HomeMy WebLinkAboutContract 54411-CO2 F_ORTWORTH_ City of Fort Worth CSC NO. 54411-CO2
Change Order Request
Project Name East 1st Street Bridge Improvements City Sec# 54411
Client Project#(s) 100575 33005-0800450-5740010-100575-005080-9999&33002-0800450-5740010-100575-005080-9999
Project East 1st Street Bridge Improvements
Description
Contractor Fort Worth Civil Constructors,LLC Change Order# 2 Date 1/13/2021
City Project Mgr. Carlos M Gonzalez City Inspector Ryan Garrett Miller
Contract Time
Dept. PARD Totals CD
Original Contract Amount $836,554.59 836,554.59 180
Extras to Date $20,642.28 $20,642.28
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $857,196.87 $857,196.87 180
Go to ADD&DEL Tabs to Enter CO Backup $43,768.00 $43,768.00 21
Revised Contract Amount 900,964.87 900,964.87 201
Original Funds Available for Change Orders $40,000.00 $40,000.00
Remaining Funds Available for this CO $19,357.72 $19,357.72
Additional Funding(if necessary) 1 $24,410.28 $24,410.28
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 7.70%
MAXALLOWABLE CONTRACTAMOUNT(ORIGINAL CONTRACT COST+25%) $1,045,693.24
JUSTIFICATION(REASONS)FOR CHANGE ORDER
During construction,the plan calls for removing the existing asphalt roadway and using the gravel under the road to compact the new concrete sidewalk's grades. However,
after removing the asphalt road,there was no gravel under the road. Therefore,it was determined by both parties to use the roadway millings to compact and stabilizes the
grades for the new trail.
During construction,the plans and specs call for the contractor to touch up,clean up,and add several materials to the bridge.Both parties agreed it would be better to paint
the bridge's exposed entire northern section and only touch up the southern area.
Lastly,during the project,the contractor submitted an asphalt request for substitution. The city determines the product to be adequate for the project but chipper in price.
The contractor agreed to provide the city with some credit by using the substitute asphalt product.
The city requested the contractor for a quote to re-use the roadway milling,paint the entire bridge,and the credit for the asphalt product substitution. Upon reviewing the
proposed scope and pricing,staff found the fee fair and reasonable. The Park&Recreation Department will use the project's available funds to award this change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in
full(both time and money)for all costs arising out of,or incidental to,the above Change Order. The Project/Program Manager signing below
acknowledges that he/she is the person responsible for the monitoring and administration of this contract,including ensuring all performance and
reporting requirements.
Contractor's Company Name Contractor Name Contract Signature Date
Fort Worth Civil Constructors,LLC Austin Alumbua h 9° Jan 25,2021
Inspector/Inspection Supervisor 111111111110 Date Project Manager/Program Manager Date
1�oJ- Jan 25,2021 /eowr ;'p-„k- 2-"(� C'
„�„ ..ir Cr/ i i � Jan 25,2021
Assistant Director(Dept) Date Dire apartment(Dept) Date
°n11-1 IT) Jan 26,2021 Jan 26,2021
Assistant City ttorney Date Assistant City Manager Date
blxk�F.b 1,NSSOS3]CST Feb 1,2021 Feb 1,2021
Council Action if required)
M&C Number M&C Date Approved
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
City of Fort Worth
Change Order Additions
Project Name East 1st Street Bridge Improvements City Sec# 54411
Client Project# 100575 33005-0800450-5740010-100575-005080-9999&33002.0800450.5740010-100575-005080-
Contractor Fort Worth Civil Constructors,LLC PM Carlos M Gonzalez Inspector Ryan Garrett Miller
Change Order Submittal# IJ Date 1I13I2021
AODITION5
ITEM DESCRIPTION DEPT Qty Unit UnitCost Total
i umionus Concrete on Dock
ropose n ge ain ing
ncre a Trail Milling Import PARD
PARD $118,148.00
Sub Total Additions 118,1 88.00
Change Order Additions Page 2 of 4
FORT WORrii City of Fort Worth
_. — Change Order Deletions
Project Name East 1st Street Bridge Improvements City Sec# 54411
Client Project# 100575 33005-0800450-5740010-100575-005080-9999&33002.0800450.5740010-100575-005080-
Contractor Fort Worth Civil Constructors,LLC PM Carlos M Gonzalez Inspector Ryan Garrett Miller
Change Order Submittal# O2 Date 111312021
DELETIONS
ITEM DESCRIPTION DEPT Qty Unit UnitCost Total
I- Bitumionus Concrete on Deck PARD 45.00000000T N
I- lean and Paint uperstructure PARD L 4,
I- lean and Paint Railing PARD L
I- lean and Paint New Railing PARD 1.00000000 L
PARD $74,380.00
Sub Total Deletions 74,380.00
Change Order Deletions Page 3 of 4
M/SBE for this Change Order
M/SBE Sub Type of Service Amount for this CO
N/A
Total $0.00
Previous Change Orders
CO# DATE AMOUNT
Total $0.00
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible for
the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
Carlos M Gonzalez
Name of Employee
Park Planner
Title
❑ This form is N/A as No City Funds are associated with this Contract
Fo
Carlos M Gonzalez
Printed Name Signature
d'dUbn�
z dpa FORT�aa
Attested by: 00
��o °�9��d
�vo o=o
vtw ° d
o°OOO0000°°o° pFY
OFFICIAL RECORD
CITY SECRETARY
FT. WORTH, TX
Project: East 1st Street Bridge Improvements
Project# 100575
Summary Highway:
;; -1 K. Import Millings to Grade Trail Date: 08-Jan-21
COR Number: 4
Item Description QTY UM Unit Price Amount
1 Import Millings to Grade Trail 62.000 LID $ 203.985 $ 12,647.07
Total $ 12,647.07
Page 1 of 1 11812021 10:02 AM
Force Account Daily Time and Material
City The Ctiy of Fort Worth Project East 1st Street Bridge Improvements Control Highway
Description of Work: Import Millings to Grade Trail
Date: 11812021__
- -
EQUIPMENT Labor ,
Description Hrs Rate Amount -Hours '� ate Amount
Reg. O.T. Reg.�T.
