HomeMy WebLinkAboutContract 54148-CO1 CSC No.54148-COI
FORT WORTH, City of Fort Worth
Change Order Request
Project Name I VCWRF Sludge Thickening Improvements Cily Sec# 1 54148
Client ProjecI#(s)J Village Creek Water Reclamation Facility(VCWRF)Sludge Thickening Improvements(CO2647)
Project Upgrading/Modification of primary and WAS thickening processes;including improvements to existing GBT and sludge buildings,gravity thickeners,WAS
Description storage&sludge blend tanks,Dissolved AirFloatatlon Tanks(DAFT),and Backwash Clarifier.
Contractorl Eagle Contracting,LP Change Order#1 1 Date 1/12/2021
City Project Mgr. Farida Goderya City Inspeclorl Kevin Sidebotlom I Scott Atwood
Dept. Water Department Contract TimeTotals (CD)
Original Contract Amount 17,480,000.00 $17,48D,ODO.OD 730
Extras to Dale $0.00
Credits to Dale $0.00
Pending Change Orders(in M&C Process) $0.00
Contract Cost to Date $17.480 000.00 17.480 000.00 730
Amount of Proposed Change Order $91,838.00 91 838.00
Revised Contract Amount S17.571.838.00 $17,571,838.00
Original Funds Available for Change Orders $305,900.00 $305 900.00
Remaining Funds Available for this CO
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.530-
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $21.850,000.00
JUSRACATION(REASONS)FOR CHANGE ORDER
This Change Order# 1 is for multiple Contract Modification Requests(CMR)and a Proposed Contract Modifications(PCM),as identified in the attached sheets.This
change order does not include any time extension for the contract.The Staff has reviewed the related CMRIPCM and recommends approval.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
Contractor's Company Name Contractor(Name) Contract ' nature Date
Eagle Contracting,LP Philip Bennett 12'2 j
Ins tor/Inspection Supervisor Date Project and Contract Compliance Manager Date
Kevin Sideboltom or Scott Atwood,FNI _Jrdy(Lr'-
Pr-fdflil•MIst1 er Date Senior Capital Project Officer Date
Farida Gode a — 1/21/21
Assistant Director Date Director,Conti De ent(Dept) Date
Tony Sholola 0A S ti ll < rr`i Chris Harder0.0,0-0,54,06k,- Janzz,zoz1
Assistant CityAttornBy Dale Assistant City Manager Dale
Janzz,zozr Dana Bur hdoff °a R""G Jan 22,2021
Council Action If required)
M&C Number I N/A M&C Date Approved NIA
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
��+rtr_9n tit City of Fort Worth
T Change Order Additions
Project Name VCWRF Sludge Thickening Improvements City Sec# 54148
Client Project# r Village Creek Water Reclamation Facility(VCWRF)Sludge Thickening Improvements(CO2647)
Contractor Eagle Contracting,LP PMJ Fanda Goderya Inspector®
Change Order Submittal# Dale 1/12/2021
AUUI I TUNS
Unit UnitCost total
Glass Glazing a er epa men
Holding Tanks Sluice Gate Size Adjustment ate- epadmenl
Unforeseen Concrete Demo aler epartmenl
Concrete Repair aler epartmenl
Cast Stone Replacement ate- epartmenl
Larger RD I and GBT FeedPump Motors a er epadmenl
Water Department 91,838.00
bUb otalA001110FIS
Change Order Additions Page 2 of 2
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
forthe monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Signature
Farida Goderya,PhD,PE
Name of Employee
Senior Project Manager
Title
aroRr
ATTEST: �1. �0���
Oh o o A,
10
0000
City Secretary KayserMaty J. �aa��neXASba�
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
Village Creek WRF-Sludge Thickening Improvements
Contract Modification Request-No.2-(Rev 1)
Date:9-22-20
Work Description �`-L �-IT T� T�
Change in Glass Specification(RFI-9). Original scope included i +� E
Solarban 72 over Starphire. RFI-9 changed glass type to Solarban CONTRAC-'TINC , L P.
90 over Starphire. Approximately 637SF.
