction Staking
h. Progress Payments
i. Extra Work and Change Order Procedures
j. Field Orders
k. Disposal Site Letter for Waste Material
l. Insurance Renewals
m. Payroll Certification
n. Material Certifications and Quality Control Testing
o. Public Safety and Convenience
p. Documentation of Pre-Construction Conditions
q. Weekend Work Notification
r. Legal Holidays
s. Trench Safety Plans
t. Confined Space Entry Standards
u. Coordination with the City’s representative for operations of existing water
systems
v. Storm Water Pollution Prevention Plan
w. Coordination with other Contractors
x. Early Warning System
y. Contractor Evaluation
z. Special Conditions applicable to the project
aa. Damages Claims
bb. Submittal Procedures
cc. Substitution Procedures
dd. Correspondence Routing
ee. Record Drawings
ff. Temporary construction facilities
gg. MBE/SBE procedures
hh. Final Acceptance
ii. Final Payment
jj. Questions or Comments
01 31 19 - 3
DAP PRECONSTRUCTION MEETING
Page 3 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 32 33 - 1
DAP PRECONSTRUCTION VIDEO
Page 1 of 2
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
SECTION 01 32 33
PRECONSTRUCTION VIDEO
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative and procedural requirements for:
a. Preconstruction Videos
B. Deviations from this City of Fort Worth Standard Specification
1. Though not mandatory, it is highly recommended on infill developer projects.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Preconstruction Video
1. Produce a preconstruction video of the site/alignment, including all areas in the
vicinity of and to be affected by construction.
a. Provide digital copy of video upon request by the City.
2. Retain a copy of the preconstruction video until the end of the maintenance surety
period.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
01 32 33 - 2
DAP PRECONSTRUCTION VIDEO
Page 2 of 2
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 33 00 - 1
DAP SUBMITTALS
Page 1 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
SECTION 01 33 00
DAP SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. General methods and requirements of submissions applicable to the following
Work-related submittals:
a. Shop Drawings
b. Product Data (including Standard Product List submittals)
c. Samples
d. Mock Ups
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Coordination
1. Notify the City in writing, at the time of submittal, of any deviations in the
submittals from the requirements of the Contract Documents.
2. Coordination of Submittal Times
a. Prepare, prioritize and transmit each submittal sufficiently in advance of
performing the related Work or other applicable activities, or within the time
specified in the individual Work Sections, of the Specifications.
b. Contractor is responsible such that the installation will not be delayed by
processing times including, but not limited to:
a) Disapproval and resubmittal (if required)
b) Coordination with other submittals
c) Testing
d) Purchasing
e) Fabrication
f) Delivery
g) Similar sequenced activities
c. No extension of time will be authorized because of the Contractor's failure to
transmit submittals sufficiently in advance of the Work.
01 33 00 - 2
DAP SUBMITTALS
Page 2 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
d. Make submittals promptly in accordance with approved schedule, and in such
sequence as to cause no delay in the Work or in the work of any other
contractor.
B. Submittal Numbering
1. When submitting shop drawings or samples, utilize a 9-character submittal cross-
reference identification numbering system in the following manner:
a. Use the first 6 digits of the applicable Specification Section Number.
b. For the next 2 digits number use numbers 01-99 to sequentially number each
initial separate item or drawing submitted under each specific Section number.
c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e.
A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical
submittal number would be as follows:
03 30 00-08-B
1) 03 30 00 is the Specification Section for Concrete
2) 08 is the eighth initial submittal under this Specification Section
3) B is the third submission (second resubmission) of that particular shop
drawing
C. Contractor Certification
1. Review shop drawings, product data and samples, including those by
subcontractors, prior to submission to determine and verify the following:
a. Field measurements
b. Field construction criteria
c. Catalog numbers and similar data
d. Conformance with the Contract Documents
2. Provide each shop drawing, sample and product data submitted by the Contractor
with a Certification Statement affixed including:
a. The Contractor's Company name
b. Signature of submittal reviewer
c. Certification Statement
1) “By this submittal, I hereby represent that I have determined and verified
field measurements, field construction criteria, materials, dimensions,
catalog numbers and similar data and I have checked and coordinated each
item with other applicable approved shop drawings."
D. Submittal Format
1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches.
2. Bind shop drawings and product data sheets together.
3. Order
a. Cover Sheet
1) Description of Packet
2) Contractor Certification
b. List of items / Table of Contents
c. Product Data /Shop Drawings/Samples /Calculations
E. Submittal Content
1. The date of submission and the dates of any previous submissions
01 33 00 - 3
DAP SUBMITTALS
Page 3 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
2. The Project title and number
3. Contractor identification
4. The names of:
a. Contractor
b. Supplier
c. Manufacturer
5. Identification of the product, with the Specification Section number, page and
paragraph(s)
6. Field dimensions, clearly identified as such
7. Relation to adjacent or critical features of the Work or materials
8. Applicable standards, such as ASTM or Federal Specification numbers
9. Identification by highlighting of deviations from Contract Documents
10. Identification by highlighting of revisions on resubmittals
11. An 8-inch x 3-inch blank space for Contractor and City stamps
F. Shop Drawings
1. As specified in individual Work Sections includes, but is not necessarily limited to:
a. Custom-prepared data such as fabrication and erection/installation (working)
drawings
b. Scheduled information
c. Setting diagrams
d. Actual shopwork manufacturing instructions
e. Custom templates
f. Special wiring diagrams
g. Coordination drawings
h. Individual system or equipment inspection and test reports including:
1) Performance curves and certifications
i. As applicable to the Work
2. Details
a. Relation of the various parts to the main members and lines of the structure
b. Where correct fabrication of the Work depends upon field measurements
1) Provide such measurements and note on the drawings prior to submitting
for approval.
G. Product Data
1. For submittals of product data for products included on the City’s Standard Product
List, clearly identify each item selected for use on the Project.
2. For submittals of product data for products not included on the City’s Standard
Product List, submittal data may include, but is not necessarily limited to:
a. Standard prepared data for manufactured products (sometimes referred to as
catalog data)
1) Such as the manufacturer's product specification and installation
instructions
2) Availability of colors and patterns
3) Manufacturer's printed statements of compliances and applicability
4) Roughing-in diagrams and templates
5) Catalog cuts
6) Product photographs
01 33 00 - 4
DAP SUBMITTALS
Page 4 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
7) Standard wiring diagrams
8) Printed performance curves and operational-range diagrams
9) Production or quality control inspection and test reports and certifications
10) Mill reports
11) Product operating and maintenance instructions and recommended
spare-parts listing and printed product warranties
12) As applicable to the Work
H. Samples
1. As specified in individual Sections, include, but are not necessarily limited to:
a. Physical examples of the Work such as:
1) Sections of manufactured or fabricated Work
2) Small cuts or containers of materials
3) Complete units of repetitively used products color/texture/pattern swatches
and range sets
4) Specimens for coordination of visual effect
5) Graphic symbols and units of Work to be used by the City for independent
inspection and testing, as applicable to the Work
I. Do not start Work requiring a shop drawing, sample or product data nor any material to
be fabricated or installed prior to the approval or qualified approval of such item.
1. Fabrication performed, materials purchased or on-site construction accomplished
which does not conform to approved shop drawings and data is at the Contractor's
risk.
2. The City will not be liable for any expense or delay due to corrections or remedies
required to accomplish conformity.
3. Complete project Work, materials, fabrication, and installations in conformance
with approved shop drawings, applicable samples, and product data.
J. Submittal Distribution
1. Electronic Distribution
a. Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another external FTP site approved by the
City.
b. Shop Drawings
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
b) If Contractor requires more than 1 hard copy of Shop Drawings
returned, Contractor shall submit more than the number of copies listed
above.
c. Product Data
1) Upload submittal to designated project directory and notify appropriate
City representatives via email of submittal posting.
2) Hard Copies
a) 3 copies for all submittals
d. Samples
1) Distributed to the Project Representative
2. Hard Copy Distribution (if required in lieu of electronic distribution)
01 33 00 - 5
DAP SUBMITTALS
Page 5 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
a. Shop Drawings
1) Distributed to the City
2) Copies
a) 8 copies for mechanical submittals
b) 7 copies for all other submittals
c) If Contractor requires more than 3 copies of Shop Drawings returned,
Contractor shall submit more than the number of copies listed above.
b. Product Data
1) Distributed to the City
2) Copies
a) 4 copies
c. Samples
1) Distributed to the Project Representative
2) Copies
a) Submit the number stated in the respective Specification Sections.
3. Distribute reproductions of approved shop drawings and copies of approved
product data and samples, where required, to the job site file and elsewhere as
directed by the City.
a. Provide number of copies as directed by the City but not exceeding the number
previously specified.
K. Submittal Review
1. The review of shop drawings, data and samples will be for general conformance
with the design concept and Contract Documents. This is not to be construed as:
a. Permitting any departure from the Contract requirements
b. Relieving the Contractor of responsibility for any errors, including details,
dimensions, and materials
c. Approving departures from details furnished by the City, except as otherwise
provided herein
2. The review and approval of shop drawings, samples or product data by the City
does not relieve the Contractor from his/her responsibility with regard to the
fulfillment of the terms of the Contract.
a. All risks of error and omission are assumed by the Contractor, and the City will
have no responsibility therefore.
3. The Contractor remains responsible for details and accuracy, for coordinating the
Work with all other associated work and trades, for selecting fabrication processes,
for techniques of assembly and for performing Work in a safe manner.
4. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which City finds to be in the interest of
the City and to be so minor as not to involve a change in Contract Price or time for
performance, the City may return the reviewed drawings without noting an
exception.
5. Submittals will be returned to the Contractor under 1 of the following codes:
a. Code 1
1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or
comments on the submittal.
a) When returned under this code the Contractor may release the
equipment and/or material for manufacture.
b. Code 2
01 33 00 - 6
DAP SUBMITTALS
Page 6 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of
the notations and comments IS NOT required by the Contractor.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
c. Code 3
1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is
assigned when notations and comments are extensive enough to require a
resubmittal of the package.
a) The Contractor may release the equipment or material for manufacture;
however, all notations and comments must be incorporated into the
final product.
b) This resubmittal is to address all comments, omissions and
non-conforming items that were noted.
c) Resubmittal is to be received by the City within 15 Calendar Days of
the date of the City's transmittal requiring the resubmittal.
d. Code 4
1) "NOT APPROVED" is assigned when the submittal does not meet the
intent of the Contract Documents.
a) The Contractor must resubmit the entire package revised to bring the
submittal into conformance.
b) It may be necessary to resubmit using a different manufacturer/vendor
to meet the Contract Documents.
6. Resubmittals
a. Handled in the same manner as first submittals
1) Corrections other than requested by the City
2) Marked with revision triangle or other similar method
a) At Contractor’s risk if not marked
b. Submittals for each item will be reviewed no more than twice at the City’s
expense.
1) All subsequent reviews will be performed at times convenient to the City
and at the Contractor's expense, based on the City's or City
Representative’s then prevailing rates.
2) Provide Contractor reimbursement to the City within 30 Calendar Days for
all such fees invoiced by the City.
c. The need for more than 1 resubmission or any other delay in obtaining City's
review of submittals, will not entitle the Contractor to an extension of Contract
Time.
7. Partial Submittals
a. City reserves the right to not review submittals deemed partial, at the City’s
discretion.
b. Submittals deemed by the City to be not complete will be returned to the
Contractor, and will be considered "Not Approved" until resubmitted.
c. The City may at its option provide a list or mark the submittal directing the
Contractor to the areas that are incomplete.
8. If the Contractor considers any correction indicated on the shop drawings to
constitute a change to the Contract Documents, then written notice must be
provided thereof to the Developer at least 7 Calendar Days prior to release for
manufacture.
01 33 00 - 7
DAP SUBMITTALS
Page 7 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
9. When the shop drawings have been completed to the satisfaction of the City, the
Contractor may carry out the construction in accordance therewith and no further
changes therein except upon written instructions from the City.
10. Each submittal, appropriately coded, will be returned within 30 Calendar Days
following receipt of submittal by the City.
L. Mock ups
1. Mock Up units as specified in individual Sections, include, but are not necessarily
limited to, complete units of the standard of acceptance for that type of Work to be
used on the Project. Remove at the completion of the Work or when directed.
M. Qualifications
1. If specifically required in other Sections of these Specifications, submit a P.E.
Certification for each item required.
