HomeMy WebLinkAboutContract 55397 CSC No. 55397
CITY OF FORT WORTH, TEXAS
STANDARD AGREEMENT FOR ENGINEERING RELATED PROFESSIO
SERVICES
This AGREEMENT is between the City of Fort Worth, a Texas home-rule
municipality ("CITY"), and Alan Plummer and Associates, Inc. d/b/a Plummer Associates,
Inc. (PLUMMER) authorized to do business in Texas, ("ENGINEER"), for a PROJECT
generally described as: Design, Bid and Construction Services for the Westcreek Channel
Improvements.
Article I
Scope of Services
The Scope of Services is set forth in Attachment A.
Article II
Compensation and Term of Agreement
A. The ENGINEER's compensation shall be in the amount up to $375,470 as set
forth in Attachment B.
B. Unless otherwise terminated pursuant to Article VI. D. herein, this Agreement
shall be for a term beginning upon the effective date, as described below, and
shall continue until the expiration of the funds or completion of the subject
matter contemplated herein, whichever occurs first.
Article III
Terms of Payment
Payments to the ENGINEER will be made as follows:
A. Invoice and Payment
(1) The Engineer shall provide the City sufficient documentation, including but
not limited to meeting the requirements set forth in Attachment D to this
AGREEMENT, to reasonably substantiate the invoices.
(2) The ENGINEER will issue monthly invoices for all work performed under this
AGREEMENT. Invoices are due and payable within 30 days of receipt.
City of Fort worth,Texas OFFICIAL RECORD
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 1 of 17 CITY SECRETARY
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments Resources
Documents_01-Standard Agreement—Standard Engineering Agreement.doc FT. WORTH, TX
(3) Upon completion of services enumerated in Article I, the final payment of
any balance will be due within 30 days of receipt of the final invoice.
(4) In the event of a disputed or contested billing, only that portion so contested
will be withheld from payment, and the undisputed portion will be paid. The
CITY will exercise reasonableness in contesting any bill or portion thereof.
No interest will accrue on any contested portion of the billing until mutually
resolved.
(5) If the CITY fails to make payment in full to ENGINEER for billings contested
in good faith within 60 days of the amount due, the ENGINEER may, after
giving 7 days' written notice to CITY, suspend services under this
AGREEMENT until paid in full. In the event of suspension of services, the
ENGINEER shall have no liability to CITY for delays or damages caused the
CITY because of such suspension of services.
Article IV
Obligations of the Engineer
Amendments to Article IV, if any, are included in Attachment C.
A. General
The ENGINEER will serve as the CITY's professional engineering
representative under this Agreement, providing professional engineering
consultation and advice and furnishing customary services incidental
thereto.
B. Standard of Care
The ENGINEER shall perform its services:
(1) with the professional skill and care ordinarily provided by competent
engineers practicing in the same or similar locality and under the same or
similar circumstances and professional license; and
(2) as expeditiously as is prudent considering the ordinary professional
skill and care of a competent engineer.
C. Subsurface Investigations
(1) The ENGINEER shall advise the CITY with regard to the necessity for
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 2 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
subcontract work such as special surveys, tests, test borings, or other
subsurface investigations in connection with design and engineering
work to be performed hereunder. The ENGINEER shall also advise
the CITY concerning the results of same. Such surveys, tests, and
investigations shall be furnished by the CITY, unless otherwise
specified in Attachment A.
(2) In soils, foundation, groundwater, and other subsurface investigations,
the actual characteristics may vary significantly between successive
test points and sample intervals and at locations other than where
observations, exploration, and investigations have been made.
Because of the inherent uncertainties in subsurface evaluations,
changed or unanticipated underground conditions may occur that
could affect the total PROJECT cost and/or execution. These
conditions and cost/execution effects are not the responsibility of the
ENGINEER.
D. Preparation of Engineering Drawings
The ENGINEER will provide to the CITY the original drawings of all plans in
ink on reproducible mylar sheets and electronic files in .pdf format, or as
otherwise approved by CITY, which shall become the property of the CITY.
CITY may use such drawings in any manner it desires; provided, however,
that the ENGINEER shall not be liable for the use of such drawings for any
project other than the PROJECT described herein.
E. Engineer's Personnel at Construction Site
(1) The presence or duties of the ENGINEER's personnel at a construction site,
whether as on-site representatives or otherwise, do not make the
ENGINEER or its personnel in any way responsible for those duties that
belong to the CITY and/or the CITY's construction contractors or other
entities, and do not relieve the construction contractors or any other entity of
their obligations, duties, and responsibilities, including, but not limited to, all
construction methods, means, techniques, sequences, and procedures
necessary for coordinating and completing all portions of the construction
work in accordance with the Contract Documents and any health or safety
precautions required by such construction work. The ENGINEER and its
personnel have no authority to exercise any control over any construction
contractor or other entity or their employees in connection with their work or
any health or safety precautions.
(2) Except to the extent of specific site visits expressly detailed and set forth in
Attachment A, the ENGINEER or its personnel shall have no obligation or
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 3 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
responsibility to visit the construction site to become familiar with the
progress or quality of the completed work on the PROJECT or to determine,
in general, if the work on the PROJECT is being performed in a manner
indicating that the PROJECT, when completed, will be in accordance with
the Contract Documents, nor shall anything in the Contract Documents or
this AGREEMENT between CITY and ENGINEER be construed as requiring
ENGINEER to make exhaustive or continuous on-site inspections to
discover latent defects in the work or otherwise check the quality or quantity
of the work on the PROJECT. If the ENGINEER makes on-site
observation(s) of a deviation from the Contract Documents, the ENGINEER
shall inform the CITY.
(3) When professional certification of performance or characteristics of
materials, systems or equipment is reasonably required to perform the
services set forth in the Scope of Services, the ENGINEER shall be entitled
to rely upon such certification to establish materials, systems or equipment
and performance criteria to be required in the Contract Documents.
F. Opinions of Probable Cost, Financial Considerations, and Schedules
(1) The ENGINEER shall provide opinions of probable costs based on the
current available information at the time of preparation, in accordance
with Attachment A.
(2) In providing opinions of cost, financial analyses, economic feasibility
projections, and schedules for the PROJECT, the ENGINEER has no
control over cost or price of labor and materials; unknown or latent
conditions of existing equipment or structures that may affect operation
or maintenance costs; competitive bidding procedures and market
conditions; time or quality of performance by third parties; quality, type,
management, or direction of operating personnel; and other economic
and operational factors that may materially affect the ultimate
PROJECT cost or schedule. Therefore, the ENGINEER makes no
warranty that the CITY's actual PROJECT costs, financial aspects,
economic feasibility, or schedules will not vary from the ENGINEER's
opinions, analyses, projections, or estimates.
G. Construction Progress Payments
Recommendations by the ENGINEER to the CITY for periodic construction
progress payments to the construction contractor will be based on the
ENGINEER's knowledge, information, and belief from selective sampling
and observation that the work has progressed to the point indicated. Such
recommendations do not represent that continuous or detailed examinations
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 4 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
have been made by the ENGINEER to ascertain that the construction
contractor has completed the work in exact accordance with the Contract
Documents; that the final work will be acceptable in all respects; that the
ENGINEER has made an examination to ascertain how or for what purpose
the construction contractor has used the moneys paid; that title to any of the
work, materials, or equipment has passed to the CITY free and clear of liens,
claims, security interests, or encumbrances; or that there are not other
matters at issue between the CITY and the construction contractor that
affect the amount that should be paid.
H. Record Drawings
Record drawings, if required, will be prepared, in part, on the basis of
information compiled and furnished by others, and may not always represent
the exact location, type of various components, or exact manner in which the
PROJECT was finally constructed. The ENGINEER is not responsible for
any errors or omissions in the information from others that is incorporated
into the record drawings.
I. Minority Business and Small Business Enterprise (MBE)(SBE)
Participation
In accord with the City of Fort Worth Business Diversity goals (Chapter 20,
Article X of the City's Code of Ordinances a/k/a Ordinance No. 20020-12-
2011, as amended), the City has goals for the participation of minority
business enterprises and/or small business enterprises in City contracts.
Engineer acknowledges the MBE and SBE goals established for this
contract and its accepted written commitment to MBE and SBE
participation. Any misrepresentation of facts (other than a negligent
misrepresentation) and/or the commission of fraud by the Engineer may
result in the termination of this Agreement and debarment from participating
in City contracts for a period of time of not less than three (3) years.
