This AGREEMENT is between the City of Fort Worth, a Texas home -rule
municipality (the "CITY"), and A.N.A. Consultants, LLC, authorized to do business in
Texas, (the "ENGINEER"), for a PROJECT generally described as: 2014 Fiscal Year
Storm Water On -Call Services.
Article I
Scope of Services
A. The Scope of Services is set forth in Attachment A.
Article II
Compensation
A. The ENGINEER's compensation shall be in the amount of $47,500 (forty
seven thousand five hundred dollars) as set forth in Attachment B.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
(3)
Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 1 of 16
OFFICIAL RECORD
CITY UCRETARY
Pt WORTH, TX
R 1 V 20?i,'?
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5)
If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B Standard of Care
The standard of care applicable to the ENGINEER s services will be the
degree of skill and diligence normally employed in the State of Texas by
professional engineers or consultants performing the same or similar
services at the time such services are performed.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 2 of 16
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER
D Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires* provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a, construction site,
whether as on -site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general if the work on the PROJECT is being performed in a manner
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
the agreement between CITY and ENGINEER be construed as requiring
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 3 of 16
(3)
ENGINEER to make exhaustive or continuous on -site inspections to
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT If the ENGINEER makes on -site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or pnce of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 4 of 16
matters at issue between the CITY and the construction contractor that
affect the amount that should be paid.
H. Record Drawings
Record drawings if required, will be prepared, in part on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity Ordinance No.
20020-12-2011, as amended, the City has goals for the participation of
minority business enterprises and/or small business enterprises in City
contracts. Engineer acknowledges the MBE and SBE goals established for
this contract and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract ENGINEER agrees that the CITY shall have access dunng normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropnate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 5 of 16
(3)
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1)
ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
u mbrella insurance with a limit of not less than $1,000,000 00 per each
o ccurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an insured under the CGL, using
ISO additional insured endorsement or a substitute providing
equivalent coverage, and under the commercial umbrella, if any
This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the
CITY. The Commercial General Liability insurance policy shall
have no exclusions by endorsements that would alter or nullify:
premises/operations, products/completed operations, contractual,
personal injury, or advertizing injury, which are normally contained
within the policy, unless the CITY approves such exclusions in
writing.
ii ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary commercial umbrella liability insurance with a limit of
n ot Tess than $1 000,000 each accident. Such insurance shall cover
liability arising out of 'any auto', including owned, hired, and non -owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non -owned is
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 6of16
acceptable.
i ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation —ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability — the ENGINEER shall maintain professional
liability, a claims -made policy, with a minimum of $1,000,000.00 per
claim and aggregate. The policy shall contain a retroactive date prior to
the date of the contract or the first date of services to be performed,
whichever is earlier. Coverage shall be maintained for a period of 5 years
following the completion of the contract. An annual certificate of
insurance specifically referencing this project shall be submitted to the
CITY for each year following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be delivered to the CITY prior to ENGINEER
proceeding with the PROJECT.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, as its interests may appear. The term CITY shall
include its employees, officers, officials, agents, and volunteers as
respects the contracted services.
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 7 of 16
d. Any failure on part of the CITY to request required insurance
documentation shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000 00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first -dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims -made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims -made.
k. Coverages, whether written on an occurrence or claims -made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
final payments.
The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 8 of 16
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in wnting of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required at its own cost and expense. However, if design
changes are required due to the changes in the permitting authonties'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 9 of 16
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City -Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY s personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services the CITY will obtain,
arrange and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land easements, rights -
of -way, and access necessary for the ENGINEER's services or PROJECT
construction.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 10 of 16
D Timely Review
The CITY will examine the ENGINEER's studies, reports sketches,
drawings, specifications, proposals, and other documents; obtain advice of
an attorney insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV E regarding the ENGINEER's Personnel at Construction Site, and
provisions providing contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third -Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 11 of 16
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
of any undertaking by the ENGINEER "
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third -party beneficianes.
