HomeMy WebLinkAboutContract 44211 (2)COMMUNITY FACILITIES AGREEMENT
THE STATE OF TEXAS § City Secretary I j
COUNTY OF TARRANT § Contract No.
WHEREAS, the undersigned Developer ("Developer") desires to make certain
improvements ("Improvements") related to a project as described below ("Project"), an
addition to the City of Fort Worth, Texas ("City"); and
WHEREAS, the Developer and the City desire to enter into this "Agreement" in
connection with the Improvements.
Developer Information:
Developer Company Name: Sundance Plaza, LLC
Address, State, Zip Code: 201 Main Street � Fort Worth, TX 76102
Phone, E-Mail: (817) 255-5700
Authorized Signatory/Title: Johnny Campbell, President &CEO
Project Name: 42" Storm Drain Improvements to serve Sundance Square
ect Location: Main Street from 3`d Street to 5`'' Street
Plat Case No.: FS-011-150 Plat Name:
Council District: 9 City Proiect No: 02030
CFA: 2012-073
Received by:
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities
6952
02-26-13 A10:59 IN
NOW, THEREFORE, KNOW ALL BY THESE PRESENTS:
For and in consideration of the covenants and conditions contained herein, the City and the
Developer do hereby agree as follows:
General Requirements
A. The Policy for the Installation of Community Faces ("Policy") dated
March 2001, approved by the City Council of the City of Fort Worth and
subsequently amended from time to time via a Mayor and Council
Communication adopted by the City Council of the City of Fort Worth, is
hereby incorporated into this Community Facilities Agreement ("CFA") as if
copied herein verbatim. Developer agrees to comply with all provisions of
said Policy in the performance of its duties and obligations hereunder and to
cause all contractors hired by Developer to comply with the Policy in
connection with the work performed by said contractors.
B. Developer shall provide financial security in conformance with paragraph 6,
Section II, of the Policy and recognizes that there shall be no reduction in the
collateral until the Project has been completed and the City has officially
accepted the infrastructure. Developer further acknowledges that said
process requires the contractor to submit an Affidavit of Bills Paid signed
by its contractor and Consent of Surety signed by its surety to ensure the
contractor has paid the sub -contractor and suppliers in full. Additionally,
the contractor will provide in writing that the contractor has been paid in
full for all the services provided under this contract.
C. Developer agrees to cause the construction of the improvements
contemplated by this Agreement and that said construction shall be
completed in a good and workmanlike manner and in accordance with all
City standards and the City -approved construction plans, specifications and
cost estimates provided for the Project and the exhibits attached hereto.
D. he following checked exhibits are made a part hereof: Water (Al
Sewer (A -I) Paving (B) Storm Drain (B-1) A. ;Street Lights
Signs (C).,
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 2 of 11
E. The Developer shall award all contracts for the construction of community
facilities in accordance with Section II, paragraph 7 of the Policy and the
contracts for the construction of the public infrastructure shall be
administered in conformance with paragraph 8, Section II, of the Policy.
F. For all infrastructure included in this Agreement for which the Developer
awards construction contract(s), Developer agrees to the following:
i. To employ a construction contractor who is approved by the director of
the department having jurisdiction over the infrastructure to be
constructed, said contractor to meet City's requirements for being insured,
licensed and bonded to do work in public streets and/or prequalified to
perform water/waste water construction as the case may be.
ii. To require its contractor to furnish to the City a payment and performance
bond in the names of the City and the Developer for one hundred percent
(100%) of the contract price of the infrastructure, and a maintenance bond
in the name of the City for one hundred percent (100%) of the contract
price of the infrastructure for a period of two (2) years insuring the
maintenance and repair of the constructed infrastructure during the term of
the maintenance bond. All bonds to be furnished before work is
commenced and to meet the requirements of Chapter 2253, Texas
Government Code.
iii. To require the contractor(s) it hires to perform the construction work
contemplated herein to provide insurance equal to or in excess of the
amounts required by the City's standard specifications and contract
documents for developer -awarded infrastructure construction contracts.
The City shall be named as additional insured on all insurance required by
said documents and same will be evidenced on the ACORD Certificate of
Insurance supplied by the contractor's insurance provider and bound in the
construction contract book.
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 3 of 11
iv. To require its contractor to give 48 hours' notice to the City's
Construction Services Division of intent to commence construction so that
City inspection personnel will be available; and to require the contractor to
allow the construction to be subject to inspection at any and all times by
City inspection forces, and not to install or relocate any sanitary sewer,
storm drain, or water pipe unless a responsible City inspector is present
and gives his consent to proceed, and to make such laboratory tests of
materials being used as may be required by the City.
v. To require its contractor to have fully executed contract documents
submitted to the City to schedule aPre-Construction Meeting. The
submittal should occur no less than 10 working days prior to the desired
date of the meeting. No construction will commence without a City -issued
Notice to Proceed to the Developer's contractor.
vi. To delay connections of buildings to service lines of sewer and water
mains constructed under this Agreement until said sewer and water mains
and service lines have been completed to the satisfaction of the Water
Department,
G. Developer agrees to provide, at its expense, all engineering drawings and
documents necessary to construct the improvements required by this
Agreement.
H. Developer shall cause the installation or adjustment of the required utilities to
serve the development or to construct the improvements required herein.
I. City shall not be responsible for any costs that may be incurred by Developer
in the relocation of any utilities that are or may be in conflict with any of the
community facilities to be installed hereunder.
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 4 of 11
J. Developer hereby releases and agrees to indemnify, defend and hold the
City harmless for any inadequacies in the preliminary plans,
specifications and cost estimates supplied by the Developer for this
Agreement.
K. Developer agrees to provide, at its expense, all necessary rights of way and
easements across property owned by Developer and required for the
construction of the current and future improvements provided for by this
Agreement.
L. The Developer further covenants and agrees to, and by these presents
does hereby, fully indemnify, hold harmless and defend the City, its
officers, agents and employees from all suits, actions or claims of any
character, whether real or asserted, brought for or on account of any
injuries or damages sustained by any persons (including death) or to
any property, resulting from or in connection with the construction,
design, performance or completion of any work to be performed by said
Developer, his contractors, subcontractors, officers, agents or
employees, or in consequence of any failure to properly safeguard the
work, or on account of any act, intentional or otherwise, neglect or
misconduct of said DEVELOPER, his contractors, sub -contractors,
officers, agents or employees.
M. Developer will further require its contractors to indemnify, defend and
hold harmless the City, its officers, agents and employees from and
against any and all claims, suits or causes of action of any nature
whatsoever, whether real or asserted, brought for or on account of any
injuries or damages to persons or property, including death, resulting
from, or in any way connected with, the construction of the infrastructure
contemplated herein, whether or not such injuries, death or damages are
caused, in whole or in part, by the alleged nealikence of the City of
Fort Worth, its officers, servants, or employees. Further, Developer will
require its contractors to indemnify, and hold harmless the City for any
losses, damages, costs or expenses suffered by the City or caused as a
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 5 of 11
t
result of said contractor's failure to complete the work and construct the
improvements in a good and workmanlike manner, free from defects, in
conformance with the Policy, and in accordance with all plans and
specifications,
N. Upon completion of all work associated with the construction of the
infrastructure and improvements, Developer will assign to the City a non-
exclusive right to enforce the contracts entered into by the Developer with its
contractor along with an assignment of all warranties given by the contractor,
whether express or implied. Further, Developer agrees that all contracts with
any contractor shall include provisions granting to the City the right to enforce
such contracts as an express intended third party beneficiary of such contracts.
O. Inspection and material testing fees are required as follows:
i. Developer shall pay in cash water and wastewater inspection fees and
material testing fees equal to two percent (2%) for a total of 4% of the
developer's share of the total construction cost as stated in the construction
contract.
ii. Developer shall pay in cash paving and storm drain inspection fees equal to
four percent (4%) and material testing fees equal to two percent (2%) for a
total of 6% of the developer's share of the total construction cost as stated in
the construction contract.
iii. Developer shall pay in cash the total cost of streetlights or if the city is not
installing the streetlights, inspection fees equal to four percent (4%) of the
developer's share of the streetlight construction cost as stated in the
construction contract.
iv. Developer shall pay in cash the total cost of street signs.