J. Right to Audit
(1) ENGINEER agrees that the CITY shall, until the expiration of five (5) years
after final payment under this contract, have access to and the right to
examine and photocopy any directly pertinent books, documents, papers
and records of the ENGINEER involving transactions relating to this
contract. ENGINEER agrees that the CITY shall have access during normal
working hours to all necessary ENGINEER facilities and shall be provided
adequate and appropriate work space in order to conduct audits in
compliance with the provisions of this section. The CITY shall give
ENGINEER reasonable advance notice of intended audits.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 5 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
(2) ENGINEER further agrees to include in all its subconsultant agreements
hereunder a provision to the effect that the subconsultant agrees that the
CITY shall, until the expiration of five (5) years after final payment under the
subcontract, have access to and the right to examine and photocopy any
directly pertinent books, documents, papers and records of such
subconsultant, involving transactions to the subcontract, and further, that the
CITY shall have access during normal working hours to all subconsultant
facilities, and shall be provided adequate and appropriate work space, in
order to conduct audits in compliance with the provisions of this article
together with subsection (3) hereof. CITY shall give subconsultant
reasonable advance notice of intended audits.
(3) ENGINEER and subconsultant agree to photocopy such documents as may
be requested by the CITY. The CITY agrees to reimburse ENGINEER for
the cost of copies at the rate published in the Texas Administrative Code in
effect as of the time copying is performed.
K. INSURANCE
(1) ENGINEER'S INSURANCE
a. Commercial General Liability — the ENGINEER shall maintain
commercial general liability (CGL) and, if necessary, commercial
umbrella insurance with a limit of not less than $1,000,000.00 per each
occurrence with a $2,000,000.00 aggregate. If such Commercial General
Liability insurance contains a general aggregate limit, it shall apply
separately to this PROJECT or location.
i. The CITY shall be included as an additional insured with all rights
of defense under the CGL, using ISO additional insured
endorsement or a substitute providing equivalent coverage, and
under the commercial umbrella, if any. This insurance shall apply
as primary insurance with respect to any other insurance or self-
insurance programs afforded to the CITY. The Commercial
General Liability insurance policy shall have no exclusions or
endorsements that would alter or nullify: premises/operations,
products/completed operations, contractual, personal injury, or
advertising injury, which are normally contained within the policy,
unless the CITY specifically approves such exclusions in writing.
ii. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the commercial general
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 6 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
liability or commercial umbrella liability insurance maintained in
accordance with this agreement.
b. Business Auto — the ENGINEER shall maintain business auto liability
and, if necessary, commercial umbrella liability insurance with a limit of
not less than $1,000,000 each accident. Such insurance shall cover
liability arising out of "any auto", including owned, hired, and non-owned
autos, when said vehicle is used in the course of the PROJECT. If the
engineer owns no vehicles, coverage for hired or non-owned is
acceptable.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by the business auto liability or
commercial umbrella liability insurance obtained by ENGINEER
pursuant to this agreement or under any applicable auto physical
damage coverage.
c. Workers' Compensation — ENGINEER shall maintain workers
compensation and employers liability insurance and, if necessary,
commercial umbrella liability insurance with a limit of not less than
$100,000.00 each accident for bodily injury by accident or $100,000.00
each employee for bodily injury by disease, with $500,000.00 policy limit.
i. ENGINEER waives all rights against the CITY and its agents,
officers, directors and employees for recovery of damages to the
extent these damages are covered by workers compensation and
employer's liability or commercial umbrella insurance obtained by
ENGINEER pursuant to this agreement.
d. Professional Liability— ENGINEER shall maintain professional liability, a
claims-made policy, with a minimum of $1,000,000.00 per claim and
aggregate. The policy shall contain a retroactive date prior to the date of
the contract or the first date of services to be performed, whichever is
earlier. Coverage shall be maintained for a period of 5 years following the
completion of the contract. An annual certificate of insurance specifically
referencing this project shall be submitted to the CITY for each year
following completion of the contract.
(2) GENERAL INSURANCE REQUIREMENTS
a. Certificates of insurance evidencing that the ENGINEER has obtained all
required insurance shall be attached to this AGREEMENT prior to its
execution.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 7 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
b. Applicable policies shall be endorsed to name the CITY an Additional
Insured thereon, subject to any defense provided by the policy, as its
interests may appear. The term CITY shall include its employees,
officers, officials, agents, and volunteers as respects the contracted
services.
c. Certificate(s) of insurance shall document that insurance coverage
specified in this agreement are provided under applicable policies
documented thereon.
d. Any failure on part of the CITY to attach the required insurance
documentation hereto shall not constitute a waiver of the insurance
requirements.
e. A minimum of thirty (30) days notice of cancellation or material change in
coverage shall be provided to the CITY. A ten (10) days notice shall be
acceptable in the event of non-payment of premium. Notice shall be sent
to the respective Department Director (by name), City of Fort Worth,
1000 Throckmorton, Fort Worth, Texas 76102.
f. Insurers for all policies must be authorized to do business in the State of
Texas and have a minimum rating of A:V or greater, in the current A.M.
Best Key Rating Guide or have reasonably equivalent financial strength
and solvency to the satisfaction of Risk Management.
g. Any deductible or self insured retention in excess of $25,000.00 that
would change or alter the requirements herein is subject to approval by
the CITY in writing, if coverage is not provided on a first-dollar basis. The
CITY, at it sole discretion, may consent to alternative coverage
maintained through insurance pools or risk retention groups. Dedicated
financial resources or letters of credit may also be acceptable to the
CITY.
h. Applicable policies shall each be endorsed with a waiver of subrogation
in favor of the CITY as respects the PROJECT.
i. The CITY shall be entitled, upon its request and without incurring
expense, to review the ENGINEER's insurance policies including
endorsements thereto and, at the CITY's discretion; the ENGINEER may
be required to provide proof of insurance premium payments.
j. Lines of coverage, other than Professional Liability, underwritten on a
claims-made basis, shall contain a retroactive date coincident with or
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 8 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
prior to the date of the contractual agreement. The certificate of
insurance shall state both the retroactive date and that the coverage is
claims-made.
k. Coverages, whether written on an occurrence or claims-made basis,
shall be maintained without interruption nor restrictive modification or
changes from date of commencement of the PROJECT until final
payment and termination of any coverage required to be maintained after
final payments.
I. The CITY shall not be responsible for the direct payment of any
insurance premiums required by this agreement.
m. Sub consultants and subcontractors to/of the ENGINEER shall be
required by the ENGINEER to maintain the same or reasonably
equivalent insurance coverage as required for the ENGINEER. When
sub consultants/subcontractors maintain insurance coverage,
ENGINEER shall provide CITY with documentation thereof on a
certificate of insurance.
L. Independent Consultant
The ENGINEER agrees to perform all services as an independent
consultant and not as a subcontractor, agent, or employee of the CITY.
The doctrine of respondeat superior shall not apply.
M. Disclosure
The ENGINEER acknowledges to the CITY that it has made full disclosure
in writing of any existing conflicts of interest or potential conflicts of interest,
including personal financial interest, direct or indirect, in property abutting the
proposed PROJECT and business relationships with abutting property cities.
The ENGINEER further acknowledges that it will make disclosure in writing
of any conflicts of interest that develop subsequent to the signing of this
contract and prior to final payment under the contract.
N. Asbestos or Hazardous Substances
(1) If asbestos or hazardous substances in any form are encountered or
suspected, the ENGINEER will stop its own work in the affected portions
of the PROJECT to permit testing and evaluation.
(2) If asbestos or other hazardous substances are suspected, the CITY may
request the ENGINEER to assist in obtaining the services of a qualified
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 9 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
subcontractor to manage the remediation activities of the PROJECT.
O. Permitting Authorities - Design Changes
If permitting authorities require design changes so as to comply with
published design criteria and/or current engineering practice standards
which the ENGINEER should have been aware of at the time this
Agreement was executed, the ENGINEER shall revise plans and
specifications, as required, at its own cost and expense. However, if design
changes are required due to the changes in the permitting authorities'
published design criteria and/or practice standards criteria which are
published after the date of this Agreement which the ENGINEER could not
have been reasonably aware of, the ENGINEER shall notify the CITY of
such changes and an adjustment in compensation will be made through an
amendment to this AGREEMENT.
P. Schedule
ENGINEER shall manage the PROJECT in accordance with the schedule
developed per Attachment D to this AGREEMENT.
Article V
Obligations of the City
Amendments to Article V, if any, are included in Attachment C.
A. City-Furnished Data
ENGINEER may rely upon the accuracy, timeliness, and completeness of
the information provided by the CITY.
B. Access to Facilities and Property
The CITY will make its facilities accessible to the ENGINEER as required for
the ENGINEER's performance of its services. The CITY will perform, at no
cost to the ENGINEER, such tests of equipment, machinery, pipelines, and
other components of the CITY's facilities as may be required in connection
with the ENGINEER's services. The CITY will be responsible for all acts of
the CITY's personnel.
