HomeMy WebLinkAboutContract 54335-PM1PROJECT MANUAL FOR THE CONSTRUCTION OF TRINITY PARKS SINGLE-FAMILY RESIDENTIAL City Project No. 102606 IPRC RECORD NO. IPRC20-0033 FID NO. 30114-0200431-102606-E07685 FILE NO. W-2699 X FILE NO. X-26419 Betsy Price David Cooke Mayor City Manager Christopher P. Harder, P.E. Director, Water Department William Johnson Director, Transportation and Public Works Department Prepared for The City of Fort Worth PACHECO KOCH CONSULTING ENGINEERS, INC. 7557 RAMBLER ROAD, SUITE 1400 DALLAS, TX 75231 TX REG. ENGINEERING FIRM F-469 TX REG. SURVEYING FIRM LS-10008000 2020 July 23, 2020 07-23-2020 CSC No. 54335-PM1 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 1 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 SECTION 00 00 10 TABLE OF CONTENTS DEVELOPER AWARDED PROJECTS Division 00 - General Conditions Last Revised 00 11 13 Invitation to Bidders 03/20/2020 00 21 13 Instructions to Bidders 03/20/2020 00 41 00 Bid Form 04/02/2014 00 42 43 Proposal Form Unit Price 05/22/2019 00 43 13 Bid Bond 04/02/2014 00 45 11 Bidders Prequalification’s 04/02/2014 00 45 12 Prequalification Statement 09/01/2015 00 45 13 Bidder Prequalification Application 03/09/2020 00 45 26 Contractor Compliance with Workers' Compensation Law 04/02/2014 00 45 40 Minority Business Enterprise Goal 08/21/2018 00 52 43 Agreement 06/16/2016 00 61 25 Certificate of Insurance 07/01/2011 00 62 13 Performance Bond 01/31/2012 00 62 14 Payment Bond 01/31/2012 00 62 19 Maintenance Bond 01/31/2012 00 72 00 General Conditions 11/15/2017 00 73 00 Supplementary Conditions 07/01/2011 00 73 10 Standard City Conditions of the Construction Contract for Developer Awarded Projects 01/10/2013 Division 01 - General Requirements Last Revised 01 11 00 Summary of Work 12/20/2012 01 25 00 Substitution Procedures 08/30/2013 01 31 19 Preconstruction Meeting 08/30/2013 01 31 20 Project Meetings 07/01/2011 01 32 33 Preconstruction Video 08/30/2013 01 33 00 Submittals 08/30/2013 01 35 13 Special Project Procedures 08/30/2013 01 45 23 Testing and Inspection Services 03/20/2020 01 50 00 Temporary Facilities and Controls 07/01/2011 01 55 26 Street Use Permit and Modifications to Traffic Control 07/01/2011 01 57 13 Storm Water Pollution Prevention Plan 07/01/2011 01 60 00 Product Requirements 03/20/2020 01 66 00 Product Storage and Handling Requirements 04/07/2014 01 70 00 Mobilization and Remobilization 04/07/2014 01 71 23 Construction Staking 04/07/2014 01 74 23 Cleaning 04/07/2014 01 77 19 Closeout Requirements 04/07/2014 01 78 23 Operation and Maintenance Data 04/07/2014 01 78 39 Project Record Documents 04/07/2014 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 2 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 Technical Specifications which have been modified by the Engineer specifically for this Project; hard copies are included in the Project’s Contract Documents Division 02 - Existing Conditions Date Modified 02 41 13 Selective Site Demolition 02 41 14 Utility Removal/Abandonment 02 41 15 Paving Removal Division 03 - Concrete 03 30 00 Cast-In-Place Concrete 03 34 13 Controlled Low Strength Material (CLSM) 03 34 16 Concrete Base Material for Trench Repair 03 80 00 Modifications to Existing Concrete Structures Division 26 - Electrical 26 05 00 Common Work Results for Electrical 26 05 10 Demolition for Electrical Systems 26 05 33 Raceways and Boxes for Electrical Systems 26 05 43 Underground Ducts and Raceways for Electrical Systems Division 31 - Earthwork 31 10 00 Site Clearing 31 23 16 Unclassified Excavation 31 23 23 Borrow 31 24 00 Embankments 31 25 00 Erosion and Sediment Control 31 36 00 Gabions 31 37 00 Riprap Division 32 - Exterior Improvements 32 01 17 Permanent Asphalt Paving Repair 32 01 18 Temporary Asphalt Paving Repair 32 01 29 Concrete Paving Repair 32 11 23 Flexible Base Courses 32 11 29 Lime Treated Base Courses 32 11 33 Cement Treated Base Courses 32 11 37 Liquid Treated Soil Stabilizer 32 12 16 Asphalt Paving 32 12 73 Asphalt Paving Crack Sealants 32 13 13 Concrete Paving 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 32 13 73 Concrete Paving Joint Sealants 32 14 16 Brick Unit Paving 32 16 13 Concrete Curb and Gutters and Valley Gutters 32 17 23 Pavement Markings 32 17 25 Curb Address Painting 32 31 13 Chain Fences and Gates 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 3 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 32 31 26 Wire Fences and Gates 32 31 29 Wood Fences and Gates 32 32 13 Cast-in-Place Concrete Retaining Walls 32 91 19 Topsoil Placement and Finishing of Parkways 32 92 13 Hydro-Mulching, Seeding, and Sodding 32 93 43 Trees and Shrubs Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 33 01 31 Closed Circuit Television (CCTV) Inspection 33 03 10 Bypass Pumping of Existing Sewer Systems 33 04 10 Joint Bonding and Electrical Isolation 33 04 11 Corrosion Control Test Stations 33 04 12 Magnesium Anode Cathodic Protection System 33 04 30 Temporary Water Services 33 04 40 Cleaning and Acceptance Testing of Water Mains 33 04 50 Cleaning of Sewer Mains 33 05 10 Utility Trench Excavation, Embedment, and Backfill 33 05 12 Water Line Lowering 33 05 13 Frame, Cover and Grade Rings - Cast Iron 33 05 13.10 Frame, Cover and Grade Rings - Composite 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 33 05 16 Concrete Water Vaults 33 05 17 Concrete Collars 33 05 20 Auger Boring 33 05 21 Tunnel Liner Plate 33 05 22 Steel Casing Pipe 33 05 23 Hand Tunneling 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 33 05 26 Utility Markers/Locators 33 05 30 Location of Existing Utilities 33 11 05 Bolts, Nuts, and Gaskets 33 11 10 Ductile Iron Pipe 33 11 11 Ductile Iron Fittings 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 33 11 14 Buried Steel Pipe and Fittings 33 11 15 Pre-Stressed Concrete Cylinder Pipe 33 12 10 Water Services 1-inch to 2-inch 33 12 11 Large Water Meters 33 12 20 Resilient Seated Gate Valve 33 12 21 AWWA Rubber-Seated Butterfly Valves 33 12 25 Connection to Existing Water Mains 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 33 12 40 Fire Hydrants 33 12 50 Water Sample Stations 33 12 60 Standard Blow-off Valve Assembly 33 31 12 Cured in Place Pipe (CIPP) 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 4 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 33 31 22 Sanitary Sewer Slip Lining 33 31 23 Sanitary Sewer Pipe Enlargement 33 31 50 Sanitary Sewer Service Connections and Service Line 33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 33 39 10 Cast-in-Place Concrete Manholes 33 39 20 Precast Concrete Manholes 33 39 30 Fiberglass Manholes 33 39 40 Wastewater Access Chamber (WAC) 33 39 60 Epoxy Liners for Sanitary Sewer Structures 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 33 41 12 Reinforced Polyethlene (SRPE) Pipe 33 46 00 Subdrainage 33 46 01 Slotted Storm Drains 33 46 02 Trench Drains 33 49 10 Cast-in-Place Manholes and Junction Boxes 33 49 20 Curb and Drop Inlets 33 49 40 Storm Drainage Headwalls and Wingwalls Division 34 - Transportation 34 41 10 Traffic Signals 34 41 10.01 Attachment A – Controller Cabinet 34 41 10.02 Attachment B – Controller Specification 34 41 10.03 Attachment C – Software Specification 34 41 11 Temporary Traffic Signals 34 41 13 Removing Traffic Signals 34 41 15 Rectangular Rapid Flashing Beacon 34 41 16 Pedestrian Hybrid Signal 34 41 20 Roadway Illumination Assemblies 34 41 20.01 Arterial LED Roadway Luminaires 34 41 20.02 Freeway LED Roadway Luminaires 34 41 20.03 Residential LED Roadway Luminaires 34 41 30 Aluminum Signs 34 71 13 Traffic Control TXDOT Item 462 – Concrete Box Culverts Item 465 – Manholes and Inlets Item 466 – Headwalls and Wingwalls 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 5 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 Technical Specifications listed below are included for this Project by reference and can be viewed/downloaded from the City’s website at: http://fortworthtexas.gov/tpw/contractors/ or https://apps.fortworthtexas.gov/ProjectResources/ Division 02 - Existing Conditions Last Revised 02 41 13 Selective Site Demolition 12/20/2012 02 41 14 Utility Removal/Abandonment 12/20/2012 02 41 15 Paving Removal 02/02/2016 Division 03 - Concrete 03 30 00 Cast-In-Place Concrete 12/20/2012 03 34 13 Controlled Low Strength Material (CLSM) 12/20/2012 03 34 16 Concrete Base Material for Trench Repair 12/20/2012 03 80 00 Modifications to Existing Concrete Structures 12/20/2012 Division 26 - Electrical 26 05 00 Common Work Results for Electrical 11/22/2013 26 05 10 Demolition for Electrical Systems 12/20/2012 26 05 33 Raceways and Boxes for Electrical Systems 12/20/2012 26 05 43 Underground Ducts and Raceways for Electrical Systems 07/01/2011 26 05 50 Communications Multi-Duct Conduit 02/26/2016 Division 31 - Earthwork 31 10 00 Site Clearing 12/20/2012 31 23 16 Unclassified Excavation 01/28/2013 31 23 23 Borrow 01/28/2013 31 24 00 Embankments 01/28/2013 31 25 00 Erosion and Sediment Control 12/20/2012 31 36 00 Gabions 12/20/2012 31 37 00 Riprap 12/20/2012 Division 32 - Exterior Improvements 32 01 17 Permanent Asphalt Paving Repair 12/20/2012 32 01 18 Temporary Asphalt Paving Repair 12/20/2012 32 01 29 Concrete Paving Repair 12/20/2012 32 11 23 Flexible Base Courses 12/20/2012 32 11 29 Lime Treated Base Courses 12/20/2012 32 11 33 Cement Treated Base Courses 12/20/2012 32 11 37 Liquid Treated Soil Stabilizer 08/21/2015 32 12 16 Asphalt Paving 12/20/2012 32 12 73 Asphalt Paving Crack Sealants 12/20/2012 32 13 13 Concrete Paving 12/20/2012 32 13 20 Concrete Sidewalks, Driveways and Barrier Free Ramps 06/05/2018 32 13 73 Concrete Paving Joint Sealants 12/20/2012 32 14 16 Brick Unit Paving 12/20/2012 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 6 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 32 16 13 Concrete Curb and Gutters and Valley Gutters 10/05/2016 32 17 23 Pavement Markings 11/22/2013 32 17 25 Curb Address Painting 11/04/2013 32 31 13 Chain Fences and Gates 12/20/2012 32 31 26 Wire Fences and Gates 12/20/2012 32 31 29 Wood Fences and Gates 12/20/2012 32 32 13 Cast-in-Place Concrete Retaining Walls 06/05/2018 32 91 19 Topsoil Placement and Finishing of Parkways 12/20/2012 32 92 13 Hydro-Mulching, Seeding, and Sodding 12/20/2012 32 93 43 Trees and Shrubs 12/20/2012 Division 33 - Utilities 33 01 30 Sewer and Manhole Testing 12/20/2012 33 01 31 Closed Circuit Television (CCTV) Inspection 03/03/2016 33 03 10 Bypass Pumping of Existing Sewer Systems 12/20/2012 33 04 10 Joint Bonding and Electrical Isolation 12/20/2012 33 04 11 Corrosion Control Test Stations 12/20/2012 33 04 12 Magnesium Anode Cathodic Protection System 12/20/2012 33 04 30 Temporary Water Services 07/01/2011 33 04 40 Cleaning and Acceptance Testing of Water Mains 02/06/2013 33 04 50 Cleaning of Sewer Mains 12/20/2012 33 05 10 Utility Trench Excavation, Embedment, and Backfill 12/12/2016 33 05 12 Water Line Lowering 12/20/2012 33 05 13 Frame, Cover and Grade Rings – Cast Iron 01/22/2016 33 05 13.10 Frame, Cover and Grade Rings – Composite 01/22/2016 33 05 14 Adjusting Manholes, Inlets, Valve Boxes, and Other Structures to Grade 12/20/2012 33 05 16 Concrete Water Vaults 12/20/2012 33 05 17 Concrete Collars 12/20/2012 33 05 20 Auger Boring 12/20/2012 33 05 21 Tunnel Liner Plate 12/20/2012 33 05 22 Steel Casing Pipe 12/20/2012 33 05 23 Hand Tunneling 12/20/2012 33 05 24 Installation of Carrier Pipe in Casing or Tunnel Liner Plate 06/19/2013 33 05 26 Utility Markers/Locators 12/20/2012 33 05 30 Location of Existing Utilities 12/20/2012 33 11 05 Bolts, Nuts, and Gaskets 12/20/2012 33 11 10 Ductile Iron Pipe 12/20/2012 33 11 11 Ductile Iron Fittings 12/20/2012 33 11 12 Polyvinyl Chloride (PVC) Pressure Pipe 11/16/2018 33 11 13 Concrete Pressure Pipe, Bar-Wrapped, Steel Cylinder Type 12/20/2012 33 11 14 Buried Steel Pipe and Fittings 12/20/2012 33 12 10 Water Services 1-inch to 2-inch 02/14/2017 33 12 11 Large Water Meters 12/20/2012 33 12 20 Resilient Seated Gate Valve 12/20/2012 33 12 21 AWWA Rubber-Seated Butterfly Valves 12/20/2012 33 12 25 Connection to Existing Water Mains 02/06/2013 33 12 30 Combination Air Valve Assemblies for Potable Water Systems 12/20/2012 33 12 40 Fire Hydrants 01/03/2014 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 7 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 33 12 50 Water Sample Stations 12/20/2012 33 12 60 Standard Blow-off Valve Assembly 06/19/2013 33 31 12 Cured in Place Pipe (CIPP) 12/20/2012 33 31 13 Fiberglass Reinforced Pipe for Gravity Sanitary Sewers 12/20/2012 33 31 15 High Density Polyethylene (HDPE) Pipe for Sanitary Sewer 12/20/2012 33 31 20 Polyvinyl Chloride (PVC) Gravity Sanitary Sewer Pipe 06/19/2013 33 31 21 Polyvinyl Chloride (PVC) Closed Profile Gravity Sanitary Sewer Pipe 12/20/2012 33 31 22 Sanitary Sewer Slip Lining 12/20/2012 33 31 23 Sanitary Sewer Pipe Enlargement 12/20/2012 33 31 50 Sanitary Sewer Service Connections and Service Line 04/26/2013 33 31 70 Combination Air Valve for Sanitary Sewer Force Mains 12/20/2012 33 39 10 Cast-in-Place Concrete Manholes 12/20/2012 33 39 20 Precast Concrete Manholes 12/20/2012 33 39 30 Fiberglass Manholes 12/20/2012 33 39 40 Wastewater Access Chamber (WAC) 12/20/2012 33 39 60 Epoxy Liners for Sanitary Sewer Structures 12/20/2012 33 41 10 Reinforced Concrete Storm Sewer Pipe/Culverts 07/01/2011 33 41 11 High Density Polyethylene (HDPE) Pipe for Storm Drain 12/20/2012 33 41 12 Reinforced Polyethlene (SRPE) Pipe 11/13/2015 33 46 00 Subdrainage 12/20/2012 33 46 01 Slotted Storm Drains 07/01/2011 33 46 02 Trench Drains 07/01/2011 33 49 10 Cast-in-Place Manholes and Junction Boxes 12/20/2012 33 49 20 Curb and Drop Inlets 12/20/2012 33 49 40 Storm Drainage Headwalls and Wingwalls 07/01/2011 Division 34 - Transportation 34 41 10 Traffic Signals 10/12/2015 34 41 10.01 Attachment A – Controller Cabinet 12/18/2015 34 41 10.02 Attachment B – Controller Specification 02/2012 34 41 10.03 Attachment C – Software Specification 01/2012 34 41 11 Temporary Traffic Signals 11/22/2013 34 41 13 Removing Traffic Signals 12/20/2012 34 41 15 Rectangular Rapid Flashing Beacon 11/22/2013 34 41 16 Pedestrian Hybrid Signal 11/22/2013 34 41 20 Roadway Illumination Assemblies 12/20/2012 34 41 20.01 Arterial LED Roadway Luminaires 06/15/2015 34 41 20.02 Freeway LED Roadway Luminaires 06/15/2015 34 41 20.03 Residential LED Roadway Luminaires 06/15/2015 34 41 30 Aluminum Signs 11/12/2013 34 41 50 Single-Mode Fiber Optic Cable 02/26/2016 34 71 13 Traffic Control 11/22/2013 00 00 00 STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Page 8 of 8 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised March 20, 2020 Appendix GC-4.01 Availability of Lands GC-4.02 Subsurface and Physical Conditions GC-4.04 Underground Facilities GC-4.06 Hazardous Environmental Condition at Site GC-6.06.D Minority and Women Owned Business Enterprise Compliance GC-6.07 Wage Rates GC-6.09 Permits and Utilities GC-6.24 Nondiscrimination GR-01 60 00 Product Requirements END OF SECTION 00 42 43 DAP - BID PROPOSAL Page 1 of 7 1 3305.0003 8" Waterline Lowering 33 05 12 EA 2 $15,000.00 $30,000.00 2 3305.0109 Trench Safety 33 05 10 LF 2153 $0.50 $1,076.50 3 3305.1103 20" Casing By Other Than Open Cut 33 05 22 LF 54 $485.00 $26,190.00 4 3305.2002 8" Water Carrier Pipe - Ductile Iron Pipe (By Other than Open Cut) 33 05 24 LF 54 $88.00 $4,752.00 5 3311.0001 Ductile Iron Water Fittings w/ Restraint 33 11 11 TON 2 $4,500.00 $9,000.00 6 3311.0261 8" PVC Water Pipe (Open Cut) 33 11 12 LF 2099 $48.00 $100,752.00 7 3312.0001 Fire Hydrant including all appurtenances, 6" gate valves, and Fire Hydrant Leads 33 12 40 EA 3 $4,092.50 $12,277.50 8 3312.0002 Water Sampling Location 33 12 50 EA 2 $500.00 $1,000.00 9 3312.0117 Connection to Existing 4"-12" Water Main 33 12 25 EA 2 $3,200.00 $6,400.00 10 3312.2003 1" Water Service (Domestic) 33 12 10 EA 45 $1,300.00 $58,500.00 11 3312.2003 1" Water Service (Irrigation) 33 12 10 EA 2 $1,300.00 $2,600.00 12 3312.3003 8" Gate Valve 33 12 20 EA 2 $1,600.00 $3,200.00 13 3312.3005 12" Gate Valve 33 12 20 EA 1 $2,200.00 $2,200.00 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Bidder's Proposal Description Bid Quantity Unit Price Bid Value Project Item Information UNIT PRICE BID Bidder's Application Specification Section No.Unit of Measure Bidlist Item No. UNIT I: WATER IMPROVEMENTS $257,948.00TOTAL UNIT I: WATER IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version September 1, 2015 TRINITY PARKS CPN 102606 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 2 of 7 Bidlist Item No. UNIT PRICE BID Bidder's Application Specification Section No.Unit of Measure Bid Quantity Unit Price Bid Value Project Item Information SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Bidder's Proposal Description 1 0241.2013 Remove 8" Sewer Line 02 41 14 LF 277 $15.00 $4,155.00 2 0241.2201 Remove 4' Sewer Manhole 02 41 14 EA 2 $2,420.00 $4,840.00 3 3301.0002 Post-CCTV Inspection 33 01 31 LF 2640 $0.50 $1,320.00 4 3301.0101 Manhole Vacuum Testing 33 01 30 EA 14 $50.00 $700.00 5 3305.0109 Trench Safety 33 05 10 LF 2640 $0.50 $1,320.00 6 3305.0113 Trench Water Stops 33 05 15 EA 5 $300.00 $1,500.00 7 3305.0116 Concrete Encasement for Utility Pipes 33 05 10 CY 10 $1,300.00 $13,000.00 8 3305.0202 Imported Embedment/Backfill, CSS 33 05 10 CY 5 $1,200.00 $6,000.00 9 3305.1103 20" Casing By Other Than Open Cut 33 05 22 LF 114 $485.00 $55,290.00 10 3305.3002 8" Sewer Carrier Pipe - Ductile Iron Pipe (By Other than Open Cut) 33 05 24 LF 108 $88.00 $9,504.00 11 3331.3101 4" Sewer Service - SDR 26 PVC 33 31 50 EA 45 $1,225.00 $55,125.00 12 3331.4115 8" Sewer Pipe - SDR 26 PVC (Open Cut) 33 11 10, 33 31 12, 33 31 20 LF 1875 $58.00 $108,750.00 13 3331.4119 8" DIP Sewer Pipe (Open Cut) 33 11 10 LF 657 $88.00 $57,816.00 14 3339.0001 Epoxy Manhole Liner 33 39 60 VF 49 $250.00 $12,250.00 15 3339.1001 4' Manhole 33 39 10, 33 39 20 EA 11 $3,390.91 $37,300.00 16 3339.1002 4' Drop Manhole 33 39 10, 33 39 20 EA 1 $13,075.00 $13,075.00 17 3339.1003 4' Extra Depth Manhole 33 39 10, 33 39 20 VF 31 $500.00 $15,500.00 18 3339.1101 5' Manhole 33 39 10, 33 39 20 EA 2 $8,637.50 $17,275.00 19 3339.1103 5' Extra Depth Manhole 33 39 10, 33 39 20 VF 19 $600.00 $11,400.00 TOTAL UNIT II: SANITARY SEWER IMPROVEMENTS $426,120.00 UNIT II: SANITARY SEWER IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version September 1, 2015 TRINITY PARKS CPN 102606 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 3 of 7 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Bidder's Proposal Description Bid Quantity Unit Price Bid Value Project Item Information UNIT PRICE BID Bidder's Application Specification Section No.Unit of Measure Bidlist Item No. 1 3137.0101 Concrete Riprap 31 37 00 SY 1525 $71.63 $109,235.75 2 3137.0102 Large Stone Riprap, dry (12" Stone Riprap)31 37 00 SY 1500 $61.92 $92,880.00 3 3137.0104 Medium Stone Riprap, dry (8" Stone Riprap)31 37 00 SY 125 $55.00 $6,875.00 4 3305.0109 Trench Safety 33 05 10 LF 845 $0.50 $422.50 5 3341.0201 21" RCP, Class III 33 41 10 LF 192 $80.00 $15,360.00 6 3341.0205 24" RCP, Class III 33 41 10 LF 162 $90.00 $14,580.00 7 3341.1303 6x4 Box Culvert 33 41 10 LF 280 $362.00 $101,360.00 8 3341.1501 8x4 Box Culvert 33 41 10 LF 211 $496.59 $104,780.49 9 3349.0001 4' Storm Junction Box 33 49 10 EA 1 $5,000.00 $5,000.00 10 3349.1000 Headwall, Box Culvert 33 49 40 CY 150 $467.00 $70,050.00 10 3349.1002 21" Flared Headwall, 1 pipe 33 49 40 EA 1 $1,800.00 $1,800.00 11 3349.1003 24" Flared Headwall, 1 pipe 33 49 40 EA 1 $2,500.00 $2,500.00 12 3349.5001 10' Curb Inlet 33 49 20 EA 4 $4,500.00 $18,000.00 13 3349.5002 15' Curb Inlet 33 49 20 EA 2 $5,600.00 $11,200.00 14 3349.7002 5' Drop Inlet 33 49 20 EA 4 $3,000.00 $12,000.00 $566,043.74 UNIT III: DRAINAGE IMPROVEMENTS TOTAL UNIT III: DRAINAGE IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version September 1, 2015 TRINITY PARKS CPN 102606 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 4 of 7 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Bidder's Proposal Description Bid Quantity Unit Price Bid Value Project Item Information UNIT PRICE BID Bidder's Application Specification Section No.Unit of Measure Bidlist Item No. 1 0170.0100 Mobilization 01 70 00 LS 1 $15,000.00 $15,000.00 2 3125.0101 SWPPP ≥ 1 acre 31 25 00 LS 1 $7,500.00 $7,500.00 3 3201.0201 Asphalt Pvmt Repair Beyond Defined Width, Residential 32 01 17 SY 50 $255.00 $12,750.00 4 3201.0616 Conc Pvmt Repair, Arterial/Industrial 32 01 29 SY 200 $311.25 $62,250.00 5 3211.0400 Hydrated Lime (36 Pounds/SY/6")32 11 29 TN 102 $185.00 $18,870.00 6 3211.0501 6" Lime Treatment 32 11 29 SY 5685 $5.00 $28,425.00 7 3213.0102 7" Conc Pvmt (Residential Collector) - "Street A" 32 13 13 SY 5300 $62.12 $329,236.00 8 3213.0301 4" Conc Sidewalk 32 13 20 SF 6335 $7.00 $44,345.00 9 3213.0506 Barrier Free Ramp, Type P-1 32 13 20 EA 2 $1,800.00 $3,600.00 10 3217.0203 8" SLD Pvmt Marking Tape (W)32 17 23 LF 30 $150.00 $4,500.00 11 3292.0201 Utility Service Surface Restoration Seeding 32 92 13 SY 1000 $7.00 $7,000.00 12 3471.0001 Traffic Control 34 71 13 MO 6 $3,500.00 $21,000.00 UNIT IV: PAVING IMPROVEMENTS TOTAL UNIT IV: PAVING IMPROVEMENTS $554,476.00 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version September 1, 2015 TRINITY PARKS CPN 102606 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 5 of 7 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Bidder's Proposal Description Bid Quantity Unit Price Bid Value Project Item Information UNIT PRICE BID Bidder's Application Specification Section No.Unit of Measure Bidlist Item No. 1 3441.3201 LED Lighting Fixture 34 41 20 EA 10 $1,500.00 $15,000.00 2 3441.3351 Furnish/Install Rdway Illum TY 11 Pole 34 41 20 EA 10 $2,500.00 $25,000.00 $40,000.00 UNIT V: STREET LIGHTING IMPROVEMENTS TOTAL UNIT V: STREET LIGHTING IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version September 1, 2015 TRINITY PARKS CPN 102606 00 42 43_Bid Proposal_DAP 00 42 43 DAP - BID PROPOSAL Page 6 of 7 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM Bidder's Proposal Description Bid Quantity Unit Price Bid Value Project Item Information UNIT PRICE BID Bidder's Application Specification Section No.Unit of Measure Bidlist Item No. TOTAL UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS UNIT VI: TRAFFIC SIGNAL IMPROVEMENTS CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS - DEVELOPER AWARDED PROJECTS Form Version September 1, 2015 TRINITY PARKS CPN 102606 00 42 43_Bid Proposal_DAP QO 42 43 DAP - BID PROPOSAL Page 7 of 7 SECTION 00 42 43 Developer Awarded Projects - PROPOSAL FORM UNIT PRICE BID Bidder's Application Project Item Informalion Bidder's Proposal Bidlist Item No. Description Specification Section No. Unit of gid Quanrity Unit Price Bid Value Measure Bid Summary UNIT I: WATER IMPROVEMENTS $257,948.00 LJNIT II: SANITARY SEWER IMPROVEMENTS _,__ . _ __ _. _ _ $426,120.00 UNIT IIf: DI2AINAGE IMPROVEMENTS $566,043.74 UNIT N: PAVING IMPROVEMENTS ^'"� `-" ---- $554 476.00 UNTF V: STAEET LIGHTING IMPROVEMENTS $72,370.Q0 IJNIT VI: "PRAFFIC SIGNAL IMPROVEMENTS --. _._ TOtal COnst7'uctiOn Bid e, Qnc nrn n. This Bid is submitted by the entity named below: BIDDER: 5 a'€� €�aa�sfruefis�an C'€�sr.gt�n,r, Iac. 421 Com�taM Ave. Irving, TX 750G1 BX: �� E Ja� tsell TTTLE: Pro.jecY M1iazn� DATE: 7?? 6/7,02i' Contractor agrees to complete WORK for FINAL ACCEPTANCE within CONTRACT commences to run as provided in the General Conditions. END OF SECTION C7TY OF FORT WORTH STANDARIT WNSTRUCTION SPECIFICATION DOCUMF.NTS - DEVELpPER AWAR➢ED PROJECTS Form Version Sep[ember 1, 2013 110 working days after the date wben the TRINITY PARKS CPN 102606 00 42 43_Bid Proposal_DAP 3/12/2021 004526-1 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Page 1 of 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 SECTION 00 45 26 CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW Pursuant to Texas Labor Code Section 406.096(a), as amended, Contractor certifies that it provides worker's compensation insurance coverage for all of its employees employed on City Project No. 102606. Contractor further certifies that, pursuant to Texas Labor Code, Section 406.096(b), as amended, it will provide to City its subcontractor's certificates of compliance with worker's compensation coverage. CONTRACTOR: SYB Construction Co.. Inc. Company By: (Please Print) 421 Compton Ave Signature: Add ress /���� Irvin�, TX 75061 Title: Vice President City/State/Zip (Please Print) THE STATE OF TEXAS COUNTY OF TARRANT § § BEFORE ME, the undersigned authority, on this day personally appeared Brian Wood , known to me to be the person whose name is subscribed to the foregoing instrument, and acknowledged to me that he/she executed the same as the act and deed of SYB Construction Co., Inc. for the purposes and consideration therein expressed and in the capacity therein stated. GIVEN UNDER MY HAND AND SEAL OF OFFICE this 22ns day of JuIV , 2020. ..�..� `.�`PPYp�e,, SUSAN WOOD _?;�' �sNotary Public, State of Texas ; �, ;�'�� Comm. Expires 08-06-2022 q9r •...��;` .,EOF �. Notary ID 883832-3 ��in�n� Notary Public in and for the State of Texas END OF SECTION CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS Revised April 2, 2014 TRINITY PARKS CPN 102606 005243-1 Developer Awarded Project Agreement Pagelof6 1 SECTION 00 52 43 2 AGREEMENT 3 THIS AGREEMENT, authorized on 07/22/2020 is made by and between the Developer, ECM 4. Trinity, LLC, authorized to do business in Texas �"Developer") , and SYB Construction 5 Company, Inc. , authorized to do business in Texas, acting by and through 6 its duly authorized representative, ("Contracior"). 7 Developer and Contractor, in consideration of the mutual covenants hereinafter set forth, agree 8 as follows: 9 Article 1. WORK 10 Contractor shall complete all Work as specified or indicated in the Contract Documents for the 11 Project identified herein. 12 Article 2. PROJECT 13 The project for which the Work under the Contract Documents may be the whole or only a part 14 is generally described as follows: 15 TRIIV I TY PARKS 16 CITY PROJECT NO. 102606, FID# 30114-02�0431-102606-E07685, W-2699, X-26419 17 Article 3. CONTRACT TIME 18 3.1 Time is of the essence. 19 All time limits for Milestones, if any, and Final Acceptance as stated in the Contract 20 Documents are of the essence to this Contract. 21 3.2 Final Acceptance. 22 The Work will be complete for Final Acceptance within 110 working days after the date 23 when the Contract Time commences to run as provided in Paragraph 12.04 of the 24 Standard City Conditions of the Construction Contract for Developer Awarded Projects. 25 3.3 Liquidated damages 26 Contractor recognizes that time is of the essence of this Agreement and that Developer 27 will suffer financial loss if the Work is not completed within the times specified in 28 Paragraph 3.2 above, plus any extension thereof allowed in accordance with Article 10 29 of the Standard City Conditions of the Construction Contract for Developer Awarded 30 Projects. The Contractor also recognizes the delays, expense and difficulties involved in CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 102606 Revised June 16, 2016 005243-2 Developer Awarded Project Agreement Page2of6 31 32 33 34 35 proving in a legal proceeding the actual loss suffered by the Developer if the Work is not cornpleted on time. Accordingly, instead of requiring any such proof , Contractor agrees that as liquidated damages for delay (but not as a penalty), Contractor shall pay Developer Zero Dollars ($0.00) for each day that expires after the time specified in Paragraph 3.2 for Final Acceptance until the City issues the Final Letter of Acceptance. 36 Article 4. CONTRACT PRICE 37 Developer agrees to pay Contractor for performance of the Work in accordance with the 38 Contract Documents an amount in current funds of One Million Eight Hundred Seventy Six 39 Thousand Nine Hundred Fifty Seven Dollars and Seventy Four Cents ($1,876,957.74). 40 Article 5. CONTRACT DOCUMENTS 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 5.1 CONTENTS: A. The Contract Documents which comprise the entire agreement between Developer and Contractor concerning the Work consist of the following: 1. This Agreement. 2. Attachments to this Agreement: a. Bid Form (As provided by Developer) 1) Proposal Form (DAP Version) 2) Prequalification Statement 3) State and Federal documents (projectspecificJ b. Insurance ACORD Form(s) c. Payment Bond (DAP Version} d. Performance Bond (DAP Versionj e. Maintenance Bond (DAP Version) f. Power of Attorney for the Bonds g. Worker's Compensation Affidavit h. MBE and/or SBE Commitment Form (If required) 57 3. Standard City General Conditions of the Construction Contract for Developer 58 Awarded Projects. 59 4. Su pplementa ry Cond itions. CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 102606 Revised June 16, 2016 005243-3 Developer Awarded Project Agreement Page3of6 60 5. Specifications specifically made a part of the Contract Documents by attachment 61 or, if not attached, as incorporated by reference and described in the Table of 62 Contents of the Project's Contract Documents. 63 6. Drawings. 64 7. Addenda. 65 8. Documentation submitted by Contractor prior to Notice of Award. 66 9. The following which may be delivered or issued after the Effective Date of the 67 Agreement and, if issued, become an incorporated part of the Contract 68 Documents: 69 a. Notice to Proceed. 70 b. Field Orders. 71 c. Change Orders. 72 d. Letter of Final Acceptance. 73 74 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 102606 Revised June 16, 2016 005243-4 Developer Awarded Project Agreement Page4of6 75 Article 6. INDEMNIFICATION 76 77 78 79 80 81 82 83 84 85 . .. 87 88 89 90 91 92 93 94 95 6.1 Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the city, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the contractor, its officers, agents, employees, subcontractors, licenses or invitees under this contract. This indemnification provision is specifically intended to operate and be effective even if it is alle�ed or proven that all or some of the dama�es bein� sou�ht were caused, in whole or in part, by any act, omission or ne�li�ence of the city. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the city in defending against such claims and causes of actions. 6.2 Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the city, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the city, arising out of, or alleged to arise out of, the vvork and services to be performed by the contractor, its officers, agents, employees, subcontractors, licensees or invitees under this contract. This indemnification provision is specifically intended to operate and be effective even if it is alle�ed or proven that all or some of the dama�es being sou�ht were caused, in whole or in part, by any act, omission or ne�li�ence of the city. 96 Article 7. MISCELLANEOUS 97 7.1 Terms. 98 Terms used in this Agreernent are defined in Article 1 of the Standard City Conditions of 99 the Construction Contract for Developer Awarded Projects. 100 7.2 Assignment of Contract. 101 This Agreement, including all of the Contract Documents may not be assigned by the 102 Contractor without the advanced express written consent of the Developer. 103 7.3 Successors and Assigns. 104 Developer and Contractor each binds itself, its partners, successors, assigns and legal 105 representatives to the other party hereto, in respect to all covenants, agreements and 106 obligations contained in the Contract Documents. CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS — DEVELOPER AWARDED PROJECTS CPN 102606 Revised June 16, 2016 ECM- Trinity, LLC. Logan Hostin Treasurer 4010-7 N. Collins Street Arlington, TX 76006 July 22, 2020 Trinity Parks. t � t�0 62 13 - 2 PERFQRMANCE BC�N D Page 2 af 4 1 �xtension of the �Qr��ract th�t m�y b� gr�nted on the part of �he D�V�Ir�per �nd�'ar C�ty, then 2 this �obli�ation sh�l1 be �nd beccame r�url �nd vcaid, otherwis� to rem�in ir� f�all f�ar�e �nd �f���t. 3 PF�C�I/I�Et� FtJ�iHER� th�t i�f any I�g�l a�t�an be file� on this Bond, v�nue sh�ll lie ir� 4 T�rrar�t �ount�,1"e�c�s or th� Ur�ited States Dist�ri�t ��urt �r�r �h� IVorth�rn Dis�rict of Texasr Fort 5 W�rth'��Divisi�n. � This bond is nn�d� and ���cu�ed in compli�r��e with the proVisions o� Ch�pt�r ��53 af � th� i�x�s �overnrr�ent Cc�d�, as �mended, �nd �II liabiliti�s c�� this bond sh�al b� det�rmin�d ir� � ��c�rdanc� with �th� prc�visic�n� �f said �tatu�. 9 IIV 1,�iIT'NES� U1/HE�E�F, the �rit��ip�l and th� ��rety h�v� SI�N EC� �nd SE�ILEC� this �� �.� instrunnen� by duly authr�riz�d ���nts �r�d �f�icers o�1 thi� �he o� da �f !%� ___ __ Y 11 r 2D �� 12 �.3 �� 15 �� 17 1� 19 �U �1 �� 23 24 �� 2� 27 2S �iTT T: ___�- �, � o �,..�,,� ��rincip�lj ��cretary CITY 4F FfJRT IN4RTH STA�IDARD CITY Ct�IVDITlO(VS — DEVELUPER All��!lARDED PRCiJECTS Revised January 31, 2012 PF�IN�IP�AL: 5Y�► Canstru�tic�n �ampany, Ir�c. ��� Bl(: � � . � Sign���re �r��n '�l �r�d r Vdce Pr�s�d��t N�me ar�d Title Address: 421 Compton Av� � Ir�ing, T7C 75��1 i ri n iTy Pa rks City Project No. 102G�� � � 00�2�3-3 PERFQRMANCE BUN D Page 3 of 3 1 � 3 4 s � � � � �� 11 1� 13 14 �� 1G 17 1� 19 20 �1 �� 2� 24 �� � 1111 i�nes� �s �o Pr�in�ipal .., �� � � ,,,�.,,,.��� - �.,<��a �;. a �,� ��' �._. �� �M . . _ � 1`�itnes� �s to �u r�ty , S lJ R ETY: T�e H�no��r Insur�nc� Compan�y ��: ° � � .. . ���n��� r� J�cl�c I�'1 �rawley, �ttcarn�� ir� F��t _ �I�rr»�ndTitle Addr��so 44� Linc�alr� �tre�t �lV'+a rces�t� r, f1ll A�. U 1� �.5 ,' \ r.� � �� T�I�phc�ne IVuml�er: °� �"" *iVote: I� si�ne� by an Q�'ficer a� ti�e Sur�ty Cc�r�p�ny, there rr�ust be �n file � c�rtifi�d e��ract frvm the by-laws sh�vvir�� th�t �hi� p�rs�on has �uthcarit�r t� sign such obli�atior�. If Sur�ty's physic�l �ddr�ss is dif��r�nt from it� rr�ailin� address, both must b� providede The date �►f th� bc�rrd shall no�t be pri�r tc� th� d�t� th� Contract is a�arded. CITY aF F4�RT INORTH STANDARD CITY C�JND(TIONS — DEVELCJPER AINARDED PR4JECTS Revised January 31, 2012 Tri n itv P a rks Cifiy Project (Ua. 102506 Q� fi2 �.3 - 4 PERFURMANC� BfJND Page 4 of � CITY QF FaRT'W(JRTH Trinity Parics STANDARD CITY CQNDITIt�NS — DCVELQPER AlllfaRDED PR(JJECTS Cit� Project �lo. �.oz�o6 �evised January 31, 2012 Trinity Parks. � S U0�214-2 PAYMENT Bi�ND Page2af3 1 ther� �his ablig�tion shai� be ar�d b�cc�r�e null �nd �►oi�d; otherwise to r�m�in in full �forc� �nd 2 �f�ec�. 3 This bar�d is made �nd executed in �amplianc� v�rith the pr�visions o�f Chap��r ��53 af 4 th� Texas �ov�rr�m�nt �ode, �s amended, �nd �II liabiliti�s �n this bond sh�ll �� d�et�rmin�d ir� 5 �c��ardar�c� with th� provisior�s of said sta�ute. � ��I Vldl°fNE�� 1JIiHE�iE�F, th� Princip�l and Sur�t�+ hav� e�ch SI�NE9� ar�d SEALED this . . ,�,��► 7 ins�rur�n�n� by duly authc�riz�d �g�nts ar�� �ffic�rs �n this� th� o�o� d�y �f � IV � p 2 � �+0 . � �TTE�T: �' �� / � �'' ��rincip�l� S�cr���ry Vtlitn�ss �s tc� Principal C IiY (� F FO FiT VIlO RTH �TA(�DA�D CITY Ct�NDITIUNS — DEVELOPER A�IIARDED PROJECTS Revised January 31, 2012 � ,� � , � � �- ���`� �.����tr����s�ar�s ��t���r��� ����. � � BY : Si�natur+� � _Brian 1l�vod, V�c� Pr�sid�r�t �lam� ar�c� Titl� A�dre�s: 421 Comptaro ��ve Irr�ing, Tx 750�1 � U R ET�(: The Hanaver In�urance Company T ri n ity P a rks City Praj�ect No. 1026Q� e i 00 �2 �� - � PAYMEIVT BQND Page3of3 �TTEST: �� : .� � �i�n�ture ��ck 11� Cr�v�l�y, A�torn�y ir� F�ct IV�n�� �r�d Titl� �.�.,�.�.�.__.. ,�..,d�� ��� ���,,� ���„„� �� ���f W � ��� �� ✓ Wi��n°�s� �� t� �u et�y �ddr�ss: �-4�� Lir�cc�ln �tre�t �%tt71"C��t�i", �� � �.� �.� T�I�phone� �I� rr� ber: _��0-�a�-��.�1 0 � IVot�. af sign�d by a n o�ff i��r o� the Su r���, th�r� ��st be �n -�i le � certif ied e�tr��t �r�arn �th� 3 k�yl�w� sho�in� th�t th�s p�r�c�n h�s a�atharity to �i�n such c�blig�tior�. If ��urety's ph�si��l 4� �ddr�ss i� dif��re�t �From its r�ailin� ad�r�ss, bo�th m�st be provi��d. 5 � � 8 The d�te o� the b�n� sh�ll n�t b� �rior �� �he dat� �h� C��tra�ct i� �w�rd��. ,r � � CITY aF FfJRT 1NC�RTH STANDARD CITY CC�NDITI�NS — DEVELCJPER AWARDED PRCJJECTS Revised January 31, 2012 Trinity Parks City Project No. 10260G Trinity Parks Trinity Parks Trinity Parks Trinity Parks Trinity Parks iHE HAIVi�VER IN�URAN�E �C?MP'�41V1� � Y M�iS�ACI-IUaETTS BAY IiV�IJRAtNCE C�.iMPANY CITI�ENS IN�lJ�NC� GC�M�AiUY CiF AMERICA J�'C� I/ti/�� �� �4 7`T+�►1411�EY iHl� Power cr� Attorr�ey limi�ks fih�e �cts of those named herei�, �nd they h�Ue nc� ata�khority to bind the �om�a�r�y excep� in �he mar�ner �nd io �khe ex�er�� her�in sfia�ted. KNC�Vlf �L.L PEI���I�S BY iHIE�'� P'RE��N"iS: That THE HANC�VER INSURANCE C(JMPANY�nd MA�SACHUSETT� BAYINSURAN�E CCJMPANY, both being corporatians arganized and existing und�rthe laws of the State o� New Hampshire, and CITIZENS IN�URANCE CtJMPANI�t�F�(1�ERI�A, a carp�ratic�n vrganized and exi�ting under�he I�vv� af th� Sfiafie of Michigan, �hereinafter individually and collectively the "�ompan�') daes hereby canstitute and appaint, �t�v�r� I�� Fo�t�r, Jack M. +Cr+awl�y, L��ri� P�lu� 9�nd T�u�� Luri C�f 1Nillis 'Tt�w�r� "41VV�t.��►n Ir�s�Ir�r�ce ��r�ri�e� W+�s�, 6r��c t�� C�al9��, TX each indi�idu�lly, if there be more than ane nam�d, as its true �nd lawful atiarney{�}-in- fact ta �ign, execute, seal, acknowl+�dge and deliver �For, �nd on its behalf, and as its �ct and deed any �lace wi�hin the Unite�l �tat�s, �ny and all surety b�nd�, re�cogni�ance�, undertakings, or Qther �uret�r obligations�. The execution af such sur��y bands, recogr�izance�, under�akings ar surefiy obligaiion�, in pursuance of these pre�ents, shall be as bin�ing upan �he �ompany as if they had been duly signed by the president and atteste�d by th� secretary of the Comp�ny, in their tawn proper persans. Provided how�v�r, that this pawfer ofi �ttorney limits the a�t� o�' thQse named herein; �nd they haVe no au�hority to bind the Company except in th� manner stafied and ia the extent af any limiiatian ���t�d below: �n� such obligations in th� IJnited �tat�s, not �o �xceed Thir�y Fi�r� �lillio�r ancl Na1�IQ0 ��35,�00,000} in �ny singde ins�tartce That �his power is rr�ade and executed pursuant ta the authority af the following Resolufiion� p��s�d by the B�ard ofi Director� af s�id Gampany, and said Resalutions r�main in full farce and effec�: RE�OLVED: That the Pr�siden� ar any Vice Pre�ident, in conjunctian with any Vice President, b� and th�y hereby are authorized and empowered ta appoint Attorneys-in-fact of the Carr�pany, in its n�me and as it a�s, �o execute and �cknawledge for and on its behalf as suret�, any and all b�nds, recogni�ances, cor�firac�s vf indemni�y, waivers afi citation and all afiher writings obligatory in the nature therevf, vvi�h pouver to �ttach fihereto the �+�al of the Campany. �n}� such writings �o executed by such Attarneys-in-fa�t �hall b� binding upon the Campany as if they had been duly �xecuted and acknowledged �y the regularly elected 4�Ffic�r� of the �om�aany in fiheir awn proper persons. RE�t�LVED: That any and all Powers vf Attorney �nd �eri;ified �opies af such ('owers af Attorney and cerfificafiio�r in re�pect fihereto, c�ranted and execut�d by fihe President o� Vic� Presid�nt in �onjuncfiion with any Vice Presiden� of fihe ��mp�ny, shall be binding on the Company fio the same �xtent as if �II signafiures �herein were manu�lly affi�ced, even though one or more of �ny such sigr�ature� thereon may be fac�imile. �A�opted Octa�er 7, 1�81 — The Hanaver Insurance Gompany; Adapied April 1�, 1982 — Massachu��tfis Bay Insur�nce �arr�pany; Adop�ed �epiennb�r �, ��Gi —�i�izens Insuranc� Cor�n�any o� America and affirmed by each Cc�mpany on IUlarch 24, 2014) IN V1JIl"NES� WHE�;Ec�F, THE HANt�VER IN�URANCE Ct�IVIPANY, MA�SACHUSEiTS BAY INSUF�ANCE CC�MP�ONYanr� �ITIZEf�� IN�Uf�AN�E CtJMPANY�F AMERICA have �au�ed these presents �to kre �e�led with tt�eir re�p�c�tive carpor�te seal�, duly at��sted by finro Vice Presid�nfi�, this �Ot"' day of Janu�r�, 2020. �"�� �f����:��. ���� � ��:��"��� ��� ������� ��������� ������ . �a�;���.�w������"� '"� t ����� ����`���"' �!���a��'�����°"�`� ���` ���.� �������" ������ ��"�'1���� .����� '� � ��.;���' �� ������,� ���'����� ���'���:��� ������'� �� ,������� ���� ��������� .»� �� !� �� � '��?�i�+�i�'�'��l�e�.�� �� �a���i�,�� ������ � +����� �� ��������� � ��.. �t���'�► �����+�� _�F ".� .� . . +•��� * } ''�{, ......<� ,�� .� ��: �,>..+�,+, �n thi� "�fl��' �fa�r +�� .��r��a�r-�3 ��2� b���s�� r�� ���� ��� ����� ��rr��d �����i��� �`i��: �'r��i��r�i a�d ti"i�� �re�id�r�i �f �"h� H�n��r�r Irr�u�r�r�c� �vr�npany, I�I�����h�ts��t� ���r �r��ur���� ���p��� �n� ��#����� ������r�� ��sr���n� �� ���-i��., �� �� p����r��fl�r �Cr��a�r� �� i�� �h� ��o�i����a�a� �nd ��irer� d���rib�� h�r�in, �nd �ck�c�wledg�� ���� �h� ��a�� ��i��� �t� ��� pr���dir�� �r���r���r�� �r� th� �ra��p�r�t� ���i� �� i�� ������r fn�ur�r�� ��a�r�p�r��r, �'I����c(��a���ts E��y In��r�r�ce Company �nd �itize�n� Ins��r�n�� �cat�np�n� �►� �r��ri��, �•������i�r�i�, �r��l ���� �h� ��i� ��rp�r��� ���1� �r��i th�ir �i�r��t�r�s �� �i�ic��� �r� �c�l� �fi�ix�d �r�d subs�rik�ed to s�aid instrum�nt b� th� �uthc�ri� ar�c# �dir����aas� �f ���� ��r��r��i�r��. ._ . . . � ������� �ti ������ ��a��� ��k���� ' ������� �� ����� �� ���������� ������� ��a�� � �t ����:� ,,� � � . � � ,.,�«,.�..�,�,. �i���� "�', �'�1���"1�� ����� � i� ?��t ��1"ii��i����� �.��1i"�� �R��� °� �, ���� �` � I, the undersigned Vice Pr��id�nt ��' Th� I��r�av��� In��r�r�+c� ���np�n�r, I�Ia���c�u��tf.� €��� lr�sur�nce �c�r�rpat�� a�d �ifii��ns Insur�nce Company�f A►rr�eri�ca, hereby c�r�ify that the above and �c�r�goin� is � f�Il, tru� �r�� r.�rr��t �c��� ��F th� �r�ig�nal Paw�r of �t�arr�ey i��ued by ��id ��rr�p�r�ie�, �n� do her�by further cerkify that the said Power� af Att�rney �r� sti�! in fi�rce �r�d ef���. �IVEN under my har�c� �r�d the ���l� of s�id �+���n �ni��, a� ��r�����r�, lttf��s��hus��s thi� �d ��' �VL. � , �� � A � t7 ,a � +�ET�..TIFIE�II� �; �P� ��� �������,������� ������� � �������� ��� ��������� ������� �� �� ���� , � ���� �F ������� �r�' � ., R ' ... _ .. ��. ., y: �� : ���� �._ . .. � � � #. �ar�r�+�� � ���g�a,. , �i�i�a�t . ., � Zil� ,� �M° TMe Hanover Insurance Campany � 444 Lincoln �tr�e� Worcester, �111A a1 �53 ,.�..,._ � � �� . . Ins�r�ne� �rc��.p'� C"..itizens Insurar�ce Camp�rty of America � 5�-5 West �rand Riv�r Avenue, Hawell, MI 48843 ���� ��}i�1��i�1�'1'� ��"�1+C� I � P� R.T�I�1" �1C�°TI�E T� ab�ain inf�rm�tion �ar ma�l<e a c�mpl�.int: Y'ou may �all The H�,nover Insuran�� C�r�pan�/�iiiz�r�s Ins�rar�ce �orr�pany of �1r�eric�.'s tall-fr�� t�l�p�h�r�e numb�r fo� ir�forrr�a�ioro or t� rr�al<� � c�ompl�.ir�� �.�: l � ��� � - Para� obt�n�� ir���rma�ion � par� s�rr�e��� ur�� qu�j�.� l�sted puede Ilamar �.I nur��ro d� tele��no ,�r�.�is d� 1�he I��,na�er Ir�sur�,r�c� ��amp�.ny/�a�ti��r�s Ir�surar�c+� ��mpan� �f America"s p�,ra, ir�f�rm�cion c� para sor���er ur�a �u�ja al: i • � r � � r '� :. i�� �r�� i �: 1���a m�,y �ls� write t� ih� Har��rrer Ir�s�r�.nc� �c�mpar�y/ l��ied t�rr�bi�r� pu�d� �s�ribir a l�h� I�a,r���v�r Insur�r��� ��ti��r�s Ins�r�.��� �Qrr�pany �f �Am�ri�a a�: �ar�pany/�i�iz�i�s Insura��e �ompar�y �� Arr�eri�a �.I� 44� Lir�coln ��r��t 11�'�r���te�F M.� C�1 �1 � ��+� L i n cc� I n Str�e�t V V�������r� 1 V 1� �� � 1� 1��� r��,y �ar��a�� the T��cas Departrr��r�t af Ins�arar�c�e to �btain i�►forr�ation. �n c�n�p��.rtiesF ��v�ra�es, righ�� o� ��r�n�l�ir�ts ��t� : � �; C � ': �'ou m�,y wri�e the T���.s C����.rir�en� c�� Ir�s�ar�r���: P. �. ���c 14�1 �4 A.u��ir�,1�.� ��714-�1�� F�,�c: ��12� 4i5-1�i1 �lll� b : htt p .//wwvv.t� � ot��a,� .�c�� E-r��.il: ��ans�ar��rP���t��ti�r�(c�idi.siate.�.us r r: �; r � , � _ r Sh�uld ��u ha�� a d�spuie c�r�+�e��in� y�ur pr�r�iurr� �r �b�ut a�lair� y�u sh�uld c�n�a�� th� a,��r�� c�r the �on�- p�,r��r first. pf the d�s�ut� is not r���lv�d, ya� r��.y cont�.ct ihe T��a,s C�epar�i�ent of I nsu ran��. �Ti�►�H iHl� I��T'I�E 1'� �`�IJR. pC�LI�: Th�s n�ti�� is f�ar ir�f�rr�r�ation �n�y �,n� does nc�i be��m� a pa�� c�r con- ditior� of th� a�ta��h�d d��um�r�t. P���� ��municar�� �o� el C�e�ar��r�ner��o d� .���ur�s d� T���.s �a��. abt�n�r i�1fc��r�a�ior� a��r�a d� �c�r�par�ias, ��b�rt�ras� d�r�ch�s �► q����.� ai: .: 1 � .� � Pued� e��ribir �.I C��p�.r�ar�+�r�io c�� .����arc�s d� Te��,s: �. C�. �o� 1 �91 C�4 .�.ustir�, T� 7�i1�-�1�D�4 F�,�: ��12� 4�i�-1�71 �'� k� : I��tp ://v�r�.td i .�e��,s .�c�v E-mai�: �or�surner�r�t���ic�r��t�i.state.t��us ," i � ;� � � r � '� � s � � �i �.i�r�e un�, disp��a �c�r�cerni�rtt� a, �u prir�a o a�n rec- lamo, �ebe �omuni�ar�� �c�n �I �,��nte o la companaa� prirr�er�. Si no s� r�su�lve la di�puta� pue�e en��r�c�� ��rr�uni�ars� ��n el d�par�arri��to �TDI}. lJ�l� E�iE �4"1�15� �4 �l�I ��LI�Z�4: Esie �.vdsc� es s�l� para prc���sitt� d� infiormacian y no se c�nvi��� �n p�.rte o ��r�dicion ��I �docum�nto adjunto. 181-1457 (5/1� CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 STANDARD CITY CONDITIONS OF THE CONSTRUCTION CONTRACT FOR DEVELOPER AWARDED PROJECTS TABLE OF CONTENTS Page Article 1 – Definitions and Terminology .......................................................................................................... 1  1.01 Defined Terms ............................................................................................................................... 1  1.02 Terminology .................................................................................................................................. 5  Article 2 – Preliminary Matters ......................................................................................................................... 6  2.01 Before Starting Construction ........................................................................................................ 6  2.02 Preconstruction Conference .......................................................................................................... 6  2.03 Public Meeting .............................................................................................................................. 6  Article 3 – Contract Documents and Amending ............................................................................................... 6  3.01 Reference Standards ..................................................................................................................... 6  3.02 Amending and Supplementing Contract Documents .................................................................. 