Volvo L-90 Loader '30.00J$ 67.65 $ 2,029.50 Loader Operator 24.00 6.00 $ 21.00 I$ 31.5.0 $ 693.00
$ $
- $ $ $
$ $ $ _
Sub-Total $ 2,029.50 Sub-Total $ 693.00
15% $ 304.43 (INSURANCES AND TAXES) 55% $ 381.15
Total Equipment: $ 2,333.93 25% $ 173.25
Total Labor: $ 1,247.40
Material-Supply Subcontract
_
Description Quantity UOM Rate Amount Quantity UOM Rate Amount
-- -
$ Trucking 62.00 LD $ 135,00 8,370.00
$ $
$ $
$ $
$ $
Sub-Total $ Sub-Total $ 8,370.00
15% $ 5% $ 418.50
Total Material:1$ Total Subcontract: $ 8,788.50
Summary
Approved:Brad Caldwell Date 01/08/21 Labor 1,247.40
Ft.Worth Civil Constructors E ui ment $ 2,333.93
Dale Material $
The City of Fort Worth Subcontract $ 8,788.50
Bond 1% $ 277.24
CORP 4 jTotaI This Sheet 12,8 7.77
1/8/2021 10:02 AM
EquipmentWatch_
www.equipmentwatch.com
All prices shown in US dollars($)
Rental Rate Blue Book@ January 15,2020
Volvo L90H
4-Wd Articulated Wheel Loaders
Size Class: m
175-199HP
Weight: t, r
HP T n
Configuration for L90H
Bucket Capacity-Heaped 2.7-9.2 cu yd Net Horsepower 184.0 hp
Operator Protection ROPS/FOPS Power Mode Diesel
Blue Book Rates
FHWA Rate is equal to the monthly ownership cost divided by 176 plus the hourly estimated operating cost.
Ownership Costs Estimated FHWA Rate—
Operating Costs
Monthly Weekly Daily Hourly Hourly Hourly
Published Rates USD$6,370.00 USD$1,785.00 USD$445.00 USD$67.00 USD$35.47 USD$71.66
Adjustments
Region(Texas: 88.9%) (USD$707.07) (USD$198.13) (USD$49.40) (USD$7.44)
Model Year
(2020: 100%)
Adjusted Hourly - -
Ownership Cost(100%)
Hourly Operating Cost(100%)
Total: USD$5,662.93 USD$1,586.86 USD$395.61 USD$59.56 USD$35.47 USD$67.65
Non-Active Use Rates Hourly
Standby Rate USD$20.27
Idling Rate USD$50.31
Rate Element Allocation
Element Percentage Value
Depreciation(ownership) 41% USD$2,611.70/mo
Overhaul(ownership) 37% USD$2,356.90/mo
CFC(ownership) 12% USD$764.40/mo
Indirect(ownership) 10% USD$637.00/mo
Fuel(operating)@ USD 3.07 51% USD$18.13/hr
Revised Date: 1st half 2020
These are the most accurate rates for the selected Revision Date(s). However,due to more frequent online updates,these rates may not match
Rental Rate Blue Book Print.Visit the Cost Recovery Product Guide on our Help page for more information.
All material herein @ 2003-2020 Inforrna All rights reserved.
Can you please send me a
load price on hauling
millings for our yard at
48.60 Mark IV Parkway in
Ft. Worth to the intersection
of East 1st Street and
Gateway Park in Ft. Worth.
