CITY OF FORT WORTH, TEXAS
STANDARD AGREEMENT FOR ENGINEERING RELATED DESIGN SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home -rule
municipality (the "CITY"), and Lawrence Jeffrey Hamilton d/b/a Hamilton Civil Engineering,
authorized to do business in Texas, (the "ENGINEER"), for a PROJECT generally
described as: Water and Sanitary Sewer Replacement Contract 2011, WSM-D.
Article I
Scope of Services
A. The Scope of Services is set forth in Attachment A.
Article II
Compensation
A. The ENGINEER's compensation is set forth in Attachment B.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
o not limited to meeting the requirements set forth in Attachment D to this
0
AGREEMENT, to reasonably substantiate the invoices.
N (2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
co
(3) Upon completion of services enumerated in Article I, the final payment of
CD any balance will be due within 30 days of receipt of the final invoice.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 1 of 16
m"�
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5) If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The standard of care applicable to the ENGINEER's services will be the
degree of skill and diligence normally employed in the State of Texas by
professional engineers or consultants performing the same or similar
services at the time such services are performed.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 2 of 16
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on -site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
the agreement between CITY and ENGINEER be construed as requiring
ENGINEER to make exhaustive or continuous on -site inspections to
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 3 of 16
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on -site
observations) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
(3) When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials, unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs, competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
matters at issue between the CITY and the construction contractor that
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 4 of 16
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority and Woman Business Enterprise (M/1111BE) Participation
In accord with City of Fort Worth Ordinance No. 15530, as amended, the
City has goals for the participation of minority business enterprises and
woman business enterprises in City contracts. Engineer acknowledges the
M/WBE goal established for this contract and its accepted written
commitment to M/WBE participation. Any misrepresentation of facts (other
than a negligent misrepresentation) and/or the commission of fraud by the
Engineer may result in the termination of this Agreement and debarment
from participating in City contracts for a period of time of not less than three
(3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page5of16
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
(3) ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an insured under the CGL, using
ISO additional insured endorsement or a substitute providing
equivalent coverage, and under the commercial umbrella, if any.
This insurance shall apply as primary insurance with respect to
any other insurance or self-insurance programs afforded to the
CITY. The Commercial General Liability insurance policy shall
have no exclusions by endorsements that would alter or nullify:
premises/operations, products/completed operations, contractual,
personal injury, or advertizing injury, which are normally contained
within the policy, unless the CITY approves such exclusions in
writing.
ii. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto —the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
liability arising out of "any auto", including owned, hired, and non -owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non -owned is
acceptable.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 6 of 16
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation —ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $10 icy
li 00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability —the ENGINEER shall maintain professional
liability, a claims -made policy, with a minimum of $1,000,000.00 per
claim and aggregate. The policy shall contain a retroactive date prior to
the date of the contract or the first date of services to be performed,
whichever is earlier. Coverage shall be maintained for a period of 5 years
following the completion of the contract. An annual certificate of
insurance specifically referencing this project shall be submitted to the
CITY for each year following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be delivered to the CITY prior to ENGINEER
proceeding with the PROJECT.
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, as its interests may appear. The term CITY shall
include its employees, officers, officials, agents, and volunteers as
respects the contracted services.
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
d. Any failure on part
documentation shall
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 7 of 16
of the CITY to request required insurance
not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first -dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims -made basis, shall contain a retroactive date coincident with or
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims -made.
k. Coverages, whether written on an occurrence or claims -made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
final payments.
I. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
m. Sub consultants and subcontractors to/of the ENGINEER shall be
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04l2012
Page 8 of 16
required by the ENGINEER to
equivalent insurance coverage as
sub consultants/subcontractors
ENGINEER shall provide CITY
certificate of insurance.
L. Independent Consultant
maintain the same or reasonably
required for the ENGINEER. When
maintain insurance coverage,
with documentation thereof on a
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities -Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
amendment to this AGREEMENT.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 9 of 16
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City -Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights -
of -way, and access necessary for the ENGINEER's services or PROJECT
construction.
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E. Prompt Notice
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 10 of 16
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER Is negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article N.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
H. Contractor Claims and Third -Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third -party beneficiaries.
(3) The CITY will include in each agreement it enters into with any other entity
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 11 of 16
oIs person regarding the PROJECT a provision that such entity or person
shall have no third -party beneficiary rights under this Agreement.
(4) Nothing contained in this section V.H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY will ensure that Builders Risk/Installation insurance is maintained
at the replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3) The CITY will specify that the Builders Risk/Installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 12 of 16
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated only by the City for convenience on
30 days' written notice. This AGREEMENT may be terminated by either the
CITY or the ENGINEER for cause if either party fails substantially to perform
through no fault of the other and does not commence correction of such
nonperformance with in 5 days of written notice and diligently complete the
correction thereafter.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
c.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses. The
CITY'S approval will be obtained in writing prior to proceeding with
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 13 of 16
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER's compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify, hold harmless, and defend the CITY against
liability for any damage caused by or resulting from an act of negligence,
intentional tort, intellectual property infringement, or failure to pay a
subcontractor or supplier committed by the ENGINEER or ENGINEER's
agent, consultant under contract, or another entity over which the
ENGINEER exercises control.
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Interpretation
Limitations on liability and indemnities in this AGREEMENT are business
understandings between the parties and shall apply to all the different
theories of recovery, including breach of contract or warranty, tort including
negligence, strict or statutory liability, or any other cause of action, except for
willful misconduct or gross negligence for limitations of liability and sole
negligence for indemnification. Parties mean the CITY and the ENGINEER,
and their officers, employees, agents, and subcontractors.
I. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 14 of 16
J. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
K. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
Article VII
Attachments, Schedules, and Signatures
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. The following attachments
and schedules are hereby made a part of this AGREEMENT:
Attachment A -Scope of Services
Attachment B —Compensation
Attachment C - Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 15 of 16
Executed and effective this the j G� day of ) Q I`J, 2012.
