AMENDMENT No . 1
TO CITY SECRETARY CONTRACT
WHEREAS, the City of Fort Worth (CITY) and Teague Nall and Perkins,
Inc., (ENGINEER) made and entered into City Secretary Contract No. 43893,
(the CONTRACT) which was authorized by the City Council on the 23rd day
of October, 2012 in the amount of $563,730.92; and
WHEREAS, the CONTRACT involves engineering services for the following
project:
Chapel Creek Bridge over Interstate Highway 30
WHEREAS, it has become necessary to execute Amendment No. 1 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement,
which amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in a proposal dated June 24, 2013, a copy
of which is attached hereto and incorporated herein. The cost to City
for the additional design services to be performed by Engineer totals
$226,205.00.
2.
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $789,935,92,
3.
All other provisions of the Contract, which are not expressly
amended herein, shall remain in full force and effect.
� ra ego, R�7C`�9 it
Page -1- DECEIVED �;�u Q � ZOi3
EXECUTED and EFFECTIVE as of the date last written by a signatory,
below.
APPROVED:
City of Fort Worth
Fernando Costa
Assistant City Manager
DATE: / /
APP$QVAL RECOMMENDED:
DouglasU
Director,
ENGINEER
Teague Nall and Perkins, Inc.
JoSep Atwood, P.E:
Director
DATE :
Wiersig, P.E
Transportation and Public Works Department
APPROVED AS TO FORM AND LEGALITY:
oug ; �� e �� wl . Y-(,
Assistant City Attorney
� III I !•- ,'• - rrw�w..
I
� Slott �
FL
IF
Page -2-
M&C: C-26486
Date: October 7, 2013
June 24, 2013
Mr. Michael Weiss, P.E.
City of Fort Worth
Transportation &Public Works Department
1000 Throckmorton
Fort Worth, Texas 76102
RE: IH 30 at Chapel Creek Boulevard Bridge replacement
Fee Proposal for Contract Amendment No. 1
DOE Number 901
CSJ: 0918-48-722
Dear Mr. Weiss:
Teague Nall and Perkins, Inc. is submitting this
contract based on additional services requested
following is a brief description and cost for the
project:
Mtn
p
League Hall R Perkins www.mpinc.com
fee Amendment for the above referenced
by TxDOT for the bridge replacement. The
additional services to be provided on this
I. Feasibility study, Operations Analysis and Geometric Design for additional U-Turn Bridge:
Teague, Nall and Perkins (TNP) performed due diligence during contract scoping phase to identify
the need to include a U-Turn bridge. Records from TxDOT and City of Fort Worth staff discussions
indicated that a U-Turn was not to be included. Upon notice to proceed, a Design Concept
Conference was held and TxDOT requested that a U-Turn feasibility analysis be conducted and
contingent upon results, U-Turn be added to the project. Feasibility was determined and
Preliminary design was performed.
A travel demand forecast study was performed to determine validity of a dated TxDOT-TPP
travel demand forecast by comparison to NCTCOG node map volumes at the request of TXDOT.
Results were used to prepare a detailed traffic operation analysis. This work is excluded in the
scope of services. TNP requested that TxDOT perform this service by TPP staff and were
instructed to perform the analysis.
Fee: $38,575
II. U-Turn Structure Final Design:
The additional U-Turn bridge will require bridge layout, foundation design, and framing detail
design services for construction bidding according to TxDOT/FHWA requirements. Turning radius
analysis for interstate truck vehicles indicate that special construction methods be employed to
provide for turning radii at the bridge ends, thus requiring the use of curved steel beam framing
and many other details to provide an aesthetically pleasing and functional structure.
Fee: $104,990
engineers
surveyors
landscape architects
III. Extend Construction Limits:
The original scope of service and fee assumptions state that the construction limits at the
approaches would stay within 200 feet of the bridge due to no significant changes to the bridge
Fort Worth � 1 100 Macon Street Fort Worth, Texas 76102 � 817.336.5773 � Dallas � 17304 Preston Road, Suite 1340 � Dallas, Texas 75252 � 214.461.9667
Denfon � 1517 Centre Place Drive, Suite 320 � Demon, Texas 76205 � 940.383.4177 `� Sherman � 200 North Travis Street, Suite 500 � Sherman, Texas 75090 � 903.870.1089
Registered by the Texas Board of Professional Engineers, Finn No. F-230 � Registered by the Texas Board of Professional Surveyors, Firm No. 1001 16-00
Mr. Michael Weiss, PE
October 24, 2013
Page 2 of 3
elevation or U-Turn bridge. It has since been established that the bridge needs to be elevated to
provide additional IH 30 main lane clearance. Additional frontage road approach lane
improvements are necessary to accommodate the U-Turn. TNP has mitigated the effects of
clearance requirement by use of low profile beams, but there still remains a need to increase the
Chapel Creek Blvd profile over IH 30 that results in extended construction limits. Additional need
to extend the construction limits is presented by traffic operations need to store queuing traffic at
signal approaches. The proposed fee is to provide for additional design sheets, cross section
design, and driveway profiles.