Looking at probably 60
loads using end dumps
W
FORT WORTH CIVIL CONSTRUCTORS, LLC
f
`S•
12.15.2020
To: Mr. Carlos Gonzalez
City of Fort Worth
Parks& Recreation Department
4200 South Freeway#2200
Fort Worth,TX 76115
Re: East 111 Street Bridge Improvements-Painting
Mr. Gonzalez,
Please find below Fort Worth Civil Constructors, LLC(FWCC) proposal for the painting of the bridge as discussed on site
on December 91h, 2020. Per the onsite meeting,our proposal includes the following:
• Full overcoat of the outside beam facing East 1"Street(north)
• Full overcoat of all handrail
• Touch up paint on the outside beam (south) and the beams and bracing underneath the bridge up to 450 SF
All areas to be painted will be solvent cleaned, hand tooled, and primed.
Painting as Described Above 1 LS $87,500.00 $87,500.00
Clean & Paint Superstructure(System 1A touch-up) -1 LS ($44,000.00) ($44,000.00)
Clean & Paint Railing(System 1A touch-up) -1 LS ($10,000.00) ($10,000.00)
Clean & Paint New Railing(System II clean & paint) -1 LS ($1,120.00) ($1,120.00)
Please let me know if you have any questions or would like to discuss further.
Respectfully,
5'1�j �"
Brad Caldwell
Project Manager
Cc: Project File
(0) 817. 562. 2292 1 (F) 817. 562. 2293 1 www.FWCivCon.com
Office: 4860 Mark IV Parkway, Fort Worth, TX 76106 1 Mail: P.O. Box 164513, Fort Worth, TX 76161
lic° 3359
car bolineo Carboc�
coatings-Linings-Fireproofing PRODUCT DATA SHEET
SELECTION & SPECIFICATION DATA
Generic Type I Waterborne Acrylic
Description Versatile high performance finish with excellent corrosion resistance and exterior weathering
properties.
• Multi-purpose interior/exterior coating
• Excellent color and gloss retention
Features Single component
• Outstanding corrosion protection
• Low odor, low VOC
• Acceptable for use in USDA facilities
Color I Refer to Carboline Color Guide. Certain colors may require multiple coats to hide.
Finish I Semi-Gloss
Acrylics,Alkyds, Epoxies, Inorganic and Organic Zincs and others as recommended under
Primer Substrates&Surface Preparation.A mist coat may be required to minimize bubbling over Inorganic
Zinc primers.
2-3 mils(51 -76 microns) per coat
Dry Film Thickness
Do not exceed 3.0 mils in a single coat
Solids Content I By Volume 37%+/-2%
593 ft2/gal at 1.0 mils (14.6 m2/I at 25 microns)
Theoretical Coverage 297 ft2/gal at 2.0 mils (7.3 m2/I at 50 microns)
Rate 198 ft2/gal at 3.0 mils (4.9 m2/I at 75 microns)
Allow for loss in mixing and application.
As Supplied : 0.5 Ibs/gal (60 gA)
VOC Values These are nominal values and may vary slightly with color.
EPA Method 24: 1.1 Ibs/gal(132 gA)
(Calculated minus water and exempt solvents)
Continuous: 235'F(113'C)
Dry Temp. Resistance Non-Continuous: 325'F (163'C)
Slight discoloration and loss of gloss is observed above 200 F (93 C).
Limitations I Apply and cure at temperatures of 50'F and above for 24 hours.
SUBSTRATES & SURFACE PREPARATION
General Surfaces must be clean and dry. Employ adequate methods to remove dirt, dust, oil and all other
contaminants that could interfere with adhesion of the coating.
SSPC-SP6 with a 1.0-2.0 mil (25-50 micron)surface profile for maximum protection. SSPC-SP2
Steel or SP3 as minimum requirement. Prime with specific Carboline primers as recommended by your
Carboline Sales Representative.
August 2018 0263 Page 1 of 4
Carbocrylic° 3359 carbohne
PRODUCT DATA SHEET coating_S-rtnrngr-Ft,epYoofng
SUBSTRATES & SURFACE PREPARATION
Galvanized Steel SSPC-SP1. Prime with Carbocrylic®120 or others as recommended by your Carboline Sales
Representative.
Concrete: Must be cured 28 days at 75°F (24°C)and 50% relative humidity or equivalent.
Laitance,form oils, curing agents and hardeners must be removed by suitable method before
Concrete or CMU coating application. Prime with Carbocrylic 120.'
CMU: Mortar joints should be thoroughly cured for a minimum of 15 days at 75°F (24°C)and 50%
relative humidity or equivalent. Prime with a latex block filler.
Drywall &Plaster Joint compound and plaster should be fully cured prior to coating application. Prime with
Carbocrylic 120.
Previously Painted Lightly sand or abrade to roughen surface and degloss the surface. Existing paint must attain
Surfaces a minimum 3A rating in accordance with ASTM D3359"X-Scribe"adhesion test. Prime with
Carbocrylic 120 or others as recommended by your Carboline Sales Representative.