(3)
The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third -party beneficiary rights under this Agreement.
(4) Nothing contained in this section V.H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER
CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY will ensure that Builders Risk/Installation insurance is maintained
at the replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3)
The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 12 of 16
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B Reuse of Project Documents
All designs, drawings, specifications documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated only by the City for convenience on
30 days' written notice. This AGREEMENT may be terminated by either the
CITY or the ENGINEER for cause if either party fails substantially to perform
through no fault of the other and does not commence correction of such
nonperformance with in 5 days of written notice and diligently complete the
correction thereafter.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 13 of 16
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
c.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses The
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify, hold harmless, and defend the CITY
against liability for any damage caused by or resulting from an act of
n egligence, intentional tort, intellectual property Infringement, or
failure to pay a subcontractor or supplier committed by the ENGINEER
o r ENGINEER's agent, consultant under contract, or another entity
over which the ENGINEER exercises control.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party
Interpretation
Limitations on liability and indemnities in this AGREEMENT are business
u nderstandings between the parties and shall apply to all the different
theones of recovery, including breach of contract or warranty tort including
n egligence, strict or statutory liability, or any other cause of action, except for
willful misconduct or gross negligence for limitations of liability and sole
negligence for indemnification. Parties mean the CITY and the ENGINEER,
and their officers, employees, agents, and subcontractors.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 14 of 16
I. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
J. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal or unenforceable in any respect, such invalidity,
illegality or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein Articles V.F., VI.B. VI.D., VLF.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
K. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
Article VII
Attachments, Schedules, and Signatures
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, supersedes all prior wntten or oral understandings, and may only be
changed by a wntten amendment executed by both parties. The following attachments
and schedules are hereby made a part of this AGREEMENT:
Attachment A - Scope of Services
Attachment B — Compensation
Attachment C - Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 15 of 16
Executed and effective this the ',,ay of
BY:
CITY OF FORT WORTH
flnia.mck 64A
Fernando Costa
Assistant City Manager
Date: I/30,/14-
APPROVAL RECOMMENDED:
GGI
By: / U) N
Doug W. iersig, PhD., P.E.
Directo , Transportation a Public
Works
20 fir
BY:
ENGINEER
A.N.A. Consultants, LLC
ark`itga�d, P.E.
Vice President
Date: s)i /i � lZo l
APPROVED AS TO FORM AND MC No.: N/A
LEGALITY
M&C Date: N/A
B
Douglas W. Black
Assistant City Attorney
ATTEST:
Mary J. Kayser
City Secretary
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 1/28/2013
Page 16 of 16
OFFICIAL RECORD
CITY SECRrtARY
Inc, WORTh, TX
ATTACHMENT "A"
Scope for Engineering Design Related Services for Storm Water Improvements Projects
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project. Under this scope, ' ENGINEER"
is expanded to include any sub -consultant, including surveyor, employed or contracted by
the ENGINEER
OBJECTIVE
To enter in to an agreement for work order based on -call design services for the City of Fort
Worth TPW Stormwater Management Group.
Task 1.
Task 2.
Task 3.
Task 4.
Task 5.
Task 6.
WORK TO BE PERFORMED
Design Management
Work Order Based Preliminary Design
Final Design
Construction Phase Services
ROW/Easement Services
Survey Services
TASK 1. DESIGN MANAGEMENT.
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources ENGINEER will manage change,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary to make progress
on the work.
1.2.
•
•
•
•
•
•
•
Managing the Team
Lead, manage and direct design team activities
Ensure quality control is practiced in performance of the work
Communicate internally among team members
Task and allocate team resources
Communications and Reporting
Attend a pre -design project kickoff/chartering meeting for each work order with CITY
staff to confirm and clarify scope, understand CITY objectives, and ensure
economical and functional designs that meet CITY requirements.
P repare estimated task hours for each work order and submit to CITY as a not -to -
exceed budget.