C. Advertisements, Permits, and Access
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 10 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
Unless otherwise agreed to in the Scope of Services, the CITY will obtain,
arrange, and pay for all advertisements for bids; permits and licenses
required by local, state, or federal authorities; and land, easements, rights-
of-way, and access necessary for the ENGINEER's services or PROJECT
construction.
D. Timely Review
The CITY will examine the ENGINEER's studies, reports, sketches,
drawings, specifications, proposals, and other documents; obtain advice of
an attorney, insurance counselor, accountant, auditor, bond and financial
advisors, and other consultants as the CITY deems appropriate; and render
in writing decisions required by the CITY in a timely manner in accordance
with the project schedule prepared in accordance with Attachment D.
E. Prompt Notice
The CITY will give prompt written notice to the ENGINEER whenever CITY
observes or becomes aware of any development that affects the scope or
timing of the ENGINEER's services or of any defect in the work of the
ENGINEER or construction contractors.
F. Asbestos or Hazardous Substances Release.
(1) CITY acknowledges ENGINEER will perform part of the work at CITY's
facilities that may contain hazardous materials, including asbestos
containing materials, or conditions, and that ENGINEER had no prior
role in the generation, treatment, storage, or disposition of such
materials. In consideration of the associated risks that may give rise to
claims by third parties or employees of City, City hereby releases
ENGINEER from any damage or liability related to the presence of
such materials.
(2) The release required above shall not apply in the event the discharge,
release or escape of hazardous substances, contaminants, or asbestos
is a result of ENGINEER's negligence or if ENGINEER brings such
hazardous substance, contaminant or asbestos onto the project.
G. Contractor Indemnification and Claims
The CITY agrees to include in all construction contracts the provisions of
Article IV.E. regarding the ENGINEER's Personnel at Construction Site, and
provisions providing for contractor indemnification of the CITY and the
ENGINEER for contractor's negligence.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 11 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
H. Contractor Claims and Third-Party Beneficiaries
(1) The CITY agrees to include the following clause in all contracts with
construction contractors and equipment or materials suppliers:
"Contractors, subcontractors and equipment and materials
suppliers on the PROJECT, or their sureties, shall maintain
no direct action against the ENGINEER, its officers,
employees, and subcontractors, for any claim arising out of,
in connection with, or resulting from the engineering
services performed. Only the CITY will be the beneficiary
of any undertaking by the ENGINEER."
(2) This AGREEMENT gives no rights or benefits to anyone other than the CITY
and the ENGINEER and there are no third-party beneficiaries.
(3) The CITY will include in each agreement it enters into with any other entity
or person regarding the PROJECT a provision that such entity or person
shall have no third-party beneficiary rights under this Agreement.
(4) Nothing contained in this Section H. shall be construed as a waiver of any
right the CITY has to bring a claim against ENGINEER.
I. CITY's Insurance
(1) The CITY may maintain property insurance on certain pre-existing structures
associated with the PROJECT.
(2) The CITY may secure Builders Risk/installation insurance at the
replacement cost value of the PROJECT. The CITY may provide
ENGINEER a copy of the policy or documentation of such on a certificate of
insurance.
(3) The CITY will specify that the Builders Risk/installation insurance shall be
comprehensive in coverage appropriate to the PROJECT risks.
J. Litigation Assistance
The Scope of Services does not include costs of the ENGINEER for required
or requested assistance to support, prepare, document, bring, defend, or
assist in litigation undertaken or defended by the CITY. In the event CITY
requests such services of the ENGINEER, this AGREEMENT shall be
amended or a separate agreement will be negotiated between the parties.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 12 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
K. Changes
The CITY may make or approve changes within the general Scope of
Services in this AGREEMENT. If such changes affect the ENGINEER's cost
of or time required for performance of the services, an equitable adjustment
will be made through an amendment to this AGREEMENT with appropriate
CITY approval.
Article VI
General Legal Provisions
Amendments to Article VI, if any, are included in Attachment C.
A. Authorization to Proceed
ENGINEER shall be authorized to proceed with this AGREEMENT upon
receipt of a written Notice to Proceed from the CITY.
B. Reuse of Project Documents
All designs, drawings, specifications, documents, and other work products of
the ENGINEER, whether in hard copy or in electronic form, are instruments
of service for this PROJECT, whether the PROJECT is completed or not.
Reuse, change, or alteration by the CITY or by others acting through or on
behalf of the CITY of any such instruments of service without the written
permission of the ENGINEER will be at the CITY's sole risk. The CITY shall
own the final designs, drawings, specifications and documents.
C. Force Majeure
The ENGINEER is not responsible for damages or delay in performance
caused by acts of God, strikes, lockouts, accidents, or other events beyond
the control of the ENGINEER that prevent ENGINEER's performance of its
obligations hereunder.
D. Termination
(1) This AGREEMENT may be terminated
a.) by the City for its convenience upon 30 days' written notice to
ENGINEER.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 13 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
b.) by either the CITY or the ENGINEER for cause if either party fails
substantially to perform through no fault of the other and the
nonperforming party does not commence correction of such
nonperformance within 5 days' written notice or thereafter fails to
diligently complete the correction.
(2) If this AGREEMENT is terminated for the convenience of the City, the
ENGINEER will be paid for termination expenses as follows:
a.) Cost of reproduction of partial or complete studies, plans,
specifications or other forms of ENGINEER'S work product;
b.) Out-of-pocket expenses for purchasing electronic data files and other
data storage supplies or services;
c.) The time requirements for the ENGINEER'S personnel to document
the work underway at the time of the CITY'S termination for
convenience so that the work effort is suitable for long time storage.
(3) Prior to proceeding with termination services, the ENGINEER will
submit to the CITY an itemized statement of all termination expenses. The
CITY'S approval will be obtained in writing prior to proceeding with
termination services.
E. Suspension, Delay, or Interruption to Work
The CITY may suspend, delay, or interrupt the services of the ENGINEER
for the convenience of the CITY. In the event of such suspension, delay, or
interruption, an equitable adjustment in the PROJECT's schedule,
commitment and cost of the ENGINEER's personnel and subcontractors,
and ENGINEER' compensation will be made.
F. Indemnification
In accordance with Texas Local Government Code Section 271.904, the
ENGINEER shall indemnify or hold harmless the CITY against liability
for any damage committed by the ENGINEER or ENGINEER's agent,
consultant under contract, or another entity over which the ENGINEER
exercises control to the extent that the damage is caused by or
resulting from an act of negligence, intentional tort, intellectual
property infringement, or failure to pay a subcontractor or supplier.
CITY is entitled to recover its reasonable attorney's fees in proportion
to the ENGINEER's liability.
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 14 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
G. Assignment
Neither party shall assign all or any part of this AGREEMENT without the
prior written consent of the other party.
H. Jurisdiction
The law of the State of Texas shall govern the validity of this AGREEMENT,
its interpretation and performance, and any other claims related to it. The
venue for any litigation related to this AGREEMENT shall be Tarrant County,
Texas.
I. Severability and Survival
If any of the provisions contained in this AGREEMENT are held for any
reason to be invalid, illegal, or unenforceable in any respect, such invalidity,
illegality, or unenforceability will not affect any other provision, and this
AGREEMENT shall be construed as if such invalid, illegal, or unenforceable
provision had never been contained herein. Articles V.F., VI.B., VI.D., VI.F.,
VI.H., and VI.I. shall survive termination of this AGREEMENT for any cause.
J. Observe and Comply
ENGINEER shall at all times observe and comply with all federal and State
laws and regulations and with all City ordinances and regulations which in
any way affect this AGREEMENT and the work hereunder, and shall
observe and comply with all orders, laws ordinances and regulations which
may exist or may be enacted later by governing bodies having jurisdiction or
authority for such enactment. No plea of misunderstanding or ignorance
thereof shall be considered. ENGINEER agrees to defend, indemnify and
hold harmless CITY and all of its officers, agents and employees from and
against all claims or liability arising out of the violation of any such order, law,
ordinance, or regulation, whether it be by itself or its employees.
