Contract 45430 (2)
COMMUNITY FACILITIES AGREEMENT THE STATE OF TEXAS COUNTY OF TARRANT § City Secretary Contract Na L['Sq 430 WHEREAS, the undersigned Developer ("Developer") desires to make certain improvements ("Improvements") related to a project as described below ("Project") within the City of Fort Worth, Texas ("City"); and WHEREAS, the Developer and the City desire to enter into this Community Facilities Agreement ("CFA" or "Agreement") in connection with the Improvements. Developer and Project Information: Developer Company Name: Pulte Homes of Texas, L.P. Address, State, Zip Code: 4800 Regent Blvd., Suite 100 I Irving, TX 75063 Phone, E-Mail: (972) 304-2800, clint.vincent@pultegroup.com Authorized Signatory/Title: Clint Vincent, Division Vice President of Land Development Project Name and Brief Description: Water, Sewer, Paving, Storm Drain & Street Light Improvements to serve West Fork Ranch Ph. 5B Project Location: South of Bailey Boswell Road and West of Horseman Road Plat Case No.: FP-013-019 Plat Name: Parr Trust Council District: 2 To be completed by staff' Received by: City Project No: 02216 CFA: 2014-004 DOE: 7174 Date: OFFIrrAL RECORD CITY SECRETARY FT. WORfl, • • 1 2014 NOW, THEREFORE, For and in consideration of the covenants and conditions contained herein, the City and the Developer do hereby agree as follows: General Requirements A. The Policy for the Installation of Community Facilities ("Policy") dated March 2001, approved by the City Council of the City of Fort Worth, as amended, is hereby incorporated into this Agreement as if copied herein verbatim. Developer agrees to comply with all provisions of said Policy in the performance of its duties and obligations hereunder and to cause all contractors hired by Developer to comply with the Policy in connection with the work performed by said contractors. B. Developer shall provide financial security in conformance with paragraph 6, Section II, of the Policy and recognizes that there shall be no reduction in the collateral until the Project has been completed and the City has officially accepted the Improvements. Developer further acknowledges that said process requires the contractor to submit an Affidavit of Bills paid signed by its contractor and Consent of Surety signed by its surety to ensure the contractor has paid the sub -contractor and suppliers in full. Additionally, the contractor will provide in writing that the contractor has been paid in full for all the services provided under this contract. C. Developer agrees to cause the construction of the Improvements contemplated by this Agreement and that said construction shall be completed in a good and workmanlike manner and in accordance with all City standards and the City - approved construction plans, specifications and cost estimates provided for the Project and the exhibits attached hereto. D. The following checked exhibits are made a part hereof: Water (A) _X_, Sewer (A-1) JL. Paving (B) X� Storm Drain (B-1) X ,Street Lights & Signs (C) X . E. The Developer shall award all contracts for the construction of the Improvements in accordance with Section II, paragraph 7 of the Policy and the contracts shall be administered in conformance with paragraph 8, Section II, of the Policy. F. For all Improvements included in this Agreement for which the Developer awards construction contract(s), Developer agrees to the following: i. To employ a construction contractor who is approved by the director of the department having jurisdiction over the infrastructure to be constructed, said contractor to meet City's requirements for being insured, licensed and bonded to do work in public streets and/or prequalified to perform water/waste water construction as the case may be. ii. To require its contractor to furnish to the City a payment and performance bond in the names of