6  Article 4 – Bonds and Insurance ....................................................................................................................... 7  4.01 Licensed Sureties and Insurers ..................................................................................................... 7  4.02 Performance, Payment, and Maintenance Bonds ........................................................................ 7  4.03 Certificates of Insurance ............................................................................................................... 7  4.04 Contractor’s Insurance .................................................................................................................. 9  4.05 Acceptance of Bonds and Insurance; Option to Replace ........................................................... 12  Article 5 – Contractor’s Responsibilities ........................................................................................................ 12  5.01 Supervision and Superintendent ................................................................................................. 12  5.02 Labor; Working Hours ................................................................................................................ 13  5.03 Services, Materials, and Equipment ........................................................................................... 13  5.04 Project Schedule .......................................................................................................................... 14  5.05 Substitutes and “Or-Equals” ....................................................................................................... 14  5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) ..................................... 16  5.07 Concerning Subcontractors, Suppliers, and Others ................................................................... 16  5.08 Wage Rates.................................................................................................................................. 18  5.09 Patent Fees and Royalties ........................................................................................................... 19  5.10 Laws and Regulations ................................................................................................................. 19  5.11 Use of Site and Other Areas ....................................................................................................... 19  5.12 Record Documents ...................................................................................................................... 20  5.13 Safety and Protection .................................................................................................................. 21  5.14 Safety Representative ................................................................................................................. 21  5.15 Hazard Communication Programs ............................................................................................. 22  5.16 Submittals .................................................................................................................................... 22  5.17 Contractor’s General Warranty and Guarantee .......................................................................... 23  CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.18 Indemnification ........................................................................................................................... 24  5.19 Delegation of Professional Design Services .............................................................................. 24  5.20 Right to Audit: ............................................................................................................................ 25  5.21 Nondiscrimination....................................................................................................................... 25  Article 6 – Other Work at the Site ................................................................................................................... 26  6.01 Related Work at Site ................................................................................................................... 26  Article 7 – City’s Responsibilities................................................................................................................... 26  7.01 Inspections, Tests, and Approvals .............................................................................................. 26  7.02 Limitations on City’s Responsibilities ....................................................................................... 26  7.03 Compliance with Safety Program ............................................................................................... 27  Article 8 – City’s Observation Status During Construction ........................................................................... 27  8.01 City’s Project Representative ..................................................................................................... 27  8.02 Authorized Variations in Work .................................................................................................. 27  8.03 Rejecting Defective Work .......................................................................................................... 27  8.04 Determinations for Work Performed .......................................................................................... 28  Article 9 – Changes in the Work ..................................................................................................................... 28  9.01 Authorized Changes in the Work ............................................................................................... 28  9.02 Notification to Surety .................................................................................................................. 28  Article 10 – Change of Contract Price; Change of Contract Time ................................................................ 28  10.01 Change of Contract Price ............................................................................................................ 28  10.02 Change of Contract Time............................................................................................................ 28  10.03 Delays .......................................................................................................................................... 28  Article 11 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work ...................... 29  11.01 Notice of Defects ........................................................................................................................ 29  11.02 Access to Work ........................................................................................................................... 29  11.03 Tests and Inspections .................................................................................................................. 29  11.04 Uncovering Work ....................................................................................................................... 30  11.05 City May Stop the Work ............................................................................................................. 30  11.06 Correction or Removal of Defective Work ................................................................................ 30  11.07 Correction Period ........................................................................................................................ 30  11.08 City May Correct Defective Work ............................................................................................. 31  Article 12 – Completion .................................................................................................................................. 32  12.01 Contractor’s Warranty of Title ................................................................................................... 32  12.02 Partial Utilization ........................................................................................................................ 32  12.03 Final Inspection ........................................................................................................................... 32  12.04 Final Acceptance ......................................................................................................................... 33  Article 13 – Suspension of Work .................................................................................................................... 33  13.01 City May Suspend Work ............................................................................................................ 33  Article 14 – Miscellaneous .............................................................................................................................. 34  14.01 Giving Notice .............................................................................................................................. 34  CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.02 Computation of Times ................................................................................................................ 34  14.03 Cumulative Remedies ................................................................................................................. 34  14.04 Survival of Obligations ............................................................................................................... 35  14.05 Headings ...................................................................................................................................... 35  00 73 10- 1 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 1 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 1 – DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms A. Wherever used in these General Conditions or in other Contract Documents, the terms listed below have the meanings indicated which are applicable to both the singular and plural thereof, and words denoting gender shall include the masculine, feminine and neuter. Said terms are generally capitalized or written in italics, but not always. When used in a context consistent with the definition of a listed-defined term, the term shall have a meaning as defined below whether capitalized or italicized or otherwise. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 1. Agreement - The written instrument which is evidence of the agreement between Developer and Contractor covering the Work 2. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States Occupational Safety and Health Administration. 3. Business Day – A business day is defined as a day that the City conducts normal business, generally Monday through Friday, except for federal or state holidays observed by the City. 4. Buzzsaw – City’s on-line, electronic document management and collaboration system. 5. Calendar Day – A day consisting of 24 hours measured from midnight to the next midnight. 6. City— The City of Fort Worth, Texas, a Texas home-rule municipal corporation, acting by, its governing body through its City Manager, his designee, or agents authorized pursuant to its duly authorized charter on his behalf. 7. Community Facilities Agreement (CFA) -–A Contract between the Developer and the City for the Construction of one or more following public facilities within the City public right-of- way or easement: Water, Sanitary Sewer, Street, Storm Drain, Street Light, and Street Signs. A CFA may include private facilities within the right-of-way dedicated as private right-of- way or easement on a recorded plat. 8. Contract—The entire and integrated written document incorporating the Contract Documents between the Developer, Contractor, and/or City concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral. 9. Contract Documents—Those items that make up the contract and which must include the Agreement, and it’s attachments such as standard construction specifications, standard City Conditions, other general conditions of the Developer, including: a. An Agreement 00 73 10- 2 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 2 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 b. Attachments to the Agreement i. Bid Form ii. Vendor Compliance with State Law Non-Resident Bidder iii. Prequalification Statement c. Current Prevailing Wage Rates Table (if required by City) d. Insurance Accord Form e. Payment Bond f. Performance Bond g. Maintenance Bond h. Power of Attorney for Bonds i. Workers Compensation Affidavit j. MWBE Commitment Form( If required by City) k. General Conditions l. Supplementary Conditions m. The Standard City Conditions n. Specifications specifically made part of the Contract Documents by attachment, if not attached, as incorporated by reference and described in the Table of Contents of the Project’s Contract Documents o. Drawings p. Documentation submitted by contractor prior to Notice of Award. q. The following which may be delivered or issued after the effective date if the Agreement and, if issued become an incorporated part of the Contract Documents i. Notice to Proceed ii. Field Orders iii. Change Orders iv. Letters of Final Acceptance r. Approved Submittals, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents. 10. Contractor—The individual or entity with whom Developer has entered into the Agreement. 11. Day or day – A day, unless otherwise defined, shall mean a Calendar Day. 12. Developer – An individual or entity that desires to make certain improvements within the City of Fort Worth 13. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Submittals are not Drawings as so defined. 14. Engineer—The licensed professional engineer or engineering firm registered in the State of Texas performing professional services for the Developer. 15. Final Acceptance – The written notice given by the City to the Developer and/or Contractor that the Work specified in the Contract Documents has been completed to the satisfaction of the City. 00 73 10- 3 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 3 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 16. Final Inspection – Inspection carried out by the City to verify that the Contractor has completed the Work, and each and every part or appurtenance thereof, fully, entirely, and in conformance with the Contract Documents. 17. General Requirements—A part of the Contract Documents between the Developer and a Contractor. 18. Laws and Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 19. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property. 20. Milestone—A principal event specified in the Contract Documents relating to an intermediate Contract Time prior to Final Acceptance of the Work. 21. Non-Participating Change Order—A document, which is prepared for and reviewed by the City, which is signed by Contractor, and Developer, and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 22. Participating Change Order—A document, which is prepared for and approved by the City, which is signed by Contractor, Developer, and City and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement. 23. Plans – See definition of Drawings. 24. Project Schedule—A schedule, prepared and maintained by Contractor, in accordance with the General Requirements, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the Work within the Contract Time. 25. Project—The Work to be performed under the Contract Documents. 26. Project Representative—The authorized representative of the City who will be assigned to the Site. 27. Public Meeting – An announced meeting conducted by the Developer to facilitate public participation and to assist the public in gaining an informed view of the Project. 28. Regular Working Hours – Hours beginning at 7:00 a.m. and ending at 6:00 p.m., Monday thru Friday (excluding legal holidays). 29. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the Work will be judged. 00 73 10- 4 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 4 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 30. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities. 31. Site—Lands or areas indicated in the Contract Documents as being furnished by City or Developer upon which the Work is to be performed, including rights-of-way, permits, and easements for access thereto, and such other lands furnished by City or Developer which are designated for the use of Contractor. 32. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto. Specifications may be specifically made a part of the Contract Documents by attachment or, if not attached, may be incorporated by reference as indicated in the Table of Contents (Division 00 00 00) of each Project. 33. Standard City Conditions – That part of the Contract Documents setting forth requirements of the City. 34. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site. 35. Submittals—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work. 36. Superintendent – The representative of the Contractor who is available at all times and able to receive instructions from the City and/or Developer and to act for the Contractor. 37. Supplementary Conditions—That part of the Contract Documents which amends or supplements the General Conditions. 38. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor. 39. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including but not limited to, those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems. 40. Weekend Working Hours – Hours beginning at 9:00 a.m. and ending at 5:00 p.m., Saturday, Sunday or legal holiday, as approved in advance by the City. 00 73 10- 5 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 5 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 41. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction including any Participating Change Order, Non-Participating Change Order, or Field Order, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents. 42. Working Day – A working day is defined as a day, not including Saturdays, Sundays, or legal holidays authorized by the City for contract purposes, in which weather or other conditions not under the control of the Contractor will permit the performance of the principal unit of work underway for a continuous period of not less than 7 hours between 7 a.m. and 6 p.m. 1.02 Terminology A. The words and terms discussed in Paragraph 1.02.B through D are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning. B. Defective: 1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it: a. does not conform to the Contract Documents; or b. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or c. has been damaged prior to City’s written acceptance. C. Furnish, Install, Perform, Provide: 1. The word “Furnish” or the word “Install” or the word “Perform” or the word “Provide” or the word “Supply,” or any combination or similar directive or usage thereof, shall mean furnishing and incorporating in the Work including all necessary labor, materials, equipment, and everything necessary to perform the Work indicated, unless specifically limited in the context used. D. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning. 00 73 10- 6 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 6 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 2 – PRELIMINARY MATTERS 2.01 Before Starting Construction Baseline Schedules: Submit to City in accordance with the Contract Documents, and prior to starting the Work. New schedules will be submitted to City when Participating Change Orders or Non- Participating Change Orders occur. 2.02 Preconstruction Conference Before any Work at the Site is started, the Contractor shall attend a Preconstruction Conference as specified in the Contract Documents. 2.03 Public Meeting Contractor may not mobilize any equipment, materials or resources to the Site prior to Contractor attending the Public Meeting as scheduled by the City. ARTICLE 3 – CONTRACT DOCUMENTS AND AMENDING 3.01 Reference Standards A. Standards, Specifications, Codes, Laws, and Regulations 1. Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to Laws or Regulations, whether such reference be specific or by implication, shall mean the standard, specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract Documents. 2. No provision or instruction shall be effective to assign to City, or any of its officers, directors, members, partners, employees, agents, consultants, or subcontractors, any duty or authority to supervise or direct the performance of the Work or any duty or authority to undertake responsibility inconsistent with the provisions of the Contract Documents. 3.02 Amending and Supplementing Contract Documents A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof by a Participating Change Order or a Non-Participating Change Order. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work not involving a change in Contract Price or Contract Time, may be authorized, by one or more of the following ways: 1. A Field Order; 00 73 10- 7 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 7 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. City’s or Engineer’s review of a Submittal (subject to the provisions of Paragraph 5.16.C); or 2. City’s written interpretation or clarification. ARTICLE 4 – BONDS AND INSURANCE 4.01 Licensed Sureties and Insurers All bonds and insurance required by the Contract Documents to be purchased and maintained by Contractor shall be obtained from surety or insurance companies that are duly licensed or authorized in the State of Texas to issue bonds or insurance policies for the limits and coverage so required. Such surety and insurance companies shall also meet such additional requirements and qualifications as may be provided Section 4.04. 4.02 Performance, Payment, and Maintenance Bonds A. Contractor shall furnish performance and payment bonds in the name of Developer and City, in accordance with Texas Government Code Chapter 2253 or successor statute, each in an amount equal to the Contract Price as security for the faithful performance and payment of all of Contractor’s obligations under the Contract Documents. B. Contractor shall furnish maintenance bonds in the name of Developer and City in an amount equal to the Contract Price as security to protect the City against any defects in any portion of the Work described in the Contract Documents. Maintenance bonds shall remain in effect for two (2) years after the date of Final Acceptance by the City. C. All bonds shall be in the form prescribed by the Contract Documents except as provided otherwise by Laws or Regulations, and shall be executed by such sureties as are named in the list of “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” as published in Circular 570 (amended) by the Financial Management Service, Surety Bond Branch, U.S. Department of the Treasury. All bonds signed by an agent or attorney-in-fact must be accompanied by a sealed and dated power of attorney which shall show that it is effective on the date the agent or attorney-in-fact signed each bond. D. If the surety on any bond furnished by Contractor is declared bankrupt or becomes insolvent or its right to do business is terminated in the State of Texas or it ceases to meet the requirements of Paragraph 4.02.C, Contractor shall promptly notify City and shall, within 30 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the requirements of Paragraphs 4.01 and 4.02.C. 4.03 Certificates of Insurance Contractor shall deliver to Developer and City, with copies to each additional insured and loss payee identified in these Standard City Conditions certificates of insurance (and other evidence of insurance requested by City or any other additional insured) which Contractor is required to purchase and maintain. 00 73 10- 8 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 8 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. The certificate of insurance shall document the City, an as “Additional Insured” on all liability policies. 2. The Contractor’s general liability insurance shall include a, “per project” or “per location”, endorsement, which shall be identified in the certificate of insurance provided to the City. 3. The certificate shall be signed by an agent authorized to bind coverage on behalf of the insured, be complete in its entirety, and show complete insurance carrier names as listed in the current A.M. Best Property & Casualty Guide 4. The insurers for all policies must be licensed and/or approved to do business in the State of Texas. Except for workers’ compensation, all insurers must have a minimum rating of A-: VII in the current A. M. Best Key Rating Guide or have reasonably equivalent financial strength and solvency to the satisfaction of Risk Management. If the rating is below that required, written approval of City is required. 5. All applicable policies shall include a Waiver of Subrogation (Rights of Recovery) in favor of the City. In addition, the Contractor agrees to waive all rights of subrogation against the Engineer (if applicable), and each additional insured identified in these Standard City Conditions. Failure of the City to demand such certificates or other evidence of full compliance with the insurance requirements or failure of the City to identify a deficiency from evidence that is provided shall not be construed as a waiver of Contractor’s obligation to maintain such lines of insurance coverage. 6. If insurance policies are not written for specified coverage limits, an Umbrella or Excess Liability insurance for any differences is required. Excess Liability shall follow form of the primary coverage. 7. Unless otherwise stated, all required insurance shall be written on the “occurrence basis”. If coverage is underwritten on a claims-made basis, the retroactive date shall be coincident with or prior to the date of the effective date of the agreement and the certificate of insurance shall state that the coverage is claims-made and the retroactive date. The insurance coverage shall be maintained for the duration of the Contract and for three (3) years following Final Acceptance provided under the Contract Documents or for the warranty period, whichever is longer. An annual certificate of insurance submitted to the City shall evidence such insurance coverage. 8. Policies shall have no exclusions by endorsements, which, neither nullify or amend, the required lines of coverage, nor decrease the limits of said coverage unless such endorsements are approved in writing by the City. In the event a Contract has been bid or executed and the exclusions are determined to be unacceptable or the City desires additional insurance coverage, and the City desires the contractor/engineer to obtain such coverage, the contract price shall be adjusted by the cost of the premium for such additional coverage plus 10%. 9. Any self-insured retention (SIR), in excess of $25,000.00, affecting required insurance coverage shall be approved by the City in regards to asset value and stockholders' equity. In 00 73 10- 9 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 9 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 lieu of traditional insurance, alternative coverage maintained through insurance pools or risk retention groups, must also be approved by City. 10. Any deductible in excess of $5,000.00, for any policy that does not provide coverage on a first-dollar basis, must be acceptable to and approved by the City. 11. City, at its sole discretion, reserves the right to review the insurance requirements and to make reasonable adjustments to insurance coverage’s and their limits when deemed necessary and prudent by the City based upon changes in statutory law, court decision or the claims history of the industry as well as of the contracting party to the City. The City shall be required to provide prior notice of 90 days, and the insurance adjustments shall be incorporated into the Work by Change Order. 12. City shall be entitled, upon written request and without expense, to receive copies of policies and endorsements thereto and may make any reasonable requests for deletion or revision or modifications of particular policy terms, conditions, limitations, or exclusions necessary to conform the policy and endorsements to the requirements of the Contract. Deletions, revisions, or modifications shall not be required where policy provisions are established by law or regulations binding upon either party or the underwriter on any such policies. 13. City shall not be responsible for the direct payment of insurance premium costs for Contractor’s insurance. 4.04 Contractor’s Insurance A. Workers Compensation and Employers’ Liability. Contractor shall purchase and maintain such insurance coverage with limits consistent with statutory benefits outlined in the Texas Workers’ Compensation Act (Texas Labor Code, Ch. 406, as amended), and minimum limits for Employers’ Liability as is appropriate for the Work being performed and as will provide protection from claims set forth below which may arise out of or result from Contractor’s performance of the Work and Contractor’s other obligations under the Contract Documents, whether it is to be performed by Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable: 1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts; 2. claims for damages because of bodily injury, occupational sickness or disease, or death of Contractor’s employees. 3. The limits of liability for the insurance shall provide the following coverages for not less than the following amounts or greater where required by Laws and Regulations a. Statutory limits b. Employer's liability 00 73 10- 10 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 10 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $100,000 each accident/occurrence 2) $100,000 Disease - each employee 3) $500,000 Disease - policy limit B. Commercial General Liability. Coverage shall include but not be limited to covering liability (bodily injury or property damage) arising from: premises/operations, independent contractors, products/completed operations, personal injury, and liability under an insured contract. Insurance shall be provided on an occurrence basis, and as comprehensive as the current Insurance Services Office (ISO) policy. This insurance shall apply as primary insurance with respect to any other insurance or self-insurance programs afforded to the City. The Commercial General Liability policy, shall have no exclusions by endorsements that would alter of nullify premises/operations, products/completed operations, contractual, personal injury, or advertising injury, which are normally contained with the policy, unless the City approves such exclusions in writing. 1. For construction projects that present a substantial completed operation exposure, the City may require the contractor to maintain completed operations coverage for a minimum of no less than three (3) years following the completion of the project 2. Contractor's Liability Insurance under this Section which shall be on a per project basis covering the Contractor with minimum limits of: a. $1,000,000 each occurrence b. $2,000,000 aggregate limit 3. The policy must have an endorsement (Amendment – Aggregate Limits of Insurance) making the General Aggregate Limits apply separately to each job site. 4. The Commercial General Liability Insurance policies shall provide “X”, “C”, and “U” coverage’s. Verification of such coverage must be shown in the Remarks Article of the Certificate of Insurance. C. Automobile Liability. A commercial business auto policy shall provide coverage on “any auto”, defined as autos owned, hired and non-owned and provide indemnity for claims for damages because bodily injury or death of any person and or property damage arising out of the work, maintenance or use of any motor vehicle by the Contractor, any Subcontractor or Supplier, or by anyone directly or indirectly employed by any of them to perform any of the Work, or by anyone for whose acts any of them may be liable. 1. Automobile Liability, Contractor’s Liability Insurance under this Section, which shall be in an amount not less than the following amounts: a. Automobile Liability - a commercial business policy shall provide coverage on "Any Auto", defined as autos owned, hired and non-owned. 00 73 10- 11 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 11 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1) $1,000,000 each accident on a combined single limit basis. Split limits are acceptable if limits are at least: 2) $250,000 Bodily Injury per person 3) $500,000 Bodily Injury per accident / 4) $100,000 Property Damage D. Railroad Protective Liability. If any of the work or any warranty work is within the limits of railroad right-of-way, the Contractor shall comply with the following requirements: 1. The Contractor’s construction activities will require its employees, agents, subcontractors, equipment, and material deliveries to cross railroad properties and tracks owned and operated by: ____________________________________________________________ Write the name of the railroad company. (If none, then write none) 2. The Contractor shall conduct its operations on railroad properties in such a manner as not to interfere with, hinder, or obstruct the railroad company in any manner whatsoever in the use or operation of its/their trains or other property. Such operations on railroad properties may require that Contractor to execute a “Right of Entry Agreement” with the particular railroad company or companies involved, and to this end the Contractor should satisfy itself as to the requirements of each railroad company and be prepared to execute the right-of-entry (if any) required by a railroad company. The requirements specified herein likewise relate to the Contractor’s use of private and/or construction access roads crossing said railroad company’s properties. 3. The Contractual Liability coverage required by Paragraph 5.04D of the General Conditions shall provide coverage for not less than the following amounts, issued by companies satisfactory to the City and to the Railroad Company for a term that continues for so long as the Contractor’s operations and work cross, occupy, or touch railroad property: a. General Aggregate: _____________________________________ Enter limits provided by Railroad Company (If none, write none) b. Each Occurrence: : _____________________________________ Enter limits provided by Railroad Company (If none, write none) 4. With respect to the above outlined insurance requirements, the following shall govern: a. Where a single railroad company is involved, the Contractor shall provide one insurance policy in the name of the railroad company. However, if more than one grade separation or at-grade crossing is affected by the Project at entirely separate locations on the line or lines of the same railroad company, separate coverage may be required, each in the amount stated above. b. Where more than one railroad company is operating on the same right-of-way or where several railroad companies are involved and operated on their own separate rights-of- NONE NONE NONE 00 73 10- 12 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 12 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 way, the Contractor may be required to provide separate insurance policies in the name of each railroad company. c. If, in addition to a grade separation or an at-grade crossing, other work or activity is proposed on a railroad company’s right-of-way at a location entirely separate from the grade separation or at-grade crossing, insurance coverage for this work must be included in the policy covering the grade separation. d. If no grade separation is involved but other work is proposed on a railroad company’s right-of-way, all such other work may be covered in a single policy for that railroad, even though the work may be at two or more separate locations. 5. No work or activities on a railroad company’s property to be performed by the Contractor shall be commenced until the Contractor has furnished the City with an original policy or policies of the insurance for each railroad company named, as required above. All such insurance must be approved by the City and each affected Railroad Company prior to the Contractor’s beginning work. 6. The insurance specified above must be carried until all Work to be performed on the railroad right-of-way has been completed and the grade crossing, if any, is no longer used by the Contractor. In addition, insurance must be carried during all maintenance and/or repair work performed in the railroad right-of-way. Such insurance must name the railroad company as the insured, together with any tenant or lessee of the railroad company operating over tracks involved in the Project. E. Notification of Policy Cancellation: Contractor shall immediately notify City upon cancellation or other loss of insurance coverage. Contractor shall stop work until replacement insurance has been procured. There shall be no time credit for days not worked pursuant to this section. 4.05 Acceptance of Bonds and Insurance; Option to Replace If City has any objection to the coverage afforded by or other provisions of the bonds or insurance required to be purchased and maintained by the Contractor in accordance with Article 5 on the basis of non-conformance with the Contract Documents, the Developer and City shall so notify the Contractor in writing within 10 Business Days after receipt of the certificates (or other evidence requested). Contractor shall provide to the City such additional information in respect of insurance provided as the Developer or City may reasonably request. If Contractor does not purchase or maintain all of the bonds and insurance required by the Contract Documents, the Developer or City shall notify the Contractor in writing of such failure prior to the start of the Work, or of such failure to maintain prior to any change in the required coverage. ARTICLE 5 – CONTRACTOR’S RESPONSIBILITIES 5.01 Supervision and Superintendent A. Contractor shall supervise, inspect, and direct the Work competently and efficiently, devoting such attention thereto and applying such skills and expertise as may be necessary to perform the 00 73 10- 13 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 13 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Work in accordance with the Contract Documents. Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction. B. At all times during the progress of the Work, Contractor shall assign a competent, English- speaking, Superintendent who shall not be replaced without written notice to City. The Superintendent will be Contractor’s representative at the Site and shall have authority to act on behalf of Contractor. All communication given to or received from the Superintendent shall be binding on Contractor. C. Contractor shall notify the City 24 hours prior to moving areas during the sequence of construction. 5.02 Labor; Working Hours A. Contractor shall provide competent, suitably qualified personnel to perform construction as required by the Contract Documents. Contractor shall at all times maintain good discipline and order at the Site. B. Except as otherwise required for the safety or protection of persons or the Work or property at the Site or adjacent thereto, and except as otherwise stated in the Contract Documents, all Work at the Site shall be performed during Regular Working Hours. Contractor will not permit the performance of Work beyond Regular Working Hours or for Weekend Working Hours without City’s written consent (which will not be unreasonably withheld). Written request (by letter or electronic communication) to perform Work: 1. for beyond Regular Working Hours request must be made by noon at least two (2) Business Days prior 2. for Weekend Working Hours request must be made by noon of the preceding Thursday 3. for legal holidays request must be made by noon two Business Days prior to the legal holiday. 5.03 Services, Materials, and Equipment A. Unless otherwise specified in the Contract Documents, Contractor shall provide and assume full responsibility for all services, materials, equipment, labor, transportation, construction equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, Contractor required testing, start-up, and completion of the Work. B. All materials and equipment incorporated into the Work shall be as specified or, if not specified, shall be of good quality and new, except as otherwise provided in the Contract Documents. All special warranties and guarantees required by the Specifications shall expressly run to the benefit of City. If required by City, Contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment. 00 73 10- 14 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 14 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. All materials and equipment to be incorporated into the Work shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable Supplier, except as otherwise may be provided in the Contract Documents. 5.04 Project Schedule A. Contractor shall adhere to the Project Schedule established in accordance with Paragraph 2.01 and the General Requirements as it may be adjusted from time to time as provided below. 1. Contractor shall submit to City for acceptance (to the extent indicated in Paragraph 2.01 and the General Requirements) proposed adjustments in the Project Schedule. 2. Proposed adjustments in the Project Schedule that will change the Contract Time shall be submitted in accordance with the requirements of Article 9. Adjustments in Contract Time for projects with City participation shall be made by participating change orders. 5.05 Substitutes and “Or-Equals” A. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type, function, appearance, and quality required. Unless the specification or description contains or is followed by words reading that no like, equivalent, or “or-equal” item or no substitution is permitted, other items of material or equipment of other Suppliers may be submitted to City for review under the circumstances described below. 1. “Or-Equal” Items: If in City’s sole discretion an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by City as an “or-equal” item, in which case review and approval of the proposed item may, in City’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purposes of this Paragraph 5.05.A.1, a proposed item of material or equipment will be considered functionally equal to an item so named if: a. City determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results imposed by the design concept of the completed Project as a functioning whole; and 3) it has a proven record of performance and availability of responsive service; and b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the City or increase in Contract Time; and 00 73 10- 15 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 15 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. 2. Substitute Items: a. If in City’s sole discretion an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item under Paragraph 5.05.A.1, it may be submitted as a proposed substitute item. b. Contractor shall submit sufficient information as provided below to allow City to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefor. Requests for review of proposed substitute items of material or equipment will not be accepted by City from anyone other than Contractor. c. Contractor shall make written application to City for review of a proposed substitute item of material or equipment that Contractor seeks to furnish or use. The application shall comply with Section 01 25 00 and: 1) shall certify that the proposed substitute item will: i. perform adequately the functions and achieve the results called for by the general design; ii. be similar in substance to that specified; iii. be suited to the same use as that specified; and 2) will state: i. the extent, if any, to which the use of the proposed substitute item will prejudice Contractor’s achievement of final completion on time; ii. whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with City for other work on the Project) to adapt the design to the proposed substitute item; iii. whether incorporation or use of the proposed substitute item in connection with the Work is subject to payment of any license fee or royalty; and 3) will identify: i. all variations of the proposed substitute item from that specified; ii. available engineering, sales, maintenance, repair, and replacement services; and 00 73 10- 16 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 16 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 4) shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and Damage Claims of other contractors affected by any resulting change. B. Substitute Construction Methods or Procedures: If a specific means, method, technique, sequence, or procedure of construction is expressly required by the Contract Documents, Contractor may furnish or utilize a substitute means, method, technique, sequence, or procedure of construction approved by City. Contractor shall submit sufficient information to allow City, in City’s sole discretion, to determine that the substitute proposed is equivalent to that expressly called for by the Contract Documents. Contractor shall make written application to City for review in the same manner as those provided in Paragraph 5.05.A.2. C. City’s Evaluation: City will be allowed a reasonable time within which to evaluate each proposal or submittal made pursuant to Paragraphs 5.05.A and 5.05.B. City may require Contractor to furnish additional data about the proposed substitute. City will be the sole judge of acceptability. No “or-equal” or substitute will be ordered, installed or utilized until City’s review is complete, which will be evidenced by a Change Order in the case of a substitute and an accepted Submittal for an “or-equal.” City will advise Contractor in writing of its determination. D. Special Guarantee: City may require Contractor to furnish at Contractor’s expense a special performance guarantee, warranty, or other surety with respect to any substitute. Contractor shall indemnify and hold harmless City and anyone directly or indirectly employed by them from and against any and all claims, damages, losses and expenses (including attorneys fees) arising out of the use of substituted materials or equipment. E. City’s Cost Reimbursement: City will record City’s costs in evaluating a substitute proposed or submitted by Contractor pursuant to Paragraphs 5.05.A.2 and 5.05.B. Whether or not City approves a substitute so proposed or submitted by Contractor, Contractor may be required to reimburse City for evaluating each such proposed substitute. Contractor may also be required to reimburse City for the charges for making changes in the Contract Documents. F. Contractor’s Expense: Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense. G. Substitute Reimbursement: Costs (savings or charges) attributable to acceptance of a substitute shall be incorporated to the Contract by Participating Change Order. 