HomeMy WebLinkAboutContract 38054-CO6 City of Fort Worth CITY SECRETARY�O (�
Change Order Request CONTRACT NO.
Change Order No. Date TPW Project No. Funding(FAC)
6 (six) 1/31/11 C 295 541200
208090023880
Facility and Project Description City Secretary Contract No.
Nashville Neighborhood Policing District No. 6 38054
ORIGINAL CONTRACT AMOUNT................................................................ $8,216,000
EXTRAS TO DATE..................:...............................................— $ 75,503
CREDITS TO DATE.................................................................... ($19,530)
CONTRACTCOST TO DATE.................................................................................................. $8,271,973
AMOUNT OF PROPOSED CHANGE ORDER............................................................................ $ 14,722
REVISED CONTRACT AMOUNT............................................................................................. $8,286,695
ORIGINAL FUNDS AVAILABLE FOR CHANGE ORDERS............................................................ $ 144,000
REMAINING FUNDS AVAILABLE FOR CHANGE ORDERS......................................................... $ El?
ADDITIONAL FUNDING (IF NECESSARY)................................................................................ 0
IN ACCORDANCE WITH THIS CHANGE ORDER, THE CONTRACTOR SHALL:
Provide all labor and materials as per attached PCR's:
PCR 7—Paint Exterior Plaster add $ 5,115
PCR 74—Add additional vertical blinds add $ 1,471
PCR 76—Add roller shade at window"A" add $ 552
PCR 77 - Add automatic roller shade at front lobby add $ 19,950
PCR 78 Delete lighted handrail and add standard SS rail (deduct) ($ 12,366)
OFFICIAL RECORD
14,722
--------—----------------------- -GMY-510FUM!- --------------------------------------ADD _ $- ----------
FT.WORTH,TX TOTAL ADD $ 14,722
PCR 75 is rejected
It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full(both time
and money)for all costs arising out of,or incidental to,the above Change Order
Contractor's Name
Crossland Construction Company, Inc.
Original Contract Time Additional Approved Time To Date Approved Contract Time To Date Additional Time For This Change Order
430 cd 95 cd 525 cd 0 cd
Contractor
ontract rrossl onstru i n Company Date Construction na Date
Chief,Arch iteK�-z Services Division ,Date f Dir ,tor,Transportation and Public works Date
ProjectAr 'ect!P ns Will ��.pob 7Qate Cit Att Date /
City ManagerCouncil Actlo Date1/8/08
emu° A(U
❑ Approved ' ` REQUIRED
❑ Other
0
cilitiManagement Division 0 8—0 5—1 1 A 0 8 31 M I
Ml yHP.11]m>C1X, secretary" ); rder Form(12/19/01)
CROSSLANDPotential Change Orders
CONSTRUCTION COMPANY, INC, summary,Grouped by Company ID
Fort Worth Police and Traffic Facility#6 Project# 146015.000 Crossland Construction Co.,Inc.
1100 Nashville Ave. Tel: 214-578-0743 Fax: NA
Fort Worth,Texas 76102
item No Description Budget Allocation Estimate Pre o•_•• ' o • • •• App -o •- e o A e 9 p
Eno • -o ll, 11'
a'� i7!n �..� xa.•..�.,,.. '`� ''> �`,.•.;.�u3,�bis�ra,�,i"� �y y v`3y t'.M4:°y�1� c.ua'°" ��t�a '�S i °s �.tis �� "! ° .r ° ,'za.;�-x, ->7�`+rafxtrv+rF ....< •
P: `��.::>+� GEa,�} IM• �IVtFF'. ..�.ii
001 Painting 9,300.00 9,300.00 9,300.00 9,300.00 8/20/2009
Level 001 10.00%Overhead&Profit 930.00 930.00 930.00 930.00
Markup
o5f PG(
Y7-
Proft Manager Printed on: 8/13/2009 Texas Page 1
i
U0II0ILUU7 t3U.Jb 94b4409029 THOMPSON PAGE 01/01
THOMPSON PAINTING
1014 N. Maryland
Carrollton, TX 75006
Ph. (972)242-2661
Fax (972)242-5686
DATE: E Augq§t 10. 2009
TO: Crossland Construction
ATTN: Aaron HOW
RE: Proiosai
We propose to paint the exterior Portland cement plaster @ the FW police
facility#6 for the sum of 19,300.00
Breakdcm. n:
1. 1 coat Accu Shield Primer
2. 2 coats Accu Shield Elastomeric( coverage- 75 sq_ ft. per gallon)
3_ Boorn Rental (1 week)
* No specification on material given
Thompson Painting,
L.H. Thompson
Charles,Thompson (940)440-9029 cell (214)680-6723
Chelly cthomR@rnvway.com
CROSSLAND Potential Change Orders
CONSTRUCTION COMPANY, INC. Summary,Grouped by Company ID
Fort Worth Police and Traffic Facility#6 Project# OBTX09MC Crossland Construction Co.,Inc.
1100 Nashville Ave. Tel: 214-578-0743 Fax: NA
Fort Worth,Texas 76102
Budget Allocation Estimate - -Prop wroved Applied Change Order Quote Due Quote Rec'd
001 Additional Vertical Blinds 1,337.00 1,337.00 1,337.00 1,337.00 10/18/2010
Level 1 10.00%Overhead&Profit 133.70 133.70 133.70 133.70
Markup
Prolog Manager Printed on: 10/11/2010 TEXAS2008 Page 1
Page 111
Tex-Sun Shade & Blind Co. QUOTE
12640 East Northwest Hwy
Suite 413 Date
Dallas, TX 75228 10/6/2010
Tel 972-279-0132 Fax 972-279-0611
www.tex-sun.com Project
mike@tex-sun.com Crossland Change Order#5
FW Police
Prepared By: Mike Wiethorn Addenda
Quantity Description Amount
ALL PRICES INCLUDE INSTALLATION
2 Additional Vertical Blinds in Rooms 122&117 $1,337.00
CROSSLAND Potential Change Orders
CONSTRUCTION COMPANY, INC. Summary, Grouped by Company ID
Fort Worth Police and Traffic Facility#6 Project# 08TX09MC Crossland Construction Co.,Inc.
1100 Nashville Ave. Tel: 214-578-0743 Fax: NA
Fort Worth,Texas 76102
Item No Description Budget • • ••o • P ••—rove—d-----Appliecl Change Order Quote • • -
• • •. • -• •. - i �
001 Roller Shade 502.00 502.00 502.00 502.00 11/10/2010
Level 1 10.00%Overhead&Profit 50.20 50.20 50.20 50.20
Markup
ling
Prolog Manager Printed on: 11/3/2010 TEXAS2008 Page 1
Tex-Sun Shade & Blind Co. QUOTE
12640 East Northwest Hwy
Suite 413 Date
Dallas, TX 75228 11/3/2010
Tel 972-279-0132 Fax 972-279-0611
www.tex-sun.com Project
mike@tex-sun.com Crossland
Police
Prepared By: Mike Wiethorn Addenda
Quantity Description Amount
ALL PRICES INCLUDE INSTALLATION
1 Roller Shade w/Side Channel $502.00
1
I
i
i
i
i
i
i
i
I
i
Not subject to cancellation.Claims for shortage or damage cannot be considered unless reported within 5 days after receipt. �
We cannot accept merchandise returned without our permission.6%interest after 60 days.All bills payable in Dallas,Texas. j
i
CROSSLAND Potential Change Orders
CONSTRUCTION COMPANY, INC. Summary, Grouped by Company ID
Fort Worth Police and Traffic Facility#6 Project# 06TX09MC Crossland Construction Co.,Inc.
1100 Nashville Ave. Tel: 214-578-0743 Fax: NA
Fort Worth,Texas 76102
Item No Description Budget Allocation Estimate — Propol sed �Approved Applied Change Order Quote Due Quote Rec'd
001 Shades&Electrical 18,136.00 18,136.00 113,136.00 18,136.00 11/15/2010
Level 1 10.00%Overhead&Profit 1,813.60 1,813.60 1,813.60 1,813.60
Markup
Prolog Manager Printed on: 11/8/2010 TEXAS2008 Page 1
Tex-Sun Shade & Blind Co. QUOTE
12640 East Northwest Hwy
Suite 413 Date
Dallas, TX 75228 11/5/2010
Tel 972-279-0132 Fax 972-279-0611
www.tex-sun.com Project
mike@tex-sun.com Corssland
FW Police&Traffic
Prepared By: Mike Wiethorn Addenda
Quantity Description Amount
ALL PRICES INCLUDE INSTALLATION
PR 023
5 Motorized Roller Shades in Front Lobby(approx 6'x18') $7,450.00
with Group Controller and Low Voltage Wall Switch and Top Fascia
[side trans not recommended]
for Side Tracks,add$2,250
Scaffolding,installed and removed by Betco Scaffolding $4,300.00
Electrical work performed by Affiliated Electric $4,136.00
Not subject to cancellation.Claims for shortage or damage cannot be considered unless reported within 5 days after receipt.
We cannot accept merchandise returned without our permission.6%interest after 60 days.All bills payable in Dallas,Texas.
CROSSLAND Potential Change Orders
CONSTRUCTION COMPANY, INC. Summary, Grouped by Company ID
Fort Worth Police and Traffic Facility#6 Project# 08TX09MC: Crossland Construction Co.,Inc.
1100 Nashville Ave. Tel: 214-578-0743 Fax: NA
Fort Worth,Texas 76102
Item No Description Budget Allocation Estimate Propq'Qed ppfi�d &"nge Order Quote Due Quote Rec'd-
001 Lighted Rail Deduct (21,142.00) (21,142.00) (21,142.00) (21,142.00)
002 Stainless Handrail Add 9,385.20 9,385.20 9,385.20 9,385.20
Level 1 5.18%Overhead&Profit (606.96) (608.96) (608.96) (608.96)
Markup(Bid Amount)
Prolog Manager Printed on: 1 211 312 01 0 TEXAS2008 Pagel
A&S
1701 BRENNAN AVE 817-626-7720
FORT WORTH, TEXAS 76106 FAX 817-626-0267
Crossland
Attn: Aason Hight
Project: Police Station
Subject: Single Rails
Fab 1 %SST pipe handrail for the east and west stairs'
The above for the sum of $6,812.00 Fab
$1,720.00 Install
$853.20 Profit
Total $9,385.20
Thanks
Steve
THANK YOU
,T&tw,,ra4;c,d
Aaron Hight
From: Michael Kim [mbebrite@yahoo.com]
Sent: Thursday, December 09, 2010 9:54 AM
To: Aaron Hight
Subject: Fw: RE: Lighted Handrail -Fort Worth Police
Dear Aaron,
Please be advised of folloeing breakdown.
1. Hand Rail Light Fixtures: $19,800.00
2. Labor: $1,342.00
Total Deducticle Amount: $21,142.00
Do you need above statement in our Invoice Form as like before?
Thanks,
Michael Kim
Brite Electric, Inc.
11055 Dennis Rd. #17
Dallas, TX 75229
Tel (972) 243-5323
Fax (972) 243-8486
--- On Mon, 12/6/10, Mark Lawless <mlawless(a,,,summit com>wrote:
From: Mark Lawless<rnlawless/,&surrmit.com>
Subject: RE: Lighted Handrail -Fort Worth Police
To: "Michael Kim" <mbebrite(a)yahoo.com>, "Micah Mashek" <mmashek@summit.com>
Date: Monday, December 6, 2010, 3:29 PM
Mr Kim,
We have $19,800 from the original order to give back. This will not be a credit rather lust the
amount we will short bill from the original purchase order.No credit is forthcoming.
Mark
From: Aaron Hight rmailto:ahightacrosslandconstruction.coml
Sent: Monday, December 06, 2010 11:49 AM
To: Michael Kim; Micah Mashek; Mark Lawless
RROJECT ISI I ARY SHEET
(Change Order Attachment)
PROJECT NAME: Nashville Neighborhood Policing District No 6
BuySpeed No: CSCO-09-00052392
Contract No: CS38054
D.O.E. No: N/A
Attachment to Change Order No: 6
Today's Date: 2111111
TOTAL
Original Contract Amount: $ 8;216,000.00
Extras to Date: $ 75,503.00
Credits to Date: $ (19,530.00)
Contract Amount to Date: $ 8,27 1,973.00
Amount of Proposed Change Order: $ 14,722.00
Revised Contract Amount: $ 8,286,695.00
Contingency Funds Avail. for Admin. Change Orders: $ 144,000.00
Remaining Funds Available for Change Orders: $ 73,305.00
Additional Funding (if necessary): $ -
Prepared By: Karen Striker T/PW Business Support
FORT WORTH
Routing & Transmittal Slip
To: Department Initials Date
01 Dalton Murayama TPW �I
02 Glenn F. Balog TPW
03 Karen Stryker TPW (A
04 William A. Verkest, P.E. TPW z
05 Doug Black �z<<I,111cln LAW
06 Fernando Costa ACM
07 Jack Durham TPW
Proiect: NASHVILLE NEIGHBORHOOD POLICING
DISTRICT No. 6
Change Order 6
Remarks: Change Order 6—Provide additional blinds and automatic roller shades as requested by
Police Personnel and add paint at exterior plaster and change interior lighted handrails to standard
stainless steel rails as per the attached PCR's.
M&C is not required.
_Action _File _Note& Return
_Approval _For Clearance Per Conversation
_As Requested _For Correction —Per
Prepare Reply
_Circulate _ For Your Information See Me
_Comment _ Investigate X Signature
_Coordination _Justify _Other
NOTE to CMO: Please call Jack Durham @#392-8072 for pickup upon completion.
TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
ARCHITECTURAL SERVICES SECTION,FACILITIES MANAGEMENT DIVISION
909 Taylor Street, Suite 35 *Fort Worth,TX 76102
Fax 817-871-8488