HomeMy WebLinkAboutContract 53880-CO1 FORT WORTH.
CSC No.53880-COI
City Of Fort Worth
Change Order Request
Facility and
Project North Tri-Ethnic Community Center Renovations City Sec No. 53880
Description:
Funding(FID)21001-0190463-5740010-100621-9919Q1 City Proj.No. 100621
No.(s)
Contractor:ICIVIE Builders&Engineers,Inc. Change Order#F-71 Date: 121912020
City Project Mgr.I Ronnie Clements City Inspector: Mike Milam
Phone Number:(817)392-8014 Phone Number: (817)392-2297
Contract Time
(CD)
Original Contract Amount-------------------------------------------- $394,535.00 120
Extras to Date---------------------------------------------------- $0.00 0
Credits to Date--------------------------------------------------- $0.00 0
Pending Change Orders(in M&C Process)---------------------------------- $0.00 0
Contract Cost to Date----------------------------------------------- $394,535.00 120
Amount of Proposed Change Order-------------------------------------- $13,117.66 89
Revised Contract Amount-------------------------------------------- $407,652.66 209
Original Funds Available for Change Orders--------------------------------- $0.00
Remaining Funds Available for this CO------------------------------------ $0.00
Additional Funding(if necessary)--------------------------------------- $0.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 3.33%
MAX ALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $493,168.75
JUSTIFICATION(REASONS)FOR CHANGE ORDER
The purpose of Change Order#1 is for various unforseen changes to include modification of east exterior stairs,an additional P-lam door,
shortening of a block wing wall in the restroom,and modifications to the umial screen and an additional screen between sinks. These
changes were approved by Neighborhood Services Department.Change Orders No.1 increases the original contract($394,535.00)by
$13,117.66 for a revised contract amount of$407,652.66.A 3.33 percent increase to the original contract price.Additionally,there are 47
days added to the contract for this work and other 42 days added for other unforseens that were corrected thrrough contingency allowance
expenditures.
It is understood and agreed that the acceptance of this Change Order by the contractor consitutes an accord and satisfaction and represents
payment in full(both time and money)for all costs arising out of,or inclndental to the above Change Order.
Contractor's Company Name Contractor Name Contractor Signature Date
CME Builders&Engineers,Inc. --+ Dec 11,2020
PMD Inspector Date Project Manager Date
Dec 11,2020 R M Clements Dec 11,2020
PMD Superintendent Date Arohitecural Services Manager Date
amauiami o 11 m MMC Dec 11,2020 �' � ��, DeC 11,2020
Project Architect Date Director/Property Management Department Date
Dec 11,2020 34eye COPIfPi Dec 17,2020
o ke�17 m 11:QCS
Assistant City Attorney Date As Dade
18 Strong Dec 17,2020 DanasurandoFF Dec 17,2020 OFFICIAL RECORD
oaa euBkaon n,mmlapsan
CITY SECRETARY
M&C Number N/A M&C Date Approved N/A
p t Von),Q4 FT. WORTH, TX
Contract Compliance Manager: p �°° °°°°0,
a o9 p
By signing I acknowledge that I am the person responsible pia °id &.'
�
for the monitoring and adminstration of this contract,includir PpQ* *�° Brian R.Glass,AIA
ensuring all performance and reporting requirements. da�zz 4 TEXp ap Architectural Services Manager 0
b4nuao�
✓yk*"�T ` Dec 21,2020
CME BUILDERS & ENGINEERS, INC.
CT E 1505 E. Henderson Street
Cleburne, Texas 76031
CONSTRUCTION MANAGEMENT ENGINEERS
Phone: 817-641-0406 FAX: 817-645-8685
October 26, 2020
RE: Cost Proposal —Eastern Stairs
North Tri Ethnic Community Center
Fort Worth, TX
All,
After reviewing the correspondence from Mr. Milam, as well as the revised response from RFI No. 24, based on
concerns of confined working space to "build around" the existing slope wall, our subcontractor has determined
the most cost effective and sensible solution is as follows:
"We propose to furnish to continue with the proposed demolition of the existing exterior stair wall, stopping at
the existing landing. We propose to build the new stair structure as per original drawings. Prior to forming and
pouring new steps, we will core drill the existing land and pump flowable fill grout to fill existing void."