5.06 Pre-Qualification of Bidders (Prime Contractors and Subcontractors) A. The Contractor and any subcontractors are required to be prequalified for the work types requiring pre-qualification 5.07 Concerning Subcontractors, Suppliers, and Others A. Minority and Women Owned Business Enterprise Compliance: 00 73 10- 17 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 17 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Required for this Contract. (Check this box if there is any City Participation) Not Required for this Contract. It is City policy to ensure the full and equitable participation by Minority and Women Business Enterprises (MWBE) in the procurement of goods and services on a contractual basis. If the Contract Documents provide for a MWBE goal, Contractor is required to comply with the intent of the City’s MWBE Ordinance (as amended) by the following: 1. Contractor shall, upon request by City, provide complete and accurate information regarding actual work performed by a MWBE on the Contract and payment therefor. 2. Contractor will not make additions, deletions, or substitutions of accepted MWBE without written consent of the City. Any unjustified change or deletion shall be a material breach of Contract and may result in debarment in accordance with the procedures outlined in the Ordinance. 3. Contractor shall, upon request by City, allow an audit and/or examination of any books, records, or files in the possession of the Contractor that will substantiate the actual work performed by an MWBE. Material misrepresentation of any nature will be grounds for termination of the Contract. Any such misrepresentation may be grounds for disqualification of Contractor to bid on future contracts with the City for a period of not less than three years. B. Contractor shall be fully responsible to City for all acts and omissions of the Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work just as Contractor is responsible for Contractor’s own acts and omissions. Nothing in the Contract Documents: 1. shall create for the benefit of any such Subcontractor, Supplier, or other individual or entity any contractual relationship between City and any such Subcontractor, Supplier or other individual or entity; nor 2. shall create any obligation on the part of City to pay or to see to the payment of any moneys due any such Subcontractor, Supplier, or other individual or entity except as may otherwise be required by Laws and Regulations. C. Contractor shall be solely responsible for scheduling and coordinating the Work of Subcontractors, Suppliers, and other individuals or entities performing or furnishing any of the Work under a direct or indirect contract with Contractor. D. All Subcontractors, Suppliers, and such other individuals or entities performing or furnishing any of the Work shall communicate with City through Contractor. E. All Work performed for Contractor by a Subcontractor or Supplier will be pursuant to an appropriate agreement between Contractor and the Subcontractor or Supplier which specifically binds the Subcontractor or Supplier to the applicable terms and conditions of these Contract X 00 73 10- 18 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 18 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents, Contractor shall provide City contract numbers and reference numbers to the Subcontractors and/or Suppliers. 5.08 Wage Rates Required for this Contract. Not Required for this Contract. A. Duty to pay Prevailing Wage Rates. The Contractor shall comply with all requirements of Chapter 2258, Texas Government Code (as amended), including the payment of not less than the rates determined by the City Council of the City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage rates are included in these Contract Documents. B. Penalty for Violation. A Contractor or any Subcontractor who does not pay the prevailing wage shall, upon demand made by the City, pay to the City $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code 2258.023. C. Complaints of Violations and City Determination of Good Cause. On receipt of information, including a complaint by a worker, concerning an alleged violation of 2258.023, Texas Government Code, by a Contractor or Subcontractor, the City shall make an initial determination, before the 31st day after the date the City receives the information, as to whether good cause exists to believe that the violation occurred. The City shall notify in writing the Contractor or Subcontractor and any affected worker of its initial determination. Upon the City’s determination that there is good cause to believe the Contractor or Subcontractor has violated Chapter 2258, the City shall retain the full amounts claimed by the claimant or claimants as the difference between wages paid and wages due under the prevailing wage rates, such amounts being subtracted from successive progress payments pending a final determination of the violation. D. Arbitration Required if Violation Not Resolved. An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the Contractor or Subcontractor and any affected worker does not resolve the issue by agreement before the 15th day after the date the City makes its initial determination pursuant to Paragraph C above. If the persons required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and binding on all parties and may be enforced in any court of competent jurisdiction. E. Records to be Maintained. The Contractor and each Subcontractor shall, for a period of three (3) years following the date of acceptance of the work, maintain records that show (i) the name and X 00 73 10- 19 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 19 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 occupation of each worker employed by the Contractor in the construction of the Work provided for in this Contract; and (ii) the actual per diem wages paid to each worker. The records shall be open at all reasonable hours for inspection by the City. The provisions of Paragraph 6.23, Right to Audit, shall pertain to this inspection. F. Progress Payments. With each progress payment or payroll period, whichever is less, the Contractor shall submit an affidavit stating that the Contractor has complied with the requirements of Chapter 2258, Texas Government Code. G. Posting of Wage Rates. The Contractor shall post prevailing wage rates in a conspicuous place at all times. H. Subcontractor Compliance. The Contractor shall include in its subcontracts and/or shall otherwise require all of its Subcontractors to comply with Paragraphs A through G above. 5.09 Patent Fees and Royalties A. To the fullest extent permitted by Laws and Regulations, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement of patent rights or copyrights incident to the use in the performance of the Work or resulting from the incorporation in the Work of any invention, design, process, product, or device not specified in the Contract Documents. 5.10 Laws and Regulations A. Contractor shall give all notices required by and shall comply with all Laws and Regulations applicable to the performance of the Work. Except where otherwise expressly required by applicable Laws and Regulations, the City shall not be responsible for monitoring Contractor’s compliance with any Laws or Regulations. B. If Contractor performs any Work knowing or having reason to know that it is contrary to Laws or Regulations, Contractor shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such Work. However, it shall not be Contractor’s responsibility to make certain that the Specifications and Drawings are in accordance with Laws and Regulations, but this shall not relieve Contractor of Contractor’s obligations under Paragraph 3.01. 5.11 Use of Site and Other Areas A. Limitation on Use of Site and Other Areas: 1. Contractor shall confine construction equipment, the storage of materials and equipment, and the operations of workers to the Site and other areas permitted by Laws and Regulations, and shall not unreasonably encumber the Site and other areas with construction equipment or 00 73 10- 20 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 20 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 other materials or equipment. Contractor shall assume full responsibility for any damage to any such land or area, or to the owner or occupant thereof, or of any adjacent land or areas resulting from the performance of the Work. 2. At any time when, in the judgment of the City, the Contractor has obstructed or closed or is carrying on operations in a portion of a street, right-of-way, or easement greater than is necessary for proper execution of the Work, the City may require the Contractor to finish the section on which operations are in progress before work is commenced on any additional area of the Site. 3. Should any Damage Claim be made by any such owner or occupant because of the performance of the Work, Contractor shall promptly attempt to resolve the Damage Claim. 4. Pursuant to Paragraph 5.18, Contractor shall indemnify and hold harmless City, from and against all claims, costs, losses, and damages arising out of or relating to any claim or action, legal or equitable, brought by any such owner or occupant against City. B. Removal of Debris During Performance of the Work: During the progress of the Work Contractor shall keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris shall conform to applicable Laws and Regulations. C. Site Maintenance Cleaning: 24 hours after written notice is given to the Contractor that the clean-up on the job site is proceeding in a manner unsatisfactory to the City or Developer, if the Contractor fails to correct the unsatisfactory procedure, the City may take such direct action as the City deems appropriate to correct the clean-up deficiencies cited to the Contractor in the written notice (by letter or electronic communication), and shall be entitled to recover its cost in doing so. The City may withhold Final Acceptance until clean-up is complete and cost are recovered. D. Final Site Cleaning: Prior to Final Acceptance of the Work Contractor shall clean the Site and the Work and make it ready for utilization by City or adjacent property owner. At the completion of the Work Contractor shall remove from the Site all tools, appliances, construction equipment and machinery, and surplus materials and shall restore to original condition or better all property disturbed by the Work. E. Loading Structures: Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. 5.12 Record Documents A. Contractor shall maintain in a safe place at the Site or in a place designated by the Contractor and approved by the City, one (1) record copy of all Drawings, Specifications, Addenda, Change Orders, Field Orders, and written interpretations and clarifications in good order and annotated to show changes made during construction. These record documents together with all approved 00 73 10- 21 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 21 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Samples and a counterpart of all accepted Submittals will be available to City for reference. Upon completion of the Work, these record documents, any operation and maintenance manuals, and Submittals will be delivered to City prior to Final Inspection. Contractor shall include accurate locations for buried and imbedded items. 5.13 Safety and Protection A. Contractor shall be solely responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the Work. Such responsibility does not relieve Subcontractors of their responsibility for the safety of persons or property in the performance of their work, nor for compliance with applicable safety Laws and Regulations. Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to: 1. all persons on the Site or who may be affected by the Work; 2. all the Work and materials and equipment to be incorporated therein, whether in storage on or off the Site; and 3. other property at the Site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures, utilities, and Underground Facilities not designated for removal, relocation, or replacement in the course of construction. B. Contractor shall comply with all applicable Laws and Regulations relating to the safety of persons or property, or to the protection of persons or property from damage, injury, or loss; and shall erect and maintain all necessary safeguards for such safety and protection. Contractor shall notify owners of adjacent property and of Underground Facilities and other utility owners when prosecution of the Work may affect them, and shall cooperate with them in the protection, removal, relocation, and replacement of their property. C. Contractor shall comply with the applicable requirements of City’s safety programs, if any. D. Contractor shall inform City of the specific requirements of Contractor’s safety program, if any, with which City’s employees and representatives must comply while at the Site. E. All damage, injury, or loss to any property referred to in Paragraph 5.13.A.2 or 5.13.A.3 caused, directly or indirectly, in whole or in part, by Contractor, any Subcontractor, Supplier, or any other individual or entity directly or indirectly employed by any of them to perform any of the Work, or anyone for whose acts any of them may be liable, shall be remedied by Contractor. F. Contractor’s duties and responsibilities for safety and for protection of the Work shall continue until such time as all the Work is completed and City has accepted the Work. 5.14 Safety Representative Contractor shall inform City in writing of Contractor’s designated safety representative at the Site. 00 73 10- 22 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 22 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 5.15 Hazard Communication Programs Contractor shall be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers in accordance with Laws or Regulations. 5.16 Submittals A. Contractor shall submit required Submittals to City for review and acceptance. Each submittal will be identified as required by City. 1. Submit number of copies specified in the General Requirements. 2. Data shown on the Submittals will be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to show City the services, materials, and equipment Contractor proposes to provide and to enable City to review the information for the limited purposes required by Paragraph 5.16.C. 3. Submittals submitted as herein provided by Contractor and reviewed by City for conformance with the design concept shall be executed in conformity with the Contract Documents unless otherwise required by City. 4. When Submittals are submitted for the purpose of showing the installation in greater detail, their review shall not excuse Contractor from requirements shown on the Drawings and Specifications. 5. For-Information-Only submittals upon which the City is not expected to conduct review or take responsive action may be so identified in the Contract Documents. 6. Submit required number of Samples specified in the Specifications. 7. Clearly identify each Sample as to material, Supplier, pertinent data such as catalog numbers, the use for which intended and other data as City may require to enable City to review the submittal for the limited purposes required by Paragraph 5.16.C. B. Where a Submittal is required by the Contract Documents or the Schedule of Submittals, any related Work performed prior to City’s review and acceptance of the pertinent submittal will be at the sole expense and responsibility of Contractor. C. City’s Review: 1. City will provide timely review of required Submittals in accordance with the Schedule of Submittals acceptable to City. City’s review and acceptance will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work, conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 00 73 10- 23 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 23 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 2. City’s review and acceptance will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and acceptance of a separate item as such will not indicate approval of the assembly in which the item functions. 3. City’s review and acceptance shall not relieve Contractor from responsibility for any variation from the requirements of the Contract Documents unless Contractor has complied with the requirements of Section 01 33 00 and City has given written acceptance of each such variation by specific written notation thereof incorporated in or accompanying the Submittal. City’s review and acceptance shall not relieve Contractor from responsibility for complying with the requirements of the Contract Documents. 5.17 Contractor’s General Warranty and Guarantee A. Contractor warrants and guarantees to City that all Work will be in accordance with the Contract Documents and will not be defective. City and its officers, directors, members, partners, employees, agents, consultants, and subcontractors shall be entitled to rely on representation of Contractor’s warranty and guarantee. B. Contractor’s warranty and guarantee hereunder excludes defects or damage caused by: 1. abuse, modification, or improper maintenance or operation by persons other than Contractor, Subcontractors, Suppliers, or any other individual or entity for whom Contractor is responsible; or 2. normal wear and tear under normal usage. C. Contractor’s obligation to perform and complete the Work in accordance with the Contract Documents shall be absolute. None of the following will constitute an acceptance of Work that is not in accordance with the Contract Documents or a release of Contractor’s obligation to perform the Work in accordance with the Contract Documents: 1. observations by City; 2. recommendation or payment by City or Developer of any progress or final payment; 3. the issuance of a certificate of Final Acceptance by City or any payment related thereto by City; 4. use or occupancy of the Work or any part thereof by City; 5. any review and acceptance of a Submittal by City; 6. any inspection, test, or approval by others; or 00 73 10- 24 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 24 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7. any correction of defective Work by City. D. The Contractor shall remedy any defects or damages in the Work and pay for any damage to other work or property resulting therefrom which shall appear within a period of two (2) years from the date of Final Acceptance of the Work unless a longer period is specified and shall furnish a good and sufficient maintenance bond, complying with the requirements of Article 4.02.B. The City will give notice of observed defects with reasonable promptness. 5.18 Indemnification A. Contractor covenants and agrees to indemnify, hold harmless and defend, at its own expense, the City, its officers, servants and employees, from and against any and all claims arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licenses or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. This indemnity provision is intended to include, without limitation, indemnity for costs, expenses and legal fees incurred by the City in defending against such claims and causes of actions. B. Contractor covenants and agrees to indemnify and hold harmless, at its own expense, the City, its officers, servants and employees, from and against any and all loss, damage or destruction of property of the City, arising out of, or alleged to arise out of, the work and services to be performed by the Contractor, its officers, agents, employees, subcontractors, licensees or invitees under this Contract. THIS INDEMNIFICATION PROVISION IS SPECIFICALLY INTENDED TO OPERATE AND BE EFFECTIVE EVEN IF IT IS ALLEGED OR PROVEN THAT ALL OR SOME OF THE DAMAGES BEING SOUGHT WERE CAUSED, IN WHOLE OR IN PART, BY ANY ACT, OMISSION OR NEGLIGENCE OF THE CITY. 5.19 Delegation of Professional Design Services A. Contractor will not be required to provide professional design services unless such services are specifically required by the Contract Documents for a portion of the Work or unless such services are required to carry out Contractor’s responsibilities for construction means, methods, techniques, sequences and procedures. B. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of Contractor by the Contract Documents, City will specify all performance and design criteria that such services must satisfy. Contractor shall cause such services or certifications to be provided by a properly licensed professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, and Submittals prepared by such professional. Submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional’s written approval when submitted to City. 00 73 10- 25 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 25 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 C. City shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided City has specified to Contractor performance and design criteria that such services must satisfy. D. Pursuant to this Paragraph 5.19, City’s review and acceptance of design calculations and design drawings will be only for the limited purpose of checking for conformance with performance and design criteria given and the design concept expressed in the Contract Documents. City’s review and acceptance of Submittals (except design calculations and design drawings) will be only for the purpose stated in Paragraph 5.16.C. 5.20 Right to Audit: A. The City reserves the right to audit all projects utilizing City funds B. The Contractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of the Contractor involving transactions relating to this Contract. Contractor agrees that the City shall have access during Regular Working Hours to all necessary Contractor facilities and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Contractor reasonable advance notice of intended audits. C. Contractor further agrees to include in all its subcontracts hereunder a provision to the effect that the subcontractor agrees that the City shall, until the expiration of three (3) years after final payment under this Contract, have access to and the right to examine and photocopy any directly pertinent books, documents, papers, and records of such Subcontractor, involving transactions to the subcontract, and further, that City shall have access during Regular Working Hours to all Subcontractor facilities, and shall be provided adequate and appropriate work space in order to conduct audits in compliance with the provisions of this Paragraph. The City shall give Subcontractor reasonable advance notice of intended audits. D. Contractor and Subcontractor agree to photocopy such documents as may be requested by the City. The City agrees to reimburse Contractor for the cost of the copies as follows at the rate published in the Texas Administrative Code in effect as of the time copying is performed. 5.21 Nondiscrimination A. The City is responsible for operating Public Transportation Programs and implementing transit- related projects, which are funded in part with Federal financial assistance awarded by the U.S. Department of Transportation and the Federal Transit Administration (FTA), without discriminating against any person in the United States on the basis of race, color, or national origin. B. Title VI, Civil Rights Act of 1964 as amended: Contractor shall comply with the requirements of the Act and the Regulations as further defined in the Supplementary Conditions for any project receiving Federal assistance. 00 73 10- 26 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 26 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 6 – OTHER WORK AT THE SITE 6.01 Related Work at Site A. City may perform other work related to the Project at the Site with City’s employees, or other City contractors, or through other direct contracts therefor, or have other work performed by utility owners. If such other work is not noted in the Contract Documents, then written notice thereof will be given to Contractor prior to starting any such other work; and B. Contractor shall afford each other contractor who is a party to such a direct contract, each utility owner, and City, if City is performing other work with City’s employees or other City contractors, proper and safe access to the Site, provide a reasonable opportunity for the introduction and storage of materials and equipment and the execution of such other work, and properly coordinate the Work with theirs. Contractor shall do all cutting, fitting, and patching of the Work that may be required to properly connect or otherwise make its several parts come together and properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering such work; provided, however, that Contractor may cut or alter others' work with the written consent of City and the others whose work will be affected. C. If the proper execution or results of any part of Contractor’s Work depends upon work performed by others under this Article 7, Contractor shall inspect such other work and promptly report to City in writing any delays, defects, or deficiencies in such other work that render it unavailable or unsuitable for the proper execution and results of Contractor’s Work. Contractor’s failure to so report will constitute an acceptance of such other work as fit and proper for integration with Contractor’s Work except for latent defects in the work provided by others. ARTICLE 7 – CITY’S RESPONSIBILITIES 7.01 Inspections, Tests, and Approvals City’s responsibility with respect to certain inspections, tests, and approvals is set forth in Paragraph 11.03. 7.02 Limitations on City’s Responsibilities A. The City shall not supervise, direct, or have control or authority over, nor be responsible for, Contractor’s means, methods, techniques, sequences, or procedures of construction, or the safety precautions and programs incident thereto, or for any failure of Contractor to comply with Laws and Regulations applicable to the performance of the Work. City will not be responsible for Contractor’s failure to perform the Work in accordance with the Contract Documents. B. City will notify the Contractor of applicable safety plans pursuant to Paragraph 5.13. 00 73 10- 27 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 27 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 7.03 Compliance with Safety Program While at the Site, City’s employees and representatives shall comply with the specific applicable requirements of Contractor’s safety programs of which City has been informed pursuant to Paragraph 5.13. ARTICLE 8 – CITY’S OBSERVATION STATUS DURING CONSTRUCTION 8.01 City’s Project Representative City will provide one or more Project Representative(s) during the construction period. The duties and responsibilities and the limitations of authority of City’s representative during construction are set forth in the Contract Documents. A. City’s Project Representative will make visits to the Site at intervals appropriate to the various stages of construction as City deems necessary in order to observe the progress that has been made and the quality of the various aspects of Contractor’s executed Work. Based on information obtained during such visits and observations, City’s Project Representative will determine, in general, if the Work is proceeding in accordance with the Contract Documents. City’s Project Representative will not be required to make exhaustive or continuous inspections on the Site to check the quality or quantity of the Work. City’s Project Representative’s efforts will be directed toward providing City a greater degree of confidence that the completed Work will conform generally to the Contract Documents. B. City’s Project Representative’s visits and observations are subject to all the limitations on authority and responsibility in the Contract Documents. 8.02 Authorized Variations in Work City’s Project Representative may authorize minor variations in the Work from the requirements of the Contract Documents which do not involve an adjustment in the Contract Price or the Contract Time and are compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. These may be accomplished by a Field Order and will be binding on City Developer, and also on Contractor, who shall perform the Work involved promptly. 8.03 Rejecting Defective Work City will have authority to reject Work which City’s Project Representative believes to be defective, or will not produce a completed Project that conforms to the Contract Documents or that will prejudice the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. City will have authority to conduct special inspection or testing of the Work as provided in Article 11, whether or not the Work is fabricated, installed, or completed. 00 73 10- 28 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 28 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 8.04 Determinations for Work Performed Contractor will determine the actual quantities and classifications of Work performed. City’s Project Representative will review with Contractor the preliminary determinations on such matters before rendering a written recommendation. City’s written decision will be final (except as modified to reflect changed factual conditions or more accurate data). ARTICLE 9 – CHANGES IN THE WORK 9.01 Authorized Changes in the Work A. Without invalidating the Contract and without notice to any surety, City may, at any time or from time to time, order Extra Work. Upon notice of such Extra Work, Contractor shall promptly proceed with the Work involved which will be performed under the applicable conditions of the Contract Documents (except as otherwise specifically provided). Extra Work shall be memorialized by a Participating Change Order which may or may not precede an order of Extra work. B. For minor changes of Work not requiring changes to Contract Time or Contract Price on a project with City participation, a Field Order may be issued by the City. 9.02 Notification to Surety If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Work or the provisions of the Contract Documents (including, but not limited to, Contract Price or Contract Time), the giving of any such notice will be Contractor’s responsibility. The amount of each applicable bond will be adjusted by the Contractor to reflect the effect of any such change. ARTICLE 10 – CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIME 10.01 Change of Contract Price A. The Contract Price may only be changed by a Participating Change Order for projects with City participation. 10.02 Change of Contract Time A. The Contract Time may only be changed by a Participating Change Order for projects with City participation. 10.03 Delays A. If Contractor is delayed, City shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project. 00 73 10- 29 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 29 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 ARTICLE 11 – TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK 11.01 Notice of Defects Notice of all defective Work of which City has actual knowledge will be given to Contractor. Defective Work may be rejected, corrected, or accepted as provided in this Article 13. 11.02 Access to Work City, independent testing laboratories, and governmental agencies with jurisdictional interests will have access to the Site and the Work at reasonable times for their observation, inspection, and testing. Contractor shall provide them proper and safe conditions for such access and advise them of Contractor’s safety procedures and programs so that they may comply therewith as applicable. 11.03 Tests and Inspections A. Contractor shall give City timely notice of readiness of the Work for all required inspections, tests, or approvals and shall cooperate with inspection and testing personnel to facilitate required inspections or tests. B. If Contract Documents, Laws or Regulations of any public body having jurisdiction require any of the Work (or part thereof) to be inspected, tested, or approved, Contractor shall assume full responsibility for arranging and obtaining such independent inspections, tests, retests or approvals, pay all costs in connection therewith, and furnish City the required certificates of inspection or approval; excepting, however, those fees specifically identified in the Supplementary Conditions or any Texas Department of Licensure and Regulation (TDLR) inspections, which shall be paid as described in the Supplementary Conditions. C. Contractor shall be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests, re-tests, or approvals required for City’s acceptance of materials or equipment to be incorporated in the Work; or acceptance of materials, mix designs, or equipment submitted for approval prior to Contractor’s purchase thereof for incorporation in the Work. Such inspections, tests, re-tests, or approvals shall be performed by organizations approved by City. D. City may arrange for the services of an independent testing laboratory (“Testing Lab”) to perform any inspections or tests (“Testing”) for any part of the Work, as determined solely by City. 1. City will coordinate such Testing to the extent possible, with Contractor; 2. Should any Testing under this Section 11.03 D result in a “fail”, “did not pass” or other similar negative result, the Contractor shall be responsible for paying for any and all retests. Contractor’s cancellation without cause of City initiated Testing shall be deemed a negative result and require a retest. 00 73 10- 30 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 30 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 3. Any amounts owed for any retest under this Section 11.03 D shall be paid directly to the Testing Lab by Contractor. City will forward all invoices for retests to Developer/Contractor. 4. If Contractor fails to pay the Testing Lab, City will not issue a letter of Final Acceptance until the Testing Lab is Paid E. If any Work (or the work of others) that is to be inspected, tested, or approved is covered by Contractor without written concurrence of City, Contractor shall, if requested by City, uncover such Work for observation. 11.04 Uncovering Work A. If any Work is covered contrary to the Contract Documents or specific instructions by the City, it must, if requested by City, be uncovered for City’s observation and replaced at Contractor’s expense. 11.05 City May Stop the Work If the Work is defective, or Contractor fails to supply sufficient skilled workers or suitable materials or equipment, or fails to perform the Work in such a way that the completed Work will conform to the Contract Documents, City may order Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of City to stop the Work shall not give rise to any duty on the part of City to exercise this right for the benefit of Contractor, any Subcontractor, any Supplier, any other individual or entity, or any surety for, or employee or agent of any of them. 11.06 Correction or Removal of Defective Work A. Promptly after receipt of written notice, Contractor shall correct all defective Work pursuant to an acceptable schedule, whether or not fabricated, installed, or completed, or, if the Work has been rejected by City, remove it from the Project and replace it with Work that is not defective. Contractor shall pay all claims, costs, additional testing, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such correction or removal (including but not limited to all costs of repair or replacement of work of others). Failure to require the removal of any defective Work shall not constitute acceptance of such Work. B. When correcting defective Work under the terms of this Paragraph 11.06 or Paragraph 11.07, Contractor shall take no action that would void or otherwise impair City’s special warranty and guarantee, if any, on said Work. 11.07 Correction Period A. If within two (2) years after the date of Final Acceptance (or such longer period of time as may be prescribed by the terms of any applicable special guarantee required by the Contract 00 73 10- 31 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 31 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 Documents), any Work is found to be defective, or if the repair of any damages to the land or areas made available for Contractor’s use by City or permitted by Laws and Regulations as contemplated in Paragraph 5.10.A is found to be defective, Contractor shall promptly, without cost to City and in accordance with City’s written instructions: 1. repair such defective land or areas; or 2. correct such defective Work; or 3. if the defective Work has been rejected by City, remove it from the Project and replace it with Work that is not defective, and 4. satisfactorily correct or repair or remove and replace any damage to other Work, to the work of others or other land or areas resulting therefrom. B. If Contractor does not promptly comply with the terms of City’s written instructions, or in an emergency where delay would cause serious risk of loss or damage, City may have the defective Work corrected or repaired or may have the rejected Work removed and replaced. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) arising out of or relating to such correction or repair or such removal and replacement (including but not limited to all costs of repair or replacement of work of others) will be paid by Contractor. C. Where defective Work (and damage to other Work resulting therefrom) has been corrected or removed and replaced under this Paragraph 11.07, the correction period hereunder with respect to such Work may be required to be extended for an additional period of one year after the end of the initial correction period. City shall provide 30 days written notice to Contractor and Developer should such additional warranty coverage be required. Contractor’s obligations under this Paragraph 11.07 are in addition to any other obligation or warranty. The provisions of this Paragraph 11.07 shall not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 11.08 City May Correct Defective Work A. If Contractor fails within a reasonable time after written notice from City to correct defective Work, or to remove and replace rejected Work as required by City in accordance with Paragraph 11.06.A, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) days written notice to Contractor and the Developer, correct, or remedy any such deficiency. B. In exercising the rights and remedies under this Paragraph 11.09, City shall proceed expeditiously. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, and incorporate in the Work all materials and equipment incorporated in the Work, stored at the Site or for which City has paid Contractor but which are 00 73 10- 32 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 32 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 stored elsewhere. Contractor shall allow City, City’s representatives, agents, consultants, employees, and City’s other contractors, access to the Site to enable City to exercise the rights and remedies under this Paragraph. C. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or other dispute resolution costs) incurred or sustained by City in exercising the rights and remedies under this Paragraph 13.09 will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price. D. Contractor shall not be allowed an extension of the Contract Time because of any delay in the performance of the Work attributable to the exercise of City’s rights and remedies under this Paragraph 11.09. ARTICLE 12 – COMPLETION 12.01 Contractor’s Warranty of Title Contractor warrants and guarantees that title to all Work, materials, and equipment covered by any Application for Payment will pass to City no later than the time of Final Acceptance and shall be free and clear of all Liens. 12.02 Partial Utilization A. Prior to Final Acceptance of all the Work, City may use or occupy any substantially completed part of the Work which has specifically been identified in the Contract Documents, or which City, determines constitutes a separately functioning and usable part of the Work that can be used by City for its intended purpose without significant interference with Contractor’s performance of the remainder of the Work. City at any time may notify Contractor in writing to permit City to use or occupy any such part of the Work which City determines to be ready for its intended use, subject to the following conditions: 1. Contractor at any time may notify City in writing that Contractor considers any such part of the Work ready for its intended use. 2. Within a reasonable time after notification as enumerated in Paragraph 14.05.A.1, City and Contractor shall make an inspection of that part of the Work to determine its status of completion. If City does not consider that part of the Work to be substantially complete, City will notify Contractor in writing giving the reasons therefor. 3. Partial Utilization will not constitute Final Acceptance by City. 12.03 Final Inspection A. Upon written notice from Contractor that the entire Work is complete in accordance with the Contract Documents: 00 73 10- 33 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 33 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 1. within 10 days, City will schedule a Final Inspection with Contractor. 2. City will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies. 12.04 Final Acceptance A. Upon completion by Contractor to City’s satisfaction, of any additional Work identified in the Final Inspection, City will issue to Contractor a letter of Final Acceptance upon the satisfaction of the following: 1. All documentation called for in the Contract Documents, including but not limited to the evidence of insurance required by Paragraph 5.03; 2. consent of the surety, if any, to Final Acceptance; 3. a list of all pending or released Damage Claims against City that Contractor believes are unsettled; and 4. affidavits of payments and complete and legally effective releases or waivers (satisfactory to City) of all Lien rights arising out of or Liens filed in connection with the Work. 5. after all Damage Claims have been resolved: a. directly by the Contractor or; b. Contractor provides evidence that the Damage Claim has been reported to Contractor’s insurance provider for resolution. 6. Issuing Final Acceptance by the City shall not relieve the Contractor of any guarantees or other requirements of the Contract Documents which specifically continue thereafter. ARTICLE 13 – SUSPENSION OF WORK 13.01 City May Suspend Work A. At any time and without cause, City may suspend the Work or any portion thereof by written notice to Contractor and which may fix the date on which Work will be resumed. Contractor shall resume the Work on the date so fixed. During temporary suspension of the Work covered by these Contract Documents, for any reason, the City will stop contract time on City participation projects. B. Should the Contractor not be able to complete a portion of the Project due to causes beyond the control of and without the fault or negligence of the Contractor, and should it be determined by mutual consent of the Contractor and City that a solution to allow construction to proceed is not 00 73 10- 34 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 34 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 available within a reasonable period of time, Contractor may request an extension in Contract Time, directly attributable to any such suspension. C. If it should become necessary to suspend the Work for an indefinite period, the Contractor shall store all materials in such a manner that they will not obstruct or impede the public unnecessarily nor become damaged in any way, and he shall take every precaution to prevent damage or deterioration of the work performed; he shall provide suitable drainage about the work, and erect temporary structures where necessary. ARTICLE 14 – MISCELLANEOUS 14.01 Giving Notice A. Whenever any provision of the Contract Documents requires the giving of written notice, it will be deemed to have been validly given if: 1. delivered in person to the individual or to a member of the firm or to an officer of the corporation for whom it is intended; or 2. delivered at or sent by registered or certified mail, postage prepaid, to the last business address known to the giver of the notice. B. Business address changes must be promptly made in writing to the other party. C. Whenever the Contract Documents specifies giving notice by electronic means such electronic notice shall be deemed sufficient upon confirmation of receipt by the receiving party. 14.02 Computation of Times When any period of time is referred to in the Contract Documents by days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday the next Working Day shall become the last day of the period. 14.03 Cumulative Remedies The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Contract Documents. The provisions of this Paragraph will be as effective as if repeated specifically in the Contract Documents in connection with each particular duty, obligation, right, and remedy to which they apply. 00 73 10- 35 Standard City Conditions Of The Construction Contract For Developer Awarded Projects Page 35 of 35 CITY OF FORT WORTH STANDARD CITY CONDITIONS – DEVELOPER AWARDED PROJECTS Revised: January 10, 2013 14.04 Survival of Obligations All representations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor. 14.05 Headings Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. 