Change Order Request
Project Namel Village Creek Chlorine Enclosure City Sec No. 51447
Project No.(s) P227/56007 070SF30WF80 City Proj.No, CO2273
Project Description: Enclosure of the Gaseous Chlorine and Sulfur Dioxide Storage Facilitie
Contractor: Crescent Constructor, Inc. Change Order: 0 Date: 1/21/2021
City Project Mgr.1 Seiavash Mir City Inspector: Nathan Gray
Phone Number:1 817-392-8404 Phone Number: 817-991-0629
Dept. Sewer Totals Contract Time
(Calender days)
Original Contract Amount $8,573,000.00 $8,573,000.00 480
Extras to Date $65,000.00 $65,000.00 140
Credits to Date
Pending Change Orders(in M&C Process)
Contract Cost to Date $8,638,000.00 $8,638,000.00 620
Amount of Proposed Change Order $18,057.00 $18,057.00 242
Revised Contract Amount $8,656,057.00 $8,656,057.00 862
Original Funds Available for Change Orders $257,000.00 $257,000.00
Remaining Funds Available for this CO $192,000.00 $192,000.00
Additional Funding(if necessary)
CHANGE ORDERS to DATE(INCLUDING THIS ONE)AS%OF ORIGINAL CONTRACT 0.97%
MAXALLOWABLE CONTRACT AMOUNT(ORIGINAL CONTRACT COST+25%) $10,716,250.00
JUSTIFICATION(REASONS) FOR CHANGE ORDER
Change Order No. 3 will provide for the following:
.Addition of Brick Ledge angle to support high roof brick veneer (RFI 35)
-Connecting evaporator steam vents to the drain system to allow condensate to drain (RFI 36) (8 Locations)
-Re-configuration of evaporator steam exhaust lines to exit building (Plant Request) (8 Locations)
.Modifications to the existing PVC lines to level up the pipe lines due to differential settlement of the existing CL2 pipe
rack
-Addition of purflex connectors to existing Box E Remote Ejector Lines (RFI 38) (2 EA)
-The deletion of pay item quantities that are no longer needed on the project
Staff recommends the addition of 242 calendar days to the project for the change order.
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment
in full(both time and money)for all costs arising out of,or incidental to,the above Change Order.
Contractor's Company Name Contractor Name Qqntractor,SLanature Date
Crescent Constructor, Inc. Ryan Glanz,P,.E. �`� I Z/ZI 2Z)
Inspector Date ProJect Mana a Date
Nathan Gray Z 1/21/2021 Seiavash Mira-az2 1/21/2021
Director(Water Dept) Date Construction Manager(Carollo Date
Chris Harder, P.EO&dA a&6&rFeb 4,2021 Troy Laman, P.E.
r. 1/21/2021
Assistant City Attorney Dale Assistant City Manager f Date
Doug Blac -r—M �1: 0 Feb 4,2021 Dana Burghdoff°tea B�S�rab`gym �« Feb 4 2021
Council Action(If Required) OFFICIAL RECORD
M&C Number N/A M&C Date Approved N/A CITY SECRETARY
FT.WORTH,TX
FORT WORTH City of Fort Worth
Change Order Additions
Project Name Village Creek Chlorine Enclosure City Sec No. 1 51447
Project No.(s) P227/56007 070SF30WF80 I I City Proj.No. CO2273
Project Village Creek WRF Liquid Biosolids Storage Tank
Description
Contractor Crescent Constructor, Inc. Change Order: 0 Date: 12/21/2020
City Project Mgr. Seiavash Mir City Inspector Nathan Gray
ADDITIONS
ITEM DESCRIPTION DEPT Qty Unit Unit Cost Total
3.1 BRICK LEDGE ANGLE ADDED Sewer 1.00 LS $5,000.00 $5,000.00
3.2 EVAPORATOR STEAM DRAIN LINES ADDED AND EXTENDED Sewer 8.00 EA $625.00 $5,000.00
3.3 EVAPORATOR STEAM EXHAUST LINES EXTENDED Sewer 8.00 EA $1,325.00 $10,600.00
3.4 CL2 PIPE RACK DIFFERENTAL SETTLEMENT PVC LINES ADDED Sewer 17.00 EA $200.00 $3,400.00
3.5 ADD PURFLEX CONNECTORS TO BOX E EJECTOR LINES Sewer 2.00 EA $3,000.00 $6,000.00
Sewer $30,000.00
Additions Sub Total $30,000.00
FORT WORTH City of Fort Worth
Change Order Deletions
Project Name Village Creek Chlorine Enclosure City Sec No, 51447
Project No.(s) P227/56007 070SF30VVF80 DOE No. City Proj. No. I CO2273
Project Description Enclosure of the Gaseous Chlorine and Sulfur Dioxide Storage Facilitie
Contractor Crescent Constructor,Inc. Change Order: I -3 I Date[ 12/21/2020