BY: BY:
CITY OF FORT WORTH ENGINEER
Lawrence Jeffrey Hamilton d/b/a
Hamilton Civil Engineering
Fernando Costa
Assistant City Manager
Date: /2
APPROVAL RECOMMENDED:
By:
/ql rA( \V
S. Frank Crumb, P.E.
Director, Water Department
APPROVED
LEGALITY
By:
AS TO FORM AND
Assistant City Attorney
Owner
Date: l
M&C Date• '�- I � • l Z.
ATTEST: p � 000004PA
pro U IGot
woo o
o°
a j J. Kay/ter d
City Secre o°. __,o°°°�
City of Fort Worth, Texas
Standard Agreement for Engineering Related Design Services
PMO Official Release Date: 05/04/2012
Page 16 of i6
OFFICIAL REC®R®
CITY SECRETARY'
T. WORTH, TX
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM*D
CITY PROJECT NO.: 01929
ATTACHMENT A
ne%A Uesian
Improvements
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 VV U
CITY PROJECT NO.: 01929
The scope set forth herein defines the work to be performed by the ENGINEER in
completing the project. Both the CITY and ENGINEER have attempted to clearly define the
work to be performed and address the needs of the Project.
WORK TO BE PERFORMED
Task 1. Design Management
Task 2. Conceptual Design
Task 3. Preliminary Design
Task 4. Final Design
Task 5. Bid Phase Services
Task 6. Construction Phase Services
Task 7. ROW/Easement Services
Task 8. Survey and Subsurface Utility Engineering Services
Task 9. Plan Submittal Checklists
TASK 1. DESIGN MANAGEMENT.
ENGINEER shall ensure efficient and effective use of ENGINEER's and CITY's time and
resources.
ENGINEER shall manage change,
■ communicate effectively,
■ coordinate internally and externally as needed, and
■ proactively address issues with the CITY's Project Manager and others as
necessary to make progress on the work.
1.1. Managing the Team
Lead, manage and direct design team activities
■ Ensure quality control is practiced in performance of the work
Communicate internally among team members
• Task and allocate team resources
1.2. Communications and Reporting
City of FortWorth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 1 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
• Attend a pre -design project kickoff/chartering meeting with CITY staff to confirm and
clarify scope, understand CITY objectives, and ensure economical and functional
designs that meet CITY requirements
• Conduct review meetings with the CITY at the end of each design phase
Prepare invoices and submit monthly in the format requested by the CITY.
Prepare and submit monthly progress reports in the format provided by the Water
Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule updates
with a schedule narrative monthly, as required in Attachment D to this Standard
Agreement and according to the City of Fort Worth's Schedule Guidance Document.
Complete Monthly MWWBE Report Form and Final Summary Payment Report Form at
the end of the project
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design
With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall work with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope.
Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub -consultants shall carry readily visible
information identifying the name of the company and the company representative.
ASSUMPTIONS
15 MWBE reports will be prepared
• 4 meetings with city staff
15 monthly water department progress reports will be prepared
15 monthly project schedule updates will be prepared
DELIVERABLES
A. Meeting summaries with action items
B. Monthly invoices
C. Monthly progress reports
D. Baseline design schedule
E. Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 2 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM-D
CITY PROJECT NO.: 01929
F. Monthly MMBE Report Form and Final Summary Payment Report Form
G. Plan Submittal Checklists (See Task 9)
TASK 2. CONCEPTUAL DESIGN (30 PERCENT).
The Conceptual Design shall be submitted to CITY per the approved Project Schedule.
The purpose of the conceptual design is for the ENGINEER to
■ Study the project,
■ Identify and develop alternatives that enhance the system,
■ Present (through the defined deliverables) these alternatives to the CITY
■ Recommend the alternatives that successfully addresses the design problem, and
■ Obtain the CITY's endorsement of this concept.
ENGINEER will develop the conceptual design of the infrastructure as follows.
2.1. Data Collection
• In addition to data obtained from the CITY, ENGINEER will research proposed
improvements in conjunction with any other planned future improvements that
may influence the project.
• The ENGINEER will also identify and seek to obtain data for existing conditions
that may impact the project including but not limited to; utilities, agencies (TXDOT
and railroads), City Master Plans, and property ownership as available from the
Tax Assessor's office.
• The data collection efforts will also include conducting special coordination
meetings with affected property owners and businesses as necessary to develop
sewer re-routing plans.
• The ENGINEER shall visit the project site and obtain the meter numbers and sizes
on all existing meters to be replaced on the project and shall identify existing
sample stations and fire line locations.
2.2. Geotechnicallnvestigations
• ENGINEER shall advise the CITY of test borings and other subsurface
investigations that may be needed for the project. If the CITY determines that
such borings or investigations are needed, then the ENGINEER shall work with
the CITY and CITY's geotechnical consultant to draw up specifications for such
testing program. The cost of such testing will be paid for by the CITY.
2.3. The Conceptual Design Package shall include the following:
• Cover Sheet
• Graphic exhibits and written summary of alternative design concepts considered,
strengths and weaknesses of each, and the rationale for selecting the
recommended design concept.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 3 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
Proposed phasing of any water and sanitary sewer work that is included in this
project documented in both the project schedule and narrative form.
Documentation of key design decisions.
Estimates of probable construction cost.
ASSUMPTIONS
0 Geotechnical borings are expected for this project.
3 copies of the conceptual design package (30% design) will be delivered.
Report shall be letter sized and comb- bound with a clear plastic cover. Drawings
will be half size fold outs bound in the report
DWF files created from design CAD drawings will be uploaded to the designated
project folder in Buzzsaw
• ENGINEER shall prepare the meeting minutes of the Concept Review meeting
and revise the report, if needed.
ENGINEER shall not proceed with Preliminary Design activities without obtaining
written approval by the CITY of the Conceptual Design Package.
DELIVERABLES
A. Conceptual Design Package
TASK 3. PRELIMINARY DESIGN (60 PERCENT).
