HomeMy WebLinkAboutResolution 5333-01-2021 A Resolution
NO. 5333-01-2021
A RESOLUTION AUTHORIZING EXECUTION OF AN ADVANCED
FUNDING AGREEMENT WITH THE TEXAS DEPARTMENT OF
TRANSPORTATION IN THE AMOUNT OF $1,440,539.00, OF WHICH
LOCAL PARTICIPATION IS $658,225.00, FOR THE MCCART AVE &
ALTAMESA BLVD INTERSECTION IMPROVEMENTS PROJECT
WHEREAS, federal law establishes federally funded programs for transportation
improvements to implement its public purpose; and
WHEREAS, the Texas Transportation Code, Section 201.103 establishes that the
State shall design, construct and operate a system of highways and roads in cooperation
with local governments, and Section 222.052 authorizes the Texas Department of
Transportation Commission to accept contributions from political subdivisions for
development and construction of public roads within political subdivisions; and
WHEREAS, a Master Agreement between the City of Fort Worth ("Local
Government") and the State of Texas acting through the Texas Department of Transportation
("State") has been approved which states the general terms and conditions for Advance
Funding Agreements (AFA) for transportation projects and other projects; and
WHEREAS, the City of Fort Worth desires to enter into an Advance Funding
Agreement with the Texas Department of Transportation in the amount of$1,440,539.00, of
which $723,205.00 is federal participation, $59,109.00 is state participation and
$658,225.00 is local participation for the purpose of constructing the McCart Ave &
Altamesa Blvd Intersection Improvements Project.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF FORT WORTH, THAT:
The City Manager is authorized to execute an Advance Funding Agreement with the
Texas Department of Transportation in the total estimated amount of $1,440,539.00 with
City participation in the estimated amount of $658,225.00 for the purpose of constructing
the McCart Ave & Altamesa Blvd Intersection Improvements Project.
Adopted this 121h day of January 2021.
ATTEST
®�.............
R T�O
Mary J. Kayser
City Secretary ,t
�xAs
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 01/12/21 M&C FILE NUMBER: M&C 21-0029
LOG NAME: 20MCCART AVE AT ALTAMESA BLVD AFA
SUBJECT
(CD 6)Adopt a Resolution Authorizing Execution of an Advance Funding Agreement with the Texas Department of Transportation in the Amount of
$1,440,539.00 with Federal Participation in the Amount of$723,205.00, State Participation in the Amount of$59,109.00,and Local Participation
in the amount of$658,225.00 for the McCart Avenue and Altamesa Boulevard Intersection Improvements Project,Adopt Appropriation Ordinance,
Authorize Payment to the Texas Department of Transportation in the Amount of$249,463.00,and Amend the FY2021 -2025 Capital Improvement
Program
RECOMMENDATION:
It is recommended that the City Council:
1. Adopt the attached Resolution authorizing execution of an Advance Funding Agreement with the Texas Department of Transportation
(TxDOT)in the amount of$1,440,539.00 with Federal participation in the amount of$723,205.00,State participation in the amount of
$59,109.00,and Local participation in the amount of$658,225.00 for the McCart Avenue and Altamesa Boulevard project(TxDOT Control
Section Job No.0902-90-119,0902-90-192);
2. Adopt the attached appropriation ordinance increasing estimated receipts and appropriations in the Grants Capital Projects Federal Fund,
subject to receipt of the grant, in the amount up to$803,561.00 for the McCart Ave&Altamesa Blvd project(City Project No. 101572);
3. Authorize payment to the Texas Department of Transportation in the amount of$249,463.00 for the McCart Avenue and Altamesa Boulevard
project(City Project No. 101572);and
4. Amend the FY 2021-2025 Capital Improvement Program.
DISCUSSION:
The purpose of this Mayor and Council Communication(M&C)is to adopt a resolution authorizing execution of an Advance Funding Agreement
(AFA) (Control Section Job No. 0902-90-119, 0902-90-192)for this Highway Safety Improvement Program (HSIP) project with the Texas
Department of Transportation (TxDOT)and accept the federal grant funds for the construction in the amount not-to-exceed$723,205.00. After
submitting this intersection for HSIP consideration,it was selected to receive federal funds.