Fee: $13,200
IV. Additional Retaining Walls:
During the course Geometric Design development, the need for two (2) additional retaining walls
has been identified. One located along the proposed Chapel Creek Boulevard ROW at the
Exxon Station that reduces encroachment on a storm water detention basin. The other wall is
required along Leonard Golf Links property. Both walls will limit encroachment into vital business
improvements; therefore the use of retaining wall translates into lowered damages to the
businesses. Additional geotechnical investigations are included in the proposed fee.
Design Fee: $12,000
Ge )technical Fee (DBE): $6,000
V. Additional ROW Fee Take Parcels and Easements:
During the course of Geometric Design development and ROW surveying, it was noted that a
parcel was sub -divided into many smaller lots. Therefore, the anticipated numbers of ROW fee
take parcels will increase by twelve (12) parcels from four (4) to sixteen (16) ROW fee take
exhibits.
The project will also require four (4) temporary construction easements for driveways that TxDOT
will require exhibits.
Survey Fee (DBE): $45,440+$6,000= $51,440
Summary of Contract Amendment Fee:
I. Study, Analysis, and Geometric Design for U-Turn Bridge: Fee: $38,575
II. U-Turn Structure Final Design: Fee: $104,990
III. Extend Construction Limits: Fee: $13,200
IV. Additional Retaining Wall Designs: Fee: $12,000
DBE Fee: $6,000
V. Additional ROW Exhibits: DBE Fee: $51,440
Total Contract Amendment Amount:
Schedule:
$226,205
TNP proposes a revised project schedule that accounts for public involvement delay associated
with U-Turn services and associated TxDOT approvals. The changes are not anticipated to
affect letting schedule.
Thank you for consideration of this contract amendment request. If you have any questions,
please do not hesitate to call me.
Mr. Michael Weiss, PE
October 24, 2013
Page 3 of 3
Sincerely,
tnp
feague nail & perkins
Joseph W. Atwood, P.E.
CC File: FTW12583
Teague Nall and Perkins, Inc.
Corporate Resolution
Authorization to Execute Contracts
The UNDERSIGNED hereby certifies that he is Secrefiary of TEAGUE HALL AND
PERKINS, INC. (the "Corporation"), a corporation organized and existing under the laws of
the State of Texas, and that the following resolution was adopted at the meeting of the
Board of Directors of the Corporation, which was duly called and held on the 27"' day of
December 20120 that this is a true and correct copy of the resolution; and that it has not
been revoked, amended, or altered; and is still in full force and effect.
Upon motion duly made, seconded and unanimously passed it was
RESOLVED that each of the following individuals, acting in their capacity as an
Officer of the Corporation, Principal, Office Manager and/or Director of Surveying has full
power and authority to extend employment offers, enter into contracts, or to execute and
deliver related instruments and other documents to various agencies, entities, individuals
and corporations, etc., on behalf of TEAGUE NALL AND PERKINS, INC., and that no
counter -signature is required on such contracts and documents in order to make said
contracts and documents legally binding upon the Corporation.
Mark R. Berry, Principal —CEO/Treasurer
Michael A. Jones, Principal — President
C. Ty Hilton, Principal — Vice President/Secretary
Tom Rutledge, Principal
Greg D. Saunders, Principal
Scott C. Wilhelm, Principal
Gary L. Vickery, Principal
Chris L. Schmitt, Principal / Sherman Office Manager
Stephen H. Roberson, Principal / Director of Surveying
Timothy W. May, Director of Planning and Landscape Architecture
W. L. (Bill) Wimberley, Land Acquisition and Utility Coordination Manager
Robert Jenkins, Traffic Engineering Manager
Michael Wellbaum, Director of Energy Services
Joe Atwood, Director of Transportation
IN WITNESS WHEREOF, the UNDERSIGNED has hereunto set his hand and the seal
of the Corporation this the 28'f' day of December 2012. „
SECRET-ARY OF THE CORPORATION
C. Ty Hilton
p
M&C Review
Page 1 of 2
Official site of the City of Fort Worth, Texas
illi�illill III iiiiiiiiii 1� r
P.