Owner: Engineer: Contractor:
Fort Worth Water Utilities Freese&Nichols Eagle Contracting
4055 International Plaza,Ste 200 5700 Park Vista Circle
Ft.Worth,TX 76109 Ft Worth,Texas 76244
Chad Simmons
Labor Material Equipment Subcontractor
TOTALS: $ $ - $ - $ 1,576.55 $1,576.55
Eagle Insurance 0.25% $3.94
Overhead&Profit-5%Subcontracted Work $78.83
Overhead&Profit-15%Self Performed Work $0.00
Subtotal $1,659.32
Bond @ 1% $16.59
Subtotal $1,675.91
Total Amount This Cost Proposal $1,675.91
I
Time Extension Required-0 Calendar Days I
V
ROUNDED $ 1,676.00
Village Creek WRF-Sludge Thickening Improvements
Contract Modification Request-No.3-Rev 1
Date:9-22-20 +
Work Description �` �T
Change the slide gate size at the WAS Holding Tank#1  from i�
the 18"x 18"Size denoted on Drawing WT-M4(Note 12)to match CONTRACTING, L P,
the existing gate size of 36"x 36",when field verified.
Owner: Engineer: Contractor:
Fort Worth Water Utilities Freese&Nichols Eagle Contracting
4055 International Plaza,Ste 200 5700 Park Vista Circle
Ft.Worth,TX 76109 Ft Worth,Texas 76244
Chad Simmons
Labor Material Equipment Subcontractor
TOTALS: $ - $ 3,000.00 $ $ - $3,000.00
Eagle Insurance 0.25% $7.50
Overhead&Profit-5%Subcontracted Work $0.00
Overhead&Profit-15%Self Performed Work $450.00
Subtotal $3,457.50
Bond @ 1% $34.58
Subtotal $3,492.08
Total Amount This Cost Proposal $3,492.08
Time Extension Required-0 Calendar Days I
V
ROUNDED $ 3,492.00
Village Creek WRF-Sludge Thickening Improvements
Contract Modification Request-No.3-Rev 1
Date: 10/30/20
Work Description �`_�
Demo unforseen concrete in the basement area for the installation
of the new drain lines.Remove 2'-0"of additional concrete below CONTRACTING, ( P
the floor slab using jack hammers and a Bobcat in order to install
new drain lines. Please reference RFI-22.(5M x 9Days)
Owner: Engineer: Contractor:
Fort Worth Water Utilities Freese&Nichols Eagle Contracting
4055 International Plaza,Ste 200 5700 Park Vista Circle
Ft.Worth,TX 76109 Ft Worth,Texas 76244
Chad Simmons
Labor Material Equipment Subcontractor
TOTALS: $ 11,842.32 $ - $ 5,109.55 $ - $16,951.87
Eagle Insurance 0.25% $42.38
Overhead&Profit-5%Subcontracted Work $0.00
Overhead&Profit-15%Self Performed Work $2,542.78
Subtotal $19,537.03
Bond @ 1% $195.37
Subtotal $19,732.40
Total Amount This Cost Proposal $19,732,40
1
Time Extension Required-0 Calendar Days 1
V
ROUNDED $ 19,732.00
Contract Modification Request
Project VCWRF Sludge Thickening Improvements Project Number
Owner City of Fort Worth CSC#54148 CO2647
Contractor Eagle Contracting, LP
Construction Manager Freese and Nichols, Inc.
Design Professional Freese and Nichols, Inc.
CMR No. 005 Description Unforeseen Concrete Demo
Specification
Drawing No. TF-P2 Detail Description Detail 1/TF-P2
Reference Document
❑X Request for Information No. 022 ❑ Field Order No.
❑ Shop Drawing Deviation Request No.
Contractor proposes the following modifications to the Contract Documents:
Demo unforseen concrete in the basement area for the installation of the new drain lines. Remove 2'-0" of ditional
concrete below the floor slab using jack hammers and a Bobcat in order to install new drain lines. Please reference
RFI-022.
Basis of Compensation
❑ Unit Prices ❑X Lump Sum calculated using Cost of Work provisions in the Contract
❑ Time and Materials using Cost of Work provisions in the Contract
The compensation offered for this Contract Modification Request is the full, complete, and final compensation for
all costs Contractor may incur because of or relating to this change whether said costs are known, unknown,
foreseen, or unforeseen at this time, including without limitation, any cost for delay, extended overhead, ripple or
impact cost, or any other effect on changed or unchanged Work because of this Contract Modification Request.
Requested changes in Contract Times are the complete and final adjustments for impacts to the ability of
Contractor to complete the Work within the Contract Times and are the only adjustments to which Contractor is
entitled.All terms and provisions of the Contract Documents remain in effect except as specifically modified by this
Contract Modification Request.
