HomeMy WebLinkAboutContract 52926-FP1 City Secretary
Contract No. 52926 -FP1
FORTWORTH, Date Received NOv 23,2020
NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: Water & Sewer, Paving, Drainage & Street Light Improvements
City Project No.: 102086
Improvement Type(s): ❑ Paving ❑ Drainage ❑x Street Lights ❑ Traffic Signals
Original Contract Price: $40,317.74
Amount of Approved Change Order(s):
Revised Contract Amount: $40,317.74
Total Cost of Work Complete: $40,317.74
RcGra��'�yv6�e Richard Wolfe(Nov 20,2 0153 Nov 2020206 CST) f
Contractor Date
President
Title
Independent Utility Construction, Inc.
Company Name
MA4V-e,U;V
Matt Cain(Nov 20,20201625 CSC Nov 20 f2020
Project Inspector Date
Debbie J.Willhelm N 0 202017:40 CS Nov 20 12020
Project Tanager Date
4761`Iz6 SW494t/L1y�6l4?I Nov 23 2020
Janie Scarlett Morales(Nov 23,2020 0756 CSC f
CFA Manager Date
D & aA346� Nov 23 2020
ff(Dana Burghdo v23,2 1123 CST) 7
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT. WORTH, TX
Notice of Project Completion
Project Name: Water& Sewer, Paving, Drainage & Street Light Improvements
City Project No.: 102086
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 30 CD Days Charged: 247
Work Start Date: 12/2/2019 Work Complete Date: 8/5/2020
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name WATER,SEWER,PAVING,DRAINAGE AND STREET LIGHT IMPROVME
Contract Limits
Project Type STREET LIGHTING
City Project Numbers 102086
DOE Number 2086
Estimate Number 1 Payment Number 1 For Period Ending 8/5/2020
CD
City Secretary Contract Number Contract Time XD
Contract Date 10/21/2019 Days Charged to Date 247
Project Manager NA Contract is 100.00 Complete
Contractor INDEPENDENT UTILITY CONSTRUCTION
5109 SUN VALLEY DRIVE
FORT WORTH, TX 76119
Inspectors CORDOVA / CAIN,M
Wednesday,November 4,2020 Page 1 of 4
City Project Numbers 102086 DOE Number 2086
Contract Name WATER,SEWER,PAVING,DRAINAGE AND STREET LIGHT IMPROV Estimate Number 1
Contract Limits Payment Number 1
Project Type STREET LIGHTING For Period Ending 8/5/2020
Project Funding
UNIT V:STREET LIGHTING IMPROVEMENTS
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 2"CONDT PVC SCH 80(T) 263 LF $11.70 $3,077.10 263 $3,077.10
2 RDWY ILLUM FOUNDATION TY 1 9 EA $1,584.00 $14,256.00 9 $14,256.00
3 6-6-6 TRIPLEX ALUM ELEC CONDUCTOR 263 LF $3.28 $862.64 263 $862.64
4 RDWY ILLUM ASSEMBLY TY 11 9 EA $2,458.00 $22,122.00 9 $22,122.00
Sub-Total of Previous Unit $40,317.74 $40,317.74
--------------------------------------
Wednesday,November 4,2020 Page 2 of 4
City Project Numbers 102086 DOE Number 2086
Contract Name WATER,SEWER,PAVING,DRAINAGE AND STREET LIGHT IMPROV Estimate Number I
Contract Limits Payment Number 1
Project Type STREET LIGHTING For Period Ending 8/5/2020
Project Funding
Contract Information Summary
Original Contract Amount $40,317.74
Change Orders
Total Contract Price $40,317.74
Total Cost of Work Completed $40,317.74
Less %Retained $0.00
Net Earned $40,317.74
Earned This Period $40,31T74
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $40,317.74
Wednesday,November 4,2020 Page 3 of 4
City Project Numbers 102086 DOE Number 2086
Contract Name WATER,SEWER,PAVING,DRAINAGE AND STREET LIGHT IMPROV Estimate Number I
Contract Limits Payment Number I
Project Type STREET LIGHTING For Period Ending 8/5/2020
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors CORDOVA / CAIN,M Contract Date 10/21/2019
Contractor INDEPENDENT UTILITY CONSTRUCTION Contract Time 30 CD
5109 SUN VALLEY DRIVE Days Charged to Date 247 CD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $40,317.74
Less %Retained $0.00
Net Earned $40,317.74
Earned This Period $40,317.74
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $40,317.74
Wednesday,November 4,2020 Page 4 of 4
FORT WORTH.
TRANSPORTATION AND PUBLIC WORKS
October 28, 2020
Independent Utility Construction, Inc.