N. Request for Information (RFI)
1. Contractor Request for additional information
a. Clarification or interpretation of the contract documents
b. When the Contractor believes there is a conflict between Contract Documents
c. When the Contractor believes there is a conflict between the Drawings and
Specifications
1) Identify the conflict and request clarification
2. Sufficient information shall be attached to permit a written response without further
information.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
01 33 00 - 8
DAP SUBMITTALS
Page 8 of 8
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days
01 35 13 - 1
DAP SPECIAL PROJECT PROCEDURES
Page 1 of 7
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August, 30, 2013
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedures for special project circumstances that includes, but is not limited to:
a. Coordination with the Texas Department of Transportation
b. Work near High Voltage Lines
c. Confined Space Entry Program
d. Air Pollution Watch Days
e. Use of Explosives, Drop Weight, Etc.
f. Water Department Notification
g. Public Notification Prior to Beginning Construction
h. Coordination with United States Army Corps of Engineers
i. Coordination within Railroad permits areas
j. Dust Control
k. Employee Parking
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 33 12 25 – Connection to Existing Water Mains
1.2 REFERENCES
A. Reference Standards
1. Reference standards cited in this Specification refer to the current reference
standard published at the time of the latest revision date logged at the end of this
Specification, unless a date is specifically cited.
2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752.
High Voltage Overhead Lines.
3. North Central Texas Council of Governments (NCTCOG) – Clean Construction
Specification
1.3 ADMINISTRATIVE REQUIREMENTS
A. Coordination with the Texas Department of Transportation
1. When work in the right-of-way which is under the jurisdiction of the Texas
Department of Transportation (TxDOT):
a. Notify the Texas Department of Transportation prior to commencing any work
therein in accordance with the provisions of the permit
01 35 13 - 2
DAP SPECIAL PROJECT PROCEDURES
Page 2 of 7
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August, 30, 2013
b. All work performed in the TxDOT right-of-way shall be performed in
compliance with and subject to approval from the Texas Department of
Transportation
B. Work near High Voltage Lines
1. Regulatory Requirements
a. All Work near High Voltage Lines (more than 600 volts measured between
conductors or between a conductor and the ground) shall be in accordance with
Health and Safety Code, Title 9, Subtitle A, Chapter 752.
2. Warning sign
a. Provide sign of sufficient size meeting all OSHA requirements.
3. Equipment operating within 10 feet of high voltage lines will require the following
safety features
a. Insulating cage-type of guard about the boom or arm
b. Insulator links on the lift hook connections for back hoes or dippers
c. Equipment must meet the safety requirements as set forth by OSHA and the
safety requirements of the owner of the high voltage lines
4. Work within 6 feet of high voltage electric lines
a. Notification shall be given to:
1) The power company (example: ONCOR)
a) Maintain an accurate log of all such calls to power company and record
action taken in each case.
b. Coordination with power company
1) After notification coordinate with the power company to:
a) Erect temporary mechanical barriers, de-energize the lines, or raise or
lower the lines
c. No personnel may work within 6 feet of a high voltage line before the above
requirements have been met.
C. Confined Space Entry Program
1. Provide and follow approved Confined Space Entry Program in accordance with
OSHA requirements.
2. Confined Spaces include:
a. Manholes
b. All other confined spaces in accordance with OSHA’s Permit Required for
Confined Spaces
D. Use of Explosives, Drop Weight, Etc.
1. When Contract Documents permit on the project the following will apply:
a. Public Notification
1) Submit notice to City and proof of adequate insurance coverage, 24 hours
prior to commencing.
2) Minimum 24 hour public notification in accordance with Section 01 31 13
E. Water Department Coordination
1. During the construction of this project, it will be necessary to deactivate, for a
period of time, existing lines. The Contractor shall be required to coordinate with
the Water Department to determine the best times for deactivating and activating
those lines.
01 35 13 - 3
DAP SPECIAL PROJECT PROCEDURES
Page 3 of 7
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August, 30, 2013
2. Coordinate any event that will require connecting to or the operation of an existing
City water line system with the City’s representative.
a. Coordination shall be in accordance with Section 33 12 25.
b. If needed, obtain a hydrant water meter from the Water Department for use
during the life of named project.
c. In the event that a water valve on an existing live system be turned off and on
to accommodate the construction of the project is required, coordinate this
activity through the appropriate City representative.
1) Do not operate water line valves of existing water system.
a) Failure to comply will render the Contractor in violation of Texas Penal
Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor
will be prosecuted to the full extent of the law.
b) In addition, the Contractor will assume all liabilities and
responsibilities as a result of these actions.
F. Public Notification Prior to Beginning Construction
1. Prior to beginning construction on any block in the project, on a block by block
basis, prepare and deliver a notice or flyer of the pending construction to the front
door of each residence or business that will be impacted by construction. The notice
shall be prepared as follows:
a. Post notice or flyer 7 days prior to beginning any construction activity on each
block in the project area.
1) Prepare flyer on the Contractor’s letterhead and include the following
information:
a) Name of Project
b) City Project No (CPN)
c) Scope of Project (i.e. type of construction activity)
d) Actual construction duration within the block
e) Name of the contractor’s foreman and phone number
f) Name of the City’s inspector and phone number
g) City’s after-hours phone number
2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit
A.
3) Submit schedule showing the construction start and finish time for each
block of the project to the inspector.
4) Deliver flyer to the City Inspector for review prior to distribution.
b. No construction will be allowed to begin on any block until the flyer is
delivered to all residents of the block.
G. Public Notification of Temporary Water Service Interruption during Construction
1. In the event it becomes necessary to temporarily shut down water service to
residents or businesses during construction, prepare and deliver a notice or flyer of
the pending interruption to the front door of each affected resident.
2. Prepared notice as follows:
a. The notification or flyer shall be posted 24 hours prior to the temporary
interruption.
b. Prepare flyer on the contractor’s letterhead and include the following
information:
1) Name of the project
2) City Project Number
01 35 13 - 4
DAP SPECIAL PROJECT PROCEDURES
Page 4 of 7
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August, 30, 2013
3) Date of the interruption of service
4) Period the interruption will take place
5) Name of the contractor’s foreman and phone number
6) Name of the City’s inspector and phone number
c. A sample of the temporary water service interruption notification is attached as
Exhibit B.
d. Deliver a copy of the temporary interruption notification to the City inspector
for review prior to being distributed.
e. No interruption of water service can occur until the flyer has been delivered to
all affected residents and businesses.
f. Electronic versions of the sample flyers can be obtained from the Project
Construction Inspector.
H. Coordination with United States Army Corps of Engineers (USACE)
1. At locations in the Project where construction activities occur in areas where
USACE permits are required, meet all requirements set forth in each designated
permit.
I. Coordination within Railroad Permit Areas
1. At locations in the project where construction activities occur in areas where
railroad permits are required, meet all requirements set forth in each designated
railroad permit. This includes, but is not limited to, provisions for:
a. Flagmen
b. Inspectors
c. Safety training
d. Additional insurance
e. Insurance certificates
f. Other employees required to protect the right-of-way and property of the
Railroad Company from damage arising out of and/or from the construction of
the project. Proper utility clearance procedures shall be used in accordance
with the permit guidelines.
2. Obtain any supplemental information needed to comply with the railroad’s
requirements.
J. Dust Control
1. Use acceptable measures to control dust at the Site.
a. If water is used to control dust, capture and properly dispose of waste water.
b. If wet saw cutting is performed, capture and properly dispose of slurry.
K. Employee Parking
1. Provide parking for employees at locations approved by the City.
01 35 13 - 5
DAP SPECIAL PROJECT PROCEDURES
Page 5 of 7
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August, 30, 2013
1.4 SUBMITTALS [NOT USED]
1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.6 CLOSEOUT SUBMITTALS [NOT USED]
1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.8 QUALITY ASSURANCE [NOT USED]
1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.10 FIELD [SITE] CONDITIONS [NOT USED]
1.11 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson
1.3.B – Added requirement of compliance with Health and Safety Code, Title 9.
Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines.
01 35 13 - 6
DAP SPECIAL PROJECT PROCEDURES
Page 6 of 7
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August, 30, 2013
EXHIBIT A
(To be printed on Contractor’s Letterhead)
Date:
CPN No.:
Project Name:
Mapsco Location:
Limits of Construction:
THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT
WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR
PROPERTY.
CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE
OF THIS NOTICE.
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER
ISSUE, PLEASE CALL:
Mr. <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.>
OR
Mr. <CITY INSPECTOR> AT < TELEPHONE NO.>
AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL
01 35 13 - 7
DAP SPECIAL PROJECT PROCEDURES
Page 7 of 7
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August, 30, 2013
EXHIBIT B
01 45 23 - 1
DAP TESTING AND INSPECTION SERVICES
Page 1 of 2
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
SECTION 01 45 23
TESTING AND INSPECTION SERVICES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Testing and inspection services procedures and coordination
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
a. Contractor is responsible for performing, coordinating, and payment of all
Quality Control testing.
b. City is responsible for performing and payment for first set of Quality
Assurance testing.
1) If the first Quality Assurance test performed by the City fails, the
Contractor is responsible for payment of subsequent Quality Assurance
testing until a passing test occurs.
a) Final acceptance will not be issued by City until all required payments
for testing by Contractor have been paid in full.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Testing
1. Complete testing in accordance with the Contract Documents.
2. Coordination
a. When testing is required to be performed by the City, notify City, sufficiently
in advance, when testing is needed.
b. When testing is required to be completed by the Contractor, notify City,
sufficiently in advance, that testing will be performed.
3. Distribution of Testing Reports
a. Electronic Distribution
1) Confirm development of Project directory for electronic submittals to be
uploaded to City’s Buzzsaw site, or another form of distribution approved
by the City.
01 45 23 - 2
DAP TESTING AND INSPECTION SERVICES
Page 2 of 2
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised August 30, 2013
2) Upload test reports to designated project directory and notify appropriate
City representatives via email of submittal posting.
3) Hard Copies
a) 1 copy for all submittals submitted to the Project Representative
b. Hard Copy Distribution (if required in lieu of electronic distribution)
1) Tests performed by City
a) Distribute 1 hard copy to the Contractor
2) Tests performed by the Contractor
a) Distribute 3 hard copies to City’s Project Representative
4. Provide City’s Project Representative with trip tickets for each delivered load of
Concrete or Lime material including the following information:
a. Name of pit
b. Date of delivery
c. Material delivered
B. Inspection
1. Inspection or lack of inspection does not relieve the Contractor from obligation to
perform work in accordance with the Contract Documents.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 50 00 - 1
DAP TEMPORARY FACILITIES AND CONTROLS
Page 1 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised JULY 1, 2011
SECTION 01 50 00
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Provide temporary facilities and controls needed for the Work including, but not
necessarily limited to:
a. Temporary utilities
b. Sanitary facilities
c. Storage Sheds and Buildings
d. Dust control
e. Temporary fencing of the construction site
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Temporary Utilities
1. Obtaining Temporary Service
a. Make arrangements with utility service companies for temporary services.
b. Abide by rules and regulations of utility service companies or authorities
having jurisdiction.
c. Be responsible for utility service costs until Work is approved for Final
Acceptance.
1) Included are fuel, power, light, heat and other utility services necessary for
execution, completion, testing and initial operation of Work.
2. Water
a. Contractor to provide water required for and in connection with Work to be
performed and for specified tests of piping, equipment, devices or other use as
required for the completion of the Work.
b. Provide and maintain adequate supply of potable water for domestic
consumption by Contractor personnel and City’s Project Representatives.
c. Coordination
1) Contact City 1 week before water for construction is desired
01 50 00 - 2
DAP TEMPORARY FACILITIES AND CONTROLS
Page 2 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised JULY 1, 2011
d. Contractor Payment for Construction Water
1) Obtain construction water meter from City for payment as billed by City’s
established rates.
3. Electricity and Lighting
a. Provide and pay for electric powered service as required for Work, including
testing of Work.
1) Provide power for lighting, operation of equipment, or other use.
b. Electric power service includes temporary power service or generator to
maintain operations during scheduled shutdown.
4. Telephone
a. Provide emergency telephone service at Site for use by Contractor personnel
and others performing work or furnishing services at Site.
5. Temporary Heat and Ventilation
a. Provide temporary heat as necessary for protection or completion of Work.
b. Provide temporary heat and ventilation to assure safe working conditions.
B. Sanitary Facilities
1. Provide and maintain sanitary facilities for persons on Site.
a. Comply with regulations of State and local departments of health.
2. Enforce use of sanitary facilities by construction personnel at job site.
a. Enclose and anchor sanitary facilities.
b. No discharge will be allowed from these facilities.
c. Collect and store sewage and waste so as not to cause nuisance or health
problem.
d. Haul sewage and waste off-site at no less than weekly intervals and properly
dispose in accordance with applicable regulation.
3. Locate facilities near Work Site and keep clean and maintained throughout Project.
4. Remove facilities at completion of Project
C. Storage Sheds and Buildings
1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor
above ground level for materials and equipment susceptible to weather damage.
2. Storage of materials not susceptible to weather damage may be on blocks off
ground.
3. Store materials in a neat and orderly manner.
a. Place materials and equipment to permit easy access for identification,
inspection and inventory.
4. Equip building with lockable doors and lighting, and provide electrical service for
equipment space heaters and heating or ventilation as necessary to provide storage
environments acceptable to specified manufacturers.