The project includes pedestrian safety and traffic signal improvements as well as pavement reconstruction of left-turn lanes to increase capacity.
The intersection improvements will provide orderly movement of traffic through the intersection while increasing safety for pedestrians and
vehicles.
Since this is a HSIP project,TxDOT will be letting the construction.They will absorb the indirect cost for providing statewide support services to
this federally funded project in the amount of$59,109.00. For this AFA, a 90% (federal)to 10% (local)match is required. Consequently,the
federal and local participation of the grant component are$723,205.00 and$80,356.00,respectively. In addition to the local participation,the City
will provide$577,869.00(available from M&C G-19306 2018 Bond Program)towards the AFA for engineering,environmental,and construction
as well as to cover additional City scope items identified during the preliminary engineering phase of this project. Before the start of construction,
an advanced payment to TxDOT is required in the amount of$249,463.00.The final payment to TxDOT for local participation will be based on
actual costs.
The following tables summarizes the funding history and the total costs for the project.
Funding History Summary for the McCart Ave&Altamesa Blvd project(City Project No. 101572)
Fund Federal State Local Appropriation M&C
Amount No.
2018 Bond Program-34018 :::][]EF,45OO:OOOO $3,450,000.00 G
19306
Transportation Impact Fee Capital Legacy Fund,Service 20-
Area W-39008 - - 11 $281,053.24 $281,053.24 II 0757
I
Transportation Impact Fee 10pital Fund,Service Area Y- _ _ F$281,053.24 $281,053.24 07 -
Subtotal $4,012,106.48 $4,012,106,48I—�
Additional Funding Considered in this M&C for the McCart Ave&
Altamesa Blvd project(City Project No. 101572)
Fund Federal State Local Appropriation
Amount
Appropriated
Federal Grant $723,205.00 - - $723,205.00
Match
Unappropriated
Indirect State - $59,109.00 - -
Cost
Appropriated
Local Grant - - $80,356.00 $80,356.00
Match
Unappropriated -
Local Match
Subtotal $723,205.00 $59,109.00 $658,225.00 $803,561.00
Total Project Costs for the McCart Ave&Altamesa Blvd project(City
Project No. 101572)
Fund Federal State Local
12018 Bond Program-34018 - - $3,369,644.00
Grants Capital Projects
Federal—31001
Transportation Impact Fee
Capital Legacy Fund, - - $281,053.24
Service Area W-39008
Transportation Impact Fee
Capital Fund,Service Area Y - - $281,053.24
-30108
Appropriated
$723,205.00 - -
Federal Grant Match
Unappropriated Indirect -
State Cost
Unappropriated Local Match
Total Project Cost with all funding sources both appropriated
and unappropriated: $5,372,289.48
This project is included in the 2018 Bond Program. Available resources within the General Fund will be used to provide interim financing until debt
is issued. Once debt associated with the project is sold, bond proceeds will reimburse the General Fund in accordance with the statement
expressing official Intent to Reimburse that was adopted as part of the ordinance canvassing the bond election(Ordinance No.23209-05-2018)
and subsequent actions taken by the Mayor and Council.
Construction is anticipated to start in August 2021 and finish August 2022.
Funding for this project was not included in the FY2021-2025 Capital Improvement Program due to the approval for federal Highway Safety
Improvement Program (HSIP)funds. The action in this M&C will amend the FY2021-2025 Capital Improvement Program as approved in
connection with Ordinance 24446-09-2020.
This project is located in COUNCIL DISTRICT 6.
A Form 1295 is not required because:This contract will be with a governmental entity,state agency or public institution of higher education:Texas
Department of Transportation
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds
will be available in the current capital budget,as appropriated,in the Grants Cap Projects Federal Fund,The Transportation and Public Works
Department(and Financial Management Services)will be responsible for the collection and deposit of funds due to the City.Prior to expenditure
being incurred,the Transportation&Public Works Department has the responsibility to validate the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Oriainating Business Unit Head: William Johnson 7801
Additional Information Contact: Monty Hall 8662
Lissette Acevedo 2722