The attached revised proposal is based on that scope of work. Please review and advise if this is acceptable.
CME SUMMARY A/E
COST PROPOSAL CONTRACTOR �X
OWNER
PROJECT Fort Worth Tri-Ethnic Commurift Center 1 of 1
Facility sheet
2020-002 CME Builders& Engineers, Inc.
CSP Number Contractor Contract Modification
DATE: October 26, 2020 No: 08
Cost Estimate No.
DESCRIPTION
RFI No. 24- Eastern Stairs
SUMMARY
MAt an increase in the contract price(contingency)of$4,634.70 (broken down in itemized detail below)
❑ At no change in the contract price
❑ At reduction in contract price of (broken down in itemized detail below)
❑X With an extension of 28 days to the period of performance
Cost Detail
a. Direct Labor(attached supporting detailed estimate) $ 288.60
b. Insurance $ 101.98
c. Materials/Expenses $ 40.00
Subtotal $ 430.58
d. Overhead 5% $ 21.53
e. Profit 5% $ 21.53
f. Employment taxes under FICA and FUTA $ 37.16
General Contractor Total: $ 510.80
g. Subcontracts
Company JCategory of Work jAmount
Cates, Courtney& Roe Concrete Is 3,749.00
$ 0.00
$ 0.00
Subcontract Total: $ 3,749.00
h. Contractor's 10% Commission on Total of Subcontracts $ 374.90
I. Contractor's Total $ 510.80
Total increase cw4eerease to contract rice: $ 4,634.70
\\Cmenas\cmenas\Current Projects\Fort Worth, TX North Tri-Ethnic Community Center\Cost Estimates\Cost Estimate
No. 8- Eastern Stairs\Revised Cost Estimate No. 8- RFI 24 Eastern Stairs.xls
CATES COURTNEY & ROEBUCK
CONCRETE CONTRACTORS
P.O. Box 301 • Fort Worth,TX 76101 •3228 South Freeway Fort Worth, TX 76110
Office(817) 921-3183 • Fax(817) 921-4986
www.ccrconcrete.com
Request for Change Order#3revl
10/23/20
To: Robert Carroll
CME Builders&Engineers, Inc
North Tri-Ethnic Community Center
RE: Reference to RFI 24- Eastern Stairs
We propose to furnish to continue with the proposed demolition of the existing
exterior stair wall,stopping at the existing landing.
We propose to build the new stair structure as per original drawings.
Prior to forming and pouring new steps,we will core drill the existing land and
pump flowable fill grout to fill existing void.
Please see the revised RCO forgrout filling of void.
Inclusions:
1. Core Drill 3 to 4 holes in upper landing.
2. Pump up to 5 CY's of flowable fill grout to fill void under upper landing.
Lump Sum Request for Change Order#3: $3,749.00
Thankyou for choosing Cates, Courtney and Roebuck,Inc.foryour concrete needs.
Sincerely Yours,
Randy Colle
"Concrete- The Foundation of Fort Worth"
North Tri-Ethnic Community Center
30/23/2020
Ro`-AMUK
Cates,Courtney&Roebuck, Inc.
P.O. Box 301, Fort Worth,TX 76101
office 817-921-3183
fax 817-921-4986
Request for C/O#3 revl
Referance to RFI 24-Eastern Stairs
Quantity Unit Unit Price Amount
Labor-Core Drill Landing 8 Hrs 30.001 $240.00
I1 $0.00
1 $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL: $240.00
Materials,Equipment,and Services Quantity Unit Unit Price Amount
Flowable Fill Grout 5 CY 120.00 $600.00
Pump 1 Ea 1500.00 $1,500.00
Core Drill 1 LS 800.00 $800.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
SUBTOTAL: 2,900.00
Summary I Amount
Labor $240.00
Payroll Taxes, Insurance, Benefits $120.00
Material,Equipment,and Services $2,900.00
Overhead/Profit $489.00
TOTAL $3,749.00
CME BUILDERS & ENGINEERS, INC.