Wood I Lightly sand with fine sandpaper and remove dust. Prime with Carbocrylic 120.
PVC Remove all oils, grease, and dirt. Prepare surface by light sanding/abrading to degloss and provide
anchor profile.
PERFORMANCE DATA
All test data was generated under laboratory conditions. Field testing results may vary.
Test Method System Results
Blasted Steel No blistering, rusting or rust
ASTM B117 Salt Fog 1 ct. IOZ creepage at scribe after 1500 hours
1 ct.3359
ASTM D1653 Water Vapor Transmission 1 ct.3359 Water Vapor Permeance
(WVP)of 3.94 U.S. Perms
Blasted Steel
ASTM D3359 Adhesion 1 ct 3358 5A
1 ct 3359
ASTM D3363 Pencil Hardness 1 ct. Acrylic Pr. 5B
2 cts. 3359
ASTM D4060 Abrasion 1 ct. Acrylic Pr.2 cts. 3359 185 mg. loss.3000 cycles, CS10 Wheel
ASTM D4213 Scrub Resistance 1 ct.3359 .0235/.0655 Microliters per 100
cycles Wet/Dry Film Volume
ASTM D4541 Adhesion Stainless Steel 1675 psi(Elcometer)
1 ct 3359
ASTM E84 Flame and Smoke 1 ct 3358 Flame 10 Smoke 20 Class A
1 ct.3359
Test reports and additional data available upon written request.
MIXING & THINNING
Mixing I Power mix until uniform in consistency.Avoid excessive air entrapment.
August 2018 0263 Page 2 of 4
lic® 3359
car bolineo Carboc�
coatings-Linings-Fireproofing PRODUCT DATA SHEET
MIXING & THINNING
May be thinned up to 6 oz/gal(5%)with clean, potable water. Areas with cool substrate and warm
ambient conditions can experience a surface skinning and separation. Under these conditions, the
Thinning use of 6-12 oz/gal (5-10%) of Additive 102 assists in the proper film formation at the recommended
dry film thickness,without surface skinning. Use of thinners other than those supplied by Carboline
may adversely affect product performance and void product warranty,whether expressed or
implied.
APPLICATION EQUIPMENT GUIDELINES
Listed below are general equipment guidelines for the application of this product.Job site conditions may require modifications
to these guidelines to achieve the desired results.
Spray Application Pre-rinse equipment with undiluted Carboline Surface Cleaner 3 followed by clean potable water
(General) before spraying.The following spray equipment has been found suitable and is available from
manufacturers such as Binks, DeVilbiss and Graco.
Conventional Spray Pressure pot equipped with dual regulators, '/z' I.D. minimum material hose, .086" I.D.fluid tip and
appropriate air cap.
Pump Ratio: 30:1 (min.)*
Pump Ratio:45:1 for two or more guns
GPM Output: 3.0(min.)
Material Hose: 3/8" I.D. (min.)
Airless Spray Tip Size: .017-.019"
Output PSI: 1800-2100
Filter Size: 60 mesh
*Teflon packings are recommended and available from the pump manufacturer. For ease of
application, remove the pickup tube and immerse the lower unit directly into the material.
Brush &Roller Multiple coats may be required to achieve desired appearance, hiding and recommended dry film
(General) thickness.Avoid excessive re-brushing or re-rolling.
Brush I Use a synthetic bristle brush.
Roller Use a short-nap synthetic roller cover with phenolic core. For rough surfaces, use a 3/8"woven nap
synthetic roller.
APPLICATION CONDITIONS
Condition Material Surface Ambient Humidity
Minimum 50°F (10°C) 50°F(10°C) 50°F(10°C) 0%
Maximum 105°F (41°C) 130°F (54°C) 110°F (43-C) 85%
Do not apply when the surface temperature is less than 5'F(3'C)above the dew point. Do not apply if temperatures are
expected to drop below 50°F (10°C)within 24 hours of application.Special application techniques may be required above
or below normal application conditions.
August 2018 0263 Page 3 of 4
Carbocrylic° 3359 carbohne
PRODUCT DATA SHEET coating_S-rtnrngr-Ft,epYoofng
CURING SCHEDULE
Surface Temp. Dry to Handle Dry to Topcoat
50°F (10°C) 3 Hours 3 Hours
75°F (24°C) 2 Hours 2 Hours
90°F (32°C) 1 Hour 1 Hour
These times are based on a 2.0-3.0 mil (50-75 micron)dry film thickness. Higher film thicknesses, insufficient ventilation, high
humidity or cooler temperatures will require longer cure times.
The acrylic film forming process may require several weeks at 75°F (24°C)with proper ventilation to develop adhesion and water
resistance. High humidity, high film thickness, insufficient ventilation or cooler temperatures will lengthen the Dry to Handle and
Dry to Topcoat times due to slower water evaporation rate.Waterborne acrylics are sensitive to moisture during early cure and are
susceptible to handling damage.