P. COMPLETION WITHIN 2 YEARS
i. The City's obligation to participate (exclusive of front foot charges) in the
cost of the community facilities shall terminate if the facilities are not
completed within two (2) years, provided, however, if construction of the
community facilities has started within the two year period, the developer
may request that the CFA be extended for one year. If the community
facilities are not completed within such extension period, there will be no
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 6 of 11
further obligation of the City to participate. City participation in a CFA
shall be subject to the availability of City funds and approval by the Fort
Worth City Council.
ii. Nothing contained herein is intended to limit the Developer's
obligations under the Policy, this Agreement, its financial guarantee,
its agreement with its contractor or other related agreements.
iii. The City may utilize the Developer's financial guarantee submitted for
this Agreement to cause the completion of the construction of the
community facilities if at the end of two (2) years from the date of this
Agreement the community facilities have not been completed and
accepted.
iv. The City may utilize the Developer's financial guarantee to cause the
completion of the construction of the community facilities or to cause the
payment of costs for construction of same before the expiration of two (2)
years if the Developer breaches this Agreement, becomes insolvent or fails
to pay costs of construction and the financial guarantee is not a
Completion Agreement. If the financial guarantee is a Completion
Agreement and the Developer's contractors and/or suppliers are not paid
for the costs of supplies and/or construction, the contractors and/or
suppliers may put a lien upon the property which is the subject of the
Completion Agreement.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 7 of 11
Cost Summary Sheet
Project Name: 42 Storm Drain Improvements to serve.Sundance Square
CFA No.: 2012-073
DOE No.: 6952
An Engineer's Estimate of Probable Cost is acceptable. However, the construction contract price
will ultimately determine the amount of CFA fees and financial guarantee. The bid price and any
additional CFA payments will be required prior to scheduling a pre -construction meeting.
An itemized estimate corresponding to each project -specific exhibit is required to support the
following information.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 8 of 11
Items
DeNelopers Cost
A. Water and Sewer Construction
1, Water Construction
$
2. Sewer Construction
$
-
Water and Server Construction Total
$
-
B. TPW Construction
1. Street
$
2. Storm Drain
$
686,398.50
3, Street Lights Installed by De%eloper
$
-
TPW Construction Cost Total
$
6869398,50
Total Construction Cost (excluding the fees):
$
686,398.50
Construction Fees:
C. Water/Sewer Inspection Fee (2%)
$
-
D. Water/Sewer Material Testing Fee (2%)
$
-
Sub -Total for Water Construction Fees
$
-
E. TPW Inspection Fee (4%)
$
279455,94
F. TPW Material Testing (2%)
$
13,727.97
G. Street Light Inspsection Cost
$
-
H. Street Signs Installation Cost
$
-
Sub -Total for TPW Construction Fees
$
41,183.91
',Total Construction Fees: $ 41,183.91
Choice
Financial Guarantee Options, choose one Amount (ck one)
Bond = 100%
$ 686,398.50
Completion Agreement = 100% / Holds Plat
$ 686,398,50
Cash Escrow Water/Sanitary Sewer= 125%
$ -
Cash Escrow Paung/Storm Drain = 125%
$ 857,998.13
Letter of Credit = 125% w/2yr expiration period
$ 857,998,13
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities
Page 9 of 11
IN TESTIMONY WHEREOF, the City of Fort Worth has caused this instrument to be executed
in quadruplicate in its name and on its behalf by its Assistant City Manager and said Developer has
executed this instrument in quadruplicate, at Fort Worth, Texas, effective as of the date subscribed by
the Assistant City Manager.
SUNDANCE PLAZA, LLC,
a Texas limited liability company
By: Sundance S
its managing ag
By:
Johnny
Date:
(Print)
1,
Recommended by:
Water Department
CITY OF FORT WORTH
L.P., fit0 6
Fernando Costa
Assistant City Manager
Date: Z,ZS�/Y
and CEO
Wendy Chi-Babulal, EMBA, P.E. Douglas
Development Engineering Manager Director
Approved as to Form &Legality:
Doug al s W. Black
Assistant City Attorney
M&C No. Al
Date:
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 10 of 11
Wiersig, P.E.
��� f if i.;�i�;��;I
Check items associated with the project being undertaken; checked items must be
included as Attachments to this Agreement
Included Attachment
® Location Map
❑ Exhibit A: Water Improvements
❑ Water Estimate
❑ Exhibit A-1: Sewer Improvements
❑ Sewer Estimate
❑ Exhibit B: Paving Improvements
❑ Paving Estimate
® Exhibit B-1: Storm Drain Improvements
® Storm Drain Estimate
❑ Exhibit C: Street Lights and Signs Improvements
❑ Street Lights and Signs Estimate
(Remainder of Page Intentionally Left Blank)
CFW-Sundance Plaza LLC
CFA for Stormwater Facilities Page 11 of 11
VICINITY MAP
NOT TO SCALE
SUNDANCE SQUARE
42" STORM DRAIN IMPROVEMENTS
a
LL DOE # 6952
CITY PROJECT # 02030
iV
nic'UNAW
Q
N
O
N
Ay
550 Bailey Avenue • Suite 400 • Fort Worth, Texas 76107
Tel: 817.335.1121 • Fax: 817.335.7437
o (TX REG. F-1114)
0
J
a
i !!