5. Fill and grade site for temporary structures to provide drainage away from
temporary and existing buildings.
6. Remove building from site prior to Final Acceptance.
D. Temporary Fencing
1. Provide and maintain for the duration or construction when required in contract
documents
E. Dust Control
01 50 00 - 3
DAP TEMPORARY FACILITIES AND CONTROLS
Page 3 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised JULY 1, 2011
1. Contractor is responsible for maintaining dust control through the duration of the
project.
a. Contractor remains on-call at all times
b. Must respond in a timely manner
F. Temporary Protection of Construction
1. Contractor or subcontractors are responsible for protecting Work from damage due
to weather.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 INSTALLATION
A. Temporary Facilities
1. Maintain all temporary facilities for duration of construction activities as needed.
3.5 [REPAIR] / [RESTORATION]
3.6 RE-INSTALLATION
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES
A. Temporary Facilities
01 50 00 - 4
DAP TEMPORARY FACILITIES AND CONTROLS
Page 4 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised JULY 1, 2011
1. Remove all temporary facilities and restore area after completion of the Work, to a
condition equal to or better than prior to start of Work.
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 55 26 - 1
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 1 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised July 1, 2011
SECTION 01 55 26
STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Administrative procedures for:
a. Street Use Permit
b. Modification of approved traffic control
c. Removal of Street Signs
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 34 71 13 – Traffic Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES
A. Reference Standards
1. Reference standards cited in this specification refer to the current reference standard
published at the time of the latest revision date logged at the end of this
specification, unless a date is specifically cited.
2. Texas Manual on Uniform Traffic Control Devices (TMUTCD).
1.4 ADMINISTRATIVE REQUIREMENTS
A. Traffic Control
1. General
a. When traffic control plans are included in the Drawings, provide Traffic
Control in accordance with Drawings and Section 34 71 13.
b. When traffic control plans are not included in the Drawings, prepare traffic
control plans in accordance with Section 34 71 13 and submit to City for
review.
1) Allow minimum 10 working days for review of proposed Traffic Control.
B. Street Use Permit
1. Prior to installation of Traffic Control, a City Street Use Permit is required.
a. To obtain Street Use Permit, submit Traffic Control Plans to City
Transportation and Public Works Department.
01 55 26 - 2
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 2 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised July 1, 2011
1) Allow a minimum of 5 working days for permit review.
2) Contractor’s responsibility to coordinate review of Traffic Control plans for
Street Use Permit, such that construction is not delayed.
C. Modification to Approved Traffic Control
1. Prior to installation traffic control:
a. Submit revised traffic control plans to City Department Transportation and
Public Works Department.
1) Revise Traffic Control plans in accordance with Section 34 71 13.
2) Allow minimum 5 working days for review of revised Traffic Control.
3) It is the Contractor’s responsibility to coordinate review of Traffic Control
plans for Street Use Permit, such that construction is not delayed.
D. Removal of Street Sign
1. If it is determined that a street sign must be removed for construction, then contact
City Transportation and Public Works Department, Signs and Markings Division to
remove the sign.
E. Temporary Signage
1. In the case of regulatory signs, replace permanent sign with temporary sign meeting
requirements of the latest edition of the Texas Manual on Uniform Traffic Control
Devices (MUTCD).
2. Install temporary sign before the removal of permanent sign.
3. When construction is complete, to the extent that the permanent sign can be
reinstalled, contact the City Transportation and Public Works Department, Signs
and Markings Division, to reinstall the permanent sign.
F. Traffic Control Standards
1. Traffic Control Standards can be found on the City’s Buzzsaw website.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
01 55 26 - 3
DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL
Page 3 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised July 1, 2011
Revision Log
DATE NAME SUMMARY OF CHANGE
01 57 13 - 1
DAP STORM WATER POLLUTION PREVENTION
Page 1 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised July 1, 2011
SECTION 01 57 13
STORM WATER POLLUTION PREVENTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Procedures for Storm Water Pollution Prevention Plans
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the
Contract
2. Division 1 – General Requirements
3. Section 31 25 00 – Erosion and Sediment Control
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Construction Activities resulting in less than 1 acre of disturbance
a. Work associated with this Item is considered subsidiary to the various Items
bid. No separate payment will be allowed for this Item.
2. Construction Activities resulting in greater than 1 acre of disturbance
a. Measurement and Payment shall be in accordance with Section 31 25 00.
1.3 REFERENCES
A. Abbreviations and Acronyms
1. Notice of Intent: NOI
2. Notice of Termination: NOT
3. Storm Water Pollution Prevention Plan: SWPPP
4. Texas Commission on Environmental Quality: TCEQ
5. Notice of Change: NOC
A. Reference Standards
1. Reference standards cited in this Specification refer to the current reference
standard published at the time of the latest revision date logged at the end of this
Specification, unless a date is specifically cited.
2. Integrated Storm Management (iSWM) Technical Manual for Construction
Controls
1.4 ADMINISTRATIVE REQUIREMENTS
A. General
1. Contractor is responsible for resolution and payment of any fines issued associated
with compliance to Stormwater Pollution Prevention Plan.
01 57 13 - 2
DAP STORM WATER POLLUTION PREVENTION
Page 2 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised July 1, 2011
B. Construction Activities resulting in:
1. Less than 1 acre of disturbance
a. Provide erosion and sediment control in accordance with Section 31 25 00 and
Drawings.
2. 1 to less than 5 acres of disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) TCEQ Small Construction Site Notice Required under general permit
TXR150000
a) Sign and post at job site
b) Prior to Preconstruction Meeting, send 1 copy to City Department of
Transportation and Public Works, Environmental Division, (817) 392-
6088.
2) Provide erosion and sediment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
3. 5 acres or more of Disturbance
a. Texas Pollutant Discharge Elimination System (TPDES) General Construction
Permit is required
b. Complete SWPPP in accordance with TCEQ requirements
1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee
a) Sign and post at job site
b) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
2) TCEQ Notice of Change required if making changes or updates to NOI
3) Provide erosion and sediment control in accordance with:
a) Section 31 25 00
b) The Drawings
c) TXR150000 General Permit
d) SWPPP
e) TCEQ requirements
4) Once the project has been completed and all the closeout requirements of
TCEQ have been met a TCEQ Notice of Termination can be submitted.
a) Send copy to City Department of Transportation and Public Works,
Environmental Division, (817) 392-6088.
1.5 SUBMITTALS
A. SWPPP
1. Submit in accordance with Section 01 33 00, except as stated herein.
a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City
as follows:
1) 1 copy to the City Project Manager
a) City Project Manager will forward to the City Department of
Transportation and Public Works, Environmental Division for review
01 57 13 - 3
DAP STORM WATER POLLUTION PREVENTION
Page 3 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised July 1, 2011
B. Modified SWPPP
1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City
in accordance with Section 01 33 00.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
01 60 00 - 1
DAP PRODUCT REQUIREMENTS
Page 1 of 2
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
SECTION 01 60 00
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. References for Product Requirements and City Standard Products List
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES [NOT USED]
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. A list of City approved products for use is located on Buzzsaw as follows:
1. Resources\02 - Construction Documents\Standard Products List
B. Only products specifically included on City’s Standard Product List in these Contract
Documents shall be allowed for use on the Project.
1. Any subsequently approved products will only be allowed for use upon specific
approval by the City.
C. Any specific product requirements in the Contract Documents supersede similar
products included on the City’s Standard Product List.
1. The City reserves the right to not allow products to be used for certain projects even
though the product is listed on the City’s Standard Product List.
D. Although a specific product is included on City’s Standard Product List, not all
products from that manufacturer are approved for use, including but not limited to, that
manufacturer’s standard product.
E. See Section 01 33 00 for submittal requirements of Product Data included on City’s
Standard Product List.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
01 60 00 - 2
DAP PRODUCT REQUIREMENTS
Page 2 of 2
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
10/12/12 D. Johnson Modified Location of City’s Standard Product List
4/7/2014 M.Domenech Revised for DAP application
01 66 00 - 1
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 1 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
SECTION 01 66 00
PRODUCT STORAGE AND HANDLING REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Scheduling of product delivery
2. Packaging of products for delivery
3. Protection of products against damage from:
a. Handling
b. Exposure to elements or harsh environments
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY AND HANDLING
A. Delivery Requirements
1. Schedule delivery of products or equipment as required to allow timely installation
and to avoid prolonged storage.
2. Provide appropriate personnel and equipment to receive deliveries.
3. Delivery trucks will not be permitted to wait extended periods of time on the Site
for personnel or equipment to receive the delivery.
01 66 00 - 2
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 2 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
4. Deliver products or equipment in manufacturer's original unbroken cartons or other
containers designed and constructed to protect the contents from physical or
environmental damage.
5. Clearly and fully mark and identify as to manufacturer, item and installation
location.
6. Provide manufacturer's instructions for storage and handling.
B. Handling Requirements
1. Handle products or equipment in accordance with these Contract Documents and
manufacturer’s recommendations and instructions.
C. Storage Requirements
1. Store materials in accordance with manufacturer’s recommendations and
requirements of these Specifications.
2. Make necessary provisions for safe storage of materials and equipment.
a. Place loose soil materials and materials to be incorporated into Work to prevent
damage to any part of Work or existing facilities and to maintain free access at
all times to all parts of Work and to utility service company installations in
vicinity of Work.
3. Keep materials and equipment neatly and compactly stored in locations that will
cause minimum inconvenience to other contractors, public travel, adjoining owners,
tenants and occupants.
a. Arrange storage to provide easy access for inspection.
4. Restrict storage to areas available on construction site for storage of material and
equipment as shown on Drawings, or approved by City’s Project Representative.
5. Provide off-site storage and protection when on-site storage is not adequate.
a. Provide addresses of and access to off-site storage locations for inspection by
City’s Project Representative.
6. Do not use lawns, grass plots or other private property for storage purposes without
written permission of owner or other person in possession or control of premises.
7. Store in manufacturers’ unopened containers.
8. Neatly, safely and compactly stack materials delivered and stored along line of
Work to avoid inconvenience and damage to property owners and general public
and maintain at least 3 feet from fire hydrant.
9. Keep public and private driveways and street crossings open.
10. Repair or replace damaged lawns, sidewalks, streets or other improvements to
satisfaction of City’s Project Representative.
a. Total length which materials may be distributed along route of construction at
one time is 1,000 linear feet, unless otherwise approved in writing by City’s
Project Representative.
01 66 00 - 3
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 3 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 ERECTION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL
A. Tests and Inspections
1. Inspect all products or equipment delivered to the site prior to unloading.
B. Non-Conforming Work
1. Reject all products or equipment that are damaged, used or in any other way
unsatisfactory for use on the project.
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION
A. Protect all products or equipment in accordance with manufacturer's written directions.
B. Store products or equipment in location to avoid physical damage to items while in
storage.
C. Protect equipment from exposure to elements and keep thoroughly dry if required by
the manufacturer.
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
01 66 00 - 4
DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS
Page 4 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 70 00 - 1
DAP MOBILIZATION AND REMOBILIZATION
Page 1 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
SECTION 01 70 00
MOBILIZATION AND REMOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Mobilization and Demobilization
a. Mobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
to the Site
2) Establishment of necessary general facilities for the Contractor’s operation
at the Site
3) Premiums paid for performance and payment bonds
4) Transportation of Contractor’s personnel, equipment, and operating supplies
to another location within the designated Site
5) Relocation of necessary general facilities for the Contractor’s operation
from 1 location to another location on the Site.
b. Demobilization
1) Transportation of Contractor’s personnel, equipment, and operating supplies
away from the Site including disassembly
2) Site Clean-up
3) Removal of all buildings and/or other facilities assembled at the Site for this
Contract
c. Mobilization and Demobilization do not include activities for specific items of
work that are for which payment is provided elsewhere in the contract.
2. Remobilization
a. Remobilization for Suspension of Work specifically required in the Contract
Documents or as required by City includes:
1) Demobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly or temporarily securing
equipment, supplies, and other facilities as designated by the Contract
Documents necessary to suspend the Work.
b) Site Clean-up as designated in the Contract Documents
2) Remobilization
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site necessary to resume the Work.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site necessary to resume the Work.
3) No Payments will be made for:
a) Mobilization and Demobilization from one location to another on the
Site in the normal progress of performing the Work.
b) Stand-by or idle time
c) Lost profits
3. Mobilizations and Demobilization for Miscellaneous Projects
a. Mobilization and Demobilization
01 70 00 - 2
DAP MOBILIZATION AND REMOBILIZATION
Page 2 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1) Mobilization shall consist of the activities and cost on a Work Order basis
necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies to the Site for the issued Work Order.
b) Establishment of necessary general facilities for the Contractor’s
operation at the Site for the issued Work Order
2) Demobilization shall consist of the activities and cost necessary for:
a) Transportation of Contractor’s personnel, equipment, and operating
supplies from the Site including disassembly for each issued Work
Order
b) Site Clean-up for each issued Work Order
c) Removal of all buildings or other facilities assembled at the Site for
each Work Oder
b. Mobilization and Demobilization do not include activities for specific items of
work for which payment is provided elsewhere in the contract.