CLEANUP & SAFETY
Cleanup Use clean potable water followed with suitable solvent to dry equipment. In case of spillage, absorb
and dispose of in accordance with local applicable regulations.
Read and follow all caution statements on this product data sheet and on the SIDS for this product.
Safety Employ normal workmanlike safety precautions. Use adequate ventilation. Keep container closed
when not in use.
PACKAGING, HANDLING & STORAGE
36 months at 75'F (24°C)
Shelf Life *Shelf Life: (actual stated shelf life)when kept at recommended storage conditions and in original
unopened containers.
Storage Temperature& 40'-110°F (4°-43°C)
Humidity 0-95% Relative Humidity
Shipping Weight 1 Gallon- 11 Ibs(5 kg)
(Approximate) 5 Gallons-51 Ibs(23 kg)
50 Gallons-525 Ibs(239 kg)
Flash Point(Setaflash) >200°F (93°C)
WARRANTY
To the best of our knowledge the technical data contained herein is true and accurate on the date of publication and is subject
to change without prior notice. User must contact Carboline Company to verify correctness before specifying or ordering. No
guarantee of accuracy is given or implied.We guarantee our products to conform to Carboline quality control.We assume no
responsibility for coverage, performance, injuries or damages resulting from use. Carbolines sole obligation, if any, is to replace
or refund the purchase price of the Carboline product(s)proven to be defective, at Carbolines option. Carboline shall not be liable
for any loss or damage. NO OTHER WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY CARBOLINE, EXPRESS OR
IMPLIED, STATUTORY, BY OPERATION OF LAW, OR OTHERWISE, INCLUDING MERCHANTABILITY AND FITNESS FOR A
PARTICULAR PURPOSE.All of the trademarks referenced above are the property of Carboline International Corporation unless
otherwise indicated.
August 2018 0263 Page 4 of 4
Carbomastic° 15
car bolineo
coatings-Linings-Fireproofing PRODUCT DATA SHEET
SELECTION & SPECIFICATION DATA
Generic Type I Epoxy mastic
Aluminum-pigmented, low-stress, high-solids mastic with a proven field history. Carbomastic
Description 15 was the pioneer mastic coating in a number of industrial markets and today still provides
unmatched levels of barrier protection and corrosion resistance over existing finishes and rusted or
SSPC-SP2 or SP3-cleaned steel.
• Excellent performance over minimal surface preparation of steel substrates
• Suitable as a topcoat for most tightly adhered existing coatings
• Excellent choice for field touch-up of zinc-rich primers and galvanized steel
Features Unique formulation with aluminum flakes provides exceptional barrier protection
• Available in a low temperature cure version (Carbomastic 15 FC)
• Suitable for use under insulation on hot surfaces operating up to 300 °F(150 °C)
• VOC compliant to current AIM regulations
Aluminum(C901); Red (M500)
Color Color variations within a batch and from batch to batch may occur due to the metallic pigments
and variations in application techniques and conditions.*Red (M500) is available for use as a
contrasting primer in multiple coat applications, but should always be topcoated.
Primer I Self-priming. May be applied over most tightly adhering coatings as well as inorganic zinc primers.
3-5 mils(76- 127 microns) over existing coatings
Dry Film Thickness 7- 10 mils (178-254 microns) in one or two coats in severe exposures
Do not exceed 10.0 mils(250 microns) in a single coat.
Solids Content I By Volume 90%+/-2%
HAPs Values I As supplied: 0.70 Ibs/solid gal
1444 ft2/gal at 1.0 mils (35.4 m2/I at 25 microns)
Theoretical Coverage 481 ft2/gal at 3.0 mils (11.8 m2/I at 75 microns)
Rate 144 ft2/gal at 10.0 mils (3.5 m2/I at 250 microns)
Allow for loss in mixing and application.
Temperature resistance under insulation: Up to 300°F(150°C)
Severe Exposures
Discoloration is observed above 180°F(82"C) but does not affect performance.
As Supplied : 0.7 Ibs/gal (88 gA)
Thinner 10 : 32 oz/gal: 2.0 Ibs/gal (242 g/1)
Thinner 236 E : 32 oz/gal: 0.7 Ibs/gal (88 g/1)
VOC Values Thinner 72 : 32 oz/gal: 2.07 Ibs/gal (248 g/1)
Thinner 76 : 32 oz/gal: 1.9 Ibs/gal (231 g/1)
These are nominal values.
Topcoats I May be coated with Acrylics, Epoxies, Alkyds, or Polyurethanes depending on exposure and need.
April 2020 0185 Page 1 of 5
Carbomastic° 15 Carb01111e®
PRODUCT DATA SHEET coating_S-rtnrngr-Ft,epYoofng
SUBSTRATES & SURFACE PREPARATION
Surfaces must be clean and dry. Employ adequate methods to remove dirt, dust, oil and all other
General contaminants that could interfere with adhesion of the coating in accordance with SSPC-SP 1 and
follow the guidelines below.