P repare invoices, in accordance with Attachment B to this Standard Agreement and
submit at the completion of the work order in the format requested by the CITY
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 1 of 9
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design.
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs ENGINEER shall work with regulatory
authorities to obtain approval of the designs and make changes necessary to meet
their requirements, as part of the design scope.
Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub -consultants shall carry readily visible
information identifying the name of the company and the company representative.
DELIVERABLES
A. Meeting summaries with action items
B. Work order based invoices
TASK 2. WORK ORDER BASED PRELIMINARY DESIGN
•
The purpose of the work order based design is for the ENGINEER to identify, develop,
communicate through the defined deliverables, and recommend the design concept that
successfully addresses the design problem, and to obtain the CITY's endorsement of this
concept. ENGINEER will utilize concepts and criteria contained in the current CITY — iSWM
Criteria Manual for Site Development and Construction for conceptual planning and design.
The services to be performed by the ENGINEER hereunder shall include storm drainage
engineering design tasks, as specified by the CITY. The services hereunder may be
requested by the CITY on a project -to -project basis, which will normally require one (1) day
to several months to complete.
The ENGINEER shall be given written authorization to proceed with the requested services
along with a PROJECT INFORMATION AND INSTRUCTION PACKET which shall contain
the scope of services to be provided. Each PROJECT INFORMATION AND INSTRUCTION
PACKET issued to ENGINEER shall become a part of this agreement, and it will be the
ENGINEER'S responsibility to make certain that completed data is furnished to the CITY IN
THE EXACT FORMAT REQUESTED IN THE INFORMATION AND INSTRUCTION
PACKET, and that copies of the original field data are submitted to the CITY for inclusion
into the permanent project files.
Time is of the essence, therefore the ENGINEER agrees to begin work on any requested
services within five (5) working days after the receipt of the written authorization to begin
work, and work authonzed hereunder shall be completed within a time period do be
specified in writing at the time the ENGINEER is authorized to begin work. The ENGINEER
agrees that it may be requested to perform services simultaneously on one (1) or more
projects at any given time, and that the foregoing time limitations will apply to each individual
request for services which the ENGINEER'S forces are working.
ENGINEER will develop the work order based design of the infrastructure as follows.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 2 of 9
2.1. Data Collection
In addition to data obtained from the CITY, ENGINEER will research and make
efforts to obtain pertinent information to aid in coordination of the proposed
improvements with any planned future improvements that may influence the
project ENGINEER will also identify and seek to obtain data for existing
conditions that may impact the project including; utilities, agencies (such as
TxDOT and railroads), CITY Master Plans, CITY drainage complaint files,
existing applicable drainage studies, FEMA floodplain and floodway maps,
existing models of project area (if any) and property ownership as available from
the Tax Assessor s office.
2.2. Drainage Computations — If Necessary
A ENGINEER will delineate the watershed based on contour data and field
verification and document existing street, right-of-way and storm drain capacities
for the subject site. A drainage area map will be drawn at maximum 1" = 200'
scale from available 2-foot contour data with the contours labeled. Data source
and year will be provided by the CITY Calculations regarding street and right-of-
way capacities and design discharges (5-year and 100-year frequencies) at
selected critical locations will be provided. Other frequencies as required by
iSWM criteria may be appropriate for outfalls and sensitive locations. Capacities
of existing storm drain will be calculated and shown. All calculations shall
conform to CITY criteria delineated in the current CITY iSWM Criteria Manual for
Site Development and Construction. All locations in the project area where 100-
year runoff exceeds available storm drain and right-of-way capacities shall be
clearly identified. The ENGINEER's responsibility includes recommendations for
improvements of the existing system as deemed reasonable and consistent with
CITY standards.
