NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: P&D, W&S, Street Lighting to Serve Elizabeth Creek Phase 1
City Project No.: 102000
Improvement Type(s): ❑ Paving ❑ Drainage 0 Street Lights ❑ Traffic Signals
Original Contract Price: $138,486.40
Amount of Approved Change Order(s):
Revised Contract Amount: $138,486.40
Total Cost of Work Complete: $138,486.40
Dec 4, 2020
Rig .Volfe(Dec 4,20201
Contractor Date
President
Title
Independent Utility Construction,Inc.
Company Name
Dec 4, 2020
Mark Mc adin Pec 4, ;ST)
Project Inspector Date
Kam• (� P.E• Dec 4 2020
KhalJaafari P.E. ec4,202022:44 CST)
Project Manager Date
Laurie Lewis on behalf of Tanie Morales Dec 7, 2020
Laurie Lewis on behalf of Janie Morales(Dec'
CFA w' 4 e Date
? e5e Dec 7, 2020
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX Page 1 of 2
Notice of Project Completion
Project Name: P&D, W&S, Street Lighting to Serve Elizabeth Creek Phase 1
City Project No.: 102000
City's Attachments
Final Pay Estimate ❑x
Change Order(s): ❑ Yes ❑x N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety >
Statement of Contract Time
Contract Time: 255 CD Days Charged: 366
Work Start Date: 12/2/2019 Work Complete Date: 12/1/2020
Page 2 of 2
FORT WORTH
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name ELIZABETH CREEK PHASE 1
Contract Limits
Project Type STREET LIGHTING
City Project Numbers 102000
DOE Number 2000
Estimate Number 1 Payment Number 1 For Period Ending 12/1/2020
CD
City Secretary Contract Number Contract Time 25ED
Contract Date 10/30/2019 Days Charged to Date 366
Project Manager NA Contract is 100.00 Complete
Contractor INDEPENDENT UTILITY CONSTRUCTION
5109 SUN VALLEY DRIVE
FORT WORTH, TX 76119
Inspectors CORDOVA,R / MCFADIN,M
l
1
Friday,December 4,2020 Page 1 of 4
City Project Numbers 102000 DOE Number 2000
Contract Name ELIZABETH CREEK PHASE 1 Estimate Number I
Contract Limits Payment Number I
Project Type STREET LIGHTING For Period Ending 12/1/2020
Project Funding
UNIT V:STREET LIGHTING IMPROVEMENTS
Item Estimated Estimated Completed Completed
Description of Items Unit Unit Cost
No. Quanity Total Quanity Total
---------------------------------------
1 2"CONDT PVC SCH 80(T) 2610 LF $11.39 $29,727.90 2610 $29,727.90
2 FURNISHIINSTALL LED LIGHTING FIXTURE 34 EA $270.00 $9,180.00 34 $9,180.00
(70 WATT ATBO)
3 RDWY ILLUM FOUNDATION TY 1,2,4 34 EA $1,064.00 $36,176.00 34 $36,176.00
4 FURNISH/INSTALL RDWAY ILLUM TY I I POLE 34 EA $1,436.00 $48,824.00 34 $48,824.00
5 FURNISH/INSTALL TYPE 33B ARM 34 EA $210.00 $7,140.00 34 $7,140.00
6 NO 10 INSULATED ELEC COND 7830 LF $0.95 $7,438.50 7830 $7,438.50
--------------------------------------
Sub-Total of Previous Unit $138,486.40 $138,486.40
--------------------------------------
Friday,December 4,2020 Page 2 of 4
City Project Numbers 102000 DOE Number 2000
Contract Name ELIZABETH CREEK PHASE 1 Estimate Number 1
Contract Limits Payment Number 1
Project Type STREET LIGHTING For Period Ending 12/1/2020
Project Funding
Contract Information Summary
Original Contract Amount $138,486.40
Change Orders
Total Contract Price $138,486.40
Total Cost of Work Completed $138,486.40
Less %Retained $0.00
Net Earned $138,486.40
Earned This Period $138,486A0
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $138,486.40
Friday,December 4,2020 Page 3 of 4
City Project Numbers 102000 DOE Number 2000
Contract Name ELIZABETH CREEK PHASE I Estimate Number I
Contract Limits Payment Number I
Project Type STREET LIGHTING For Period Ending 12/1/2020
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors CORDOVA,R / MCFADIN,M Contract Date 10/30/2019
Contractor INDEPENDENT UTILITY CONSTRUCTION Contract Time 255 CD
5109 SUN VALLEY DRIVE Days Charged to Date 366 CD
FORT WORTH, TX 76119 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $138,486.40
Less %Retained $0.00
Net Earned $138,486.40
Earned This Period $138,486.40
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $138,486.40
Friday,December 4,2020 Page 4 of 4
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
December 2, 2020
Independent Utility Construction INC
5109 Sun Valley Dr
Fort Worth Tx. 76119
RE: Acceptance Letter
Project Name: Paving, Water, Sewer, Drainage, Street Lighting to Seve Elizabeth Creek Ph1
Project Type: Street Lighting
City Project No.: 102000
To Whom It May Concern:
On December 1, 2020 a final inspection was made on the subject project. There were no punch list
items identified at that time. The final inspection indicates that the work meets the City of Fort Worth
specifications and is therefore accepted by the City. The warranty period will start on December 1,
2020, which is the date of the final inspection and will extend of two (2)years in accordance with the
Contract Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at Khal
Jaafari.