Immersion: NACE No.2/SSPC-SP 10 with a 2.0-3.0 mil (50-75 microns)surface profile.
Non-Immersion: NACE No.3/SSPC-SP 6 with a 2.0-3.0 mil (50-75 microns)surface profile for
maximum protection. SSPC-SP 2, SSPC-SP 3, NACE No.4/SSPC-SP 7, NACE/SSPC WJ-1 to
Steel WJ-41or SSPC-SP 14 are also acceptable methods. For alternate methods contact Carboline
Technical Service.
When using under fireproofing products, defer to the primer surface preparation requirements in the
product data sheet of the fireproofing product.
For optimum performance clean and abrade in accordance with SSPC-SP 16.
Galvanized Steel When using under fireproofing products, defer to the primer surface preparation requirements in the
product data sheet of the fireproofing product.
Previously Painted Clean and lightly sand or abrade to roughen and degloss the surface. Existing coating must attain a
Surfaces minimum 3A rating in accordance with ASTM D3359 adhesion test.
PERFORMANCE DATA
All test data was generated under laboratory conditions. Field testing results may vary.
Test Method System Results
ASTM 4060 Taber Abrasion 1 ct. CM15 130 mg loss; 1000 cycles using
CS 17 wheel and 1000 gm load,
ASTM B117 Salt Spray Rusted Steel 1 ct. CM 15 No blistering, rusting, or softening
No rust creep from scribe
ASTM D1735 Water Fog Rusted Steel 1 ct CM 15 No blistering or softening,
No creep from scribe
A) Conical-crack 0.38",
ASTM D522 Flexibility Blasted steel 1 ct. CM15 actual elongation 48.57%
B) Cylindrical-no cracking observed
A) Blasted Steel 1 ct. CM 15, Area Damaged
ASTM G 14 Impact Resistance B) Rusted Steel 1 ct. CM 15 A) 1/4 inch (0.25")
B) 1/4-9/16 inch (0.44")
Test reports and additional data available upon written request.
MIXING & THINNING
Mixing I Power mix separately, then combine and power mix. DO NOT MIX PARTIAL KITS.
May be thinned up to 32 oz/gal (25%)with Thinner 10 for normal conditions. For application
to hot substrates up to 200 °F (93 °C) it is recommended to thin approximately 25%(32 oz/
Thinning gal)with Thinner 230.Thinner 72 may be used for hot or windy conditions. Use Thinner 76 for
nonphotochemically reactive thinner or Thinner 236E for exempt thinner. Use of thinners other than
those recommended and supplied by Carboline may adversely affect product performance and void
product warranty,whether expressed or implied.
Ratio 1 1:1 Ratio (A to B)
April 2020 0185 Page 2 of 5
Carbomastic° 15
car bolineo
coatings-Linings-Fireproofing PRODUCT DATA SHEET
MIXING & THINNING
2 hours @ 75°F (24 °C) unthinned.
Pot Life 1 hour @ 90°F (32 °C) unthinned
Pot life ends when coating becomes too viscous to use
APPLICATION EQUIPMENT GUIDELINES
Listed below are general equipment guidelines for the application of this product.Job site conditions may require modifications
to these guidelines to achieve the desired results.
Spray Application The following spray equipment has been found suitable and is available from manufacturers such
(General) as Binks, DeVilbiss and Graco.
Conventional Spray Pressure pot equipped with dual regulators, 3/8" I.D. minimum material hose,0.086" I.D.fluid tip
and appropriate air cap.
Pump Ratio: 30:1 (min.)*
GPM Output: 3.0(min.)
Material Hose: 3/8" I.D. (min.)
Airless Spray Tip Size: 0.019-0.025"
Output PSI: 1900-2100
Filter Size: 60 mesh
*PTFE packings are recommended and available from the pump manufacturer.
Plural Component May be applied by plural component spray equipment. Contact Carboline Technical Service for
specific recommendations.
Brush &Roller Multiple coats may be required to obtain desired appearance, recommended dry film thickness
(General) and adequate hiding. Avoid excessive re-brushing or rerolling. Use clean natural bristle brush or
medium nap phenolic core roller.Work coating into all irregularities.
APPLICATION CONDITIONS
Condition Material Surface Ambient Humidity
Minimum 50°F (10°C) 50°F(10°C) 50°F(10°C) 0%
Maximum 90°F (32°C) 200°F (93°C) 100°F (38°C) 95%
This product simply requires the substrate temperature to be above the dew point. Condensation due to substrate temperatures
below the dew point can cause flash rusting on prepared steel and interfere with proper adhesion to the substrate. Special
application techniques and/or thinning may be required for application when conditions are above and below normal application
conditions.