4. Emergency Mobilizations and Demobilization for Miscellaneous Projects
a. A Mobilization for Miscellaneous Projects when directed by the City and the
mobilization occurs within 24 hours of the issuance of the Work Order.
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Mobilization and Demobilization
a. Measure
1) This Item is considered subsidiary to the various Items bid.
b. Payment
1) The work performed and materials furnished in accordance with this Item
are subsidiary to the various Items bid and no other compensation will be
allowed.
2. Remobilization for suspension of Work as specifically required in the Contract
Documents
a. Measurement
1) Measurement for this Item shall be per each remobilization performed.
b. Payment
1) The work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Specified Remobilization” in accordance with Contract
Documents.
c. The price shall include:
1) Demobilization as described in Section 1.1.A.2.a.1)
2) Remobilization as described in Section 1.1.A.2.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
01 70 00 - 3
DAP MOBILIZATION AND REMOBILIZATION
Page 3 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
3. Remobilization for suspension of Work as required by City
a. Measurement and Payment
1) This shall be submitted as a Contract Claim in accordance with Article 10
of Section 00 72 00.
2) No payments will be made for standby, idle time, or lost profits associated
with this Item.
4. Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Mobilization” in accordance with Contract
Documents. Demobilization shall be considered subsidiary to mobilization
and shall not be paid for separately.
c. The price shall include:
1) Mobilization as described in Section 1.1.A.3.a.1)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects
a. Measurement
1) Measurement for this Item shall be for each Mobilization and
Demobilization required by the Contract Documents
b. Payment
1) The Work performed and materials furnished in accordance with this Item
and measured as provided under “Measurement” will be paid for at the unit
price per each “Work Order Emergency Mobilization” in accordance with
Contract Documents. Demobilization shall be considered subsidiary to
mobilization and shall not be paid for separately.
c. The price shall include
1) Mobilization as described in Section 1.1.A.4.a)
2) Demobilization as described in Section 1.1.A.3.a.2)
d. No payments will be made for standby, idle time, or lost profits associated this
Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS [NOT USED]
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
01 70 00 - 4
DAP MOBILIZATION AND REMOBILIZATION
Page 4 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 74 23 - 1
DAP CLEANING
Page 1 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
SECTION 01 74 23
CLEANING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Intermediate and final cleaning for Work not including special cleaning of closed
systems specified elsewhere
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Scheduling
1. Schedule cleaning operations so that dust and other contaminants disturbed by
cleaning process will not fall on newly painted surfaces.
2. Schedule final cleaning upon completion of Work and immediately prior to final
inspection.
1.5 SUBMITTALS [NOT USED]
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE [NOT USED]
1.10 STORAGE, AND HANDLING
A. Storage and Handling Requirements
1. Store cleaning products and cleaning wastes in containers specifically designed for
those materials.
01 74 23 - 2
DAP CLEANING
Page 2 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED]
2.2 MATERIALS
A. Cleaning Agents
1. Compatible with surface being cleaned
2. New and uncontaminated
3. For manufactured surfaces
a. Material recommended by manufacturer
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 APPLICATION [NOT USED]
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING
A. General
1. Prevent accumulation of wastes that create hazardous conditions.
2. Conduct cleaning and disposal operations to comply with laws and safety orders of
governing authorities.
3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in
storm or sanitary drains or sewers.
4. Dispose of degradable debris at an approved solid waste disposal site.
5. Dispose of nondegradable debris at an approved solid waste disposal site or in an
alternate manner approved by City and regulatory agencies.
01 74 23 - 3
DAP CLEANING
Page 3 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
6. Handle materials in a controlled manner with as few handlings as possible.
7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with
this project.
8. Remove all signs of temporary construction and activities incidental to construction
of required permanent Work.
9. If project is not cleaned to the satisfaction of the City, the City reserves the right to
have the cleaning completed at the expense of the Contractor.
10. Do not burn on-site.
B. Intermediate Cleaning during Construction
1. Keep Work areas clean so as not to hinder health, safety or convenience of
personnel in existing facility operations.
2. At maximum weekly intervals, dispose of waste materials, debris and rubbish.
3. Confine construction debris daily in strategically located container(s):
a. Cover to prevent blowing by wind
b. Store debris away from construction or operational activities
c. Haul from site at a minimum of once per week
4. Vacuum clean interior areas when ready to receive finish painting.
a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance.
5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which
may become airborne or transported by flowing water during the storm.
C. Exterior (Site or Right of Way) Final Cleaning
1. Remove trash and debris containers from site.
a. Re-seed areas disturbed by location of trash and debris containers in accordance
with Section 32 92 13.
2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object
that may hinder or disrupt the flow of traffic along the roadway.
3. Clean any interior areas including, but not limited to, vaults, manholes, structures,
junction boxes and inlets.
4. If no longer required for maintenance of erosion facilities, and upon approval by
City, remove erosion control from site.
5. Clean signs, lights, signals, etc.
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
01 74 23 - 4
DAP CLEANING
Page 4 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 77 19 - 1
DAP CLOSEOUT REQUIREMENTS
Page 1 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
SECTION 01 77 19
CLOSEOUT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. The procedure for closing out a contract
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Guarantees, Bonds and Affidavits
1. No application for final payment will be accepted until all guarantees, bonds,
certificates, licenses and affidavits required for Work or equipment as specified are
satisfactorily filed with the City.
B. Release of Liens or Claims
1. No application for final payment will be accepted until satisfactory evidence of
release of liens has been submitted to the City.
1.5 SUBMITTALS
A. Submit all required documentation to City’s Project Representative.
01 77 19 - 2
DAP CLOSEOUT REQUIREMENTS
Page 2 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1.6 INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 CLOSEOUT PROCEDURE
A. Prior to requesting Final Inspection, submit:
1. Project Record Documents in accordance with Section 01 78 39
2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23
B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section
01 74 23.
C. Final Inspection
1. After final cleaning, provide notice to the City Project Representative that the Work
is completed.
a. The City will make an initial Final Inspection with the Contractor present.
b. Upon completion of this inspection, the City will notify the Contractor, in
writing within 10 business days, of any particulars in which this inspection
reveals that the Work is defective or incomplete.
2. Upon receiving written notice from the City, immediately undertake the Work
required to remedy deficiencies and complete the Work to the satisfaction of the
City.
3. Upon completion of Work associated with the items listed in the City's written
notice, inform the City, that the required Work has been completed. Upon receipt
of this notice, the City, in the presence of the Contractor, will make a subsequent
Final Inspection of the project.
4. Provide all special accessories required to place each item of equipment in full
operation. These special accessory items include, but are not limited to:
a. Specified spare parts
b. Adequate oil and grease as required for the first lubrication of the equipment
c. Initial fill up of all chemical tanks and fuel tanks
d. Light bulbs
e. Fuses
f. Vault keys
g. Handwheels
h. Other expendable items as required for initial start-up and operation of all
equipment
D. Notice of Project Completion
01 77 19 - 3
DAP CLOSEOUT REQUIREMENTS
Page 3 of 3
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1. Once the City Project Representative finds the Work subsequent to Final Inspection
to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet).
E. Supporting Documentation
1. Coordinate with the City Project Representative to complete the following
additional forms:
a. Final Payment Request
b. Statement of Contract Time
c. Affidavit of Payment and Release of Liens
d. Consent of Surety to Final Payment
e. Pipe Report (if required)
f. Contractor’s Evaluation of City
g. Performance Evaluation of Contractor
F. Letter of Final Acceptance
1. Upon review and acceptance of Notice of Project Completion and Supporting
Documentation, in accordance with General Conditions, City will issue Letter of
Final Acceptance and release the Final Payment Request for payment.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP application
01 78 23 - 1
DAP OPERATION AND MAINTENANCE DATA
Page 1 of 5
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
SECTION 01 78 23
OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Product data and related information appropriate for City's maintenance and
operation of products furnished under Contract
2. Such products may include, but are not limited to:
a. Traffic Controllers
b. Irrigation Controllers (to be operated by the City)
c. Butterfly Valves
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS
A. Schedule
1. Submit manuals in final form to the City within 30 calendar days of product
shipment to the project site.
1.5 SUBMITTALS
A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be
approved by the City prior to delivery.
1.6 INFORMATIONAL SUBMITTALS
A. Submittal Form
1. Prepare data in form of an instructional manual for use by City personnel.
2. Format
a. Size: 8 ½ inches x 11 inches
b. Paper
1) 40 pound minimum, white, for typed pages
2) Holes reinforced with plastic, cloth or metal
c. Text: Manufacturer’s printed data, or neatly typewritten
01 78 23 - 2
DAP OPERATION AND MAINTENANCE DATA
Page 2 of 5
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
d. Drawings
1) Provide reinforced punched binder tab, bind in with text
2) Reduce larger drawings and fold to size of text pages.
e. Provide fly-leaf for each separate product, or each piece of operating
equipment.
1) Provide typed description of product, and major component parts of
equipment.
2) Provide indexed tabs.
f. Cover
1) Identify each volume with typed or printed title "OPERATING AND
MAINTENANCE INSTRUCTIONS".
2) List:
a) Title of Project
b) Identity of separate structure as applicable
c) Identity of general subject matter covered in the manual
3. Binders
a. Commercial quality 3-ring binders with durable and cleanable plastic covers
b. When multiple binders are used, correlate the data into related consistent
groupings.
4. If available, provide an electronic form of the O&M Manual.
B. Manual Content
1. Neatly typewritten table of contents for each volume, arranged in systematic order
a. Contractor, name of responsible principal, address and telephone number
b. A list of each product required to be included, indexed to content of the volume
c. List, with each product:
1) The name, address and telephone number of the subcontractor or installer
2) A list of each product required to be included, indexed to content of the
volume
3) Identify area of responsibility of each
4) Local source of supply for parts and replacement
d. Identify each product by product name and other identifying symbols as set
forth in Contract Documents.
2. Product Data
a. Include only those sheets which are pertinent to the specific product.
b. Annotate each sheet to:
1) Clearly identify specific product or part installed
2) Clearly identify data applicable to installation
3) Delete references to inapplicable information
3. Drawings
a. Supplement product data with drawings as necessary to clearly illustrate:
1) Relations of component parts of equipment and systems
2) Control and flow diagrams
b. Coordinate drawings with information in Project Record Documents to assure
correct illustration of completed installation.
c. Do not use Project Record Drawings as maintenance drawings.
4. Written text, as required to supplement product data for the particular installation:
a. Organize in consistent format under separate headings for different procedures.
b. Provide logical sequence of instructions of each procedure.
01 78 23 - 3
DAP OPERATION AND MAINTENANCE DATA
Page 3 of 5
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
5. Copy of each warranty, bond and service contract issued
a. Provide information sheet for City personnel giving:
1) Proper procedures in event of failure
2) Instances which might affect validity of warranties or bonds
C. Manual for Materials and Finishes
1. Submit 5 copies of complete manual in final form.
2. Content, for architectural products, applied materials and finishes:
a. Manufacturer's data, giving full information on products
1) Catalog number, size, composition
2) Color and texture designations
3) Information required for reordering special manufactured products
b. Instructions for care and maintenance
1) Manufacturer's recommendation for types of cleaning agents and methods
2) Cautions against cleaning agents and methods which are detrimental to
product
3) Recommended schedule for cleaning and maintenance
3. Content, for moisture protection and weather exposure products:
a. Manufacturer's data, giving full information on products
1) Applicable standards
2) Chemical composition
3) Details of installation
b. Instructions for inspection, maintenance and repair
D. Manual for Equipment and Systems
1. Submit 5 copies of complete manual in final form.
2. Content, for each unit of equipment and system, as appropriate:
a. Description of unit and component parts
1) Function, normal operating characteristics and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Operating procedures
1) Start-up, break-in, routine and normal operating instructions
2) Regulation, control, stopping, shut-down and emergency instructions
3) Summer and winter operating instructions
4) Special operating instructions
c. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Alignment, adjusting and checking
d. Servicing and lubrication schedule
1) List of lubricants required
e. Manufacturer's printed operating and maintenance instructions
f. Description of sequence of operation by control manufacturer
1) Predicted life of parts subject to wear
2) Items recommended to be stocked as spare parts
g. As installed control diagrams by controls manufacturer
h. Each contractor's coordination drawings
1) As installed color coded piping diagrams
01 78 23 - 4
DAP OPERATION AND MAINTENANCE DATA
Page 4 of 5
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
i. Charts of valve tag numbers, with location and function of each valve
j. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
k. Other data as required under pertinent Sections of Specifications
3. Content, for each electric and electronic system, as appropriate:
a. Description of system and component parts
1) Function, normal operating characteristics, and limiting conditions
2) Performance curves, engineering data and tests
3) Complete nomenclature and commercial number of replaceable parts
b. Circuit directories of panelboards
1) Electrical service
2) Controls
3) Communications
c. As installed color coded wiring diagrams
d. Operating procedures
1) Routine and normal operating instructions
2) Sequences required
3) Special operating instructions
e. Maintenance procedures
1) Routine operations
2) Guide to "trouble shooting"
3) Disassembly, repair and reassembly
4) Adjustment and checking
f. Manufacturer's printed operating and maintenance instructions
g. List of original manufacturer's spare parts, manufacturer's current prices, and
recommended quantities to be maintained in storage
h. Other data as required under pertinent Sections of Specifications
4. Prepare and include additional data when the need for such data becomes apparent
during instruction of City's personnel.