5109 Sun Valley Dr.
Fort Worth,TX. 76119
RE: Acceptance Letter
Project Name: Water,Sewer, Paving,and Street Light Improvements to Serve Kingspoint Phase 3
Project Type: Development
City Project No.: 102086
To Whom It May Concern:
On August 17, 2020 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on October 27, 2020. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on October 27, 2020,which is the date
of the punch list completion and will extend of two (2)years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at
(817)392-2481.
Sincerely,
T�aZ5;�i C. 4/g&e''Pi�
Debbie INUhelm(N 0,2020 17:40 CST)
Debbie Wil elm, Project Manager
Cc: Matt Cain, Inspector
Ron Cordova, Inspection Supervisor
Edward D'avila,Senior Inspector
Mike Domenech, Program Manager
UA Engineering, Consultant
Independent Utility Construction, Inc., Contractor
Kingspoint Antares S-F, LLC, Developer
File
E-Mail:
Douglas W. Wiersig, P.E., PhD., Director,TPW Chris Harder, P.E.,Assistant Director,Water
Richard Martinez,Assistant Director,TPW Wendy Chi-Babulal, P.E.,Water
Marisa Conlin,Traffic Engineering Tony Sholola, P.E.,Water
Allen Hall,Superintendent,TPW Richard Zavala, Director, PARD
John Robert Carman, P.E., Director,Water David Creek,Assistant Director, PARD
Rev.9/15/16
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, on this day personally appeared RICHARD
W OLFE, President of INDEPENDENT UTILITY CONSTRUCTION INC. known
to me to be a credible person, and after being duly sworn by me, upon his oath deposed
and said;
"That all persons, firms, associations, corporations, or other organizations
furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth has
been paid in full;
That there are no claims pending for personal injury and/or property damages;
On Contract described as: Kingspoint Phase 3—City Project No. 102086
BY:
Richard Wolfe, President
S�
RIBED AND SWORN TO BEFORE ME on this day of
2020.
CHRISTINA GARCIA
�2�PRei;=Notary Public, State of Texas
'�` Comm. Expires 12 20 2020 Gf�
„pill%% Notary ID 130940785 Notary Public, State of Texas
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
CONTRACTOR ❑
TO FINAL PAYMENT SURETY ❑
OTHER
(SIMILAR TO AIA DOCUMENT G707)
Bond No. 012676N
PROJECT: Street Lighting Improvements to serve Kingspoint Phase 3
(name,address) Fort Worth,TX
TO (Owner)
ARCHITECT'S PROJECT NO:
City of Fort Worth CONTRACT FOR:
200 Texas Street
Fort Worth,TX 76102
L� CONTRACT DATE:
CONTRACTOR: Independent Utiity Construction,inc.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above, the(here insert name and
address of Surety Company)
Westfield Insurance Company
555 Republic Drive,Suite 450 ,SURETY COMPANY,
Plano, TX 75074
on bond of(here insert name and address of Contractor)
Independent Utility Construction, Inc.
5109 Sun Valley Drive CONTRACTOR,
Fort Worth,TX 76119
hereby approves of the final payment to the Contractor, and agrees that the final payment to the Contractor shall not relieve the
Surety Company of any of its obligations to(here insert name and address of Owner)
City of Fort Worth
200 Texas Street OWNER,
Fort Worth, TX 76102
as set forth in the said Surety Company's bond.
IN WITNESS WHEREOF,
The Surety Company has hereunto set its hand this 15th day of July 2020
WESTFIELD INSURANCE COMPANY
Surety Company
By L
Q, -jj I Jjl.'�(-T/J
Signature of A thorized Representative
Attest:
(Seal): Elizabeth Gray Attorney—in—Fact
Title
Note:This form is intended to be used as a companion document to the Contractors Affidavit of Payment of Debts and Claims,Current Edition
THIS POWER OF ATTORNEY SUPERCEDES ANY PREVIOUS POWER BEARINU I HIS SAMt
POWER#AND ISSUED PRIOR TO 04/20/11, FOR ANY PERSON OR PERSONS NAMED BELOW.
POWER NO. 4220052 06
General Power Westfield Insurance Co.
of Attorney Westfield National Insurance Co.
CERTIFIED COPY Ohio Farmers Insurance Co.