K. Immigration Nationality Act
ENGINEER shall verify the identity and employment eligibility of its
employees who perform work under this Agreement, including completing
the Employment Eligibility Verification Form (1-9). Upon request by CITY,
ENGINEER shall provide CITY with copies of all 1-9 forms and supporting
eligibility documentation for each employee who performs work under this
Agreement. ENGINEER shall adhere to all Federal and State laws as well
as establish appropriate procedures and controls so that no services will
be performed by any ENGINEER employee who is not legally eligible to
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 15 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
perform such services. ENGINEER SHALL INDEMNIFY CITY AND
HOLD CITY HARMLESS FROM ANY PENALTIES, LIABILITIES, OR
LOSSES DUE TO VIOLATIONS OF THIS PARAGRAPH BY ENGINEER,
ENGINEER'S EMPLOYEES, SUBCONTRACTORS, AGENTS, OR
LICENSEES. CITY, upon written notice to ENGINEER, shall have the
right to immediately terminate this Agreement for violations of this
provision by ENGINEER.
L. Prohibition On Contracts With Companies Boycotting Israel
ENGINEER acknowledges that in accordance with Chapter 2270 of the
Texas Government Code, CITY is prohibited from entering into a contract
with a company for goods or services unless the contract contains a
written verification from the company that it: (1) does not boycott Israel;
and (2) will not boycott Israel during the term of the contract. The terms
"boycott Israel" and "company" shall have the meanings ascribed to those
terms in Section 808.001 of the Texas Government Code. By signing
this contract, ENGINEER certifies that ENGINEER'S signature
provides written verification to the CITY that ENGINEER: (1) does not
boycott Israel; and (2) will not boycott Israel during the term of the
contract.
This AGREEMENT, including its attachments and schedules, constitutes the entire
AGREEMENT, which supersedes all prior written or oral understandings, and may only be
changed by a written amendment executed by both parties. This AGREEMENT may be
executed in one or more counterparts and each counterpart shall, for all purposes, be
deemed an original, but all such counterparts shall together constitute but one and the
same instrument. The following attachments and schedules are hereby made a part of
this AGREEMENT:
Attachment A- Scope of Services
Attachment B - Compensation
Attachment C -Amendments to Standard Agreement for Engineering Services
Attachment D - Project Schedule
Attachment E - Location Map
City of Fort Worth,Texas
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 16 of 17
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments ResourcesP_01 - Engineering Agreement
Documents_01-Standard Agreement—Standard Engineering Agreement.doc
Duly executed by each party's designated representative to be effective on the date
subscribed by the City's designated Assistant City Manager.
BY: BY:
CITY OF FORT WORTH ENGINEER
PLUMMER ASSOCIATES, INC.
0AN41 gu"koJ�E G�o�q� l aGt
Dana Burghdoff( r 11,20 11:05 C51)
Dana Burghdoff George I Farah, P.E.
Assistant City Manager NW Texas Conveyance Team Leader
Date: Mar 11,2021 Date:02/23/2021
APPROVAL RECOMMENDED:
Y•W Johown(MaA,202109:54 CST)
William Johnson
Director, Transportation & Public Works
Contract Compliance Manager:
By signing, I acknowledge that I am the
person responsible for the monitoring and
administration of this contract, including
ensuring all performance and reporting
requirements.
Fred Ehler, P.E., CFM
Project Manager
APPROVED AS TO FORM AND LEGALITY
Dee-09
By:Mack(Mar 9,202118:20 CST)
77 Douglas W. Black
Assistant City Attorney
ATTEST: pph°FORT a� 2021-706529
1 pp' o i-01
O� Form 1295 No.
`y U� °a°
—o 0
Mary J. Kayser *000
0 *� M&C No.: 21-0150
°
City Secretary �� r°°°°°5 ap
M&C Date: 3-3-2021 03/02/21
City of Fort worth,Texas OFFICIAL RECORD
Standard Agreement for Engineering Related Design Services
Revised Date:11.17.17
Page 17 of 17 CITY SECRETARY
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\Draft Westcreek Channel Improvments Resources
Documents_01-Standard Agreement—Standard Engineering Agreement.doc FT. WORTH, TX
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
Scope for Engineering Design Related Services for Westcreek Channel Improvements Project
The scope set forth herein defines the tasks to be performed by the ENGINEER in completing
the project. Both the CITY and ENGINEER have attempted to clearly define the scope of work
to be performed and address the needs of the Project. Under this scope, "ENGINEER" is
expanded to include any sub-consultant, including surveyor, employed or contracted by the
ENGINEER.
OBJECTIVE
Basic Engineering Services will involve the conceptual, preliminary, and final design of a storm
water channel Improvements for approximately 2,200 LF east of Westcreek Blvd and south of
Westcreek Park in the City of Fort Worth, Texas including drainage computations, regulatory
assistance, design, bid phase and construction phase service to improve the channel
conditions. Minor similar modifications to two concrete channels connected to the Westcreek
Channel may be necessary and will be evaluated in this project. One earthen swale to the east
of this project area is indeed of minor erosion repairs and is included in this scope of services.
The ENGINEER will complete the engineering design, permitting related services as outlined
below within 365 calendar days after the "Notice to Proceed" letter is issued. Construction
Phase services are expected to be completed within 365 calendar days from the date of"Notice
to Proceed" letter is issues to the Contractor.
SCOPE OF WORK TO BE PERFORMED
Task 1: Design Management
Task 2: Conceptual Design
Task 3: Preliminary Design
Task 4: Final Design
Task 5: Bid Phase Services
Task 6: Construction Phase Services
Task 7: ROW/Easement Services
Task 8: Survey Services
Task 9: Permitting
TASK 1: DESIGN MANAGEMENT
ENGINEER will manage the work outlined in this scope to ensure efficient and effective use
of ENGINEER's and CITY's time and resources. ENGINEER will manage change,
communicate effectively, coordinate internally and externally as needed, and proactively
address issues with the CITY's Project Manager and others as necessary to make progress
on the scope of work.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 1 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
1.1 Managing the Team:
• Lead, manage and direct design team activities
• Ensure quality control is practiced in performance of the scope of work
• Communicate internally among team members
• Task and allocate team resources
1.2 Communications and Reporting:
• Attend a pre-design project kickoff/chartering meeting with CITY staff to confirm
and clarify scope, understand CITY objectives, and ensure economical and
functional designs that meet CITY requirements.
• Conduct review meetings with the CITY at the end of each design Task.
• Prepare invoices, in accordance with Attachment B to this Standard Agreement
and submit monthly in the format requested by the CITY.
• Prepare and submit monthly progress reports in the format provided by the
respective CITY Department.
• Prepare and submit baseline Project Schedule initially, and Project Schedule
updates with a schedule narrative monthly, as required in Attachment D to this
Standard Agreement and according to the City of Fort Worth's Schedule Guidance
Document.
• Complete Monthly Small Business Enterprise (SBE) Report Form and Final
Summary Payment Report Form at the end of the project.
• Coordinate with other agencies and entities as necessary for the design of the
proposed infrastructure, and provide and obtain information needed to prepare the
design.
• With respect to coordination with permitting authorities, ENGINEER shall
communicate with permitting authorities such that their regulatory requirements are
appropriately reflected in the designs. ENGINEER shall coordinate with regulatory
authorities to obtain approval of the designs, and make changes necessary to meet
their requirements, as part of the design scope.
• Personnel and Vehicle Identification: When conducting site visits to the project
location, the ENGINEER or any of its sub-consultants shall carry readily visible
information identifying the name of the company and the company representative.
ASSUMPTIONS
• The following meetings with CITY staff will occur over the length of the project:
a) Pre-Design/Scoping Project Kickoff/Chartering Meetings (2)
b) Design Submittal Review Meetings (3)
c) Four public Meetings are planned for this project.
d) Three coordination meetings.
e) Four franchise utility coordination meetings.
f) Three stakeholder meetings.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 2of16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
• The ENGINEER will conduct three internal quality control meetings with senior staff
prior to submittal to the CITY for each of the following tasks:
a) Conceptual Design Package (30%)
b) Preliminary Design Drawings (60%)
c) 90% Construction Plans
• Two (2) Site Visits.
DELIVERABLES
• Meeting summaries with action items
• Monthly invoices (24)
• Monthly progress reports (24)
• Baseline design schedule
• Monthly schedule updates with schedule narrative describing any current or
anticipated schedule changes
• Monthly SBE Report Form and Final Summary Payment Report Form
TASK 2: CONCEPTUAL DESIGN (30 PERCENT)
The Conceptual Design Package shall be submitted to CITY per the approved Project
Schedule.
The purpose of the conceptual design is for the ENGINEER to identify, develop,
communicate through the defined deliverables, and recommend the design concept that
successfully addresses the design problem, and to obtain the CITY's endorsement of this
concept.