2.3. Development of Preliminary Design Drawings shall include the following:
• Cover Sheet
• Drainage area maps showing proposed improvements with drainage calculations
and hydraulic computations in accordance with the current iSWM Critena Manual
for Site Development and Construction. — If necessary
• A Project Control Sheet, showing all Control Points used or set while gathering
data. Generally on a scale of not less than 1:400. The following information shall
be indicated for each Control Point: Identified (existing City Monument #8901, PK
Nail, 5/8" Iron Rod); X Y and Z Coordinates, in an identified coordinate system,
and a referred bearing base Z coordinate on City Datum only; descriptive location
(i e set in the centerline of the inlet in the South curb line of North Side Drive at the
East end of radius at the Southeast corner of North Side Drive and North Main
Street). — If necessary
• Overall project easement layout sheet(s). — If necessary
• Plan and profile drawings of proposed storm water improvements, including
existing lot layout with property ownership, streets, curb lines, driveways,
medians (if applicable) sidewalks, existing and proposed water and sanitary
sewer mains existing utilities gathered during the SUE and existing utility
easements within the project limits.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 3 of 9
• The ENGINEER will prepare standard and special detail sheets that are not
already included in the City's standard details. These may include connection
details between various parts of the project, tunneling details, boring and jacking
details, waterline relocations, details unique to the construction of the project,
trenchless details, and special service lateral reconnections.
ASSUMPTIONS
•
•
All storm water calculations and design shall conform to the current CITY iSWM
Criteria Manual for Site Development and Construction.
1 electronic pdf copy and three (3) copies of the design package will be
delivered. Drawings will be half size (11" x 17").
• All submitted documents and checklists will also be uploaded to the designated
project folder in Buzzsaw
• ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design Package.
DELIVERABLES
A. Preliminary Design drawings
B Estimates of probable construction cost
TASK 3. FINAL CONSTRUCTION DOCUMENTS (100 PERCENT).
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows
• The ENGINEER shall submit a final design estimate of probable construction cost with
the final design plans submitted. This estimate shall use ONLY standard CITY bid items.
• The ENGINEER shall submit Final Plans (100%) to the CITY Each plan sheet shall be
stamped, dated, and signed by the ENGINEER registered in State of Texas.
ASSUMPTIONS
• All storm water calculations and design shall conform to the current CITY iSWM Criteria
Manual for Site Development and Construction.
• 1 electronic pdf copy and seven (7) copies of the design package will be delivered.
Drawings will be half size (11" x 17").
DELIVERABLES
A. 100% construction plans.
B. Detailed estimates of probable construction cost for the authorized construction project,
including summaries of bid items and quantities using the CITY's standard bid items and
format
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 4 of 9
TASK 4. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
4.1 Construction Support
• The ENGINEER shall visit the project site at requested intervals as construction
proceeds to observe and report on progress.
• The ENGINEER shall review shop drawings, samples and other submittals
submitted by the contractor for general conformance with the design concepts and
general compliance with the requirements of the contract for construction. Such
review shall not relieve the Contractor from its responsibility for performance in
accordance with the contract for construction, nor is such review a guarantee that
the work covered by the shop drawings, samples and submittals is free of errors,
inconsistencies or omissions.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents review change orders, and make
recommendations as to the acceptability of the work.
• The ENGINEER shall attend the `Final" project walk through and assist with
preparation of final punch list.
4.2 Record Drawings
• The ENGINEER shall prepare record drawings from information provided by the
CITY depicting any changes made to the Final Drawings during construction.
The following information shall be provided by the CITY:
o As -Built Survey
o Red -Line Markups from the Contractor
o Red -Line Markups from City Inspector
o Copies of Approved Change Orders
o Approved Substitutions
The ENGINEER shall modify the Final Drawings electronically and shall place a
stamp on the plans indicating that they represent Record Drawings of the project
as constructed The stamp shall be signed and dated by the ENGINEER and
shall be placed on each plan sheet, whether there are any revisions on the sheet
o r not. Each sheet shall clearly indicate all changes which apply to that sheet by
clouding and numbering, or other suitable means.