Sincerely,
Khaliaafari P.E. ec4,202022:44CST)
Khal Jaafri, Project Manager
Cc: Mark McFadin, Inspector
Ron Cordova, Inspection Supervisor
Gary Deyon, Senior Inspector
Victor Torneno, Program Manager
Peloton Land Solutions, Consultant
Independent Utility Construction, Contractor
Pulte Group, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev.08/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OFTARRANT
Before me, the undersigned authority, on this day personally appeared RICHARD
WOLFE, President of INDEPENDENT UTILITY CONSTRUCTION INC. known
to me to be a credible person, and after being duly sworn by me, upon his oath deposed
and said;
"That all persons, firms, associations, corporations, or other organizations
furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort Worth has
been paid in full;
That there are no claims pending for personal injury and/or property damages;
On Contract described as: Elizabeth Creek Phase 1 —City Project No. 102000
BY:
Richard Wolfe, President
�t�BSCRIBE,q AND SWORN TO BEFORE ME on this Rodayof
r2-020.
\IUU
Py pie�, CHRISTiNA GARCIA
Notary Public, State of Texas
r
Comm. Expires 12-20-2020
i�rF OF•���� Notary ID 130940785 ary Public, State of Texas
ll/f it l,t y
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
CONTRACTOR ❑ RECEIVED NOY 2 0 pp10 TO FINAL PAYMENT STY El
OTHER
(SIMILAR TO AIA DOCUMENT G707)
Bond No. 049447V
PROJECT: Street Lighting Improvements to serve Elizabeth Creek Phase 1
(name,address) Fort Worth,TX
TO (Owner)
ARCHITECT'S PROJECT NO:
F— City of Fort Worth CONTRACT FOR:
200 Texas Street
Fort Worth, TX 76102
CONTRACT DATE:
CONTRACTOR: Independent Utility Construction,Inc.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above,the(here insert name and
address of Surety Company)
Westfield Insurance Company
555 Republic Drive, Suite 450 ,SURETY COMPANY,
Plano, TX 75074
on bond of(here insert name and address of Contractor)
Independent Utility Construction, Inc.
5109 Sun Valley Drive CONTRACTOR,
Fort Worth,TX 76119
hereby approves of the final payment to the Contractor, and agrees that the final payment to the Contractor shall not relieve the
Surety Company of any of its obligations to(here insert name and address of Owner)
City of Fort Worth
200 Texas Street
Fort Worth, TX 76102 OWNER,
as set forth in the said Surety Company's bond.
IN WITNESS WHEREOF,
The Surety Company has hereunto set its hand this 17th day of November 2020
WESTFIELD INSURANCE COMPANY
Surety Company Q /l
By 11 l c l �
Signature of Aufhorized Representative
Attest:
(Seal): Elizabeth Gray Attorney—in—Fact
Title
Note:This form is intended to be used as a companion document to the Contractor's Affidavit of Payment of Debts and Claims,Current Edition
THIS POWER OF ATTORNEY SUPERCEDES ANY PREVIOUS POWER BEARINU I NlS SAMt
POWER#AND ISSUED PRIOR TO 04/20111, FOR ANY PERSON OR PERSONS NAMED BELOW.
POWER NO. 4220052 06
General Power Westfield Insurance Co.
of Attorney Westfield National Insurance Co.
Ohio Farmers Insurance Co.
CERTIFIED COPY Westfield Center, Ohio
Know All Men by These Presents, That WESTFIELD INSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY and OHIO
FARMERS INSURANCE COMPANY, corporations, hereinafter referred to individually as a "Company" and collectively as "Companies," duly
organized and existing under the laws of the State of Ohio, and having its pribapal office in Westfield Center, Medina County, Ohio, do by these
presents make, constitute and appoint
CHARLES D. SWEENEY, MICHAEL A. SWEENEY, KYLE W. SWEENEY, ELIZABETH GRAY, JOINTLY OR SEVERALLY
of FORT WORTH and State of TX its true and lawful Attorneys)-in-Fact, with full power and authority hereby conferred in its name,
place and stead, to execute, acknowledge and deliver any and all bonds, recognizances, undertakings, or other instruments or contracts of
suretyship- - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - -- - - - -
LIMITATION: THIS POWER OF ATTORNEY CANNOT BE USED TO EXECUTE NOTE GUARANTEE, MORTGAGE DEFICIENCY, MORTGAGE
GUARANTEE, OR BANK DEPOSITORY BONDS.