Proposed Net Change in Contract Price $ 19,732.00
Proposed Net Change in Contract Times 0 days
Required Documentation
® Detailed cost breakdown attached showing labor, materials, equipment, and all other costs for this change
❑ Schedule attached to show impacts and justification for requested change in Contract Times
Reason for the CMR
See RFI-022
1
Village Creek WRF-Sludge Thickening Improvements
Contract Modification Request-No.6
Date: 11/3/20
Work Description .` /-"'LE
Repair the vertical surface of the Gravity Thickener Trough @ l�
238LF Circumference x X-0"Tall=714SF. 1 -501b bag covers— CONTRACTING, L
6sf per test patch on(11-3-20). It is estimated by the time it took to
complete the patch area,that it will take 4men x 5 days to
complete each tank repair(GT#1 >#3)-Price is for BOTH
tanks complete
Owner: Engineer: Contractor:
Fort Worth Water Utilities Freese&Nichols Eagle Contracting
4055 International Plaza,Ste 200 5700 Park Vista Circle
Ft.Worth,TX 76109 Ft Worth,Texas 76244
Chad Simmons
Labor Material Equipment Subcontractor
TOTALS: $ 9,804.00 $ 14,110.91 $ 410.27 $ - $24,325.18
Eagle Insurance 0.25% $60.81
Overhead&Profit-5%Subcontracted Work $0.00
Overhead&Profit-15%Self Performed Work $3,648.78
Subtotal $28,034.77
Bond @ 1% $280.35
Subtotal $28,315.12
Total Amount This Cost Proposal $28,315.12
I
Time Extension Required-0 Calendar Days I
V
ROUNDED $ 28,315.00
Village Creek WRF-Sludge Thickening Improvements
Project Contract Modification-No.1
Date: 10-26-20
Work Description r
Replace fifteen(15)pieces of cast stone parapet on the Sludge E. I 7 L E
Thickening Facility due to cracks and/or deteriation. Caulk Joints, CONTRACTING,ACTING. L R
and apply waterproofing/paint prior to new roofing
Owner: Engineer: Contractor:
Fort Worth Water Utilities Freese&Nichols Eagle Contracting
4055 International Plaza,Ste 200 5700 Park Vista Circle
Ft.Worth,TX 76109 Ft Worth,Texas 76244
Chad Simmons
Labor Material Equipment Subcontractor
TOTALS: $ 4,715.04 $ 425.63 $ - $ 13,102.00 $18,242.67
Eagle Insurance 0.25% $45.61
Overhead&Profit-5%Subcontracted Work $1,310.20
Overhead&Profit-15%Self Performed Work $771.10
Subtotal $20,369.57
Bond @ 1% $203.70
Subtotal $20,573.27
Total Amount This Cost Proposal $20,573.27
I
Time Extension Required-0 Calendar Days
V
ROUNDED $ 20,573.00
Village Creek WRF-Sludge Thickening Improvements
PCM-No.2
Date: 12-3-20
Work Description 4(�L
Provide pricing to increase the motor size of the RDT and GBT +
feed pumps per the below revised flow and head conditions. CONTRACTING, L P.
Include in the pricing upsized wire and breakers per the attached
drawings as well upsized 15 HP VFDs.RDT Feed Pump(Wemco)
Increase from 10 HP to 15 HP•Typical Flow:400 gpm @ 30.5-ft
TDH•Pump is on VFD and will range from a max flow of 500 gpm
@ 41.5-ft and min flow of about 280 gpm @ 23-ft GBT Feed Pump
(Gorman Rupp)•Increase from 7.5 HP to 15 HP•Typical Flow:400
gpm @ 43-ft TDH•Pump is on VFD and will range from a max flow
of 500 gpm @ 58-ft and min flow of about 280 gpm @ 30-ft
Owner: Engineer: Contractor:
Fort Worth Water Utilities Freese&Nichols Eagle Contracting
4055 International Plaza,Ste 200 5700 Park Vista Circle
Ft.Worth,TX 76109 Ft Worth,Texas 76244
Chad Simmons
Labor Material Equipment Subcontractor
TOTALS: $ 228.00 $ 7,310.03 $ - $ 8,329.63 $15,867.66
Eagle Insurance 0.25% $39.67
Overhead&Profit-5%Subcontracted Work $832.96
Overhead&Profit-15%Self Performed Work $1,130.70
Subtotal
$17,871.00
Bond @ 1% $178.71
Subtotal
$18,049.71
Total Amount This Cost Proposal $18,049.71
I
Time Extension Required-0 Calendar Days
V
ROUNDED $ 18,050.00