01 11 00 - 1 DAP SUMMARY OF WORK Page 1 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects CPN 102606 Revised December 20, 2012 SECTION 01 11 00 1 SUMMARY OF WORK 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Summary of Work to be performed in accordance with the Contract Documents 6 B. Deviations from this City of Fort Worth Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 - Bidding Requirements, Contract Forms, and Conditions of the Contract 10 2. Division 1 - General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Work associated with this Item is considered subsidiary to the various items bid. 14 No separate payment will be allowed for this Item. 15 1.3 REFERENCES [NOT USED] 16 1.4 ADMINISTRATIVE REQUIREMENTS 17 A. Work Covered by Contract Documents 18 1. Work is to include furnishing all labor, materials, and equipment, and performing 19 all Work necessary for this construction project as detailed in the Drawings and 20 Specifications. 21 B. Subsidiary Work 22 1. Any and all Work specifically governed by documentary requirements for the 23 project, such as conditions imposed by the Drawings or Contract Documents in 24 which no specific item for bid has been provided for in the Proposal and the item is 25 not a typical unit bid item included on the standard bid item list, then the item shall 26 be considered as a subsidiary item of Work, the cost of which shall be included in 27 the price bid in the Proposal for various bid items. 28 C. Use of Premises 29 1. Coordinate uses of premises under direction of the City. 30 2. Assume full responsibility for protection and safekeeping of materials and 31 equipment stored on the Site. 32 3. Use and occupy only portions of the public streets and alleys, or other public places 33 or other rights-of-way as provided for in the ordinances of the City, as shown in the 34 Contract Documents, or as may be specifically authorized in writing by the City. 35 a. A reasonable amount of tools, materials, and equipment for construction 36 purposes may be stored in such space, but no more than is necessary to avoid 37 delay in the construction operations. 38 01 11 00 - 2 DAP SUMMARY OF WORK Page 2 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects CPN 102606 Revised December 20, 2012 b. Excavated and waste materials shall be stored in such a way as not to interfere 1 with the use of spaces that may be designated to be left free and unobstructed 2 and so as not to inconvenience occupants of adjacent property. 3 c. If the street is occupied by railroad tracks, the Work shall be carried on in such 4 manner as not to interfere with the operation of the railroad. 5 1) All Work shall be in accordance with railroad requirements set forth in 6 Division 0 as well as the railroad permit. 7 D. Work within Easements 8 1. Do not enter upon private property for any purpose without having previously 9 obtained permission from the owner of such property. 10 2. Do not store equipment or material on private property unless and until the 11 specified approval of the property owner has been secured in writing by the 12 Contractor and a copy furnished to the City. 13 3. Unless specifically provided otherwise, clear all rights-of-way or easements of 14 obstructions which must be removed to make possible proper prosecution of the 15 Work as a part of the project construction operations. 16 4. Preserve and use every precaution to prevent damage to, all trees, shrubbery, plants, 17 lawns, fences, culverts, curbing, and all other types of structures or improvements, 18 to all water, sewer, and gas lines, to all conduits, overhead pole lines, or 19 appurtenances thereof, including the construction of temporary fences and to all 20 other public or private property adjacent to the Work. 21 5. Notify the proper representatives of the owners or occupants of the public or private 22 lands of interest in lands which might be affected by the Work. 23 a. Such notice shall be made at least 48 hours in advance of the beginning of the 24 Work. 25 b. Notices shall be applicable to both public and private utility companies and any 26 corporation, company, individual, or other, either as owners or occupants, 27 whose land or interest in land might be affected by the Work. 28 c. Be responsible for all damage or injury to property of any character resulting 29 from any act, omission, neglect, or misconduct in the manner or method or 30 execution of the Work, or at any time due to defective work, material, or 31 equipment. 32 6. Fence 33 a. Restore all fences encountered and removed during construction of the Project 34 to the original or a better than original condition. 35 b. Erect temporary fencing in place of the fencing removed whenever the Work is 36 not in progress and when the site is vacated overnight, and/or at all times to 37 provide site security. 38 c. The cost for all fence work within easements, including removal, temporary 39 closures and replacement, shall be subsidiary to the various items bid in the 40 project proposal, unless a bid item is specifically provided in the proposal. 41 01 11 00 - 3 DAP SUMMARY OF WORK Page 3 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – Developer Awarded Projects CPN 102606 Revised December 20, 2012 1.5 SUBMITTALS [NOT USED] 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE [NOT USED] 5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.11 FIELD [SITE] CONDITIONS [NOT USED] 7 1.12 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 01 25 00 - 1 DAP SUBSTITUTION PROCEDURES Page 1 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 SECTION 01 25 00 1 SUBSTITUTION PROCEDURES 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. The procedure for requesting the approval of substitution of a product that is not 6 equivalent to a product which is specified by descriptive or performance criteria or 7 defined by reference to 1 or more of the following: 8 a. Name of manufacturer 9 b. Name of vendor 10 c. Trade name 11 d. Catalog number 12 2. Substitutions are not "or-equals". 13 B. Deviations from this City of Fort Worth Standard Specification 14 1. None. 15 C. Related Specification Sections include, but are not necessarily limited to: 16 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 17 2. Division 1 – General Requirements 18 1.2 PRICE AND PAYMENT PROCEDURES 19 A. Measurement and Payment 20 1. Work associated with this Item is considered subsidiary to the various items bid. No 21 separate payment will be allowed for this Item. 22 1.3 REFERENCES [NOT USED] 23 1.4 ADMINISTRATIVE REQUIREMENTS 24 A. Request for Substitution - General 25 1. Within 30 days after award of Contract (unless noted otherwise), the City will 26 consider formal requests from Contractor for substitution of products in place of 27 those specified. 28 2. Certain types of equipment and kinds of material are described in Specifications by 29 means of references to names of manufacturers and vendors, trade names, or catalog 30 numbers. 31 a. When this method of specifying is used, it is not intended to exclude from 32 consideration other products bearing other manufacturer's or vendor's names, 33 trade names, or catalog numbers, provided said products are "or-equals," as 34 determined by City. 35 3. Other types of equipment and kinds of material may be acceptable substitutions 36 under the following conditions: 37 a. Or-equals are unavailable due to strike, discontinued production of products 38 meeting specified requirements, or other factors beyond control of Contractor; 39 or, 40 01 25 00 - 2 DAP SUBSTITUTION PROCEDURES Page 2 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 b. Contractor proposes a cost and/or time reduction incentive to the City. 1 1.5 SUBMITTALS 2 A. See Request for Substitution Form (attached) 3 B. Procedure for Requesting Substitution 4 1. Substitution shall be considered only: 5 a. After award of Contract 6 b. Under the conditions stated herein 7 2. Submit 3 copies of each written request for substitution, including: 8 a. Documentation 9 1) Complete data substantiating compliance of proposed substitution with 10 Contract Documents 11 2) Data relating to changes in construction schedule, when a reduction is 12 proposed 13 3) Data relating to changes in cost 14 b. For products 15 1) Product identification 16 a) Manufacturer's name 17 b) Telephone number and representative contact name 18 c) Specification Section or Drawing reference of originally specified 19 product, including discrete name or tag number assigned to original 20 product in the Contract Documents 21 2) Manufacturer's literature clearly marked to show compliance of proposed 22 product with Contract Documents 23 3) Itemized comparison of original and proposed product addressing product 24 characteristics including, but not necessarily limited to: 25 a) Size 26 b) Composition or materials of construction 27 c) Weight 28 d) Electrical or mechanical requirements 29 4) Product experience 30 a) Location of past projects utilizing product 31 b) Name and telephone number of persons associated with referenced 32 projects knowledgeable concerning proposed product 33 c) Available field data and reports associated with proposed product 34 5) Samples 35 a) Provide at request of City. 36 b) Samples become the property of the City. 37 c. For construction methods: 38 1) Detailed description of proposed method 39 2) Illustration drawings 40 C. Approval or Rejection 41 1. Written approval or rejection of substitution given by the City 42 2. City reserves the right to require proposed product to comply with color and pattern 43 of specified product if necessary to secure design intent. 44 3. In the event the substitution is approved, if a reduction in cost or time results, it will 45 be documented by Change Order. 46 01 25 00 - 3 DAP SUBSTITUTION PROCEDURES Page 3 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 4. Substitution will be rejected if: 1 a. Submittal is not through the Contractor with his stamp of approval 2 b. Request is not made in accordance with this Specification Section 3 c. In the Developer’s opinion, acceptance will require substantial revision of the 4 original design 5 d. In the City’s or Developer’s opinion, substitution will not perform adequately 6 the function consistent with the design intent 7 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 8 1.7 CLOSEOUT SUBMITTALS [NOT USED] 9 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 10 1.9 QUALITY ASSURANCE 11 A. In making request for substitution or in using an approved product, the Contractor 12 represents that the Contractor: 13 1. Has investigated proposed product, and has determined that it is adequate or 14 superior in all respects to that specified, and that it will perform function for which it 15 is intended 16 2. Will provide same guarantee for substitute item as for product specified 17 3. Will coordinate installation of accepted substitution into Work, to include building 18 modifications if necessary, making such changes as may be required for Work to be 19 complete in all respects 20 4. Waives all claims for additional costs related to substitution which subsequently 21 arise 22 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 23 1.11 FIELD [SITE] CONDITIONS [NOT USED] 24 1.12 WARRANTY [NOT USED] 25 PART 2 - PRODUCTS [NOT USED] 26 PART 3 - EXECUTION [NOT USED] 27 END OF SECTION 28 29 Revision Log DATE NAME SUMMARY OF CHANGE 30 01 25 00 - 4 DAP SUBSTITUTION PROCEDURES Page 4 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 EXHIBIT A 1 REQUEST FOR SUBSTITUTION FORM: 2 3 TO: 4 PROJECT: DATE: 5 We hereby submit for your consideration the following product instead of the specified item for 6 the above project: 7 SECTION PARAGRAPH SPECIFIED ITEM 8 9 10 Proposed Substitution: 11 Reason for Substitution: 12 Include complete information on changes to Drawings and/or Specifications which proposed 13 substitution will require for its proper installation. 14 15 Fill in Blanks Below: 16 A. Will the undersigned contractor pay for changes to the building design, including engineering 17 and detailing costs caused by the requested substitution? 18 19 20 B. What effect does substitution have on other trades? 21 22 23 C. Differences between proposed substitution and specified item? 24 25 26 D. Differences in product cost or product delivery time? 27 28 29 E. Manufacturer's guarantees of the proposed and specified items are: 30 31 Equal Better (explain on attachment) 32 The undersigned states that the function, appearance and quality are equivalent or superior to the 33 specified item. 34 Submitted By: For Use by City 35 36 Signature Recommended Recommended 37 as noted 38 39 Firm Not recommended Received late 40 Address By 41 Date 42 Date Remarks 43 Telephone 44 45 For Use by City: 46 47 Approved Rejected 48 City Date 49 01 31 19 - 1 DAP PRECONSTRUCTION MEETING Page 1 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 SECTION 01 31 19 1 PRECONSTRUCTION MEETING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Provisions for the preconstruction meeting to be held prior to the start of Work to 6 clarify construction contract administration procedures 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. No construction schedule required unless requested by the City. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Coordination 19 1. Attend preconstruction meeting. 20 2. Representatives of Contractor, subcontractors and suppliers attending meetings 21 shall be qualified and authorized to act on behalf of the entity each represents. 22 3. Meeting administered by City may be tape recorded. 23 a. If recorded, tapes will be used to prepare minutes and retained by City for 24 future reference. 25 B. Preconstruction Meeting 26 1. A preconstruction meeting will be held within 14 days after the delivery of the 27 distribution package to the City. 28 a. The meeting will be scheduled and administered by the City. 29 2. The Project Representative will preside at the meeting, prepare the notes of the 30 meeting and distribute copies of same to all participants who so request by fully 31 completing the attendance form to be circulated at the beginning of the meeting. 32 3. Attendance shall include: 33 a. Developer and Consultant 34 b. Contractor's project manager 35 c. Contractor's superintendent 36 d. Any subcontractor or supplier representatives whom the Contractor may desire 37 to invite or the City may request 38 01 31 19 - 2 DAP PRECONSTRUCTION MEETING Page 2 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 e. Other City representatives 1 f. Others as appropriate 2 4. Preliminary Agenda may include: 3 a. Introduction of Project Personnel 4 b. General Description of Project 5 c. Status of right-of-way, utility clearances, easements or other pertinent permits 6 d. Contractor’s work plan and schedule 7 e. Contract Time 8 f. Notice to Proceed 9 g. Construction Staking 10 h. Progress Payments 11 i. Extra Work and Change Order Procedures 12 j. Field Orders 13 k. Disposal Site Letter for Waste Material 14 l. Insurance Renewals 15 m. Payroll Certification 16 n. Material Certifications and Quality Control Testing 17 o. Public Safety and Convenience 18 p. Documentation of Pre-Construction Conditions 19 q. Weekend Work Notification 20 r. Legal Holidays 21 s. Trench Safety Plans 22 t. Confined Space Entry Standards 23 u. Coordination with the City’s representative for operations of existing water 24 systems 25 v. Storm Water Pollution Prevention Plan 26 w. Coordination with other Contractors 27 x. Early Warning System 28 y. Contractor Evaluation 29 z. Special Conditions applicable to the project 30 aa. Damages Claims 31 bb. Submittal Procedures 32 cc. Substitution Procedures 33 dd. Correspondence Routing 34 ee. Record Drawings 35 ff. Temporary construction facilities 36 gg. MBE/SBE procedures 37 hh. Final Acceptance 38 ii. Final Payment 39 jj. Questions or Comments 40 01 31 19 - 3 DAP PRECONSTRUCTION MEETING Page 3 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 1.5 SUBMITTALS [NOT USED] 1 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.7 CLOSEOUT SUBMITTALS [NOT USED] 3 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.9 QUALITY ASSURANCE [NOT USED] 5 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.11 FIELD [SITE] CONDITIONS [NOT USED] 7 1.12 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 13 01 32 33 - 1 DAP PRECONSTRUCTION VIDEO Page 1 of 2 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 SECTION 01 32 33 1 PRECONSTRUCTION VIDEO 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Administrative and procedural requirements for: 6 a. Preconstruction Videos 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. Though not mandatory, it is highly recommended on infill developer projects. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 1.2 PRICE AND PAYMENT PROCEDURES 13 A. Measurement and Payment 14 1. Work associated with this Item is considered subsidiary to the various items bid. 15 No separate payment will be allowed for this Item. 16 1.3 REFERENCES [NOT USED] 17 1.4 ADMINISTRATIVE REQUIREMENTS 18 A. Preconstruction Video 19 1. Produce a preconstruction video of the site/alignment, including all areas in the 20 vicinity of and to be affected by construction. 21 a. Provide digital copy of video upon request by the City. 22 2. Retain a copy of the preconstruction video until the end of the maintenance surety 23 period. 24 1.5 SUBMITTALS [NOT USED] 25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 26 1.7 CLOSEOUT SUBMITTALS [NOT USED] 27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28 1.9 QUALITY ASSURANCE [NOT USED] 29 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 30 1.11 FIELD [SITE] CONDITIONS [NOT USED] 31 1.12 WARRANTY [NOT USED] 32 PART 2 - PRODUCTS [NOT USED] 33 01 32 33 - 2 DAP PRECONSTRUCTION VIDEO Page 2 of 2 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 PART 3 - EXECUTION [NOT USED] 1 END OF SECTION 2 3 Revision Log DATE NAME SUMMARY OF CHANGE 4 01 33 00 - 1 DAP SUBMITTALS Page 1 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 SECTION 01 33 00 1 DAP SUBMITTALS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. General methods and requirements of submissions applicable to the following 6 Work-related submittals: 7 a. Shop Drawings 8 b. Product Data (including Standard Product List submittals) 9 c. Samples 10 d. Mock Ups 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. None. 13 C. Related Specification Sections include, but are not necessarily limited to: 14 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 – General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS 22 A. Coordination 23 01 33 00 - 2 DAP SUBMITTALS Page 2 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 1. Notify the City in writing, at the time of submittal, of any deviations in the 1 submittals from the requirements of the Contract Documents. 2 2. Coordination of Submittal Times 3 a. Prepare, prioritize and transmit each submittal sufficiently in advance of 4 performing the related Work or other applicable activities, or within the time 5 specified in the individual Work Sections, of the Specifications. 6 b. Contractor is responsible such that the installation will not be delayed by 7 processing times including, but not limited to: 8 a) Disapproval and resubmittal (if required) 9 b) Coordination with other submittals 10 c) Testing 11 d) Purchasing 12 e) Fabrication 13 f) Delivery 14 g) Similar sequenced activities 15 c. No extension of time will be authorized because of the Contractor's failure to 16 transmit submittals sufficiently in advance of the Work. 17 d. Make submittals promptly in accordance with approved schedule, and in such 18 sequence as to cause no delay in the Work or in the work of any other 19 contractor. 20 B. Submittal Numbering 21 1. When submitting shop drawings or samples, utilize a 9-character submittal cross-22 reference identification numbering system in the following manner: 23 a. Use the first 6 digits of the applicable Specification Section Number. 24 b. For the next 2 digits number use numbers 01-99 to sequentially number each 25 initial separate item or drawing submitted under each specific Section 26 number. 27 c. Last use a letter, A-Z, indicating the resubmission of the same drawing (i.e. 28 A=2nd submission, B=3rd submission, C=4th submission, etc.). A typical 29 submittal number would be as follows: 30 01 33 00 - 3 DAP SUBMITTALS Page 3 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 1 03 30 00-08-B 2 3 1) 03 30 00 is the Specification Section for Concrete 4 2) 08 is the eighth initial submittal under this Specification Section 5 3) B is the third submission (second resubmission) of that particular shop 6 drawing 7 C. Contractor Certification 8 1. Review shop drawings, product data and samples, including those by 9 subcontractors, prior to submission to determine and verify the following: 10 a. Field measurements 11 b. Field construction criteria 12 c. Catalog numbers and similar data 13 d. Conformance with the Contract Documents 14 2. Provide each shop drawing, sample and product data submitted by the Contractor 15 with a Certification Statement affixed including: 16 a. The Contractor's Company name 17 b. Signature of submittal reviewer 18 c. Certification Statement 19 1) “By this submittal, I hereby represent that I have determined and verified 20 field measurements, field construction criteria, materials, dimensions, 21 catalog numbers and similar data and I have checked and coordinated 22 each item with other applicable approved shop drawings." 23 D. Submittal Format 24 1. Fold shop drawings larger than 8 ½ inches x 11 inches to 8 ½ inches x 11inches. 25 2. Bind shop drawings and product data sheets together. 26 3. Order 27 01 33 00 - 4 DAP SUBMITTALS Page 4 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 a. Cover Sheet 1 1) Description of Packet 2 2) Contractor Certification 3 b. List of items / Table of Contents 4 c. Product Data /Shop Drawings/Samples /Calculations 5 E. Submittal Content 6 1. The date of submission and the dates of any previous submissions 7 2. The Project title and number 8 3. Contractor identification 9 4. The names of: 10 a. Contractor 11 b. Supplier 12 c. Manufacturer 13 5. Identification of the product, with the Specification Section number, page and 14 paragraph(s) 15 6. Field dimensions, clearly identified as such 16 7. Relation to adjacent or critical features of the Work or materials 17 8. Applicable standards, such as ASTM or Federal Specification numbers 18 9. Identification by highlighting of deviations from Contract Documents 19 10. Identification by highlighting of revisions on resubmittals 20 11. An 8-inch x 3-inch blank space for Contractor and City stamps 21 F. Shop Drawings 22 1. As specified in individual Work Sections includes, but is not necessarily limited to: 23 a. Custom-prepared data such as fabrication and erection/installation (working) 24 drawings 25 01 33 00 - 5 DAP SUBMITTALS Page 5 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 b. Scheduled information 1 c. Setting diagrams 2 d. Actual shopwork manufacturing instructions 3 e. Custom templates 4 f. Special wiring diagrams 5 g. Coordination drawings 6 h. Individual system or equipment inspection and test reports including: 7 1) Performance curves and certifications 8 i. As applicable to the Work 9 2. Details 10 a. Relation of the various parts to the main members and lines of the structure 11 b. Where correct fabrication of the Work depends upon field measurements 12 1) Provide such measurements and note on the drawings prior to submitting 13 for approval. 14 G. Product Data 15 1. For submittals of product data for products included on the City’s Standard 16 Product List, clearly identify each item selected for use on the Project. 17 2. For submittals of product data for products not included on the City’s Standard 18 Product List, submittal data may include, but is not necessarily limited to: 19 a. Standard prepared data for manufactured products (sometimes referred to as 20 catalog data) 21 1) Such as the manufacturer's product specification and installation 22 instructions 23 2) Availability of colors and patterns 24 3) Manufacturer's printed statements of compliances and applicability 25 4) Roughing-in diagrams and templates 26 5) Catalog cuts 27 01 33 00 - 6 DAP SUBMITTALS Page 6 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 6) Product photographs 1 7) Standard wiring diagrams 2 8) Printed performance curves and operational-range diagrams 3 9) Production or quality control inspection and test reports and certifications 4 10) Mill reports 5 11) Product operating and maintenance instructions and recommended 6 spare-parts listing and printed product warranties 7 12) As applicable to the Work 8 H. Samples 9 1. As specified in individual Sections, include, but are not necessarily limited to: 10 a. Physical examples of the Work such as: 11 1) Sections of manufactured or fabricated Work 12 2) Small cuts or containers of materials 13 3) Complete units of repetitively used products color/texture/pattern 14 swatches and range sets 15 4) Specimens for coordination of visual effect 16 5) Graphic symbols and units of Work to be used by the City for independent 17 inspection and testing, as applicable to the Work 18 I. Do not start Work requiring a shop drawing, sample or product data nor any material 19 to be fabricated or installed prior to the approval or qualified approval of such item. 20 1. Fabrication performed, materials purchased or on-site construction accomplished 21 which does not conform to approved shop drawings and data is at the Contractor's 22 risk. 23 2. The City will not be liable for any expense or delay due to corrections or remedies 24 required to accomplish conformity. 25 3. Complete project Work, materials, fabrication, and installations in conformance 26 with approved shop drawings, applicable samples, and product data. 27 01 33 00 - 7 DAP SUBMITTALS Page 7 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 J. Submittal Distribution 1 1. Electronic Distribution 2 a. Confirm development of Project directory for electronic submittals to be 3 uploaded to City’s Buzzsaw site, or another external FTP site approved by the 4 City. 5 b. Shop Drawings 6 1) Upload submittal to designated project directory and notify appropriate 7 City representatives via email of submittal posting. 8 2) Hard Copies 9 a) 3 copies for all submittals 10 b) If Contractor requires more than 1 hard copy of Shop Drawings 11 returned, Contractor shall submit more than the number of copies 12 listed above. 13 c. Product Data 14 1) Upload submittal to designated project directory and notify appropriate 15 City representatives via email of submittal posting. 16 2) Hard Copies 17 a) 3 copies for all submittals 18 d. Samples 19 1) Distributed to the Project Representative 20 2. Hard Copy Distribution (if required in lieu of electronic distribution) 21 a. Shop Drawings 22 1) Distributed to the City 23 2) Copies 24 a) 8 copies for mechanical submittals 25 b) 7 copies for all other submittals 26 c) If Contractor requires more than 3 copies of Shop Drawings returned, 27 Contractor shall submit more than the number of copies listed above. 28 01 33 00 - 8 DAP SUBMITTALS Page 8 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 b. Product Data 1 1) Distributed to the City 2 2) Copies 3 a) 4 copies 4 c. Samples 5 1) Distributed to the Project Representative 6 2) Copies 7 a) Submit the number stated in the respective Specification Sections. 8 3. Distribute reproductions of approved shop drawings and copies of approved 9 product data and samples, where required, to the job site file and elsewhere as 10 directed by the City. 11 a. Provide number of copies as directed by the City but not exceeding the 12 number previously specified. 13 K. Submittal Review 14 1. The review of shop drawings, data and samples will be for general conformance 15 with the design concept and Contract Documents. This is not to be construed as: 16 a. Permitting any departure from the Contract requirements 17 b. Relieving the Contractor of responsibility for any errors, including details, 18 dimensions, and materials 19 c. Approving departures from details furnished by the City, except as otherwise 20 provided herein 21 2. The review and approval of shop drawings, samples or product data by the City 22 does not relieve the Contractor from his/her responsibility with regard to the 23 fulfillment of the terms of the Contract. 24 a. All risks of error and omission are assumed by the Contractor, and the City will 25 have no responsibility therefore. 26 3. The Contractor remains responsible for details and accuracy, for coordinating the 27 Work with all other associated work and trades, for selecting fabrication 28 processes, for techniques of assembly and for performing Work in a safe manner. 29 01 33 00 - 9 DAP SUBMITTALS Page 9 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 4. If the shop drawings, data or samples as submitted describe variations and show a 1 departure from the Contract requirements which City finds to be in the interest of 2 the City and to be so minor as not to involve a change in Contract Price or time for 3 performance, the City may return the reviewed drawings without noting an 4 exception. 5 5. Submittals will be returned to the Contractor under 1 of the following codes: 6 a. Code 1 7 1) "NO EXCEPTIONS TAKEN" is assigned when there are no notations or 8 comments on the submittal. 9 a) When returned under this code the Contractor may release the 10 equipment and/or material for manufacture. 11 b. Code 2 12 1) "EXCEPTIONS NOTED". This code is assigned when a confirmation of the 13 notations and comments IS NOT required by the Contractor. 14 a) The Contractor may release the equipment or material for 15 manufacture; however, all notations and comments must be 16 incorporated into the final product. 17 c. Code 3 18 1) "EXCEPTIONS NOTED/RESUBMIT". This combination of codes is assigned 19 when notations and comments are extensive enough to require a 20 resubmittal of the package. 21 a) The Contractor may release the equipment or material for 22 manufacture; however, all notations and comments must be 23 incorporated into the final product. 24 b) This resubmittal is to address all comments, omissions and 25 non-conforming items that were noted. 26 c) Resubmittal is to be received by the City within 15 Calendar Days of 27 the date of the City's transmittal requiring the resubmittal. 28 d. Code 4 29 1) "NOT APPROVED" is assigned when the submittal does not meet the intent 30 of the Contract Documents. 31 01 33 00 - 10 DAP SUBMITTALS Page 10 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 a) The Contractor must resubmit the entire package revised to bring the 1 submittal into conformance. 2 b) It may be necessary to resubmit using a different 3 manufacturer/vendor to meet the Contract Documents. 4 6. Resubmittals 5 a. Handled in the same manner as first submittals 6 1) Corrections other than requested by the City 7 2) Marked with revision triangle or other similar method 8 a) At Contractor’s risk if not marked 9 b. Submittals for each item will be reviewed no more than twice at the City’s 10 expense. 11 1) All subsequent reviews will be performed at times convenient to the City 12 and at the Contractor's expense, based on the City's or City 13 Representative’s then prevailing rates. 14 2) Provide Contractor reimbursement to the City within 30 Calendar Days for 15 all such fees invoiced by the City. 16 c. The need for more than 1 resubmission or any other delay in obtaining City's 17 review of submittals, will not entitle the Contractor to an extension of 18 Contract Time. 19 7. Partial Submittals 20 a. City reserves the right to not review submittals deemed partial, at the City’s 21 discretion. 22 b. Submittals deemed by the City to be not complete will be returned to the 23 Contractor, and will be considered "Not Approved" until resubmitted. 24 c. The City may at its option provide a list or mark the submittal directing the 25 Contractor to the areas that are incomplete. 26 8. If the Contractor considers any correction indicated on the shop drawings to 27 constitute a change to the Contract Documents, then written notice must be 28 provided thereof to the Developer at least 7 Calendar Days prior to release for 29 manufacture. 30 01 33 00 - 11 DAP SUBMITTALS Page 11 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 9. When the shop drawings have been completed to the satisfaction of the City, the 1 Contractor may carry out the construction in accordance therewith and no further 2 changes therein except upon written instructions from the City. 3 10. Each submittal, appropriately coded, will be returned within 30 Calendar Days 4 following receipt of submittal by the City. 5 L. Mock ups 6 1. Mock Up units as specified in individual Sections, include, but are not necessarily 7 limited to, complete units of the standard of acceptance for that type of Work to 8 be used on the Project. Remove at the completion of the Work or when directed. 9 M. Qualifications 10 1. If specifically required in other Sections of these Specifications, submit a P.E. 11 Certification for each item required. 12 N. Request for Information (RFI) 13 1. Contractor Request for additional information 14 a. Clarification or interpretation of the contract documents 15 b. When the Contractor believes there is a conflict between Contract Documents 16 c. When the Contractor believes there is a conflict between the Drawings and 17 Specifications 18 1) Identify the conflict and request clarification 19 2. Sufficient information shall be attached to permit a written response without 20 further information. 21 22 23 24 25 1.5 SUBMITTALS [NOT USED] 26 01 33 00 - 12 DAP SUBMITTALS Page 12 of 12 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August 30, 2013 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1 1.7 CLOSEOUT SUBMITTALS [NOT USED] 2 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 3 1.9 QUALITY ASSURANCE [NOT USED] 4 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 5 1.11 FIELD [SITE] CONDITIONS [NOT USED] 6 1.12 WARRANTY [NOT USED] 7 PART 2 - PRODUCTS [NOT USED] 8 PART 3 - EXECUTION [NOT USED] 9 END OF SECTION 10 11 Revision Log DATE NAME SUMMARY OF CHANGE 12/20/2012 D. Johnson 1.4.K.8. Working Days modified to Calendar Days 12 01 35 13 - 1 DAP SPECIAL PROJECT PROCEDURES Page 1 of 7 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August, 30, 2013 SECTION 01 35 13 1 SPECIAL PROJECT PROCEDURES 2 [Text in Blue is for information or guidance. Remove all blue text in the final project document.] 3 PART 1 - GENERAL 4 1.1 SUMMARY 5 A. Section Includes: 6 1. The procedures for special project circumstances that includes, but is not limited to: 7 a. Coordination with the Texas Department of Transportation 8 b. Work near High Voltage Lines 9 c. Confined Space Entry Program 10 d. Air Pollution Watch Days 11 e. Use of Explosives, Drop Weight, Etc. 12 f. Water Department Notification 13 g. Public Notification Prior to Beginning Construction 14 h. Coordination with United States Army Corps of Engineers 15 i. Coordination within Railroad permits areas 16 j. Dust Control 17 k. Employee Parking 18 l. {Coordination with North Central Texas Council of Governments Clean 19 Construction Specification [remove if not required]} 20 B. Deviations from this City of Fort Worth Standard Specification 21 1. None. 22 C. Related Specification Sections include, but are not necessarily limited to: 23 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 24 2. Division 1 – General Requirements 25 3. Section 33 12 25 – Connection to Existing Water Mains 26 27 1.2 REFERENCES 28 A. Reference Standards 29 1. Reference standards cited in this Specification refer to the current reference 30 standard published at the time of the latest revision date logged at the end of this 31 Specification, unless a date is specifically cited. 32 2. Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. 33 High Voltage Overhead Lines. 34 3. North Central Texas Council of Governments (NCTCOG) – Clean Construction 35 Specification 36 1.3 ADMINISTRATIVE REQUIREMENTS 37 A. Coordination with the Texas Department of Transportation 38 1. When work in the right-of-way which is under the jurisdiction of the Texas 39 Department of Transportation (TxDOT): 40 01 35 13 - 2 DAP SPECIAL PROJECT PROCEDURES Page 2 of 7 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August, 30, 2013 a. Notify the Texas Department of Transportation prior to commencing any work 1 therein in accordance with the provisions of the permit 2 b. All work performed in the TxDOT right-of-way shall be performed in 3 compliance with and subject to approval from the Texas Department of 4 Transportation 5 B. Work near High Voltage Lines 6 1. Regulatory Requirements 7 a. All Work near High Voltage Lines (more than 600 volts measured between 8 conductors or between a conductor and the ground) shall be in accordance with 9 Health and Safety Code, Title 9, Subtitle A, Chapter 752. 10 2. Warning sign 11 a. Provide sign of sufficient size meeting all OSHA requirements. 12 3. Equipment operating within 10 feet of high voltage lines will require the following 13 safety features 14 a. Insulating cage-type of guard about the boom or arm 15 b. Insulator links on the lift hook connections for back hoes or dippers 16 c. Equipment must meet the safety requirements as set forth by OSHA and the 17 safety requirements of the owner of the high voltage lines 18 4. Work within 6 feet of high voltage electric lines 19 a. Notification shall be given to: 20 1) The power company (example: ONCOR) 21 a) Maintain an accurate log of all such calls to power company and record 22 action taken in each case. 23 b. Coordination with power company 24 1) After notification coordinate with the power company to: 25 a) Erect temporary mechanical barriers, de-energize the lines, or raise or 26 lower the lines 27 c. No personnel may work within 6 feet of a high voltage line before the above 28 requirements have been met. 29 C. Confined Space Entry Program 30 1. Provide and follow approved Confined Space Entry Program in accordance with 31 OSHA requirements. 32 2. Confined Spaces include: 33 a. Manholes 34 b. All other confined spaces in accordance with OSHA’s Permit Required for 35 Confined Spaces 36 D. Use of Explosives, Drop Weight, Etc. 37 1. When Contract Documents permit on the project the following will apply: 38 a. Public Notification 39 1) Submit notice to City and proof of adequate insurance coverage, 24 hours 40 prior to commencing. 41 2) Minimum 24 hour public notification in accordance with Section 01 31 13 42 E. Water Department Coordination 43 01 35 13 - 3 DAP SPECIAL PROJECT PROCEDURES Page 3 of 7 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August, 30, 2013 1. During the construction of this project, it will be necessary to deactivate, for a 1 period of time, existing lines. The Contractor shall be required to coordinate with 2 the Water Department to determine the best times for deactivating and activating 3 those lines. 4 2. Coordinate any event that will require connecting to or the operation of an existing 5 City water line system with the City’s representative. 6 a. Coordination shall be in accordance with Section 33 12 25. 7 b. If needed, obtain a hydrant water meter from the Water Department for use 8 during the life of named project. 9 c. In the event that a water valve on an existing live system be turned off and on 10 to accommodate the construction of the project is required, coordinate this 11 activity through the appropriate City representative. 12 1) Do not operate water line valves of existing water system. 13 a) Failure to comply will render the Contractor in violation of Texas Penal 14 Code Title 7, Chapter 28.03 (Criminal Mischief) and the Contractor 15 will be prosecuted to the full extent of the law. 16 b) In addition, the Contractor will assume all liabilities and 17 responsibilities as a result of these actions. 18 F. Public Notification Prior to Beginning Construction 19 1. Prior to beginning construction on any block in the project, on a block by block 20 basis, prepare and deliver a notice or flyer of the pending construction to the front 21 door of each residence or business that will be impacted by construction. The notice 22 shall be prepared as follows: 23 a. Post notice or flyer 7 days prior to beginning any construction activity on each 24 block in the project area. 25 1) Prepare flyer on the Contractor’s letterhead and include the following 26 information: 27 a) Name of Project 28 b) City Project No (CPN) 29 c) Scope of Project (i.e. type of construction activity) 30 d) Actual construction duration within the block 31 e) Name of the contractor’s foreman and phone number 32 f) Name of the City’s inspector and phone number 33 g) City’s after-hours phone number 34 2) A sample of the ‘pre-construction notification’ flyer is attached as Exhibit 35 A. 36 3) Submit schedule showing the construction start and finish time for each 37 block of the project to the inspector. 38 4) Deliver flyer to the City Inspector for review prior to distribution. 39 b. No construction will be allowed to begin on any block until the flyer is 40 delivered to all residents of the block. 41 G. Public Notification of Temporary Water Service Interruption during Construction 42 1. In the event it becomes necessary to temporarily shut down water service to 43 residents or businesses during construction, prepare and deliver a notice or flyer of 44 the pending interruption to the front door of each affected resident. 45 2. Prepared notice as follows: 46 a. The notification or flyer shall be posted 24 hours prior to the temporary 47 interruption. 48 01 35 13 - 4 DAP SPECIAL PROJECT PROCEDURES Page 4 of 7 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August, 30, 2013 b. Prepare flyer on the contractor’s letterhead and include the following 1 information: 2 1) Name of the project 3 2) City Project Number 4 3) Date of the interruption of service 5 4) Period the interruption will take place 6 5) Name of the contractor’s foreman and phone number 7 6) Name of the City’s inspector and phone number 8 c. A sample of the temporary water service interruption notification is attached as 9 Exhibit B. 10 d. Deliver a copy of the temporary interruption notification to the City inspector 11 for review prior to being distributed. 12 e. No interruption of water service can occur until the flyer has been delivered to 13 all affected residents and businesses. 14 f. Electronic versions of the sample flyers can be obtained from the Project 15 Construction Inspector. 16 H. Coordination with United States Army Corps of Engineers (USACE) 17 1. At locations in the Project where construction activities occur in areas where 18 USACE permits are required, meet all requirements set forth in each designated 19 permit. 20 I. Coordination within Railroad Permit Areas 21 1. At locations in the project where construction activities occur in areas where 22 railroad permits are required, meet all requirements set forth in each designated 23 railroad permit. This includes, but is not limited to, provisions for: 24 a. Flagmen 25 b. Inspectors 26 c. Safety training 27 d. Additional insurance 28 e. Insurance certificates 29 f. Other employees required to protect the right-of-way and property of the 30 Railroad Company from damage arising out of and/or from the construction of 31 the project. Proper utility clearance procedures shall be used in accordance 32 with the permit guidelines. 33 2. Obtain any supplemental information needed to comply with the railroad’s 34 requirements. 35 J. Dust Control 36 1. Use acceptable measures to control dust at the Site. 37 a. If water is used to control dust, capture and properly dispose of waste water. 38 b. If wet saw cutting is performed, capture and properly dispose of slurry. 39 K. Employee Parking 40 1. Provide parking for employees at locations approved by the City. 41 01 35 13 - 5 DAP SPECIAL PROJECT PROCEDURES Page 5 of 7 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August, 30, 2013 1.4 SUBMITTALS [NOT USED] 1 1.5 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 2 1.6 CLOSEOUT SUBMITTALS [NOT USED] 3 1.7 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 4 1.8 QUALITY ASSURANCE [NOT USED] 5 1.9 DELIVERY, STORAGE, AND HANDLING [NOT USED] 6 1.10 FIELD [SITE] CONDITIONS [NOT USED] 7 1.11 WARRANTY [NOT USED] 8 PART 2 - PRODUCTS [NOT USED] 9 PART 3 - EXECUTION [NOT USED] 10 END OF SECTION 11 12 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.3.B – Added requirement of compliance with Health and Safety Code, Title 9. Safety, Subtitle A. Public Safety, Chapter 752. High Voltage Overhead Lines. 13 01 35 13 - 6 DAP SPECIAL PROJECT PROCEDURES Page 6 of 7 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August, 30, 2013 EXHIBIT A 1 (To be printed on Contractor’s Letterhead) 2 3 4 5 Date: 6 7 CPN No.: 8 Project Name: 9 Mapsco Location: 10 Limits of Construction: 11 12 13 14 15 16 THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE CITY OF FORT 17 WORTH, OUR COMPANY WILL WORK ON UTILITY LINES ON OR AROUND YOUR 18 PROPERTY. 19 20 CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS FROM THE DATE 21 OF THIS NOTICE. 22 23 IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY OR ANY OTHER 24 ISSUE, PLEASE CALL: 25 26 27 Mr. <CONTRACTOR’S SUPERINTENDENT> AT <TELEPHONE NO.> 28 29 OR 30 31 Mr. <CITY INSPECTOR> AT < TELEPHONE NO.> 32 33 AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL (817) 392 8306 34 35 PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL 36 37 01 35 13 - 7 DAP SPECIAL PROJECT PROCEDURES Page 7 of 7 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised August, 30, 2013 EXHIBIT B 1 2 3 4 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 1 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised March 20, 2020 TRINITY PARKS CPN 102606 Number] SECTION 01 45 23 TESTING AND INSPECTION SERVICES PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Testing and inspection services procedures and coordination B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Work associated with this Item is considered subsidiary to the various Items bid. No separate payment will be allowed for this Item. a. Contractor is responsible for performing, coordinating, and payment of all Quality Control testing. b. City is responsible for performing and payment for first set of Quality Assurance testing. 