ENGINEER will develop the conceptual design of the infrastructure as follows:
2.1 Data Collection:
• In addition to data obtained from the CITY, ENGINEER will research and make
efforts to obtain pertinent information to aid in coordination of the proposed
improvements with any planned future improvements that may influence the
project. ENGINEER will also identify and seek to obtain data for existing conditions
that may impact the project including; utilities, agencies (such as USCOE and
railroads), CITY Master Plans, CITY drainage complaint files, existing applicable
drainage studies, FEMA floodplain and floodway maps, existing models of project
area (if any) and property ownership as available from the Tax Assessor's office.
2.2 Drainage Computations:
2.2.1 ENGINEER will perform an advanced hydraulic analysis using the HEC-RAS
software developed by the USACE to analyze the channel water surface, velocity
distribution, and floodplain limits for the 100-year event. The models will span the
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 3of16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
from the Westcreek Drive bridge approximately 2,200 ft downstream to Peggy
Drive. The HEC-RAS hydraulic model will be used to identify water surface
elevations and velocity distribution throughout the reach.
2.2.2 Specific hydrology analysis is not included in this scope and hydraulic model flow
values will be adjust in order to model the current FEMA Base Flood Elevations
in the current FEMA FIS report creating a duplicate effective hydraulic model.
2.2.3 ENGINEER will evaluate the hydraulics of the HEC-RAS model and provide
conceptual recommendations for embankment protection along the channel
segment. The goal with the conceptual recommendations is to not increase the
100-year water surface elevations thought the channel segment in addition to
upstream of the channel improvements. Hydraulic analysis will include an
existing and a proposed developed condition.
2.3 Prepare typical section cuts and repair options to present to the City for review and
approval prior to commencing with the conceptual design package.
2.4 The Conceptual Design Package shall include the following:
• Written summary of alternative design concepts considered, strengths and
weaknesses of each, and the rationale for selecting the recommended design
concept.
• Cover sheet
• Drainage area map with supporting drainage computations in the CITY's standard
tabular format.
• SUE Plan sheets sealed by a licensed professional engineer registered in the
State of Texas.
• Horizontal alignment (excluding profiles) of proposed storm water improvements
for each alternative, including existing lot layout, streets, street right-of-way,
proposed easements, and existing utilities gathered during the SUE within the
project limits.
• Documentation of key design decisions (Project Decision Log).
• Estimates of probable construction cost.
ASSUMPTIONS
• All storm water calculations and design shall conform to the City of Fort Worth
Stormwater Criteria Manual, Sept. 2015.
• Eight (8) copies of the Conceptual Design Package will be delivered no later than
75 calendar days from the date of the Notice to Proceed. Drawings will be half size
(11"x 17").
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in BIM 360.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 4 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
• The Conceptual Design Package shall be reviewed and approved by the CITY no
later than 30 calendar days from the date the Conceptual Design Package is
delivered. ENGINEER shall not proceed with Preliminary Design activities without
written approval by the CITY of the Conceptual Design Package.
DELIVERABLES
• Conceptual Design Package.
TASK 3: PRELIMINARY DESIGN (60 PERCENT)
Preliminary plans shall be submitted to CITY per the approved Project Schedule.
ENGINEER will develop the preliminary design of the infrastructure as follows:
3.1 Development of Preliminary Design Drawings shall include the following:
• Cover Sheet
• Drainage area maps showing proposed improvements with drainage calculations
and hydraulic computations in accordance with the City of Fort Worth Stormwater
Criteria Manual, Sept. 2015.
• A Project Control Sheet, showing all Control Points, used or set while gathering
data. Generally on a scale of not less than 1:400. The following information shall
be indicated for each Control Point: Identified (existing City Monument#8901, PK
Nail, 5/8" Iron Rod); X, Y and Z Coordinates, in an identified coordinate system, and
a referred bearing base. Z coordinate on City Datum only; descriptive location (i.e.
set in the centerline of the inlet in the South curb line of North Side Drive at the East
end of radius at the Southeast corner of North Side Drive and North Main Street).
• Overall project easement layout sheet(s).
• SUE plan drawings.
• Plan and profile drawings of proposed storm water improvements, including
existing lot layout with property ownership, streets, curb lines, driveways, medians
(if applicable), sidewalks, existing and proposed water and sanitary sewer mains,
existing utilities gathered during the SUE and existing utility easements within the
project limits.
• No less than two bench marks per plan/profile sheet.
• The ENGINEER will prepare standard and special detail sheets that are not already
included in the City's standard details. These may include connection details
between various parts of the project, tunneling details, boring and jacking details,
waterline relocations, details unique to the construction of the project, trenchless
details, and special service lateral reconnections.
• Station equations relating utilities to paving, when appropriate.
• Proposed roadway profile grades and elevations along each curb line; elevations at
all P.V.I.'s; P.I's half stations; high and low points; vertical curve information; and
pertinent AASHTO calculations. Profiles for existing curbs (if any)and existing
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 5of16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
ground at the left and right of right-of-way lines shall be shown. Existing found
property corners (e.g. Iron pins)along the existing right-of-way shall be shown on the
plans. Profiles for existing and proposed storm drain mains and laterals shall be
provided.
• Channel plan and profile drawings shall include existing channel centerline, existing
left and right top of channel bank, proposed top of channel backs, and 100 year
water surface profile.
• Preliminary roadway and/or channel cross-sections will be developed, from the
survey notes, at intervals not-to-exceed 100 foot along the project length and will
extend 10 foot past the right of way line on both sides of the street. Provide option
for a plan view sheet and a typical section. Additional cross-sections at important
features including driveways, P.I.'s of intersecting streets, (minimum distance of 100
foot along cross-street at each P.I.)walks, retaining walls, etc., will also be provided.
Profiles of centerline of driveways will also be provided where necessary. Scale will
be 1" = 20' horizontal and 1" = 2'vertical. Excavation and embankment volumes and
end area computations shall also be provided.
3.2 Subsurface Utility Engineering:
Provide Subsurface Utility Engineering (SUE) shall be performed in accordance with
Cl/ASCE 38-02 to Quality Level B and A as described below:
Quality Level D
• Conduct appropriate investigations (e.g., owner records, County/CITY records,
personal interviews, visual inspections, etc.), to help identify utility owners that may
have facilities within the project limits or that may be affected by the project.
• Collect applicable records (e.g., utility owner base maps, "as built" or record
drawings, permit records, field notes, geographic information system data, oral
histories, etc.) on the existence and approximate location of existing involved
utilities.
• Review records for: evidence or indication of additional available records; duplicate
or conflicting information; need for clarification.
• Develop SUE plan sheets and transfer information on all involved utilities to
appropriate design plan sheets, electronic files, and/or other documents as
required. Exercise professional judgment to resolve conflicting information. For
information depicted, indicate: utility type and ownership; date of depiction; quality
level(s); end points of any utility data; line status (e.g., active, abandoned, out of
service); line size and condition; number of jointly buried cables; and encasement.
Quality Level C (includes tasks as described for Quality Level D)
• Identify surface features, from project topographic data and from field observations,
that are surface appurtenances of subsurface utilities.
• Include survey and correlation of aerial or ground-mounted utility facilities in Quality
Level C tasks.
FAOpportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 6of16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
• Survey surface features of subsurface utility facilities or systems.
• The survey shall also include (in addition to subsurface utility features visible at the
ground surface): determination of invert elevations of any manholes and vaults;
sketches showing interior dimensions and line connections of such manholes and
vaults; any surface markings denoting subsurface utilities, furnished by utility
owners for design purposes.
• Exercise professional judgment to correlate data from different sources, and to
resolve conflicting information.
• Update (or prepare) plan sheets, electronic files, and/or other documents to reflect
the integration of Quality Level D and Quality Level C information.
• Recommend follow-up investigations (e.g., additional surveys, consultation with
utility owners, etc.) as may be needed to further resolve discrepancies.
• Provide Quality Level C to identify overhead utilities on the project and provide the
overhead utility information on the SUE plan sheets.
Level B (includes tasks as described for Quality Level C)
• Select and apply appropriate surface geophysical method(s)to search for and
detect subsurface utilities within the project limits, and/or to trace a particular utility
line or system.
• Based on an interpretation of data, mark the indications of utilities on the ground
surface for subsequent survey. Utilize paint or other method acceptable for
marking of lines.
• Unless otherwise directed, mark centerline of single-conduit lines, and outside
edges of multi-conduit systems.
• Resolve differences between designated utilities and utility records and surveyed
appurtenances.
• Recommend additional measures to resolve differences if they still exist.
Recommendations may include additional or different surface geophysical
methods, exploratory excavation, or upgrade to Quality Level A data.
• As an alternative to the physical marking of lines, the ENGINEER may, with CITY's
approval, utilize other means of data collection, storage, retrieval, and reduction,
that enables the correlation of surface geophysical data to the project's survey
control.