the City and the Developer for one hundred percent (100%) of the contract price of the Improvements, and a maintenance bond in the name of the City for one hundred percent (100%) of the contract price of the Improvements for a period of two (2) years insuring the maintenance and repair of the constructed infrastructure during the term of the maintenance bond. All bonds to be furnished before work is commenced and to meet the requirements of Chapter 2253, Texas Government Code. iii. To require the contractor(s) it hires to perfoiin the construction work contemplated herein to provide insurance equal to or in excess of the amounts required by the City's standard specifications and contract documents for developer -awarded infrastructure construction contracts. The City shall be named as additional insured on all insurance required by said documents and same will be evidenced on the ACORD Certificate of Insurance supplied by the contractor's insurance provider and bound in the construction contract book iv. To require its contractor to give 48 hours notice to the City's Construction Services Division of intent to commence construction so that City inspection personnel will be available; and to require the contractor to allow the construction to be subject to inspection at any and all times by City inspection forces, and not to install or relocate any sanitary sewer, storm drain, or water pipe unless a responsible City inspector is present and gives his consent to proceed, and to make such laboratory tests of materials being used as may be required by the City v. To require its contractor to have fully executed contract documents submitted to the City to schedule a Pre -Construction Meeting. The submittal should occur no less than 10 working days prior to the desired date of the meeting. No construction will commence without a City -issued Notice to Proceed to the Developer's contractor. vi. To delay connections of buildings to service lines of sewer and water mains constructed under this Agre ment until said sewer and water mains and service lines have been completed to the satisfaction of the Water Department. G. Developer agrees to provide, at its expense, all engineering drawings and documents necessary to construct the improvements required by this Agreement. H. Developer shall cause the installation or adjustment of the required utilities to serve the development or to construct the Improvements required herein. I. City shall not be responsible for any costs that may be incurred by Developer in the relocation of any utilities that are or may be in conflict with any of the community facilities to be installed hereunder. J. Developer hereby releases and agrees to indemnify, defend and hold the City harmless for any inadequacies in the preliminary plans, specifications and cost estimates supplied by the Developer for this Agreement. K. Developer agrees to provide, at its expense, all necessary rights of way and easements across property owned by Developer and required for the construction of the current and future improvements provided for by this Agreement. L. The Developer further covenants and agrees to, and by these presents does hereby, fully indemnify, hold harmless and defend the City, its officers, agents and employees from all suits, actions or claims of any character, whether real or asserted, brought for or on account of any injuries or damages sustained by any persons (including death) or to any property, resulting from or in connection with the construction, design, performance or completion of any work to be performed by said Developer, his contractors, subcontractors, officers, agents or employees or in consequence of any failure to properly safeguard the work, or on account of any act, intentional or otherwise, neglect or misconduct of said DEVELOPER, his contractors, sub -contractors, officers, agents or employees, whether or not such injuries, death or damages are caused, in whole or in part, by the alleged negligence of the City of Fort Worth, its officers, servants, or enrnlovees. M. Developer will further require its contractors to indemnify, defend and hold harmless the City, its officers, agents and employees from and against any and all claims, suits or causes of action of any nature whatsoever, whether real or asserted, brought for or on account of any injuries or damages to persons or property, including death, resulting from, or in any way connected with, the construction of the infrastructure contemplated herein, whether or not such injuries, death or damages are caused, in whole or in part, by the alleged negligence of the City of Fort Worth, its officers, servants. or employees. Further, Developer will require its contractors to indemnify, and hold harmless the City for any losses, damages, costs or expenses suffered by the City or caused as a result of said contractor's failure to complete the work and construct the improvements in a good and workmanlike manner, free from defects, in conformance with the Policy, and in accordance with all plans and specifications. N. Upon completion of all work associated with the construction of the infrastructure and Improvements, Developer will assign to the City a non-exclusive right to enforce the contracts entered into by the Developer with its contractor along with an assignment of all warranties given by the contractor, whether express or implied Further, Developer agrees that all contracts with any contractor shall include provisions granting to the City the right to enforce such contracts as an express intended third party beneficiary of such contracts. O. Inspection and material testing fees are required as follows: i. Developer shall pay in cash water and wastewater inspection fees and material testing fees equal to two percent (2%) for a total of 4% of the developer's share of the total construction cost as stated in the construction contract. ii. Developer shall pay in cash paving and storm drain inspection fees equal to four percent (4%) and material testing fees equal to two percent (2%) for a total of 6% of the developer's share of the total construction cost as stated in the construction contract. iii. Developer shall pay in cash the total cost of streetlights or if the city is not installing the streetlights, inspection fees equal to four percent (4%) of the developer's share of the streetlight construction cost as stated in the construction contract. iv. Developer shall pay in cash the total cost of street signs P. COMPLETION WITHIN 2 YEARS i. If applicable, the City's obligation to participate (exclusive of front foot charges) in the cost of the Improvements shall terminate if the Improvements are not completed within two (2) years provided, however, if construction of the Improvements has started within the two year period, the developer may request that the CFA be extended for one year. If the Improvements are not completed within such extension period, there will be no further obligation of the City to participate. City participation in a CFA shall be subject to the availability of City funds and approval by the Fort Worth City Council. ii. Nothing contained herein is intended to limit the Developer's obligations under the Policy, this Agreement, its financial guarantee, its agreement with its contractor or other related agreements. iii. The City may utilize the Developer's financial guarantee submitted for this Agreement to cause the completion of the construction of the Improvements if at the end of two (2) years from the date of this Agreement the Improvements have not been completed and accepted. iv. The City may utilize the Developer's financial guarantee to cause the completion of