1) If the first Quality Assurance test performed by the City fails, the Contractor is responsible for payment of subsequent Quality Assurance testing until a passing test occurs. a) Final acceptance will not be issued by City until all required payments for testing by Contractor have been paid in full. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS A. Testing 1. Complete testing in accordance with the Contract Documents. 2. Coordination a. When testing is required to be performed by the City, notify City, sufficiently in advance, when testing is needed. b. When testing is required to be completed by the Contractor, notify City, sufficiently in advance, that testing will be performed. 3. Distribution of Testing Reports a. Electronic Distribution 1) Confirm development of Project directory for electronic submittals to be uploaded to the City’s document management system, or another form of distribution approved by the City. 01 45 23 DAP TESTING AND INSPECTION SERVICES Page 2 of 2 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised March 20, 2020 TRINITY PARKS CPN 102606 Number] 2) Upload test reports to designated project directory and notify appropriate City representatives via email of submittal posting. 3) Hard Copies a) 1 copy for all submittals submitted to the Project Representative b. Hard Copy Distribution (if required in lieu of electronic distribution) 1) Tests performed by City a) Distribute 1 hard copy to the Contractor 2) Tests performed by the Contractor a) Distribute 3 hard copies to City’s Project Representative 4. Provide City’s Project Representative with trip tickets for each delivered load of Concrete or Lime material including the following information: a. Name of pit b. Date of delivery c. Material delivered B. Inspection 1. Inspection or lack of inspection does not relieve the Contractor from obligation to perform work in accordance with the Contract Documents. 1.5 SUBMITTALS [NOT USED] 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE [NOT USED] 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 03/20/2020 D.V. Magaña Removed reference to Buzzsaw and noted that electronic submittals be uploaded through the City’s document management system. 01 50 00 - 1 DAP TEMPORARY FACILITIES AND CONTROLS Page 1 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised JULY 1, 2011 SECTION 01 50 00 1 TEMPORARY FACILITIES AND CONTROLS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Provide temporary facilities and controls needed for the Work including, but not 6 necessarily limited to: 7 a. Temporary utilities 8 b. Sanitary facilities 9 c. Storage Sheds and Buildings 10 d. Dust control 11 e. Temporary fencing of the construction site 12 B. Deviations from this City of Fort Worth Standard Specification 13 1. None. 14 C. Related Specification Sections include, but are not necessarily limited to: 15 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 16 2. Division 1 – General Requirements 17 1.2 PRICE AND PAYMENT PROCEDURES 18 A. Measurement and Payment 19 1. Work associated with this Item is considered subsidiary to the various Items bid. 20 No separate payment will be allowed for this Item. 21 1.3 REFERENCES [NOT USED] 22 1.4 ADMINISTRATIVE REQUIREMENTS 23 A. Temporary Utilities 24 1. Obtaining Temporary Service 25 a. Make arrangements with utility service companies for temporary services. 26 b. Abide by rules and regulations of utility service companies or authorities 27 having jurisdiction. 28 c. Be responsible for utility service costs until Work is approved for Final 29 Acceptance. 30 1) Included are fuel, power, light, heat and other utility services necessary for 31 execution, completion, testing and initial operation of Work. 32 2. Water 33 a. Contractor to provide water required for and in connection with Work to be 34 performed and for specified tests of piping, equipment, devices or other use as 35 required for the completion of the Work. 36 b. Provide and maintain adequate supply of potable water for domestic 37 consumption by Contractor personnel and City’s Project Representatives. 38 c. Coordination 39 1) Contact City 1 week before water for construction is desired 40 01 50 00 - 2 DAP TEMPORARY FACILITIES AND CONTROLS Page 2 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised JULY 1, 2011 d. Contractor Payment for Construction Water 1 1) Obtain construction water meter from City for payment as billed by City’s 2 established rates. 3 3. Electricity and Lighting 4 a. Provide and pay for electric powered service as required for Work, including 5 testing of Work. 6 1) Provide power for lighting, operation of equipment, or other use. 7 b. Electric power service includes temporary power service or generator to 8 maintain operations during scheduled shutdown. 9 4. Telephone 10 a. Provide emergency telephone service at Site for use by Contractor personnel 11 and others performing work or furnishing services at Site. 12 5. Temporary Heat and Ventilation 13 a. Provide temporary heat as necessary for protection or completion of Work. 14 b. Provide temporary heat and ventilation to assure safe working conditions. 15 B. Sanitary Facilities 16 1. Provide and maintain sanitary facilities for persons on Site. 17 a. Comply with regulations of State and local departments of health. 18 2. Enforce use of sanitary facilities by construction personnel at job site. 19 a. Enclose and anchor sanitary facilities. 20 b. No discharge will be allowed from these facilities. 21 c. Collect and store sewage and waste so as not to cause nuisance or health 22 problem. 23 d. Haul sewage and waste off-site at no less than weekly intervals and properly 24 dispose in accordance with applicable regulation. 25 3. Locate facilities near Work Site and keep clean and maintained throughout Project. 26 4. Remove facilities at completion of Project 27 C. Storage Sheds and Buildings 28 1. Provide adequately ventilated, watertight, weatherproof storage facilities with floor 29 above ground level for materials and equipment susceptible to weather damage. 30 2. Storage of materials not susceptible to weather damage may be on blocks off 31 ground. 32 3. Store materials in a neat and orderly manner. 33 a. Place materials and equipment to permit easy access for identification, 34 inspection and inventory. 35 4. Equip building with lockable doors and lighting, and provide electrical service for 36 equipment space heaters and heating or ventilation as necessary to provide storage 37 environments acceptable to specified manufacturers. 38 5. Fill and grade site for temporary structures to provide drainage away from 39 temporary and existing buildings. 40 6. Remove building from site prior to Final Acceptance. 41 D. Temporary Fencing 42 1. Provide and maintain for the duration or construction when required in contract 43 documents 44 E. Dust Control 45 01 50 00 - 3 DAP TEMPORARY FACILITIES AND CONTROLS Page 3 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised JULY 1, 2011 1. Contractor is responsible for maintaining dust control through the duration of the 1 project. 2 a. Contractor remains on-call at all times 3 b. Must respond in a timely manner 4 F. Temporary Protection of Construction 5 1. Contractor or subcontractors are responsible for protecting Work from damage due 6 to weather. 7 1.5 SUBMITTALS [NOT USED] 8 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 9 1.7 CLOSEOUT SUBMITTALS [NOT USED] 10 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 11 1.9 QUALITY ASSURANCE [NOT USED] 12 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 13 1.11 FIELD [SITE] CONDITIONS [NOT USED] 14 1.12 WARRANTY [NOT USED] 15 PART 2 - PRODUCTS [NOT USED] 16 PART 3 - EXECUTION [NOT USED] 17 3.1 INSTALLERS [NOT USED] 18 3.2 EXAMINATION [NOT USED] 19 3.3 PREPARATION [NOT USED] 20 3.4 INSTALLATION 21 A. Temporary Facilities 22 1. Maintain all temporary facilities for duration of construction activities as needed. 23 3.5 [REPAIR] / [RESTORATION] 24 3.6 RE-INSTALLATION 25 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 26 3.8 SYSTEM STARTUP [NOT USED] 27 3.9 ADJUSTING [NOT USED] 28 3.10 CLEANING [NOT USED] 29 3.11 CLOSEOUT ACTIVITIES 30 A. Temporary Facilities 31 01 50 00 - 4 DAP TEMPORARY FACILITIES AND CONTROLS Page 4 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised JULY 1, 2011 1. Remove all temporary facilities and restore area after completion of the Work, to a 1 condition equal to or better than prior to start of Work. 2 3.12 PROTECTION [NOT USED] 3 3.13 MAINTENANCE [NOT USED] 4 3.14 ATTACHMENTS [NOT USED] 5 END OF SECTION 6 7 Revision Log DATE NAME SUMMARY OF CHANGE 8 01 55 26 - 1 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 1 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised July 1, 2011 SECTION 01 55 26 1 STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Administrative procedures for: 6 a. Street Use Permit 7 b. Modification of approved traffic control 8 c. Removal of Street Signs 9 B. Deviations from this City of Fort Worth Standard Specification 10 1. None. 11 C. Related Specification Sections include, but are not necessarily limited to: 12 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 13 2. Division 1 – General Requirements 14 3. Section 34 71 13 – Traffic Control 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Work associated with this Item is considered subsidiary to the various Items bid. 18 No separate payment will be allowed for this Item. 19 1.3 REFERENCES 20 A. Reference Standards 21 1. Reference standards cited in this specification refer to the current reference standard 22 published at the time of the latest revision date logged at the end of this 23 specification, unless a date is specifically cited. 24 2. Texas Manual on Uniform Traffic Control Devices (TMUTCD). 25 1.4 ADMINISTRATIVE REQUIREMENTS 26 A. Traffic Control 27 1. General 28 a. When traffic control plans are included in the Drawings, provide Traffic 29 Control in accordance with Drawings and Section 34 71 13. 30 b. When traffic control plans are not included in the Drawings, prepare traffic 31 control plans in accordance with Section 34 71 13 and submit to City for 32 review. 33 1) Allow minimum 10 working days for review of proposed Traffic Control. 34 B. Street Use Permit 35 1. Prior to installation of Traffic Control, a City Street Use Permit is required. 36 a. To obtain Street Use Permit, submit Traffic Control Plans to City 37 Transportation and Public Works Department. 38 01 55 26 - 2 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 2 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised July 1, 2011 1) Allow a minimum of 5 working days for permit review. 1 2) Contractor’s responsibility to coordinate review of Traffic Control plans for 2 Street Use Permit, such that construction is not delayed. 3 C. Modification to Approved Traffic Control 4 1. Prior to installation traffic control: 5 a. Submit revised traffic control plans to City Department Transportation and 6 Public Works Department. 7 1) Revise Traffic Control plans in accordance with Section 34 71 13. 8 2) Allow minimum 5 working days for review of revised Traffic Control. 9 3) It is the Contractor’s responsibility to coordinate review of Traffic Control 10 plans for Street Use Permit, such that construction is not delayed. 11 D. Removal of Street Sign 12 1. If it is determined that a street sign must be removed for construction, then contact 13 City Transportation and Public Works Department, Signs and Markings Division to 14 remove the sign. 15 E. Temporary Signage 16 1. In the case of regulatory signs, replace permanent sign with temporary sign meeting 17 requirements of the latest edition of the Texas Manual on Uniform Traffic Control 18 Devices (MUTCD). 19 2. Install temporary sign before the removal of permanent sign. 20 3. When construction is complete, to the extent that the permanent sign can be 21 reinstalled, contact the City Transportation and Public Works Department, Signs 22 and Markings Division, to reinstall the permanent sign. 23 F. Traffic Control Standards 24 1. Traffic Control Standards can be found on the City’s Buzzsaw website. 25 1.5 SUBMITTALS [NOT USED] 26 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 27 1.7 CLOSEOUT SUBMITTALS [NOT USED] 28 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 29 1.9 QUALITY ASSURANCE [NOT USED] 30 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 31 1.11 FIELD [SITE] CONDITIONS [NOT USED] 32 1.12 WARRANTY [NOT USED] 33 PART 2 - PRODUCTS [NOT USED] 34 PART 3 - EXECUTION [NOT USED] 35 END OF SECTION 36 01 55 26 - 3 DAP STREET USE PERMIT AND MODIFICATIONS TO TRAFFIC CONTROL Page 3 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised July 1, 2011 1 Revision Log DATE NAME SUMMARY OF CHANGE 2 01 57 13 - 1 DAP STORM WATER POLLUTION PREVENTION Page 1 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised July 1, 2011 SECTION 01 57 13 1 STORM WATER POLLUTION PREVENTION 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Procedures for Storm Water Pollution Prevention Plans 6 B. Deviations from this City of Fort Worth Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the 10 Contract 11 2. Division 1 – General Requirements 12 3. Section 31 25 00 – Erosion and Sediment Control 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Construction Activities resulting in less than 1 acre of disturbance 16 a. Work associated with this Item is considered subsidiary to the various Items 17 bid. No separate payment will be allowed for this Item. 18 2. Construction Activities resulting in greater than 1 acre of disturbance 19 a. Measurement and Payment shall be in accordance with Section 31 25 00. 20 1.3 REFERENCES 21 A. Abbreviations and Acronyms 22 1. Notice of Intent: NOI 23 2. Notice of Termination: NOT 24 3. Storm Water Pollution Prevention Plan: SWPPP 25 4. Texas Commission on Environmental Quality: TCEQ 26 5. Notice of Change: NOC 27 A. Reference Standards 28 1. Reference standards cited in this Specification refer to the current reference 29 standard published at the time of the latest revision date logged at the end of this 30 Specification, unless a date is specifically cited. 31 2. Integrated Storm Management (iSWM) Technical Manual for Construction 32 Controls 33 1.4 ADMINISTRATIVE REQUIREMENTS 34 A. General 35 1. Contractor is responsible for resolution and payment of any fines issued associated 36 with compliance to Stormwater Pollution Prevention Plan. 37 01 57 13 - 2 DAP STORM WATER POLLUTION PREVENTION Page 2 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised July 1, 2011 B. Construction Activities resulting in: 1 1. Less than 1 acre of disturbance 2 a. Provide erosion and sediment control in accordance with Section 31 25 00 and 3 Drawings. 4 2. 1 to less than 5 acres of disturbance 5 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction 6 Permit is required 7 b. Complete SWPPP in accordance with TCEQ requirements 8 1) TCEQ Small Construction Site Notice Required under general permit 9 TXR150000 10 a) Sign and post at job site 11 b) Prior to Preconstruction Meeting, send 1 copy to City Department of 12 Transportation and Public Works, Environmental Division, (817) 392-13 6088. 14 2) Provide erosion and sediment control in accordance with: 15 a) Section 31 25 00 16 b) The Drawings 17 c) TXR150000 General Permit 18 d) SWPPP 19 e) TCEQ requirements 20 3. 5 acres or more of Disturbance 21 a. Texas Pollutant Discharge Elimination System (TPDES) General Construction 22 Permit is required 23 b. Complete SWPPP in accordance with TCEQ requirements 24 1) Prepare a TCEQ NOI form and submit to TCEQ along with required fee 25 a) Sign and post at job site 26 b) Send copy to City Department of Transportation and Public Works, 27 Environmental Division, (817) 392-6088. 28 2) TCEQ Notice of Change required if making changes or updates to NOI 29 3) Provide erosion and sediment control in accordance with: 30 a) Section 31 25 00 31 b) The Drawings 32 c) TXR150000 General Permit 33 d) SWPPP 34 e) TCEQ requirements 35 4) Once the project has been completed and all the closeout requirements of 36 TCEQ have been met a TCEQ Notice of Termination can be submitted. 37 a) Send copy to City Department of Transportation and Public Works, 38 Environmental Division, (817) 392-6088. 39 1.5 SUBMITTALS 40 A. SWPPP 41 1. Submit in accordance with Section 01 33 00, except as stated herein. 42 a. Prior to the Preconstruction Meeting, submit a draft copy of SWPPP to the City 43 as follows: 44 1) 1 copy to the City Project Manager 45 a) City Project Manager will forward to the City Department of 46 Transportation and Public Works, Environmental Division for review 47 01 57 13 - 3 DAP STORM WATER POLLUTION PREVENTION Page 3 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised July 1, 2011 B. Modified SWPPP 1 1. If the SWPPP is revised during construction, resubmit modified SWPPP to the City 2 in accordance with Section 01 33 00. 3 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 4 1.7 CLOSEOUT SUBMITTALS [NOT USED] 5 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 6 1.9 QUALITY ASSURANCE [NOT USED] 7 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 8 1.11 FIELD [SITE] CONDITIONS [NOT USED] 9 1.12 WARRANTY [NOT USED] 10 PART 2 - PRODUCTS [NOT USED] 11 PART 3 - EXECUTION [NOT USED] 12 END OF SECTION 13 14 Revision Log DATE NAME SUMMARY OF CHANGE 15 01 60 00 - 1 DAP PRODUCT REQUIREMENTS Page 1 of 2 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 SECTION 01 60 00 1 PRODUCT REQUIREMENTS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. References for Product Requirements and City Standard Products List 6 B. Deviations from this City of Fort Worth Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10 2. Division 1 – General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES [NOT USED] 12 1.3 REFERENCES [NOT USED] 13 1.4 ADMINISTRATIVE REQUIREMENTS 14 A. A list of City approved products for use is located on Buzzsaw as follows: 15 1. Resources\02 - Construction Documents\Standard Products List 16 B. Only products specifically included on City’s Standard Product List in these Contract 17 Documents shall be allowed for use on the Project. 18 1. Any subsequently approved products will only be allowed for use upon specific 19 approval by the City. 20 C. Any specific product requirements in the Contract Documents supersede similar 21 products included on the City’s Standard Product List. 22 1. The City reserves the right to not allow products to be used for certain projects even 23 though the product is listed on the City’s Standard Product List. 24 D. Although a specific product is included on City’s Standard Product List, not all 25 products from that manufacturer are approved for use, including but not limited to, that 26 manufacturer’s standard product. 27 E. See Section 01 33 00 for submittal requirements of Product Data included on City’s 28 Standard Product List. 29 1.5 SUBMITTALS [NOT USED] 30 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 31 1.7 CLOSEOUT SUBMITTALS [NOT USED] 32 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 33 1.9 QUALITY ASSURANCE [NOT USED] 34 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 35 01 60 00 - 2 DAP PRODUCT REQUIREMENTS Page 2 of 2 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 PART 3 - EXECUTION [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 10/12/12 D. Johnson Modified Location of City’s Standard Product List 4/7/2014 M.Domenech Revised for DAP application 7 01 66 00 - 1 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 1 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 SECTION 01 66 00 1 PRODUCT STORAGE AND HANDLING REQUIREMENTS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Scheduling of product delivery 6 2. Packaging of products for delivery 7 3. Protection of products against damage from: 8 a. Handling 9 b. Exposure to elements or harsh environments 10 B. Deviations from this City of Fort Worth Standard Specification 11 1. None. 12 C. Related Specification Sections include, but are not necessarily limited to: 13 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 14 2. Division 1 – General Requirements 15 1.2 PRICE AND PAYMENT PROCEDURES 16 A. Measurement and Payment 17 1. Work associated with this Item is considered subsidiary to the various Items bid. 18 No separate payment will be allowed for this Item. 19 1.3 REFERENCES [NOT USED] 20 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 21 1.5 SUBMITTALS [NOT USED] 22 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 23 1.7 CLOSEOUT SUBMITTALS [NOT USED] 24 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 25 1.9 QUALITY ASSURANCE [NOT USED] 26 1.10 DELIVERY AND HANDLING 27 A. Delivery Requirements 28 1. Schedule delivery of products or equipment as required to allow timely installation 29 and to avoid prolonged storage. 30 2. Provide appropriate personnel and equipment to receive deliveries. 31 3. Delivery trucks will not be permitted to wait extended periods of time on the Site 32 for personnel or equipment to receive the delivery. 33 01 66 00 - 2 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 2 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 4. Deliver products or equipment in manufacturer's original unbroken cartons or other 1 containers designed and constructed to protect the contents from physical or 2 environmental damage. 3 5. Clearly and fully mark and identify as to manufacturer, item and installation 4 location. 5 6. Provide manufacturer's instructions for storage and handling. 6 B. Handling Requirements 7 1. Handle products or equipment in accordance with these Contract Documents and 8 manufacturer’s recommendations and instructions. 9 C. Storage Requirements 10 1. Store materials in accordance with manufacturer’s recommendations and 11 requirements of these Specifications. 12 2. Make necessary provisions for safe storage of materials and equipment. 13 a. Place loose soil materials and materials to be incorporated into Work to prevent 14 damage to any part of Work or existing facilities and to maintain free access at 15 all times to all parts of Work and to utility service company installations in 16 vicinity of Work. 17 3. Keep materials and equipment neatly and compactly stored in locations that will 18 cause minimum inconvenience to other contractors, public travel, adjoining owners, 19 tenants and occupants. 20 a. Arrange storage to provide easy access for inspection. 21 4. Restrict storage to areas available on construction site for storage of material and 22 equipment as shown on Drawings, or approved by City’s Project Representative. 23 5. Provide off-site storage and protection when on-site storage is not adequate. 24 a. Provide addresses of and access to off-site storage locations for inspection by 25 City’s Project Representative. 26 6. Do not use lawns, grass plots or other private property for storage purposes without 27 written permission of owner or other person in possession or control of premises. 28 7. Store in manufacturers’ unopened containers. 29 8. Neatly, safely and compactly stack materials delivered and stored along line of 30 Work to avoid inconvenience and damage to property owners and general public 31 and maintain at least 3 feet from fire hydrant. 32 9. Keep public and private driveways and street crossings open. 33 10. Repair or replace damaged lawns, sidewalks, streets or other improvements to 34 satisfaction of City’s Project Representative. 35 a. Total length which materials may be distributed along route of construction at 36 one time is 1,000 linear feet, unless otherwise approved in writing by City’s 37 Project Representative. 38 01 66 00 - 3 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 3 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 PART 3 - EXECUTION 4 3.1 INSTALLERS [NOT USED] 5 3.2 EXAMINATION [NOT USED] 6 3.3 PREPARATION [NOT USED] 7 3.4 ERECTION [NOT USED] 8 3.5 REPAIR / RESTORATION [NOT USED] 9 3.6 RE-INSTALLATION [NOT USED] 10 3.7 FIELD [OR] SITE QUALITY CONTROL 11 A. Tests and Inspections 12 1. Inspect all products or equipment delivered to the site prior to unloading. 13 B. Non-Conforming Work 14 1. Reject all products or equipment that are damaged, used or in any other way 15 unsatisfactory for use on the project. 16 3.8 SYSTEM STARTUP [NOT USED] 17 3.9 ADJUSTING [NOT USED] 18 3.10 CLEANING [NOT USED] 19 3.11 CLOSEOUT ACTIVITIES [NOT USED] 20 3.12 PROTECTION 21 A. Protect all products or equipment in accordance with manufacturer's written directions. 22 B. Store products or equipment in location to avoid physical damage to items while in 23 storage. 24 C. Protect equipment from exposure to elements and keep thoroughly dry if required by 25 the manufacturer. 26 3.13 MAINTENANCE [NOT USED] 27 3.14 ATTACHMENTS [NOT USED] 28 END OF SECTION 29 30 01 66 00 - 4 DAP PRODUCT STORAGE AND HANDLING REQUIREMENTS Page 4 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 1 01 70 00 - 1 DAP MOBILIZATION AND REMOBILIZATION Page 1 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 SECTION 01 70 00 1 MOBILIZATION AND REMOBILIZATION 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Mobilization and Demobilization 6 a. Mobilization 7 1) Transportation of Contractor’s personnel, equipment, and operating supplies 8 to the Site 9 2) Establishment of necessary general facilities for the Contractor’s operation 10 at the Site 11 3) Premiums paid for performance and payment bonds 12 4) Transportation of Contractor’s personnel, equipment, and operating supplies 13 to another location within the designated Site 14 5) Relocation of necessary general facilities for the Contractor’s operation 15 from 1 location to another location on the Site. 16 b. Demobilization 17 1) Transportation of Contractor’s personnel, equipment, and operating supplies 18 away from the Site including disassembly 19 2) Site Clean-up 20 3) Removal of all buildings and/or other facilities assembled at the Site for this 21 Contract 22 c. Mobilization and Demobilization do not include activities for specific items of 23 work that are for which payment is provided elsewhere in the contract. 24 2. Remobilization 25 a. Remobilization for Suspension of Work specifically required in the Contract 26 Documents or as required by City includes: 27 1) Demobilization 28 a) Transportation of Contractor’s personnel, equipment, and operating 29 supplies from the Site including disassembly or temporarily securing 30 equipment, supplies, and other facilities as designated by the Contract 31 Documents necessary to suspend the Work. 32 b) Site Clean-up as designated in the Contract Documents 33 2) Remobilization 34 a) Transportation of Contractor’s personnel, equipment, and operating 35 supplies to the Site necessary to resume the Work. 36 b) Establishment of necessary general facilities for the Contractor’s 37 operation at the Site necessary to resume the Work. 38 3) No Payments will be made for: 39 a) Mobilization and Demobilization from one location to another on the 40 Site in the normal progress of performing the Work. 41 b) Stand-by or idle time 42 c) Lost profits 43 3. Mobilizations and Demobilization for Miscellaneous Projects 44 a. Mobilization and Demobilization 45 01 70 00 - 2 DAP MOBILIZATION AND REMOBILIZATION Page 2 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 1) Mobilization shall consist of the activities and cost on a Work Order basis 1 necessary for: 2 a) Transportation of Contractor’s personnel, equipment, and operating 3 supplies to the Site for the issued Work Order. 4 b) Establishment of necessary general facilities for the Contractor’s 5 operation at the Site for the issued Work Order 6 2) Demobilization shall consist of the activities and cost necessary for: 7 a) Transportation of Contractor’s personnel, equipment, and operating 8 supplies from the Site including disassembly for each issued Work 9 Order 10 b) Site Clean-up for each issued Work Order 11 c) Removal of all buildings or other facilities assembled at the Site for 12 each Work Oder 13 b. Mobilization and Demobilization do not include activities for specific items of 14 work for which payment is provided elsewhere in the contract. 15 4. Emergency Mobilizations and Demobilization for Miscellaneous Projects 16 a. A Mobilization for Miscellaneous Projects when directed by the City and the 17 mobilization occurs within 24 hours of the issuance of the Work Order. 18 B. Deviations from this City of Fort Worth Standard Specification 19 1. None. 20 C. Related Specification Sections include, but are not necessarily limited to: 21 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 22 2. Division 1 – General Requirements 23 1.2 PRICE AND PAYMENT PROCEDURES 24 A. Measurement and Payment 25 1. Mobilization and Demobilization 26 a. Measure 27 1) This Item is considered subsidiary to the various Items bid. 28 b. Payment 29 1) The work performed and materials furnished in accordance with this Item 30 are subsidiary to the various Items bid and no other compensation will be 31 allowed. 32 2. Remobilization for suspension of Work as specifically required in the Contract 33 Documents 34 a. Measurement 35 1) Measurement for this Item shall be per each remobilization performed. 36 b. Payment 37 1) The work performed and materials furnished in accordance with this Item 38 and measured as provided under “Measurement” will be paid for at the unit 39 price per each “Specified Remobilization” in accordance with Contract 40 Documents. 41 c. The price shall include: 42 1) Demobilization as described in Section 1.1.A.2.a.1) 43 2) Remobilization as described in Section 1.1.A.2.a.2) 44 d. No payments will be made for standby, idle time, or lost profits associated this 45 Item. 46 01 70 00 - 3 DAP MOBILIZATION AND REMOBILIZATION Page 3 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 3. Remobilization for suspension of Work as required by City 1 a. Measurement and Payment 2 1) This shall be submitted as a Contract Claim in accordance with Article 10 3 of Section 00 72 00. 4 2) No payments will be made for standby, idle time, or lost profits associated 5 with this Item. 6 4. Mobilizations and Demobilizations for Miscellaneous Projects 7 a. Measurement 8 1) Measurement for this Item shall be for each Mobilization and 9 Demobilization required by the Contract Documents 10 b. Payment 11 1) The Work performed and materials furnished in accordance with this Item 12 and measured as provided under “Measurement” will be paid for at the unit 13 price per each “Work Order Mobilization” in accordance with Contract 14 Documents. Demobilization shall be considered subsidiary to mobilization 15 and shall not be paid for separately. 16 c. The price shall include: 17 1) Mobilization as described in Section 1.1.A.3.a.1) 18 2) Demobilization as described in Section 1.1.A.3.a.2) 19 d. No payments will be made for standby, idle time, or lost profits associated this 20 Item. 21 5. Emergency Mobilizations and Demobilizations for Miscellaneous Projects 22 a. Measurement 23 1) Measurement for this Item shall be for each Mobilization and 24 Demobilization required by the Contract Documents 25 b. Payment 26 1) The Work performed and materials furnished in accordance with this Item 27 and measured as provided under “Measurement” will be paid for at the unit 28 price per each “Work Order Emergency Mobilization” in accordance with 29 Contract Documents. Demobilization shall be considered subsidiary to 30 mobilization and shall not be paid for separately. 31 c. The price shall include 32 1) Mobilization as described in Section 1.1.A.4.a) 33 2) Demobilization as described in Section 1.1.A.3.a.2) 34 d. No payments will be made for standby, idle time, or lost profits associated this 35 Item. 36 1.3 REFERENCES [NOT USED] 37 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 38 1.5 SUBMITTALS [NOT USED] 39 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 40 1.7 CLOSEOUT SUBMITTALS [NOT USED] 41 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 42 1.9 QUALITY ASSURANCE [NOT USED] 43 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 44 01 70 00 - 4 DAP MOBILIZATION AND REMOBILIZATION Page 4 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 PART 3 - EXECUTION [NOT USED] 4 END OF SECTION 5 6 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 7 01 71 23 - 1 DAP CONSTRUCTION STAKING AND SURVEY Page 1 of 4 CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 TRINITY PARKS CPN 102606 Number] SECTION 01 71 23 CONSTRUCTION STAKING AND SURVEY PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Requirements for construction staking and construction survey B. Deviations from this City of Fort Worth Standard Specification 1. None. C. Related Specification Sections include, but are not necessarily limited to: 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 2. Division 1 – General Requirements 1.2 PRICE AND PAYMENT PROCEDURES A. Measurement and Payment 1. Construction Staking a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 2. Construction Survey a. Measurement 1) This Item is considered subsidiary to the various Items bid. b. Payment 1) The work performed and the materials furnished in accordance with this Item are subsidiary to the various Items bid and no other compensation will be allowed. 1.3 REFERENCES [NOT USED] 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 1.5 SUBMITTALS A. Submittals, if required, shall be in accordance with Section 01 33 00. B. All submittals shall be approved by the City prior to delivery. 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS A. Certificates 1. Provide certificate certifying that elevations and locations of improvements are in conformance or non-conformance with requirements of the Contract Documents. a. Certificate must be sealed by a registered professional land surveyor in the State of Texas. CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 TRINITY PARKS CPN 102606 Number] 01 71 23 - 2 DAP CONSTRUCTION STAKING AND SURVEY Page 2 of 4 B. Field Quality Control Submittals 1. Documentation verifying accuracy of field engineering work. 1.7 CLOSEOUT SUBMITTALS [NOT USED] 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 1.9 QUALITY ASSURANCE A. Construction Staking 1. Construction staking will be performed by the City. 2. Coordination a. Contact City’s Project Representative at least 2 weeks in advance for scheduling of Construction Staking. b. It is the Contractor’s responsibility to coordinate staking such that construction activities are not delayed or negatively impacted. 3. General a. Contractor is responsible for preserving and maintaining stakes furnished by City. b. If in the opinion of the City, a sufficient number of stakes or markings have been lost, destroyed or disturbed, by Contractor’s neglect, such that the contracted Work cannot take place, then the Contractor will be required to pay the City for new staking with a 25 percent markup. The cost for staking will be deducted from the payment due to the Contractor for the Project. B. Construction Survey 1. Construction Survey will be performed by the City. 2. Coordination a. Contractor to verify that control data established in the design survey remains intact. b. Coordinate with the City prior to field investigation to determine which horizontal and vertical control data will be required for construction survey. c. It is the Contractor’s responsibility to coordinate Construction Survey such that construction activities are not delayed or negatively impacted. d. Notify City if any control data needs to be restored or replaced due to damage caused during construction operations. 1) City shall perform replacements and/or restorations. 3. General a. Construction survey will be performed in order to maintain complete and accurate logs of control and survey work as it progresses for Project Records. b. The Contractor will need to ensure coordination is maintained with the City to perform construction survey to obtain construction features, including but not limited to the following: 1) All Utility Lines a) Rim and flowline elevations and coordinates for each manhole or junction structure 2) Water Lines a) Top of pipe elevations and coordinates for waterlines at the following locations: (1) Every 250 linear feet CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 TRINITY PARKS CPN 102606 Number] 01 71 23 - 3 DAP CONSTRUCTION STAKING AND SURVEY Page 3 of 4 (2) Horizontal and vertical points of inflection, curvature, etc. (All Fittings) (3) Cathodic protection test stations (4) Sampling stations (5) Meter boxes/vaults (All sizes) (6) Fire lines (7) Fire hydrants (8) Gate valves (9) Plugs, stubouts, dead-end lines (10) Air Release valves (Manhole rim and vent pipe) (11) Blow off valves (Manhole rim and valve lid) (12) Pressure plane valves (13) Cleaning wyes (14) Casing pipe (each end) b) Storm Sewer (1) Top of pipe elevations and coordinates at the following locations: (a) Every 250 linear feet (b) Horizontal and vertical points of inflection, curvature, etc. c) Sanitary Sewer (1) Top of pipe elevations and coordinates for sanitary sewer lines at the following locations: (a) Every 250 linear feet (b) Horizontal and vertical points of inflection, curvature, etc. (c) Cleanouts c. Construction survey will be performed in order to maintain complete and accurate logs of control and survey work associated with meeting or exceeding the line and grade required by these Specifications. d. The Contractor will need to ensure coordination is maintained with the City to perform construction survey and to verify control data, including but not limited to the following: 1) Established benchmarks and control points provided for the Contractor’s use are accurate 2) Benchmarks were used to furnish and maintain all reference lines and grades for tunneling 3) Lines and grades were used to establish the location of the pipe 4) Submit to the City copies of field notes used to establish all lines and grades and allow the City to check guidance system setup prior to beginning each tunneling drive. 5) Provide access for the City to verify the guidance system and the line and grade of the carrier pipe on a daily basis. 6) The Contractor remains fully responsible for the accuracy of the work and the correction of it, as required. 7) Monitor line and grade continuously during construction. 8) Record deviation with respect to design line and grade once at each pipe joint and submit daily records to City. 9) If the installation does not meet the specified tolerances, immediately notify the City and correct the installation in accordance with the Contract Documents. 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] CITY OF FORT WORTH STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS Revised April 7, 2014 TRINITY PARKS CPN 102606 Number] 01 71 23 - 4 DAP CONSTRUCTION STAKING AND SURVEY Page 4 of 4 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1.12 WARRANTY [NOT USED] PART 2 - PRODUCTS [NOT USED] PART 3 - EXECUTION 3.1 INSTALLERS [NOT USED] 3.2 EXAMINATION [NOT USED] 3.3 PREPARATION [NOT USED] 3.4 APPLICATION 3.5 REPAIR / RESTORATION [NOT USED] 3.6 RE-INSTALLATION [NOT USED] 3.7 FIELD [OR] SITE QUALITY CONTROL A. It is the Contractor’s responsibility to maintain all stakes and control data placed by the City in accordance with this Specification. B. Do not change or relocate stakes or control data without approval from the City. 3.8 SYSTEM STARTUP [NOT USED] 3.9 ADJUSTING [NOT USED] 3.10 CLEANING [NOT USED] 3.11 CLOSEOUT ACTIVITIES [NOT USED] 3.12 PROTECTION [NOT USED] 3.13 MAINTENANCE [NOT USED] 3.14 ATTACHMENTS [NOT USED] END OF SECTION Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 01 74 23 - 1 DAP CLEANING Page 1 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 SECTION 01 74 23 1 CLEANING 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Intermediate and final cleaning for Work not including special cleaning of closed 6 systems specified elsewhere 7 B. Deviations from this City of Fort Worth Standard Specification 8 1. None. 9 C. Related Specification Sections include, but are not necessarily limited to: 10 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 11 2. Division 1 – General Requirements 12 3. Section 32 92 13 – Hydro-Mulching, Seeding and Sodding 13 1.2 PRICE AND PAYMENT PROCEDURES 14 A. Measurement and Payment 15 1. Work associated with this Item is considered subsidiary to the various Items bid. 16 No separate payment will be allowed for this Item. 17 1.3 REFERENCES [NOT USED] 18 1.4 ADMINISTRATIVE REQUIREMENTS 19 A. Scheduling 20 1. Schedule cleaning operations so that dust and other contaminants disturbed by 21 cleaning process will not fall on newly painted surfaces. 22 2. Schedule final cleaning upon completion of Work and immediately prior to final 23 inspection. 24 1.5 SUBMITTALS [NOT USED] 25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 26 1.7 CLOSEOUT SUBMITTALS [NOT USED] 27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28 1.9 QUALITY ASSURANCE [NOT USED] 29 1.10 STORAGE, AND HANDLING 30 A. Storage and Handling Requirements 31 1. Store cleaning products and cleaning wastes in containers specifically designed for 32 those materials. 33 01 74 23 - 2 DAP CLEANING Page 2 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 1.11 FIELD [SITE] CONDITIONS [NOT USED] 1 1.12 WARRANTY [NOT USED] 2 PART 2 - PRODUCTS 3 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIEDPRODUCTS [NOT USED] 4 2.2 MATERIALS 5 A. Cleaning Agents 6 1. Compatible with surface being cleaned 7 2. New and uncontaminated 8 3. For manufactured surfaces 9 a. Material recommended by manufacturer 10 2.3 ACCESSORIES [NOT USED] 11 2.4 SOURCE QUALITY CONTROL [NOT USED] 12 PART 3 - EXECUTION 13 3.1 INSTALLERS [NOT USED] 14 3.2 EXAMINATION [NOT USED] 15 3.3 PREPARATION [NOT USED] 16 3.4 APPLICATION [NOT USED] 17 3.5 REPAIR / RESTORATION [NOT USED] 18 3.6 RE-INSTALLATION [NOT USED] 19 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 20 3.8 SYSTEM STARTUP [NOT USED] 21 3.9 ADJUSTING [NOT USED] 22 3.10 CLEANING 23 A. General 24 1. Prevent accumulation of wastes that create hazardous conditions. 25 2. Conduct cleaning and disposal operations to comply with laws and safety orders of 26 governing authorities. 27 3. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in 28 storm or sanitary drains or sewers. 29 4. Dispose of degradable debris at an approved solid waste disposal site. 30 5. Dispose of nondegradable debris at an approved solid waste disposal site or in an 31 alternate manner approved by City and regulatory agencies. 32 01 74 23 - 3 DAP CLEANING Page 3 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 6. Handle materials in a controlled manner with as few handlings as possible. 1 7. Thoroughly clean, sweep, wash and polish all Work and equipment associated with 2 this project. 3 8. Remove all signs of temporary construction and activities incidental to construction 4 of required permanent Work. 5 9. If project is not cleaned to the satisfaction of the City, the City reserves the right to 6 have the cleaning completed at the expense of the Contractor. 7 10. Do not burn on-site. 8 B. Intermediate Cleaning during Construction 9 1. Keep Work areas clean so as not to hinder health, safety or convenience of 10 personnel in existing facility operations. 11 2. At maximum weekly intervals, dispose of waste materials, debris and rubbish. 12 3. Confine construction debris daily in strategically located container(s): 13 a. Cover to prevent blowing by wind 14 b. Store debris away from construction or operational activities 15 c. Haul from site at a minimum of once per week 16 4. Vacuum clean interior areas when ready to receive finish painting. 17 a. Continue vacuum cleaning on an as-needed basis, until Final Acceptance. 18 5. Prior to storm events, thoroughly clean site of all loose or unsecured items, which 19 may become airborne or transported by flowing water during the storm. 20 C. Exterior (Site or Right of Way) Final Cleaning 21 1. Remove trash and debris containers from site. 22 a. Re-seed areas disturbed by location of trash and debris containers in accordance 23 with Section 32 92 13. 24 2. Sweep roadway to remove all rocks, pieces of asphalt, concrete or any other object 25 that may hinder or disrupt the flow of traffic along the roadway. 26 3. Clean any interior areas including, but not limited to, vaults, manholes, structures, 27 junction boxes and inlets. 28 4. If no longer required for maintenance of erosion facilities, and upon approval by 29 City, remove erosion control from site. 30 5. Clean signs, lights, signals, etc. 31 3.11 CLOSEOUT ACTIVITIES [NOT USED] 32 3.12 PROTECTION [NOT USED] 33 3.13 MAINTENANCE [NOT USED] 34 3.14 ATTACHMENTS [NOT USED] 35 36 37 38 39 40 01 74 23 - 4 DAP CLEANING Page 4 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 END OF SECTION 1 2 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 3 01 77 19 - 1 DAP CLOSEOUT REQUIREMENTS Page 1 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 SECTION 01 77 19 1 CLOSEOUT REQUIREMENTS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. The procedure for closing out a contract 6 B. Deviations from this City of Fort Worth Standard Specification 7 1. None. 8 C. Related Specification Sections include, but are not necessarily limited to: 9 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 10 2. Division 1 – General Requirements 11 1.2 PRICE AND PAYMENT PROCEDURES 12 A. Measurement and Payment 13 1. Work associated with this Item is considered subsidiary to the various Items bid. 14 No separate payment will be allowed for this Item. 15 1.3 REFERENCES [NOT USED] 16 1.4 ADMINISTRATIVE REQUIREMENTS 17 A. Guarantees, Bonds and Affidavits 18 1. No application for final payment will be accepted until all guarantees, bonds, 19 certificates, licenses and affidavits required for Work or equipment as specified are 20 satisfactorily filed with the City. 21 B. Release of Liens or Claims 22 1. No application for final payment will be accepted until satisfactory evidence of 23 release of liens has been submitted to the City. 24 1.5 SUBMITTALS 25 A. Submit all required documentation to City’s Project Representative. 