• The following disclaimer shall be included with the Record Drawing stamp:
o These Record Drawings were prepared using information provided by
others and represent the as constructed conditions to the extent that
documented changes were provided for recording. The ENGINEER
assumes no liability for undocumented changes and certifies only that the
documented changes are accurately depicted on these drawings.
• The ENGINEER shall submit a set of sealed Final Drawings, modified and
stamped as Record Drawings, electronically for record storage. The ENGINEER
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 5 of 9
•
may keep copies of the information provided by the CITY for their files, but all
original red lined drawings shall be returned to the CITY with the electronic copy.
Record Drawings shall also be submitted as an Adobe Acrobat PDF format
(version 6.0 or higher) file and DWF format Each PDF and DWF file shall
contain all associated sheets of the particular plan set. Singular PDF and DWF
files for each sheet of a plan set will not be accepted. PDF and DWF files
shall conform to naming conventions as follows:
I. TPW file name example — "W-1956_org47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "_org' designating the file is
of an original plan set, ` 47" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667_org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36' shall be the total number
of sheets in this file.
Example: X-12755_orgl8.pdf
Both PDF and DWF files shall be uploaded to the project's Record Drawing folder
in Buzzsaw.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number (817) 392-8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
ASSUMPTIONS
• Weekly site visits are assumed.
DELIVERABLES
B. Response to Contractor's Request for Information
C. Review of Change Orders
D. Review of shop drawings
E Final Punch List items
F. Record Drawings
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 6 of 9
TASK 5. ROW/EASEMENT SERVICES — IF NECESSARY.
ENGINEER will support and perform activities related to ROW and easements as outlined
below, per scoping direction and guidance from the CITY's Project Manager.
5.1. Right -of -Way Research
• The ENGINEER shall determine rights -of -way and easement needs for
construction of the project. Required temporary and permanent easements will
be identified based on available information and recommendations will be made
for approval by the CITY.
5.2 Right-of-Way/Easement Preparation and Submittal.
• The ENGINEER shall prepare documents to be used to obtain right-of-way and
permanent and/or temporary easements required to construct the improvements.
• The documentation shall be provided in conformance with the checklists and
templates available on the CITY's Buzzsaw site.
5.3 Temporary Right of Entry Preparation and Submittal
• Prior to construction, the ENGINEER shall prepare, mail and obtain Temporary
Right of Entries from landowners. It is assumed that letters will only be required
for land owners adjacent to temporary construction easements or who are
directly affected by the project and no easement is required to enter their
property.
• The documentation shall be provided in conformance with the checklists and
templates available on the CITY's Buzzsaw site.
ASSUMPTIONS
• Right -of -Way research includes review of property/right-of-way records based on
current Internet based Tarrant Appraisal District (TAD) information available at
the start of the project and available on -ground property information (i.e. iron
rods, fences, stakes etc.). It does not include effort for chain of title research,
parent track research, additional research for easements not included in the
TAD right-of-way takings, easement vacations and abandonments, right-of-way
vacations and street closures.
DELIVERABLES
A. Right -of -Way, easement exhibits and metes and bounds provided on CITY forms
B. Temporary Right of Entry Letters
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 7 of 9
TASK 6. SURVEY. — IF NECESSARY
ENGINEER will provide survey support as follows.
6.1 Design Survey
ENGINEER will perform field surveys to collect horizontal and vertical elevations
and other information needed by ENGINEER in design and preparation of plans
for the project Information gathered during the survey shall include topographic
data, utilities as required by the SUE, structures, trees (measure caliper, identify
overall canopy, and have qualified arborist identify species of trees) and other
features relevant to the final plan sheets. Existing drainage at intersections will
be verified by field surveys. Spot elevations will be shown on intersection layouts
with cross slope to fit intersecting grade lines.
• The minimum survey information to be provided on the plans shall include the
following •
A Project Control Sheet showing ALL Control Points, used or set while
gathering data Generally on a scale of not Tess than 1:400
The following information about each Control Point,
a. Identified (Existing. CITY Monument #8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a
referred bearing base Z coordinate on CITY Datum only.
