HomeMy WebLinkAboutContract 54099-CO1 FORTWORTH, City of Fort Worth CSC NO. 54099-COI
Change Order Request
Projecl Name VCWRF Grit Removal Facility City Sec I/ 54099
Client Project Ills)[ Village Creek Water Reclamation Facility(VCWRF)Sludge Thickening Improvements(CO2647)
Project The project consist of a new Grit Facility with 0 slacked tray vordex grit removal units,structural modifications to existing Headwork Facility,modificataions
Descdption to Odor Control Biofiller System,and EleclricaVHVAC/Plumbing/Yard Piping
Contractor Crescent Constructors,Inc. Change Order#1 1 Dale 12/15/2020
City Project Mgr. Fadda Goderya 4 City Inspectorl Kevin Sidebottom/ScottAllwood(FNI)
Dept. Water Department Contract Time
Totals (CD)
Original Contract Amount $25,797,000.00 $25,797,000.00 730
Extras to Date $0.00 0
Credits to Date $0.00 0
Pending Change Orders(in M&C Process) $0.00 p
Contract Cost to Date $25,797,000.00 $25,797,000.00 730
Amount of Proposed Change Order $19,965.00 $19,965.OD 0
Revised ContractAmount $25,816,965.00 $25,816,965.00 730
Original Funds Available for Change Orders $332,463.00 $332,463.00
Remaining Funds Available for this CO $332,463.00 $332,463.00
Additional Funding(if necessary) $0.00 $0.00
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.08%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $32,246,250.00
JUSTIFICATION(REASONS)FOR CHANGE ORDER
This Change Order II 01 is for Iwo(2)Proposed Contract Modifications(PCMs),as identified in the attached sheet.This change order does not include any lime extension for
the contract.The Staff has reviewed the related PCMs and recommends approval.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
Contractor's Company Name Contractor Nama Contract Sl nature Dale
Crescent Constructors,Inc. Ran Glanz
Ins eclor/lns ection Supervisor i Dale, . Project and Contract Complian64ithagot. Date
Kevin Sideboltam or Scott Atwood,FNI J'1�11 0:'. `s !.' 12-22.2020
Program Manager Dale Senior Capital Project Officer Date
Farida Gode a 12/23/20
Assistan101feclor(Dept) Dale, Director,Contracting Department(Dept) Date
Tony Sholola To o Chris Harder 46— —1- OK28'2020
AssIslant City Attorney Dale lAssislantCil Manager Dale
Dec28,2020 zow panaBur hdoff `Tg1tw�' De 28,2020
CouncilAction,if required)
M&C Number NIA M&C Date Approved NIA
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
FUtt v NVrlitl 11 City of Fort Worth
I-- Change Order Additions
Project Name VCWRF Grit Removal Facility City Sec# 54099
Client Project# Village Creek Water Reclamadon Facility(VCWRF)Sludge Thickening Improvements(CO2647)
Contractor Crescent Constructors,Inc. PM Farida Goderya Inspector
Change Order Submittal# F-7-1 Date 126/2020
ADDITIONS
PITEM DESCRIPTION DEPT ty Unit Unit Cost Total
Line psize Water epartment 77 1,
2 PCM02-Fiber Connectors Water Department 1.00000000 LS $2,765.00
Water Department $19,965.00
Sub Total Additions $19,965.00
Change Order Additions Page 1 of 1
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Farida Goderya, PhD, PE
Name of Employee
Senior Project Manager
Title
ATTEST: �F �Rl�a���
�voa o
Mary J.Kayser �p *00
o° °o
City Secretary ��
� a11�aEXASob
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
PROPOSED CONTRACT MODIFICATION (PCM
OWNER: CITY OF FORT WORTH, TEXAS PROJECT NO.