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Provide operation and maintenance data by personnel with the following criteria:
1. Trained and experienced in maintenance and operation of described products
2. Skilled as technical writer to the extent required to communicate essential data
3. Skilled as draftsman competent to prepare required drawings
01 78 23 - 5
DAP OPERATION AND MAINTENANCE DATA
Page 5 of 5
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED]
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS [NOT USED]
PART 3 - EXECUTION [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
8/31/2012 D. Johnson 1.5.A.1 – title of section removed
4/7/2014 M.Domenech Revised for DAP Application
01 78 39 - 1
DAP PROJECT RECORD DOCUMENTS
Page 1 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
SECTION 01 78 39
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Work associated with the documenting the project and recording changes to project
documents, including:
a. Record Drawings
b. Water Meter Service Reports
c. Sanitary Sewer Service Reports
d. Large Water Meter Reports
B. Deviations from this City of Fort Worth Standard Specification
1. None.
C. Related Specification Sections include, but are not necessarily limited to:
1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract
2. Division 1 – General Requirements
1.2 PRICE AND PAYMENT PROCEDURES
A. Measurement and Payment
1. Work associated with this Item is considered subsidiary to the various Items bid.
No separate payment will be allowed for this Item.
1.3 REFERENCES [NOT USED]
1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED]
1.5 SUBMITTALS
A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to
City’s Project Representative.
1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED]
1.7 CLOSEOUT SUBMITTALS [NOT USED]
1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED]
1.9 QUALITY ASSURANCE
A. Accuracy of Records
1. Thoroughly coordinate changes within the Record Documents, making adequate
and proper entries on each page of Specifications and each sheet of Drawings and
other Documents where such entry is required to show the change properly.
2. Accuracy of records shall be such that future search for items shown in the Contract
Documents may rely reasonably on information obtained from the approved Project
Record Documents.
01 78 39 - 2
DAP PROJECT RECORD DOCUMENTS
Page 2 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
3. To facilitate accuracy of records, make entries within 24 hours after receipt of
information that the change has occurred.
4. Provide factual information regarding all aspects of the Work, both concealed and
visible, to enable future modification of the Work to proceed without lengthy and
expensive site measurement, investigation and examination.
1.10 STORAGE AND HANDLING
A. Storage and Handling Requirements
1. Maintain the job set of Record Documents completely protected from deterioration
and from loss and damage until completion of the Work and transfer of all recorded
data to the final Project Record Documents.
2. In the event of loss of recorded data, use means necessary to again secure the data
to the City's approval.
a. In such case, provide replacements to the standards originally required by the
Contract Documents.
1.11 FIELD [SITE] CONDITIONS [NOT USED]
1.12 WARRANTY [NOT USED]
PART 2 - PRODUCTS
2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED]
2.2 RECORD DOCUMENTS
A. Job set
1. Promptly following receipt of the Notice to Proceed, secure from the City, at no
charge to the Contractor, 1 complete set of all Documents comprising the Contract.
B. Final Record Documents
1. At a time nearing the completion of the Work and prior to Final Inspection, provide
the City 1 complete set of all Final Record Drawings in the Contract.
2.3 ACCESSORIES [NOT USED]
2.4 SOURCE QUALITY CONTROL [NOT USED]
PART 3 - EXECUTION
3.1 INSTALLERS [NOT USED]
3.2 EXAMINATION [NOT USED]
3.3 PREPARATION [NOT USED]
3.4 MAINTENANCE DOCUMENTS
A. Maintenance of Job Set
1. Immediately upon receipt of the job set, identify each of the Documents with the
title, "RECORD DOCUMENTS - JOB SET".
01 78 39 - 3
DAP PROJECT RECORD DOCUMENTS
Page 3 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
2. Preservation
a. Considering the Contract completion time, the probable number of occasions
upon which the job set must be taken out for new entries and for examination,
and the conditions under which these activities will be performed, devise a
suitable method for protecting the job set.
b. Do not use the job set for any purpose except entry of new data and for review
by the City, until start of transfer of data to final Project Record Documents.
c. Maintain the job set at the site of work.
3. Coordination with Construction Survey
a. At a minimum clearly mark any deviations from Contract Documents
associated with installation of the infrastructure.
4. Making entries on Drawings
a. Record any deviations from Contract Documents.
b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the
change by graphic line and note as required.
c. Date all entries.
d. Call attention to the entry by a "cloud" drawn around the area or areas affected.
e. In the event of overlapping changes, use different colors for the overlapping
changes.
5. Conversion of schematic layouts
a. In some cases on the Drawings, arrangements of conduits, circuits, piping,
ducts, and similar items, are shown schematically and are not intended to
portray precise physical layout.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) However, design of future modifications of the facility may require
accurate information as to the final physical layout of items which are
shown only schematically on the Drawings.
b. Show on the job set of Record Drawings, by dimension accurate to within 1
inch, the centerline of each run of items.
1) Final physical arrangement is determined by the Contractor, subject to the
City's approval.
2) Show, by symbol or note, the vertical location of the Item ("under slab", "in
ceiling plenum", "exposed", and the like).
3) Make all identification sufficiently descriptive that it may be related
reliably to the Specifications.
c. The City may waive the requirements for conversion of schematic layouts
where, in the City's judgment, conversion serves no useful purpose. However,
do not rely upon waivers being issued except as specifically issued in writing
by the City.
B. Final Project Record Documents
1. Transfer of data to Drawings
a. Carefully transfer change data shown on the job set of Record Drawings to the
corresponding final documents, coordinating the changes as required.
b. Clearly indicate at each affected detail and other Drawing a full description of
changes made during construction, and the actual location of items.
c. Call attention to each entry by drawing a "cloud" around the area or areas
affected.
01 78 39 - 4
DAP PROJECT RECORD DOCUMENTS
Page 4 of 4
CITY OF FORT WORTH Heritage Trace Parkway
STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS City Project #102139
Revised April 7, 2014
d. Make changes neatly, consistently and with the proper media to assure
longevity and clear reproduction.
2. Transfer of data to other Documents
a. If the Documents, other than Drawings, have been kept clean during progress of
the Work, and if entries thereon have been orderly to the approval of the City,
the job set of those Documents, other than Drawings, will be accepted as final
Record Documents.
b. If any such Document is not so approved by the City, secure a new copy of that
Document from the City at the City's usual charge for reproduction and
handling, and carefully transfer the change data to the new copy to the approval
of the City.
3.5 REPAIR / RESTORATION [NOT USED]
3.6 RE-INSTALLATION [NOT USED]
3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED]
3.8 SYSTEM STARTUP [NOT USED]
3.9 ADJUSTING [NOT USED]
3.10 CLEANING [NOT USED]
3.11 CLOSEOUT ACTIVITIES [NOT USED]
3.12 PROTECTION [NOT USED]
3.13 MAINTENANCE [NOT USED]
3.14 ATTACHMENTS [NOT USED]
END OF SECTION
Revision Log
DATE NAME SUMMARY OF CHANGE
4/7/2014 M.Domenech Revised for DAP Application
GEOTECHNICAL REPORT
GEOTECHNICAL EXPLORATION
HERITAGE TRACE BRIDGE
WATERSBEND SOUTH – PHASES 1B, 1C,
1D, 3, 5, AND 6
Off Wagley Robertson Road
Fort Worth, Texas
ALPHA Report No. W182958-1-Draft
April 11, 2019
Prepared for:
FORESTAR (USA) REAL ESTATE GROUP, INC. - DALLAS
14755 Preston Road, Suite 130
Dallas, Texas 75254
Attention: Mr. Matt Johnson
Prepared By:
Geotechnical
Construction Materials
Environmental
TBPE Firm No. 813
5058 Brush Creek Road
Fort Worth, Texas 76119
Tel: 817-496-5600
Fax: 817-496-5608
www.alphatesting.com
April 11, 2019
Forestar (USA) Real Estate Group, Inc. -
Dallas
14755 Preston Road, Suite 130
Dallas, Texas 75254
Attention: Mr. Matt Johnson
Re: Geotechnical Exploration
Heritage Trace Bridge Watersbend South – Phases 1B, 1C, 1D, 3, 5, and 6
Off Wagley Robertson Road
Fort Worth, Texas
ALPHA Report No. W182958-1-Draft
Attached is the report of the geotechnical exploration performed for the project referenced above.
This study was authorized on January 3, 2019 and performed in accordance with ALPHA Proposal
No. 68158-1-rev1 dated December 27, 2018.
This report contains results of field explorations and laboratory testing and an engineering
interpretation of these with respect to available project characteristics. The results and analyses
were used to develop recommendations to aid design and construction of bridge foundations.
Recommendations for the pavement associated with the bridge are provided in ALPHA Report
No. W182958-A, dated January 28, 2018.
ALPHA TESTING, INC. appreciates the opportunity to be of service on this project. If we can be
of further assistance, such as providing materials testing services during construction, please
contact our office.
Sincerely,
ALPHA TESTING, INC.
DRAFT DRAFT
Mark L. McKay, P.E. Brian J. Hoyt, P.E.
Director of Geotechnical Engineering Geotechnical Department Manager
MLM /BJH/aeg
Copies: (1-PDF) Client
1
TABLE OF CONTENTS
ALPHA REPORT NO. W182958-1-DRAFT
1.0 PURPOSE AND SCOPE .................................................................................................... 1
2.0 PROJECT CHARACTERISTICS ...................................................................................... 1
3.0 FIELD EXPLORATION .................................................................................................... 2
4.0 LABORATORY TESTS .................................................................................................... 2
5.0 GENERAL SUBSURFACE CONDITIONS ...................................................................... 2
6.0 DESIGN Recommendations ............................................................................................... 3
6.1 Drilled, Straight-Shaft Piers .................................................................................... 3
6.2 Pier Caps and Grade Beams .................................................................................... 5
6.3 Embankment Fill and Potential Movements ........................................................... 5
6.4 Seismic Considerations ........................................................................................... 6
6.5 Associated Pavement .............................................................................................. 6
6.6 Drainage and Other Considerations ........................................................................ 6
7.0 GENERAL CONSTRUCTION PROCEDURES AND GUIDELINES ............................. 7
7.1 Site Preparation and Grading .................................................................................. 7
7.2 Foundation Excavations .......................................................................................... 8
7.3 Fill Compaction ...................................................................................................... 9
7.4 Utilities .................................................................................................................. 10
7.5 Groundwater ......................................................................................................... 10
8.0 LIMITATIONS ................................................................................................................. 11
APPENDIX
A-1 Methods of Field Exploration
Boring Location Plan – Figure 1
B-1 Methods of Laboratory Testing
Logs of Borings
Key to Soil Symbols and Classifications
ALPHA Report No. W182958-1-Draft
1
1.0 PURPOSE AND SCOPE
The purpose of this geotechnical exploration is for ALPHA TESTING, INC. (“ALPHA”) to
evaluate for the “Client” some of the physical and engineering properties of subsurface materials
at selected locations on the subject site with respect to formulation of appropriate geotechnical
design parameters for proposed bridge foundations. The field exploration was accomplished by
securing subsurface samples from widely spaced test borings performed across the project site.
Engineering analyses were performed from results of the field exploration and results of laboratory
tests conducted on representative samples.
Also included are general comments pertaining to reasonably anticipated construction problems
and recommendations concerning earthwork and quality control testing during construction. This
information can be used to evaluate subsurface conditions and to aid in ascertaining whether
construction meets project specifications.
Recommendations provided in this report were developed from information obtained from test
borings depicting subsurface conditions only at the specific boring locations and at the particular
time designated on the logs. Subsurface conditions at other locations may differ from those
observed at the boring locations, and subsurface conditions at boring locations may vary at
different times of the year. The scope of work may not fully define the variability of subsurface
materials and conditions that are present on the site.
The nature and extent of variations from conditions encountered at the borings may not become
evident until construction. If significant variations then appear evident, our office should be
contacted to re-evaluate our recommendations after performing on-site observations and possibly
other tests.