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South
curb line of North Side Drive at the East end of radius at the Southeast
corner of North Side Drive and North Main Street).
6.2. Temporary Right of Entry Preparation and Submittal
• Prior to entering property for field survey, the ENGINEER shall prepare, mail and
obtain Temporary Right of Entry from landowners.
• The documentation shall be provided in conformance with the checklists and
templates available on the CITY's Buzzsaw site.
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
This section is intended to clarify between the CITY and ENGINEER typical items that may
arise in the project that are explicitly not included in this Scope of Work, but may be added
later at the written direction of the CITY.]
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services
described in the tasks above. However, ENGINEER can provide these services, if
needed, upon the CITY's written request Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be
agreed upon in writing by both parties before the services are performed. These
additional services include the following:
• Negotiation of easements or property acquisition.
• Services related to development of the CITY's project financing and/or budget.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 8 of 9
•
•
•
•
•
•
•
•
S ervices related to disputes over pre -qualification, bid protests, bid rejection
and re -bidding of the contract for construction.
Construction management and inspection services
S erformance of materials testing or specialty testing services.
S ervices necessary due to the default of the Contractor.
S ervices related to damages caused by fire, flood, earthquake or other acts of
God.
Services related to warranty claims, enforcement and inspection after final
completion.
S ervices to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
Performance of miscellaneous and supplemental services related to the project
as requested by the CITY.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 07/23/2012
Page 9 of 9
ATTACHMENT B
COMPENSATION
Design Services for
2014 Fiscal Year On -Call Services
City Project No. SWM-004
Time and Materials with Rate Schedule Project
Compensation
A. The ENGINEER shall be compensated for personnel time, non -labor expenses,
and subcontract expenses in performing services enumerated in Attachment A
as follows:
Personnel Time. Personnel time shall be compensated based upon hours
worked directly in performing the PROJECT multiplied by the appropriate Labor
Category Rate for the ENGINEER's team member performing the work.
Labor Category Rate as presented in the rate schedule table below is the rate for
each labor category performing the work and includes all direct salaries,
overhead, and profit during regular business hours. Overtime or work performed
on weekends will be subject to a 1.5 multiplier of the FY2014 rate listed below.
Labor Category
P rincipal
Quality Control Manager
P roject Manager / Project Engineer
P roject Manager / Project Surveyor
Engineer Intern / Survey Intern
Engineering Designer / Survey Technician
2-Man Survey Crew
GPS Survey Crew
Reproduction
Word Processor / Secretary
FY2014 Rate
($/hour)
$185.00
$150.00
$140.00
$135.00
$105.00
$95.00
$130.00
$150 00
$45.00
$45.00
ii. Non -Labor Expenses. Non -labor expenses shall be reimbursed as Direct
Expenses at invoice or internal office cost
Direct Expenses (non -labor) include, but are not limited to, mileage, travel and
lodging expenses mail, supplies, printing and reproduction services, other direct
expenses associated with delivery of the work, plus applicable sales, use, value
added, business transfer gross receipts, or other similar taxes.
Subcontract Expenses. Subcontract expenses and outside services shall
be reimbursed at cost to ENGINEER plus a markup of ten percent (10%).
iv. Budgets. ENGINEER will make reasonable efforts to complete the work
within the budget and will keep the City informed of progress toward that end so
that the budget or work effort can be adjusted if found necessary.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 8.09.2012
Page 1 of 4
B-1
ATTACHMENT B
COMPENSATION
ENGINEER is not obligated to incur costs beyond the indicated budgets, as may
be adjusted, nor is the City obligated to pay ENGINEER beyond these limits.
If ENGINEER projects, in the course of providing the necessary services, that the
PROJECT cost presented in Article 2 of this Agreement will be exceeded, whether
by change in scope of the project, increased costs or other conditions, the
ENGINEER shall immediately report such fact to the City and, if so instructed by
the City, shall suspend all work hereunder.
