HomeMy WebLinkAboutOrdinance 24686-01-2021 ORDINANCE NO.24686-01-2021
AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE 2014 BOND
PROGRAM FUND BY INCREASING APPROPRIATIONS IN THE
MONTGOMERY STREET — CAMP BOWIE (CITY PROJECT NO. CO2432) IN
THE AMOUNT OF $273,801.67 AND DECREASING APPROPRIATIONS IN THE
FUND 34014 APPROPRIATION ONLY PROJECT (CITY PROJECT NO. U34014)
BY THE SAME AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE;
MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES;
REPEALING ALL ORDINANCES IN CONFLICT HEREWITH;AND PROVIDING
AN EFFECTIVE DATE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH,
TEXAS:
SECTION 1.
That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-2021 in the
Budget of the City Manager, there shall also be adjusted appropriations in the 2014 Bond Program Fund by
increasing appropriations in the Montgomery Street—Camp Bowie(City Project No. CO2432)in the amount
of$273,801.67 and decreasing appropriations in the Fund 34014 Appropriation Only project (City Project
No.U34014)by the same amount.
SECTION 2.
That should any portion,section or part of a section of this ordinance be declared invalid, inoperative or void
for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair
the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall
be and remain in full force and effect.
SECTION 3.
That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and
appropriations amending the same except in those instances where the provisions of this ordinance are in
direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of
said prior ordinances and appropriations are hereby expressly repealed.
SECTION 4.
This ordinance shall take effect upon adoption.
APPROVED AS TO FORM AND LEGALITY: CITY SECRETARY
Mack(Jan 27,202118:25 CST) MAIFI V
Douglas W Black Mary J. Kayser
Sr.Assistant City Attorney FOR T
A.
ADOPTED AND EFFECTIVE: Janu�26,20212021
XX
sm
11S � -
��
mmins P.
•�-- Wit" .• [- - y4- + ' _
SIR
41M+ieaNat 111 .t �� - ' .Y70- � C
I� ■ '� `� �J�•.il lr*r.�*� IMul
�i ��Ii � ±ter ms 1 1�ii11 11 'ski -
R flliM im awl
IP
# v
3 - 1 •
-CH#�
MMEM
' 1Nff�l Ilil F7 1�111 _ st +L
lilt
Is
rl��i � ���IM1y�11lG�l1�1- � r • 11 � -! �. },.. t — �
Eli
din
III
1�1 111 -� r rt _y,� ,•
a
f 1L
"U I !
ARLINGTON
EIGHTS
. EASTERN
TORM DRAI +.
lot
w
EL{swm-.
MEN ■ !rr'yrtF r '+ AF r
#� h4
AR
r 1 11 11 +ALM] 16W 7
PL 1
S • • :• • L
• 1
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 01/26/21 M&C FILE NUMBER: M&C 21-0077
LOG NAME: 20MONTGOMERY CHANGE ORDER 3 AND APPROPRIATIONS
SUBJECT
(CD 7)Authorize Execution of Change Order No.3 to the Montgomery Street/Eastern Arlington Heights Drainage Construction Manager-at-Risk
Agreement with Haydon Building Corp, in an Amount up to$227,972.63,for Additional Paving,Storm Drain,Streetlight,Traffic Signal,
Landscaping, Irrigation,Water,and Sanitary Sewer Work,Thereby Increasing the Guaranteed Maximum Price to$17,827,823.41, Provide
$50,000.00 for Contingencies and Construction Services,Adopt Appropriation Ordinance,and Amend the FY2021-2025 Capital Improvement
Program(2014 Bond Program)
RECOMMENDATION:
It is recommended that the City Council:
1.Authorize Change Order No.3 to City Secretary Contract No.47328,the Montgomery Street/Eastern Arlington Heights Drainage Construction
Manager-at-Risk Agreement with Haydon Building Corp, in an amount up to$227,972.63,for additional paving,storm drain,streetlight,traffic
signal,landscaping,irrigation,water,and sanitary sewer work,thereby increasing the Guaranteed Maximum Price to$17,827,823.41 and the
addition of 81 calendar days to the contract time(City Project Numbers 02432 and 100218);
2.Adopt the attached Appropriation Ordinance adjusting appropriations in the 2014 Bond Program Fund by increasing appropriations in the
Montgomery Street—Camp Bowie(City Project No.CO2432)in the amount of$273,801.67 and decreasing appropriations in the Fund 34014
Appropriation Only project(City Project No.U34014)by the same amount;and
3.Amend the FY2021-2025 Capital Improvement Program.