26 01 77 19 - 2 DAP CLOSEOUT REQUIREMENTS Page 2 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 1.6 INFORMATIONAL SUBMITTALS [NOT USED] 1 1.7 CLOSEOUT SUBMITTALS [NOT USED] 2 PART 2 - PRODUCTS [NOT USED] 3 PART 3 - EXECUTION 4 3.1 INSTALLERS [NOT USED] 5 3.2 EXAMINATION [NOT USED] 6 3.3 PREPARATION [NOT USED] 7 3.4 CLOSEOUT PROCEDURE 8 A. Prior to requesting Final Inspection, submit: 9 1. Project Record Documents in accordance with Section 01 78 39 10 2. Operation and Maintenance Data, if required, in accordance with Section 01 78 23 11 B. Prior to requesting Final Inspection, perform final cleaning in accordance with Section 12 01 74 23. 13 C. Final Inspection 14 1. After final cleaning, provide notice to the City Project Representative that the Work 15 is completed. 16 a. The City will make an initial Final Inspection with the Contractor present. 17 b. Upon completion of this inspection, the City will notify the Contractor, in 18 writing within 10 business days, of any particulars in which this inspection 19 reveals that the Work is defective or incomplete. 20 2. Upon receiving written notice from the City, immediately undertake the Work 21 required to remedy deficiencies and complete the Work to the satisfaction of the 22 City. 23 3. Upon completion of Work associated with the items listed in the City's written 24 notice, inform the City, that the required Work has been completed. Upon receipt 25 of this notice, the City, in the presence of the Contractor, will make a subsequent 26 Final Inspection of the project. 27 4. Provide all special accessories required to place each item of equipment in full 28 operation. These special accessory items include, but are not limited to: 29 a. Specified spare parts 30 b. Adequate oil and grease as required for the first lubrication of the equipment 31 c. Initial fill up of all chemical tanks and fuel tanks 32 d. Light bulbs 33 e. Fuses 34 f. Vault keys 35 g. Handwheels 36 h. Other expendable items as required for initial start-up and operation of all 37 equipment 38 D. Notice of Project Completion 39 01 77 19 - 3 DAP CLOSEOUT REQUIREMENTS Page 3 of 3 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 1. Once the City Project Representative finds the Work subsequent to Final Inspection 1 to be satisfactory, the City will issue a Notice of Project Completion (Green Sheet). 2 E. Supporting Documentation 3 1. Coordinate with the City Project Representative to complete the following 4 additional forms: 5 a. Final Payment Request 6 b. Statement of Contract Time 7 c. Affidavit of Payment and Release of Liens 8 d. Consent of Surety to Final Payment 9 e. Pipe Report (if required) 10 f. Contractor’s Evaluation of City 11 g. Performance Evaluation of Contractor 12 F. Letter of Final Acceptance 13 1. Upon review and acceptance of Notice of Project Completion and Supporting 14 Documentation, in accordance with General Conditions, City will issue Letter of 15 Final Acceptance and release the Final Payment Request for payment. 16 3.5 REPAIR / RESTORATION [NOT USED] 17 3.6 RE-INSTALLATION [NOT USED] 18 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 19 3.8 SYSTEM STARTUP [NOT USED] 20 3.9 ADJUSTING [NOT USED] 21 3.10 CLEANING [NOT USED] 22 3.11 CLOSEOUT ACTIVITIES [NOT USED] 23 3.12 PROTECTION [NOT USED] 24 3.13 MAINTENANCE [NOT USED] 25 3.14 ATTACHMENTS [NOT USED] 26 END OF SECTION 27 28 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP application 29 01 78 23 - 1 DAP OPERATION AND MAINTENANCE DATA Page 1 of 5 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 SECTION 01 78 23 1 OPERATION AND MAINTENANCE DATA 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Product data and related information appropriate for City's maintenance and 6 operation of products furnished under Contract 7 2. Such products may include, but are not limited to: 8 a. Traffic Controllers 9 b. Irrigation Controllers (to be operated by the City) 10 c. Butterfly Valves 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. None. 13 C. Related Specification Sections include, but are not necessarily limited to: 14 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 – General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS 22 A. Schedule 23 1. Submit manuals in final form to the City within 30 calendar days of product 24 shipment to the project site. 25 1.5 SUBMITTALS 26 A. Submittals shall be in accordance with Section 01 33 00. All submittals shall be 27 approved by the City prior to delivery. 28 1.6 INFORMATIONAL SUBMITTALS 29 A. Submittal Form 30 1. Prepare data in form of an instructional manual for use by City personnel. 31 2. Format 32 a. Size: 8 ½ inches x 11 inches 33 b. Paper 34 1) 40 pound minimum, white, for typed pages 35 2) Holes reinforced with plastic, cloth or metal 36 c. Text: Manufacturer’s printed data, or neatly typewritten 37 01 78 23 - 2 DAP OPERATION AND MAINTENANCE DATA Page 2 of 5 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 d. Drawings 1 1) Provide reinforced punched binder tab, bind in with text 2 2) Reduce larger drawings and fold to size of text pages. 3 e. Provide fly-leaf for each separate product, or each piece of operating 4 equipment. 5 1) Provide typed description of product, and major component parts of 6 equipment. 7 2) Provide indexed tabs. 8 f. Cover 9 1) Identify each volume with typed or printed title "OPERATING AND 10 MAINTENANCE INSTRUCTIONS". 11 2) List: 12 a) Title of Project 13 b) Identity of separate structure as applicable 14 c) Identity of general subject matter covered in the manual 15 3. Binders 16 a. Commercial quality 3-ring binders with durable and cleanable plastic covers 17 b. When multiple binders are used, correlate the data into related consistent 18 groupings. 19 4. If available, provide an electronic form of the O&M Manual. 20 B. Manual Content 21 1. Neatly typewritten table of contents for each volume, arranged in systematic order 22 a. Contractor, name of responsible principal, address and telephone number 23 b. A list of each product required to be included, indexed to content of the volume 24 c. List, with each product: 25 1) The name, address and telephone number of the subcontractor or installer 26 2) A list of each product required to be included, indexed to content of the 27 volume 28 3) Identify area of responsibility of each 29 4) Local source of supply for parts and replacement 30 d. Identify each product by product name and other identifying symbols as set 31 forth in Contract Documents. 32 2. Product Data 33 a. Include only those sheets which are pertinent to the specific product. 34 b. Annotate each sheet to: 35 1) Clearly identify specific product or part installed 36 2) Clearly identify data applicable to installation 37 3) Delete references to inapplicable information 38 3. Drawings 39 a. Supplement product data with drawings as necessary to clearly illustrate: 40 1) Relations of component parts of equipment and systems 41 2) Control and flow diagrams 42 b. Coordinate drawings with information in Project Record Documents to assure 43 correct illustration of completed installation. 44 c. Do not use Project Record Drawings as maintenance drawings. 45 4. Written text, as required to supplement product data for the particular installation: 46 a. Organize in consistent format under separate headings for different procedures. 47 b. Provide logical sequence of instructions of each procedure. 48 01 78 23 - 3 DAP OPERATION AND MAINTENANCE DATA Page 3 of 5 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 5. Copy of each warranty, bond and service contract issued 1 a. Provide information sheet for City personnel giving: 2 1) Proper procedures in event of failure 3 2) Instances which might affect validity of warranties or bonds 4 C. Manual for Materials and Finishes 5 1. Submit 5 copies of complete manual in final form. 6 2. Content, for architectural products, applied materials and finishes: 7 a. Manufacturer's data, giving full information on products 8 1) Catalog number, size, composition 9 2) Color and texture designations 10 3) Information required for reordering special manufactured products 11 b. Instructions for care and maintenance 12 1) Manufacturer's recommendation for types of cleaning agents and methods 13 2) Cautions against cleaning agents and methods which are detrimental to 14 product 15 3) Recommended schedule for cleaning and maintenance 16 3. Content, for moisture protection and weather exposure products: 17 a. Manufacturer's data, giving full information on products 18 1) Applicable standards 19 2) Chemical composition 20 3) Details of installation 21 b. Instructions for inspection, maintenance and repair 22 D. Manual for Equipment and Systems 23 1. Submit 5 copies of complete manual in final form. 24 2. Content, for each unit of equipment and system, as appropriate: 25 a. Description of unit and component parts 26 1) Function, normal operating characteristics and limiting conditions 27 2) Performance curves, engineering data and tests 28 3) Complete nomenclature and commercial number of replaceable parts 29 b. Operating procedures 30 1) Start-up, break-in, routine and normal operating instructions 31 2) Regulation, control, stopping, shut-down and emergency instructions 32 3) Summer and winter operating instructions 33 4) Special operating instructions 34 c. Maintenance procedures 35 1) Routine operations 36 2) Guide to "trouble shooting" 37 3) Disassembly, repair and reassembly 38 4) Alignment, adjusting and checking 39 d. Servicing and lubrication schedule 40 1) List of lubricants required 41 e. Manufacturer's printed operating and maintenance instructions 42 f. Description of sequence of operation by control manufacturer 43 1) Predicted life of parts subject to wear 44 2) Items recommended to be stocked as spare parts 45 g. As installed control diagrams by controls manufacturer 46 h. Each contractor's coordination drawings 47 1) As installed color coded piping diagrams 48 01 78 23 - 4 DAP OPERATION AND MAINTENANCE DATA Page 4 of 5 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 i. Charts of valve tag numbers, with location and function of each valve 1 j. List of original manufacturer's spare parts, manufacturer's current prices, and 2 recommended quantities to be maintained in storage 3 k. Other data as required under pertinent Sections of Specifications 4 3. Content, for each electric and electronic system, as appropriate: 5 a. Description of system and component parts 6 1) Function, normal operating characteristics, and limiting conditions 7 2) Performance curves, engineering data and tests 8 3) Complete nomenclature and commercial number of replaceable parts 9 b. Circuit directories of panelboards 10 1) Electrical service 11 2) Controls 12 3) Communications 13 c. As installed color coded wiring diagrams 14 d. Operating procedures 15 1) Routine and normal operating instructions 16 2) Sequences required 17 3) Special operating instructions 18 e. Maintenance procedures 19 1) Routine operations 20 2) Guide to "trouble shooting" 21 3) Disassembly, repair and reassembly 22 4) Adjustment and checking 23 f. Manufacturer's printed operating and maintenance instructions 24 g. List of original manufacturer's spare parts, manufacturer's current prices, and 25 recommended quantities to be maintained in storage 26 h. Other data as required under pertinent Sections of Specifications 27 4. Prepare and include additional data when the need for such data becomes apparent 28 during instruction of City's personnel. 29 1.7 CLOSEOUT SUBMITTALS [NOT USED] 30 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 31 1.9 QUALITY ASSURANCE 32 A. Provide operation and maintenance data by personnel with the following criteria: 33 1. Trained and experienced in maintenance and operation of described products 34 2. Skilled as technical writer to the extent required to communicate essential data 35 3. Skilled as draftsman competent to prepare required drawings 36 01 78 23 - 5 DAP OPERATION AND MAINTENANCE DATA Page 5 of 5 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 1.10 DELIVERY, STORAGE, AND HANDLING [NOT USED] 1 1.11 FIELD [SITE] CONDITIONS [NOT USED] 2 1.12 WARRANTY [NOT USED] 3 PART 2 - PRODUCTS [NOT USED] 4 PART 3 - EXECUTION [NOT USED] 5 END OF SECTION 6 7 Revision Log DATE NAME SUMMARY OF CHANGE 8/31/2012 D. Johnson 1.5.A.1 – title of section removed 4/7/2014 M.Domenech Revised for DAP Application 8 01 78 39 - 1 DAP PROJECT RECORD DOCUMENTS Page 1 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 SECTION 01 78 39 1 PROJECT RECORD DOCUMENTS 2 PART 1 - GENERAL 3 1.1 SUMMARY 4 A. Section Includes: 5 1. Work associated with the documenting the project and recording changes to project 6 documents, including: 7 a. Record Drawings 8 b. Water Meter Service Reports 9 c. Sanitary Sewer Service Reports 10 d. Large Water Meter Reports 11 B. Deviations from this City of Fort Worth Standard Specification 12 1. None. 13 C. Related Specification Sections include, but are not necessarily limited to: 14 1. Division 0 – Bidding Requirements, Contract Forms and Conditions of the Contract 15 2. Division 1 – General Requirements 16 1.2 PRICE AND PAYMENT PROCEDURES 17 A. Measurement and Payment 18 1. Work associated with this Item is considered subsidiary to the various Items bid. 19 No separate payment will be allowed for this Item. 20 1.3 REFERENCES [NOT USED] 21 1.4 ADMINISTRATIVE REQUIREMENTS [NOT USED] 22 1.5 SUBMITTALS 23 A. Prior to submitting a request for Final Inspection, deliver Project Record Documents to 24 City’s Project Representative. 25 1.6 ACTION SUBMITTALS/INFORMATIONAL SUBMITTALS [NOT USED] 26 1.7 CLOSEOUT SUBMITTALS [NOT USED] 27 1.8 MAINTENANCE MATERIAL SUBMITTALS [NOT USED] 28 1.9 QUALITY ASSURANCE 29 A. Accuracy of Records 30 1. Thoroughly coordinate changes within the Record Documents, making adequate 31 and proper entries on each page of Specifications and each sheet of Drawings and 32 other Documents where such entry is required to show the change properly. 33 2. Accuracy of records shall be such that future search for items shown in the Contract 34 Documents may rely reasonably on information obtained from the approved Project 35 Record Documents. 36 01 78 39 - 2 DAP PROJECT RECORD DOCUMENTS Page 2 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 3. To facilitate accuracy of records, make entries within 24 hours after receipt of 1 information that the change has occurred. 2 4. Provide factual information regarding all aspects of the Work, both concealed and 3 visible, to enable future modification of the Work to proceed without lengthy and 4 expensive site measurement, investigation and examination. 5 1.10 STORAGE AND HANDLING 6 A. Storage and Handling Requirements 7 1. Maintain the job set of Record Documents completely protected from deterioration 8 and from loss and damage until completion of the Work and transfer of all recorded 9 data to the final Project Record Documents. 10 2. In the event of loss of recorded data, use means necessary to again secure the data 11 to the City's approval. 12 a. In such case, provide replacements to the standards originally required by the 13 Contract Documents. 14 1.11 FIELD [SITE] CONDITIONS [NOT USED] 15 1.12 WARRANTY [NOT USED] 16 PART 2 - PRODUCTS 17 2.1 OWNER-FURNISHED [OR] OWNER-SUPPLIED PRODUCTS [NOT USED] 18 2.2 RECORD DOCUMENTS 19 A. Job set 20 1. Promptly following receipt of the Notice to Proceed, secure from the City, at no 21 charge to the Contractor, 1 complete set of all Documents comprising the Contract. 22 B. Final Record Documents 23 1. At a time nearing the completion of the Work and prior to Final Inspection, provide 24 the City 1 complete set of all Final Record Drawings in the Contract. 25 2.3 ACCESSORIES [NOT USED] 26 2.4 SOURCE QUALITY CONTROL [NOT USED] 27 PART 3 - EXECUTION 28 3.1 INSTALLERS [NOT USED] 29 3.2 EXAMINATION [NOT USED] 30 3.3 PREPARATION [NOT USED] 31 3.4 MAINTENANCE DOCUMENTS 32 A. Maintenance of Job Set 33 1. Immediately upon receipt of the job set, identify each of the Documents with the 34 title, "RECORD DOCUMENTS - JOB SET". 35 01 78 39 - 3 DAP PROJECT RECORD DOCUMENTS Page 3 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 2. Preservation 1 a. Considering the Contract completion time, the probable number of occasions 2 upon which the job set must be taken out for new entries and for examination, 3 and the conditions under which these activities will be performed, devise a 4 suitable method for protecting the job set. 5 b. Do not use the job set for any purpose except entry of new data and for review 6 by the City, until start of transfer of data to final Project Record Documents. 7 c. Maintain the job set at the site of work. 8 3. Coordination with Construction Survey 9 a. At a minimum clearly mark any deviations from Contract Documents 10 associated with installation of the infrastructure. 11 4. Making entries on Drawings 12 a. Record any deviations from Contract Documents. 13 b. Use an erasable colored pencil (not ink or indelible pencil), clearly describe the 14 change by graphic line and note as required. 15 c. Date all entries. 16 d. Call attention to the entry by a "cloud" drawn around the area or areas affected. 17 e. In the event of overlapping changes, use different colors for the overlapping 18 changes. 19 5. Conversion of schematic layouts 20 a. In some cases on the Drawings, arrangements of conduits, circuits, piping, 21 ducts, and similar items, are shown schematically and are not intended to 22 portray precise physical layout. 23 1) Final physical arrangement is determined by the Contractor, subject to the 24 City's approval. 25 2) However, design of future modifications of the facility may require 26 accurate information as to the final physical layout of items which are 27 shown only schematically on the Drawings. 28 b. Show on the job set of Record Drawings, by dimension accurate to within 1 29 inch, the centerline of each run of items. 30 1) Final physical arrangement is determined by the Contractor, subject to the 31 City's approval. 32 2) Show, by symbol or note, the vertical location of the Item ("under slab", "in 33 ceiling plenum", "exposed", and the like). 34 3) Make all identification sufficiently descriptive that it may be related 35 reliably to the Specifications. 36 c. The City may waive the requirements for conversion of schematic layouts 37 where, in the City's judgment, conversion serves no useful purpose. However, 38 do not rely upon waivers being issued except as specifically issued in writing 39 by the City. 40 B. Final Project Record Documents 41 1. Transfer of data to Drawings 42 a. Carefully transfer change data shown on the job set of Record Drawings to the 43 corresponding final documents, coordinating the changes as required. 44 b. Clearly indicate at each affected detail and other Drawing a full description of 45 changes made during construction, and the actual location of items. 46 c. Call attention to each entry by drawing a "cloud" around the area or areas 47 affected. 48 01 78 39 - 4 DAP PROJECT RECORD DOCUMENTS Page 4 of 4 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 Revised April 7, 2014 d. Make changes neatly, consistently and with the proper media to assure 1 longevity and clear reproduction. 2 2. Transfer of data to other Documents 3 a. If the Documents, other than Drawings, have been kept clean during progress of 4 the Work, and if entries thereon have been orderly to the approval of the City, 5 the job set of those Documents, other than Drawings, will be accepted as final 6 Record Documents. 7 b. If any such Document is not so approved by the City, secure a new copy of that 8 Document from the City at the City's usual charge for reproduction and 9 handling, and carefully transfer the change data to the new copy to the approval 10 of the City. 11 3.5 REPAIR / RESTORATION [NOT USED] 12 3.6 RE-INSTALLATION [NOT USED] 13 3.7 FIELD [OR] SITE QUALITY CONTROL [NOT USED] 14 3.8 SYSTEM STARTUP [NOT USED] 15 3.9 ADJUSTING [NOT USED] 16 3.10 CLEANING [NOT USED] 17 3.11 CLOSEOUT ACTIVITIES [NOT USED] 18 3.12 PROTECTION [NOT USED] 19 3.13 MAINTENANCE [NOT USED] 20 3.14 ATTACHMENTS [NOT USED] 21 END OF SECTION 22 23 Revision Log DATE NAME SUMMARY OF CHANGE 4/7/2014 M.Domenech Revised for DAP Application 24 CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 GC-4.02 Subsurface and Physical Conditions THIS PAGE LEFT INTENTIONALLY BLANK TRINITY PROJECT - 11432 PIPELINE ROAD EULESS, TX SUBMITTED TO: PROJECT NO. SUBMITTED DATE: ECM DEVELOPMENT, LLC 0619-2797 AUGUST 20, 2019 Geotechnical & Environmental Engineering Construction Materials Testing Laboratory Testing LANDTEC ENGINEERS, LLC 1700 Robert Road Suite 101 Mansfield, Texas 76063 / 817.572.2818 Arlington I Fort Worth I Mansfield I The Colony August 20, 2019 Report No. 0619-2797 TJ Moore, President ECM Development 4010-7 North Collins Street Arlington, Texas 76005 RE: Geotechnical Engineering Exploration and Report Trinity Project – 11432 Pipeline Road, Euless, Texas The results of our final geotechnical study for the referenced project are presented in the following engineering report. The study has been conducted in general agreement with our proposal and your subsequent authorization to proceed. Thank you for this opportunity to provide engineering services on this project. If you have any questions, please let us know. Sincerely, LANDTEC ENGINEERS, LLC G. Scott Graves, E.I.T. Thomas D. Baker, P.E., RPLS Project Engineer Sr. Geotechnical Engineer August 20, 2019 Texas Board of Professional Engineers Texas Board of Professional Land Surveyors Firm Registration No. F-000329 Firm Registration No. 100956-00 Distribution by PDF: T.J. Moore LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc i TABLE OF CONTENTS ________________________________________________________________ Section Page No. 1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 1.1 Project Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 1.2 Purpose and Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 2 Subsurface Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 2.1 Subsurface Stratification . . . . . . . . . . . . . . . . . . . . . . . . . . 2 2.2 Subsurface Seepage Observations . . . . . . . . . . . . . . . . . 3 2.3 Geology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 2.4 Seismic Site Classification . . . . . . . . . . . . . . . . . . . . . . . . . 4 3 Analysis and Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . 5 3.1 Geotechnical Considerations . . . . . . . . . . . . . . . . . . . . . . 5 3.2 Potential Vertical Movements (PVM) . . . . . . . . . . . . . . . . . 6 3.3 Slab-On-Grade Foundation Recommendations . . . . . . . . 7 4 Moisture Control – Site Grading and Landscaping . . . . . . . . . . . . 8 5 Site Grading and Earthwork . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 5.1 General Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 5.2 Subgrade Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 5.3 Placing of Material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 5.4 Moisture and Density Control . . . . . . . . . . . . . . . . . . . . . . . 13 5.5 Excavations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 5.6 Acceptance of Imported Fill . . . . . . . . . . . . . . . . . . . . . . . . . 17 6 General Comments and Conditions . . . . . . . . . . . . . . . . . . . . . . . . 17 ________________________________________________________________ APPENDIX A – Plan of Borings, Boring Logs & General Notes, Description of Field Exploration APPENDIX B – Summary of Laboratory Results, Description of Laboratory Testing APPENDIX C – Drainage Illustrations APPENDIX D – Site Photos APPENDIX E – GBA Statement LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 1 1.0 INTRODUCTION 1.1 Project Description The following final geotechnical engineering report presents the results of a geotechnical study for the 19-acre Trinity Project at 11432 Pipeline Road in Euless, Texas. A preliminary report was provided on July 29, 2019 and since that time additional information has been provided to LandTec Engineers, additional analysis of field and laboratory data occurred, and, additional site observations were made. A site plan indicating lots and blocks was provided to LandTec by ECM and was used to prepare our Plan of Borings. The development will consist of one and two story, lightly loaded houses supported by slab- on-grade foundations. Below grade slabs and/or basements are not planned for these structures. At the time of our field exploration the site appears to have been mined for sand and gravel in the past and now consists of open areas with grass and small tree growth, partially wooded and vegetated areas, some areas of fill material dumped at the site including concrete, asphalt, wood, brick, rocks and rubble (construction type debris). See photos in Appendix C. Elevations within the areas of our 5 borings range from approximately Elev. 540 ft. near Boring B-1 on the north to Elev. 532 ft. near Boring B-4 on the southeast side of the site. Several random piles of soil are higher in elevation than the borings and there are also areas lower in surface elevation than the borings. A pond is present in the southwest part of the site as shown on the Plan of Borings and there may be other areas where water surfaces exist. 1.2 Purpose and Scope The purpose of these services is to provide information and geotechnical engineering recommendations for site grading and foundations for homes in the proposed development. Our scope of services included the following.  Exploring subsurface conditions and obtaining soil samples.  Obtain physical soil properties by laboratory testing including classification, strength, dry unit weight and particularly to determine current soil moisture content and swell potential. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 2  Provide an estimate of the Potential Soil Movement (PVM) values using both Tex- 124-E calculations and swell test data.  Provide foundation recommendations and allowable bearing capacity.  Provide recommendations for general earthwork and fill placement including compaction and moisture requirements. The geotechnical recommendations presented in this report are based on the available information provided by the client and subsurface conditions described in this report. If any of the stated information is incorrect, please inform LandTec Engineers in writing so that we may amend the recommendations presented in this report if appropriate. The scope of services did not include an environmental assessment for determining the presence or absence of wetlands, or hazardous or toxic materials in the soil, bedrock, surface water, groundwater, or air on or below, or around this site. Any statements in this report or on the boring logs regarding odors, colors, and unusual or suspicious items or conditions are strictly for informational purposes. The scope of services did not include any slope stability analysis for embankments, cut-fill slopes, excavations or retaining walls. These services can be provided under a separate proposal, if requested by the client. 2.0 SUBSURFACE CONDITIONS 2.1 Subsurface Stratification The five (5) widely spaced borings drilled for the exploration of the site encountered sand, sand/gravel mixtures, clayey sand, sandy lean clay, lean clay and clay. Some fill and/or possible fill material was also encountered in the borings to various depths as shown on the boring logs. In some cases the soils appear to be natural in situ soils and in other cases the soils appear to be fill material with similar characteristics of color, plasticity and consistency. Boring B-2 encountered blackish gray and brown to black material to approximately 15 feet below existing grade. The area of this boring should be explored to determine the horizontal and vertical limits of the fill. Fill from this boring should be removed and replaced with compacted soils consisting of clayey sands and sandy clays (SC and low CL Class Soils) and be tested using the moisture and density specs provided in Section 5, General Site Grading. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 3 Areas at the site with obvious piles of construction debris, concrete, rubble, wood, etc. (see Appendix C) should also be removed and replaced with compacted soils are referenced in the previous paragraph. The horizontal and vertical limits of the random debris piles may not be known until encountered during site grading work, excavating and proof rolling. Consistency terms for the soil (firm, stiff, very stiff, hard, etc.) are for relative comparison of the various samples and are not intended to be used as an indication of the ease or difficulty of excavation or excavation stability. Soil consistency terms on the logs may be based upon a combination of the test and observation methods listed in the general notes and upon field observations. Soil samples obtained during the drilling and sampling process were visually observed and descriptions recorded including type, texture, color, consistency and moisture. From these observations of the various soils encountered in the borings from top to bottom, laboratory test assignments were made to determine the soil plasticity, consistency, strength, moisture content and swell potential. 2.2 Subsurface Seepage Observations Shallow subsurface seepage was observed in the borings during the drilling on July 3, 2019. The depth where seepage was observed during drilling ranged from approximately 10 to 15 feet below existing grade. See “Remarks” section of boring log for information. Subsurface seepage water is subject to fluctuations over time due to seasonal variations in the amount of rainfall or lack of (drought); site topography and runoff; hydraulic conductivity of soil strata; and other factors not evident at the time the borings were performed. Installation of piezometers placed into water bearing zones above and/or within the primary shale and sandstone underlying this site would be required to determine the actual perched groundwater regime. Water traveling through the soil (subsurface water) is often unpredictable. This could be due to seasonal changes in shallow subsurface water and due to the unpredictable nature of subsurface seepage paths. Therefore, it is necessary during construction for the contractor to be observant for shallow subsurface seepage in excavations in order to assess the situation and make necessary changes and/or recommendations. Installation of monitor wells or piezometers placed into water bearing zones above and/or within the sands and clayey sands underlying this site would be required to determine the actual perched groundwater regime. Groundwater monitoring devices were not part of our service but can be installed if requested and a separate proposal with specific details and cost can be provided upon request. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 4 2.3 Geology Based on area geology maps, borings performed at the site and general experience, the site is situated within alluvial deposits and residual Woodbine Formation soils. The site appears to have been mined for sand and gravel in some areas. See prior descriptions of the site materials and conditions in 2.1 and 2.2. The alluvial soils consist of a wide range of materials including sandy lean clay, clayey sand, sand and gravel. The iron ore gravel encountered in several borings is fairly typical of alluvial deposits. Some of the soils at this site are anticipated to be residual soils of the Woodbine Geological Formation. Sands, clays, sandstones and shales generally compose the Woodbine formation. Iron oxides, lignite, gypsum, and pyrite are also found throughout the formation. Dense and irregular shaped masses or hard sandstone occur at random throughout the formation and are commonly referred to as "boulders." Structurally, the Woodbine is quite complex in that it contains numerous small faults, lenticular masses, and consequent divergent dips. It is often difficult, if not impossible, to trace a particular bed for any distance. Water is found at various levels in the formation, some as perched tables in sand lenses. Although not encountered at this site in the borings, very hard limy sandstone ROCK boulders and layers have been encountered during excavation, utility installation and pier construction on nearby sites. The hard rock has typically been observed to exist as layers and/or boulders that are a few feet thick to over 10 feet thick. Penetration into and through the rock typically requires rock tooth buckets, auger bits, core barrels, drop chisels and other hard rock tools. 2.4 Seismic Site Classification The site has been classified with respect to seismic design criteria contained in the 2015 International Building Code (IBC), Section 1613 1. The criteria require characterization of the upper 100 feet of subsurface materials. Based on the IBC criteria, the site is classified as Site Class “C” and “D” depending on the boring location as per Table 1613.5.2 for the upper 20 feet. Note the IBC requires a site soil profile determination extending a depth of 100 feet for seismic site classification. However, our scope of services did not include a boring to 100 feet. The deepest boring only extended to 20 feet, and it can only be estimated that the soils encountered continues to a depth of 100 feet. 1 International Building Code (2009). Section 1613, Earthquake Loads LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 5 3.0 ANALYSIS AND RECOMMENDATIONS 3.1 Geotechnical Considerations Earthwork at this site should be observed by the project geotechnical engineer of record and by the geotechnical engineers soil technician/site representative stationed at the site full time to observe proof rolling, removal of the unsuitable debris, rubble, soils and organics and to observe and test the new fill material used to establish design grades across the site. As previously discussed, the area of Boring B-2 should be explored to determine the horizontal and vertical limits of the fill material which should be removed and replaced with compacted and tested soils consisting of clayey sands and sandy clays (SC and low CL Class Soils) using the moisture and density specifications provided in Section 5, General Site Grading. Differential movement within the foundation can be prevented by the use of a pier and beam foundation. This type foundation consists of drilled piers placed below the zone of seasonal moisture change and/or to a specific bearing depth or material. If slab movements must be limited to less than one inch, structurally suspended slabs and grade beams are recommended. The slab and grade beams are structurally supported above the ground by the drilled pier foundation. If a pier and beam foundation system is desired, additional borings and tests will need to be performed at the site to locate suitable bearing material for pier and beam foundations. We understand proposed one and two story homes are planned for this development and the homes will be supported by slab-on-grade, post-tensioned foundations. It should be pointed out that this type of soil supported slab-on-grade foundation will have some level of risk. Soil supported slab-on-grade foundations are not designed to resist soil and foundation movements resulting from water ponding around and below the foundation, sewer and/or plumbing leaks, excessive landscape irrigation, poor drainage, and, lack of proper maintenance. Geotechnical design information for shallow slab-on-grade foundations is included in the following paragraphs. If the Post Tensioned Institute (PTI) design methodology is utilized by the structural engineer, both climatically controlled and non-climatically controlled variables should be accounted for in the overall design. Utility ditches should be backfilled so that they do not become conduits that allow surface water to flow adjacent to or below the foundation. This can be accomplished by the use of clay or concrete plugs placed within the trench backfill. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 6 Therefore, it is imperative that the developer, builder and home owner follow and implement all requirements of the geotechnical engineering report, designs made by the civil and structural engineer, appropriate Building Codes and the cities current required edition of the International Building Code (IBC) when constructing foundations and homes in this development. Since lot drainage is one of the most important items to the success of slab-on-ground foundations on expansive clay soils, it is imperative the builder and homeowner not change or block drainage swales around and between houses. The swales were designed by the civil engineer and installed by the developer to allow storm water and other water to quickly flow away from the house pad in order to prevent ponding of water. 3.2 Potential Vertical Movements (PVM) Soils can undergo shrink and swell as the soil moisture content fluctuates during seasonal wet and dry cycles and can undergo settlement with time and under certain loading conditions. The potential magnitude of soil movements can only be estimated, due to factors influenced by specific soil properties such as moisture and density, overburden pressure, site drainage, ponding of surface water, and, the overall soil moisture contents at various times during and post foundation installation. One of the methods used to estimate Potential Vertical Rise (PVR) includes Texas Department of Transportation (TxDOT) Method 124-E. Using this method as a guide only, the procedure can be used to determine a value or range of values for predicted movements of potentially expansive clay soils when they change from “dry” to “wet” soil moisture conditions. The term Potential Vertical Movement (PVM) can be considered as a measurement of the change in height of a building slab or pavement from its original constructed elevation. Swell tests can also be used to estimate PVM. Based on the information developed from our study at the time of this report, PVM values on the order of approximately 2 to 4 inches have been determined for the borings. Residential developments, where potentially expansive soils are present, will typically have variable soil and climatically controlled soil moisture conditions, especially with the ever changing North Texas weather, ranging from wet, rainy years to other years with extreme drought. Subsurface conditions consisting of fill material with variable moisture, density and plasticity also impact the design of slab-on-grade foundations. The slab designer must choose from a range of possible design assumptions used in each of the geotechnical engineer’s models to conscientiously choose the proper set of conditions that are applicable at the time of construction and location of each slab-on grade foundation. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 7 3.3 Slab-On-Grade Foundation Recommendations Stiffened, monolithically placed slab-on-grade foundations, either rebar or post-tensioned, should be designed by the structural slab design engineer to resist the estimated differential movements as provided herein. Note the PTI design methodology only accounts for climatically controlled variables. Non-climatically controlled variables include, but are not limited to pre-existing vegetation, slopes, cut and fill sections, landscaping, irrigation, installation of post-construction trees and droughts. The final design of the foundation system should also consider the anticipated PVM which has been estimated. Grade beam and footing excavations should be observed to determine that all excessively loose, soft, or otherwise undesirable materials are removed and that foundations will bear on satisfactory material. Soil exposed in the bases of all satisfactory grade beam excavations should be protected against detrimental change in condition such as from disturbance, rain, or excessive drying. Surface runoff should be drained away from the excavations and not allowed to pond. See Section 4.0 Moisture Control, for recommended site grading and landscaping requirements. Beams may be designed based on an allowable soil bearing pressure of 1,500 pounds per square foot or less within the shallow soils. The beams should extend eighteen (18) inches into natural undisturbed soil or compacted and tested fill. The beam depth is given in regards to bearing capacity and is not intended to be a structural recommendation regarding stiffness. The beam width should be 10 inches minimum. A moisture barrier material should be used beneath the slab to retard moisture migration. Grade beam and footing excavations should be observed to determine that all excessively loose, soft, or otherwise undesirable materials are removed and that foundations will bear on satisfactory material. Soil exposed in the bases of all satisfactory grade beam excavations should be protected against detrimental change in condition such as from disturbance, rain, or excessive drying. Surface runoff should be drained away from the excavations and not allowed to pond. These values should be utilized by the structural engineer to design a foundation system which can accommodate anticipated climatically and non-climatically controlled movements. Accordingly, while PTI values for climatically driven conditions are provided, estimates of non-climatically controlled movements are also provided and intended for incorporation into the final structural design. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 8 Table 3-1 Estimated Slab-On-Grade Design Parameters EEddggee MMooiissttuurree VVaarriiaattiioonn,, eemm DDiiffffeerreennttiiaall SSwweellll,, yymm CCeenntteerr LLiifftt,, fftt.. EEddggee LLiifftt,, fftt.. CCeenntteerr LLiifftt,, iinncchheess EEddggee LLiifftt,, iinncchheess 77..00 33..88 22..00 22..77 NNootteess:: 11 VVaalluueess bbaasseedd oonn VVOOLLFFLLOOWW VVeerrssiioonn 11..55 aanndd DDeessiiggnn ooff PPoosstt TTeennssiioonn SSllaabbss--oonn--GGrraaddee,, TThhiirrdd AAddddiittiioonn.. 22 TThhee oorriiggiinnaall rreesseeaarrcchh wwhhiicchh ffoorrmmss tthhee bbaassiiss ffoorr tthhee PPTTII ddeessiiggnn mmeetthhoodd eexxtteennddeedd oonnllyy ttoo YYmm vvaalluueess ooff 44 iinncchheess.. AAlltteerrnnaattiivveellyy,, ffoorr YYmm vvaalluueess oovveerr 44 iinncchheess aa ddiiffffeerreenntt ttyyppee ooff ffoouunnddaattiioonn ddeessiiggnn mmeetthhoodd,, ssuucchh aass ffiinniittee eelleemmeennttss,, mmaayy bbee uusseedd.. CCoonnssiiddeerraattiioonn sshhoouulldd bbee ggiivveenn ttoo uussiinngg mmeetthhooddss ootthheerr tthhaann PPTTII ffoorr ddeessiiggnn ttoo rreessiisstt tthhee eessttiimmaatteedd llaarrggee ddiiffffeerreennttiiaall ssooiill mmoovveemmeennttss.. 4.0 MOISTURE CONTROL – SITE GRADING AND LANDSCAPING To reduce the potential for moisture induced soil movement (uplift) as well as shrinkage (settlement), it is very important that measures be taken to control moisture changes around and below the structure. The following recommendations/comments should be incorporated into the overall project design. 1. Site grading should be designed to provide surface drainage so that water does not pond during or after construction. A minimum slope of 10 percent should be provided, such that the ground surface slopes away from the structure 10 feet or to paving. This consists of one (1) foot of drop for the first 10 feet of the ground surface away from the slab. The slab should be higher than the outside surrounding flatwork, sidewalks, entries, paving and curbs. Low areas caused by landscaping features (which also include irrigation) should be drained and/or sloped to drain so that water (irrigation or storm water) do not pond. Ponding water next to the building will cause sidewalks, entries, and any other type of flatwork to undergo differential movement, usually upward. 2. A complete gutter and downspout system is recommended. Water from roof gutters should be collected and transmitted to the storm drain system, a paved area, a drainage swale or sufficient distance from the foundation (approximately 10 to 15 feet). If downspouts discharge next to the structure onto flatwork or paved areas, the area should be watertight in order to eliminate infiltration next to the foundation and below flatwork. Joints should be sealed against moisture penetration and planned maintenance checks should repair and replace damaged joint sealer. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 9 3. Utility ditches should be backfilled so that they do not become conduits that allow surface water to flow adjacent to or below the foundation. This can be accomplished by the use of clay or concrete plugs placed within the trench backfill. Plugs should have a minimum length of three (3) feet along the trench above and below the utility pipe. The gravel embedment should be removed in this 3-foot section to prevent water from flowing through the backfill. A positive cut-off at the building line is required to prevent water from migrating along the trench and through the utility backfill. Utility trenches should not be left open for extended periods. 4. Landscape irrigation systems should be designed and located to prevent excessive moisture adjacent to the foundation. Systems should not be located where water will be sprayed onto building walls and subsequently drain downward and flow into the soils beneath foundations. 5. Utilities which project through floor slabs, particularly where expansive soils or soils subject to settlement are present, should be designed with some degree of flexibility and/or with a sleeve to reduce the potential for damage to the utilities should movement occur. 6. Contraction, control, or expansion joints should be designed and placed throughout the structure. Properly planned placement of these joints will assist in controlling the degree and location of material cracking which normally occurs due to material shrinkage, thermal effects, soil movements and other related structural conditions. 