NOTICE OF PROJECT COMPLETION
(Developer Projects)
The Transportation and Public Works Department upon the recommendation of the Project
Manager has accepted the following project as complete:
Project Name: LAKE PARC VILLAGE
City Project No.: 101685
Improvement Type(s): ❑ Paving ® Drainage ❑ Street Lights ❑ Traffic Signals
Original Contract Price: $132,517.50
Amount of Approved Change Order(s):
Revised Contract Amount:
Total Cost of Work Complete: $132,517.50
X1-,q#d0#iyilA21- Jan 21,2021
Brandon Walker(Jan 21,202114:36 CST)
Contractor Date
Vice President
Title
Walker Utilities Inc.
Company Name
uJwLzt Jan 27,2021
Project Inspector Date
Debbie.T. willhelm Jan 28 2021
Debbie J.Willhelm(Jan 28,202111:06 CST) f
P ject Manager � Date
eScarlett Morales(Jan 28,202113:23CST) Jan 28,2021
CFA Mana er Date
Dana Burghdoff(J 28,202114:36CST) Jan 28,2021
Asst. City Manager Date
OFFICIAL RECORD
CITY SECRETARY Page 1 of 2
FT.WORTH, TX
Notice of Project Completion
Project Name: LAKE PARC VILLAGE
City Project No.: 101685
City's Attachments
Final Pay Estimate
Change Order(s): ❑ Yes ® N/A
Contractor's Attachments
Affidavit of Bills Paid
Consent of Surety
Statement of Contract Time
Contract Time: 90 CD Days Charged: 357
Work Start Date: 12/3/2019 Work Complete Date: 11/23/2020
Page 2 of 2
FORT WORT H
CITY OF FORT WORTH
FINAL PAYMENT REQUEST
Contract Name LAKE PARC VILLAGE
Contract Limits
Project Type STORM DRAIN
City Project Numbers 101685
DOE Number 1685
Estimate Number 1 Payment Number 1 For Period Ending 1/21/2021
City Secretary Contract Number Contract Time 90
Contract Date Days Charged to Date 373
Project Manager NA Contract is 100.00 Complete
Contractor WALKER UTILITIES,INC.
P.O.BOX 54122
HURST, TX 76054
Inspectors OWEN / MATTEGAT
Thursday,January 21,2021 Pagel of4
City Project Numbers 101685 DOE Number 1685
Contract Name LAKE PARC VILLAGE Estimate Number 1
Contract Limits Payment Number 1
Project Type STORM DRAIN For Period Ending 1/21/2021
Project Funding
STORM DRAIN
Item Description of Items Estimated Unit Unit Cost Estimated Completed Completed
No. Quanity Total Quanity Total
---------------------------------------
1 24"RCP CLASS III 70 LF $93.00 $6,510.00 70 $6,510.00
2 30"RCP CLASS III 26 LF $110.00 $2,860.00 26 $2,860.00
3 33"RCP CLASS III 319 LF $155.00 $49,445.00 319 $49,445.00
4 36"RCP CLASS III 102 LF $205.00 $20,910.00 102 $20,910.00
5 4'STORM JUNCTION BOX 2 EA $6,200.00 $12,400.00 2 $12,400.00
6 5'STORM JUNCTION BOX 1 EA $4,900.00 $4,900.00 1 $4,900.00
7 36"FLARED HEADWALL,1 PIPE 1 EA $3,500.00 $39500.00 1 $3,500.00
8 10'CURB INLET 1 EA $4,500.00 $49500.00 1 $4,500.00
9 20'CURBINLET 2 EA $7,900.00 $159800.00 2 $15,800.00
10 TRENCH SAFETY 517 LF $2.50 $19292.50 517 $1,292.50
11 MEDIUM STONE RIP RAP GROUTED 350 SF $18.00 $6,300.00 350 $6,300.00
12 24"SET 1 PIPE 2 EA $2,050.00 $49100.00 2 $4,100.00
--------------------------------------
Sub-Total of Previous Unit $1329517.50 $1329517.50
--------------------------------------
Thursday,January 21,2021 Page 2 of
City Project Numbers 101685 DOE Number 1685
Contract Name LAKE PARC VILLAGE Estimate Number 1
Contract Limits Payment Number 1
Project Type STORM DRAIN For Period Ending 1/21/2021
Project Funding
Contract Information Summary
Original Contract Amount $132,517.50
Change Orders
Total Contract Price $132,517.50
Total Cost of Work Completed $132,517.50
Less % Retained $0.00
Net Earned $132,517.50
Earned This Period $132,517.50
Retainage This Period $0.00
Less Liquidated Damages
Days @ /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $132,517.50
Thursday,January 21,2021 Page 3 of
City Project Numbers 101685 DOE Number 1685
Contract Name LAKE PARC VILLAGE Estimate Number 1
Contract Limits Payment Number 1
Project Type STORM DRAIN For Period Ending 1/21/2021
Project Funding
Project Manager NA City Secretary Contract Number
Inspectors OATEN / MATTEGAT Contract Date
Contractor WALKER UTILITIES,INC. Contract Time 90
P.O.BOX 54122 Days Charged to Date 373
HURST, TX 76054 Contract is .000000 Complete
CITY OF FORT WORTH
SUMMARY OF CHARGES
Line Fund Account Center Amount Gross Retainage Net
Funded
--------------------------------------
Total Cost of Work Completed $132,517.50
Less % Retained $0.00
Net Earned $132,517.50
Earned This Period $132,517.50
Retainage This Period $0.00
Less Liquidated Damages
0 Days @ $0.00 /Day $0.00
LessPavement Deficiency $0.00
Less Penalty $0.00
Less Previous Payment $0.00
Plus Material on Hand Less 15% $0.00
Balance Due This Payment $132,517.50
Thursday,January 21,2021 Page 4 of
FORTWORTH.