When any budget has been increased, ENGINEER's excess costs expended prior
to such increase will be allowable to the same extent as if such costs had been
incurred after the approved increase.
B. The ENGINEER shall be paid per work order as described in Section II - Method
of Payment.
11. Method of Payment
The ENGINEER shall be paid by the City based upon an invoice created on the
basis of statements prepared from the books and records of account of the
ENGINEER, based on the actual hours and costs expended by the ENGINEER
in performing the work.
B. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER
C. ENGINEER shall prepare and submit invoices in the format and including content
as presented in Exhibit B-1.
Payment of invoices will be subject to certification by the City that such work has
been performed.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 8.09.2012
Page 2 of 4
B-2
ATTACHMENT B
COMPENSATION
III. Summary of Total Project Fees
Firm
P rime Consultant
ANA Consultants
Primary Responsibility
Engineering
P roposed MBE/SBE Sub -Consultants
N on-MBE/SBE Consultants
Project Number & Name
Fee Amount
47,500
0/0
100%
TOTAL $ 47,500 100%
Total Fee
MBE/SBE Fee MBE/SBE
City MBE/SBE Goal = N/A Consultant Committed Goal = N/A
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 8.09.2012
Page 3 of 4
B-3
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across desired work types and work phases.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 8.09.2012
Page 4 of 4
A.N.A. Consultants, LLC
office address
CFW Project Manager
Consultant's Project Manager:
Consultant's email:
Name of Project:
Labor Category
Principal
Quality. Control Manager
Project Manager / Project Engineer
(817)335-9900
(817)335-9955
5000 Thompson Terrace Colleyville TX
76034
Cannon Henry, P.E.
Travis N. Attanasio
tnattanasiocanallc. com
2014 Fiscal Year Storrn Water On -Call Services
Name
MarkAssaad, P.E.
ANA
Travis N. Attanasio, P.E., CFM
Project Manager 1 Project Surveyor Edward Khalil, RPLS
Engineer Intern / Survey Intern ANA
Engineering Designer / Survey Technician ANA
2-Man Survey Crew
GPS Survey Crew
Reproduction
Word Processor/ Secretary
Total Labor
Subcontract Service
ANA
ANA
ANA
ANA
JS Ground Engineering, PLLC
Subcontractor Subtotal
10 Percent Markup on Subcontract Services
Nonlabor Exoenses
r
Nonlabor Expense Subtotal
Hours
0.0
Total Expenses (Subcontract Services+Markup+Nonlabor Expenses)
Consultant Project No.
Proj. Invoice No.
Invoice date:
Period From Date
To Date
City Secretary Contract #:
P.O. Number:
Rate ($/hr) Amount
$185.00 $0.00
$150.00 $0.00
$140.00 $0.00
$135.00 $0.00
$105.00 $0.00
$95.00 $0.00
$130.00 $0.00
$150.00 $0.00
$45.00 $0.00
$45.00 $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Invoice
130330
$0.00
$0.00
TOTAL DUE THIS INVOICE $0.00
Task No.
Task Description
Rat
11.0 Prole N{ fJ�gppment
1 1.1 Mar1F�,7 the 1 earn
1.1.1 Team Meetinas
1.1.1 QA/QC
1 1.2 Communications and A
1.2.1 Pre-nPSion.. Coordination Meetino
1.2.1 Inypic na
2.t1 '(Mork Order Based Preliminary Deslan
1 2.1 Data Collection
2.2 fIrp,ipmie C O'lp» p/S
2.3 Prel'iminary Desion Ur1 tjpwj
1.f{ Final Desiq
1 3.1 Final/100' 'Plans
1 3.2 Constructionkyl\�tg,.s (tf"1
4.0 construction Phase Services
I 4.1 C.{I trog,(19i.§.1or ?rt
4.1.1 fmec ite Visits
4.11 Submittal Review
Request for Information/Change Order
4.1.3 Review
4.1.4 Final WO, hrwah and Punch List
1 4.2 Record Urawm9s_
Principal
`8(
Quality
Control
Manager
9
Project
Manager
Engineer
Protect
Manager
Surveyor
5140 S135
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
2014 Fiscal Year Storm Water On -Call Services
Engineer
Intern
Survey
Intern
abor (hours)
Engineering
Designer/Survey
Technician
2-Man
Survey
Crew
S 515.