Preliminary plans and specifications shall be submitted to CITY per the approved Project
Schedule.
ENGINEER will develop the preliminary design of the infrastructure as follows.
3.1. Development of Preliminary Design Drawings and Specifications shall include the
following:
• Cover Sheet
A Proiect Control Sheet, showing all Control Points, used or set while gathering
data. Generally on a scale of not less than 1:400. The following information shall
be indicated for each Control Point: Identified (existing City Monument #8901, PK
Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an identified coordinate system,
and a referred bearing base. Z coordinate on City Datum only; descriptive location
(i.e. set in the centerline of the inlet in the South curb line of North Side Drive at the
East end of radius at the Southeast corner of North Side Drive and North Main
Street).
• Overall project easement layout sheets) with property owner information.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 4 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
• Overall project water and/or sanitary sewer layout sheets. The water layout sheet
shall identify the proposed water main improvement/ existing water mains in the
vicinity and all water appurtenances along with pressure plane boundaries, water
tanks, pump stations, valves, and fire hydrants. The sewer layout sheet shall
identify the proposed sewer main improvement/existing sewer mains and all
sewer appurtenances in the vicinity.
• Overall water and/or sanitary sewer abandonment sheet.
• Coordinates on all P.C.'s, P.T.'s, P.I.'s, manholes, valves, mainline fittings, etc.,
in the same coordinate system as the Control Points.
• Bench marks per 1,000 ft of plan/profile sheet —two or more.
• Bearings given on all proposed centerlines, or baselines.
• Station equations relating utilities to paving, when appropriate.
• Plan and profile sheets which show the following: proposed water and/or sanitary
sewer plan/profile and recommended pipe size, fire hydrants, water service lines
and meter boxes, gate valves, isolation valves, manholes, existing meter
numbers and sizes that are to be replaced, existing sample locations, existing fire
line locations, existing utilities and utility easements, and all pertinent information
needed to construct the project. Legal description (Lot Nos., Block Nos., and
Addition Names) along with property ownership shall be provided on the plan
view.
• The ENGINEER shall make provisions for reconnecting all identifiable water and/or
wastewater service lines which connect directly to any main being replaced,
including replacement of existing service lines within City right-of-way or utility
easement. When the existing alignment of a water and sanitary sewer main or
lateral is changed, provisions will be made in the final plans and/or specifications
by the ENGINEER to relocate all service lines which are connected to the existing
main and connect said service lines to the relocated main.
The following shall be applicable at all locations where it is necessary to relocate or
reroute the existing private sanitary sewer service line due to the abandonment or
realignment of the existing public sanitary sewer lateral or main: The CITY shall
furnish the ENGINEER with a sample format of how the sewer service line
reroute/relocation should be designed and submitted for construction. During
design survey, if a rod can be inserted through the cleanout to the bottom of the
service line, the ENGINEER will obtain the flow line elevation and design the
service line prior to advertising the project for bid. If the service flow line
information cannot be obtained during design survey, the ENGINEER shall delay
the design of the sewer service line until after a Quality Level A Subsurface Utility
Engineering (SUE investigation has been performed). The Level A SUE will be
performed; (1) by the ENGINEER if included in the fee proposal; or (2) by the CITY
prior to bidding if the CITY determines that it is needed for satisfactory completion
of the design; or (3) by the Contractor after the project has been bid, by means of a
bid item to that effect. In all options, the ENGINEER shall propose appropriate de -
hole locations in the project and collect flow line elevation and other applicable
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 5 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
information of the sewer service line. The ENGINEER shall use this information to
provide the design for the sanitary sewer service line to be rerouted or relocated.
Provide map showing location of new manhole construction at the end of existing
sewer segments, 90 degree bends, or tee connections. Site survey or specific
design plans for manhole construction is not included as part of the scope. The
contract documents shall specify that it is the Contractor's responsibility to
coordinate utility location, etc, manhole construction.
The ENGINEER will prepare standard and special detail sheets for water line
installation and sewer rehabilitation or replacement that are not already included in
the D-section of the CITY's specifications. These may included connection details
between various parts of the project, tunneling details, boring and jacking details,
waterline relocations, details unique to the construction of the project, trenchless
details, and special service lateral reconnections.
3.2. Geotechnicallnvestigation
Soil investigations, including field and laboratory tests, borings, related
engineering analysis and recommendations for determining soil conditions will be
made. In addition to the above investigations, borings and appropriate field and
laboratory analysis will be made at reasonable intervals along the project
alignment for the Contractor's use in determining soil conditions for preparing
bids and a Trench Safety Plan.
3.3. Constructability Review
• Prior to the 60 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
3.4. Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, private utilities and government agencies to determine the
approximate location of above and underground utilities, and other facilities
(current and future) that have an impact or influence on the project. ENGINEER
will design CITY facilities to avoid or minimize conflicts with existing utilities, and
where known and possible consider potential future utilities in designs.
• The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in Buzzsaw for
forwarding to all utility companies which have facilities within the limits of the
project. The DWF files should be created directly from the CAD files as opposed
to PDF files.
3.5. Traffic Control Plan
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 6 of 15
3.6
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
Develop a traffic control plan utilizing standard traffic reroute contigurations
posted as "Typicals" on the CITY's Buzzsaw website. The typicals need not be
sealed individually, if included in the sealed contract documents.
Develop supplemental traffic control drawings as needed for review and approval
by the Traffic Division of the Transportation and Public Works Department.
These drawings shall be sealed by a professional engineer registered in the
State of Texas.
Storm Water Pollution Prevention Plan
• For projects that disturb an area greater than one (1) acre, ENGINEER will
prepare the Storm Water Pollution Prevention Plan (SWPPP) required for the
Project for use by the Contractor during construction. ENGINEER will prepare
drawings and details for proposed SWPPP improvement that the Contractor must
use during construction. Contractor will be responsible for filing the SWPPP with
appropriate regulatory agencies.
ASSUMPTIONS
public meeting(s) will be conducted or attended during the preliminary
design phase.