Level A
• Expose and locate utilities at specific locations.
• Tie horizontal and vertical location of utility to survey control.
• Provide utility size and configuration.
• Provide paving thickness and type, where applicable.
• Provide general soil type and site conditions and such other pertinent information
as is reasonably ascertainable from each test hole site.
FAOpportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 7of16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
3.3 Geotechnical Investigation/Pavement Design
• Soil investigations, including field and laboratory tests, borings, related engineering
analysis and recommendations for determining subsurface stratum, foundation and
pavement design will be made. In addition to the above investigations, borings
and appropriate field and laboratory analysis will be made at reasonable intervals
along the project alignment for the Contractor's use in determining soil conditions
for preparing bids and a Trench Safety Plan.
• The ENGINEER shall prepare a detailed geotechnical engineering study and
pavement design in conformance with the City of Fort Worth Pavement Design
Manual, Jan. 2015(Revised Dec. 2015). The study shall include
recommendations regarding utility trenching and identifying existing groundwater
elevation at each boring.
• Three soil sample borings to a depth of 30 feet below grade will be performed.
Laboratory service for the soil samples will be performed to identify soil properties.
3.4 Constructability Review
• Prior to the 60 percent review meeting with the CITY, the ENGINEER shall
schedule and attend a project site visit with the CITY Project Manager and
Construction personnel to walk the project. The ENGINEER shall summarize the
CITY's comments from the field visit and submit this information to the CITY in
writing.
3.5 Public Meeting
3.5.1 Four Public meetings are planned for this project.
3.5.2 The ENGINEER will prepare necessary exhibits for displaying at the public
meetings.
3.5.3 The ENGINEER shall attend the meeting and assist the CITY in answering
any questions.
3.6 Utility Clearance
• The ENGINEER will consult with the CITY's Transportation and Public Works
Department, Water Department, and other CITY departments, public utilities,
private utilities, and government agencies to determine the approximate location of
above and underground utilities, and other facilities (current and future)that have
an impact or influence on the project. ENGINEER will design CITY facilities to
avoid or minimize conflicts with existing utilities, and where known and possible
consider potential future utilities in designs.
FAOpportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 8of16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
• The ENGINEER shall upload individual DWF files for each plan sheet of the
approved preliminary plan set to the designated project folder in BIM 360 for
forwarding to all utility companies which have facilities within the limits of the project.
The DWF files should be created directly from the CAD files as opposed to PDF files.
3.7 Traffic Control Plan (Not Included in this Contract)
ASSUMPTIONS
• The preliminary design drawings are based on the design of concrete lined open
channel improvements.
• All storm water calculations and design shall conform to the City of Fort Worth
Stormwater Criteria Manual, Sept. 2015.
• The SUE and SUE plan sheets shall be in accordance with Cl/ASCE 38-02 to
Quality Level B for approximately 2,200 LF for the entire width of the right-of-way
as well as extending fifteen feet beyond the limits of the Westcreek Dr. Road right-
of-way on both sides of the roadway. Five (5) work days are planned for the Level
A test hole and level B locations.
• One (1) copy of the geotechnical report will be delivered to the CITY and one
electronic copy will be provided by Electronic Mail.
• Digital plans will be provided in BIM 360 for Utility Clearance and CITY will
distribute plans to franchise utilities for potential conflicts and utility relocations.
• Four(4)full size (22"x 34") plans will be delivered for Constructability Review no
later than 45 calendar days from the date of the written approval by the CITY of the
Conceptual Design Package.
• The Constructability Review meeting shall take place no later than 15 calendar
days from the date the constructability review plans are submitted.
• Eight (8) half size (11"x 17") drawings will be delivered for Preliminary Design no
later than 30 calendar days from the date of the Constructability Review Meeting.
• DWF files created from design CAD drawings will be uploaded to the designated
project folder in BIM 360.
• Specifications are not included as part of the Preliminary Design package.
• The 60 percent review meeting shall take place no later than 30 calendar days
from the date of the Preliminary Design drawings being delivered. ENGINEER shall
not proceed with Final Design activities without written approval by the CITY of the
Preliminary Design plans.
DELIVERABLES
• Preliminary Design drawings
• Geotechnical Report
• Documentation of key design decisions (Project Decision Log)
• Estimates of probable construction cost
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 9of16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
TASK 4: FINAL DESIGN (90 PERCENT) AND FINAL CONSTRUCTION DOCUMENTS
(100 PERCENT)
Upon approval of the Preliminary plans, ENGINEER will prepare construction plans as
follows:
• Final draft construction plans and specifications shall be submitted to CITY per the
approved Project Schedule.
• The ENGINEER shall submit a final design estimate of probable construction cost
with the final design plans submitted. This estimate shall use ONLY standard CITY
bid items.
• Following a 90% construction plan review meeting with the CITY, the ENGINEER
shall submit Final Plans (100%)to the CITY per the approved Project Schedule.
Each plan sheet shall be stamped, dated, and signed by the ENGINEER registered
in State of Texas.
ASSUMPTIONS
• The final design drawings and construction documents are based on the design of
a concrete lined channel improvements.
• All storm water calculations and design shall conform to the City of Fort Worth
Stormwater Criteria Manual, Sept. 2015.
• Four(4) half size (11" x 17") and four(4)full size (22"x 34") drawings and eight (8)
specifications will be delivered for the 90% design no later than 45 calendar days
from the date of the written approval by the CITY of the preliminary design
drawings.
• A DWF file for the 90% Design will be created from design CAD drawings and will
be uploaded to the project folder in BIM 360.
• The 90% construction plan review meeting shall take place no later than 30
calendar days from the date the 90% design package is submitted.
• Four(4)full size (22" x 34") bond drawings and four (4) specifications will be
delivered for the 100% design no later than 30 calendar days from the date of the
90% construction plan review meeting.
• A DWF file for the 100% Design will be created from design CAD drawings and will
be uploaded to the project folder in BIM 360.
DELIVERABLES
• 90% construction plans specifications.
• 100% construction plans and specifications.
• Documentation of key design decisions (Project Decision Log).
• Detailed estimates of probable construction cost for the authorized construction
project, including summaries of bid items and quantities using the CITY's standard
bid items and format.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 10 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
• Original cover bond for the signatures of authorized CITY officials.
TASK 5: BID PHASE SERVICES
5.1 Deliver Bid Documents—The ENGINEER will make available for bidding, upon
request by the CITY, up to forty (40) sets of the final approved and dated plans
and specifications and contract documents for the project to the CITY for
distribution to potential bidders. Proposal will be delivered in electronic format.
5.2 Bidding Assistance
5.2.1 The ENGINEER shall assist the CITY during the bid phase including
preparation and delivery of addenda to planholders and responses
to questions submitted to the CITY by prospective bidders.
ENGINEER will provide addendum required for clarification to plans
and contract documents where documents are unclear. Any
addenda required for supplemental information after final plans and
specification approval will be by Additional Services.
5.2.2 ENGINEER shall attend the scheduled pre-bid conference.
5.2.3 The ENGINEER shall attend the project bid opening and assist in
reviewing the bids for completeness and accuracy.
5.2.4 The ENGINEER shall develop bid tabulations in hard copy and
electronic format, and submit two (2)copies of the bid tabulation and
make a recommendation for award.
5.2.5 The above described bidding assistance shall be provided for one
(1) construction project.
TASK 6: CONSTRUCTION PHASE SERVICES
6.1 Preconstruction Conference — ENGINEER will attend the preconstruction
conference.
6.2 Respond to Design-Related Contractor Questions—The ENGINEER will provide
necessary interpretations and clarifications of contract documents and respond
to Requests For Information (RFI) (Upto 4) specifically related to those portions
of the Contract Documents designed by the ENGINEER.
6.3 Evaluations of Contract Modifications—The ENGINEER will review and evaluate
one (1) Contract Modification Requests (CMRs), or one Field Orders, or one
Change Order (CO) as prepared and requested by the CONTRACTOR.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 11 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
6.4 Site Visits — Engineer shall visit the project site up to four (4) occasions at
appropriate intervals as construction proceeds to observe construction activities
or answer CONTRACTOR questions.
6.5 The ENGINEER will review up to twelve (12) shop drawings (Initial or
resubmittal). Additional shop drawings review will be by CITY approval of
Additional Services.
6.6 The ENGINEER will prepare for and conduct month construction meetings two
(2) in person and six (6) virtual meetings are planned. Additional meetings
requested by the CITY will be by approval of Additional Services.
6.7 The CITY will provide record drawings from the contractor"redlines."
6.8 The CITY will review and sign pay estimates.
6.9 The ENGINEER will attend the final walkthrough and will assist in itemizing
deficiency items and making recommendation of final acceptance.
6.10 The CITY will prepare and process all change orders.
6.11 The ENGINEER will prepare Record Drawings based on the CITY's provided
redlines.
6.12 The CITY will be providing resident project representation, inspection and
material testing for the project.
6.13 Assisting the OWNER in claims disputes with Contractor(s)will be performed by
approval of Additional Services.
6.14 Performing investigations, studies and analyses of substitutions of equipment
and/or materials or deviations from the Plans and Specifications will be
performed by approval of Additional Services.
6.15 Assisting OWNER or Contractor in the defense or prosecution of litigation in
connection with or in addition to those services contemplated by this Agreement.
Such services, if any, shall be furnished by ENGINEER on a fee basis negotiated
by the respective parties outside of and in addition to this Agreement.
TASK 7: ROW/EASEMENT SERVICES
ENGINEER will support and perform activities related to ROW and easements as outlined
below, per scoping direction and guidance from the CITY's Project Manager.
7.1 Right-of-Way Research:
• The ENGINEER shall determine rights-of-way and easement needs for
construction of the project. Required temporary and permanent easements will be
identified based on available information and recommendations will be made for
approval by the CITY.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 12 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
7.2 Right-of-Way/Easement Preparation and Submittal:
• The ENGINEER shall prepare documents for the CITY to be used to obtain
temporary easements required to construct the improvements.
• The documentation shall be provided in conformance with the checklists and
templates as provided by the CITY's staff.
7.3 Temporary Right of Entry Preparation and Submittal - Not Included in This Contract.
ASSUMPTIONS
• Right-of-Way research includes review of property/right-of-way records based on
current internet based Tarrant Appraisal District (TAD) information available at the
start of the project and available on-ground property information (i.e. iron rods,
fences, stakes, etc.). It does not include effort for chain of title research, parent
track research, additional research for easements not included in the TAD, right-of-
way takings, easement vacations and abandonments, right-of-way vacations, and
street closures.
• Preparation of three (3) easements. The ENGINEER will provide three (3) signed
originals of each easement prepared.
DELIVERABLES
• Right-of-Way, easement exhibits and metes and bounds provided on CITY forms.
TASK 8: SURVEY
ENGINEER will provide survey support as follows:
8.1 Design Survey:
• ENGINEER will perform field surveys to collect horizontal and vertical elevations
and other information needed by ENGINEER in design and preparation of plans for
the project. Information gathered during the survey shall include topographic data,
utilities as required by the SUE, structures, trees (measure caliper, identify overall
canopy, and have qualified arborist identify species of trees), and other features
relevant to the final plan sheets. Existing drainage at intersections will be verified
by field surveys. Spot elevations will be shown on intersection layouts with cross
slope to fit intersecting grade lines.
• The minimum survey information to be provided on the plans shall include the
following:
a) A Project Control Sheet, showing set Control Points, used or set while
gathering data. Generally on a scale of not less than 1:400:
b) The following information about each Control Point;
i) Identified existing CITY Monuments, if any exist.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 13 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
ii) X, Y and Z Coordinates, in an identified coordinate system, and a referred
bearing base. Z coordinate on CITY Datum only.
iii) Descriptive Location (Ex. Set in the centerline of the inlet in the South curb line
of North Side Drive at the East end of radius at the Southeast corner of North
Side Drive and North Main Street).
8.2 Construction Survey- Not Included in This Contract:
ASSUMPTIONS
• Design Survey shall consist of approximately 2,200 LF and will included the entire
width of the channel.
DELIVERABLES
• Drawing of the project layout with dimensions and coordinate list.
TASK 9: PERMITTING
ENGINEER will provide permitting support for the CITY to obtain any and all agreements
and/or permits normally required for a project of this size and type, as follows.
9.1 Storm Water Pollution Prevention Plan
• For projects that disturb an area greater than one (1) acre, ENGINEER will prepare
the Storm Water Pollution Prevention Plan (SWPPP) required for the Project for
use by the Contractor during construction. ENGINEER will prepare drawings and
details for proposed SWPPP improvement that the Contractor must use during
construction. Contractor will be responsible for filing the SWPPP with appropriate
regulatory agencies.
9.2 Environmental Services
• ENGINEER will prepare a Preliminary Jurisdictional Determination (PJD) report to
identify the presence and possible impact to waters of the U.S. as regulated under
Section 404 of the Clean Water Act and as outlined in the U.S. Army Corps of
Engineers (USACE) Section 33 CFR 328.2.
• Submitting forms/applications for CITY review
• Submitting revised forms for agency review
• Responding to agency comments and requests
9.3 Floodplain Services— Not Included in This Contract.
9.4 Texas Department of Transportation (TxDOT) Permit- Not Included in This Contract
9.5 Railroad Permit - Not Included in This Contract
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 14 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
• Negotiating and coordinating to obtain approval of the agency issuing the
agreement and/or permits
• Completing all forms/applications necessary
• Submitting forms/applications for CITY review
• Submitting revised forms for agency review
• Responding to agency comments and requests
9.6 Texas Department of Licensing and Regulation (TDLR)— Not Included in This Contract
ASSUMPTIONS
• Permit preparation will begin after approval of the Conceptual Design.
• One (1) site visit prior to preparation of PJD report.
• Preparation of railroad permit application to provide grading within right-of-way.
DELIVERABLES
• Two (2) copies of PJD Report to CITY and eight (8) copies submitted to local,
state, and federal agencies.
• Tarrant Regional Water District (TRWD) coordination documentation and approval
of proposed scope of work and construction.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 15 of 16
ATTACHMENT A
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Plummer Project No. 2018-264-01
ADDITIONAL SERVICES NOT INCLUDED IN THE EXISTING SCOPE OF SERVICES
Additional Services not included in the existing Scope of Services — CITY and
ENGINEER agree that the following services are beyond the Scope of Services described in
the tasks above. However, ENGINEER can provide these services, if needed, upon the
CITY's written request. Any additional amounts paid to the ENGINEER as a result of any
material change to the Scope of the Project shall be agreed upon in writing by both parties
before the services are performed. These additional services include the following:
• Meeting and/or contacting of property owners for negotiation of easements or property
acquisition.
• Meeting and coordination with City's Property Management Department for the
negotiation of easement terms and conditions.
• Preparation of a Preconstruction Notification (PCN) application if required by USACE.
• Post-construction Letter of Map Revision (LOMR) preparation and submittal.
• Services related to development of the CITY's project financing and/or budget.
• Services related to disputes over pre-qualification, bid protests, bid rejection and re-
bidding of the contract for construction.
• Bridge, concrete apron improvements are considered special services.
• Services related to Park Conversion process.
• Construction management and inspection services.
• Performance of materials testing or specialty testing services.
• Services necessary due to the default of the Contractor.
• Services related to damages caused by fire, flood, earthquake or other acts of God.
• Services related to warranty claims, enforcement and inspection after final completion.
• Services to support, prepare, document, bring, defend, or assist in litigation undertaken
or defended by the CITY.
• City Flood plain permit.
• Performance of miscellaneous and supplemental services related to the project as
requested by the CITY.
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECTWttachment A Plummer 01262021.docx
Page 16 of 16
ATTACHMENT B
COMPENSATION
Design Services for
Westcreek Channel Improvements
City Project No. 103060
Lump Sum Project
I. Compensation
A. The ENGINEER shall be compensated a total lump sum fee of $375,470 as
summarized in Exhibit B-1 — Engineer Invoice and Section IV—Summary of Total
Project Fees. The total lump sum fee shall be considered full compensation for
the services described in Attachment A, including all labor materials, supplies,
and equipment necessary to deliver the services.
B. The ENGINEER shall be paid monthly payments as described in Section II -
Method of Payment.
II. Method of Payment
A. Partial payment shall be made to the ENGINEER monthly upon City's approval of
an invoice prepared and submitted by the ENGINEER in the format and including
content as presented in Exhibit B-1, Progress Reports as required in item III. of
this Attachment B, and Schedule as required in Attachment D to this Agreement.
B. The estimated current physical percent complete as required on the invoice shall
be calculated from the progress schedule as required in Attachment D to this
Standard Agreement and according to the current version of the City of Fort
Worth's Schedule Guidance Document.
C. The cumulative sum of such monthly partial fee payments shall not exceed the
total current project budget including all approved Amendments.
D. Each invoice shall be verified as to its accuracy and compliance with the terms of
this Agreement by an officer of the ENGINEER.