the construction of the Improvements or to cause the payment of costs for construction of same before the expiration of two (2) years if the Developer breaches this Agreement, becomes insolvent or fails to pay costs of construction and the financial guarantee is not a Completion Agreement. If the financial guarantee is a Completion Agreement and the Developer's contractors and/or suppliers are not paid for the costs of supplies and/or construction, the contractors and/or suppliers may put a lien upon the property which is the subject of the Completion Agreement. (REMAINDER OF PAGE INTENTIONALLY LEFT BLANK) Cost Summary Sheet Project Name: West Fork Ranch Ph. 5B CFA No.: 2014-004 Items A. Water and Sewer Construction 1. Water Construction 2. Sewer Construction Water and Sewer Construction Total B. TPW Construction 1. Street 2. Storm Drain 3. Street Lights Installed by Developer TPW Construction Cost Total Total Construction Cost (excluding the fees): Construction Fees: C. Water/Sewer Inspection Fee (2%) D. Water/Sewer Material Testing Fee (2%) Sub -Total for Water Construction Fees E TPW Inspection Fee (4%) F. TPW Material Testing (2%) G. Street Light lnspsection Cost H. Street Signs Installation Cost ($245 EA.) Sub -Total for TPW Construction Fees Total Construction Fees: Financial Guarantee Options, choose one Bond = 100% Completion Agreement = 100% / Holds Plat Cash Escrow Water/Sanitary Sewer= 125% Cash Escrow Paving/Storm Drain = 125% Letter of Credit = 125% w/2yr expiration period DOE No.: 7174 Developer's Cost $ $ 108,541.20 113,546.90 $ 222,088.10 $ $ $ 262,046.70 38,694.80 29,830.40 $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ 330,571.90 552,660.00 4,441.76 4,441.76 8,883.52 12, 029.66 6,014.83 1,193.22 1,000.00 20,237.71 29,121.23 Amount 552,660.00 552,660.00 277,610.13 413,214.88 690, 825.00 Choice (ck one) V IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed in quadruplicate in its name and on its behalf by its Assistant City Manager, attested by its City Secretary, with the corporate seal of the City affixed, and said Developer has executed this instrument in quadruplicate, at Fort Worth, Texas this 1 day of e/---- , 20 f . CITY OF FORT WORTH - Recommended by: Water Department Wendy Chi-abulal, EMBA, P.E. Development Engineering Manager Approved as to Form. & Legality: Dou as W. Black Assistant City Attorney M&C No. V/A, Date: ATTEST: M" ary' J. a City Secretaty ATTEST: Signature (Print) Name: Curt Millward Title: Pulte Land Project Manager Transportation & Public Works Department Douglas ' . Wiersig, P.E. Director Approved by City Manager's Office 27,0frafL__ Fernando Costa Assistant City Manager DEVELOPER: Pulte Homes of Texas, L.P. By: Pulte Nevada I, LLC its General Partner 8 Signature (Print) Name: Clint Vincent Title: Vice President of Land Development OFFICIAL RECORD CITY SECRETARY Ft WORTH, TX Check items associated with the project being undertaken; checked items must be included as Attachments to this Agreement Included /1 ►1 S Attachment Location Map Exhibit A: Water Improvements Water Estimate Exhibit A-1: Sewer Improvements Sewer Estimate Exhibit B: Paving Improvements Paving Estimate Exhibit B-1: Storm Drain Improvements Storm Drain Estimate Exhibit C: Street Lights and Signs Improvements Street Lights and Signs Estimate (Remainder of Page Intentionally Left Blank) 9 BAILEY - BOS NELL SAG INAW\ 2 \se* O l � 00^ \ / J ✓ �I D BLV MUNI NMI SAGINAW CITY LIMIT modmi w Z CCui z 03 c4 0 WESTERN CENTER BLVD irD NORTH NOT TO SCALE WEST FORK RANCH PHASE 5B OWNER / DEVELOPER Ii!II PELOTON PULTE HOMES OF TEXAS, L.P. 11111 LAND SOLUTIONS 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 DATE: JANUARY, 2014 1 GA¢Y pY 1CFa39 04 � N�pC BST G:C, FUTURE BAILEY-BOSWELL ROAD LOT 48X BLK 50 PRIVATE OPEN SPACE LEGEND PROPOSED GATE VALVE EXIST GATE VALVE PROPOSED FIRE HYDRANT EXIST FIRE HYDRANT NOTE: ALL PROPOSED WATER LINES ARE 8" UNLESS OTHERWISE NOTED EXHIBIT A - WATER Pik 0 AMENITY CENTER, PRIVATE OPEN SPACE 38 39 40 TI LOT 20X BLK 50 SIM v1FNTAL ROAD .