7. Landscape borders consisting of metal, wood, stone or other types of edging must not prevent water from flowing away from the slab and/or cause water to pond. Water must be able to flow freely away from the slab and enter a drainage swale and flow away from the slab. If any grades prevent the quick removal of water, an under-drain must be installed to collect the water and cause it to flow to an outfall point so that the water flows into a storm drain, paved surface or at least 25 feet away from the slab. Check local city codes to determine where French drains can outfall and ADA compliance requirements for slopes. 8. Trees should not be planted next to the foundation. A distance equal to the mature tree height from the foundation is suggested. A vertical moisture barrier can be used between the tree and the foundation. Tree root systems extend out from the tree to find moisture, especially in times of drought, and planting the tree the recommended distance from the slab will help prevent drying and shrinkage of the soil next to and below the foundation. This drying out and shrinkage of the soil can cause settlement of the foundation grade beam and slab. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 10 9. The key is to maintain uniform moisture around and below the foundation on a year around basis. The soil must not dry out nor become too wet. This will require deliberate effort on the part of the home owner and should be explained to the home owner in a document and in regular home owner association meetings. 10. The home owner should maintain the drainage around the foundation slab as provided when the pad was originally graded to design grades. The home owner must not change drainage patterns and cause ponding of surface or subsurface water. 11. The builder and/or home owner must not install landscape beds, plant shrubs or trees; construct patios, concrete pads, place gravel beds and A/C units within the designed drainage swale which was installed by the developer. Fence panels should not be placed into the ground and prevent storm water flow and change drainage patterns. The drainage swale between houses must be free of all objects that would block the design intent of the swale itself and that is to provide a drainage swale to quickly remove storm water or other sources of water. 12. The home builder should specify the concrete strength for slabs; perform temperature, slump and compressive strength tests as well as Quality Assurance observation during concrete placement by an independent Construction Materials Engineering and Testing company. Prior to pouring the foundation concrete, the beam depth and width, beam spacing, and sloughed soil and mud are removed from the beam excavation. 13. Post tension cables should be installed per the Post Tension slab design and checked by an independent inspector prior to concrete placement. Tendon stressing must be monitored and recorded by an independent inspector. The independent inspector can be an independent Construction Materials Engineering and Testing company, or, the inspection can be provided by the structural engineer that performed the foundation design. 14. Flatwork and pavement will be subject to post construction movement. Maximum grades practical should be used for paving and flatwork to help prevent areas where water can pond. Where paving or flatwork abuts the structures care should be taken that the joints are properly sealed and maintained to prevent the infiltration of surface water. All ADA requirements must be followed. 15. Homeowners should be advised that it is important to maintain relatively uniform ground moisture conditions throughout the life of the house to decrease shrinkage of the soils around the perimeter of the structure and reduce related foundation distress. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 11 5.0 SITE GRADING AND EARTHWORK 5.1 General This section of the report provides recommendations for site grading and observation/testing by the project geotechnical engineer or the engineers field representative. Recommendations are provided for grading including vegetation stripping, preparation of subgrade, scarifying, placement methods for fill based on what will be constructed in a particular area. Recommendations for lift thickness, moisture and density, processing, compaction methods, observation and testing the subgrade and fill are also provided. The following paragraphs apply to general earthwork at the project site. If additional fill material is needed at this site, it should be select fill material consisting of clayey sand or sandy lean clay with a Plasticity Index (PI) between 6 and 15. Other types of off-site soils proposed for the site and used to raise grades and/or backfill where existing unsuitable fill material is removed, can be evaluated by the project geotechnical engineer on a case by case basis by performing soil classification tests, standard Proctor tests, swell tests and possibly environmental tests depending on the source of the soil. 5.2 Subgrade Preparation Stripping should consist of the removal of roots, organics, vegetation, debris and rubbish not removed by the clearing and grubbing operation. The actual stripping and over- excavation depth should be based on field observations with particular attention given to old fill material and debris, drainage areas, uneven topography, and excessively wet soils. The stripped areas should be observed by LandTec Engineers to determine if additional excavation is required to remove weak or otherwise objectionable materials that would adversely affect the fill placement. The subgrade should be firm and able to support the construction equipment without displacement. Soft or yielding subgrade should be corrected and made stable before construction proceeds. The subgrade should be proof rolled to detect soft spots, which if exist, should be reworked. Proof rolling is an important item and should be performed using a heavy pneumatic tired roller, loaded dump truck or scraper or similar equipment weighing approximately 20 tons. The proof rolling operations must be observed by the project geotechnical engineer or the engineer’s field representative. In areas of the subgrade which, in the opinion of the project geotechnical engineer, are too soft, wet or otherwise unstable to allow fill construction to begin, the use of thicker initial layers (lifts) or use of geogrids may be required. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 12 The traffic of heavy equipment, including heavy compaction equipment, may create pumping and general deterioration of the soil. Occasionally some soils have to be excavated, mixed and dried, and replaced. At times, excavating and replacing with selected soils is required before an adequate subgrade can be achieved. Therefore, it should be anticipated that some construction difficulties will be encountered during periods when these soils are saturated. It will be very important to “MUCK OUT” ponds, drainage ways, etc. and remove soft, wet soils prior to filling in these areas. The earthwork contractor should be specifically directed as to the process of mucking out these types of site features to remove undesirable soft wet soils, prior to filling. If fill is placed over the soft soils, the new fill will settle and cause differential movement within the overlying fill and structures. The wet muck material will need to be excavated down to firm ground. A field representative of LandTec Engineers should be present during the excavating operation to verify removal of the soft, wet soils and to confirm the subgrade is suitable prior to filling. The wet material should be hauled to a suitable disposal area or off site to a landfill facility. 5.3 Placing of Material Fill material should be placed on a properly prepared subgrade as specified. The combined excavation, placing, and spreading operation should be done in such a manner to obtain blending of material, and to provide that the materials, when compacted will have the most practicable degree of compaction and stability. Materials excavated from cut sections and/or borrow sources and hauled to construct fills must be mixed and not segregated, except where such segregated soil zones are required. All fill should be placed in horizontal lifts. Filling along (parallel to) slopes should not be permitted. In areas where slopes will be constructed using fill, the fill should extend beyond finished contours and cut back to grade. If the surface of the fill is too smooth and hard to bond properly with a succeeding layer, the surface should be roughened and loosened by disking before the succeeding layer is placed. Where fill is to be placed next to existing fill, that fill should be removed to un-weathered, dense material. Each layer should be benched and disked as adjoining lifts are placed. Material hauling equipment should be so routed over the fill surface to distribute the added compaction afforded by the rolling equipment, and to prevent the formation of ruts on the surface. The surface of the fill should be graded to drain freely and maintained throughout construction. During the dumping and spreading process, the contractor should maintain at all times a force of personnel adequate to remove all roots and debris and all rocks greater LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 13 than about six (6) inches in maximum dimension from the fill materials. No rocks should be allowed within the final 18 inches of subgrade. Where sandstone, siltstone or other rock like materials are placed as fill, the material must be broken down to pieces less than 6- inches in diameter. This will be accomplished by large dozers, Cat 815 compactors or other suitable equipment that is acceptable to the project geotechnical engineer of record. In the event of slides in any part of the fill prior to final acceptance of the work, the contractor should remove material from the slide area and should rebuild such portion of the fill as requested by the project geotechnical engineer. 5.4 Moisture and Density Control Following the spreading and mixing of the soil, it should be processed and blended throughout its thickness to break up and provide additional mixing of materials. If the grading contractor dumps large blocks of soil from earth moving equipment, the soil should be worked with a dozer to break the blocks into sizes that can then be further broken down and blended with rippers or disc plows. Prior to placing the next layer of fill, the previously processed, compacted and tested lift should be lightly watered to created bond with subsequent lifts. The recommended loose lift thickness is eight (8) inches. The moisture content of the soil should be adjusted, if necessary, by either aeration or the addition of water to bring the moisture content within the specified range. Water required for sprinkling to bring the fill material to the proper moisture content should be applied evenly through each layer. Any layers which become damaged by weather conditions should be reprocessed to meet specification requirements. The compacted surface of a layer of fill should be lightly loosened by disking before the succeeding layer is placed. When the moisture content and the condition of the fill layer are satisfactory, compaction should be made with a self-propelled tamping-foot roller (sheep foot with cleaner teeth). The recommended compactor should be a Caterpillar 815 or similar compactor approved by the project geotechnical engineer. The tamping-foot length should be a minimum of eight (8) inches. Vibratory tamping rollers may be required for compacting some types of fill material. Non-plastic sands and granular materials should be compacted to a dry density of at least 95 percent of standard Proctor maximum dry density (ASTM D698) and within the range of 2 percentage points below to 2 percentage points above the materials optimum moisture content (-2 to +2). LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 14 In some cases very sandy, cohesionless materials will be difficult to compact and become unstable and the sands may have to be mixed with more cohesive clayey soils and/or chemical additives such Portland cement may need to be added. The geotechnical engineer should be advised of such a situation so that recommendations can be made. Clayey sands and sandy lean clays with a Plasticity Index (PI) below 20 should be compacted to a dry density of at least 95 percent of standard Proctor maximum dry density (D698) and within the range of optimum to four percentage points above the materials optimum moisture content (0 to +4). Lean clay and clay fill material with a Plasticity Index (PI) equal to or greater than 20 should be compacted to a minimum of ninety-three (93) percent but not over ninety-eight (98) percent of the maximum dry density as determined by the moisture-density relations test method ASTM Designation D 698 for standard Proctor. The moisture content for the clay fill should be to a minimum of four (4) percentage points above optimum (minimum of +4). Some adjustment in the recommended moisture content may be required, depending on the soil type, and will be made by the geotechnical engineer of record. The moisture content ranges specified are to be considered as allowable ranges. The contractor may have to maintain a more narrow range (within the maximum allowable) in order to consistently achieve the specified density for some soils or under some conditions. The moisture content and density of all fill material should be maintained at the specified range of moisture and density. Where fill depths including utility excavations exceed 10 feet, the compaction should be 100 percent as a minimum with a moisture content of -2 to +2, but will depend upon the site specific area in question and the intended use of the fill area as well as overlying structures. Field density tests should be taken as each lift of fill material is placed. One field density test per lift for each 5,000 square feet of compacted area is recommended. The project geotechnical engineer maintains the right to adjust the frequency of compaction tests based on actual field conditions and the contractor’s performance. The earthwork operations should be observed and tested on a continuing basis by an experienced engineering soil technician working in conjunction with the project geotechnical engineer. The contractor is responsible for notifying the testing agency’s on site field representative when an area is ready for compaction testing. The contractor should assist the engineering technician in taking tests to the extent of furnishing labor and equipment to prepare the areas for testing and curtailing operations in the vicinity of the test area during testing. Where compaction tests do not comply with the specifications, the contractor will rework the area and then inform the area is ready for re- tests. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 15 Each lift should be compacted, tested, and approved before another lift is added. The purpose of the field density tests is to provide some indication that uniform and adequate compaction is being obtained. Trench backfill for utilities should be properly placed and compacted. Dense or dry backfill can swell and create a mound along the ditch line. Loose or wet backfill can settle and form a depression along the ditch line. Distress to overlying structures, pavements, sidewalks, etc. can occur if heaving or settling happens. A granular bedding material is recommended for pipe bedding. Clean coarse sand or well graded crushed rock make good bedding materials. In all cases the City requirements for utility line embedment material should be followed. Care should be taken to prevent the backfilled trench throughout the subdivision development from becoming French Drains and piping surface or subsurface water beneath structures or pavements or from draining the shallow perched water from the site resulting in increasing the slab-on-grade design swell potential estimates of both PVR and PVM. The use of numerous concrete cut-off collars or clay plugs will likely be required to prevent this from occurring. LandTec should be involved in reviewing utility plans and observe the deeper upslope utility excavations to provide additional recommendations for construction of these water controlling items. Trench backfill should be placed and compacted in uniform lifts of 8 to 12 inches and be tested for moisture and density. We recommend that each lift be tested with spacing of 150 to 300 feet along the trench. Compaction should be to a minimum of 95 percent of standard Proctor density (ASTM D 698) at a moisture content ranging from one percentage point below optimum to four percentage points above optimum (-1 to +4). Where trench depths exceed 10 feet, compaction of the backfill should be to a minimum of 98% of standard Proctor, for that portion of the trench backfill below 10 feet and as determined by the geotechnical engineer. During installation of water, sanitary sewer and storm water utility lines if organics, concrete, asphalt or other types of debris are encountered in excavations they should be removed and replaced with select soil backfill placed in lifts and tested as referenced previously for trench backfill. 5.5 Excavations Excavations should consider the stability of adjacent structures, street pavement, underground utilities, etc. Unstable soils include, but are not necessarily limited to, (1) jointed, fissured, and slickensided materials (2) soils with pockets or layers of sand or gravel, and (3) soils with groundwater seepage occurring. Slopes in these types of soils may become unstable during periods of wet weather or as loads are applied to the top LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 16 and/or along the slope. The stability is also affected by weather conditions, excavation depth, adjacent structures, construction equipment, and the length of time the excavation will remain open. Surcharge loads, either static or dynamic, should not be applied to the slope, particularly at the top of slope. Construction equipment should be prevented from traveling along or near the top of the excavation slope. Monitoring of temporary slopes, trenches, and dewatering during construction should be undertaken by the contractor to detect early warnings of movement within slopes, structures, pavements, etc. Excavations should be shored to provide stability up-slope and to protect construction workers. In all cases, the requirements of the Occupational Safety and Health Administration (OSHA) must be followed. It is important for the contractor to monitor the slope stability by observation and measurement, and to prevent excessive loads (especially heavy vibratory loads) from being applied to the slope. The contractor should be responsible for maintaining the slopes in a safe condition during construction and the use of slope stability monitoring equipment is recommended. Inclinometers are one means of measuring slope movement. This report has not been prepared for trench safety design and slope angle design. In the Federal Register, Volume 54, No. 209 (October 1989), the United States Department of Labor, Occupational Safety and Health Administration (OSHA) amended its “Construction Standards for Excavations, 29 CFR, part 1926, Subpart P”. This document was issued to better insure the safety of workmen entering trenches or excavations. It is mandated by this federal regulation that excavations, whether they be utility trenches, basement excavation or footing excavations, be constructed in accordance with the new OSHA guidelines. It is our understanding that these regulations will be strictly enforced and if they are not closely followed, the owner and the contractor could be liable for substantial penalties. The contractor is solely responsible for designing and constructing stable, temporary excavations and should shore, slope, or bench the sides of the excavations as required to maintain stability of both the excavation sides and bottom. The contractor’s “responsible person”, as defined in 29 CFR Part 1926, should evaluate the soil exposed in the excavations as part of the contractor’s safety procedures. In no case should slope height, slope inclination, or excavation depth, including utility trench excavation depth, exceed those specified in local, state, and federal safety regulations. We are providing this information solely as a service to our client. LandTec Engineers does not assume responsibility for construction site safety or the contractor’s or other parties’ compliance with the local, state, and federal safety or other regulations. Fill or cut slopes constructed in the soils at the site should generally be maintained on slopes no steeper than 5 horizontal to 1 vertical (5H:1V) for slopes up to 5 feet. Some slopes in this geological formation could require flatter slopes. Slopes over 5 feet in height LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 17 should be designed based on site specific geometry and soil strength parameters. This report has not been prepared for slope angle design. Slope stability analysis for existing slopes, planned cut or fill slopes, and, slopes associated with retaining walls was not part of this scope of geotechnical engineering services. If desired and requested, a scope of services for additional engineering services can be provided. All slopes, whether temporary construction slopes or permanent fill slopes should be designed to allow drainage at planned areas where erosion protection can be provided, instead of allowing surface water to flow down unprotected slopes. Vegetative ground cover should be provided as soon as practical to completed slopes. 5.6 Acceptance of Imported Fill The owner and project geotechnical engineer must approve any soil hauled onto this project from off-site sources. The contractor must obtain a written, notarized certification from the landowner of each proposed off-site soil borrow source stating that to the best of the landowner's knowledge and belief there has never been contamination of the borrow source site with hazardous or toxic materials. The certification must be furnished to the owner prior to proceeding to furnish soils to the site. Soil materials derived from the excavation of underground petroleum storage tanks shall not be used as fill on this project. 6.0 GENERAL COMMENTS AND CONDITIONS In any geotechnical study, the design recommendations are based on a limited amount of information about the subsurface conditions. In the analysis, the geotechnical engineer must assume the subsurface conditions are similar to the conditions encountered in the boring. However, during construction, anomalies in the subsurface conditions are quite often revealed. Confirmation-Dependent Recommendations: Do not rely on these recommendations until the Geotechnical Engineer of Record (GER) confirms through field observation that the inferred conditions on which the recommendations are based are the conditions that actually exist. If observation suggests otherwise, your GER will develop the necessary modifications. The project geotechnical engineer of record should be retained to observe earthwork and foundation installation and perform materials evaluation during the construction phase of the project. This enables the project geotechnical engineer to stay abreast with the project and to be readily available to evaluate unanticipated conditions, to conduct additional tests if required and, when necessary, to recommend alternative solutions to unanticipated conditions. LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 18 It is proposed that construction observation commence at the outset of the proj ect. Experience has shown that the most suitable method for procuring these services is for the owner to contract directly with the geotechnical / materials engineer. This results in a clear, direct line of communication between the owner or his representative and the geotechnical / materials engineer. The services described in this report were performed consistent with generally accepted geotechnical engineering principles and practices. No other warranty, expressed or implied, is made. These services were performed in agreement with our client. This report is solely for the use and information of our client unless otherwise noted. Any reliance on this report by a third party is at such party's sole risk. Opinions and recommendations contained in this report apply to conditions existing when services were performed and are intended only for the client, purposes, locations, time frames, and project parameters indicated. We do not warrant the accuracy of information supplied by others, or the use of segregated portions of this report. The conclusions and recommendations in this report are invalid if:  the report is used for adjacent or other property or buildings;  grades, shallow perched seepage water levels, or both, change between the issuance of this report and construction;  any other change is implemented that materially alters the project from that proposed when this report was prepared The boring logs do not provide a warranty of the conditions that may exist at the entire site. The extent and nature of subsurface soil and shallow perched seepage variations may not become evident until construction begins. Variations in soil conditions between borings could possibly exist between or beyond the points of exploration or groundwater elevations may change, both of which may require additional studies, consultation, and possible design revisions. Any person associated with this project who observes conditions or features of the site or surrounding areas that are different from those described in this report should rep8ort the differences immediately for consideration and evaluation. This report was prepared solely for the use of our client and should be reviewed in its entirety. Surface and subsurface conditions can change over a period of time. If there is a substantial lapse of time between this report being issued and the start of construction at the site, conditions could have changed due to natural causes and/or to construction work. The site could have been excavated and/or filled after the borings were made and subsurface seepage could be higher or lower than when the borings were made. The recommendations provided in the report should not be considered applicable for an LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc 19 extended timeframe after the borings were made. LandTec should be contacted to review contents of the report if the client suspects the site has been altered by excavation or filling or any other activities noticed by the client, especially if 6 to 12 months or more have passed since the report was issued. It is recommended that LANDTEC be retained to review those portions of the plans and specifications for this project that pertain to geotechnical recommendations contained in this report as a means to determine whether the recommendations have been interpreted as intended. This is typically done when the plans are at the 50 to 75 percent design level. APPENDIX A Field Exploration � 0 � � z c� D M �. €� ; �� �� . . � �0 Z � � � 0 I . I � i, R D � � � D < Z �� � � �< � � .. � _, �- F � -�� �- • r� .� .,. �� : �� � � ; � � _ �+ �-+ ! +� , � y� � � � � ' � } � y � � �L �=� , , � � . , ,� � i '� , � � F � '.��� '- � ''� , � � � F , f � � � Ili . � � y .��{ �. � �. ' _� •- � - # � � � ' ' 1 ' _ �� ,�� . � � ` f 'r �� �� � �� � � ^� - � . . � } � ���� � � f f� / � p�y-F — J� • i ' J • � �5 �� -� �" _ -� _ c � � -�r�s � _ �, • w� t. � �• � � � T � �� � � - • r '� � � y • I ��'� � ' ^ � r =� � �� .� � � • ' ' ��"'� f r � �� , F � � ' a � M - � { - � � f � � � � • M' : � � � �• . • + ' ` � -� �� • '�i � �' � rt_r �..� 1�F, �_�-��. � cn. � � � . _ • '1� , � . �� � � � y _ � . y'�'r " " � ;� + ti E ���isi���Er � �` � ; , ��' ��_ � }+ F r F �� �, z � �• . . . . � � , m �.�r.i.,. - � � . _ � . � � t�. � - � - � - �.-x ` 1 - o X-.��.�'= ��, .� �� � -. .� � _ �- _�. { .�� � _ _�. .{ � 1 � �� � _t . � °' _ �� � ��' +�' y- `� i � ' � � . . �, � �-_� �, � � . . F � � � � , �,` �_ ' + f � �� 7 f � � 4 � � � �" � I "" �� i� I_. , 7' � � �� '1 ' 7� � J ' � . ; - � -� a � � `- L k � � ■ � ■ „ � i� � � � � � � �• � � �_�� ��� rt� � '� • � � � �- � � � � 1, r � , _ '�' e� , t''� ti j'. •• _ � � � . . F � � x � . ' _ _, 4i + ` W � � * �" � ` - , ' -� � �' �,- ��"S � �� � z 1 .y*+ - . - - - - .' �� r � -� � 0 i f, + i � ; *' � -.n � _ �-.' ' r - �. O � �.�.. � .. �—_�.� � �,.�.. ���� :. � � `+ � � � � - o � � O � Z 0 0 rn � � N J � J � �1 � � D � m 0 � � N O � � � i. � � . _ _ . 1�. . .. . � - . 1 a � Z l' .C�"� TRINITY PRO ECT OF B1�432GPIPELINE RD ENGINEERS EULESS, TEXAS TBPE REGISTRATION N0. F-329 TBPLS REGISTRATION N0. 100956-00 1700 ROBERT ROAD, STE 101 817-572-2818 4:\Projecta\7rinty Project-Pipeline Rd GEO - 2797\DR4WING\POe.dwg MANSFIELD, TX 76063 WWW.LANDTECENG.COM 9.1 3.8 40 17 29 CLAY, brown & grayish brown w/crushed concrete fill & tan sand seams, very stiff, dry (FILL) SANDY LEAN CLAY, light brown w/crushed rock, very stiff, dry (FILL) SANDY LEAN CLAY & CLAYEY SAND (SC-CL), reddish tan, very stiff, dry (FILL) SANDY LEAN CLAY, reddish tan & gray w/tan sand seams w/iron ore staining, very stiff, dry to moist w/lean clay layers (FILL) -seams of crushed stone & concrete @ approximately 8.5' CLAYEY SAND, tan, moist to wet w/iron ore particles SAND w/some gravel, tan & gray, medium dense to dense, water bearing 118.3 111.4 537.6 536.6 534.6 527.6 524.6 519.6 2.0 3.0 5.0 12.0 15.0 20.0 4.5+ 4.5+ 4.5+ 4.5+ 4.0 4.5+ 4.5+ 4.5+ 0.25 32 45 15 16 48 71 11.4 14.7 9.0 13.4 15.7 23.1 13.1 U1 U2 U3 U4 U5 U6 U7 U8 U9 S10 Unit Dry Weight,pcfRemarks: Seepage observed @ 15' during drilling. Soil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft Date: 7/3/2019 FIGURE A2 Northing: 6981966.2 Easting: 2392192.8 Unc. CompressiveStrength, tsfSymbol / USCS% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRQDHand Penetrometer,tsfBORING LOG B-1 Location: See Plan of Borings Surface El.: 539.6 PenetrationBlows / Foot5 10 15 20 25Depth, feetSheet 1 of 1 Recovery %MoistureContent, %Liquid LimitProject: Project Number: Trinity Project - 11432 Pipeline Road Euless, Texas 2797 Plastic LimitBORING LOG W/FIGURE (ELEVATIONS & DEPTH) 2797 11432 PIPELINE ROAD.GPJ LANDTEC.GDT 8/20/19 3.0 18, 50/ 2.0" 20 50/ 2.0" 17 SANDY LEAN CLAY, grayish brown w/brown sand & crushed stone, very stiff, dry (FILL) SANDY LEAN CLAY & CLAYEY SAND (SC-CL), brown & grayish brown, very stiff, dry (FILL) FILL consisting of gray & black SAND & CLAYEY SAND, soft, wet w/wood & plastic CLAY, grayish brown, stiff to very stiff, moist w/lignite particles CLAYEY SAND, tan & gray, very dense, moist 117.9 534.3 533.3 521.8 517.3 516.3 2.0 3.0 14.5 19.0 20.0 4.5+ 4.5+ 4.5+ 0.5 0.25 0.0 1.0 28 11 46 9.0 9.6 15.8 25.9 U1 U2 U3 U4 U5 U6 U7 S8 S9 S10 Unit Dry Weight,pcfRemarks: Seepage observed @ 12' during drilling. Soil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft Date: 7/3/2019 FIGURE A3 Northing: 6981616.9 Easting: 2392300.8 Unc. CompressiveStrength, tsfSymbol / USCS% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRQDHand Penetrometer,tsfBORING LOG B-2 Location: See Plan of Borings Surface El.: 536.3 PenetrationBlows / Foot5 10 15 20 25Depth, feetSheet 1 of 1 Recovery %MoistureContent, %Liquid LimitProject: Project Number: Trinity Project - 11432 Pipeline Road Euless, Texas 2797 Plastic LimitBORING LOG W/FIGURE (ELEVATIONS & DEPTH) 2797 11432 PIPELINE ROAD.GPJ LANDTEC.GDT 8/20/19 0.6 25 CLAY, brown, very stiff, dry w/crushed stone (FILL) SANDY LEAN CLAY, gray, brown & tan, stiff, dry w/tan sand & crushed rock fragments (FILL) SANDY LEAN CLAY, grayish brown, stiff (POSSIBLE FILL) CLAYEY SAND, tan w/gray, very stiff, very stiff, dry to moist w/some gravel CLAYEY SAND, reddish tan, firm, moist to wet w/gravel 107.3 537.9 532.9 530.9 525.9 519.9 2.0 7.0 9.0 14.0 20.0 4.5+ 2.0 2.0 3.0 2.0 2.0 3.0 0.5 0.5 41 16 60 11.1 16.3 14.0 15.5 U1 U2 U3 U4 U5 U6 U7 U8 U9 U10 Unit Dry Weight,pcfRemarks: Seepage observed @ 15' during drilling. Soil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft Date: 7/3/2019 FIGURE A4 Northing: 6981351.8 Easting: 2392327.1 Unc. CompressiveStrength, tsfSymbol / USCS% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRQDHand Penetrometer,tsfBORING LOG B-3 Location: See Plan of Borings Surface El.: 539.9 PenetrationBlows / Foot5 10 15 20 25Depth, feetSheet 1 of 1 Recovery %MoistureContent, %Liquid LimitProject: Project Number: Trinity Project - 11432 Pipeline Road Euless, Texas 2797 Plastic LimitBORING LOG W/FIGURE (ELEVATIONS & DEPTH) 2797 11432 PIPELINE ROAD.GPJ LANDTEC.GDT 8/20/19 3.2 0.5 33, 50/ 5.5" 50/ 2.0" 20 SANDY LEAN CLAY, tan & gray, stiff to very stiff, dry to moist w/tan sand & w/crushed stone fragments & iron ore particles (PROBABLE FILL) CLAYEY SAND, reddish tan, firm to stiff, moist w/iron ore particles CLAYEY SAND, reddish tan, firm to stiff w/gravel, wet CLAY, shaly, gray, very stiff, dry w/gray sand seams, hard 112.0 108.3 526.1 523.1 518.1 512.1 6.0 9.0 14.0 20.0 4.5+ 4.5+ 2.0 2.0 2.5 1.0 2.0 2.5 31 11 59 29 10.7 15.8 16.7 14.0 17.0 15.0 U1 U2 U3 U4 U5 U6 U7 U8 S9 S10 Unit Dry Weight,pcfRemarks: Seepage observed @ 10' during drilling. Soil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft Date: 7/3/2019 FIGURE A5 Northing: 6981405.5 Easting: 2392508.5 Unc. CompressiveStrength, tsfSymbol / USCS% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRQDHand Penetrometer,tsfBORING LOG B-4 Location: See Plan of Borings Surface El.: 532.1 PenetrationBlows / Foot5 10 15 20 25Depth, feetSheet 1 of 1 Recovery %MoistureContent, %Liquid LimitProject: Project Number: Trinity Project - 11432 Pipeline Road Euless, Texas 2797 Plastic LimitBORING LOG W/FIGURE (ELEVATIONS & DEPTH) 2797 11432 PIPELINE ROAD.GPJ LANDTEC.GDT 8/20/19 6.7 1.7 1.6 50/ 3.0" 8 49 CLAYEY SAND, reddish tan, very stiff, dry w/iron ore particles (FILL) SANDY LEAN CLAY, reddish tan & tan, stiff to very stiff, dry w/iron ore fragments (FILL) CLAYEY SAND, reddish tan, firm, dry (POSSIBLE FILL) SANDY LEAN CLAY, reddish tan, firm, moist to wet w/sand seams CLAY, gray w/reddish tan, very stiff, dry w/lignite particles SAND, tan & gray, dense, wet 116.2 109.5 93.1 532.0 530.0 525.0 522.0 516.0 514.0 2.0 4.0 9.0 12.0 18.0 20.0 4.5+ 4.5+ 2.5 3.0 1.0 0.5 0.5 0.5 4.5+ 21 78 13 29 38 24 91 6.4 18.2 14.0 8.2 27.6 21.8 U1 U2 U3 U4 U5 U6 U7 U8 U9 S10 Unit Dry Weight,pcfRemarks: Seepage observed @ 10' during drilling. Soil and rock descriptions on this boring log are a compliation of data collected in both the field and the laboratory. The stratification lines represent the approximate boundary between soil types and the transition can be gradual.SamplesCompletion Depth: 20 ft Date: 7/3/2019 FIGURE A6 Northing: 6981216.4 Easting: 2392451.2 Unc. CompressiveStrength, tsfSymbol / USCS% PassingNo. 200 SieveMATERIAL DESCRIPTION Plasticity IndexRQDHand Penetrometer,tsfBORING LOG B-5 Location: See Plan of Borings Surface El.: 534.0 PenetrationBlows / Foot5 10 15 20 25Depth, feetSheet 1 of 1 Recovery %MoistureContent, %Liquid LimitProject: Project Number: Trinity Project - 11432 Pipeline Road Euless, Texas 2797 Plastic LimitBORING LOG W/FIGURE (ELEVATIONS & DEPTH) 2797 11432 PIPELINE ROAD.GPJ LANDTEC.GDT 8/20/19 Figure A7 GENERAL NOTES DRILLING AND SAMPLING SYMBOLS: U : Thin-Walled Tube - 3” O.D., Unless otherwise noted A : Auger Sample S : Split Spoon - 2” O.D., Unless otherwise noted W : Wash Sample C : Core Barrel T : TxDOT Cone Penetrometer (TCP) RELATIVE DENSITY OF COARSE-GRAINED SOILS: CONSISTENCY OF FINE-GRAINED SOILS: Penetration Resistance Blows/foot Relative Density Unconfined Compressive Strength, Qu, tsf Consistency 0-4 Very Loose Less than 0.25 Very Soft 4-10 Loose 0.25 to 0.50 Soft 10-30 Medium Dense 0.50 to 1.00 Firm 30-50 Dense 1.00 to 2.00 Stiff over 50 Very Dense 2.00 to 4.00 Very Stiff 4.00 and higher Hard TERMS CHARACTERIZING SOIL STRUCTURE: Slickensided : Having inclined planes of weakness that are slick and glossy in appearance. Fissured : Containing shrinkage cracks, frequently filled with fine sand or silt; usually more or less vertical. Laminated : Composed of thin layers of varying color and texture. Interbedded : Composed of alternate layers of different soil types. Calcareous : Containing appreciable quantities of calcium carbonate. Well graded : Having wide range in grain sizes and substantial amounts of all intermediate particle sizes. Poorly graded : Predominantly of one grain size, or having a range of sizes with some intermediate size missing. NOTE: Slickensided and fissured clays may have lower unconfined compressive strengths because of planes of weakness or cracks in the soil. The consistency rating of such soils is based on penetrometer readings. DEGREE OF WEATHERING: Unweathered : Rock in its natural state before being exposed to atmospheric agents. Slightly Weathered : Noted predominantly by color change with no disintegrated zones. Weathered/Severely Weathered: Complete color change with consistency, texture, and general appearance approaching soil. SUBSURFACE CONDITIONS: Soil and rock descriptions on the boring logs are a compilation of field data as well as from laboratory testing of samples. The stratification lines represent the approximate boundary between materials and the transition can be gradual. Water level observations have been made in the borings at the times indicated. It must be noted that fluctuations in the groundwater level may occur due to variations in rainfall, hydraulic conductivity of soil strata, construction activity, and other factors. Hardness terms for soil and rock are for relative comparison of the various samples, and are not intended to be used as an indication of the ease or difficulty of excavation or of excavation stability. Hardness terms on the logs may be based upon a combination of the test and observation methods listed above, and upon field observations. Water Level (Level where first observed) Water Level (Level after exploration completed) Figure A8 CLASSIFICATION OF SOILS Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests Soil Classification Group Symbol Group Name GRAVELS More than 50% of coarse fraction retained on No. 4 sieve CLEAN GRAVELS Less than 5% fines CU ≥ 4 and 1 ≤ Cc ≤ 3 GW Well-graded Gravel CU ≤ 4 and 1 ≥ Cc ≥ 3 GP Poorly-graded Gravel GRAVELS WITH FINES More than 12% of fines Fines classify as ML or MH GM Silty Gravel Fines classify as CL or CH GC Clayey Gravel SANDS 50% or more of coarse fraction retained on No. 4 sieve CLEAN SANDS Less than 5% fines CU ≥ 6 and 1 ≤ Cc ≤ 3 SW Well-graded Sand CU ≤ 6 and 1 ≥ Cc ≥ 3 SP Poorly-graded Sand SANDS WITH FINES More than 12% fines Fines classify as ML or MH SM Silty Sand Fines classify as CL or CH SC Clayey Sand SILTS AND CLAYS Liquid limit less than 50% Inorganic PI ˃ 7 and plots on or above “A” line CL Lean Clay PI ˂ 4 and plots below “A” line ML Silt Organic Liquid limit – ovendried Liquid limit – not dried ˂ 0.75 OL Organic Clay Organic Silt SILTS AND CLAYS Liquid limit more than 50% Inorganic PI plots on or above “A” line CH Fat Clay PI plots below “A” line MH Elastic Silt Organic Liquid limit – ovendried Liquid limit – not dried ˂ 0.75 OH Organic Silt Organic Silt Highly fibrous organic soils Primary organic matter, dark in color, and organic odor Pt Peat LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc A9 Description of Field Exploration Soil descriptions on the boring logs are a compilation of field log data as well as from laboratory testing of samples. The stratification lines represent the approximate boundary between soil types and the transition can be gradual. The boring logs presented in this report represent the engineer’s interpretation of the field logs, visual observation of the samples as well as results of laboratory tests. Relatively undisturbed samples of cohesive soils encountered in the borings were obtained with a Shelby tube sampler. Depths at which these samples were taken, designated "U," are indicated in the "Sample" column of the boring log. Estimates of the consistency of the cohesive soil samples were obtained in the field using a hand penetrometer. The result of a hand penetrometer reading is recorded at a corresponding depth in the "Penetrometer, TSF" column of the boring log. When the capacity of the hand penetrometer is exceeded, the value of 4.5+ is recorded. Samples were also taken by driving a standard ASTM 2-in. OD split-spoon sampler (ASTM D 1586) a distance of 18 in. into the soil with a 140-lb hammer falling freely a distance of 30 inches. Where resistance was high, the number of inches of penetration for 50 blows of the hammer was recorded. Depths at which the split-spoon samples were taken in these borings are designated "S" in the "Penetration Resistance" column of the boring logs. The number of blows required to drive the sampler the final 12 in. of penetration or the inches of penetration for 50 blows is recorded at a corresponding depth in the "Blows Per Ft" column of the boring logs. Representative portions of each split-spoon sample were selected and sealed in plastic bags to prevent loss of moisture. Short term observations were made in the borings to observe for shallow subsurface seepage. Water level observations made during drilling refer only to those observed at the times and places indicated, and can vary with time, geologic condition, construction activity, rainfall and other factors. Elevations and coordinates provided on our boring logs are based on the Trimble Network System for NAD 83, North Central Texas Zone 4202 using Trimble R8 GPS equipment. Elevations may or may not tie into the site specific elevations or bench marks used by the civil engineer, city or surveyor. If site bench mark information is used by the civil engineer or surveyor, please forward to us so we can compare our survey elevations. APPENDIX B Laboratory Testing B-1 0.5 11.4 B-1 2.5 14.7 B-1 3.5 32 15 17 48 9.0 118.3 9.1 B-1 5.5 13.4 B-1 9.5 45 16 29 71 15.7 111.4 3.8 B-1 14.5 23.1 B-1 19.5 13.1 B-2 1.5 9.0 B-2 2.5 28 11 17 46 9.6 117.9 3.0 B-2 14.5 15.8 B-2 19.5 25.9 B-3 0.5 11.1 B-3 2.5 41 16 25 60 16.3 B-3 4.5 14.0 107.3 0.6 B-3 14.5 15.5 B-4 1.5 31 11 20 59 10.7 112.0 3.2 B-4 3.5 15.8 B-4 5.5 16.7 B-4 7.5 14.0 108.3 0.5 B-4 9.5 29 17.0 B-4 14.5 15.0 B-5 1.5 21 13 8 38 6.4 116.2 6.7 B-5 2.5 18.2 B-5 3.5 14.0 109.5 1.7 B-5 5.5 24 8.2 B-5 14.5 78 29 49 91 27.6 93.1 1.6 B-5 19.5 21.8 %<#200 Sieve Water Content (%) Dry Density (pcf) Unconfined Compressive Strength tsf Summary of Laboratory Results Sheet 1 of 1 Borehole Depth Liquid Limit Plastic Limit Plasticity Index Trinity Project - 11432 Pipeline Road Euless, Texas 2797 Project: Number: Date:7/3/2019US_LAB_SUMMARY_LANDTEC 2797 11432 PIPELINE ROAD.GPJ LANDTEC.GDT 8/20/19 LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc B2 SUMMARY OF RESULTS SWELL TESTS Trinity Project – 11432 Pipeline Road Euless, Texas Project No. 0619-2797 August 2019 Boring No. Sample Depth, Ft. Unit dry Weight, pcf Initial Moisture Content, % Final Moisture Content, % Applied Surcharge Pressure, psf Vertical Swell, % B-1 3-4 109.8 10.5 16.3 400 -0.2 B-2 2-3 118.0 12.2 14.7 250 0.1 B-3 4-5 110.0 15.2 17.3 500 -0.2 B-4 1-2 113.1 12.0 17.5 150 1.6 B-5 1-2 113.8 8.4 16.8 150 1.5 LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc B3 Description of Laboratory Testing Representative samples of the soils were tested in our geotechnical soils laboratory. Liquid limit and plastic limit tests (Atterberg limits) and percent passing No. 200 sieve were performed on soil samples from the borings in order to classify them according to the Unified Soil Classification (USC) System. Strength properties of the soil were evaluated by performing unconfined compression tests. The results of these tests are reported as Qu values (in tons per square foot). Moisture content and density determinations were also made on samples to determine the in situ conditions. Selected samples of soils were subjected to swell tests. The results are reported as the percent swell, with initial and final moisture content, and, overburden pressure. The overburden pressure (or confinement) simulates the pressure experienced by the soil sample for a specific depth under in-situ conditions. APPENDIX C Drainage Illustrations LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc C1 LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc C2 Ideal drainage condition between houses. Poor drainage between houses and blocked by fence & AC Unit. APPENDIX D Site Photos LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc D1 Concrete Rubble North of Boring B-2 Concrete Rubble North of Boring B-3 LANDTEC ENGINEERS 2797 Trinity Project-Pipeline Rd-Final Geot-Aug2019.doc D2 Concrete Rubble North of Boring B-5 APPENDIX E GBA Statement Geotechnical-Engineering Report Important Information about This Subsurface problems are a principal cause of construction delays, cost overruns, claims, and disputes. While you cannot eliminate all such risks, you can manage them. The following information is provided to help. The Geoprofessional Business Association (GBA) has prepared this advisory to help you – assumedly a client representative – interpret and apply this geotechnical-engineering report as effectively as possible. In that way, clients can benefit from a lowered exposure to the subsurface problems that, for decades, have been a principal cause of construction delays, cost overruns, claims, and disputes. If you have questions or want more information about any of the issues discussed below, contact your GBA-member geotechnical engineer. Active involvement in the Geoprofessional Business Association exposes geotechnical engineers to a wide array of risk-confrontation techniques that can be of genuine benefit for everyone involved with a construction project. Geotechnical-Engineering Services Are Performed for Specific Purposes, Persons, and Projects Geotechnical engineers structure their services to meet the specific needs of their clients. A geotechnical-engineering study conducted for a given civil engineer will not likely meet the needs of a civil- works constructor or even a different civil engineer. Because each geotechnical-engineering study is unique, each geotechnical- engineering report is unique, prepared solely for the client. Those who rely on a geotechnical-engineering report prepared for a different client can be seriously misled. No one except authorized client representatives should rely on this geotechnical-engineering report