0 borings at an average bore depth of feet each will be provided.
Traffic Control "Typicals" will be utilized to the extent possible. It is assumed an
additional project specific traffic control sheets will be developed for
sets of size plans will be delivered for the Constructability
Review.
1 sets of full size plans will be delivered for the Preliminary Design
(60% design).
1 sets of specifications will be delivered for the Preliminary Design (60%
design).
DWF files created from design CAD drawings will be uploaded to the designated
project folder in BUZZSaW.
The CITY's front end and technical specifications will be used. The ENGINEER
shall supplement the technical specifications if needed.
11 sets of half size drawings will be delivered for Utility Clearance.
ENGINEER shall not proceed with Final Design activities without written approval
by the CITY of the Preliminary Design plans.
DELIVERABLES
A. Preliminary Design drawings and specifications
B. Utility Clearance drawings
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 7 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM-D
CITY PROJECT NO.: 01929
C. Traffic Control Plan
D. Storm Water Pollution Prevention Plan
E. Estimates of probable construction cost
F. Data Base listing names and addresses of residents and businesses affected by
the project.
TASK 4. FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT).
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• Draft Final plans (90%) and speccations shall be submitted to CITY per the approved
Project Schedule.
• Following a 90% construction plan review meeting with the CITY, the ENGINEER shall
submit Construction Documents (100%) to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered in
State of Texas.
• The ENGINEER shall submit a final design estimate of probable construction cost with
both the 90% and 100% design packages. This estimate shall use ONLY standard CITY
bid items.
ASSUMPTIONS
2 sets of half size drawings and 1 sets of full size drawings and
1 specifications will be delivered for the 90% Design package.
A DWF file for the 90% Design will be created from design CAD drawings and will be
uploaded to the project folder in Buzzsaw.
1 sets of full size drawings and 1 specifications will be delivered for the
100% Design package.
A DWF file for the 100% Design will be created from design CAD drawings and will be
uploaded to the project folder in Buzzsaw.
[Engineer to provide estimated final sheet list (cover/index, general notes, control point
location, easement layout, SUE plan sheets, no. of plan/profiles, special detail sheets,
etc.)]
DELIVERABLES
A. 90% construction plans and specifications.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 8 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
B. 100% construction plans and specifications.
C. Detailed estimates of probable construction costs including summaries of bid items and
quantities using the CITY's standard bid items and format.
D. Original cover mylar for the signatures of authorized CITY officials.
TASK 5. BID PHASE SERVICES.
ENGINEER will support the bid phase of the project as follows.
5.1. Bid Support
• The ENGINEER shall upload all plans and contract documents onto Buzzsaw for
access to potential bidders.
• Contract documents shall be uploaded in a .xls file.
• Unit Price Proposal documents are to be created utilizing CFW Bidtools only
and combined in a specified spreadsheet workbook, Bid Proposal Worksheet
Template, and will be populated and configured so that all pages are
complete and the Summary Worksheet(s) in the workbook detail and
automatically summarize the totals from the inserted Unit Price Proposal
document worksheets.
• Plan Sets are to be uploaded to Buzzsaw in two formats, .pdf and .dwf files.
The .pdf will consist of one file of the entire plan set. The .dwf will consist of
individual files, one for each plan sheet, and will be numbered and named in
a manner similar to that of the plan set index.
• The ENGINEER shall sell contract documents and maintain a plan holders list on
Buzzsaw from documents sold and from Contractor's uploaded Plan Holder
Registrations in Buzzsaw.
• The ENGINEER will develop and implement procedures for receiving and
answering bidders' questions and requests for additional information. The
procedures shall include a log of all significant bidders questions and requests
and the response thereto. The log shall be housed and maintained in the
project's Buzzsaw folder titled Request for Information. The ENGINEER will
provide technical interpretation of the contract bid documents and will prepare
proposed responses to all bidders questions and requests, in the form of
addenda. The ENGINEER shall upload all approved addenda onto Buzzsaw and
mail addenda to all plan holders.
• Attend the prebid conference in support of the CITY.
• Assist the CITY in determining the qualifications and acceptability of prospective
contractors, subcontractors, and suppliers.
• When substitution prior to award of contracts is allowed in the contract
documents, the ENGINEER will advise the CITY as to the acceptability of
alternate materials and equipment proposed by bidders.
• Attend the bid opening in support of the CITY.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page9of15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
Tabulate and review all bids received for the construction project, assist the CITY
in evaluating bids, and recommend award of the contract. A copy of the Bid
Tabulation is to be uploaded into the project's Bid Responses folder on Buzzsaw.
• Incorporate all addenda into the contract documents and issue conformed sets.
5.2 Mylar Drawings
• The ENGINEER shall submit a set of sealed conformed mylar drawings for
record storage.
• Record Drawings shall also be submitted in both Adobe Acrobat PDF format
(version 6.0 or higher) format and DWF format. There shall be one (1) PDF file
and one (1) DWF file for the TPW plan set and a separate PDF and DWF file for
the Water plan set. Each PDF and DWF file shall contain all associated sheets
of the particular plan set. Singular PDF and DWF files for each sheet of a
plan set will not be accepted. PDF and DWF files shall conform to naming
conventions as follows:
I. TPW file name example — "W-1956_org47.pdf" where "W-1956" is the
assigned file number obtained from the CITY, "_org" designating the file is
of an original plan set, 1147" shall be the total number of sheets in this file.
Example: W-0053_org3.pdf and K-0320_org5.pdf
II. Water and Sewer file name example — "X-35667_org36.pdf" where "X-
35667" is the assigned file number obtained from the CITY, "_org"
designating the file is of an original plan set, "36" shall be the total number
of sheets in this file.
Example: X-12755_org18.pdf
Both PDF and DWF files shall be uploaded to the project's Record Drawing folder
in Buzzsaw.