April 2020 0185 Page 3 of 5
Carbomastic° 15 Carb01111e®
PRODUCT DATA SHEET coating_S-rtnrngr-Ft,epYoofng
CURING SCHEDULE
Surface Temp. Final Cure Immersion Dry to Recoat or Topcoat
50-F (10-C) 15 Days 5 Days
60-F (16-C) 10 Days 3 Days
75-F (24-C) 5 Days 24 Hours
90-F (32-C) 3 Days 18 Hours
For CM 15 Dry to Touch is 5 hours at 75'F (24°C). Maximum re-coat/topcoat times are 30 days for epoxies and 90 days for
polyurethanes at 75°F (24°C).
*These times are based on a 5.0-7.0 mil (125-175 micron)dry film thickness. Higher film thickness, insufficient ventilation or cooler
temperatures will require longer cure times and could result in solvent entrapment and premature failure. Excessive humidity or
condensation on the surface during curing can interfere with the cure, can cause discoloration and may result in a surface haze.
Any haze or blush must be removed by water washing before recoating. Recoat intervals may vary from those listed above when
using under intumescent fireproofing products. Consult Carboline Technical Service for recommended cure times before applying
Carboline intumescent products. If the maximum recoat time is exceeded,the surface must be abraded by sweep blasting prior to
the application of additional coats. Note:This product contains conductive pigments and cannot be holiday tested.
CLEANUP & SAFETY
Cleanup Use Thinner 2 or Acetone. In case of spillage, absorb and dispose of in accordance with local
applicable regulations.
Read and follow all caution statements on this product data sheet and on the SDS for this product.
Safety Employ normal workmanlike safety precautions. Use adequate ventilation. Keep container closed
when not in use.
When used as a tank lining or in enclosed areas,thorough air circulation must be used during and
after application until the coating is cured.The ventilation system should be capable of preventing
Ventilation the solvent vapor concentration from reaching the lower explosion limit for the solvents used. In
addition to ensuring proper ventilation, appropriate respirators must be used by all application
personnel.
PACKAGING, HANDLING & STORAGE
Part A&B: Min.36 months at 75°F(24°C)
Shelf Life *Shelf Life : (actual stated shelf life)when kept at recommended storage conditions and in original
unopened containers.
Storage Temperature& 45'- 110°F (7-43°C)
Humidity 0-90% Relative Humidity
Store Indoors.
Storage This product is solvent based and not affected by excursions below these published storage
temperatures, down to 10°F, for a duration of no more than 14 days.Always inspect the product
prior to use to make sure it is smooth and homogeneous when properly mixed.
Shipping Weight 2 Gallon Kit-25 Ibs(11 kg)
(Approximate) 10 Gallon Kit- 124 Ibs(56 kg)
Flash Point(Setaflash) Part A: >200°F (93°C)
Part B: 76°F (24°C)
April 2020 0185 Page 4 of 5
Carbomastic° 15
car bolineo
coatings-Linings-Fireproofing PRODUCT DATA SHEET
WARRANTY
To the best of our knowledge the technical data contained herein is true and accurate on the date of publication and is subject
to change without prior notice. User must contact Carboline Company to verify correctness before specifying or ordering. No
guarantee of accuracy is given or implied.We guarantee our products to conform to Carboline quality control.We assume no
responsibility for coverage, performance, injuries or damages resulting from use. Carbolines sole obligation, if any, is to replace
or refund the purchase price of the Carboline product(s)proven to be defective, at Carbolines option. Carboline shall not be liable
for any loss or damage. NO OTHER WARRANTY OR GUARANTEE OF ANY KIND IS MADE BY CARBOLINE, EXPRESS OR
IMPLIED, STATUTORY, BY OPERATION OF LAW, OR OTHERWISE, INCLUDING MERCHANTABILITY AND FITNESS FOR A
PARTICULAR PURPOSE.All of the trademarks referenced above are the property of Carboline International Corporation unless
otherwise indicated.
April 2020 0185 Page 5 of 5
East 1 St Street Bridge Improvements Form 03.17
Site Speciffic Work Plan
Steel Painting
GC:
Project Name: East 1st Street Bridge Improvements Project No. Job#776
Owner: City Of Ft Worth Contact: Brad Caldwell
Phone No.: Fax:
Address: City/State: Ft Worth Texas
Supervisor/Competent Person: Clay Bennett Date: 12/15/2020
Crew Size: 3-4 Job Categories: Spot Cleaning And Overcoating
Project Description
All areas to be painted will receive a solvent cleaning SSPC SP-1.
Next these areas will be hand tooled per SSPC SP-2. These areas will be primed with CM-15 from Carboline.
. The final topcoat will be applied over primed areas to match existing forest green.
We will spot paint 450 sf of rusted areas then overcoat all hand rail and northern beam only.
Schedule: 3-4 weeks depending on weather.
