HomeMy WebLinkAboutContract 43475-CO2 (2)Change Order No. Date City of Fort Worth Change Order Request TPW Project No. Funding (FAC) 2 (TWO) 9/20/2012 2012-06 GG01 536010 0205002 Facility and Project Description City Secretary Contract No, Replace Boiler System at Public Safety Building CSCN 43475 ORIGINAL CONTRACT AMOUNT................................................................ $194,500.00 EXTRAS TO DATE',,'', spossm ",mow 004 "1 I'm odd do, ''I *odes ''I ''loot $ 18,003 CREDITS TO DATE, I I I I 1 0 0 a 9 a a I I I I I I I I I I 1 0 * 0 0 1 1 1 1 1 1 1 0 0 a I I I I I I * 9 1 9 $ 0 CONTRACTCOST TO DATE,., bell'' ''I ''I 14*06M ''I a 0 1 1 1 1 1 1 1 1 1 1 0 a I I I I I 1 0 0 a a & I I I I I I 1 9 a I I I I 1 4 1 1 1 s I I I I I I I I I o 0 0 1 1 1 1 1 1 1 1 1 1 1 $ 2121503 AMOUNT OF PROPOSED CHANGE ORDER.''....,,,,, Mow wpm Ohl'', 'It a I I & I I I 1 0 t 1 0 1 1 1 1 1 1 1 4 0 6 * I I I I I I I I 1 0 a a 9 4 1 $ 14,697 REVISEDCONTRACT AMOUNT............................................................................................. $ 227,200 ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS''.... ME, ''I or* *06 'We ''I see MOM ",@Dole, ''I '',lei me, ''I ''I ''I $ 29,140 REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS,''.....'''"', Best,, 41* 01111, 114 4*9 DOE'', $ 11,137 ADDITIONAL FUNDING (IF NECESSARY),,,... Pie ell'', '',moo ''I I'laosell ''1 104 Egg $ 31560 IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL; Furnish all labor and material as per the attached Propose Change Requests Replace Domestic Cold Water Distribution header as per the proposal dated 9/14/12 ADD $ 141697 ADD $ 14,697 It is understood and agreed that the acceptance of this Change Order by the contractor constihrtes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order Contractor's Name R. L. P. Mechanical Contractors, Inc. Original Contract Time Additional Approved Time To Date Approved Contract Time To Date Additional Time For This Change Order 95 calendar days, 5 calendar days 100 calendar days 0 calendar days ntracto - R. L. P. echanical Contractors, Inc. Date Fads Maintenance Inspector Date l ' ' c, 1 Iz 7 gook d -1 / F lliti s Mainte e bp in ndffit or, Transportation and Public Works Date tw �J gi a aird pton Brown Assistan Cdesit Manager Date A sis a ttorn Date Council Action (If Required) ❑ Approve 4waro ed ❑ Othe d Distribution File Facilities Maintenance Inspector Project Manager Contractor J. by: S OFFICIAL RECUR® �0 11TY SECRETARY p°° ,"' F4n �1� [� li Gee TX 7d� 1% .Cy TPW Facilities Management Division Change Order Form (01/31/12) .-ontractors, Inc. prone 972-611-3557 �ax 972-576-0926 September 14, 2012 City of Fort Worth 1000 Throckmorton Fort Worth, Texas 76102 Attn: Mike Pease Ref: Public Safety Building —Boiler Replacement Subj: Replace domestic cold water header in the boiler plant Mr. Pease, We have proposed the following changes for your review. Our price includes: 41�1 N Hwy / 1 TACLA016331 C M8173 HUB Cert # 1752603389300 1. Remove and dispose of existing 4" DCW header including the 4" isolation gate valve 2. Provide and install kl) 4", ( ) 3, k2) 25 kl) 2-1/2" and ( ) l" ball valves to rebuild the header 3. All valves 2" and below to be sweat ball valve and 24/2" and larger to be flanged ball valves 4. All piping to be type "L" copper 5. Dielectric unions to be used at all connection points to the existing galvanized pipe 6. All prefabrication to be performed during normal business hours 7. Domestic cold water shutdown and header installation to be performed on a Saturday 8. Facility personnel to be present for drain and re -fill of system Our price. . 0 a a * 6.6 0 0 a 4 0 6 0 0 4 0 a a M 0 0 a 0 0 see 0 0 0 4 0 0 6 ot $14,697.00 Exclusions: 1. Piping insulation 2. Sales tax If there are any questions or comments please call. Thank you, David Brumley