For information on the proper manner to submit files and to obtain a file number for
the project, contact the Department of Transportation and Public Works Vault at
telephone number (817) 392.8426. File numbers will not be issued to a project
unless the appropriate project numbers and fund codes have been assigned and
are in the Department of Transportation and Public Works database.
ASSUMPTIONS
• The project will be bid only once and awarded to one contractor.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 10 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSMwD
CITY PROJECT NO.: 01929
45 sets of construction documents will be sold to and made available on
Buzzsaw for plan holders and/or given to plan viewing rooms.
1 sets of half size and 1 sets of full size drawings plans and
1 specifications (conformed, if applicable) will be delivered to the CITY.
• PDF and DWF files will be uploaded to Buzzsaw.
1 copy full size (22" x 34") mylar plans (conformed, if applicable) will be delivered
to the CITY.
DELIVERABLES
A. Addenda
B. Bid tabulations
C. Recommendation of award
D. Construction documents (conformed, if applicable)
E. Conformed mylar plans
TASK 6. CONSTRUCTION PHASE SERVICES.
ENGINEER will support the construction phase of the project as follows.
6.1 Construction Support
• The ENGINEER shall attend the preconstruction conference.
• After the pre -construction conference, the ENGINEER shall provide project
exhibits and attend public meeting to help explain the proposed project to
residents. The CITY shall select a suitable location and mail the invitation letters
to the affected customers.
• The ENGINEER shall visit the project site at requested intervals as construction
proceeds to observe and report on progress.
• As requested by the CITY, the ENGINEER shall provide necessary interpretations
and clarifications of contract documents, review change orders, and make
recommendations as to the acceptability of the work.
• The ENGINEER shall attend the "Final" project walk through and assist with
preparation of final punch list.
ASSUMPTIONS
RFI's are assumed.
Change Orders are assumed.
DELIVERABLES
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 11 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
A. Public meeting exhibits
B. Response to Contractor's Request for Information
C. Review of Change Orders
D. Review of shop drawings
E. Final Punch List items
F. Record Drawings
TASK 7. ROW/EASEMENT SERVICES.
ENGINEER will support and perform activities related to ROW and land as outlined below,
per scoping direction and guidance from the CITY's Project Manager.
7.1. Right -of -Way Research
• The ENGINEER shall determine rights -of -way, easements needs for construction
of the project. Required temporary and permanent easements will be identified
based on available information and recommendations will be made for approval
by the CITY.
7.2. Right-of-Way/Easement Preparation and Submittal.
• The ENGINEER shall prepare documents to be used to obtain right-of-way and
permanent and/or temporary easements required to construct the improvements.
• The ENGINEER shall submit the right-of-way and/or easement documents to
CITY PM for real property acquisition
• The documentation shall be provided in conformance with the checklists and
templates available on the CI I T s Buzzsaw site.
7.3. Temporary Right of Entry Preparation and Submittal
• Prior to construction, the ENGINEER shall prepare and submit Temporary Right
of Entry documents for landowners to CITY PM for real property acquisition. It is
assumed that letters will only be required for land owners adjacent to temporary
construction easements or who are directly affected by the project and no
easement is required to enter their property.
• The documentation shall be provided in conformance with the checklists and
templates available on the CITY's Buzzsaw site.
ASSUMPTIONS
1 Easements or right-of-way documents will be necessary.
15 Temporary right -of -entry documents will be necessary.
• Right -of -Way research and mapping includes review of property/right-of-way
records based on current internet based Tarrant Appraisal District (TAD)
information available at the start of the project and available on -ground property
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 12 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
information (i.e. iron rods, fences, stakes, etc.). It does not include effort for chain
of title research, parent track research, additional research for easements not
included in the TAD, right-of-way takings, easement vacations and
abandonments, right-of-way vacations, and street closures.
DELIVERABLES
A. Easement exhibits and meets and bounds provided on CITY forms.
B. Temporary Right of Entry Letters
TASK 8. SURVEY AND SUBSURFACE UTILITY ENGINEERING SERVICES.
ENGINEER will provide survey support as follows.
8.1. Design Survey
ENGINEER will perform field surveys to collect horizontal and vertical elevations
and other information needed by ENGINEER in design and preparation of plans
for the project. Information gathered during the survey shall include topographic
data, elevations of all sanitary and adjacent storm sewers, rim/invert elevations,
location of buried utilities, structures, trees (measure caliper, identify overall
canopy, and have qualified arborist identify species of trees), and other features
relevant to the final plan sheets. Existing drainage at intersections will be verified
by field surveys. Spot elevations will be shown on intersection layouts with cross
slope to fit intersecting grade lines.
The minimum survey information to be provided on the plans shall include the
following:
A Project Control Sheet, showing ALL Control Points, used or set while
gathering data. Generally on a scale of not less than 1:400:
The following information about each Control Point;
a. Identified (Existing. CITY Monument #8901, PK Nail, 5/8" Iron Rod)
b. X, Y and Z Coordinates, in an identified coordinate system, and a
referred bearing base. Z coordinate on CITY Datum only.
c. Descriptive Location (Ex. Set in the centerline of the inlet in the South
curb line of North Side Drive at the East end of radius at the Southeast
corner of North Side Drive and North Main Street).
— Coordinates on all P.C.'s, P.T.'s, P.I.'s, Manholes, Valves, etc., in the
same coordinate system, as the Control.
No less than two horizontal bench marks, per line or location.
Bearings given on all proposed centerlines, or baselines.
— Station equations relating utilities to paving, when appropriate.
8.2. Temporary Right of Entry Preparation and Submittal
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 13 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM•D
CITY PROJECT NO.: 01929
Prior to entering property, the ENGINEER shall prepare and submit Temporary
Right of Entry for landowners to CITY PM.
• The documentation shall be provided in conformance with the checklists and
templates available on the CITY's Buzzsaw site.
ASSUMPTIONS
Topographic survey at intersection will include no more than 100 ft. in each
direction.