and to bind any of the Companies thereby as fully and to the same extent as if such bonds were signed by the President,sealed with the corporate
seal of the applicable Company and duly attested by its Secretary, hereby ratifying and confirming all that the said Attorney(s)-in-Fact may do in
the premises. Said appointment is made under and by authority of the following resolution adopted by the Board of Directors of each of the
WESTFIELD INSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY and OHIO FARMERS INSURANCE COMPANY:
"Be It Resolved,that the President, any Senior Executive, any Secretary or any Fidelity& Surety Operations Executive or other Executive shall
be and is hereby vested with full power and authority to appoint any one or more suitable persons as Attorney(s)-in-Fact to represent and act for
and on behalf of the Company subject to the following provisions:
The Attorney-in-Fact. may be given full power and authority for and in the name of and on behalf of the Company,to execute,acknowledge and
deliver, any and all bonds, recognizances, contracts, agreements of indemnity and other conditional or obligatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney-in-Fact shall be as binding upon the Company as if signed by the President and sealed and attested by the Corporate Secretary.-
'Be it Further Resolved, that the signature of any such designated person and the seal of the Company heretofore or hereafter affixed to any
power of attorney or any certificate relating thereto by facsimile, and any power of attorney or certificate bearing facsimile signatures or facsimile
seal shall be valid and binding upon the Company with respect to any bond or undertaking to which it is attached.' (Each adopted at a meeting
held on February 8,2000).
In Witness Whereof, WESTFIELD INSURANCE COMPANY, WESTFIELD NATIONAL INSURANCE COMPANY and OHIO FARMERS INSURANCE
COMPANY have caused these presents to be signed by their Senior Executive and their corporate seals to be hereto affixed this 20th day of
APRIL A.D.,2011 .
Corporate =�,a�.NRr(ky,, �\O.AL/ ,nS�KSU WESTFIELD INSURANCE COMPANY
Seals .•� •.,C 'a?..• NS'':; c'-a WESTFIELD NATIONAL INSURANCE COMPANY
Affixed v° .a. o` 11 : G� OHIO FARMERS INSURANCE COMPANY
4 t, SUL -a� :c~n, SEAL m_ E o:•
�=� •-'`•....✓'•rw% ��i . .=0 oEll
f .... •sue.:
B*y:
State of Ohio """"'"`" " •• """"•" Richard L. Kinnaird, Jr.,National Surety Leader and
County of Medina ss.: Senior Executive
On this 20th day of APRIL A.D., 2011 , before me personally came Richard L. Kinnaird, Jr. to me known, who, being by me duly
sworn, did depose and say, that he resides in Medina, Ohio;that he is Senior Executive of WESTFIELD INSURANCE COMPANY,WESTFIELD
NATIONAL INSURANCE COMPANY and OHIO FARMERS INSURANCE COMPANY, the companies described in and which executed the above
instrument;that he knows the seals of said Companies;that the seals affixed to said instrument are such corporate seals;that they were so affixed
by order of the Boards of Directors of said Companies;and that he signed his name thereto by like order.
Notarial ` L
Seal at A L yy,,
Affixed �
O P'\�111ijjSF'-
;�A� f=
2�
• William J. Kahelin,A rney at Law, Notary Public
State of Ohio N .f. o My Commission Does Not Expire(Sec. 147.03 Ohio Revised Code)
County of Medina ss.: y ;
I, Frank A..Carrino, Secretary of WESTFIELD INSURANCE COMPANY,WESTFIELD NATIONAL INSURANCE COMPANY and OHIO FARMERS
INSURANCE COMPANY, do hereby certify that the above and foregoing is a true and correct copy of a Power of Attorney, executed by said
Companies,which is still in full force and effect;and furthermore,the resolutions of the Boards of Directors, set out in the Power of Attorney are
in full force and effect.
In Witness Whereof, I have hereunto set my hand and affixed the seals of said Companies at Westfield Center, Ohio, this th day of
-A November 2020 17
wm.wD j,,yN• .. .,•, WH•yq
r�'�e1 /III. Ac•."::...//V KsU
4 NSEAL =� :"' SEAL = �:�HrAitT. � 3 I�/ ( !///�(L
:N•, '�• .secretary
'b'•.ti•'�` �r� �'z,. 'o, ` 1138 :t Frank A. Carrino, Secretary
tied .....•�•
EIPOAC2 (combined) (06-02)