Change Order Request
Project Name 2014 CIP Year 3,Contract 1 City Sec No.151702
Project No.(s)56002-0600430/0700430-001787,30100-0200431-0O2481, DOE No. N/A City Pro.No.02693
34014-0200431-CO2480
Project Water,Sanitary Sewer and Paving Improvements on approximately 7.66 lane miles for 2014 CIP Year 3,Contract 1 and
Description Area Water System Improvements.
Contractorl Texas Materials Group,Inc. I Change Order# 0 Date: 10/28/2020
City Project Mgr.1 Liam Conlon 71City Inspector I William Mattegat
Phone Number: 817-392-6824 Phone Number: 817-392-8306
Dept. Water Sewer 2014 CIP TPW's 50150 Totals Contract Time
PAVE (Calandar Days)
Original Contract Amount $4,897,386.70 $1,186,890.70 $2,761,226.20 $515,863.04 $9,361,366.64 730
Extras to Date $152,527.00 $152,527.00 7
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $5,049,913.70 $1,186,890.70 $2,761,226.20 $515,863.04 $9,513,893.64 737
Amount of Proposed Change Order $0.00 $0.00 $0.00 $0.00 $0.00 0
Revised Contract Amount $5,049,913.70 $1,186,890.70 $2,761,226.20 $515,863.04 $9,513,893.64 737
Orig.Funds Available for Change Orders $195,895.00 $59,345.00 $138,061.00 $51,586.00 $444,887.00
Remaining Funds Available for this CO $43,368.00 $59,345.00 $138,061.00 $51,586.00 $292,360.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT
$11,701,708.30
JUSTIFICATION(REASONS)FOR CHANGE ORDER
Change Order No.5 provide for the installation of pavement markings at the Village Creek Treatment
Plant parking lot which was constructed via Change Order No.2.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Al Aontractor Date
Texas Materials Group, Inc. Martin Wigg 10/29/2020
I pector Project M ager // D
Director(Water Dept) Construction Supervisor(T&PW Dept) bate
Sher Ner(Odl3 101016:1 M l, S. o�ay 0/30/202
Assistant City Attorney Assistant City Manager Date
can Nov 3,2020
Council Action(if required) OFFICIAL RECORD
M&C Number N/A M&C Date Approved
CITY SECRETARY
FT. WORTH, TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name 2014 CIP Year 3,Contract 1 City Sec No. 51702
Project No.(s) 56002-0600430/0700430-001787,30100-0200431-0O2481,34014-0200431- DOENo.= City Pro.No. 02693
Project Water,Sanitary Sewer and Paving Improvements on approximately 7.66 lane miles for 2014 CIP Year 3,Contract 1 and Area
Description Water System Improvements.
Contractor Texas Materials Group,Inc. Change Order# 0 Date: 10/28/2020
City Project Mgr. Liam Conlon City Inspector William Mattegat
ADDITIONS
ITEM DESCRIPTION DEPT City Unit Unit Cost Total
1-131 Village Creek WWTP Striping Water 1.00 LS $1,620.00 $1,620.00
Water $1,620.00
Sewer
2014 CIP
TPW's 50/50 PAVE
Additions Sub Total $1,620.00
Page 1 of 1
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name 2014 CIP Year 3,Contract 1 City Sec No. 51702
Project No.(s) M002-060043010700430-co17e7,301OM200431-co2481,34014-0200431L024W DOE No. N/A City Pro.No. 02693
Project Description Water,Sanitary Sewer and Paving Improvements on approximately 7.66 lane miles for 2014 CIP Year 3,Contract 1 and
Area Water System Improvements.
Contractor FTexas Materials Group,Inc. Change Order#0 Date 10/28/2020
City Project Mgr. Liam Conlon City Inspector William Mattegat
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
1-101 3291.0100 Top Soil(50/50) Water 32.40 CY $50.00 $1,620.00
Water $1,620.00
Sewer
2014 CIP
TPW's 50/50 PAVE
Deletions Sub Total $1,620.00
Page 1 of 1
M/WBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
co# DATE AMOUNT
Total $0.00
,Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
d / H M co /.oo.J
Name of Employee
ci � 2 �v
Title
adgvvpp4�
qpF FORT as
ATTEST: ��o °°°°�paod
oo
Pv00000 =d
oo-
Mary J. Kayser o�aa a�nFzp54a
City Secretary
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX