HomeMy WebLinkAboutOrdinance 24713-02-2021 ORDINANCE NO.24713-02-2021 AN ORDINANCE ADJUSTING APPROPRIATIONS IN THE WATER AND SEWER COMMERCIAL PAPER FUND BY INCREASING APPROPRIATIONS IN THE AMOUNT OF$1,447,027.00 FOR THE 3RD BARREL PARALLEL SANITARY SEWER TO THE TWIN 90-INCH SEWERS SERVING THE VILLAGE CREEK WASTEWATER TREATMENT PLANT, BANK PROTECTION AT THE VILLAGE CREEK WASTEWATER TREATMENT PLANT AND PIPELINE EROSION ANALYSIS AT FIVE LOW WATER CROSSINGS PROJECT (CITY PROJECT NO. 103128) AND DECREASING APPROPRIATIONS IN THE UNSPECIFIED PROJECT (CITY PROJECT NO. UNSPEC) BY THE SAME AMOUNT; PROVIDING FOR A SEVERABILITY CLAUSE; MAKING THIS ORDINANCE CUMULATIVE OF PRIOR ORDINANCES; REPEALING ALL ORDINANCES IN CONFLICT HEREWITH; AND PROVIDING AN EFFECTIVE DATE. BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF FORT WORTH, TEXAS: SECTION 1. That in addition to those amounts allocated to the various City departments for Fiscal Year 2020-2021 in the Budget of the City Manager,there shall also be adjusted appropriations in the Water and Sewer Commercial Paper Fund by increasing appropriations in the amount of$1,447,027.00 for the 3rd barrel parallel sanitary sewer to the twin 90-inch sewers serving the Village Creek Wastewater Treatment Plant,bank protection at the Village Creek Wastewater Treatment Plant and Pipeline Erosion Analysis at Five Low Water Crossings project(City Project No. 103128)and decreasing appropriations in the Unspecified project(City Project No. UNSPEC)by the same amount. SECTION 2. That should any portion,section or part of a section of this ordinance be declared invalid,inoperative or void for any reason by a court of competent jurisdiction,such decision,opinion or judgment shall in no way impair the remaining portions,sections,or parts of sections of this ordinance,which said remaining provisions shall be and remain in full force and effect. SECTION 3. That this ordinance shall be cumulative of Ordinance 24446-09-2020 and all other ordinances and appropriations amending the same except in those instances where the provisions of this ordinance are in direct conflict with such other ordinances and appropriations,in which instance said conflicting provisions of said prior ordinances and appropriations are hereby expressly repealed. SECTION 4. This ordinance shall take effect upon adoption. APPROVED AS TO FORM AND LEGALITY: (� 6@C/•�i ry1,. , 1 Douglas W Black Mary J.Kayser .............RT� Sr Assistant City Attorney City Secretary ` O� ADOPTED AND EFFECTIVE: February 23,2021 * _ MAYOR AND COUNCIL COMMUNICATION MAP 603 RD B90I NTVC B P EA-F N I ,r +u f TRAMMEL DAVIS RD x ; PEAK FLOW BASIN #2 - lob 1 LEVEE BANK STABILIZATION SPEAK FLOW BASIN #1 SHALLOW , ' :s�,f+, •-,.,, x.. 4, xr ,._ # BANK REPAIR jL '4 •II ..1.1=. t 5t t VILLAGE REEK WATER i TREATMENT-PLANT ---- ` PROPERTY ti G jL *' L � i• { Of - ; FORTWORT � W ity River SL 202i MAYOR AND COUNCIL COMMUNICATION MAP 603 R D B 90 I N TVC B P EA-F N I a w WHEELER ST C _ -i76, y5 _ - # rim -rot : .W4 00 I i 5 LA r� EROSION PROTECTION ? a'40 STUDY ��. I 44 .iT,r..I ♦a k - #it/ �.L - Al FORTWO sL.tf12', • 1 • • . Wn -- ► , 111k a , ._S 14432. � � • K ��jl�t�i����li��i6f�f�ii��li��i�ii�Fi�i��i���,,...,��►s� 14,y4�3f�5{-8yin� �yS 1351t1�,[ ,4yQ� 8in^S=13457A'8m^-,.S 13458yc,�. I , � vJ'+8in 13460 + /17—W"jv' -I�I�iF��Ciifliii�'[lllRili�Mi�iti�� •�!c-fir y ...8in,.S-13461 ` c �N��i�i dMMr, 117C�i�ite ilf� �+yM08 MAN co i 8Fn S-16697 sk �a� en:11lg�ladi��teI 'o tZ -AIM► �A' wMi� �Sin:.S-16690 Arm. ii • �Ali ��lfajh1i���i'� h 'dffJ EROSION PROTECTION 1 STUDY �. O co v t.