PROJECT:VCWRF GRIT REMOVAL PROJECT OWNER: 100075
CONTRACTOR: CRESCENT CONSTRUCTORS
ENGINEER: CDM SMITH INC. ENGINEER: 0515-219463
ENGINEER'S CONTACT Amy Robinson P.E. PCM NO. 001
NOTIFICATION TO CONTRACTOR:
WE ARE CONSIDERING MAKING THE CHANGE TO THE CONTRACT DESCRIBED IN THE ATTACHED
MATERIALS AND REQUEST THAT YOU TAKE THE FOLLOWING ACTION:
❑ NOTIFY US THAT YOU CONCUR THAT THIS CHANGE DOES NOT REQUIRE A CHANGE IN CONTRACT
TIME OR AMOUNT. A FIELD ORDER WILL BE ISSUED.
✓ SUBMIT A PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED SCHEDULE FOR
PERFORMING THE DESCRIBED CHANGE.
❑ A CHANGE ORDER WILL BE ISSUED FOR PAYMENT AT THE UNIT PRICE BID
❑ PROCEED WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE CONTRACT.
BY: Amy R. Robinson, P.E., BCEE DATE: October 13, 2020
DESCRIPTION OF PROPOSED CHANGE: ✓ DESCRIBED HEREIN ✓ SEE ATTACHED
The following are changes to the Contract Drawings.
1. Provide price proposal to change (2) 12" DS-HDPE DR-11 pipe and fittings with the
following options:
a. (2) 14" DS-HDPE DR-11
b. (2) 16" DS-HDPE DR-11
CONTRACTOR'S RESPONSE:
WE RESPOND TO YOUR REQUEST AS FOLLOWS:
❑ WE CONCUR THAT THIS IS A NO COST OR TIME CHANGE, ISSUE FIELD ORDER.
X WE SUBMIT THE ATTACHED PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED
SCHEDULE FOR PERFORMING THE DESCRIBED CHANGE.
❑ WE ARE PROCEEDING WITH THE CHANGE AT THE UNIT PRICE BID
❑ WE ARE PROCEEDING WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE
CONTRACT.
BY: Ryan Glanz, Crescent Constructors DATE: 10/26/2020
ACTION TAKEN:
❑ PROPOSED CONTRACT MODIFICATION REJECTED. CONTRACTOR NOTIFIED NOT TO PROCEED.
BY: DATE:
❑ FIELD ORDER ISSUED: NO. DATE: BY:
X CHANGE ORDER ISSUED: NO. 1 DATE: 10/26/2020 BY: Amy Robinson P.E.
Proceed with upsizing 12" DS HDPE to 14" DS HDPE for $17,200. Keep HDPE pipe and
fittings with same manufacturer.
2560 Technology Drive#400
Plano,TX 75074
CONTRACT MODIFICATION REQUEST: PCM-01 - 14"
PROJECT: VILLAGE CREEK GRIT FACILITY DATE: 10/26/20
PROJECT NO. 100075
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdoum of cost SHALL be attached.
Work shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
PCM 01 Modifications to Upsize 12" DS-HDPE Line:
(1) Change 12" DS-HDPE Line to 14" Line =$17,200
(2) Change 12" DS-HDPE Line to 16" Line =$40,200
(3) If HDPE fittings can be fabricated from different vender than pipe material (33.05.33-1.5A)
an approximate$500-$750 discount can be given
*** Need material size approval and submittal approval to schedule material deliveries to the site
and the effect to the schedule timeline
TOTAL AMOUNT 1 $ 17,200
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order,the time of completion will be:
Increased By *** Calendar Days
Decreased
Unchanged
ACCEPTED
City of Fort Worth Date
❑ REJECTED
CHANGE ORDER SUMMARY
Front Sheet
VILLAGE CREEK GRIT FACILITY
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST# PCM-01 -14" Job#: 2020-02
Description Labor Material Equipment Subcontract Total
DIRECT COSTS 460 13,816 - 14,276
LABOR BURDEN&FRINGES 55% 253 253
SUBTOTALS 713 13,816 14,529
CONTRACTOR MARKUP 15% 2,179
CONTRACTOR MARKUP 5% SUBS -
BONDS&INSURANCE 3% 501
(10)
TOTALI 17,200
CLARIFICATIONS:
1
2
3
4
2560 Technology Drive#400
Plano, TX 75074
CONTRACT MODIFICATION REQUEST: PCM-02rev01
PROJECT: VILLAGE CREEK GRIT FACILITY DATE: 11/12/20
PROJECT NO. 100075
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: FARIDA GODERYA
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
Work shall not commence until authorized by the Obl"NER.