CT E 1505 E. Henderson Street
Cleburne, Texas 76031
CONSTRUCTION MANAGEMENT ENGINEERS
Phone: 817-641-0406 FAX: 817-645-8685
October 26, 2020
RE: Cost Proposal —Eastern Stairs
North Tri Ethnic Community Center
Fort Worth, TX
All,
After reviewing the correspondence from Mr. Milam, as well as the revised response from RFI No. 24, based on
concerns of confined working space to "build around" the existing slope wall, our subcontractor has determined
the most cost effective and sensible solution is as follows:
"We propose to furnish to continue with the proposed demolition of the existing exterior stair wall, stopping at
the existing landing. We propose to build the new stair structure as per original drawings. Prior to forming and
pouring new steps, we will core drill the existing land and pump flowable fill grout to fill existing void."
The attached revised proposal is based on that scope of work. Please review and advise if this is acceptable.
CME SUMMARY A/E ❑
COST PROPOSAL CONTRACTOR �X
OWNER ❑
PROJECT Fort Worth Tri-Ethnic Community Center 1 of 1
Facility sheet
2020-002 CME Builders & Engineers, Inc.
CSP Number Contractor Contract Modification
DATE: October 30,2020 No: 09
Cost Estimate No.
DESCRIPTION
RFI No. 26-Women's 118
SUMMARY
OX At an increase in the contract price of$3,441.04 (broken down in itemized detail below)
El At no change in the contract price
❑ At reduction in contract price of (broken down in itemized detail below)
OX With an extension of 6 days to the period of performance(Subject to change depending on notification to proceed with the wo k)
Cost Detail
a. Direct Labor(attached supporting detailed estimate) $ 496.60
b. Insurance $ 175.48
c. Materials/Expenses $ 120.00
Subtotal $ 792.08
d. Overhead 5% $ 39.60
e. Profit 5% $ 39.60
f. Employment taxes under FICA and FUTA $ 63.95
General Contractor Total: $ 935.24
g. Subcontracts
Company JCategory of Work JAmount
Corporate Floors loving wall Is 1,100.00
Prodigy Design IPainting $ 578.00
Cheyenne Commercial I Drywall $ 600.00
Subcontract Total: $ 2,278.00
h. Contractor's 10%Commission on Total of Subcontracts $ 227.80
I. Contractor's Total $ 935.24
Total increase of-deefease to contract rice: $ 3,441.04
11
\\Cmenas%cmenas\Current Projects\Fort Worth, TX North Tri-Ethnic Community CenteACost Estimates\Cost Estimate
No. 9-RFI 25-26\Cost Estimate No. 9- RFI 25-26 Restroom.xls
CME BUILDERS & ENGINEERS, INC.
CRIE 1505 E. Henderson Street
Cleburne, Texas 76031
CONSTRUCTION MANAGEMENT ENGINEERS
817-641-0406 Fax 817-645-8685
INVOICE
Date 10/30/2020 Inv No
To Fort Worth Tri-Ethnic Community Center Job No 26820
2950 Roosevelt Avenue
Fort Worth. TX
ITEM Amount TOTAL
Cash Advanced to: (Bills Attached)
3 day expenses S 120.00
$120.00
Job Payroll & Expense for Week Ending
1 days of Superintendent labor by CME Builders & Engineers, Inc. OFFICE
2 days of Labor by CME Builders & Engineers, Inc. CODE
Total Gross Payroll $496.60 1901
Soc Sec/Medicare .0765 $37.98 1901
State Employment Tax .0747 $37.09 2231
FUTA Tax .0541 $26.86 2221
WC/GEN LIA & VAC. .2769 $137.50 2271
TOTAL .4361 $736.03
TOTAL $856.03
Date. Change Order
Corporate 10/30/2020
F L O O R S To: Request
Cal
t
1712 Minters Chapel Road,Suite 100 COURTNEY KENDRICK
Grapevine,TX 76051
817-329-7100 Voice 800.757.7233 Toll-fn:e From: Customer PO:
www.corporatefloors.com Andrew Campbell NOTICE OF INTENT TO AW
CME Builders&Engineers TRI ETHNIC COMMUNITY CENTER 34562
1505 Henderson Street 2950 ROOSEVELT AVE
Cleburne,TX 76031 FORT WORTH,TX 76106 1
COURTNEY KENORICK
0
Phone:(817)6414)406- Phone: Phone:
Cell: Cell: Cell: 10/21/2019
Pager: Pager: Pager. .
