HomeMy WebLinkAboutContract 47702-A3 CSC No.47702-A3
AMENDMENT No.3
TO CITY SECRETARY CONTRACT
WHEREAS, the City of Fort Worth (CITY) and Stantec Consulting, Inc. ,
(ENGINEER) made and entered into City Secretary Contract No.47702 (the
CONTRACT) which was authorized by M&C C-2657 on the 29' day of March 2016
in the amount of $989,477 . 00; and
WHEREAS , the CONTRACT was subsequently revised by Amendment No. 1 in
the amount of $228,803. 00 which was authorized by M&C C-28425 on October
10, 2017 and Amendment No. 2 in the amount of $361,720. 00 which was
authorized by M&C C-28842 on September 11, 2018; and
WHEREAS, the CONTRACT involves engineering services for the
following project:
Liquid Biosolids Storage Tank; and.
WHEREAS, it has become necessary to execute Amendment No. 3 to the
CONTRACT to include an increased scope of work and revised fee.
NOW THEREFORE, CITY and ENGINEER, acting herein by and through their
duly authorized representatives, enter into the following agreement, which
amends the CONTRACT:
1.
Article I of the CONTRACT is amended to include the additional
engineering services specified in the proposal attached hereto and
incorporated herein. The cost to City for the additional professional
services to be performed by Engineer totals $40,000. 00.
2 .
Article II of the CONTRACT is amended to provide for an increase in
the fee to be paid to Engineer for all work and services performed under
the Contract, as amended, so that the total fee paid by the City for all
work and services shall be an amount of $1,620,000.00.
3.
All other provisions of the Contract, which are not expressly amended
herein, shall remain in full force and effect.
OFFICIAL RECORD
Page -1- CITY SECRETARY
FT. WORTH, TX
EXECUTED and EFFECTIVE as of the date last written by a signatory, below.
APPROVED:
City of Fort Worth ENGINEER:
Stantec Consulting, Inc.
75aN4,Lu,NgA&6o
Dana Burghdoff( r2,202 9:57 CSC
Dana Burghdoff Alex Visotski
Assistant City Manager Senior Project Manager
Mar 2,2021 02/05/2021
DATE: DATE:
APPROVAL RECOMMENDED:
ChnLftGre�tfa�det
Christopher H rder(Mar 1,202116.42 CST)
Chris Harder, P.E.
Director, Water Department
Contract Compliance Manager:
II
By signing, T acknowledge that I am the person responsible for the monitoring
and administration of this contract, including ensuring all performance and
reporting requirements.
Sei awash Mir
Project Manager
APPROVED AS TO FORM AND LEGALITY: M&C: N/A
Date: N/A
091r, 1295# : N/A
oBlxk(M,2,=109:0CSr)
Douglas W. Black
Senior Assistant City Attorney
ATTEST: 4o1 FORT
A`p�►F°°°°°°°°°o o� i
°
o
0.voo
°2A
Mary J. Kayser d�� o o*Id
lc
City Secretary ���°T°°°°°5 pp'
EX0
`I
!I
OFFICIAL RECORD
Page -2- CITY SECRETARY
FT. WORTH, TX
® Stantec Memo
To: Mir Seiavash From: Alex Visotski
200 Texas St, Fort Worth, TX 76102 12222 Merit Dr. #400 Dallas,TX 75251
File: Contract Amendment 3 Date: February 5,2021
Reference: City of Fort Worth, Contract#47702-Contract Amendment 3
Overview
This proposed contract amendment (Amendment 3) seeks approval for additional scope and
fee for the following activities for the City of Fort Worth (City) Contract No.47702 for the Village
Creek Water Reclamation Facility Storage Tank Improvement project and City Project No.02669:
1. Additional evaluation, analysis, and support due to construction services being
extended and additional documents were submitted for engineering review.
Throughout the construction of the 5MG Biosolids Storage Tank,the additional
engineering services were delivered to meet the need of the facility,which has
exceeded the prior contractual estimates and been prolonged due to weather and
COVIDI9 delays.
2. Recovering Gupta and Associates (GAI) Electrical and I&C additional fees to complete
extra inspections for RLC factory testing, electrical and I&C components of the project.
3. Additional work to complete record drawings.
A summary of Project Fees to Date is provided in Table Number 1 and a summary of each of
Amendment 3 items and the proposed fee adjustment is provided further below.
Table Number 1
Summary of Project Fees to Date
Original Project Fee $989,477.00
Amendment No] $228,803.00
Amendment No2 $361,720.00
Proposed Amendment No3 $40,000.00
Revised Contract Amount $1,620,000.00
Basis for Additional Scope/Fee
For this Amendment 3,STANTEC is seeking an increase in the project NTE by$40,000. A summary
of Amendment 3 request is provided below,
1 of 3
February 5,2021
Mir Seiavash
Page 2 of 3
Reference: City of Fort Worth,Contract#47702-Contract Amendment 3
1, Additional evaluation, analysis, and support due to construction services
Throughout the construction of the 5MG Biosolids Storage Tank,the additional engineering
services were delivered to meet the need of the facility,which has exceeded the prior
contractual estimates and been prolonged due to weather and COVID19 delays.The following
efforts are related to the additional project documentation review, planning and support for the
construction schedule extension which required a further degree of effort and design features
during construction to ensure the final product would meet the plant requirements.
• Additional support for extra punchlist inspections and re-inspections,
• Additional support for monthly progress meetings and project communication,
• Additional site observations,
• Development of checklists,
• Coordination with the contractor and subcontractor,
• Follow up with action items,
• Recording modifications for records,
• Review of additional Pay Apps, RFI's and Submittals,summarized in Table Number 2
I
i
Table Number 2
Pay BFI's Total Submittals
Approved in Contract 18 20 200
Submitted to Date 19 46 253
Additional until Completion 2 3 10
Total assumed in new charge rate 21 49 263
f
Stantec is seeking an additional fee of$26,870 to cover the costs of these activities. ( '
1
2. GAI fees to complete the project „
GAI estimated$4,230 to complete extra inspections for RLC factory testing, electrical and
I&C components of the project (includes the minority subconsultant 10%markup).
3. Additional work to complete record drawings.
The original scope document submitted to the City did not include all the necessary work
to complete the record drawings and did not account for coordinating it with our subs. i
Stantec is seeking an additional fee of$8,900 to cover the costs of these activities,which
also includes Stantec subconsultant contract management costs.
2 of 3
i
ti
February 5,2021
Mir Seiavash
Page 3 of 3
Reference: City of Fort Worth,Contract#47702-Contract Amendment 3
Revised Project Schedule
Assuming a written NTP of Amendment 3 is received by February 10, 2021,the project schedule
will not be affected.
Stantec City of Fort Worth
Alex Visotsid Mir Seiavash
Project Manager Project Manager