�y fir, 4 FORTWORTH two" '42in M 253AR* i Wilk limkia " A ' A 1 A • 0 1-�4iflk��wNi`���`+�!fis..=�i ay�.y-�tL !? � I�Si� I� Pli�wiF�rf�fr'�•'�" is' u8in-{S 1{3y4�5tsa�7�f 8irrnyyyyS�]tt1345CCr�8y c W f+�-_iAj�rl�ft�kiY� �1��1��6E1F�6�[ifRl�ikfR�v,v i �!» del kNM14t�wNE�fttRMY'Y�i��-M—W r7 130 cT • �"..; MM 8inT--S 13460rrr� "'ii�iffl�MGfkKittl�ltf6ftM�l�ftltfrl� 9i`M's 8d�� �j, i� �:,� MM�x�I ���wl�p�•�Irdi�t'rwe+ ��+o xT.-�'�� 1'�'',''"�- 8inr' 1.13461 �t x S �� � KifsiitlllkUiCl�llsii�y' i�!!w a6 'i► , IlY{�M � gly �iirwwr- rreikiw'wa3 .: wMMlri ��' � S� IJirEr �� :,�. � � ���� ��,1 i�al3���i� ',� -` � �,w.•;fit Bin S-1s697 �� jt• D�AAA co - • • PROTECTION iv jk J } s�# y¢ ».Y�'^.<.a�C tMM �•� wl.ab. f } N a - v. k f � RTY FORTWO 42fn M. 11111 old t�IwM�rww�iltl�. s:. : MAYOR AND COUNCIL COMMUNICATION MAP 603RDB90INTVCBPEA-FN I loft f• �e7V7. W fill I IArA�lEtil %n Y;ov WI ' .,; � _c V t� � � ., " Z •., t.r �<�€Si�;�:8!PN�� ,:.ftix;_- ��- - � ' Z t O f F x F r ELLIOTT_REEDER RD �,.. . '+zc. ±r v `:r..a. `^s �; ' } ! ^r r•,*_�._ ,T' .,C..�: nt Hew ;.'�;k:«.:^'s:.a�Y w ,..?•,r„•.^P ,u� r��f' t t/i ui� I +� z - y •$3 i y�� - .,.<y. �'M.'S�C:.�-..v..�l",.S` .L',rw '.".n 't i•# 4 !N5't,., 5 9{ "il X4; m, I r.r._.�... .i -.+p-•n."+w+� F,�,, e �! 1,. R' i�}.IWR �,. IAL,1p.I.lrMtl i' � RV." � —� ' t`N.:•' z sr-,.b�`,w"'�� f"!a„+•`�Xiw, a '. fit. s � „o. a,� f!l '•t, �_�- �.�, .vl;� "fig 'Q p u�ff,,'e i...•.i.. 14 •-•q� '1 _ I ,. # ..:: -" u II St 'y „^ se, � T«llrr PROPOSED 3RD BARREL '• Fork Trinity R� ' 120" PARALLEL SANITARY ver., � ? SEWER # A '}�FORT WORT rM W SL 2021 MAYOR AND COUNCIL COMMUNICATION MAP 603RDB90INTVCBPEA-FNI 49 #r / • J — T* ��• -- T 4� w�� g;, 4 CORNHER EE6^AVE x° +. T PURDUEAVE }y} ," EROSION PROTECTION STUDY DARTMOUTH AVE OL G uIF r,. ti •� `. ter C -_ANOTRE DAME AVE #_ TPLANE A11E - I FORTWORT 5L�D?1 MAYOR AND COUNCIL COMMUNICATION MAP 603RDB90INTVCBPEA-FNI IV � yyyy# 1 i 'r l R. }� IPAINTjPONI� TR Al ram.WV ti LLt, -y EROSION PROTECTION _ ►� STUDY Re. Lu -r. t .,i�� 4 Ott lu lb op op r F' FORT WORTH S�2421 City of Fort Worth, Texas Mayor and Council Communication DATE: 02/16/21 M&C FILE NUMBER: M&C 21-0128 LOG NAME: 603RDB901NTVCBPEAP-FNI SUBJECT (CD 3,4,5 and 7)Authorize Execution of an Engineering Agreement in the Amount of$1,001,447.00 with Freese and Nichols,Inc.,for Design of the 31d Barrel Parallel Sanitary Sewer to the Twin 90-inch Sewers Serving the Village Creek Wastewater Treatment Plant,Bank Protection at the Village Creek Wastewater Treatment Plant and Pipeline Erosion Analysis at Five Low Water Crossings Project,Provide for Project Costs for a Total Project Amount of$1,447,027.00,Adopt Resolution and Adopt Appropriation Ordinance RECOMMENDATION: It is recommended that the City Council: 1. Authorize execution of an Engineering Agreement with Freese and Nichols,Inc.,in the amount of$1,001,447.00 for the 3rd Barrel Parallel Sanitary Sewer to the Twin 90-inch Sewers Serving the Village Creek Wastewater Treatment Plant, Bank Protection at the Village Creek Wastewater Treatment Plant and Pipeline Erosion Analysis at Five Low Water Crossings project; 2. Adopt the attached Resolution expressing official intent to reimburse expenditures with proceeds of future debt for the 3rd Barrel Parallel Sanitary Sewer to the Twin 90-inch Sewers Serving the Village Creek Wastewater Treatment Plant,Bank Protection at the Village Creek Wastewater Treatment Plant and Pipeline Erosion Analysis at Five Low Water Crossings project;and 3. Adopt