Fax: Fax: Fax: 10/30/2020
Description of Change Order Request.
RFI 25&26 REPAIRS @ RR 118 DUE TO WING WALL CHANGE
RFI 25&26 REPAIRS @ RR 118 DUE TO WING WALL CHANGE
ADD
Line Manufacturer Quantity Unit Price Extended
1 MATERIAL&LABOR FOR REPAIRS @ WING WALL-
CORPORATE FLOORS-REPAIRS-NA- 1.00 EA $1,100.00 $1,100.00
Total ADD $1,100.00
Total This Option $1,100.00
SIGNED.
CUSTOMER'S AUTHORRATION:
PRODIGY DESIGN & RENOVATION INC.
PO Box122139 Project: North Tri-Ethnic Community Center
Arlington,Texas 76012 Location: 29M Roosevelt Ave.,Fort Worth,TX
817.277.2468 phone
817.277.1005 fox Date: October 30,2020
roberNtprodigypoint.corn
Attn: Courtney Rogers
G.C. CME Builders
ADDITIONAL WORK
Ref email dated 10-30-2020 from Courtney Rogers
RFI 025-026 in Women 118
Scope of Work Reblockfill-repaint shortened cmu Wing wall/paint break metal wrap
Patch-repair-paint gyp ceiling
Materials $120
Labor 9 MH at$45 per hour $405
OH/Profit 10% $53
Total Amount $578
Exclusions: QualHicadons:
overtime letter hours O Per plans and spec
plaster or stucco(pair C Price firm 30 days
any work not noted on this proposal ❑ Bond included
G Labor
Material
Sales tax
G Addendum no. 1
G Addendum no.2
rl Addendum no.3
Cheyenne Commercial Interiors, Inc.
2501 Pecan Springs Rd.
Cleburne, TX 76031
817-980-1631
NORTH TRI ETHNIC COMMUNITY CENTER
Fort Worth, TX
We propose the following changes to our scope of work:
RFI 25 & RFI 26-wall changes TOTAL•$600.00
Warm regards,
MIKE MILLSAP
a.
CME SUMMARY A/E
COST PROPOSAL CONTRACTOR FX
OWNER
PROJECT Fort Worth Tri-Ethnic Community Center 1 of 1
Facility sheet
2020-002 CME Builders& Engineers, Inc
CSP Number Contractor Contract Modification
DATE: November 3, 2020 No: 11
DESCRIPTION Cost Estimate No.
Remove existing door and install new door using existing hardware.
SUMMARY
�X At an increase in the contract price of$1,136.70 (broken down in itemized detail below)
At no change in the contract price
ElAt reduction in contract price of (broken down in itemized detail below)
With an extension of days to the period of performance(Days dependent on when the additional work is approved)
Cost Detail
a. Direct Labor(attached supporting detailed estimate) $ 288.60
b. Insurance $ 101.98
c. Materials/Expenses $ 40.00
Subtotal $ 430.58
d. Overhead 5% $ 21.53
e. Profit 5% $ 21.53
f. Employment taxes under FICA and FUTA $ 37.16
General Contractor Total: $ 510.80
g. Subcontracts
Company Category of Work Amount
Chas F. Williams Door Supplier $ 569.00
Subcontract Total: $ 569.00
h. Contractor's 10% Commission on Total of Subcontracts $ 56.90
I. Contractor's Total $ 510.80
Total increase of4eefease to contract price: $J= 1,136.7011
\\Cmenas\cmenas\Current Projects\Fort Worth, TX North Tri-Ethnic Community Center\Cost Estimates\Cost Estimate
No. 11 - Plam Doors\Cost Estimate No. 11 - Plam Door.xls
CME SUMMARY A/E
COST PROPOSAL CONTRACTOR FX
OWNER
PROJECT Fort Worth Tri-Ethnic Community Center 1 of 1
Facility sheet
2020-002 CME Builders& Engineers, Inc
CSP Number Contractor Contract Modification
DATE: November 3, 2020 No: 11
DESCRIPTION Cost Estimate No.