PART 1- PAINT REPAIR PLAN &COATINGS SPECIFIED (See at. QC Plan form 01.27)
DESCRIBE REPAIR PLAN: Any areas that needs to be repaired will be cleaned per SSPC-SP11 to sound
paint. The required coating will then be applied as per specs.Areas that may have runs, sags, or other surface
in-conformities will be buffed with sanding pads&repainted with required paint.
DESCRIBE COATINGS SYSTEM: System 1A alluminum mastic primer and acrylic finish coat.
Page 1 of 8 Form 03.17
PART 2- EMERGENCY CONTINGENCY PLAN
DESCRIBE EMERGENCY RESPONSE AT WORK SITE Supervisor personnel are trained in First Aid with Red Cross.
Minor accidents will be treated at site, and then transported to medical facility if required.
If major accident, emergency personnel will be called, 911. General Contractor awill be. Notified.
PART 3-WORKER PROTECTION PLAN
DESCRIBE ACTIVITIES EMITTING LEAD ON THIS WORKSITE: NONE NA
ENGINEERING CONTROLS(List all equipment that will be used to achieve compliance for this worksite):
Per 446 a modified containment using hepa shrouded tools and vaccuum to collect loose paint and rust.
ALTERNATIVE TECHNOLOGIES CONSIDERED: None
Page 2 of 8 Form 03.17
ADMINISTRATIVE CONTROL SCHEDULE(if applicable): NA
PERSONAL PROTECTIVE EQUIPMENT REQUIRED FOR THIS WORK SITE:
Respirator type by Job Category: half mask respirators
Protective Clothing by Job Category: Gloves, disposable suits, blast coveralls, safety glasses,
ear plugs.
Disposal of Laundry Arrangements: Coveralls and Tyvek suits will be disposed of with other non hazzardous
waste.
HYGIENE FACILITIES
Describe: Hand wash. HEPA vacuum for dust removal on personnel.
Location: Outside regulated area.
Decontamination Sequence:
Beginning of Shift: NA
Breaks/Lunch: NA
End of Day: NA
Page 3 of 8 Form 03.17
Wastewater Handling Arrangements: NONE
Biological Monitoring: NA
Worker Exposure Monitoring:
Training: Respirator training, worker protection plan, environmental
compliance and waste management program.
PART 4-ENVIRONMENTAL COMPLIANCE PLAN (additional information on form 03.24)
REGULATED AREA:
Will the regulated area be invoked on this project? yes x no
If yes, describe who,what,when, and why.
Keep unauthorized people out of area.
ACCEPTANCE CRITERIA
NA
VISIBLE EMISSION:
Will visible emissions assessments be performed on this project? yes x no
If yes, describe who,what,where,when and why. NA
ACCEPTANCE CRITERIA
NA
Page 4 of 8 Form 03.17
Page 5 of 8 Form 03.17
AMBIENT AIR QUALITY:
Will ambient air monitoring be performed on this project? X yes no
If yes, describe who,what,where,when, and why.
QC, to show painting conditions are met.
ACCEPTANCE CRITERIA
Per product DATA sheets.
SOIL QUALITY:
Will soil sampling be performed on this project? yes X no
ACCEPTANCE CRITERIA
NA
WATER/SEDIMENT QUALITY ASSESSMENT:
Will water sampling be performed on this project? yes X no
Will sediment sampling be performed on this project? yes X no
If yes, describe who,what when,where, and why.
ACCEPTANCE CRITERIA
NA
Page 6 of 8 Form 03.17
ACCEPTANCE CRITERIA
NA
RELEASE REPORTING:
Describe release reporting procedures used on this work site.
If over 10 lbs. lead, call TXDOT and Natural Response Center(800-4245-8802), and local emergency
personnel.
PART 5-WASTE MANAGEMENT PLAN (see additional information on form 03.24)
WASTE SAMPLING AND TESTING
Will waste sampling and testing be required? yes x no
If yes, by whom? Owner Contractor X
If performed by contractor, describe method and procedures.
NA
COLLECTION, HANDLING AND STORAGE REQUIREMENTS
Describe how the collection, handling, and storage requirements will be met for this work site.
All Non Hazzardous waste will be collected and properly stored and then disposed.
TRANSPORTATION AND DISPOSAL:
Describe how transportation and disposal requirements will be met for this work site.
If waste is classified as hazardous waste, it will be transported by licensed transport to licensed hazardous
landfill facility.
Page 7 of 8 Form 03.17
CLEARANCE TESTING:
Will clearance testing be required for this work site? yes x no
If yes, describe test method,frequency, location, etc.
NA
MISCELLANEOUS DETAILS OR SUBMITTALS:
Paint submittals Steel: Carbomastic CM-15 followed by Carbocrylic 3359 Acrylic Finish Coat
Signature: Signature:
Email: allison.tidwell@fortworthtexas.gov Email: Vania.Soto@fortworthtexas.gov
Page 8 of 8 Form 03.17