III. Progress Reports
A. The ENGINEER shall prepare and submit to the designated representative of the
Transportation and Public Works Department, monthly progress reports and
schedules in the format required by the City.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 1 of 3
B-1
F:\Opportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\ResourcesP_01 -Engineering Agreement Documents_03-Attachment
B_Attachment B for Lump Sum Design Projects(1).doc
ATTACHMENT B
COMPENSATION
IV. Summary of Total Project Fees
Firm Primary Responsibility Fee Amount %
Prime Consultant
Plummer Management, Design, Bid and 320,490 85.36
Construction Phase Services,
QA/QC. OPCC, Monthly
reporting and permitting
Proposed SBE Sub-Consultants
JQ Structural Engineering 7,000 1.86
Spooner and Topographic Survey, 21,080 5.61
Associates, Inc. Easements
CMJ Engineering Geotechnical Engineering and 9,300 2.48
drilling
LTRA Subsurface Engineering 17,600 4.69
TOTAL $375,470 100%
Project Number& Name Total Fee SBE Fee MBE/SBE
Westcreek Channel Improvements $375,470 $54,980 14.64
City SBE Goal = 10% Consultant Committed Goal = 14.64%
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 2 of 3
B-2
F:\Opportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\ResourcesP_01 -Engineering Agreement Documents_03-Attachment
B_Attachment B for Lump Sum Design Projects(1).doc
EXHIBIT "B-1"
ENGINEER INVOICE
(Supplement to Attachment B)
Insert required invoice format following this page, including negotiated total budget and
allocations of budgets across work types and work phases.
City of Fort Worth,Texas
Attachment B
PMO Official Release Date:8.09.2012
Page 3 of 3
B-3
F:\Opportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\ResourcesP_01 -Engineering Agreement Documents_03-Attachment
B_Attachment B for Lump Sum Design Projects(1).doc
c•
C C
W o
E l0
�m
C a
C
V—
T
a>
C
0
en
en
c
sa
IL
•
S c
c
oa a
S E E
ca
9 04 CI
T V C
C a0+ d
C � C •
am d
-0 =
: g mE
n v E a
v
N N IL •
E
•
.O d
w c E d aM m �
8 Z
u c
N c
a 2 u >a E E • c
c N c � E i o M E
c m
m
. N • O
G C C c C N a s
LD
rt+ 0
C
Q O
C - sa E�
l �a
CL
:.
E e
c 's
c F
v cc r w
o �
> Y $ o
Do
N CO co 0
o E
CO ?
� F a
U) d ati
{0 m •• m o 0
p ati0 MO Z o cm m m w
y v • o Z m C G Cal G d
: a Q
0 o ecZ% c = ILt Ro
a aC> � li VO o wwd US US e d
ATTACHMENT "C"
CHANGES AND AMENDMENTS TO STANDARD AGREEMENT
Design Services for
Westcreek Channel Improvements
City Project No. 103060
City of Fort Worth,Texas
Attachment C
PMO Release Date:05.19.2010
Page 1 of 1
F:\0pportunity\2018-264-00\0-0 Opportunity\0-2 PROJECT\ResourcesP 01-Engineering Agreement Documents_04-Attachment C Attachment C.doc
FORT WORTH
ATTACHMENT "D"
PROJECT SCHEDULE
A. ENGINEER Project Schedule Development
ENGINEER shall prepare a project schedule for the services to be provided in fulfilling
the requirements of the Agreement and encompassing the Scope of Work defined in
Attachment A to the Agreement.
ENGINEER shall prepare and maintain project schedule throughout the life of the project
as defined in the Agreement in compliance with the City's Specification 00 31 15 entitled
Engineer Project Schedule.
ENGINEER's project schedule will follow the Critical Path Methodology (CPM) for
planned sequencing of the work activity and timing of the work.
B. Schedule "Tier" Selection
City has identified three "Tier" levels for project schedules as defined in City's
Specification 00 31 15, to align with the size and complexity of the project as a basis for
schedule development. City's Project Manager will determine the "Tier' level for the
ENGINEER's project schedule as part of the negotiation of the Agreement.
C. Project Baseline Schedule
ENGINEER will produce an initial project schedule and submit as a "baseline" for review
and acceptance by City's Project Manager as defined in City's Specification 00 31 15
which will be referred to as the Project Baseline Schedule. Updates to the baseline
schedule follow the requirements of City's Specification 00 31 15.
D. Project Progress Schedule
ENGINEER will provide to the City, monthly updates to their project schedule indicating
progress of the Work in compliance with the requirements of City's Specification 00 31
15 and said schedule will be referred to as the Project Progress Schedule.
E. Master Project Schedule
City will develop and maintain a master project schedule for the overall project.
ENGINEER's project baseline and progress schedule submittals will be an integral part
of the development and updating process of City's Master Project Schedule.
City of Fort Worth,Texas
Attachment D
Revision Date:07.20.2018
Page 1 of 1
3
z ■�a @s «
2 « «
9L
a
�
3 « « «
�
z « «
0
0
. w
_ � § « «
Mo o
° tL § z
■ E cc 0 :3
U. § -j w z
. R « :3
o 0 z
■
2x.
« «
E -
a e
§ E ®
n g r { m -
2 £ - ƒ � ( | r a
§ a) 2 k E 2 f \ } ) - § � - / E
G a ° ' ~cm E 2 2 2 e o £
f ƒ ± J ƒ i § i $ a ) s _ % £ E -- J cl
`
k / k k \ k { § 2 2 § f k k ) /
e ] cool § > k ` 2 & t k e M ] 2 | { ) i -
) = G a 2 ƒ a k E 1 / _ m k ) k k (
ECIJ C04 m !
2 i
$
\ - i Qr 7cclE
E
m a
LL
-= rr vi N
i _ ❑ CD
C £
C uj
U W
Y Y
N N
L V
\ N
fl
f0
w,
W U
I N
w, "O
y/ co
J J�
— TAW ' ,• ,
c £
• = w
uj $
o
•
W ' J
= i Q CL
Owl
O
o
a � CD
N
W v CD
4YL Q z W � o
w
o
� O
� '1 Z U
44
Aj
City of Fort Worth, Texas
Mayor and Council Communication
DATE: 03/02/21 M&C FILE NUMBER: M&C 21-0150
LOG NAME: 20SWM WESTCREEK CHANNELREHAB DESIGN
SUBJECT
(CD 6) Authorize Execution of a Contract with Alan Plummer and Associates, Inc. d/b/a Plummer
Associates, Inc. in the Amount of$375,470.00 for the Design of the Westcreek Channel
Rehabilitation Project
RECOMMENDATION:
It is recommended that the City Council authorize execution of a contract with Alan Plummer and
Associates, Inc. d/b/a Plummer Associates, Inc. in the amount of$375,470.00 for the design of the
Westcreek Channel Rehabilitation project (City Project No. 103060).
DISCUSSION:
The engineering agreement recommended by this Mayor and Council Communication (M&C) will
provide for engineering services related to the Westcreek Channel Rehabilitation project. This
project will restore the damaged concrete channel and the streambed.
In May 2018, the Transportation and Public Works Department (TPW), Stormwater Management
Division, published a Request for Qualifications (RFQ) for various technical services associated
with drainage engineering. Based on the results of the RFQ, Plummer Associates, Inc. (Plummer)
was selected as the most qualified consultant to provide engineering services for the Westcreek
Channel Rehabilitation project. Plummer will analyze and evaluate the failure of Westcreek Channel
between Westcreek Drive and the Atchison Topeka and the Santa Fe Railroad, and design
channel improvements to mitigate the failure of the concrete-lined channel slopes and stabilize the
streambed scour. The channel improvements will restore the structural integrity of the channel
slopes and prevent further deterioration/movement to protect adjacent properties and ensure the
channel continues to effectively convey stormwater away from area homes and businesses.
Plummer will evaluate environmental and floodplain requirements and assist staff in obtaining any
required permits. Additionally, Plummer will prepare plans and specifications for construction and
provide services during bidding and construction. Plummer proposes to perform engineering
services for a fee not to exceed $375,470.00. Staff considers the fee to be fair and reasonable for
the scope of services proposed.
M/WBE Office — Plummer Associates, Inc. is in compliance with the City's BDE Ordinance by
committing to 15% SBE participation on this project. The City's SBE goal on this project is 10%.
The project is located in COUNCIL DISTRICT 6.
FISCAL INFORMATION / CERTIFICATION:
The Director of Finance certifies that funds are available in the current capital budget, as previously
appropriated, in the Storm Water Rev Ref Bonds 2020 Fund for the Westcreek Channel Rehab
project to support the approval of the above recommendation and award of the contract. Prior to
any expenditure being incurred, the Transportation & Public Works Department has the
responsibility to validate the availability of funds.