Remove existing door and install new door using existing hardware.
SUMMARY
�X At an increase in the contract price of$1,136.70 (broken down in itemized detail below)
At no change in the contract price
ElAt reduction in contract price of (broken down in itemized detail below)
With an extension of days to the period of performance(Days dependent on when the additional work is approved)
Cost Detail
a. Direct Labor(attached supporting detailed estimate) $ 288.60
b. Insurance $ 101.98
c. Materials/Expenses $ 40.00
Subtotal $ 430.58
d. Overhead 5% $ 21.53
e. Profit 5% $ 21.53
f. Employment taxes under FICA and FUTA $ 37.16
General Contractor Total: $ 510.80
g. Subcontracts
Company Category of Work Amount
Chas F. Williams Door Supplier $ 569.00
Subcontract Total: $ 569.00
h. Contractor's 10% Commission on Total of Subcontracts $ 56.90
I. Contractor's Total $ 510.80
Total increase of4eefease to contract price: $J= 1,136.7011
\\Cmenas\cmenas\Current Projects\Fort Worth, TX North Tri-Ethnic Community Center\Cost Estimates\Cost Estimate
No. 11 - Plam Doors\Cost Estimate No. 11 - Plam Door.xls
CME BUILDERS & ENGINEERS, INC.
1505 E. Henderson Street
Cleburne, Texas 76031
C, ITE
CONSTRUCTION MANAGEMENT ENGINEERS
817-641-0406 Fax 817-645-8685
INVOICE
Date 11/3/2020 Inv No
To Fort Worth Tri-Ethnic Community Center Job No 26820
2950 Roosevelt Avenue
Fort Worth, TX
ITEM Amount TOTAL
Cash Advanced to: (Bills Attached)
1 day expenses $40.00
$40.00
Job Payroll & Expense for Week Ending
OFFICE
1 days of Superintendent labor by CME Builders & Engineers, Inc. CODE
Total Gross Payroll $288.60 1901
Soc Sec/Medicare .0765 $22.07 1901
State Employment Tax .0747 S21.55 2231
FUTA Tax .0541 $15.61 2221
WC/GEN LIA & VAC. .2769 $79.91 2271
TOTAL .4361 $427.74
TOTAL $467.74
CME BUILDERS & ENGINEERS, INC.
1505 E. Henderson Street
Cleburne, Texas 76031
C, ITE
CONSTRUCTION MANAGEMENT ENGINEERS
817-641-0406 Fax 817-645-8685
INVOICE
Date 11/3/2020 Inv No
To Fort Worth Tri-Ethnic Community Center Job No 26820
2950 Roosevelt Avenue
Fort Worth, TX
ITEM Amount TOTAL
Cash Advanced to: (Bills Attached)
1 day expenses $40.00
$40.00
Job Payroll & Expense for Week Ending
OFFICE
1 days of Superintendent labor by CME Builders & Engineers, Inc. CODE
Total Gross Payroll $288.60 1901
Soc Sec/Medicare .0765 $22.07 1901
State Employment Tax .0747 S21.55 2231
FUTA Tax .0541 $15.61 2221
WC/GEN LIA & VAC. .2769 $79.91 2271
TOTAL .4361 $427.74
TOTAL $467.74
Courtney Rogers
From: Laura Nickell
Sent: Tuesday, November 3, 2020 8:23 AM
To: Courtney Rogers
Subject: FW:Additional P-lam Door
From: Michael Young [mailto:michael.young@chasfwilliams.com]
Sent: Monday, November 02, 2020 2:28 PM
To: Robert Carroll
Subject: Additional P-lam Door
Robert,
1 ea.—3'0 x7'0 flush plastic laminated wood door*
*Wilsonart 8214K-28"Phantom Charcoal" laminate.