DISCUSSION:
This Mayor and Council Communication authorizes Change Order No.3, in the amount up to$227,972.63,to the CMAR Agreement with Haydon
Building Corp(Haydon)(CSC No.47328).Change Order No.3 provides for construction services for additional asphalt and concrete pavement,
sidewalks, pavers,driveways,storm drain pipe and inlets,streetlights,traffic signals, landscpaping and irrigation,and water and sanitary
sewer services,with an additional 81 calendar days of contract time negotiated with the CMAR for the additional scope of work not contemplated
in the original schedule.The additional work items were caused by various reasons,some of which are associated with the Dickies Arena project:
• Water and sewer services,and franchise utilities not shown in record drawings found in the field during construction;
• Schedule changes during construction required the boring of streetlight conduit;
• Traffic signal at Trail Drive was upgraded and revised to avoid conflicts with franchise utilities;
• Paving,sidewalk and paver changes were prompted by the Dickies Arena project at the Harley Street and Montgomery Street entrances to
meet the project requirements;
• Landscaping and irrigation were revised to match the Arena Team's construction as well as restore businesses'which were impacted by
construction;
• Inlet types were revised to avoid utilities or provide additional room for franchise utilities.
On August 25,2015(M&C C-27427),the City Council authorized the execution of a two-phase CMAR Agreement with Haydon for Pre-
Construction Services in the amount of$68,809.00 and for the construction of Montgomery Street from Camp Bowie Boulevard to Interstate
Highway 30.
On May 16,2017(M&C C-28243),the City Council authorized Amendment No. 1 to the CMAR Agreement with Haydon to add the Eastern
Arlington Heights Storm Drain Improvements along Bryce Avenue from Montgomery Street to Sutter Street and establish a Guaranteed Maximum
Price(GMP)in the amount of$17,092,000 for construction of the project.
On December 5,2017(M&C C-28489),the City Council authorized Change Order No. 1 to the Montgomery Street/Eastern Arlington Heights
Drainage CMAR Agreement with Haydon in the amount of$261,972.67 for changes to the street paving component thereby increasing the
Guaranteed Maximum Price(GMP)to$17,353,972.67.
On June 26,2019(M&C C-29183),the City Council authorized Change Order No.2 to the Montgomery Street/Eastern Arlington Heights Drainage
CMAR Agreement with Haydon in the amount up to$245,878.11 for changes to the water and sanitary sewer components,thereby increasing the
Guaranteed Maximum Price to$17,599,850.78.(City Project No. 100218).
Additionally,funds in the amount of$50,000.00 will be used to provide for contingencies and construction services.
Funding for this project was included in the FY2021-2025 Capital Improvement Program in the amount of$$15,818,450.00.Additional funding in
the amount of$273,801.67 is needed for construction services and contingency service costs.The action in this M&C will amend the FY2021-
2025 Capital Improvement Program as shown in the tables below:
Fund Existing Additional Project Total
Funding Funding
Montgomery Street-Camp Bowie
-CO2432
2014 Bond Fund—34014 $8,324,000.00 $277,972.63 $8,601,972.63
Stormwater Capital Projects—52002 $200,000.00 $0.00 $200,000.00
Street Improvements Supplement— $1,000,000.00 $0.00 $1,000,000.00
39406
Street Improvements—39409 $94,450.00 $0.00 $94,450.00
2004 Bond Residuals-39410 $2,544,380.00 $0.00 $2,544,380.00
2008 Bond Residuals-39411 $3,405,620.00 $0.00 $3,405,620.00
Stormwater Capital Projects-59651 $250,000.00 $0.00 $250,000.00
Project Subtotal=$15,818,450.00 $277,972.63 $16,096,422.63
Fund Existing Additional Project Total
Funding Funding
Montgomery Construction
Support-102355
General Capital—30100 $78,275.44 $0.00 $78,275.44
Project Subtotal= $78,275.44 $0.00 $78,275.44
Fund Existing Additional Project Total
Funding Funding
Montgomery/E Arlington Heights -
100218
Stormwater Capital Projects—52002 $92,180.69 $0.00 $92,180.69
Water and Sewer Capital Projects— $1,930,879.00 $0.00 $1,930,879.00
56002
Stormwater Capital Projects—Bonds $2,829,883.00 $0.00 $2,829,883.00
-59651
Stormwater Capital Project Legacy— $1,991,666.31 $0.00 $1,991,666.31
59652
Project Subtotal= $6,844,609.00 $0.00 $6,844,609.00
Grand Total=$22,741,334.44 $277,972.63 $23,019,307.07
M/WBE Office: Haydon Building Corp agrees to maintain its initial MBE commitment of 12 percent that it made on the original contract and extend
and maintain that same MBE commitment of 12 percent to all prior change orders up to and inclusive of this Change Order No.3.Therefore
Haydon Building Corp remains in compliance with the City's BDE Ordinance and attests to its commitment by its signature on the Acceptance of
Previous MBE Commitment form executed by an authorized representative of its company.
The Montgomery Street project is located in COUNCIL DISTRICT 7.
FISCAL INFORMATION/CERTIFICATION:
The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds
are available in the current capital budget of the Montgomery Street-Camp Bowie project,as appropriated, in the 2014 Bond Fund. Prior to an
expenditure being incurred,the Transportation&Public Works Department has the responsibility of verifying the availability of funds.
Submitted for City Manager's Office by: Dana Burghdoff 8018
Originating Business Unit Head: William Johnson 7801
Additional Information Contact: Jennifer Roberts 8447