1'OftT`VORT11
COUNCIL ACTION: Approved on 10/7/2013
**C-26486 LOG NAME:
DATE: 10/7/2013 REFERENCE NO.: 20CHAPEL BRIDGE
AMEND 1
CODE: C TYPE: CONSENT PUBLIC NO
HEARING:
SUBJECT: Authorize Execution of Amendment No. 1 to City Secretary Contract No. 43893, an
Engineering Services Agreement with Teague Nall and Perkins, Inc., in the Amount of
$226,205.00 for the Design of Chapel Creek Bridge Over Interstate Highway 30, Thereby
Establishing a Revised Contract Cost in the Amount of $789,935.92 (COUNCIL DISTRICT
3)
RECOMMENDATION:
It is recommended that the City Council authorize the execution of Amendment No. 1 to City
Secretary Contract No. 43893, an Engineering Services Agreement with Teague Nall and Perkins,
Inc., in the amount of $226,205.00 for the Design of Chapel Creek Bridge over Interstate Highway 30,
thereby establishing a revised total contract cost in the amount of $789,935.92.
DISCUSSION:
This Professional Services Agreement provides for the design of a new six -lane bridge across
Interstate Highway 30 (IH-30) to serve Chapel Creek Boulevard. The Texas Department of
Transportation has asked that the City expand the scope of the design to include the addition of a
second turnaround at the bridge that will serve the eastbound traffic on IH-30. The proposed design
amendment will provide the services necessary to accomplish the modification in scope. Funding for
this Agreement includes the amount of $309,016.00 of 2008 Capital Improvement Program (CIP)
funds (or 19 percent of the total). The balance is being provided by Federal and State Funds. There
are sufficient funds remaining from these original amounts to pay for the additional design work.
On May 8, 2012, (M&C C-25607) the City Council authorized the execution of a Local Project
Advance Funding Agreement with the Texas Department of Transportation (TxDOT) in the amount of
$1,650,059.00 for the design of the Chapel Creek Bridge over IH-30.
On October 23, 2012, (M&C C-25937) the City Council authorized the execution of Engineering
Services Contract No. 43893 with Teague Nall and Perkins, Inc., for the design of Chapel Creek
Bridge over IH-30.
http: //apps. cfwnet. org/council�acket/mc_review. asp?ID=1903 ... 10/24/2013
M&C Review
Page 2 of 2
Amount
Description
M&C
Approved
Number
Initial Contract
$5631730.92
Design of Chapel
C-25937
10/23/2012
Creek Bridge over IH-
30
Amendment No.
$226,205.00
Design of U-Turn
pending
pending
1
Bridge over IH-30 and
additional retaining
walls, extend project
limits, and provide
additional right-of-way
exhibits
Contract Total
$789,935.92
The proposed amendment will provide for a feasibility study, traffic operations analysis, geometric
and final design of the additional U-turn bridge, extend the design limits along the IH-30 frontage
roads and Chapel Creek Boulevard due to the higher required elevation of the new bridge, design two
additional retaining walls, and to prepare additional right-of-way easements and exhibits.
Teague Nall and Perkins, Inc., proposes to complete Amendment No. 1 for a lump sum fee not to
exceed $226,205.00, for a revised total contract amount not to exceed $769,935,92, Staff considers
this fee to be fair and reasonable for the scope of services to be performed.
M/WBE Office - Teague Nall and Perkins, Inc., is in compliance with the City's DBE Ordinance by
committing to an additional 25 percent DBE participation on this Amendment No. 1. The City's DBE
goal on this Amendment is 22 percent.
This project is located in COUNCIL DISTRICT 3, Mapsco 72K.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budget, as appropriated, of the Grant Capital Projects Fund.
TO Fund/Account/Centers
Submitted for City Manager's Office bv:
Originating Department Head:
Additional Information Contact:
ATTACHMENTS
20CHAPEL CREEK BRIDGE MAP,
FROM Fund/Account/Centers
GR74 531200 020302569300
Fernando Costa (6122)
Douglas W. Wiersig (7801)
Mike Weiss (8485)
$226,
205.00
http : //apps. cfwnet. org/council�acket/mc_review. asp?ID=1903 ... 10/24/2013
•]:Ol\►lIIIKSM kINIMKS] ►ylWi1l1►II@f MICL■IJIM
30