DELIVERABLES
A. Copies of field survey data and notes signed and sealed by a licensed surveyor.
B. Drawing of the project layout with dimensions and coordinate list.
TASK 9. PLAN SUBMITTAL CHECKLISTS
Engineer shall complete and submit Plan Submittal Checklists in accordance with the
following table:
ru nwI ol IOwA1TTAl rucf'L!I ICT 1?1=n1 IIRFMFNTS
Attachment "A"
Type
Traffic
Signal
(Submit All
@ 30%)
Storm
Water
300M
Storm
Water
60%
Street
Lights
(Submit
All @
Water
/Sewer
(Submit
All @
Traffic
Engineering
(Submit All
@ 60%)
Traffic
Control
30%
Traffic
Control
60%
Traffic
Control
90%
Required for all work in City
30%
60%)
ROW
Street
X
X
X
X
X*
X
X X X
Storm Water
X
X
X X X
Water / Sewer
X
X X X
'`If included in street project
ASSUMPTIONS
DELIVERABLES
A.
Q
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 14 of 15
ATTACHMENT A
DESIGN SERVICES FOR
WATER AND SANITARY SEWER REPLACEMENT CONTRACT 2011 WSM-D
CITY PROJECT NO.: 01929
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services
described in the tasks above. However, ENGINEER can provide these services, if
needed, upon the CITY's written request. Any additional amounts paid to the
ENGINEER as a result of any material change to the Scope of the Project shall be
agreed upon in writing by both parties before the services are performed. These
additional services include the following:
• Negotiation of easements or property acquisition including temporary entries.
Services • Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre -qualification, bid protests, bid rejection
and re -bidding of the contract for construction.
• Construction management and inspection services
• Periodic site visits during construction phase
• Design phase public meetings
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of
God.
• Services related to warranty claims, enforcement and inspection after final
completion.
• Services related to submitting for permits (ie.TxDOT, railroad, etc...)
• Services related to Subsurface Utility Engineering Levels A, B, C or D
• Services related to Survey Construction Staking
• Services related to acquiring real property including but not limited to
easements, right-of-way, and/or temporary right -of -entries.
• Services to support, prepare, document, bring, defend, or assist in litigation
undertaken or defended by the CITY.
• Construction Shop drawing review, samples and other submittals submitted by
the contractor.
• Performance of miscellaneous and supplemental services related to the project
as requested by the CITY.
City of Fort Worth, Texas
Attachment A
PMO Release Date: 04.09.2012
Page 15 of 15
ATTACHMENT B
COMPENSATION
Design Services for
Water and Sanitary Sewer Replacement Contract 2011 WSM-D
City Project No. 01929
Lump Sum Project
Compensation
A. The ENGINEER shall be compensated a total lump sum fee of %P A64.00 as
summarized in Exhibit B-1 — Engineer Invoice and Section IV — Summary of Total
Project Fees. The total lump sum fee shall be considered full compensation for
the services described in Attachment A, including all labor materials, supplies,
and equipment necessary to deliver the services.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. Partial payment shall be made to the ENGINEER monthly upon City's approval of
an invoice prepared and submitted by the ENGINEER in the format and including
content as presented in Exhibit 13-1, Progress Reports as required in item III. of
this Attachment B, and Schedule as required in Attachment D to this Agreement.
B. The estimated current physical percent complete as required on the invoice shall
be calculated from the progress schedule as required in Attachment D to this
Standard Agreement and according to the current version of the City of Fort
Worth's Schedule Guidance Document.
C. The cumulative sum of such monthly partial fee payments shall not exceed the
total current project budget including all approved Amendments.
D. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Water Department monthly progress reports and schedules in the format
required by the City.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19.2010
Page 1 of 5
B-1
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm
Primary Responsibility
Fee Amount
Prime Consultant
Hamilton Civil
Engineering
Water/wastewater design
services
$971880.00
64.6
Proposed M/WBE Sub -Consultants
NEI
Spooner & Associates,
Inc.
Topographic Mapping and
Professional Surveying
services
$45,995.00
30.4
Non-M/WBE Consultants
ARC
Reproduction of plans and
specs
$ 71589000
5.0
TOTAL
$1511464,00
100%
Pro"ect Number &Name
Total Fee
M/VUBE Fee
M/WBE
Design Services For Water & Sanitary
$1511464.00
$451995000
30.4%
Sewer Replacement Contract 2011
WSM-D
City M/WBE Goal = 20%
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19.2010
Page 2 of 5
Consultant Committed Goal = 30.4%
B-2
EXHIBIT "0-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across work types and work phases.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19.2010
Page 3 of 5
B-3
��■ „ � E/mow"
;f;;\ƒ R0\\(§
G#vm0
o••W
m�0
\��
�
2
\
0
/
}
0
]
\
;
m
/
2
(
k
G
2
E
\
(
///
\
\
§
/
■
\�
\
(
/§
\
(
O
\
\
�
2
\
\
§
�
}
§
■
2
B
■
2
[
}E}]
f\
°z(
\/
CD
f(
(wu
\\\\�)\
ll
\/
CL
(CL
CD
CL
o
27
n n ,n2&e=0
/)))(/ § (fo 2
,00 J o[ r •
.. 2\
\2`
\
ƒ
�
/
EXHIBIT "B-2"
ENGINEER LEVEL OF EFFORT
(Supplement to Attachment B)
Insert level of effort following this page.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19.2010
Page 4 of 5
Exhibit B=2
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
Water and Sanitary Sewer Replacement Contract 2011, WSM=D
City Project No. 01929
Task No.