Total =$569.00* (no tax)
*2 week lead time.
Thanks,
Michael Young
scies Williams
328 Lip St
fart Wenh TX 76104
i
CME SUMMARY A/E ❑
COST PROPOSAL CONTRACTOR Q
OWNER ❑
PROJECT Fort Worth Tri-Ethnic Community Center 1 of 1
Facility sheet
2020-002 CME Builders&Engineers, Inc.
CSP Number Contractor Contract Modification
DATE: November 9,2020 No: 13
Cost Estimate No.
DESCRIPTION
Revision 10 Changes- Urinal Screens
Revision 4 Changes-Soap Dispensers
SUMMARY
EKAt an increase in the contract price of$3,223.22 (broken down in itemized detail below)
❑ At no change in the contract price
❑ At reduction in contract price of (broken down in itemized detail below)
EKWith an extension of 5 days to the period of performance(Days dependent on when the additional work is approved)
Cost Detail
a. Direct Labor(attached supporting detailed estimate) $ 144.30
b. Insurance $ 51.00
c. Materials/Expenses $ 20.00
Subtotal $ 215.30
d. Overhead 5% $ 10.77
e. Profit 5% $ 10.77
f. Employment taxes under FICA and FUTA $ 18.59
General Contractor Total: $ 255.42
g. Subcontracts
Company Category of Work Amount
Chas F.Williams Urinal Screens $ 2,528.00
Chas F.Williams Soap Dispensers $ 170.00
Subcontract Total: $ 2,698.00
h. Contractor's 10% Commission on Total of Subcontracts $ 269.80
I. Contractor's Total $ 255.42
Total increase-Tease to contract price: $ 3,223.22
X:\Facilities Management\Fac_Management\Milam\North Tri-Ethnic CC ADA Remodel\Contractors Change
Proposals\Cost Proposal No. 13- Urinal Screens-Soap Dispensers
Chas. F* WiMams Co., Inc.
BUILDING SPECIALITES
328 Lipscomb P.O.Box 1724 Fort Worth,Texas 76101 (817)332-6363 (817)429-9320 fax
Serving the Building Industry Since 1932
PROPOSAL
To: CME Builders Date: 11/9/20
Attn: Robert Carroll Job Name North Tri-Ethnic Community Center
Fort Worth, TX
Division 10 -Change Order REVISED
Solid Plastic HDPE Screens by Scranton
4-24" x 55" wall hung urinal screens
Solid Plastic Screens=$2,528.00* (no tax)
*Furnished&installed by Chas.F.Williams. Blocking in walls by others.
(which is an actual percup�entage rate of 18%simple in-Yvterest)will be added automaon 0tically a TAX NOT INCLUDED UNLESS OTHERWISE NOTED
We reserve the right to repossess any material not paid for under the terns of this
contract. TERMS OF PAYMENT-Payment in full due the loth of the month following
date of invoice.
Accepted by: Chas. F. Williams Co., lnc.
Date: M ichael Young
CME SUMMARY A/E ❑
COST PROPOSAL CONTRACTOR Q
OWNER ❑
PROJECT Fort Worth Tri-Ethnic Community Center 1 of 1
Facility sheet
2020-002 CME Builders&Engineers, Inc.
CSP Number Contractor Contract Modification
DATE: November 9,2020 No: 13
Cost Estimate No.