2.0 PROJECT CHARACTERISTICS
A bridge for Heritage Trace Parkway is proposed at a location located about one-half mile east of
Wagley Robertson Road and about one-third mile north of running water trail, just west of the
Heritage Trace subdivision referenced in the project title. The bridge will cross a creek which
drains into Loughridge Lake located about one-half mile to the southeast. We understand the
bridge will consist of two (2) abutments and two (2) bents with maximum column loads of 200
tons. A site plan illustrating the general outline of the site is provided as Figure 1, the Boring
Location Plan, in the Appendix.
At the time the field exploration was performed, the site was undergoing clearing and excavation.
Conceptual grading plans provided by the project Civil Engineer indicate the ground surface on
either side of the creek slope down toward the creek about 9 ft from an approximate elevation of
about 704 ft at the top of the banks down to and approximate elevation of about 695 ft in the middle
of the creek. The slope on the west side is relatively gradual and the slope on the east side is
relatively steep.
The referenced conceptual plans indicate fills of up to 19 ft could be required in the west bridge
approach and fills of up to 12 ft could be required in the east bridge approach. Abutment design
was not chosen at the time of this report. Once more developed plans for abutment design are
available, additional recommendations for bearing pressures and lateral earth pressures can be
evaluated. Global stability analyses and scour recommendations are not included in the scope of
ALPHA Report No. W182958-1-Draft
2
this project. However, depending on final designs, global stability analyses could be required.
Our office can evaluate the need for global stability analyses after plans have been sufficiently
developed. Scour analyses, if required, should be performed by a firm specializing in that type of
work.
3.0 FIELD EXPLORATION
Subsurface conditions for the project were explored by drilling two (2) test borings to a depth of
about 45 ft each and two (2) test borings to a depth of about 35 ft each. The borings were performed
using standard rotary drilling equipment in general accordance with ASTM Standard D 420. The
approximate locations of the test borings are shown on the Boring Location Plan, Figure 1 in the
Appendix of this report. Details of drilling and sampling operations are briefly summarized in
Methods of Field Exploration, Section A-1 of the Appendix.
Subsurface types encountered during the field exploration are presented on the Log of Boring
sheets (boring logs) included in the Appendix. The boring logs contain our Field Technician's and
Engineer's interpretations of conditions believed to exist between actual samples retrieved.
Therefore, the boring logs contain both factual and interpretive information. Lines delineating
subsurface strata on the boring logs are approximate and the actual transition between strata may
be gradual.
4.0 LABORATORY TESTS
Selected samples of the subsurface materials were tested in the laboratory to evaluate their
engineering properties as a basis in providing recommendations for foundation design and
earthwork construction. A brief description of testing procedures used in the laboratory can be
found in Methods of Laboratory Testing, Section B-1 of the Appendix. Individual test results are
presented on the Log of Boring sheets enclosed in the Appendix.
5.0 GENERAL SUBSURFACE CONDITIONS
Based on the geologic atlas maps available from the Bureau of Economic Geology, published by
the University of Texas at Austin, the project site lies within the Fort Worth Limestone and Duck
Creek Formation mapped as undivided. The Fort Worth Limestone and Duck Creek formations
generally consist of limestone with marl (limey shale) layers. Residual soils associated with the
Fort Worth Limestone and Duck Creek formation generally consist of clay soils with low to high
shrink/swell potential.
Subsurface conditions encountered in the borings generally consisted of clay and/or clayey gravel
to depths of about 2 ft to 15 ft below the ground surface. Layers of tan limestone were encountered
below the clay in Borings 1, 2 and 4. Gray limestone was encountered below the tan limestone in
Borings 1, 2 and 4 and below clayey gravel in Boring 3 at depths of about 9 ft to 15 ft and extended
to the 35 ft and 45 ft termination depth of the borings. The upper 2 ft of clay in encountered in
Boring 2 was visually classified as fill material. More detailed stratigraphic information is
presented on the Drilling Log sheets attached to this report.
ALPHA Report No. W182958-1-Draft
3
The granular materials (clayey gravel) encountered in the borings are considered relatively
permeable and are expected to have a relatively rapid response to water movement. However, the
clay and limestone encountered in the borings are considered relatively impermeable and are
expected to have a relatively slow response to water movement. Therefore, several days of
observation would be required to evaluate actual groundwater levels within the depths explored.
The groundwater level at the site is anticipated to fluctuate seasonally depending on the amount of
rainfall, prevailing weather conditions and subsurface drainage characteristics.
Groundwater was encountered on the drilling tools during drilling in Borings 2 and 3 at depths of
about 4 ft and 10 ft below the ground surface, respectively. Free groundwater was observed in the
Boring 3 at a depth of 10 ft after drilling was complete. It is common to encounter seasonal
groundwater in fill and granular soils, from natural fractures within the clayey matrix, at the
soil/rock (limestone) interface, the rock/rock (limestone/shale) interface or from fractures in the
rock (limestone or shale), particularly during or after periods of precipitation. If more detailed
groundwater information is required, monitoring wells or piezometers can be installed.
Caving gravel occurred in Boring 3 which prohibited in-situ testing of the limestone at the 20 ft
depth interval using solid flight auger drilling techniques.
Further details concerning subsurface materials and conditions encountered can be obtained from
the Log of Boring sheets provided in the Appendix.
6.0 DESIGN RECOMMENDATIONS
The following design recommendations were developed on the basis of the previously described
Project Characteristics (Section 2.0) and General Subsurface Conditions (Section 5.0). Should the
project criteria change, our office should conduct a review to determine if modifications to the
recommendations are required. Further, it is recommended our office be provided with a copy of
the final plans and specifications for review prior to construction.
The following design criteria given were developed based on conceptual grading plans referenced
in Section 2.0. Different grading than indicated on the referenced plans can alter the recommended
geotechnical design parameters. It is recommended our office be contacted once final plans are
available to verify appropriate design parameters are utilized for final foundation design. Potential
scour was not considered for this analysis, but should be taken into consideration during bridge
and embankment design.
6.1 Drilled, Straight-Shaft Piers
Our findings indicate the bridge could be supported with drilled, straight-shaft piers bearing at
least 2 ft into gray limestone. Gray limestone was encountered at depths of about 9 ft to 15 ft
below the ground surface in the Borings. Deeper penetrations will be required to develop skin
friction and/or uplift resistance. Allowable end bearing and skin friction parameters are provided
in Table A.
ALPHA Report No. W182958-1-Draft
4
Groundwater was encountered on the drilling tools during drilling in Borings 2 and 3 at depths of
about 4 ft and 10 ft below the ground surface, respectively. Caving gravel also occurred in Boring
3 which prohibited in-situ testing of the limestone at the 20 ft depth interval using solid flight auger
drilling techniques. Casing will be likely be required to control groundwater and caving soils
during pier excavation. Processing of the pier through granular soil layers overlying the limestone
may also be required. Core barrels and/or rock teeth will be required to penetrate the limestone.
Test piers should be performed prior to construction to verify constructability of drilled piers and
groundwater levels.
TABLE A
Allowable End Bearing and Skin Friction Parameters
Bearing Stratum
Allowable End
Bearing
(ksf)
Skin Friction in
Compression
(ksf)
Skin Friction in
Uplift Resistance
(ksf)
Gray Limestone 50 7 6
Piers should penetrate through any clay or shale seams and layers to utilize the recommended
bearing pressure.
At least two (2) pier shaft diameters should be provided below the bottom of the pier and the
termination depth of our deepest boring (about 45 ft below existing grade) to use the allowable
end bearing parameter. If the minimum clearance between the bottom of the pier and the deepest
boring is not provided, piers should be designed as friction piers, neglecting end bearing. In no
case should piers bear deeper than the deepest boring (about 45 ft below the existing ground
surface). Deeper borings will be required to verify the bearing stratum below 45 ft if deeper piers
are planned.
The minimum clear spacing between piers should be at least two (2) pier shaft diameters, based
on the larger pier, to develop the full load carrying capacity from skin friction. The allowable skin
friction should be reduced by 50 percent for piers with adjacent touching edges. The allowable
skin friction can be interpolated between 100 percent and 50 percent for piers spaced between two
(2) pier shaft diameters and piers with adjacent touching edges.
The allowable bearing pressure value in Table A has a factor of safety of at least three (3) and the
skin friction values have a factor of safety of at least two (2). Normal elastic settlement of piers
under loading is estimated at less than about ½ inch.
Each pier should be sufficiently embedded into the gray limestone and should be designed with
full length reinforcing steel to resist the uplift pressure (soil-to-pier adhesion) due to potential soil
swell along the shaft from post construction heave and other uplift forces applied by structural
loadings. The magnitude of uplift adhesion due to soil swell along the pier shaft cannot be defined
accurately and can vary according to the actual in-place moisture content of the soils during
construction. It is estimated the average uplift adhesion will not exceed about 2.2 kips per sq ft.
This soil adhesion is approximated to act uniformly over the portion of the pier shaft in contact
with clay soils to a maximum depth of 12 ft below the ground surface or to the top surface of
limestone, whichever is encountered first.
ALPHA Report No. W182958-1-Draft
5
Table B contains L-PILE values for design of lateral resistance of piers.
TABLE B
Design Parameters For L-PILE
Material Gray Limestone
L-Pile p-y Model Weak rock
Effective Unit Weight (γ), pci 0.081
Rock Uniaxial Compressive Strength (qu), psi 410
Rock Mass Modulus (Er), psi 41,000
Rock Quality Designation (RQD)1, % 70-90
Rock Strain Factor (krm) 0.00005
1 Rock Quality Designation (RQD) is based on our area experience and the results of the field exploration.
6.2 Pier Caps and Grade Beams
All pier caps/grade beams connecting piers should be formed and not cast in earthen trenches. Pier
caps/grade beams should be formed with a nominal 12-inch void at the bottom. Commercially
available cardboard box forms (cartons) are made for this purpose. The cardboard cartons should
extend the full length and width of the grade beams. Prior to concrete placement, the cartons
should be inspected to verify they are firm, properly placed, and capable of supporting wet
concrete. Some type of permanent soil retainer, such as pre-cast concrete panels, must be provided
to prevent soils adjacent to pier caps/grade beams from sloughing into the void space at the bottom
of the grade beams. Additionally, backfill soils placed adjacent to grade beams must be compacted
as outlined in Section 7.3.
6.3 Embankment Fill and Potential Movements
As discussed, up to 19 ft of fill will be placed in the bridge approaches. We expect near-surface,
on-site or similar clayey soil will constitute most of the embankment fill. Clayey fill placed within
10 ft of final grade should be compacted to at least 95 percent of the material’s maximum dry
density as determined by standard Proctor (ASTM D 698) moisture-density tests. Clay fill placed
at depths below 10 ft of final grade should be compacted to at least 100 percent of the materials
maximum dry density. Further recommendations for fill compaction are presented in Section 7.3
of this report.
Even when fill is properly placed and compacted as recommended herein, relatively deep fills (in
excess of about 10 ft) are subject to settlement due to compression of the fill from self-weight.
The portion of fill placed as recommended in the upper 10 ft could be subject to settlement of
about 1 percent of the fill thickness and the portion below 10 ft of final grade could be subject to
settlement of up to about 2 percent. The total estimated settlement of the maximum 14 ft depth of
fill could be as much as 2½ to 3½ inches. This settlement could cause differential movement
between the pavement and the bridge deck. We expect the embankment fill will have achieved
about 70 percent settlement (about 2 ½ inches) after about 3 months with about 1 inch settlement
remaining.
ALPHA Report No. W182958-1-Draft
6
The underlying native soils will also be subject to some degree of settlement. We estimate
consolidation of the underlying soil could be about ½ inch to 1 inch and we expect it will take
about one to two years for about 50 to 70 percent of the settlement to occur. Consolidation tests
would be required to provide a more detailed settlement analysis for the underlying native soils.
Our office should be contacted if this service is desired.
In addition to consolidation settlement of new fill material, active clay soils which could compose
the majority of the new fill are subject to changes in volume due to seasonal changes in moisture
content. We estimate potential seasonal movements due to shrinking and swelling of active clay
soils could be up to about 6 inches. Potential seasonal movements from active clays can also cause
differential movement between the pavement and the bridge deck.
Potential seasonal movements were estimated using methods outlined by the Texas Department of
Transportation (TxDOT) Test Method Tex-124-E, and engineering judgment and experience. The
estimated movements were calculated assuming the moisture content of the in-situ soil within the
normal zone of seasonal moisture content change varies between a "dry" condition and a "wet"
condition as defined by methods outlined in Texas Department of Transportation Test Method
Tex-124-E. Movements exceeding our estimates could also occur if positive drainage of surface
water is not maintained or if soils are subject to an outside water source (generally within the upper
10 ft to 15 ft of the soil mass), such as leakage from a utility line or subsurface moisture migration
from off-site locations.