Westfield Center, Ohio
Know All Men by These Presents, That WESTFIELD INSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY and OHIO
FARMERS INSURANCE COMPANY, corporations, hereinafter referred to individually as a "Company" and collectively as -Companies," duly
organized and existing under the laws of the State of Ohio, and having its principal office in Westfield Center, Medina County, Ohio, do by these
presents make, constitute and appoint
CHARLES D. SWEENEY, MICHAEL A. SWEENEY, KYLE W. SWEENEY, ELIZABETH GRAY, JOINTLY OR SEVERALLY
of FORT WORTH and State of TX its true and lawful Attorney(s)-in-Fact, with full power and authority hereby conferred in its name,
place and stead, to execute, acknowledge and deliver any and all bonds, recognizances, undertakings, or other instruments or contracts of
suretyship- - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - -- - -
LIMITATION: THIS POWER OF ATTORNEY CANNOT BE USED TO EXECUTE NOTE GUARANTEE, MORTGAGE DEFICIENCY, MORTGAGE
GUARANTEE, OR BANK DEPOSITORY BONDS.
and to bind any of the Companies thereby as fully and to the same extent as if such bonds were signed by the President,sealed with the corporate
seal of the applicable Company and duly attested by its Secretary, hereby ratifying and confirming all that the said Attorney(s)-in-Fact may do in
the.premises. Said appointment is made under and by authority of the following resolution adopted by the Board of Directors of each of the
WESTFIELD INSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY and OHIO FARMERS INSURANCE COMPANY:
-Be It Resolved,that the President, any Senior Executive, any Secretary or any Fidelity& Surety Operations Executive or other Executive shall
be and is hereby vested with full power and authority to appoint any one or more suitable persons as Attorney(s)-in-Fact to represent and act for
and on behalf of the Company subject to the following provisions:
The Attorney-in-Fact. may be given full power and authority for and in the name of and on behalf of the Company,to execute,acknowledge and
deliver, any and all bonds, recognizances, contracts, agreements of indemnity and other conditional or obligatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney-in-Fact shall be as binding upon the Company as if signed by the President and sealed and attested by the Corporate Secretary.-
'Be it Further Resolved, that the signature of any such designated person and the seal of the Company heretofore or hereafter affixed to any
power of attorney or any certificate relating thereto by facsimile, and any power of attorney or certificate bearing facsimile signatures or facsimile
seal shall be valid and binding upon the Company with respect to any bond or undertaking to which it is attached.- (Each adopted at a meeting
held on February 8,2000).
In Witness Whereof, WESTFIELD INSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY and OHIO FARMERS INSURANCE
COMPANY have caused these presents to be signed by their Senior Executive and their corporate seals to be hereto affixed this 20th day of
APRIL A.D.,2011 .
Corporate
- tOrv�C WESTFIELD INSURANCE COMPANY
Seals tiQ�a.. •••�fC�;,; `�P�.•• !NpG,; `,. '......v1su �c,a WESTFIELD NATIONAL INSURANCE COMPANY
Affixed �v .cy. 0 p:• Z= =�_!;• — '•.� OHIO FARMERS INSURANCE COMPANY
�f
�J SEAL
.w •�
., .. By:
State of Ohio ......... Richard L. Kinnaird, Jr., National Surety Leader and
County of Medina ss.: Senior Executive
On this 20th day of APRIL A.D., 2011 before me personally came Richard L. Kinnaird, Jr. to me, known, who, being by me duly
sworn, did depose and say, that he resides in Medina, Ohio; that he is Senior Executive of WESTFIELD INSURANCE COMPANY,WESTFIELD
NATIONAL INSURANCE COMPANY and OHIO FARMERS INSURANCE COMPANY, the companies described in and which executed the above
instrument;that he knows the seals of said Companies;that the seals affixed to said instrument are such corporate seals;that they were so affixed
by order of the Boards of Directors of said Companies; and that he signed his name thereto by like order.
Notarial `H,
Seat `•R1 A L ``•
Affixed
O'er '=f
_ ' William J. Kahelin,A rney at Law, Notary Public
State of Ohio :; doAkwjo My Commission Does Not Expire (Sec. 147.03 Ohio Revised Code)
County of Medina ss.: .r
I, Frank A. Carrino, Secretary of WESTFIELD INSURANCE COMPANY,WESTFIELD NATIONAL INSURANCE COMPANY and OHIO FARMERS
INSURANCE COMPANY, do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney, executed by said
Companies,which is still in full force and effect; and furthermore,the resolutions of the Boards of Directors, set out in the Power of Attorney are
in full force and effect.
In Witness Whereof, I have hereunto set my hand and affixed the seals of said Companies at Westfield Center, Ohio, this 15th day of
Juty ,r asA"Di'-Q20 :••'�;cir���';'•,
C,�
SEAL
's u►- _ .a e Secretary
SEAL
�`' .ze� �� �z,: o`• .: : 1848: Frank A. Carrinc, Secretary
EIPOAC2 (combined) (06-02)