Task Description
Labor (hours)
Total Labor
Cost
Expense
Total Expense
Cost
Task Sub Total
Project
Director
Project
Manager
Project
Engineer
EIT
CARD
Administrative
Subconsultant
Travel
Reproduction
Rate
$160
$130
$120
$90
$75
$60
MWBE
Non-MWBE
1.0
Project Management
32
0
0
0
0
24
$6,560
$0
$0
$0
$192
$192
$6,752
1.1
IManaging the Team
1.1.1
Internal Team Meetings
$0
$0
$0
1.1.2
QA/QC
$0
$0
$0
1.2
Communications and Reporting
1.2.1
Pre -Design Coordination Meeting
2
$320
$0
$320
1.2.2
Design Submittal Review Meetings
2
$320
$0
$320
1.2.3
Prepare Baseline Schedule
4
24
$2,080
$120
$120
$2,200
1.2.4
Prepare Monthly Progress Reports with
Schedule
12
$1,920
$36
$36
$1,956
1.2.5
Prepare Monthly MWBE Reports
12
$1,920
$36
$36
$1,956
Conceptual Design (30-Percent)
84
0
0
0
0
0
$139440
$0
$0
$75
$151
$226
$13,666
Data Collection
24
$3,840
$75
$60
$135
$3,975
Conceptual Design Package
$91
$91
$91
N
Cover Sheet
8
$1,280
$0
$1,280
Exhibits and Summary
40
$6,400
$0
$6,400
Phasing
8
$1,280
$0
$1,280
2.2.4
Construction Estimate
4
$640
$0
$640
3.0
Preliminary Design (60 Percent)
278
0
0
0
0
0
$44,480
$0
$0
$50
$691
$741
$45,221
3.1
Preliminary Design Package
$600
$600
$600
3.1.1
Cover
6
$960
$0
$960
3.1.2
Overall Layout
16
$2,560
$0
$2,560
3.1.3
Plan and Plan/Profile Sheets
204
$32,640
$0
$32,640
3.1.4
Specifications
36
$5,760
$0
$5,760
3.1.5
Construction Estimate
8
$1,280
$0
$1,280
3.2
Constructability Review
4
$640
$50
$91
$141
$781
3.3
Utility Clearance
4
$640
$0
$640
4.0
Final Design
102
0
0
0
0
0
$16,320
$0
$0
$0
$755
$755
$172076
4.1
Final Draft (90%) Construction Plans and
Specifications
64
$10,240
$400
$400
$101640
4.2 lFinal
(100%) Plans and Specifications
36
1
1
$5,760
$350
$350
$6,110
4.3
Construction Estimates (90% and 100%)
2
$32000`
$5
$5
$325
5.0 113id
Phase
44
0
01
0
0
0
$7,040
$0
$0
$0
$5,295
$5,295
$12,335
City of Fort Worth, Texas
Attachment B -Level of Effort Supplement
PMO Official Release Date: 5.19.2010
Exhibit B=2
Level of Effort Spreadsheet
TASK/HOUR BREAKDOWN
Design Services for
Water and Sanitary Sewer Replacement Contract 2011, WSM=D
City Project No. 01929
Task No.
Task Description
Labor (hours)
Total Labor
Cost
Expense
Total Expense
Cost
Task Sub Total
Project
Director
Project
Manager
Project
En ineer
EIT
CADD
Administrative
Subconsultant
Travel
Reproduction
Rate
$160
$130
$120
$90
$75
$60
MWBE
Non-MWBE
5.1
Bid Support
5.1.1
Upload Documents to Buzzsaw
4
$640
$0
$640
5.1.2
Sell Contract Documents and Maintain
Plan Holders List
24
$3,840
$4,725
$4,725
$8,565
5.1.3
Issue Addenda
4
$640
$110
$110
$750
5.1 A
Attend Bid Opening
2
$320
$0
$320
5.1.5
Tabulate Bids and Recommend Award
6
$960
$10
$10
$970
5.2
Mylar Drawings
4
$640
$450
$450
$1,090
6.0
Construction Phase Services
14
0
0
0
0
0
$2,240
$0
$0
$50
$300
$350
$2,690
6.1
Construction Support
6.1.1
Attend Preconstruction Conference
2
$320
$25
$25
$345
6.1.2
Attend Public Meeting
2
$320
$25
$25
$345
6.1.3
As -Built Plans
8
$1,280
$300
$300
$1,580
6.1 A
Final Walk Through and Punch List
2
$320
$0
$320
7.0
ROW/Easement Services
12
0
0
0
0
0
$1,920
$0
$0
$0
$30
$30
$1,950
7.1
Right -of -Entry Documents
12
$1,920
$30
$30
$1,950
8.0
Survey
8
0
0
0
0
0
$1,280
$45,995
$0
$0
$0
$45,995
$47,275
8.1
Design Survey
8
1
$11280
$45,995
$45,995
$47,275
Totals
574
0
0
0
0
24
$939280
$45,995
$0
$1751
$7,4141
$53,584
$146,864
Description
WP
Water
Sewer
Conceptual Design
31
$14,619.00
$1,567.00
Preliminary Design
32
$50,965,00
$5,462,00
Final Design
33
$24,365,00
$2,611000
Survey
51
$46,853,00
$5,022,00
Subtotal
1$136,802,001
$14,662.00
Total
$151,464, 00
City of Fort Worth, Texas
Attachment B -Level of Effort Supplement
PMO Official Release Date: 5.19.2010
Project Summary
Total Hours
598
Total Labor
$93,280
Total Expense
$53,584
MWBE Subconsultant
$45,995
Non-MWBE Subconsultant
$0
10% Sub Markup
$4,600
MWBE Participation
30.4%
Total Project Cost
$151,464
EXHIBIT "B-3"
ENGINEER OPINION OF PROBABLE CONSTRUCTION COST
(Supplement to Attachment B)
Insert opinion of probable construction cost following this page.
City of Fort Worth, Texas
Attachment B
PMO Official Release Date: 5.19.2010
Page 5 of 5
B-5
ATTACHMENT " C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
Water and Sanitary Sewer Replacement Contract 2011 WSM-D
City Project No. 01929
NONE.
City of Fort Worth, Texas
Attachment C
PMO Release Date: 05.19.2010
Page I of I
`.
'.
OF
OF I
OF i
ILFee
Fee
• lj � ) ' r �rOF
1 i i � �� y r M !`
1-19
,.
OF poeIt
IF Am"I
IF
oe
i��Feel
1# 6 i i t
1 Fe- _
+ go fee��ft ti s �, i y�
I g 1 r'
iF
IL OF
o or'' �'OF
1 "
IF a
OF
"ir go
OF go mem.
OF If FF
CIF.
me
k I f . It.: �
to N41
't..tFemme
em
i`:� E �1'
OFF
Fee
�.
tr
`i ♦ IF We
i f : :r14 yyys
go
p Fee
x
�
r �
.!
tu ,
1 aFAIL
,
0 P.r. yil r
�,
OF
—�1;., I i _ Vz_..:3I,Tt,'
Me CA I l OF
1 r . to p
OF
—'I IF
fslr
ti
tub kr t , j,
' 9 l wI r q
Or or I OF
91411
- - - -- - - - - - e-:
ATTACHMENT E
Water and Sanitary Sewer Replacement Contract
2001 WSM-D
PAGE2OF2
Official site of the City of Fort Worth, Texas
OK`I' WOR'IAII
COUNCIL ANION: Approved on 7/10/2012 -Ordinance Nos. 20271-07-2012 and 20272-07-2012
DATE: 7/10/2012 REFERENCE NO.: **C-25704 LOG NAME. HA
HAMILTONTON
CODE: C TYPE. CONSENT PUBLIC NO
HEARING.
SUBJECT: Authorize Execution of an Engineering Agreement with Lawrence Jeffrey Hamilton d/b/a
Hamilton Civil Engineering in the Amount of $151,464.00 for Water and Sanitary Sewer
Replacement Contract 2011, WSM-D on Schadt Avenue, Market Avenue, Pearl Avenue,
Prospect Avenue, Columbus Avenue, Loving Avenue and Roosevelt Avenue and Adopt
Appropriation Ordinances (COUNCIL DISTRICT 2)
RECOMMENDATION:
It is recommended that the City Council:
1. Authorize the transfer of $182,464.00 from the Water and Sewer Fund in the amounts of
$154,802.00 to the Water Capital Projects Fund and $27,662.00 to the Sewer Capital Projects Fund;
2. Adopt the attached appropriation ordinances increasing estimated receipts and appropriations in
the Water Capital Projects Fund in the amount of $154,802.00 and in the Sewer Capital Projects
Fund in the amount of $27,662.00; and
3. Authorize the execution of a contract with Lawrence Jeffrey Hamilton d/b/a Hamilton Civil
Engineering in the amount of $151,464.00 for Water and Sanitary Sewer Replacement Contract
2011, WSM-D.
DISCUSSION:
This project consists of the preparation of plans and specifications for the replacement of the
deteriorated Water and/or Sanitary Sewer Mains as indicated on the following streets:
Streef
From
To
Scope of Work
Schadt Avenue
28St
Street
NE 3J-1
Street
Water/Sewer
Market Avenue
PNW
25thStreet
NW
26thStreet
Water
Pearl Avenue
25th
Street
NW
26tt'
Street
Water
Prospect Avenue
NW
26th
Street
Cliff
Street
Water
Columbus Avenue
NW
26th
Street
NW
27th
Street
Water
Loving Avenue
NW
26th
Street
NW
28th
Street
Water
Roosevelt Avenue
NW
25th
Street
NW
28th
Street
Water/Sewer
Lawrence Jeffrey Hamilton d/b/a Hamilton Civil Engineering proposes to perform the design work for
a lump sum fee of $151,464.00. Staff considers this fee to be fair and reasonable for the scope of
services proposed.
M/WBE — Hamilton Civil Engineering is in compliance with City's M/WBE ordinance by committing to
30 percent M/WBE participation. The City's goal on this project is 20 percent. Additionally, Hamilton
Civil Engineering is a certified M/WBE firm.
In addition to the contract amount, $31,000.00 (water: $18,000.00 and sewer: $13,000.00) is required
for project management, real property acquisition and utility coordination.
The project is located in COUNCIL DISTRICT 2.
FISCAL INFORM I ION/CERTIFICATION:
The Financial Management Services Director ceres that upon approval of the above
recommendations, and adoption of the attached appropriation ordinances, funds will be available in
the current capital budget, as appropriated, of the Water Capital Projects Fund and the Sewer Capital
Projects Fund.
70 Fund/Account/Centers FROM Fund/Account/Centers
1&2 1) PE45 538040 0609020 $154,802.00
P253 476045 6021701929ZZ $154,802.00
1) PE45 538040 0709020 $27,662.00
1 &2
P258 476045 7021701929ZZ $27.662.00 3)P258 531200 702170192931 1 567.00
2) P253 511010 602170192930 $10,000900 3) P258 531200 702170192932 $5,462,00
2) P253 531200 602170192931 $14,619,00 3) P258 531200 702170192933 2 611,00
2) P253 531200 602170192932 $50,965.00 3) P258 531200 702170192951 $5,022mOO
2) P253 531200 602170192933 $24,365,00 3)P253 531200 602170192931 $14,619.00
2) P253 541100 602170192941 5 000.00 3) P253 531200 602170192932 $50v965.00
2) P258 531350 602170192942 $2,000,00 3) P253 531200 602170192933 $24,365000
2) P253 531200 602170192951 $46,853400 3) P253 531200 602170192951 $46,853.00
2)P253 531350 602170192973 $1,000,00
2)P258 511010 702170192930 $5,000M
2) P258 531200 702170192931 $1,567,00
2) P258 531200 702170192932 5 462.00
2)P258 531200 702170192933 $2,611,00
2)P258 541200 702170192941 5 000.00
2) P258 531350 702170192942 2 000.00
2) P258 531200 702170192951 5 022.00
2)P258 531350 702170192973 $1,000,00
Submitted far City Manager's Office by:
Originating department Head:
Additional Information Contact:
ATTACHMENTS
6011 WSIVID-HAMILTON (V(AP 01.pdf
6011WSMD-HAMILTON MAP 02.pdf
6011WSMD-HAMILTON P253 AO12.doc
6011WSMD-HAMILTON P258 AO12.doc