Construction Allowance Request
Project Name 2018 Bond Street Reconstruction,Conlract 3 City Sec# 53990
Client Project#(s)l 101121
Project A combined street paving improvements and water and sanitary sewer main replacements for 2018 Bond Street Reconstruction Contract 3
Description
Contractor Stabile&Winn,Inc. CA#1 2 Date 12/18/2020
-fly Project Mgr. Kristian Sugrim City Inspectorl Julius IVIC in
UNIT or DEPT Unit I TPW Unit II Water Unit III Sewer Totals Contract Time
CD
Original Contract Amount $1,545,403.50 42,975.00 77,400.00 1,665,778.50 210
Extras to Date 24
Credits to Date 1,545,40
Current Contract Amount �+ca._ 43 $42.975.00 $77,400.00 4473A— 234
mount of—Proposed Allocation 0 .00 $0.00 4, 00.00 "24
65
Original Allowance Available to Allocation 50,000.00 10,000.00 20,000.00 299
Allowance Funds Previously Allocated 26,241.00
Revised Allowance Balance 12,356.00 10,000.00 $15,900.00
JUSTIFICATION(REASONS)FOR CONSTRUCTION ALLOWANCE
IN ACCORDANCE WITH THIS CONSTRUCTION ALLOWANCE REQUEST,THE CONTRACT SHALL: Furnish all labor and material as per attached proposed Construction
Allowance Request: This Construction allowance includes a bid item for installation and removal of approximately 621ons of wash-rock that was applied to the excavated street
segment on Rosita while the franchise utilities,(AT&T and Oncor),worked on relocating their assets,in an effort to Improve drivability for the residents.Also,this allowance
includes a bid item for major adjustment for an existing sanitary sewer manhole at the intersection of Rosita Street and Jean Hills Lane.Staff agrees with the additional time
requested which was caused by franchise utilities relocations delays.
It is understood and agreed that the acceptance of this Construction Allowance Request by the contractor constitutes an accord and
satisfaction and represents payment in full(both time and money)for all costs arising out of,or Incidental to,the above Construction
Allowance Request. The Project/Program Manager signing below acknowledges that he/she is the person responsible for the monitoring and
administration of this contract,including ensuring all performance and reporting requirements.
Contractor's Company Name Contractor Name Contract Signature Date
Stabile&Winn,Inc. Je 7e� HeiAeera Dec 22,2020
Inspector/inspection Supervisor Date Project and Contract Compliance Manager Date
>-/%• ���•�-%�. Dec 23,2020 Krictian. m Dec 23,2020
Program Manager Date Sdrh rCapilal Project Officer Date
.l""'"-_ Dec 23,2020 - Dec 23,2020
Assistant Director(Dept) Date Director,Contracting Department(Dept) Date
n:re ierr Dec 28,2020 :Ll Jam- Dec 28,2020
Assistant City Attorney Date Assistant City Manager Date
Dec 28,2020 Dnna Bu +_{dofF__ Dec 28,2020
A'
O�ko-P.4
000000 �a� ATTEST: Y.i'�OiIGC/,A2r��iDh7.A�f_
p�OO d 'for Ran3'4P.Gav:'_".-3t.301116'.31 CST)
_0 °_0 Mary J.Kayser,City Secretary
° °
0
*% �
oO0000000°° a
daa�nEapSbpp
Construction Allowance SUMMARY OFFICIAL RECORD
Page 1 of 4
CITY SECRETARY
FT. WORTH, TX
FORT WORT11 City of Fort Worth
Construction Allowance Additions
Project Name 2018 Bond Street Reconstruction,Contract 3 Icity Sec# 399
Client Project# 101121
Contractorl Stabile&Winn,Inc. PMJ Kristian Sugrim Inspector Julius McLaurin
Construction Allowance Submittal# 0 Date
ADDITIONS
ITEM DESCRIPTION DEPT Oty Unit Unit Cost Total
1-44 Install&remove wash-rock on Rosita Unit I TPW 1.00000000 LS $11,403.00 $11,403.00
Miscellaneous Structural Adjustment,Hosita Street,S I A 1+3bni ewer
Unit I TPW $11,403.00
Unit II Water $0.00
Unit III Sewer $4,100.00
Total Additions 5,5
Construction Allowance Additions
Page 2 of 4
Construction Allowance Value
FORT WORTH City of Fort Worth
Construction Allowance Value
Project Name 2018 Bond Street Reconstruction Contract 3 City Sec#
Client Project# F 10 1 1121
Contractorl Stabile&Winn,Inc. PM Inspector Julius McLaurin
Construction Allowance Submittal# 0 Date
GONSTRUCTION ALLOWANCE VALUE 6EING USED
ITEM DESCRIPTION Qty Unit Unit Cost Total
1-40 9999.0007 Paving Reconstruction Improvement Allowance 0.228060 LS $50,000.00 $11,403.00
III-15 9999.0006 Sanitary Sewer Improvement Allowance 0.205000 LS $20,000.00 $4,100.00
Construction Allowance Value
3 of 4
MISBE for this Construction Allowance Request
M/SBE Sub Type of Service Amount for this CAR
Total $0.00
Previous Construction Allowance Requests
CAR DATE AMOUNT
Total $0.00
Construction Allowance MSBE Data
Page 4 of 4
Contract Compliance Manager:
By signing I acknowledge that I am the person responsible
for the monitoring and administration of this contract, including
ensuring all performance and reporting requirements.
�..,—
Kristian Su _im /
Name of Employee/Signature
Proiect Manager
Title
❑ This form is N/A as No City Funds are associated with this Contract
Kristian Sugrim / \
Printed Name Signature