Description of the Proposed Change & Clarifications
Pricing for the following
PCM 02 Change Comm Fiber Termination Connectors:
(1) Order New Connectors and Install Fused Connectors =$ 2,765
TOTAL AMOUNT $ 2,765
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased By 0 Calendar Days
Decreased
Unchanged
0 ACCEPTED Amy Robinson, CDM Smith November 13, 2020
City of Fort Worth Date
❑ REJECTED
PROPOSED CONTRACT MODIFICATION (PCM)
OWNER: CITY OF FORT WORTH, TEXAS PROJECT NO.
PROJECT:VCWRF GRIT REMOVAL PROJECT OWNER: 100075
CONTRACTOR: CRESCENT CONSTRUCTORS
ENGINEER: CDM SMITH INC. ENGINEER: 0515-219463
ENGINEER'S CONTACT Amy Robinson, P.E. PCM NO. 002 Rev 1
NOTIFICATION TO CONTRACTOR:
WE ARE CONSIDERING MAKING THE CHANGE TO THE CONTRACT DESCRIBED IN THE ATTACHED
MATERIALS AND REQUEST THAT YOU TAKE THE FOLLOWING ACTION:
❑ NOTIFY US THAT YOU CONCUR THAT THIS CHANGE DOES NOT REQUIRE A CHANGE IN CONTRACT
TIME OR AMOUNT. A FIELD ORDER WILL BE ISSUED.
✓ SUBMIT A PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED SCHEDULE FOR
PERFORMING THE DESCRIBED CHANGE.
❑ A CHANGE ORDER WILL BE ISSUED FOR PAYMENT AT THE UNIT PRICE BID
❑ PROCEED WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE CONTRACT.
BY: Amy R. Robinson, P.E., BCEE DATE: November 2, 2020
DESCRIPTION OF PROPOSED CHANGE: ✓ DESCRIBED HEREIN ✓ SEE ATTACHED
The following are changes to the Contract Drawings.
In lieu of using the Unicam connectors approved under submittal 47, please provide cost
proposal and schedule impact (if any) for providing pigtail fused splices for fiber
connection/termination.
CONTRACTOR'S RESPONSE:
WE RESPOND TO YOUR REQUEST AS FOLLOWS:
❑ WE CONCUR THAT THIS IS A NO COST OR TIME CHANGE, ISSUE FIELD ORDER.
✓ WE SUBMIT THE ATTACHED PRICE PROPOSAL WITH DETAILED COST BREAKDOWN AND REVISED
SCHEDULE FOR PERFORMING THE DESCRIBED CHANGE.
❑ WE ARE PROCEEDING WITH THE CHANGE AT THE UNIT PRICE BID
❑ WE ARE PROCEEDING WITH THE CHANGE UNDER THE TIME AND MATERIALS PROVISIONS OF THE
CONTRACT.
BY: Ryan Glanz, Crescent Constructors DATE: November 12, 2020
ACTION TAKEN:
❑ PROPOSED CONTRACT MODIFICATION REJECTED. CONTRACTOR NOTIFIED NOT TO PROCEED.
BY: DATE:
❑ FIELD ORDER ISSUED: NO. DATE: BY:
✓ CHANGE ORDER ISSUED: NO. 1 DATE: November 13, 2020 BY: Amy Robinson, P.E.. BCEE
PCM 002 approved for $2,765 and 0 days.
CHANGE ORDER SUMMARY
Front Sheet
VILLAGE CREEK GRIT FACILITY
CHANGE DESCRIPTION:
CONTRACT MODIFICATION REQUEST# PCM-02rev01 Job#: 2020-02
Description Labor Material Equipment Subcontract Total
DIRECT COSTS - - - 2,557 2,657
LABOR BURDEN&FRINGES 55% - -
SUBTOTALS 2,557 2,557
CONTRACTOR MARKUP 15% -
CONTRACTOR MARKUP 5% SUBS 128
BONDS&INSURANCE 3% 81
TOTALI 2,765
CLARIFICATIONS:
1
2
3
4