If the level of settlement and/or seasonal movements discussed herein are not acceptable, our office
should be provided information regarding the desired level of post construction movement for
further evaluation and recommendations. These values do not consider potential scour from the
creek channel.
6.4 Seismic Considerations
The Site Class for seismic design is based on several factors that include soil profile (soil or rock),
shear wave velocity, and strength, averaged over a depth of 100 ft. Since our borings did not
extend to 100-foot depths, we based our determinations on the assumption that the subsurface
materials below the bottom of the borings were similar to those encountered at the termination
depth. Based on Section 1613.3.2 of the 2012 International Building Code and Table 20.3-1 in the
2010 ASCE-7, we recommend using Site Class C (very dense soil or soft rock) for seismic design
at this site.
6.5 Associated Pavement
Recommendations for the pavement associated with the bridge are provided in ALPHA Report
No. W182958-A, dated January 28, 2018.
6.6 Drainage and Other Considerations
Adequate drainage should be provided to reduce seasonal variations in the moisture content of
subgrade soils. Final grades within 10 ft of the bridge structures should be adjusted to slope away
from the foundations and pavement at a minimum slope of 2 percent. Maintaining positive
surface drainage throughout the life of the pavement is essential.
ALPHA Report No. W182958-1-Draft
7
7.0 GENERAL CONSTRUCTION PROCEDURES AND GUIDELINES
Variations in subsurface conditions could be encountered during construction. To permit
correlation between test boring data and actual subsurface conditions encountered during
construction, it is recommended a registered Professional Engineering firm be retained to observe
construction procedures and materials.
Some construction problems, particularly degree or magnitude, cannot be reasonably anticipated
until the course of construction. The recommendations offered in the following paragraphs are
intended not to limit or preclude other conceivable solutions, but rather to provide our
observations based on our experience and understanding of the project characteristics and
subsurface conditions encountered at the borings.
7.1 Site Preparation and Grading
Limestone was encountered at a depth of about 3 ft below the existing ground surface in Boring 1
and could be encountered during general excavation at this site. From our experience, this
limestone can be hard and difficult to excavate. Rock excavation methods (including, but not
limited to rock teeth, rippers, jack hammers, or sawcutting) may be required to remove the
limestone. Crushing equipment may be required to process the limestone if it is desired to use this
material as compacted fill on the site. The contractor selected should have experience with
excavation in hard limestone.
Existing fill was encountered to a depths about 2 ft below the ground surface in Boring 2. Although
not encountered in the boring, existing fill materials can also contain organics, boulders, rubble,
and other debris which could be encountered during site grading and general excavation. The
earthwork and excavation contracts should contain provision for removal of unsuitable materials
in the existing fill. Test pit excavations performed prior to construction can be used to evalu ate
the depth, extent and composition of existing fill at this site. ALPHA would be pleased to provide
this service if desired.
All areas supporting pavement, flatwork and areas to receive new fill should be properly prepared.
After completion of the necessary stripping, clearing, and excavating and prior to placing
any required fill, the exposed soil subgrade should be carefully evaluated by probing and
testing. Any undesirable material (organic material, wet, soft, or loose soil) still in place
should be removed.
The exposed soil subgrade should be further evaluated by proof rolling with a heavy
pneumatic tired roller, loaded dump truck or similar equipment weighing approximately
25 tons to check for pockets of soft or loose material hidden beneath a thin crust of possibly
better soil. Proof-rolling procedures should be observed routinely by a Professional
Engineer or his designated representative. Any undesirable material exposed during the
proof-roll (organic material, wet, soft, or loose soil) exposed from the proof roll should be
removed and replaced with well-compacted material as outlined in Section 7.3.
Prior to placement of any fill, the exposed soil subgrade should then be scarified to a
minimum depth of 6 inches and recompacted as outlined in Section 7.3.
ALPHA Report No. W182958-1-Draft
8
If fill is to be placed on existing slopes (natural or constructed) steeper than six horizontal to one
vertical (6:1), the fill materials should be benched into the existing slopes in such a manner as to
provide a minimum bench width of five (5) feet. This should provide a good contact between the
existing soils and new fill materials, reduce potential sliding planes and allow relatively horizontal
lift placements.
The contractor is responsible for designing any excavation slopes, temporary sheeting or shoring.
Design of these structures should include any imposed surface surcharges. Construction site safety
is the sole responsibility of the contractor, who shall also be solely responsible for the means,
methods and sequencing of construction operations. The contractor should also be aware that
slope height, slope inclination or excavation depths (including utility trench excavations) should
in no case exceed those specified in local, state and/or federal safety regulations, such as OSHA
Health and Safety Standard for Excavations, 29 CFR Part 1926, or successor regulations.
Stockpiles should be placed well away from the edge of the excavation and their heights shou ld
be controlled so they do not surcharge the sides of the excavation. Surface drainage should be
carefully controlled to prevent flow of water over the slopes and/or into the excavations.
Construction slopes should be closely observed for signs of mass movement, including tension
cracks near the crest or bulging at the toe. If potential stability problems are observed, a
geotechnical engineer should be contacted immediately. Shoring, bracing or underpinning
required for the project (if any) should be designed by a professional engineer registered in the
State of Texas.
Due to the nature of the clay soils found near the surface at some of the borings, traffic of heavy
equipment (including heavy compaction equipment) may create pumping and general deterioration
of shallow soils. Therefore, some construction difficulties should be anticipated during periods
when these soils are saturated.
7.2 Foundation Excavations
All foundation excavations should be monitored to verify foundations bear on suitable material.
The bearing stratum exposed in the base of all foundation excavations should be protected against
any detrimental change in conditions. Surface runoff water should be drained away from
excavations and not allowed to collect. All concrete for foundations should be placed as soon as
practical after the excavation is made. Drilled piers should be excavated and concrete placed the
same day.
Prolonged exposure of the bearing surface to air or water will result in changes in strength and
compressibility of the bearing stratum. Therefore, if delays occur, straight shaft pier excavations
should be slightly widened, deepened and cleaned, or a new (deeper) design penetration made in
order to provide a fresh bearing surface.
All pier shafts should have a minimum diameter of 1/30th of the length of the pier or 2 ft, whichever
is greater, to facilitate clean-out of the base and proper monitoring. Concrete placed in pier holes
should be directed through a tremie, hopper, or equivalent. Placement of concrete should be
vertical through the center of the shaft without hitting the sides of the pier or reinforcement to
reduce the possibility of segregation of aggregates. Concrete placed in piers should have a
minimum slump of 5 inches (but not greater than 7 inches) to avoid potential honey-combing.
ALPHA Report No. W182958-1-Draft
9
Observations during pier drilling should include, but not necessarily be limited to, the following
items:
Verification of proper bearing strata and consistency of subsurface stratification with
regard to boring logs,
Confirmation the minimum required penetration into the bearing strata is achieved,
Complete removal of cuttings from bottom of pier holes,
Proper handling of any observed water seepage and sloughing of subsurface materials,
No more than 2 inches of standing water should be permitted in the bottom of pier holes
prior to placing concrete, and
Verification of pier diameter and steel reinforcement.
Groundwater was encountered on the drilling tools during drilling in Borings 2 and 3 at depths of
about 4 ft and 10 ft below the ground surface, respectively. Caving gravel also occurred in Boring
3 which prohibited in-situ testing of the limestone at the 20 ft depth interval using solid flight auger
drilling techniques. We expect casing will be required to control caving soils and groundwater.
The casing should be seated in the limestone, below the depth of seepage. After the casing is
seated, all loose material should be removed. As casing is extracted, care should be taken to
maintain a positive head of plastic concrete and minimize the potential for intrusion of water
seepage or sloughing of sandy soils. In addition, it may be necessary to process the pier shaft
excavations through the wet granular soils encountered above the limestone.
7.3 Fill Compaction
The following recommendations pertain to general fill placement. Bridge approach/embankment
fill should be compacted as recommended in Section 6.3.
Clayey soils with a plasticity index equal to or greater than 25 should be compacted to a dry density
between 93 and 97 percent of standard Proctor maximum dry density (ASTM D 698). The
compacted moisture content of the clays during placement should be within the range of 2 to 6
percentage points above optimum.
Clayey soils with a plasticity index below 25 should be compacted to a dry density of at least 95
percent of standard Proctor maximum dry density (ASTM D 698) and within the range of 1
percentage point below to 3 percentage points above the material's optimum moisture content.
Clayey materials used as fill should be processed and the largest particle or clod should be less
than 6 inches prior to compaction.
Non-plastic granular materials (gravel) should be compacted to at least 95 percent of standard
Proctor maximum dry density (ASTM D 698) and within the range of 2 percent below to 1
percentage points above the material's optimum moisture content. Compaction of these soils is
very sensitive to moisture content and these soils are prone to pumping when too wet and rutting
when too dry.
ALPHA Report No. W182958-1-Draft
10
In cases where mass fills are more than 10 ft deep, the fill/backfill below 10 ft should be compacted
to at least 100 percent of standard Proctor maximum dry density (ASTM D-698) and within 2
percentage points of the material's optimum moisture content. The portion of the fill/backfill
shallower than 10 ft should be compacted as outlined herein.
Compaction should be accomplished by placing fill in about 8-inch thick loose lifts and
compacting each lift to at least the specified minimum dry density. Field density and moisture
content tests should be performed on each lift.
7.4 Utilities
In cases where utility lines are more than 10 ft deep, the fill/backfill below 10 ft should be
compacted to at least 100 percent of standard Proctor maximum dry density (ASTM D 698) and
within –2 to +2 percentage points of the material's optimum moisture content. The portion of the
fill/backfill shallower than 10 ft should be compacted as previously outlined. Density tests should
be performed on each lift (maximum 12-inch thick) and should be performed as the trench is being
backfilled.
Even if fill is properly compacted, fills in excess of about 10 ft are still subject to settlements over
time of up to about 1 to 2 percent of the total fill thickness. This should be considered when
designing utility lines under pavements and/or other areas with deep fill.
If utility trenches or other excavations extend to or beyond a depth of 5 ft below construction grade,
the contractor or others shall be required to develop an excavation safety plan to protect personnel
entering the excavation or excavation vicinity. The collection of specific geotechnical data and
the development of such a plan, which could include designs for sloping and benching or various
types of temporary shoring, is beyond the scope of this study. Any such designs and safety plans
shall be developed in accordance with current OSHA guidelines and other applicable industry
standards.
7.5 Groundwater
Groundwater was encountered on the drilling tools during drilling in Borings 2 and 3 at depths of
about 4 ft and 10 ft below the ground surface, respectively. However, from our experience with
similar soils, shallower groundwater seepage could be encountered in excavations for foundations,
pavement, utility conduits and other general excavations. The risk of encountering seepage
increases with depth of excavation and during or after periods of precipitation. Standard sump pits
and pumping may be adequate to control minor seepage on a local basis.
Where groundwater is encountered in granular soils, sump pits may not be adequate to control
seepage and supplemental dewatering measures may be necessary to control groundwater seepage.
Supplemental dewatering measures include (but are not limited to) submersible pumps in slotted
casings and well points.
ALPHA Report No. W182958-1-Draft
11
In any areas where cuts are made, attention should be given to possible seasonal water seepage
that could occur through natural cracks and fissures in the newly exposed stratigraphy. The risk
of seepage is increased where limestone is exposed in excavations and slopes or is near final grade.
In these areas, subsurface drains may be required to intercept seasonal groundwater seepage. The
need for these or other de-watering devices should be carefully addressed during construction. Our
office could be contacted to visually observe the final grades to evaluate the need for such drains.
8.0 LIMITATIONS
Professional services provided in this geotechnical exploration were performed, findings obtained,
and recommendations prepared in accordance with generally accepted geotechnical engineering
principles and practices. The scope of services provided herein does not include an environmental
assessment of the site or investigation for the presence or absence of hazardous materials in the
soil, surface water or groundwater. ALPHA, upon written request, can be retained to provide these
services.
ALPHA is not responsible for conclusions, opinions or recommendations made by others based
on this data. Information contained in this report is intended for the exclusive use of the Client
(and their designated design representatives), and is related solely to design of the specific
structures outlined in Section 2.0. No party other than the Client (and their designated design
representatives) shall use or rely upon this report in any manner whatsoever unless such party shall
have obtained ALPHA’s written acceptance of such intended use. Any such third party using this
report after obtaining ALPHA’s written acceptance shall be bound by the limitations and
limitations of liability contained herein, including ALPHA’s liability being limited to the fee paid
to it for this report. Recommendations presented in this report should not be used for design of
any other structures except those specifically described in this report. In all areas of this report in
which ALPHA may provide additional services if requested to do so in writing, it is presumed that
such requests have not been made if not evidenced by a written document accepted by ALPHA.