� ? T I12 13 I 14 15 I r 0 NORTH 200' GRAPHIC SCALE WEST FORK RANCH PHASE 5B DATE: JANUARY. 2014 OWNER / DEVELOPER* PULTE HOMES OF TEXAS, L.P. 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 (i?il PELOTON III LAND SOLUTIONS 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 vAes aloft NPNpCRT GS. 1 1`i FUTURE BAILEY-BOSWELL ROAD 1 LOT 46X BLK 50 • PRIVATE OPEN SPACE LEGEND --�-- PROPOSED SEWER LINES © - EXIST SEWER LINES NOTE: ALL PROPOSED SANITARY SEWER LINES ARE 8' UNLESS OTHERWISE NOTED EXHIBIT Al - WASTEWATER - 17 SIM_MENTa RJAD 1 36 I 16 LOT 20X BLK 50 j 22 23 I 24 I I 25 { - 50 133U32t PRETA WAY -. st Z 11 I I 12 I 13 I 14 I 15 II 8 —PLAME RA LANE CH IMP OM PAO AMENITY CENTER, PRIVATE OPEN SPACE 38 40 31 17 1 30 18 1 1 0 NORTH 200' MIS WEST FORK RANCH PHASE 5B GRAPHIC SCALE DATE: JANUARY, 2014 OWNER / DEVELOPER: PULTE HOMES OF TEXAS, L.P. 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 PELOTON III I LAND SOLUTIONS 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 ra GP•�,ip2 0 B/393 NE CRC" FUTURE BAILEY-BOSWELL ROAD LEGEND LOT 46X BLK 50 PRIVATE OPEN SPACE ti 29' B-B / 50' ROW (TYP) SIDEWALK BY DEVELOPER SIDEWALK BY HOMEBUILDER H.C. RAMPS BY DEVELOPER EXHIBITB- PAVING si L"AfY AMENITY CENTER, PRIVATE OPEN — SPACE 39 40 3 LOT 20X BLK 50 1 36 I 34 PRETA WAY I13 I 14 I 15 IMMI r---1 9 I 10 11 11 I 12 I 13 [I, 0 NORTH 200' GRAPHIC SCALE WEST FORK RANCH PHASE 5B DATE: JANUARY, 2014 OWNER / DEVELOPER° PULTE HOMES OF TEXAS, L.P. 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 li?Il PE LOTO N Ill I LAND SOLUTIONS 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 GAY Yt LC3 T39 N Ne Np2G06..t G;t. T FUTURE BAILEY-BOSWELL ROAD LEGEND 10T46X BLK 50 PRIVATE OPEN SPACE • MINI NM AMENITY CENTER, PRIVATE OPEN SPACE PROPOSED STORM DRAIN INLET - EXIST STORM DRAIN INLET -�-- PROPOSED STORM DRAIN MANHOLE PROPOSED STORM DRAIN HEADWALL EXHIBIT B1 - STORM DRAINAGE UGH i - __ .. S PNp 40p61 00 # .2269 �/ LOT 50 I! .I 20 119 I 18 II 17 I� I I' - i • 1 36 9 35 PRETA WMY _ 8 I 32 I 31 I 17 io• PLAMERA_ LA 4E_" INLETS 25 L_ WEspNASo.,- ', '_ .,.2269 30 I 29 GH 0 NORTH 200' WEST FORK RANCH PHASE 5B GRAPHIC SCALE DATE: JANUARY. 2014 OWNER / DEVELOPER' PULTE HOMES OF TEXAS, L.P. 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 PELOTON 1111 LAND SOLUTIONS 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 1 GF` OC-0//93 N,osAc� co T. FUTURE BAILEY=BOSWELL ROAD LOT 46X BLK 50 PRIVATE OPEN SPACE LEGEND PROPOSED STREET LIGHTS EXIST STREET LIGHTS EXHIBIT C - STREET LIGHTS +r AMENITY CENTER, PRIVATE OPEN SPACE LOT 20X BLK 50 20 19 ( 18 I 17 1 ,RETA WE Y I 14 I I 15 I 16 I 17 18 I I 32 I 31 NORTH 200' WEST FORK RANCH PHASE 5B GRAPHIC SCALE DATE: JANUARY. 2014 OWNER / DEVELOPER: PULTE HOMES OF TEXAS, L.P. 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 Hill PELOTON III I LAND SOLUTIONS 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 TITTATIT G C . /39 O2 BkN N� CT. FUT RE BAILEY-BOSWELL ROAD LOT 46X BLK 50 PRIVATE OPEN SPACE LEGEND PROPOSED STREET NAME SIGNS A EXIST SIGNS i AMENITY CENTER, PRIVATE OPEN SPACE 38 1 39 40 I LOT 20X BLK 50 1 36 I SON vd�s PNPe 4Tp61 -. - D0Ep',-2y69 -- SIMMENT 34 33 ?RETA WAY • EXHIBIT CI - STREET NAME SIGNS 8 I I / 7/ I Ik PLAy1ERA LANE 30 1 0 NORTH 200' WEST FORK RANCH PHASE 5B GRAPHIC SCALE DATE: JANUARY, 2014 OWNER / DEVELOPER: PULTE HOMES OF TEXAS, L.P. 