G PS
Survey
Crew
Reproduction Word Processor
(In -House) / Secretary
;5 $45
EXPENSE 1
Total Labor Employee
Cost Mileage
Reproduction
Total Expense Task Sub Total Labor Percent of
Cost Total Fee
Task Percent of
Total Fee
32 10
0
2 0
0
1 20
59,795
$100
S0
$100
S9,895
81
9
1
201 10
2
$5,820
$1,350
S1,260
201 S1 ,365
(_ 0
52
12
21
20
0
0
461 0
4
2
1
0
40
40
0
$100
S13,o0
$1,870
$3,085
$8,495
5100
$100
$200
S20U
$0
$5,820
$0
$1,350
$0
$1,260
$0
$1.365
S300
$300
S0
S0
12.25%
S13,750
$2,170
$3.085
$8,495
C 0
21
L
30
20
1d
0
10
7
40
40
0
0
0
31
11,
b
6
I
0
0
12 0
12
40
40
01 2
0
S10,850
S9,135
S1,715,
S100
$100
$600
$600
S700
$700
S11,550
S9,835
$0
51,715
0
55,940
$1,540
$840
$840
$1,490
S1,230
$100
$100 $60
S60
$160
S6,100
S0
$0
2.84% 20.83%
2.65°k
2.87%
4.57%
6.49%
17.88%
20.71%
3.61%
$1.54 3.24%
$84 1.77%
S0
$0
S0
$840 1.77%
$1,490 3.14%1
$1,23Q 2.59%
51 0 f2 {F f> �lFes
1 5.1 16 9 - es rc
I tig -ol-way/Easement Preparation and
5.2 Submittal
1 5.3 TemoorOc;,t Riaht of Enrfv SubmilVk
6.0 Surypft
1 6.1 Desjrt; Survo,\�,
City of Fort Worth, Toxas
Attachment B - Level of Effort Supplement
PMO Official Release Date: 8.09,2012
0 0
0
61 af' 151 0
0
0
0
52,235
3
3
7
7
1
0
31
0
7
5
15
0
Totals 10
Total Amounts py Labe JF�j f�(
Percent Labor of T tal L36of 118"�
9
51.350
2.05%
145
$
i3.1 T%
3
191 10
$2.565 $1050
4.34°h l 1.28%
7
5
15
0
S665
$1,070
$500
$3,970
$3,970
SO
50
SO
SO
SO
28.95%
24.32%
12.84%
52,235
S0
$665
1.40%
$0
$1.070
$0
$500
S0
$0
$3,970
$3,970
2.25%
1.05%
8.36%
122
5
15
83
511 51I95650 �7 750 �,3J35
27.1466k 1.14% j.d ��, 1 .95°�
20
$900
4.57°k
S46,240
$4001 S860
51,260
S47,500
4.71%
8.36%
rolect ��f4 I
Total Hours 4311)I
Total Labor $46 240J
Total FYs!�n f $ .2bC,{(,l{{
Total Prole�t 1 6s I S47.501 99.456k 100.00%I
1 of 1
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
2014 Fiscal Year Storm Water On -Call Services
City Project No. SWM-004
1. Scour analysis is not included.
2. Preparation of Letter of Map Revision (LOMR) documents, are not included.
3. Subsurface Utility Engineering is not included
4. Utility clearance and coordination is not included
5. Construction inspection, administration, and bidding is not included
6. Preparation of construction Specifications are not included.
7. Monthly meeting reports and schedule updating are not included.
8. Geotechnical Engineering and pavement design services are not included.