DESCRIPTION
Revision 10 Changes- Urinal Screens
Revision 4 Changes-Soap Dispensers
SUMMARY
EKAt an increase in the contract price of$3,223.22 (broken down in itemized detail below)
❑ At no change in the contract price
❑ At reduction in contract price of (broken down in itemized detail below)
EKWith an extension of 5 days to the period of performance(Days dependent on when the additional work is approved)
Cost Detail
a. Direct Labor(attached supporting detailed estimate) $ 144.30
b. Insurance $ 51.00
c. Materials/Expenses $ 20.00
Subtotal $ 215.30
d. Overhead 5% $ 10.77
e. Profit 5% $ 10.77
f. Employment taxes under FICA and FUTA $ 18.59
General Contractor Total: $ 255.42
g. Subcontracts
Company Category of Work Amount
Chas F.Williams Urinal Screens $ 2,528.00
Chas F.Williams Soap Dispensers $ 170.00
Subcontract Total: $ 2,698.00
h. Contractor's 10% Commission on Total of Subcontracts $ 269.80
I. Contractor's Total $ 255.42
Total increase-Tease to contract price: $ 3,223.22
X:\Facilities Management\Fac_Management\Milam\North Tri-Ethnic CC ADA Remodel\Contractors Change
Proposals\Cost Proposal No. 13- Urinal Screens-Soap Dispensers
CME SUMMARY A/E ❑
COST PROPOSAL CONTRACTOR Q
OWNER ❑
PROJECT Fort Worth Tri-Ethnic Community Center 1 of 1
Facility sheet
2020-002 CME Builders&Engineers, Inc.
CSP Number Contractor Contract Modification
DATE: November 9,2020 No: 13
Cost Estimate No.
DESCRIPTION
Revision 10 Changes- Urinal Screens
Revision 4 Changes-Soap Dispensers
SUMMARY
EKAt an increase in the contract price of$3,223.22 (broken down in itemized detail below)
❑ At no change in the contract price
❑ At reduction in contract price of (broken down in itemized detail below)
EKWith an extension of 5 days to the period of performance(Days dependent on when the additional work is approved)
Cost Detail
a. Direct Labor(attached supporting detailed estimate) $ 144.30
b. Insurance $ 51.00
c. Materials/Expenses $ 20.00
Subtotal $ 215.30
d. Overhead 5% $ 10.77
e. Profit 5% $ 10.77
f. Employment taxes under FICA and FUTA $ 18.59
General Contractor Total: $ 255.42
g. Subcontracts
Company Category of Work Amount
Chas F.Williams Urinal Screens $ 2,528.00
Chas F.Williams Soap Dispensers $ 170.00
Subcontract Total: $ 2,698.00
h. Contractor's 10% Commission on Total of Subcontracts $ 269.80
I. Contractor's Total $ 255.42
Total increase-Tease to contract price: $ 3,223.22
X:\Facilities Management\Fac_Management\Milam\North Tri-Ethnic CC ADA Remodel\Contractors Change
Proposals\Cost Proposal No. 13- Urinal Screens-Soap Dispensers
Chas. F* WiMams Co., Inc.
BUILDING SPECIALITES
328 Lipscomb P.O.Box 1724 Fort Worth,Texas 76101 (817)332-6363 (817)429-9320 fax
Serving the Building Industry Since 1932
PROPOSAL
To: CME Builders Date: 11/9/20
Attn: Robert Carroll Job Name North Tri-Ethnic Community Center
Fort Worth, TX
Division 10 -Change Order REVISED
Solid Plastic HDPE Screens by Scranton
4-24" x 55" wall hung urinal screens
Solid Plastic Screens=$2,528.00* (no tax)
*Furnished&installed by Chas.F.Williams. Blocking in walls by others.
(which is an actual percup�entage rate of 18%simple in-Yvterest)will be added automaon 0tically a TAX NOT INCLUDED UNLESS OTHERWISE NOTED
We reserve the right to repossess any material not paid for under the terns of this
contract. TERMS OF PAYMENT-Payment in full due the loth of the month following
date of invoice.
Accepted by: Chas. F. Williams Co., lnc.
Date: M ichael Young