00 v, I o
N N
itm
W
z � I
' z Z
I al;;
m Q
CJ6Lci
o
I� (n J J O W ui
co
Ca
LLJ
V
O W� Q) LOLLI
X W
Q
W
%�j
m 21
�!c 1 0 EX
O
EX - BQ -
x
Ex- o`Ds
W 5T ST
I ?
z
z Q ZI it x I o
Q W J Q II WI o ��.
00
o WZ Q _Q W3 0 II w I I Loft oN
0 !ems J O O II W ! co
Z! I I m
ct N p Y M j N �lollW W:
N Lo N co j d I °°loll I Adak
v I Wes. III
Lo
6Mp•Jan0Jai l!q!gXA Vd7\sl!q!4x3 VdJ UUGIS 9T0T-ZT\sl!q!4x3\56uunej0\u6!sa0\£00'88T0009\OOT000\uo.rpnP0Jd\:9 :HiVd3lld Wd 00:£ :1V ETOZ'£0 Aienue£'Aepsm4l :NO pe47'ln4jeW :A9 031101d '`
SECTION 00 42 43
PROPOSAL FORM
Project Type:
42" Storm Drain Improvements
UNIT PRICE BID Bidder's Application
Project Item Information Bidder's Proposal
Bidlist Specificatio Unit of
Item No. Description n Section Measure Bid Quantity Unit Price Bid Value
__ _. No,
1 0241.0100 Remove Sidewalk 0241 13 SF 432 $7.00 $3,024.00
2 0241.0300 Remove ADA Ramp 0241 13 EA 5 $50.00 $250.00
3 0241,1200 Remove Brick Pvmt 024115 SY 1406 $80.25 $112,831o50
4 0241.1300 Remove Conc Curb&Gutter 0241 15 LF 230 $0.50 $115.00
5 0241.3011 Remove 15" Storm Line 0241 14 LF 275 $43.00 $111825a00
6 0241.3013 Remove 18" Storm Line 0241 14 LF 202 $43.00 $83686600
1 1-17 0241.3017 Remove 30" Storm Line 0241 14 LF 555 $20.00 $11,100400
8 0241.3101 15" Storm Abandonment Plug 0241 14 EA
1 $100.00 $100.00
9 0241.3102 18" Storm Abandonment Plug 0241 14 EA 1 $100,00
$100.00
10 024163501 Remove Storm Junction 0241 14 LS
Structure 1 $11000.00 $1,0 OM
11 0241.4001 Remove 10' Curb Inlet 0241 14 EA 1 $19000,00 $1,000000
12 3213.0303 6" Conc Sidewalk 32 13 20 SF 432 $8.00 $3,456.00
13 3214.0200 Brick Pvmt Repair 32 14 16 SY 1406 $81.00 $113,886,00
14 3216,0102 7" Conc Curb and Gutter 32 16 13 LF 230 $2.50 $575000
_ . . _. _. _ . .. ..
15 3305.0109 Trench Safety 33 05 10 LF 850 $3.00 $2,550.00
11
16 3341,0205 24" RCP, Class III 3341 10 LF 280 $268.00 $75,040,00
.._ .
17 3341,0302 30" RCP, Class III 3341 10 LF 45 $298.00 $13,410.00
18 3341.0402 42" RCP, Class III 3341 10 LF 525 $436.00 $2281900.00
19 3349.0002 5' Storm Junction Box 33 49 10 EA 3 $7,500,00 $22,500.00
20 334905001 10' Curb Inlet 33 49 20 EA 7 $3,500.00 $24,500,00
21 3349,5002 15' Curb Inlet 33 49 20 EA 1 $4,750.00 $49750600
22 3471,0001 Traffic Control 3471 13 MO 1 $361000.00 $361000.00
23 19999.0000 Pavement Markings 1999999 1 LS 1 $10,800.00 $10,800,00
Bid Summary
Base Bid
Alternate Bid
Deductive Alternate Bid
Additive Alternate Bid
Total Deductive Alternate Bid
Total Additive Alternate
Total Bid $686,398.50