TRANSPORTATION AND PUBLIC WORKS
12/30/2020
Walker Utilities Inc
124 Brown Trail
Hurst, Tx. 76053
RE: Acceptance Letter
Project Name: Lake Parc Village
Project Type: Development
City Project No.: 101685
To Whom It May Concern:
On November 23, 2020 a final inspection was made on the subject project. There were punch list items
identified at that time. The punch list items were completed on December 9, 2020. The final inspection
and the corrected punch list items indicate that the work meets the City of Fort Worth specifications and
is therefore accepted by the City. The warranty period will start on December 9, 2020, which is the date
of the punch list completion and will extend of two (2)years in accordance with the Contract
Documents.
If you have any questions concerning this letter of acceptance, please feel free to contact me at 817-
392-2481.
Sincerely,
Debbie T. wilMolm
Debbie J.Wilhelm(Jan 28,202111:06 CST)
Debbie J.Willhelm, P.E., Project Manager
Cc:William Mattegat, Inspector
Billy Owen, Inspection Supervisor
Joesph Rogers,Senior Inspector
Victor,Tornero, Program Manager
Donohue Consulting Inc, Consultant
Walker Utilites Inc, Contractor
DBRC Construction LLC, Developer
File
E-Mail: TPW_Acceptance@fortworthtexas.gov
Rev.8/20/19
AFFIDAVIT
STATE OF TEXAS
COUNTY OF TARRANT
Before me, the undersigned authority, a Notary Public in the state and
county aforesaid, on this day personally appeared Brandon Walker,
Vice President, of Walker Utilities Inc., known to me to be a credible
person, who being by me duly sworn, upon his oath deposed and said;
That all persons, firms, associations, corporations or other
organizations furnishing labor and/or materials have been paid in full;
That the wage scale established by the City Council in the City of Fort
Worth has been paid; and
That there are no claims pending for personal injury and/or property
damages;
On Contract described as;
Lake Parc Village Water, Sanitary Sewer, and Storm Drain Improvements
City Project # 101685
BY
Subscribed and sworn before me on this day of
D2 c e�rt her
JASO , o
`S>'RY PG4
�20.•••••,ate N ESCOBEDO
%0c Notary Public,State of Texas
..:+Pc Comm. Expires 02-26-2021 ary Public in Tarrant
� °i��`�� NotaryID
126617961 County, Texas
CONSENT OF OWNER ❑
SURETY COMPANY ARCHITECT ❑
TO FINAL PAYMENT CONTRACTOR ❑
AIA DOCUMENT G707 SURETY V
OTHER ❑ BOND#4426483
PROJECT: Lake Parc Village
(name,address)
TO: (Owner) CONTRACT FOR:WATER,SANITARY,PAVING,DRAINAGE&STREET
LIGHT FACILITIES
City of Ft.Worth,
200 Texas St. CONTRACT DATE:8/6/2019
Fort Worth,TX 76102
CONTRACTOR:
Walker Utilities,Inc.
In accordance with the provisions of the Contract between the Owner and the Contractor as indicated above,the
(here insert name and address of Surety Company)
SureTec Insurance Company
2103 CityWest Blvd.,Suite 1300
Houston,TX 77042
,SURETY COMPANY,
on bond of
(here insert name and address of Contractor)
Walker Utilities,Inc.