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 lull PELOTON II' LAND aownoxa 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 34 33 ?RETA WAY • EXHIBIT CI - STREET NAME SIGNS 8 I I / 7/ I Ik PLAy1ERA LANE 30 1 0 NORTH 200' WEST FORK RANCH PHASE 5B GRAPHIC SCALE DATE: JANUARY, 2014 OWNER / DEVELOPER: PULTE HOMES OF TEXAS, L.P. 4800 REGENT BLVD. SUITE 100 IRVING, TX 75063 972-304-2800 lull PELOTON II' LAND aownoxa 5751 KROGER DRIVE SUITE 185 KELLER, TX 76244 PHONE: 817-562-3350 PELOTON LAND SOLUTIONS 5751 KROGER OR STE. 185 KELLER, TX 76244 817.562.3350 EXHIBIT A - WATER IMPROVEMENTS ITEM # DESCRIPTION 3311.0263 3312.3003 3312.0001 3311.0001 9999.0000 8" PVC Water Line 8" Gate Valve & Box Fire Hydrant Assembly (includes 6" GV) Ductile Iron Fittings Concrete Blocking - Type B 3312.2001 'Water Service, 1" Tap to Main (Residential) 3312.0117 1Water Service, 1" Tap to Main 3312.0103 I Connect to Existing Water Line 3305.0109 'Trench Safety TOTAL WATER CFA ESTIMATE FOR: PArin TRUST ADDITION WEST FORK RANCH PHASE 5B 2/4/2014 EXHIBIT Al - SANITARY SEWER IMPROVEMENTS ITEM # 3331.4115 3331.4116 3339.1001 3339.1003 DESCRIPTION 8" Sanitary Sewer Main (SDR-26 PVC) 8" Sanitary Sewer Main (SDR-26 PVC) with Cement Stabilized Sand Manhole - Std 4' Dia Manhole - Extra Depth over 6' 3301.0101 'Manhole - Vacuum Test 3331.3101 ISewer Service - 4" Tap (SDR - 26) 3331.3313 (Connect to Ex SS Line 3305.0109 'Trench Safety 3301.0002 I Post Construction CCTV TOTAL SANITARY SEWER I I 1 1 UNIT QTY LF EA EA TON CY EA EA EA LF UNIT LF LF EA VF EA EA EA LF LF 2,064 3 2 1.0 25 49 j 3j 5I 2,064 I QTY 1,536 140 7 17 7 48 2 1,676 1,676 UNIT PRICE 24.50 1,045.00 3,345.00 4,400.00 150.00 705.00 1,825.00 650.00 0.05 36.75 50.50 2,340.00 210.00 140.00 547.32 450.00 0.05 1.10 TOTAL' 50,568.00 3,135.00 6,690.00 4,400.00 375.00 34, 545.00 5,475.00 3,250.00 103.20 $108,541.20 I TOTAL 56,448.00 7,070.00 16,380.00 3,570.00 I 980.00 I 26,271.36 900.00 83.80 1,843.60 $113,546.76 WFR_PHSB_CFA_20140204, Ph5B 1 of 3 3/7/2014 PELOTON LAND SOLUTIONS 5751 KROGER DR STE 165 KELLER, TX 76244 817.562 3350 EXHIBIT B- PAVING IMPROVEMENTS IITEM # I 3213.0101 3211.0501 3211.0400 3213.0302 3213.0501 3216.0102 DESCRIPTION 6" Reinf. Conc. Pvmt. w/ 7" Curbs for 29' b-b street 6" Lime Stabilized Subgrade for 29'b-b street Hydrated Lime (30#/SY) 4', 4" Conc. Sidewalk (Residential) B/F Ramps (Type R-1) Install Conc. Curb & Gutter 9999.0000 'Remove Existing Concrete 9999.0000 'Remove Barricade and Connect to Existing Header 9999.0000 !Traffic Control Plan ITOTAL PAVING EXHIBIT BI- STORM DRAIN IMPROVEMENTS I ITEM # DESCRIPTION 3341.0208 27" RCP 3341.0205 24" RCP 3341.0201 21" RCP 3349.3004 127" Headwall 3349.5001 110' Std Curb Inlet 3137.0101 118" Thick Rock Rip Rap 9999.0000 'Remove Plug and Connect to Ex I 9999.0000 (Trench Safety (TOTAL STORM DRAIN CFA ESTIMATE FOR: PARR TRUST ADDITION WEST FORK RANCH PHASE 5B 2/4/2014 1 I I 1 I 1 UNIT QTY SY 6,555 SY 6,979 TON 105 LF EA LF SY EA LS UNIT LF LF LF EA EA SY EA LF QTY 1,410 2 101 I 395 I 4I 1I 149 136 101 1 5I 11 I 1I 386 I 32.00 2.30 135.00 4.00 1,500.00 20.00 20.00 500.00 1,500.00 59.00 51.00 47.00 1,925.00 2,860.00 110.00 I 670.00 I 0.30 I TOTAL 209,760.00 16, 051.70 14,175.00 5,640.00 3,000.00 2,020.00 7,900.00 2,000.00 1,500.00 $262,046.70 I TOTAL 8,791.00 6,936.00 4,747.00 1,925.00 I 14, 300.00 I 1,210.00 I 670.00 115.80 $38,694.80 WFR_PHSB_CFA_20140204, Ph5B 2 of 3 3/7/2014 • •.. • • • • P E L O T O N 6FA ESTIMATE FOR: PARR TRUST ADDITION WEST FORK RANCH PHASE 5B 2/4/2014 LAND SOLUTIONS 5751 KRONER DR STE. 185 KELLER. TX 76244 817.562 3350 EXHIBIT C e STREET LIGHTING IMPROVEMENTS DESCRIPTION 3441.3302 Roadway Iilum Assembly - Type D25-6 Pole w/150W MH Luminaire 3441.3301 Light Pole Foundation- Type 4 9999.0000 #10 THHW Aluminum Conductor 9999.0000 2" PVC Conduit, Sch 80 TOTAL STREET LIGHTS EXHIBIT C1 -STREET SIGNS I I 1 DESCRIPTION Street Name Blades (TOTAL STREET SIGNS UNIT QTY EA EA LF LF UNIT EA 8 8 1,920 QTY 640 2 1,700.00 1,300.00 0.72 6.95 500.00 TOTAL' 13,600.00 10,400.00 1,382.40 4,448.00 $29,830.40 I TOTAL I 1,000.00 I $1,000.00 I WFR_PH5B_CFA_20140204, Ph5B 3 of 3 3/7/2014