City Project Mgr, Seiavash Mir City Inspector L Nathan Gray
DELETIONS
ITEM DESCRIPTION DEPT Qty JUnIt Unit Cost JTotal
3.7 DELETE 6°PAVING EXISTING TANK AREA Sewer -101.00 ISY $75.00 -$7,575.00
3.8 DELETE EVAPORATOR DISCONNECTS Sewer -8.00 EA $546.00 -$4,368.00
Sewer -$11,943.00
Deletions Sub Total -$11,943.00
WWBE Breakdown for this Change Order
MWBE Sub Type of Service Amount for this CO
Total $0.00
Previous Change Orders
Co# DATE AMOUNT
Total $0.00
Contract Compliance Manager
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements,
Signature
1
Seiavash Mir
Name of Employee
Project Manager
Title
,CYp�°FORT d
ATTEST: p�o '?,i` I
A�° o�1d
�v� °
Ovg o=�
Mary J. Kayser a a�°!°°°°°5°q 1
City Secretary 11�nEXA�a
I
OFFICIAL RECORD
CITY SECRETARY
FT.WORTH,TX
2560 Technology Drive#400
Plano, TX 75074
CONTRACT MODIFICATION REQUEST: PCM-02rev01
PROJECT: VILLAGE CREEK CHLORINE ENCLOSURE DATE: 12/18/20
PROJECT NO. C51447
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: SEIAVASH MIR
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
6York shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
(1) Addition of Brick Ledge angle to support high roof brick veneer (RFI 35) = $5,000
(2) Connect evaporator steam vents to the drain system to allow condensate to
drain (RFI 36)(8 Locations) = $5,000 ($625/EA)
(3) Re-configure evaporator steam exhaust lines to exit building
(Plant Request 02/10 email)(8 Locations) = $10,600 ($1,325/EA)
(4) Due to differental settlement of the existing C12 pipe rack additional
modifications were needed to the existing PVC lines to level up the pipe lines = $ 3,400 ($200/EA)
(Sheet 101)(17 locations)
(5) Add purflex connectors to existing Box E Remote Ejector Lines (RFI 38)(2 EA) _ $6,000 ($3000/EA)
(6) Rain Days and Covid Impacts (April 2020 - Dec 2020)
TOTAL AMOUNT 1 $ 30,000
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations,and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased By 242 Calendar Days
Decreased
Unchanged
ACCEPTED
City of Fort Worth Date
❑ REJECTED
2560 Technology Drive#400
Plano, TX 75074
CONTRACT MODIFICATION REQUEST: PCM-03
PROJECT: VILLAGE CREEK CHLORINE ENCLOSURE DATE: 12/18/20
PROJECT NO. C51447
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: SEIAVASH MIR
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHILL be attached.
WoNc shall not commence until authorized by the OWNER.
Description of the Proposed Change & Clarifications
Pricing for the following
(A) Delete installation of 6" Paving in the existing tank area. In the Village Creek
electrical improvements project, this new paving is demo'd out
(Delete 101 SY of 6" Concrete Paving x$75.00/SY)(RFI 50) _ ($7,575)
TOTAL AMOUNT 1 $ (7,575)
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order,the time of completion will be:
Increased By 0 Calendar Days
Decreased
Unchanged
ACCEPTED
City of Fort Worth Date
❑ REJECTED
2560 Technology Drive#400
Plano,TX 75074
I
I
CONTRACT MODIFICATION REQUEST: PCM-04
PROJECT: VILLAGE CREEK CHLORINE ENCLOSURE DATE: 12/21/20
PROJECT NO. C51447
ATTENTION: CITY OF FORT WORTH
1000 THROCKMORTON STREET
FORT WORTH, TX 76102
ATTN: SEIAVASH MIR
Attention:
The following change in contract on this project is proposed:
A breakdown of cost SHALL be attached.
6T'ar•k shall not commence until authorized by the O1'NER.
Description of the Proposed Change & Clarifications
Pricing for the following
(1) Deleted new evaporator disconnects (RFI 39)(8 Locations) _ $4,368 ($546/EA)
TOTAL AMOUNT $ (4,368)
Ryan Glanz
Crescent
All work shall be in accordance with the terms, stipulations, and conditions of the
original Contract Documents. If the work herein provided for is Approved by
Change Order, the time of completion will be:
Increased By 0 Calendar Days
Decreased
Unchanged
ACCEPTED
City of Fort Worth Date
❑ REJECTED