Further, subsurface conditions can change with passage of time. Recommendations contained
herein are not considered applicable for an extended period of time after the completion date of
this report. It is recommended our office be contacted for a review of the contents of this report
for construction commencing more than one (1) year after completion of this report. Non -
compliance with any of these requirements by the Client or anyone else shall release ALPHA from
any liability resulting from the use of, or reliance upon, this report.
Recommendations provided in this report are based on our understanding of information provided
by the Client about characteristics of the project. If the Client notes any deviation from the facts
about project characteristics, our office should be contacted immediately since this may materially
alter the recommendations. Further, ALPHA is not responsible for damages resulting from
workmanship of designers or contractors. It is recommended the Owner retain qualified personnel,
such as a Geotechnical Engineering firm, to verify construction is performed in accordance with
plans and specifications.
APPENDIX
ALPHA Report No. W182958-1-Draft
A-1 METHODS OF FIELD EXPLORATION
Using standard rotary drilling equipment, a total of four (4) test borings were performed for this
geotechnical exploration at the approximate locations shown on the Boring Location Plan, Figure
1. The boring locations were staked by using a handheld GPS device or by pacing or taping and
estimating right angles from landmarks which could be identified in the field and as shown on the
site plan provided during this study. The locations of the test borings shown on the Boring
Location Plan are considered accurate only to the degree implied by the methods used to define
them.
Relatively undisturbed samples of the cohesive subsurface materials were obtained by
hydraulically pressing 3-inch O.D. thin-wall sampling tubes into the underlying soils at selected
depths (ASTM D 1587). These samples were removed from the sampling tubes in the field and
evaluated visually. One representative portion of each sample was sealed in a plastic bag for use
in future visual evaluation and possible testing in the laboratory.
Texas Department of Transportation Texas Cone Penetration (TCP) tests were completed in the
field to determine the apparent in-place strength characteristics of the rock type materials. A 3-
inch diameter steel cone driven by a 170-pound hammer dropped 24 inches is the basis for TxDOT
strength correlations. Depending on the resistance (strength) of the materials, either the number of
blows of the hammer required to provide 12 inches of penetration, or the inches of penetration of
the cone due to 100 blows of the hammer are recorded on the field logs and are shown on the Log
of Boring sheets as “TX Cone” (reference: TxDOT Test Method TEX 132-E).
Logs of the borings are included in the Appendix. The logs show visual descriptions of subsurface
strata encountered using the Unified Soil Classification System. Sampling information, pertinent
field data, and field observations are also included. Samples not consumed by testing will be
retained in our laboratory for at least 14 days and then discarded unless the Client requests
otherwise.
BORING LOCATION PLANGEOTECHNICAL EXPLORATIONHERITAGE TRACE BRIDGE -WATERSBEND SOUTH - PHASES 1B, 1C, 1D, 3, 5, AND 6 OFF WAGLEY ROBERTSON ROADFORT WORTH, TEXASALPHA PROJECT NO. W182958-1-DRAFTFIGURE 1 B-1 B-3 B-2 B-4 WAGLEY ROBERTSON ROAD B-1 B-3 B-2 B-4 WAGLEY ROBERTSON ROAD NAPPROXIMATE BORING LOCATION
ALPHA Report No. W182958-1-Draft
B-1 METHODS OF LABORATORY TESTING
Representative samples were evaluated and classified by a qualified member of the Geotechnical
Division and the boring logs were edited as necessary. To aid in classifying the subsurface
materials and to determine the general engineering characteristics, natural moisture content tests
(ASTM D 2216), Atterberg-limit tests (ASTM D 4318), percent material passing sieve #200
(ASTM D 422) and dry unit weight determinations were performed on selected samples. In
addition, an unconfined compressive strength tests (ASTM D 2166) and pocket-penetrometer tests
were conducted on selected soil samples to evaluate the soil shear strength. Results of the se
laboratory tests are provided on the Log of Boring sheets.
36
11
73 24 49
100/
1"
100/
0.75"
100/
0.5"
100/
0.75"
100/
0"
100/
0.25"
100/
0"
100/
0.75"
100/
0"
Dark Brown CLAY
Tan LIMESTONE with clay seams and layers
Gray LIMESTONE with shale seams
TEST BORING TERMINATED AT 45 FT
3.0
9.0
45.0
2.0
4.5 Water Content, %% PassingNo. 200 SieveLiquid LimitPlastic LimitPlasticity IndexGraphic LogNorth:TX Cone or Std.Pen. (blows/ft,in)Recovery %RQDSample TypeMATERIAL DESCRIPTION
West:
5058 Brush Creek Rd.
Fort Worth, Texas
76119
Phone: 817-496-5600
Fax: 817-496-5608
www.alphatesting.com
Start Date:2/14/2019 End Date:2/14/2019
Project:Heritage Trace Bridge, Watersbend South - Phases 1B, 1C, 1D, 3, 5, and 6
Client:Forestar (USA) Real Estate Group, Inc. - Dallas
Hammer Drop (lbs / in):140 / 30
Surface Elevation:Unit Dry Weight(pcf)Depth, feet5
10
15
20
25
30
35
40
45
GROUND WATER OBSERVATIONS
After Hours (ft):PocketPenetrometer (tsf)On Rods (ft):
Drilling Method:CONTINUOUS FLIGHT AUGER
Unconfined Comp.Strength (tsf).NONE
After Drilling (ft):.DRY
.
PROJECT NO.:W182958-1
Location:Fort Worth, Texas
Sheet 1 of 1
BORING NO.:1
9
10
19
10
11
52
46
19
17
33
29
10
25
100/
6"
100/
0.25"
100/
0.5"
100/
1"
100/
1.25"
100/
1"
100/
0.75"
100/
1.25"
Brown CLAY with calcareous nodules, limestone
fragments, and gravel - FILL
Tan CLAY with calcareous nodules and limestone
fragments
- gravelly below 7 ft
Tan LIMESTONE with clay seams and layers
Gray LIMESTONE
TEST BORING TERMINATED AT 45 FT
2.0
7.0
11.0
45.0
3.0 Water Content, %% PassingNo. 200 SieveLiquid LimitPlastic LimitPlasticity IndexGraphic LogNorth:TX Cone or Std.Pen. (blows/ft,in)Recovery %RQDSample TypeMATERIAL DESCRIPTION
West:
5058 Brush Creek Rd.
Fort Worth, Texas
76119
Phone: 817-496-5600
Fax: 817-496-5608
www.alphatesting.com
Start Date:3/27/2019 End Date:3/27/2019
Project:Heritage Trace Bridge, Watersbend South - Phases 1B, 1C, 1D, 3, 5, and 6
Client:Forestar (USA) Real Estate Group, Inc. - Dallas
Hammer Drop (lbs / in):140 / 30
Surface Elevation:Unit Dry Weight(pcf)Depth, feet5
10
15
20
25
30
35
40
45
GROUND WATER OBSERVATIONS
After Hours (ft):PocketPenetrometer (tsf)On Rods (ft):4
Drilling Method:CONTINUOUS FLIGHT AUGER
Unconfined Comp.Strength (tsf).
After Drilling (ft):.DRY
.
PROJECT NO.:W182958-1
Location:Fort Worth, Texas
Sheet 1 of 1
BORING NO.:2
27
23
20
33
16
15
75
67
55
22
17
45
38
8
50/
2"
100/
0.25"
100/
2"
100/
1.25"
Dark Brown CLAY
Brown CLAY with limestone seams
Tan CLAYEY GRAVEL
Gray LIMESTONE
- no test conducted at 20 ft due to caving gravel from
upper layer
TEST BORING TERMINATED AT 35 FT
2.0
8.0
15.0
35.0
943.25
2.0
2.5
3.9 Water Content, %% PassingNo. 200 SieveLiquid LimitPlastic LimitPlasticity IndexGraphic LogNorth:TX Cone or Std.Pen. (blows/ft,in)Recovery %RQDSample TypeMATERIAL DESCRIPTION
West:
5058 Brush Creek Rd.
Fort Worth, Texas
76119
Phone: 817-496-5600
Fax: 817-496-5608
www.alphatesting.com
Start Date:3/27/2019 End Date:3/27/2019
Project:Heritage Trace Bridge, Watersbend South - Phases 1B, 1C, 1D, 3, 5, and 6
Client:Forestar (USA) Real Estate Group, Inc. - Dallas
Hammer Drop (lbs / in):140 / 30
Surface Elevation:Unit Dry Weight(pcf)Depth, feet5
10
15
20
25
30
35
40
45
GROUND WATER OBSERVATIONS
After Hours (ft):PocketPenetrometer (tsf)On Rods (ft):10
Drilling Method:CONTINUOUS FLIGHT AUGER
Unconfined Comp.Strength (tsf).
After Drilling (ft):10.
.
PROJECT NO.:W182958-1
Location:Fort Worth, Texas
Sheet 1 of 1
BORING NO.:3
26
8
16
15
55
40
20
17
35
23
10
50/
3"
100/
2.5"
100/
1.25"
100/
0.75"
100/
1.25"
100/
0.5"
100/
1"
Brown and Tan CLAY with calcareous nodules and
limestone fragments
Tan and Gray CLAY with limestone fragments
Tan LIMESTONE with clay seams and layers
Gray LIMESTONE with shale seams
TEST BORING TERMINATED AT 35 FT
3.0
7.0
8.0
35.0
3.25 Water Content, %% PassingNo. 200 SieveLiquid LimitPlastic LimitPlasticity IndexGraphic LogNorth:TX Cone or Std.Pen. (blows/ft,in)Recovery %RQDSample TypeMATERIAL DESCRIPTION
West:
5058 Brush Creek Rd.
Fort Worth, Texas
76119
Phone: 817-496-5600
Fax: 817-496-5608
www.alphatesting.com
Start Date:3/26/2019 End Date:3/26/2019
Project:Heritage Trace Bridge, Watersbend South - Phases 1B, 1C, 1D, 3, 5, and 6
Client:Forestar (USA) Real Estate Group, Inc. - Dallas
Hammer Drop (lbs / in):140 / 30
Surface Elevation:Unit Dry Weight(pcf)Depth, feet5
10
15
20
25
30
35
40
45
GROUND WATER OBSERVATIONS
After Hours (ft):PocketPenetrometer (tsf)On Rods (ft):
Drilling Method:CONTINUOUS FLIGHT AUGER
Unconfined Comp.Strength (tsf).NONE
After Drilling (ft):.DRY
.
PROJECT NO.:W182958-1
Location:Fort Worth, Texas
Sheet 1 of 1
BORING NO.:4
TEXAS CONE PENETRATION
FILL
LIMESTONE
(MH), Elastic SILT
SANDSTONE
(GP), Poorly Graded GRAVEL
LOW
MEDIUM
HIGH
VERY HIGH
4 TO 15
16 TO 25
26 TO 35
OVER 35
SAMPLING SYMBOLS
(OL), ORGANIC SILT
(OH), ORGANIC CLAY
8.0" OR LARGER
3.0" TO 8.0"
0.75" TO 3.0"
5.0 mm TO 3.0"
2.0 mm TO 5.0 mm
0.4 mm TO 5.0 mm
0.07 mm TO 0.4 mm
0.002 mm TO 0.07 mm
LESS THAN 0.002 mm
SOIL & ROCK SYMBOLS
KEY TO SOIL SYMBOLS
AND CLASSIFICATIONS
(CH), High Plasticity CLAY VERY LOOSE
LOOSE
MEDIUM
DENSE
VERY DENSE
RELATIVE DENSITY OF COHESIONLESS SOILS (blows/ft)
0 TO 4
5 TO 10
11 TO 30
31 TO 50
OVER 50
SHELBY TUBE (3" OD except where
noted otherwise)
SPLIT SPOON (2" OD except where
noted otherwise)
AUGER SAMPLE
ROCK CORE (2" ID except where
noted otherwise)
PARTICLE SIZE IDENTIFICATION (DIAMETER)
(CL), Low Plasticity CLAY
(SP), Poorly Graded SAND
(GW), Well Graded GRAVEL
(GC), CLAYEY GRAVEL
(GM), SILTY GRAVEL
BOULDERS
COBBLES
COARSE GRAVEL
FINE GRAVEL
COURSE SAND
MEDIUM SAND
FINE SAND
SILT
CLAY
TRACE
LITTLE
SOME
AND
1 TO 10
11 TO 20
21 TO 35
36 TO 50
RELATIVE PROPORTIONS (%)
VERY SOFT
SOFT
FIRM
STIFF
VERY STIFF
HARD
LESS THAN 0.25
0.25 TO 0.50
0.50 TO 1.00
1.00 TO 2.00
2.00 TO 4.00
OVER 4.00
SHEAR STRENGTH OF COHESIVE SOILS (tsf)
RELATIVE DEGREE OF PLASTICITY (PI)SHALE / MARL
(SC), CLAYEY SAND
(SW), Well Graded SAND
(SM), SILTY SAND
(ML), SILT