the attached Appropriation Ordinance adjusting appropriations in the Water and Sewer Commercial Paper Fund by increasing appropriations in the amount of$1,447,027.00 for the 3rd Barrel Parallel Sanitary Sewer to the Twin 90-inch Sewers Serving the Village Creek Wastewater Treatment Plant,Bank Protection at the Village Creek Wastewater Treatment Plant and Pipeline Erosion Analysis at Five Low Water Crossings project(City Project No. 103128)and decreasing appropriations in the Unspecified project(City Project No. UNSPEC)by the same amount. DISCUSSION: This Mayor and Council Communication(M&C)is to authorize the preparation of plans and specifications for the construction of 3rd Barrel Parallel Sanitary Sewer to the Twin 90-inch Sewers Serving the Village Creek Wastewater Treatment Plant and Bank Protection at the Village Creek Wastewater Treatment Plant project.In addition,erosion analysis will be conducted at five locations where large water or sanitary sewer mains cross local streams to identify what needs to be done to protect these assets. Freese and Nichols, Inc., proposes to provide all the necessary design services and analysis for the project for a fee of$1,001,447.00.Staff considers the proposed fee to be fair and reasonable for the scope of services proposed. In addition to the contract amount,$445,580.00(Sewer:$384,580.00;Water:$61,000.00)is required for project management,real property acquisition,utility coordination,public outreach,and material testing. This project will have no impact on the Water Department operating budget when complete. Funding for 3rd barrel parallel sanitary sewer,bank protection,and pipeline erosion analysis is depicted below: Fund Existing Additional Project Total* Appropriations Appropriations W&S Commercial $0.00 $1,447,027.00$1,447,027.00 Paper-Fund 56019 Project Total $0.001 $1,447,027.00$1,447,027.00 *Numbers rounded for presentation purposes. This project is anticipated to be included in a future revenue bond issue for the Water&Sewer Fund.Available cash within the Water and Sewer portfolio and the City's portfolio along with the appropriation authority authorized under the Callable Commercial Paper Program(CP)will be used to provide interim financing for this project until debt is issued.Once debt associated with this project is sold,bond proceeds will be used to reimburse the Water and Sewer portfolio and the City's portfolio in accordance with the attached reimbursement resolution.Under federal law,debt must be issued within approximately three years in order for these expenses to be reimbursable.Adoption of the attached resolution does not obligate the City to sell bonds,but preserves the ability of the City to reimburse itself from tax-exempt bond proceeds. M/WBE OFFICE: Freese and Nichols, Inc.,is in compliance with the City's BDE Ordinance by committing to 12 percent SBE participation.The City's SBE goal on this project is 10 percent.. The project is located in COUNCIL DISTRICTS 3,4,5 and 7. FISCAL INFORMATION/CERTIFICATION: The Director of Finance certifies that upon approval of the above recommendations and adoption of the attached appropriation ordinance,funds will be available in the W&S Commercial Paper Fund for the 3rd Main to W Fork Trunk Mains project.Prior to any expenditure being incurred,the Water Department has the responsibility to validate the availability of funds. Submitted for City Manager's Office by: Dana Burghdoff 8018 Originating Business Unit Head: Chris Harder 5020 Additional Information Contact: Pratima Poudyal 6149