P.O.Box 54122
Hurst,TX 76053 ,CONTRACTOR,
hereby approves of the final payment to the Contractor, and agrees that final payment to the Contractor shall
not relieve the Surety company of any of its obligations to
(here inserl name and address of Owner)
City of Ft.Worth
200 Texas St. OWNER,
Fort Worth,TX 76102
as set forth in the said Surety Company's bond
IN WITNESS WHEROF,
The Surety Company has hereunto set its hand this9th day of December , 2020
SureTec Insurance Conmmny
Surety mpany
igna of u orized Representative
Attest ft&
(seal): Elena Sells Witness Jennifer Clark Attorney-in-Fact
Title
AIA DOCUMENT G707*CONSENT OF SURETY COMPANY TO FINAL PAYMENT*APRIL 1970 EDITION*AIA
1970 THE AMERICAN INSTITUTE OF ARCHITECTS,1735 NEW YORK AVE.NW WASHINGTON,D.C.2006
POA#: 4221800
SureTec Insurance Company
LIMITED POWER OF ATTORNEY
Know All Men by These Presents, That SURETEC INSURANCE COMPANY (the "Company"), a corporation duly organized and
existing under the laws of the State of Texas, and having its principal office in Houston, Harris County, Texas, does by these presents
make,constitute and appoint
Kathy Sells,Lanny Land,Steven W.Lewis, Elena Sells,Jennifer Clark
its true and lawful Attorney-in-fact,with full power and authority hereby conferred in its name,place and stead,to execute, acknowledge
and deliver any and all bonds, recognizances, undertakings or other instruments or contracts of suretyship to include waivers to the
conditions of contracts and consents of surety for,providing the bond penalty does not exceed
Ten Million and 00/100 Dollars($10,000,000.00)
and to bind the Company thereby as fully and to the same extent as if such bond were signed by the President, sealed with the corporate
seal of the Company and duly attested by its Secretary, hereby ratifying and confirming all that the said Attorney-in-Fact may do in the
premises. Said appointment is made under and by authority of the following resolutions of the Board of Directors of the SureTec
Insurance Company:
Be it Resolved, that the President,any Vice-President, any Assistant Vice-President,any Secretary or any Assistant Secretary shall be and is
hereby vested with full power and authority to appoint any one or more suitable persons as Attorney(s)-in-Fact to represent and act for and on
behalf of the Company subject to the following provisions:
Attorney-in-Fact may be given full power and authority for and in the name of and of behalf of the Company, to execute, acknowledge and
deliver,any and all bonds,recognizances, contracts,agreements or indemnity and other conditional or obligatory undertakings and any and all
notices and documents canceling or terminating the Company's liability thereunder, and any such instruments so executed by any such
Attorney-in-Fact shall be binding upon the Company as if signed by the President and sealed and effected by the Corporate Secretary.
Be it Resolved, that the signature of any authorized officer and seal of the Company heretofore or hereafter affixed to any power of attorney or
any certificate relating thereto by facsimile,and any power of attorney or certificate bearing facsimile signature or facsimile seal shall be valid
and binding upon the Company with respect to any bond or undertaking to which it is attached. (Adopted at a meeting held on 20'of April,
1999.)
lit Witness Whereof, SURETEC INSURANCE COMPANY has caused these presents to be signed by its President,and its corporate seal
to be hereto affixed this nth day of m-Y ,A.D. 2= .
SURETEC INSURANCE COMPANY
NCF
to X � '�0 By:
�
t w y z1 Michael C. Keimig,President
State of Texas ss:
County of Harris
On this Ah day of M■y A.D. 2= before me personally came Michael C.Keimig, to me known,who,being by me duly sworn, did depose and say,
that he resides in Houston,Texas,that he is President of SURETEC INSURANCE COMPANY,the company described in and which executed the above
instrument;that he knows the seal of said Company;that the seal affixed to said instrument is such corporate seal;that it was so affixed by order of the
Board of Directors of said Company;and that he signed his name thereto by like order.
un un.. r
.o,►P:.��•s TANYA SNEED
NoWy Pubic,SW&TOM
s117
* 00M f6tpitss03.30= Tanya Sneed,Notafy Public
''Nq:' `''f ID 128S71xlt
'�.. �'" Now My commission exp1res March 30,2023
1,M.Brent Beaty,Assistant Secretary of SURETEC INSURANCE COMPANY,do hereby certify that the above and foregoing is a true and correct copy
of a Power of Attorney,executed by said Company, which is still in full force and effect;and furthermore,the resolutions of the Board of Directors,set
out in the Power of Attorney are in full force and effect.
Given under my hand and the seal of said Company at Houston, Texas this 9th day of D 06mber- , A.D.
M. Brent Beaty,Assistann e9retary
Any instrument issued in excess of the penalty stated above is totally void and without any validity. 4221800
For verification of the authority of this power you may call(713)812-0800 any business day between 8:30 am and 5:00 pm CST.