without first conferring with the geotechnical engineer who prepared it. And no one – not even you – should apply this report for any purpose or project except the one originally contemplated. Read this Report in Full Costly problems have occurred because those relying on a geotechnical- engineering report did not read it in its entirety. Do not rely on an executive summary. Do not read selected elements only. Read this report in full. You Need to Inform Your Geotechnical Engineer about Change Your geotechnical engineer considered unique, project-specific factors when designing the study behind this report and developing the confirmation-dependent recommendations the report conveys. A few typical factors include: • the client’s goals, objectives, budget, schedule, and risk-management preferences; • the general nature of the structure involved, its size, configuration, and performance criteria; • the structure’s location and orientation on the site; and • other planned or existing site improvements, such as retaining walls, access roads, parking lots, and underground utilities. Typical changes that could erode the reliability of this report include those that affect: • the site’s size or shape; • the function of the proposed structure, as when it’s changed from a parking garage to an office building, or from a light-industrial plant to a refrigerated warehouse; • the elevation, configuration, location, orientation, or weight of the proposed structure; • the composition of the design team; or • project ownership. As a general rule, always inform your geotechnical engineer of project changes – even minor ones – and request an assessment of their impact. The geotechnical engineer who prepared this report cannot accept responsibility or liability for problems that arise because the geotechnical engineer was not informed about developments the engineer otherwise would have considered. This Report May Not Be Reliable Do not rely on this report if your geotechnical engineer prepared it: • for a different client; • for a different project; • for a different site (that may or may not include all or a portion of the original site); or • before important events occurred at the site or adjacent to it; e.g., man-made events like construction or environmental remediation, or natural events like floods, droughts, earthquakes, or groundwater fluctuations. Note, too, that it could be unwise to rely on a geotechnical-engineering report whose reliability may have been affected by the passage of time, because of factors like changed subsurface conditions; new or modified codes, standards, or regulations; or new techniques or tools. If your geotechnical engineer has not indicated an “apply-by” date on the report, ask what it should be, and, in general, if you are the least bit uncertain about the continued reliability of this report, contact your geotechnical engineer before applying it. A minor amount of additional testing or analysis – if any is required at all – could prevent major problems. Most of the “Findings” Related in This Report Are Professional Opinions Before construction begins, geotechnical engineers explore a site’s subsurface through various sampling and testing procedures. Geotechnical engineers can observe actual subsurface conditions only at those specific locations where sampling and testing were performed. The data derived from that sampling and testing were reviewed by your geotechnical engineer, who then applied professional judgment to form opinions about subsurface conditions throughout the site. Actual sitewide-subsurface conditions may differ – maybe significantly – from those indicated in this report. Confront that risk by retaining your geotechnical engineer to serve on the design team from project start to project finish, so the individual can provide informed guidance quickly, whenever needed. This Report’s Recommendations Are Confirmation-Dependent The recommendations included in this report – including any options or alternatives – are confirmation-dependent. In other words, they are not final, because the geotechnical engineer who developed them relied heavily on judgment and opinion to do so. Your geotechnical engineer can finalize the recommendations only after observing actual subsurface conditions revealed during construction. If through observation your geotechnical engineer confirms that the conditions assumed to exist actually do exist, the recommendations can be relied upon, assuming no other changes have occurred. The geotechnical engineer who prepared this report cannot assume responsibility or liability for confirmation- dependent recommendations if you fail to retain that engineer to perform construction observation. This Report Could Be Misinterpreted Other design professionals’ misinterpretation of geotechnical- engineering reports has resulted in costly problems. Confront that risk by having your geotechnical engineer serve as a full-time member of the design team, to: • confer with other design-team members, • help develop specifications, • review pertinent elements of other design professionals’ plans and specifications, and • be on hand quickly whenever geotechnical-engineering guidance is needed. You should also confront the risk of constructors misinterpreting this report. Do so by retaining your geotechnical engineer to participate in prebid and preconstruction conferences and to perform construction observation. Give Constructors a Complete Report and Guidance Some owners and design professionals mistakenly believe they can shift unanticipated-subsurface-conditions liability to constructors by limiting the information they provide for bid preparation. To help prevent the costly, contentious problems this practice has caused, include the complete geotechnical-engineering report, along with any attachments or appendices, with your contract documents, but be certain to note conspicuously that you’ve included the material for informational purposes only. To avoid misunderstanding, you may also want to note that “informational purposes” means constructors have no right to rely on the interpretations, opinions, conclusions, or recommendations in the report, but they may rely on the factual data relative to the specific times, locations, and depths/elevations referenced. Be certain that constructors know they may learn about specific project requirements, including options selected from the report, only from the design drawings and specifications. Remind constructors that they may perform their own studies if they want to, and be sure to allow enough time to permit them to do so. Only then might you be in a position to give constructors the information available to you, while requiring them to at least share some of the financial responsibilities stemming from unanticipated conditions. Conducting prebid and preconstruction conferences can also be valuable in this respect. Read Responsibility Provisions Closely Some client representatives, design professionals, and constructors do not realize that geotechnical engineering is far less exact than other engineering disciplines. That lack of understanding has nurtured unrealistic expectations that have resulted in disappointments, delays, cost overruns, claims, and disputes. To confront that risk, geotechnical engineers commonly include explanatory provisions in their reports. Sometimes labeled “limitations,” many of these provisions indicate where geotechnical engineers’ responsibilities begin and end, to help others recognize their own responsibilities and risks. Read these provisions closely. Ask questions. Your geotechnical engineer should respond fully and frankly. Geoenvironmental Concerns Are Not Covered The personnel, equipment, and techniques used to perform an environmental study – e.g., a “phase-one” or “phase-two” environmental site assessment – differ significantly from those used to perform a geotechnical-engineering study. For that reason, a geotechnical- engineering report does not usually relate any environmental findings, conclusions, or recommendations; e.g., about the likelihood of encountering underground storage tanks or regulated contaminants. Unanticipated subsurface environmental problems have led to project failures. If you have not yet obtained your own environmental information, ask your geotechnical consultant for risk-management guidance. As a general rule, do not rely on an environmental report prepared for a different client, site, or project, or that is more than six months old. Obtain Professional Assistance to Deal with Moisture Infiltration and Mold While your geotechnical engineer may have addressed groundwater, water infiltration, or similar issues in this report, none of the engineer’s services were designed, conducted, or intended to prevent uncontrolled migration of moisture – including water vapor – from the soil through building slabs and walls and into the building interior, where it can cause mold growth and material-performance deficiencies. Accordingly, proper implementation of the geotechnical engineer’s recommendations will not of itself be sufficient to prevent moisture infiltration. Confront the risk of moisture infiltration by including building-envelope or mold specialists on the design team. Geotechnical engineers are not building- envelope or mold specialists. Copyright 2016 by Geoprofessional Business Association (GBA). Duplication, reproduction, or copying of this document, in whole or in part, by any means whatsoever, is strictly prohibited, except with GBA’s specific written permission. Excerpting, quoting, or otherwise extracting wording from this document is permitted only with the express written permission of GBA, and only for purposes of scholarly research or book review. Only members of GBA may use this document or its wording as a complement to or as an element of a report of any kind. Any other firm, individual, or other entity that so uses this document without being a GBA member could be committing negligent Telephone: 301/565-2733 e-mail: info@geoprofessional.org www.geoprofessional.org LANDTEC ENGINEERS, LLC ARLINGTON | FORT WORTH | MANSFIELD | THE COLONY 1700 Robert Road, Suite 101 | Mansfi eld, Texas 76063 (w) 817-572-2818 | www.landteceng.com geotechnical engineering environmental engineering construction materials testing laboratory testing SERVICES Geotechnical & Environmental Engineering Construction Materials Testing Laboratory Testing LANDTEC ENGINEERS, LLC 1700 Robert Road Suite 101 Mansfield, Texas 76063 / 817.572.2818 Arlington I Fort Worth I Mansfield I The Colony April 8, 2020 Project No.: 2797 Addendum No. 2 Logan Hostin Development Manager ECM Development, LLC 4010-7 North Collins Street Arlington, Texas 76005 lhostin@ecmdev.com 817-266-5192 RE: Trinity Parks - Single Family Subdivision Fort Worth, Tarrant County, Texas Addendum No. 2 Dear Logan: Based on information provided by the City of Fort Worth in a February 24, 2020 email to Javier Jaramillo, P.E. at Pacheco Koch, the following recommendations for street paving are provided. We understand the subdivision streets are classified by the City of Fort Worth as “residential collector”. Residential Collector Street: The City of Fort Worth Paving Manual dated December 14, 2015, Table 3.3 indicates the minimum pavement section for a residential collector street. Minimum of seven (7) inches of concrete pavement placed on a minimum of six (6) inches of stabilized subgrade. The use of lime or cement for stabilization of the pavement subgrade can be determined when the final subgrade elevation is achieved. The City of Fort Worth requires sampling of the subgrade soils once the utilities are installed and final street grade is achieved, to perform soil classification tests and soil-pH-lime series tests on representative subgrade soils. LANDTEC ENGINEERS 2797 Trinity Park-Addendum 2-Pvmt-Geot-April2020.docx 2 Reinforcing steel for the 7-inch concrete pavement section includes #3 rebar @ 18 inches on center each way. See Table 4.1, page 12 of the Manual. Expansion joint dowel bar size includes the #7 bar for 7-inch pavement. See Table 4.3, Page 14 of the Manual. Asphalt Pavement for Tie In: If full depth asphalt pavement is used for the entry off Trinity Blvd. or Pipeline Road, we recommend a minimum of eight (8) inches of HMAC placed on a minimum of six (6) inches of stabilized subgrade. The asphalt section (from top down) should consist of 2 inches of Type D and 6 inches of Type B. The Type B mix should be placed in two lifts of 3 inches each If you have any questions regarding this Addendum No. 2, please let us know. Sincerely, April 8, 2020 Thomas D. Baker, P.E., RPLS I LandTec Engineers, LLC Texas Board of Professional Engineers Firm Registration No. F-000329 Texas Board of Professional Land Surveyors Firm Registration No. 100956-00 Distribution by PDF: Logan Hostin – ECM Development Javier Jaramillo, P.E. – Pacheco Koch (jjaramillo@pkce.com) CITY OF FORT WORTH TRINITY PARKS STANDARD CONSTRUCTION SPECIFICATION DOCUMENTS – DEVELOPER AWARDED PROJECTS CPN 102606 GR-01 60 00 Product Requirements THIS PAGE LEFT INTENTIONALLY BLANK CITY OF FORT WORTH WATER DEPARTMENT STANDARD PRODUCT LIST Updated: September 06, 2019 The Fort Worth Water Department’s Standard Products List has been developed to minimize the submittal review of products which meet the Fort Worth Water Department’s Standard Specifications during utility construction projects. When Technical Specifications for specific products, are included as part of the Construction Contract Documents, the requirements of the Technical Specification will override the Fort Worth Water Department’s Standard Specifications and the Fort Worth Water Department’s Standard Products List and approval of the specific products will be based on the requirements of the Technical Specification whether or not the specific product meets the Fort Worth Water Department’s Standard Specifications or is on the Fort Worth Water Department’s Standard Products List. Table of Content (Click on items to go directly to the page) Items Page A.Water & Sewer 1. Manholes & Bases/Components ........................................................... 1 2.Manholes & Bases/Fiberglass ............................................................... 2 3.Manholes & Bases/Frames & Covers/Rectangular ............................... 3 4.Manholes & Bases/Frames & Covers/Round ....................................... 4 5.Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight .. 5 6.Manholes & Bases/Precast Concrete .................................................... 6 7.Manholes & Bases/Rehab Systems/Cementitious ................................ 7 8.Manholes & Bases/Rehab Systems/NonCementitious ......................... 8 9.Manhole Insert (Field Operations Use Only) ........................................ 9 10. Pipe Casing Spacer ............................................................................... 10 11. Pipes/Ductile Iron ................................................................................. 11 12. Utility Line Marker ............................................................................... 12 B.Sewer 13. Coatings/Epoxy ..................................................................................... 13 14. Coatings/Polyurethane .......................................................................... 14 15. Combination Air Valves ....................................................................... 15 16. Pipes/Concrete ...................................................................................... 16 17. Pipe Enlargement System (Method) ..................................................... 17 18. Pipes/Fiberglass Reinforced Pipe ......................................................... 18 19. Pipes/HDPE .......................................................................................... 19 20. Pipes/PVC (Pressure Sewer) ................................................................. 20 21. Pipes/PVC* ........................................................................................... 21 22. Pipes/Rehab/CIPP ................................................................................. 22 23. Pipes/Rehab/Fold & Form .................................................................... 23 24. Pipes/Open Profile Large Diameter ...................................................... 24 C.Water 25. Appurtenances ....................................................................................... 25 26. Bolts, Nuts, and Gaskets ....................................................................... 26 27. Combination Air Release Valve ........................................................... 27 28. Dry Barrel Fire Hydrants ...................................................................... 28 29. Meters ................................................................................................... 29 30. Pipes/PVC (Pressure Water) ................................................................. 30 31. Pipes/Valves & Fittings/Ductile Iron Fittings ....................................... 31 32. Pipes/Valves & Fittings/Resilient Seated Gate Valve .......................... 32 33. Pipes/Valves & Fittings/Rubber Seated Butterfly Valve ...................... 33 34. Polyethylene Encasement ..................................................................... 34 35. Sampling Stations ................................................................................. 35 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeWater & Sewer - Manholes & Bases/Components 33-39-10 (Rev 2/3/16)07/23/97 33 05 13 Urethane Hydrophilic Waterstop Asahi Kogyo K.K. Adeka Ultra-Seal P-201 ASTM D2240/D412/D79204/26/00 33 05 13 Offset Joint for 4' Diam. MH Hanson Concrete Products Drawing No. 35-0048-00104/26/00 33 05 13 Profile Gasket for 4' Diam. MH. Press-Seal Gasket Corp. 250-4G Gasket ASTM C-443/C-361 SS MH1/26/99 33 05 13 HDPE Manhole Adjustment Rings Ladtech, Inc HDPE Adjustment Ring Non-traffic area5/13/05 33 05 13 Manhole External Wrap Canusa - CPS WrapidSeal Manhole Encapsulation SystemCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019* From Original Standard Products ListClick to Return to the Table of Content1 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Fiberglass 33-39-13 (1/8/13)1/26/99 33 39 13 Fiberglass Manhole Fluid Containment, Inc. Flowtite ASTM 3753 Non-traffic area08/30/06 33 39 13 Fiberglass Manhole L.F. ManufacturingNon-traffic area* From Original Standard Products ListClick to Return to the Table of Content2 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Frames & Covers/Rectangular 33-05-13 (Rev 2/3/16)* 33 05 13 Manhole Frames and Covers Western Iron Works, Bass & Hays Foundry 1001 24"x40" WD* From Original Standard Products ListClick to Return to the Table of Content3 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Frames & Covers/Standard (Round) 33-05-13 (Rev 2/3/16)*33 05 13 Manhole Frames and CoversWestern Iron Works, Bass & Hays Foundry3002424" Dia.*33 05 13 Manhole Frames and CoversMcKinley Iron Works Inc.A 24 AM24" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1272ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR- 165-LM (Hinged)ASTM A48 & AASHTO M30624" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryNF 1274ASTM A48 & AASHTO M30630" Dia.08/24/18 33 05 13 Manhole Frames and CoversNeenah FoundryR-1743-LM (Hinged)ASTM A48 & AASHTO M30630" dia.33 05 13 Manhole Frames and CoversSigma CorporationMH-144N33 05 13 Manhole Frames and CoversSigma CorporationMH-143N33 05 13 Manhole Frames and CoversPont-A-MoussonGTS-STD24" dia.33 05 13 Manhole Frames and CoversNeenah Casting24" dia.10/31/06 33 05 13 Manhole Frames and Covers (Hinged)PowersealHinged Ductile Iron Manhole ASTM A53624" Dia.7/25/03 33 05 13 Manhole Frames and CoversSaint-Gobain Pipelines (Pamrex/rexus)RE32-R8FS30" Dia.01/31/06 33 05 1330" Dia. MH Ring and CoverEast Jordan Iron WorksV1432-2 and V1483 DesignsAASHTO M306-0430" Dia.11/02/10 33 05 1330" Dia. MH Ring and CoverSigma CorporationMH1651FWN & MH1650230" Dia07/19/11 33 05 1330" Dia. MH Ring and CoverStar Pipe ProductsMH32FTWSS-DC 30" Dia08/10/11 33 05 1330" Dia. MH Ring and CoverAccucast220700 Heavy Duty with Gasket Ring30" Dia10/14/13 33 05 1330" Dia. MH Ring and Cover (Hinged & Lockable)East Jordan Iron Works 30" ERGO XL Assembly with Cam Lock/MPIC/T-Gasket ASSHTO M105 & ASTM A53630" Dia06/01/17 34 05 1330" Dia. MH Ring and Cover (Hinged & Lockable) CISIP Industries2280 (32")ASTM A 4830" Dia.09/16/19 33 05 13.1030" Dia. MH Ring and Cover Composite Access Products, L.P.CAP-ONE-30-FTW, Composite, w/ Lock w/o Hing30" Dia.* From Original Standard Products ListClick to Return to the Table of Content4 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Frames & Covers/Water Tight & Pressure Tight 33-05-13 (Rev 2/3/16)* 33 05 13 Manhole Frames and Covers Pont-A-Mousson Pamtight 24" Dia.* 33 05 13 Manhole Frames and Covers Neenah Casting24" Dia.* 33 05 13 Manhole Frames and Covers Western Iron Works,Bass & Hays Foundry 300-24P 24" Dia.* 33 05 13 Manhole Frames and Covers McKinley Iron Works Inc. WPA24AM 24" Dia.03/08/00 33 05 13 Manhole Frames and Covers Accucast RC-2100 ASTM A 48 24" Dia.04/20/01 33 05 13 Manhole Frames and Covers (SIP)Serampore Industries Private Ltd. 300-24-23.75 Ring and Cover ASTM A 48 24" Dia.* From Original Standard Products ListClick to Return to the Table of Content5 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Precast Concrete (Rev 1/8/13)* 33 39 10 Manhole, Precast Concrete Hydro Conduit Corp SPL Item #49 ASTM C 478 48"* 33 39 10 Manhole, Precast Concrete Wall Concrete Pipe Co. Inc. ASTM C-443 48"09/23/96 33 39 10 Manhole, Precast Concrete Concrete Product Inc. 48" I.D. Manhole w/ 32" Cone ASTM C 478 48" w/32" cone05/08/18 33 39 10 Manhole, Precast Concrete The Turner Company 48", 60" I.D. Manhole w/ 32" Cone ASTM C 478 48", 60"10/27/06 33 39 10 Manhole, Precast Concrete Oldcastle Precast Inc.48" I.D. Manhole w/ 24" Cone ASTM C 478 48" Diam w 24" Ring06/09/10 33 39 10 Manhole, Precast (Reinforce Polymer)Concrete US Composite Pipe Reinforced Polymer Concrete ASTM C-76 48" to 72"09/06/19 33 39 20 Manhole, Precast Concrete Forterra Pipe and Precast 60" & 72" I.D. Manhole w/32" Cone ASTM C-76 60" & 72"* From Original Standard Products ListClick to Return to the Table of Content6 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Rehab Systems/Cementitious* E1-14 Manhole Rehab Systems Quadex04/23/01 E1-14 Manhole Rehab Systems Standard Cement Materials, Inc. Reliner MSPE1-14 Manhole Rehab Systems AP/M Permaform4/20/01 E1-14 Manhole Rehab System Strong Company Strong Seal MS2A Rehab System5/12/03 E1-14 Manhole Rehab System (Liner) Poly-triplex Technologies MH repair product to stop infiltration ASTM D581308/30/06 General Concrete Repair FlexKrete Technologies Vinyl Polyester Repair Product Misc. Use* From Original Standard Products ListClick to Return to the Table of Content7 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manholes & Bases/Rehab Systems/NonCementitious05/20/96 E1-14 Manhole Rehab Systems Sprayroq, Spray Wall Polyurethane Coating ASTM D639/D790* E1-14 Manhole Rehab Systems Sun Coast12/14/01 Coating for Corrosion protection(Exterior) ERTECH Series 20230 and 2100 (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications08/30/06 Coatings for Corrosion Protection Citadel SLS-30 Solids Epoxy Sewer Applications03/19/1833 05 16, 33 39 10, 33 39 20 Coating for Corrosion protection(Exterior) Sherwin WilliamsRR&C Dampproofing Non-Fibered Spray Grade (Asphatic Emulsion)For Exterior Coating of Concrete Structures Only* From Original Standard Products ListClick to Return to the Table of Content8 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Manhole Inserts - Field Operations Use Only (Rev 2/3/16)* 33 05 13 Manhole Insert Knutson Enterprises Made to Order - Plastic ASTM D 1248 For 24" dia.* 33 05 13 Manhole Insert South Western Packaging Made to Order - Plastic ASTM D 1248 For 24" dia.* 33 05 13 Manhole Insert Noflow-Inflow Made to Order - Plastic ASTM D 1248 For 24" dia.09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. LifeSaver - Stainless Steel For 24" dia.09/23/96 33 05 13 Manhole Insert Southwestern Packing & Seals, Inc. TetherLok - Stainless Steel For 24" dia* From Original Standard Products ListClick to Return to the Table of Content9 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Pipe Casing Spacers 33-05-24 (07/01/13)11/04/02 Steel Band Casing Spacers Advanced Products and Systems, Inc. Carbon Steel Spacers, Model SI02/02/93 Stainless Steel Casing Spacer Advanced Products and Systems, Inc. Stainless Steel Spacer, Model SSI04/22/87 Casing Spacers Cascade Waterworks Manufacturing Casing Spacers09/14/10 Stainless Steel Casing Spacer Pipeline Seal and Insulator Stainless Steel Casing Spacer Up to 48"09/14/10 Coated Steel Casin Spacers Pipeline Seal and Insulator Coated Steel Casin Spacers Up to 48" 05/10/11 Stainless Steel Casing Spacer Powerseal 4810 Powerchock Up to 48"03/19/18 Casing Spacers BWM SS-12 Casing Spacer(Stainless Steel)03/19/18 Casing Spacers BWMFB-12 Casing Spacer (Coated Carbon Steel) for Non_pressure Pipe and Grouted Casing* From Original Standard Products ListClick to Return to the Table of Content10 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Pipes/Ductile Iron 33-11-10(1/8/13)* 33 11 10 Ductile Iron Pipe Griffin Pipe Products, Co. Super Bell-Tite Ductile Iron Pressure Pipe, AWWA C150, C1513" thru 24"08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co.American Fastite Pipe (Bell Spigot) AWWA C150, C151 4" thru 30"08/24/18 33 11 10 Ductile Iron Pipe American Ductile Iron Pipe Co.American Flex Ring (Restrained Joint) AWWA C150, C151 4" thru 30"* 33 11 10 Ductile Iron Pipe U.S. Pipe and Foundry Co. AWWA C150, C151* 33 11 10 Ductile Iron Pipe McWane Cast Iron Pipe Co. AWWA C150, C151* From Original Standard Products ListClick to Return to the Table of Content11 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water & Sewer - Utility Line Marker (08/24/2018)* From Original Standard Products ListClick to Return to the Table of Content12 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Coatings/Epoxy 33-39-60 (01/08/13)02/25/02 Epoxy Lining System Sauereisen, Inc SewerGard 210RS LA County #210-1.3312/14/01 Epoxy Lining System Ertech Technical Coatings Ertech 2030 and 2100 Series04/14/05 Interior Ductile Iron Pipe Coating Induron Protecto 401 ASTM B-117 Ductile Iron Pipe Only01/31/06 Coatings for Corrosion Protection Chesterton Arc 791, S1HB, S1, S2 Acid Resistance Test Sewer Applications8/28/2006 Coatings for Corrosion Protection Warren Environmental S-301 and M-301 Sewer Applications* From Original Standard Products ListClick to Return to the Table of Content13 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Coatings/Polyurethane* From Original Standard Products ListClick to Return to the Table of Content14 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Combination Air Valves 05/25/18 33-31-70 Air Release Valve A.R.I. USA, Inc. D025LTP02(Composite Body) 2"* From Original Standard Products ListClick to Return to the Table of Content15 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Concrete* E1-04 Conc. Pipe, Reinforced Wall Concrete Pipe Co. Inc. ASTM C 76* E1-04 Conc. Pipe, Reinforced Hydro Conduit Corporation Class III T&G, SPL Item #77 ASTM C 76* E1-04 Conc. Pipe, Reinforced Hanson Concrete Products SPL Item #95-Manhole, #98- PipeASTM C 76* E1-04 Conc. Pipe, Reinforced Concrete Pipe & Products Co. Inc. ASTM C 76* From Original Standard Products ListClick to Return to the Table of Content16 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipe Enlargment System (Method)33-31-23 (01/18/13)PIM System PIM Corporation Polyethylene PIM Corp., Piscata Way, N.J. Approved PreviouslyMcConnell Systems McLat Construction Polyethylene Houston, Texas Approved PreviouslyTRS Systems Trenchless Replacement System Polyethylene Calgary, Canada Approved Previously* From Original Standard Products ListClick to Return to the Table of Content17 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipe/Fiberglass Reinforced Pipe 33-31-13(1/8/13)7/21/97 33 31 13 Cent. Cast Fiberglass Hobas Pipe USA, Inc. Hobas Pipe (Non-Pressure) ASTM D3262/D375403/22/10 33 31 13 Fiberglass Pipe Ameron Bondstrand RPMP Pipe ASTM D3262/D375410/30/03 Glass-Fiber Reinforced Polymer Pipe Thompson Pipe Group Flowtite ASTM D3262/D37544/14/05 Polymer Modified Concrete Pipe Amitech USA Meyer Polycrete Pipe ASTM C33, A276, F477 8" to 102", Class V06/09/10 E1-9 Reinforced Polymer Concrete Pipe US Composite Pipe Reinforced Polymer Concrete Pipe ASTM C-76* From Original Standard Products ListClick to Return to the Table of Content18 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/HDPE 33-31-23(1/8/13)* High-density polyethylene pipe Phillips Driscopipe, Inc. Opticore Ductile Polyethylene Pipe ASTM D 1248 8"* High-density polyethylene pipe Plexco Inc. ASTM D 1248 8"* High-density polyethylene pipe Polly Pipe, Inc. ASTM D 1248 8"High-density polyethylene pipe CSR Hydro Conduit/Pipeline Systems McConnell Pipe Enlargement ASTM D 1248* From Original Standard Products ListClick to Return to the Table of Content19 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/PVC (Pressure Sewer) 33-11-12 (4/1/13)12/02/11 33-11-12 DR-14 PVC Pressure Pipe Pipelife Jetstream PVC Pressure Pipe AWWA C900 4" thru 12"10/22/14 33-11-12 DR-14 PVC Pressure Pipe Royal Building Products Royal Seal PVC Pressure Pipe AWWA C900 4" thru 12"* From Original Standard Products ListClick to Return to the Table of Content20 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/PVC* 33-31-20 (7/1/13)* 33-31-20 PVC Sewer Pipe Certain-Teed Products Corp ASTM D 3034 4" thru 15"* 33-31-20 PVC Sewer Pipe Napco Manufacturing CorpASTM D 3034, D 17844" & 8"* 33-31-20 PVC Sewer Pipe J-M Manufacturing Co., Inc. (JM Eagle) ASTM D 3034 4" - 15"12/23/97* 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation SDR-26 and SDR-35 ASTM F 789, ASTM D 30344" thru 15"* 33-31-20 PVC Sewer Pipe Lamson Vylon Pipe ASTM F 789 4" thru 15"33-31-20 PVC Sewer Pipe Royal Building Products Royal Seal Solid Wall Pipe SDR 26 & 35 ASTM 3034 4" thru 15"01/18/18 33-31-20 PVC Sewer Pipe Vinyltech PVC Pipe Gravity Sewer ASTM D3034 4" thru 15"11/11/98 33-31-20 PVC Sewer Pipe Diamond Plastics Corporation "S" Gravity Sewer Pipe ASTM F 679 18" to 27"* 33-31-20 PVC Sewer Pipe J-M Manufacturing Co, Inc. (JM Eagle) ASTM F 679 18" - 27"09/11/12 33-31-20 PVC Sewer Pipe Pipelife Jet Stream SDR-26 and SDr-35 ASTM F-679 18"05/06/0533-31-20PVC Solid Wall Pipe Diamond Plastics CorporationPS 46 ASTM F-679 18" to 48"04/27/0633-31-20PVC Sewer Fittings HarcoSDR-26 and SDR-35 Gasket Fittings ASTM D-3034, D-1784, etc 4" - 15"*33-31-20PVC Sewer Fittings Plastic Trends, In.cGasketed PVC Sewer Main Fittings ASTM D 303411/17/99E100-2Closed Profile PVC Pipe Diamond Plastics CorporationASTM 1803/F794 18" to 48"3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 35 ASTM F679 18"- 24"3/19/2018 33 31 20 PVC Sewer Pipe Pipelife Jet Stream SDR 26 ASTM D3034 4"- 15"3/29/2019 33 31 20Gasketed Fittings (PVC)GPK Products, Inc. SDR 26 ASTM D3034/F-679 4"- 15"9/6/2019 33 31 20 PVC Sewer Pipe NAPCO SDR 26, SDR 35 ASTM D3034 4" - 8"9/6/2019 33 31 20 PVC Sewer Pipe Sanderson Pipe Corp. SDR 26, SDR 35 ASTM D3034 8"* From Original Standard Products ListClick to Return to the Table of Content21 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Rehab/CIPP 33-31-12 (01/18/13)* Cured in Place Pipe Insituform Texark, Inc ASTM F 121605/03/99 Cured in Place Pipe National Envirotech Group National Liner, (SPL) Item #27 ASTM F-1216/D-581305/29/96 Cured in Place Pipe Reynolds Inc/Inliner Technolgy (Inliner USA) Inliner Technology ASTM F 1216* From Original Standard Products ListClick to Return to the Table of Content22 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Rehab/Fold & Form* Fold and Form Pipe Cullum Pipe Systems, Inc.11/03/98 Fold and Form Pipe Insituform Technologies, Inc. Insituform "NuPIpe" ASTM F-1504Fold and Form Pipe American Pipe & Plastics, Inc.Demo. Purpose Only12/04/00 Fold and Form Pipe Ultraliner Ultraliner PVC Alloy Pipeliner ASTM F-1504, 1871, 186706/09/03 Fold and Form Pipe Miller Pipeline Corp. EX Method ASTM F-1504, F-1947 Up to 18" diameter* From Original Standard Products ListClick to Return to the Table of Content23 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Sewer - Pipes/Open Profile Large Diameter09/26/91 E100-2 PVC Sewer Pipe, Ribbed Lamson Vylon Pipe Carlon Vylon H.C. Closed Profile Pipe, ASTM F 679 18" to 48"09/26/91 E100-2 PVC Sewer Pipe, Ribbed Extrusion Technologies, Inc. Ultra-Rib Open Profile Sewer Pipe ASTM F 679 18" to 48"E100-2 PVC Sewer Pipe, Ribbed Uponor ETI Company11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Double Wall Advanced Drainage Systems (ADS) SaniTite HP Double Wall (Corrugated)ASTM F 2736 24"-30"11/10/10 (E100-2) Polypropylene (PP) Sewer Pipe, Triple Wall Advanced Drainage Systems (ADS) SaniTite HP Triple Wall Pipe ASTM F 2764 30" to 60"05/16/11 Steel Reinforced Polyethylene Pipe ConTech Construction Products Durmaxx ASTM F 2562 24" to 72"* From Original Standard Products ListClick to Return to the Table of Content24 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Appurtenances 33-12-10 (07/01/13)01/18/18 33-12-10 Double Strap Saddle Romac 202NS Nylon Coated AWWA C800 1"-2" SVC, up to 24" Pipe08/28/02 Double Strap Saddle Smith Blair #317 Nylon Coated Double Strap Saddle07/23/12 33-12-10 Double Strap Service Saddle Mueller Company DR2S Double (SS) Strap DI Saddle AWWA C800 1"-2" SVC, up to 24" Pipe10/27/87 Curb Stops-Ball Meter Valves McDonald 6100M,6100MT & 610MT 3/4" and 1"10/27/87 Curb Stops-Ball Meter Valves McDonald 4603B, 4604B, 6100M, 6100TM and 6101M 1½" and 2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.FB600-7NL, FB1600-7-NL, FV23-777-W-NL, L22-77NL AWWA C800 2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.FB600-6-NL, FB1600-6-NL, FV23-666-W-NL, L22-66NL AWWA C800 1-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Ford Meter Box Co., Inc.FB600-4-NL, FB1600-4-NL, B11-444-WR-NL, B22444-WR-NL, L28-44NL AWWA C800 1"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.B-25000N, B-24277N-3, B-20200N-3, H-15000N, , H-1552N, H142276NAWWA C800, ANSF 61, ANSI/NSF 372 2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.B-25000N, B-20200N-3, B-24277N-3,H-15000N, H-14276N, H-15525NAWWA C800, ANSF 61, ANSI/NSF 372 1-1/2"5/25/2018 33-12-10 Curb Stops-Ball Meter Valves Mueller Co., Ltd.B-25000N, B-20200N-3,H-15000N, H-15530NAWWA C800, ANSF 61, ANSI/NSF 372 1"01/26/00 Coated Tapping Saddle with Double SS Straps JCM Industries, Inc. #406 Double Band SS Saddle 1"-2" Taps on up to 12" 0/5/21/12 33-12-25 Tapping Sleeve (Coated Steel) JCM Industries, Inc. 412 Tapping Sleeve ESS AWWA C-223 Up to 30" w/12" Out05/10/11 Tapping Sleeve (Stainless Steel) Powerseal 3490AS (Flange) & 3490MJ 4"-8" and 16"02/29/12 33-12-25 Tapping Sleeve (Coated Steel) Romac FTS 240 AWWA C-223 U p to 42" w/24" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST Stainless Steel AWWA C-223 Up to 24" w/12" Out02/29/12 33-12-25 Tapping Sleeve (Stainless Steel) Romac SST III Stainless Steel AWWA C-223 Up to 30" w/12" Out05/10/11 Joint Repair Clamp Powerseal 3232 Bell Joint Repair Clamp4" to 30"Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW37C-12-1EPAF FTWPlastic Meter Box w/Composite Lid DFW Plastics Inc. DFW39C-12-1EPAF FTW08/30/06 Plastic Meter Box w/Composite Lid DFW Plastics Inc. DFW65C-14-1EPAF FTW Class "A"Concrete Meter Box Bass & Hays CMB37-B12 1118 LID-9Concrete Meter Box Bass & Hays CMB-18-Dual 1416 LID-9Concrete Meter Box Bass & Hays CMB65-B65 1527 LID-9* From Original Standard Products ListClick to Return to the Table of Content25 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Bolts, Nuts, and Gaskets 33-11-05 (01/08/13)* From Original Standard Products ListClick to Return to the Table of Content26 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Combination Air Release 33-31-70 (01/08/13)* E1-11 Combination Air Release Valve GA Industries, Inc. Empire Air and Vacuum Valve, Model 935 ASTM A 126 Class B, ASTM A 240 - float, ASTM A 307 - Cover Bolts1" & 2"* E1-11 Combination Air Release Valve Multiplex Manufacturing Co.Crispin Air and Vacuum Valves, Model No. 1/2", 1" & 2"* E1-11 Combination Air Release Valve Valve and Primer Corp. APCO #143C, #145C and #147C 1", 2" & 3"* From Original Standard Products ListClick to Return to the Table of Content27 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Dry Barrel Fire Hydrants 33-12-40 (01/15/14)10/01/87 E-1-12 Dry Barrel Fire Hydrant American-Darling Valve Drawing Nos. 90-18608, 94-18560 AWWA C-50203/31/88 E-1-12 Dry Barrel Fire Hydrant American Darling Valve Shop Drawing No. 94-18791 AWWA C-50209/30/87 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Shop Drawing No. D-19895 AWWA C-50201/12/93 E-1-12 Dry Barrel Fire Hydrant American AVK Company Model 2700 AWWA C-50208/24/88 E-1-12 Dry Barrel Fire Hydrant Clow Corporation Drawings D20435, D20436, B20506 AWWA C-502E-1-12 Dry Barrel Fire Hydrant ITT Kennedy Valve Shop Drawing No. D-80783FW AWWA C-50209/24/87 E-1-12 Dry Barrel Fire Hydrant M&H Valve Company Shop Drawing No. 13476 AWWA C-50210/14/87 E-1-12 Dry Barrel Fire Hydrant Mueller CompanyShop Drawings No. 6461 A-423 Centurion AWWA C-50201/15/88 E1-12 Dry Barrel Fire Hydrant Mueller CompanyShop Drawing FH-12A-423 Super Centurion 200 AWWA C-50210/09/87 E-1-12 Dry Barrel Fire Hydrant U.S. Pipe & Foundry Shop Drawing No. 960250 AWWA C-50209/16/87 E-1-12 Dry Barrel Fire Hydrant Waterous Company Shop Drawing No. SK740803 AWWA C-50208/12/16 33-12-40 Dry Barrel Fire Hydrant EJ (East Jordan Iron Works) WaterMaster 5CD250* From Original Standard Products ListClick to Return to the Table of Content28 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Meters02/05/93 E101-5 Detector Check Meter Ames Company Model 1000 Detector Check Valve AWWA C550 4" - 10"08/05/04 Magnetic Drive Vertical Turbine Hersey Magnetic Drive Vertical AWWA C701, Class 1 3/4" - 6"* From Original Standard Products ListClick to Return to the Table of Content29 Approval Spec No. ClasssificationManufacturerModel No.National SpecSizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/PVC (Pressure Water) 33-31-70 (01/08/13)01/18/18 33-11-12 PVC Pressure PipeVinyltech PVC PipeAWWA C900, AWWA C605, ASTM D17844"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR14AWWA C9004"-12"3/19/2018 33 11 12 PVC Pressure PipePipelife Jet StreamDR18AWWA C90016"-24"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationDR 14AWWA C9004"-12"5/25/2018 33 11 12 PVC Pressure PipeDiamond Plastics CorporationTrans 21, DR 14, DR 18AWWA C90016"-24"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manifacturing Co., Inc d/b/a JM EagleDR 14"Blue Brute"AWWA C900-16UL 1285ANSI/NSF 61FM 16124"-12"12/6/2018 33 11 12 PVC Pressure PipeJ-M Manifacturing Co., Inc d/b/a JM EagleDR 18"Blue Brute"AWWA C900-16UL 1285ANSI/NSF 61FM 161216"-24"9/6/2019 33 11 12 PVC Pressure PipeUnderground Solutions Inc.DR14 Fusible PVCAWWA C9004" - 8"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR18AWWA C90016" - 24"9/6/2019 33 11 12 PVC Pressure PipeNAPCODR14AWWA C9004"- 12"9/6/2019 33 11 12 PVC Pressure PipeSanderson Pipe Corp.DR14AWWA C9004"- 12"* From Original Standard Products ListClick to Return to the Table of Content30 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/Valves & Fittings/Ductile Iron Fittings 33-11-11 (01/08/13)07/23/92 E1-07 Ductile Iron Fittings Star Pipe Products, Inc. Mechanical Joint Fittings AWWA C153 & C110* E1-07 Ductile Iron Fittings Griffin Pipe Products, Co. Mechanical Joint Fittings AWWA C 110* E1-07 Ductile Iron Fittings McWane/Tyler Pipe/ Union Utilities DivisionMechanical Joint Fittings, SSB Class 350AWWA C 153, C 110, C 11108/11/98 E1-07 Ductile Iron Fittings Sigma, Co.Mechanical Joint Fittings, SSB Class 351AWWA C 153, C 110, C 11202/26/14 E1-07 MJ Fittings AccucastClass 350 C-153 MJ FittingsAWWA C153 4"-12"05/14/98 E1-07 Ductile Iron Joint Restraints Ford Meter Box Co./Uni-FlangeUni-Flange Series 1400 AWWA C111/C153 4" to 36"05/14/98 E1-24 PVC Joint Restraints Ford Meter Box Co./Uni-FlangeUni-Flange Series 1500 Circle-LockAWWA C111/C153 4" to 24" 11/09/04 E1-07 Ductile Iron Joint Restraints One Bolt, Inc.One Bolt Restrained Joint FittingAWWA C111/C116/C153 4" to 12"02/29/12 33-11-11 Ductile Iron Pipe Mechanical Joint Restraint EBAA Iron, Inc.Megalug Series 1100 (for DI Pipe)AWWA C111/C116/C153 4" to 42"02/29/12 33-11-11 PVC Pipe Mechanical Joint Restraint EBAA Iron, Inc.Megalug Series 2000 (for PVC Pipe)AWWA C111/C116/C153 4" to 24"08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co.Sigma One-Lok SLC4 - SLC10AWWA C111/C153 4" to 10"03/06/19 33-11-11 Mechanical Joint Retainer Glands(PVC) Sigma, Co.Sigma One-Lok SLCS4 - SLCS12AWWA C111/C153 4" to 12"08/05/04 E1-07 Mechanical Joint Retainer Glands(PVC) Sigma, Co.Sigma One-Lok SLCEAWWA C111/C153 12" to 24"08/10/98 E1-07 MJ Fittings(DIP) Sigma, Co.Sigma One-Lok SLDEAWWA C153 4" - 24"10/12/10 E1-24 Interior Restrained Joint System S & B Techncial ProductsBulldog System ( Diamond Lok 21 & JM Eagle ASTM F-1624 4" to 12"08/16/06 E1-07 Mechanical Joint Fittings SIP Industries(Serampore)Mechanical Joint FittingsAWWA C153 4" to 24"11/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.PVC Stargrip Series 4000ASTM A536 AWWA C11111/07/16 33-11-11 Mechanical Joint Retainer Glands Star Pipe Products, Inc.DIP Stargrip Series 3000ASTM A536 AWWA C11103/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Black For DIPASTM A536 AWWA C111 3"-48"03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR14 PVC PipeASTM A536 AWWA C111 4"-12"03/19/18 33-11-11 Mechanical Joint Retainer Glands SIP Industries(Serampore)EZ Grip Joint Restraint (EZD) Red for C900 DR18 PVC PipeASTM A536 AWWA C111 16"-24"* From Original Standard Products ListClick to Return to the Table of Content31 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/Valves & Fittings/Resilient Seated Gate Valve* 33-12-20 (05/13/15)Resilient Wedged Gate Valve w/no Gears American Flow Control Series 2500 Drawing # 94-20247 16"12/13/02 Resilient Wedge Gate Valve American Flow Control Series 2530 and Series 2536 AWWA C515 30" and 36"08/31/99 Resilient Wedge Gate Valve American Flow Control Series 2520 & 2524 (SD 94-20255) AWWA C515 20" and 24"05/18/99 Resilient Wedge Gate Valve American Flow Control Series 2516 (SD 94-20247) AWWA C515 16"10/24/00 E1-26 Resilient Wedge Gate Valve American Flow Control Series 2500 (Ductile Iron) AWWA C515 4" to 12"08/05/04 Resilient Wedge Gate Valve American Flow Control 42" and 48" AFC 2500 AWWA C515 42" and 48"05/23/91 E1-26 Resilient Wedge Gate Valve American AVK Company American AVK Resilient Seaded GV AWWA C509 4" to 12"01/24/02 E1-26 Resilient Wedge Gate Valve American AVK Company20" and smaller* E1-26 Resilient Seated Gate Valve Kennedy4" - 12"* E1-26 Resilient Seated Gate Valve M&H4" - 12"* E1-26 Resilient Seated Gate Valve Mueller Co.4" - 12"11/08/99 Resilient Wedge Gate Valve Mueller Co. Series A2361 (SD 6647) AWWA C515 16"01/23/03 Resilient Wedge Gate Valve Mueller Co. Series A2360 for 18"-24" (SD 6709) AWWA C515 24" and smaller05/13/05 Resilient Wedge Gate Valve Mueller Co. Mueller 30" & 36", C-515 AWWA C515 30" and 36"01/31/06 Resilient Wedge Gate Valve Mueller Co. Mueller 42" & 48", C-515 AWWA C515 42" and 48"01/28/88 E1-26 Resilient Wedge Gate Valve Clow Valve Co. AWWA C509 4" - 12"10/04/94 Resilient Wedge Gate Valve Clow Valve Co. 16" RS GV (SD D-20995) AWWA C515 16"11/08/99 E1-26 Resilient Wedge Gate Valve Clow Valve Co. Clow RW Valve (SD D-21652) AWWA C515 24" and smaller11/29/04 Resilient Wedge Gate Valve Clow Valve Co. Clow 30" & 36" C-515 AWWA C515 30" and 36" (Note 3)11/30/12 Resilient Wedge Gate Valve Clow Valve Co. Clow Valve Model 2638 AWWA C515 24" to 48" (Note 3)05/08/91 E1-26 Resilient Seated Gate Valve Stockham Valves & Fittings AWWA C 509, ANSI 420 - stem, ASTM A 276 Type 304 - Bolts & nuts4" - 12"* E1-26 Resilient Seated Gate Valve U.S. Pipe and Foundry Co.Metroseal 250, requirements SPL #743" to 16"10/26/16 33-12-20 Resilient Seated Gate Valve EJ (East Jordan Iron Works)EJ FlowMaster Gate Valve & Boxes08/24/18Matco Gate Valve Matco-Norca225 MRAWWA/ANSI C115/An21.15 4" to 16"* From Original Standard Products ListClick to Return to the Table of Content32 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Pipes/Valves & Fittings/Rubber Seated Butterfly Valve 33-12-21 (07/10/14)* E1-30 Rubber Seated Butterfly Valve Henry Pratt Co. AWWA C-504 24"* E1-30 Rubber Seated Butterfly Valve Mueller Co. AWWA C-504 24"and smaller1/11/99 E1-30 Rubber Seated Butterfly Valve Dezurik Valves Co. AWWA C-504 24" and larger06/12/03 E1-30 Valmatic American Butterfly Valve Valmatic Valve and Manufacturing Corp. Valmatic American Butterfly Valve. AWWA C-504 Up to 84" diameter04/06/07 E1-30 Rubber Seated Butterfly Valve M&H Valve M&H Style 4500 & 1450 AWWA C-504 24" to 48"03/19/18 33 12 21 Rubber Seated Butterfly Valve G. A. Industries (Golden Anderson) AWWA C504 Butterfly Valve AWWA C-504 30"-54" * From Original Standard Products ListClick to Return to the Table of Content33 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Polyethylene Encasement 33-11-10 (01/08/13)05/12/05 E1-13 Polyethylene Encasment Flexsol Packaging Fulton Enterprises AWWA C105 8 mil LLD05/12/05 E1-13 Polyethylene Encasment Mountain States Plastics (MSP) and AEP Ind. Standard Hardware AWWA C105 8 mil LLD05/12/05 E1-13 Polyethylene Encasment AEP Industries Bullstrong by Cowtown Bolt & Gasket AWWA C105 8 mil LLD09/06/19 33-11-11 Polyethylene Encasment Northtown Products Inc. PE Encasement fro DIP AWWA C105 8 mil LLD* From Original Standard Products ListClick to Return to the Table of Content34 Approval Spec No. Classsification Manufacturer Model No. National Spec SizeCITY OF FORT WORTHWATER DEPARTMENT STANDARD PRODUCT LISTNote: All water or sewer pipe larger than 15 inch diameter shall be approved for use by the Water Department on a project specific basis. Special bedding may be required for some pipes.Updated: 09/06/2019Water - Sampling Station3/12/96 Water Sampling Station Water Plus B20 Water Sampling Station* From Original Standard Products ListClick to Return to the Table of Content35