HomeMy WebLinkAboutContract 49565-CO4 F(3I,-' o�;. City of Fort Worth CSC No.49565-CO4 ` f Change Order Request Project Name:1 Marine Creek Interceptor Improvements,Phase I City Sec No.: 1 49565 Project No.(s): 59607.0700430-CO1783 DOE No. 7214 City Proj.No,;1 02223 Project Description: Pipe enlargement to upgrade and replace an existing deteriorated sanitary sewer main located within the Marine Creek Basin beginning from Bowman Roberts Rd./Cromwell Marine Creek Rd. Contractor William J,Schultz,Inc.dba Circle C Construclion Co. Change Order It Dale: 10/27/2020 City Project Mgr,I Waller Norwood,P.E, City Inspector; I Judy Die Phone Number: (817)392-5026 Phone Number: (817)392-8452 Dept, Water Sewer Totals Contract Time (Calender days) Original Contract Amount $1,634,700.00 $1,634,700.00 320 Extras to Date $64,370.00 $64,370.00 0120 Credits to Date Pending Change Orders(In M&C Process) Contract Cost to Date $1,699,070.00 $1,699,070.00 440 Arnount of Proposed Change Order $0.00 $0.00 650 Revised Contract Amount $1,699,070.00 $1,699,070.00 1,090 Original Funds Available for Change Orders $81,800.00 $81,800.00 Remaining Funds Available for this CO $17,430.00 $17,430.00 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 1 3,94% MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $2,043,375.00 JUSTIFICATION(REASONS)FOR CHANGE ORDER Change Order No.4 will provide an additional 650 calendar days on the project for the following: • Delay waiting for Atmos Energy to confirm ownership and adjust conflicting gas mains that were encountered during construction. . Extremely wet soil condition from rain events prevented the application of protective manhole coating to manholes in close proximity to the creek. Resolution of issues identified from the post construction TV inspection. • Delay waiting for easements to be acquired to construct segments of the sewer main. i It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's Company Name Contractor Name Contractor Signature Date wllllam J.Schultz.Inc.dba Circlo C Conslrucllon co. Teri SkellyF10/28/20k ns ector Date Pro ect Manager Date O rector(Water Dept)' Date Consl cllon Supervisor(Water Dept) Date Assistant City Attorney I Date Assistant City Manager Date t!(A Oct 30,2020 ktnn S<<�/rd�/ of{ Nov 2,2020 Council Action If Required M&C Number NIA M&C Date Approved A OFFICIAL RECORD CITY SECRETARY FT.WORTH, TX Fo)1,-' V�rL))n iC iyi City of Fort W01111 --- _ - --- C:haiige Order Acid ii:iom Project Name Marine Creek Interceptor Improvements,Phase I City Sec No.: 49565 Project No.(s): 59607-0700430-CO1783 DOENo.[= City Proj. No.: 02223 Project Pipe enlargement to upgrade and replace an existing deteriorated sanitary sewer main located within the Marine Creek Description Basin beginning from Bowman Roberts Rd./Cromwell Marine Creek Rd. Contractor William J.Schultz. Inc.dba Circle C Construclion Co. Change Order:0 Date: 10/27/2020 City Project Mgr. Walter Norwood, P.E. City Inspector FJUdy Die ADDITIONS —I'I"EIVI— ESCRIPTION J DEPT J Oty IUnit Unit Cost I Total Water Sewer Page 2 of 4 Additions Sub Total FC3aT MVC3NZ-.14 City of Fort Worth Change Order Deletions Project Name Marine Creek Interceptor Improvements,Phase I City Sec No.; 1 49565 Project No.(s): 59607-0700430-CO1783 DOE No. 7214 City Proj.No.: 02223 Project Description Pipe enlargement to upgrade and replace an existing deteriorated sanitary sewer main located within the Marine Creek Basin beginning from Bowman Roberts Rd./Cromwell Marine Creek Rd. Contractor William J.Schultz.Inc.dba Circle C Construction Co. Change Order: ® Date 10/27/2020 City Project Mgr. Walter Norwood,P.E. City Inspector; Judy Die DELETIONS ITEM DESCRIPT ION DEPT Qty Unit Unit Cost (Total Water Sewer Page 3 of 4 Deletions Sub Total iAMBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders coif DATE AMOUNT Total $0.00 Page 4 of 4 Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and adnunistration of this contract, including ensuring all performance and reporting requirements, Signature �)IYAav knllwclo r Naive of Binployee Title pooFOR' 00 a ATTEST: a�o d~o o o $ Qo° dd d� Y 00oo0000�o a Mary J. Kayser a ?EXpSoo City Secretary nnuaa4o OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX