Loading...
HomeMy WebLinkAboutContract 51918-CO3 CSC No.51918-CO3 FOP,T WORTH City of Fort Worth Change Order Request Project Name:1 Cultural District/Will Rogers Water and Sewer Improvements Part 6 City Sec No.: 1 51918 Project No.(s): 0600430-CO178010700430-CO1780 DOE No. N/A CityPrcj.No.:1 01468 Project Description: Water and Sanitary Sewer Main Installation on Crestline Dr.and Trinity Park Contractor: William J.Schultz,Inc.dba Circle C Construction Co. Change Order# 0 Date 1/7/2021 City Project Mgr.1 John R.Kasavich City Inspector: I Carmen Drake Phone Number: 817-392-8480 Phone Number: 817-392-8347 Dept. Water Sewer Totals Contract Time (Calender days) Original Contract Amount $1,424,716.00 $489,949.00 $1,914,665.00 425 Extras to Date $217,245.11 $217,245.11 0190 Credits to Date Pending Change Orders(in M&C Process) Contract Cost to Date $1,641,961.11 $489,949.00 $2,131,910.11 615 Amount of Change Order $0.00 $0.00 $0.00 120 Revised Contract Amount $1,641,961.11 $489,949.00 $2,131,910.11 735 Original Funds Available for Change Orders $169,711.00 $57,589.00 $227,300.00 89.00 Remaining Funds Available for this CO $57,589.00 $57,5 Additional Funding(if necessary) CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 11.35% MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25916) $2,393,331.25 JUSTIFICATION(REASONS)FOR CHANGE ORDER Change Order No.3 will provide an additional 120 calendar days on the project for the time it took to resolve pavement and grass restoration issues that were identified by the Parks Department for work that was conducted within Trinity Park. I i I I It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time and money)for all costs arising out of,or incidental to,the above Change Order. Contractor's Company Name Contractor Name Contract Si at re Date NllliarnJ.Schultz,Inc.dbaCircreCConsWctionCo. Teri Skelly pector Date Project Manager Date Director(Water Dept) Date Con truction Supervisor(Water Dept) Date I ,�o..�,b ue itmiiemcsn Jan 11,2021 Assistant City Attorney Date Assistant City Manager Date � Zbira Jan A,2021 ,��„�� ....„ Jan 14.2021 Council Action(If Required) OFFICIAL RECORD M&C Number N/A M&C Date Approved N A CITY SECRETARY FT. WORTH, TX o�a-r b a- City of Fort Worth Change Order Additions Project Name Cultural District/Will Rogers Water and Sewer Improvements Part 6 City Sec No.: 51918 Project No.(s): 0600430-CO1780/0700430-001780 DOE No. N/A City Proj.No.: 01468 Project Description Water and Sanitary Sewer Main Installation on Crestline Dr.and Trinity Park Contractor William J.Schultz,Inc.dba Circle C Construction Co. Change Order:= Date: 1!7l2021 City Project Mgr. John R.Kasavich City Inspector r Carmen Drake ADDITIONS DEPT Qty Unit Unit Cost Total Water Sewer Page 2 of 4 Additions Sub Total Fc3p,->c .r City of Fort Worth Change Order Deletions Project Name Cultural District/Will Rogers Water and Sewer Improvements Part 6 City Sec No.: 51918 Project No.(s): 0600430-CO1780/0700430-CO1780 DOE No. N/A City Proj.No.: 01468 Project Description Water and Sanitary Sewer Main Installation on Crestline Dr.and Trinity Park Contractor William J.Schultz,Inc.dba Circle C Construction Co. Change Order: F-3 ] Date 1/7/2021 City Project Mgr. John R.Kasavich City Inspector: Carmen Drake DELETIONS ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total _ Water Sewer Page 3 of 4 Deletions Sub Total IVIMBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Total $0.00 Previous Change Orders co# DATE AMOUNT i i i Total $0.00 Page 4 of 4 Contract Compliance Manager By signing I acknowledge that I am the person responsible for the monitoring and administration of this contract, including ensuring all performance and reporting requirements. Signature Name of Employee Title a ORr ATTEST; O� ...... �,a�� ��0 0 Mary J. Kayser d �c .00 ,d City Secretary daEXA`roQp OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX