HomeMy WebLinkAboutContract 38187 CITY SECRETARY
D.O.E. FILE CITY SECRETAW
CONTRACT NO.
CONTRACTOR'S BONDING CO.
CONSTRUCTION'S COPY SPECIFICATIONS
,AND
`CLIENT DEPARTMENT
CONTRACT DOCUMENTS
_ LOST CREEK PHASE 2 DRAINAGE IMPROVEMENTS FOR
BEN CREEK COURT, BLUE CREEK COURT, AND
POWDERHORN ROAD
DRAINAGE IMPROVEMENTS
LOST CREEK ADDITION-FROM BEN CREEK COURT SOUTH TO GOLF COURSE
LOST CREEK ADDITION-FROM BLUE CREEK COURT SOUTH TO MARY'S CREEK
WESTPOINT ADDITION-FROM POWDERHORN ROAD TO PARK JUST SOUTH OF
LITTLE VALLEY ROAD
FILE NO.SD-0135
DOE PROJECT NO. 4744
TPW PROJECT NO. C200 541200 2032800087 83
IN THE CITY OF FORT WORTH,TEXAS
MIKE MONCRIEF DALE A.FISSELER,P.E.
MAYOR CITY MANAGER
FRANK CRUMB,P.E.-DIRECTOR
FORT WORTH WATER DEPARTMENT
GREG SIMMONS,P.E.--ACTING DIRECTOR
DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS
A.DOUGLAS RADEMAKER, P.E. - DIRECTOR
DEPARTMENT OF ENGINEERING
Prepared by:
OF
Clk
4 J.B.DAVIES INC .� •'' .;9 ��
w .
.r ENGINEERS-SURVEYORS r*�' •��* d
F. Pi, i 3C FORT WORTH,TEXAS %*............................:.*1
DAVID C. MATHIESEN !
...............................
93582
01-239989-9191-M I APRIL 2008 r ! •�s pG`
e� o� /CENsE
01 -239989-919 1-MI
, ORIGINAL
01-23-09 P02:02 IN
r
Page 1 of;
City of Fort Worth, Texas
Mayor and Council Communication
COUNCIL ACTION: Approved on 12/9/2008
DATE: Tuesday, December 09, 2008
LOG NAME: 20LOSTCREEKPH2 REFERENCE NO.: C-23228
SUBJECT:
Authorize Contract with Bumsco Construction, Inc., in the Amount of $265,469.00 for Lost Creek
Phase 2 Drainage Improvements
RECOMMENDATION:
It is recommended that the City Council authorize the City Manager to execute a contract with Bumsco
Construction, Inc., in the amount of $265,469.00 for construction of the Lost Creek Phase 2 Drainage
Improvements.
DISCUSSION:
The 2004 Capital Improvement Program (CIP) included funds for the design of capital projects of storm
drain facilities to alleviate recurring flooding problems in various locations. The existence of undersized
drainage facilities has contributed to flooding of homes on Ben Creek Court and Blue Creek Court,
adjacent to the Lost Creek Golf Course, and on Powderhom Road.
On November 30, 2004, the City Manager executed adrriinistratively an engineering agreement with J. B.
Davies, Inc., for the design of the Lost Creek Phase 2 Drainage Improvements.
This design resulted in the recommendation for the construction of storm drain facilities in the following
locations:
. Blue Creek Court, west of Snow Creek Drive to Cul-de-Sac.
. Ben Creek Court, east of Lost Creek Boulevard to south of Dead End.
. Powderhom Road, Lone Pine Road to Little Valley Road.
Available bond funding for the proposed work is not sufficient to complete the project. The Storm Water
Utility Program will provide additional funds to implement the construction of this project.
The project was advertised for bid on April 24 and May 1, 2008, in the Fort Worth Star-Telegram. The
following bids were received on May 22, 2008:
Bidders Amount Time of Completion
Bumsco Construction,Inc. $265,469.00 60 Working Days
Jackson Constuucion TX, LTD $288,255.00
S.H.U.C., Inc. $295,889.00
Humphrey 8 Morton Const. Co., Inc. $304,307.30
Ed A.Wilson, Inc. $320,737.50
Gin-Spen, Inc. $344,961.00
http://apps.cfwnet.org/council_packet/Reports/mc_print.asp 12/10/2008
Page 2 of
Funding in the amount of $25,093.00 is included for associated storm drain and paving construction
survey, project management, pre-construction, materials testing, inspection and project closeout. The
contingency fund for possible change orders for storm drain construction and paving is$13,273.00.
M/WBE — Bumsco Construction, Inc., is in compliance with the City's M/WBE Ordinance by committing to
21 percent M/WBE participation. The City's goal on this project is 20 percent.
This project is located in COUNCIL DISTRICT 3, Mapsco 58X, 71U and V.
FISCAL INFORMATION/CERTIFICATION:
The Financial Management Services Director certifies that funds are available in the current capital
budgets, as appropriated, of the Street Improvements Fund and the Storm Water Capital Projects 2007
Revenue Bonds Fund.
TO Fund/Account/Centem FROM Fund/Account/Centers
C200 541200 203280008783 $198,500.00
P229 541200 203280008783 $66,969.00
Submitted for City Manager's Office by: Fernando Costa (6122)
Originating Department Head: Greg Simmons (7862)
Additional Information Contact: Richard Argomaniz (8653)
http://apps.cfwnet.orgtcouncil_packet/Reportsimc_print.asp 12/10/2008
MAY-16-2008 FR1 04:56 PM CITY F. W. ENGINEERING FAX N0, 817 871 7854 P. 02
CITY OF FORT WORTH
DEPARTMENT OF ENGINEERTNG
FNGINEERING SERVICES DIVISION
ADDENDUM NO. 1
Lost Creek Phase 2 Drainage Improvements
Lost Creek Addition—From Ben Creek Court to Golf Course
Lost Creek Addition—From.Blue Creek Court South to Mary's Creek
Westpoint Addition—From Powderhorn Road to Park Just South of Little Valley Road
TPW Project No. C200 541200 2032900097 83
DOE No.4744
File No. SD-0135
RELEASE DATE: May 16,2008
BIDS RECEIVED: May 22,2008
INFORMATION TO BIDDERS:
The Contract Documents for the above mentioned project are revised and amended as follows:
1. Unit II,DrainAee Improvements:
Add to Special Provision 99 Pay Item-3' x 2% 3' x 3' Reinforced Concrete Box Sections
—"All transitions from RC Box Storm Drain to RCP Storm Drain and/or RC Box Storm
Drains shall be installed with prefabricated transition sections from a City approved pipe
manufacturer or as directed by the Engineer. Alternative Box to RCP and/or Box
transition methodologies may be permitted only if approved by Engineer prior to
construction."
2. Unit 11,Drainage Improvements:
Add Pay Items to Proposal:
SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT
BID
SC.99 47 2 EA, Install Pipe Transition For Proposed RC Box to
SC.100 Existing RCP Storm rain
BID- f.1ut,U' Dollars& $1000.00 $Zoao,o
00542 _. ^Cents Per EA.
SC_99 48 1 EA Install Pipe Transition From Proposed 2'X3'.RC
BID- Box to Proposed 3' 3'RC Box Storm Sewer.
00542 _Dollars& $ D.a D $(XD.OO
Cents Per EA.
SC.12 49 3 EA ,tnta-hol�j Existin San' ry Sewer Service Lines.
BID- � Dollars&
00899 Yt-O Cents Per EA. $SOD•yy $65)
Page I of 2
MAY-16-2008 FRI 04:56 PM CITY F, W, ENGJNEERINd FAX N0, 817 871 7854 P. 03
Please acknowledge receipt of the Addendum in the following locations:
(1) In the space provided below
(2) In the Proposal,Units 11: Drainage Improvements
(3) Indicate in upper case letters on the outside of the sealed bid envelop:
"RECEIVED& ACKNOWLEDGED ADDENDUM NO. 1"
Failure to acknowledge the receipt of Addendum No. 1 could cause the subject bidder to be
considered "NON-RESPONSIVE", resulting in disqualification.
RECEIPT ACKNOWLEDGED: A. DOUGLAS RADEMAKER,P.E.
DIRECTOR,DEPARTMENT OF ENGINEERING
By By:
Dena Johnson,P.E.
Title: �_. `C Program Manager
�r
j ..
h
Page 2 of 2
SPECIFICATIONS
AND
CONTRACT DOCUMENTS
LOST CREEK PHASE 2 DRAINAGE IMPROVEMENTS FOR
BEN CREEK COURT, BLUE CREEK COURT, AND
POWDERHORN ROAD
DRAINAGE IMPROVEMENTS
LOST CREEK ADDITION—FROM BEN CREEK COURT SOUTH TO GOLF COURSE
LOST CREEK ADDITION—FROM BLUE CREEK COURT SOUTH TO MARY'S CREEK
WESTPOINT ADDITION—FROM POWDERHORN ROAD TO PARK JUST SOUTH OF
LITTLE VALLEY ROAD
FILE NO.SD-0135
DOE PROJECT NO. 4744
TPW PROJECT NO. C200 541200 2032800087 83
IN THE CITY OF FORT WORTH,TEXAS
MIKE MONCRIEF DALE A.FISSELER,P.E.
MAYOR CITY MANAGER
FRANK CRUMB,P.E.-DIRECTOR
FORT WORTH WATER DEPARTMENT
GREG SIMMONS,P.E.--ACTING DIRECTOR
DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS
A.DOUGLAS RADEMAKER, P.E. - DIRECTOR
DEPARTMENT OF ENGINEERING
Prepared by:
J.B.DAVIES INC P�P��•O r %;r 1I1
ENGINEERS-SURVEYORS o*r?.•' '�d'*1¢
FORT WORTH,TEXAS j
....:......................... ..Z
DAVID C.MATHIESEN /
I................................/
ar/ •o: 93582
APRIL 2008 I1tllp�cc I��ENSE. •.
�`L
TABLE OF CONTENTS
1. Notice to Bidders
2. Comprehensive Notice to Bidders
3. Prevailing Wage Rates
4. Compliance with and Enforcement of Prevailing Wage Laws
5. Special Instructions to Bidders(TPW)
6. Special Instructions to Bidders(Water)
7. Proposal
8. Statement of Materials and Other Charges
9. Conflict of Interest Disclosure Requirement
10. Conflict of Interest Questionnaire(Form CIQ)
11. Vendor Compliance to State Law
12. Minority and Women Business Enterprises Specifications
13. Subcontractors/Suppliers Utilization Form
14. Prime Contractor Waiver Form
15. Good Faith Effort Fora
16. Joint Venture Eligibility Form
_ 17. Special Provisions
18. `Green'Cement Policy Compliance Statement
19. Details
20. Permits/Easements
21. Certificate of Insurance
22. Contractor Compliance With Worker's Compensation Law
23. Equipment Schedule
— 24. Experience Record
25. Performance Bond
26. Payment Bond
_ 27. Maintenance Bond
28. Contract
UN
NOTICE TO BIDDERS
Sealed Proposals for the following:
2004 CAPITAL IMPROVEMENT PROGRAM
LOST CREEK PHASE 2 DRAINAGE IMPROVEMENTS FOR:
BLUE CREEK COURT,BEN CREEK COURT,AND POWDERHORN ROAD
D.O.E.NO.4744
PROJECT NO. C200 641200 2032800087 83
Addressed to Mr. Dale Fisseler, City Manager of the City of Fort Worth, Texas, will be received at
the Purchasing Office until 1:30 P.M., Thursdpy, May 22 , 2008, and then publicly opened and
read aloud at 2:00 p.m., In the Council Chambers. Plans, Specifications and Contract Documents
for this project may be purchased at the office of the Department of Engineering, Municipal Office
Building, 1000 Throckmorton Street, Fort Worth, Texas. One set of plans and documents may be
purchased for a non-refundable cost of thirty dollars($30.00)per set.
Bidders shall not separate, detach, or remove any portion, segment or sheets from the contract
documents at any time. Bidders`must complete the proposal sections and submit the complete
specifications book or face rejection'of bid as non-responsive.
The major work on the referenced project consists of the following:
48 LF 24"Class III RCP
121 LF 30"Class III RCP
103 LF 3'X2' Reinforced Concrete Box Storm Sewer
307 LF TXT Reinforced Concrete Box Storm Sewer
1 Standard 4' Storm Manhole
1 Standard 5' Storm Manhole
For additional information concerning this project, please contact David Mathiesen, P.E., Project
Manager at the office of J. B. Davies, Inc. (817) 870-0056 or Richard Argomaniz, P.E. Project
.. Manager, at the City of Fort Worth, (817)392-8653.
A pre-bid conference will be held on Wednesday, May 14, 2008 at 11:00 a.m., In the Department
of Transportation and Public Works Conference Room, Room 270, 2nd Floor, City Municipal
Building, 1000 Throckmorton Street, Fort Worth, Texas. Bidders are encouraged to review the
plans and specifications prior to the pre-bid conference.
Department of Engineering
A Douglas Rademaker, Director
Advertising Dates:
April 24, 2008
i
May 1, 2008
01 Nofte to Biddwr_Rev.doo
COMPREHENSIVE NOTICE TO BIDDERS
Sealed proposals for the following:
2004 CAPITAL IMPROVEMENT PROGRAM
LOST CREEK PHASE 2 DRAINAGE IMPROVEMENTS.FOR
BLUE CREEK COURT,BEN CREEK COURT AND POWDERHORN ROAD:
DRAINAGE IMPROVEMENTS
LOST CREEK ADDITION.—FROM.BLUE CREEK COURT SOUTH TO MARY`S'CREEK
LOST CREEK ADDITION-FROM BEN CREEK COURT SOUTH TO GOLF COURSE
WEST POINT ADDITION-FROM POWDERHORN ROAD.TO PARK JUST SOUTH OF LITTLE:
VALLEY ROAD
0.0:e.NO.4744
CITY PROJECT NO.C200 641.200 2032800087 83
Addressed to Mr. Dale Fisseler, City Manager of the City of Fort Worth,-Teicas,.:will be recelved at
.,tha ,Purchasing Office until 1,.30 p.m. on Thursday May 22, 2008 and then publicly opened.'and
read.aloud at 2:00 p.m.in the Council Chambers. Plans, specifications, and contract documents for'
this. project may be obtained.at the 'office of the Department of Engineering, Municipal: Office.:
.. :Building. 1000 Throckmorton Street, Fort Worth, Texas. A..set of plans and..documents may be
purchased on a ton-refundable basis for thirty dollars ($30.00) for'each set. These docurnetits.
contain additional information for prospective bidders.
,All:bidders will be required to comply with'provision 5159a of 'Vernon s.Annotated.Civi[Statutee of
the State of Texas with respect to.the payment of prevailing.Wage rates..and City.Ordinance'No
.7218,as amended by City,Ordinance No:.7400(Fort Worth City Cade Sections 13-Ar21 through.1.3-
.A:29),prohibiting discrimination in employment practices.
Bid:security is required in accordance with Paragraph 2 of the Special Instructions to.Bidders.
.The .major work on the above project shall generally consist of fhe following (quantities sMr+t!
approximate):
48 LF 24"Class III RCP
121 LF 30"Class III RCP
103.I F 3'X2'Reinforced Concrete Box Storm Sewer:
307 LF . 3'X3'Reinforced Concrete Box Storm Sewer.
I Standard 4'Storm MaWidle
1 Standard 5'Storm Manhole
Included in:the above will be all other items of construction as outlined in the plans and
Specifications.
Construction time is§0 Working Days
AWARD OF CONTRACT: The City reserves the right to reject any and/or all bids and waive::any
and/or all formalities. No bid may be withdrawn until the expiration of ninety(90)days from the*date
of receipt.of Contractor's documents. The award of contract, If made,will be within nine. (90)days
after the opening of bids, but in no case will the award be made until all the.necessary investigations
are made.as to the responsibility of the bidder to whom it is proposed .to award the contract.
Bidders shall. not separate, detach, or remove any portion, segment, or sheets from;the contract
document at any time. Bidders must complete the proposal sections and submit the complete
specifications book or face rejection of the bid as non-responsive.
Bidders are responsible for obtaining all addenda to the contract.documents_and acknowledging
.0 receipt of the addenda by initialing the appropriate spaces on the Proposal form. Bids that do.not
acknowledge receipt of all addenda may be rejected as being non-responsive. Information.
HEAVY&HIGHWAY CONSTRUCTION
PREVAILING WAGE RATES 2008
Air Tool Opera
for $10.06
Asphalt Distributor Operator $13.99
Asphalt Paving Machine r $12.78
Asphalt Raker $11.01
Asphalt Shoveler $ 8.80
Batching Plant Weigher $14.15
Broom or Sweeper Operator $ 9.88
.� Bulldozer QpgqDr $13.22
Cwpenter $12.80
Concrete Finisher,Paving $12.85
Concrete Finisher,Structures $13.27
Concrete Paving Curbing Machine Operator $12.00
Concrete Pa-vinj Finishing MachineOperator_ $13.63
Concrete Paving Joint Sealer Operator $12.50
.� Concrete eavipA Saw Operator $13.56
Concrete Paving Spreader Operaq $14.50
Concrete Rubber $10.61
Crane,Clamshell,Backhoe Derrick,Dragline,Shoves O rator $14.12
Electrician $18.12
Flagger $ 8.43
Form Builder/Setter Structures $11.63
Form Setter,Paving&Curb $11.83
Foundation Drill Operator,Crawler Mounted $13.67
Foundation Drill Operator,Truck Mounted $16.30
Front End Loader Operator $12.62
Laborer,Common $ 9.18
Laborer,Utility $10.65
Mechanic $16.97
Milling Machine Operator,Fine Grade $11.83
Mixer Operator $11.58
Motor Grader OpSator,Fine Grade $15.20
Motor Grader razor,Rough $14.50
.• Oiler $14.98
Painter,Structures $13.17
Pavement Marking Machine Operator $10.04
Pi la er $11.04
.. Reinforcing Steel Setter,Paving $14.86
Reinforcing Steel Setter,Structure $16.29
Roller Operator,Pneumatic,Self-Propelled $11.07
Roller Operator,Steel Wheel,Flat Wheel/Tamping Wheel/Tamping $10.92
Roller Operator,Steel Wheel,Plant Mix Pavement $11.28
Scraper Operator $11.42
Servicer $12.32
Slip Form Machine Operator $12.33
Spreader Box Operator $10.92
Tractor Operator,Crawler Tye $12.60
Tractor Op5rator,Pneumatic $12.91
Traveling Mixer Operator $12.03
Truck Driver,Lowboy-Float $14.93
Truck Driver Single Axle,Heavy $1 I.47
Truck Driver,Single Axle,Light $10.91
Truck Driver,Tandem Axle,Semi-Trailer $11.75
Truck Driver,Transit-Mix $12.08
Wagon Drill,Boring Machine,Post Hole Driller Operator $14.00
Welder $13.57
Work Zone Barricade Servicer $10.09
Comuliance with and Enforcement of Prevailing Wage Laws
(a) Duty to pay Prevailing Wage Rates. The contractor shall comply with all
requirements of Chapter 2258, Texas Government Code(Chapter 2258),
including the payment of not less than the rates determined by the City Council of
the City of Fort Worth to be the prevailing wage rates in accordance with Chapter
2258. Such prevailing wage rates are included in these contract documents.
(b) Penalty for Violation. A contractor or any subcontractor who does not pay the
prevailing wage shall,upon demand made by the City,pay to the City$60 for
each worker employed for each calendar day or part of the day that the worker is
paid less than the prevailing wage rates stipulated in these contract documents.
This penalty shall be retained by the City to offset its administrative costs,
pursuant to Texas Government Code 2258.023.
.L
(c) Complaints of Violations and City Determination of Good Cause. On receipt of
information, including a complaint by a worker, concerning an alleged violation
of 2258.023,Texas Government Code,by a contractor or subcontractor,the City
shall make an initial determination,before the 31 sc day after the date the City
receives the information, as to whether good cause exists to believe that the
violation occurred. The City shall notify in writing the contractor or
subcontractor and any affected worker of its initial determination. Upon the
City's determination that there is good cause to believe the contractor or
subcontractor has violated Chapter 2258,the City shall retain the full amounts
claimed by the claimant or claimants as the difference between wages paid and
wages due under the prevailing wage rates, such amounts being subtracted from
successive progress payments pending a final determination of the violation.
(d) Arbitration Required if Violation Not Resolved. An issue relating to an alleged
LL violation of Section 2258.023,Texas Government Code,including a penalty owed
to the City or an affected worker, shall be submitted to binding arbitration in
accordance with the Texas General Arbitration Act(Article 224 et seq.,Revised
Statutes)if the contractor or subcontractor and any affected worker do not resolve
the issue by agreement before the 15th day after the date the City makes its initial
determination pursuant to paragraph(c)above. If the persons required to arbitrate
under this section do not agree on an arbitrator before the 1 lth day after the date
that arbitration is required,a district court shall appoint an arbitrator on the
petition of any of the persons. The City is not a party in the arbitration. The
`y decision and award of the arbitrator is final and binding on all parties and may be
enforced in any court of competent jurisdiction.
(e) Records to be Maintained. The contractor and each subcontractor shall, for a
period of three(3)years following the date of acceptance of the work,maintain
records that show(i)the name and occupation of each worker employed by the
contractor in the construction of the work provided for in this contract; and(ii)the
actual per diem wages paid to each worker. The records shall be open at all
COMPREHENSIVE NOTICE To:isIaDERs
regarding the status of addenda may be obtained by contacting the.Department of Engineering at
(817)3924910.'
In accord with the City of Fort Worth Ordinance No .15530, the City of Fort Worth has:goals for the.
participation of"m1n6nty business enterprises and:i Omen business enterprises.in City contracts: A--
copy'of the,Ordinance can be obtained from the Office of the City Secretary,: rra add�r;on,the btddsl
shall submit.the:MBEIWBE UTILIZATION FORM;. SUB.CbNTRACTOR/ SUPPLIER: UT:ILZATION: `
FORM, PRIME CONTRACTOR WAIVER FORM"GOOD FAITH EFFORT FORM and/or the-JalNT:
VENTURE FORM.("Documentation") q0 appropriate, The Documentation must be received by the
, .
managing de artment no later than 5:00
9 g P
p;m.; anthin..five:(5).Gity business days after bid'opening• :•
:date. The bidder shall obtain a receipt from the appropriate employee of the managing:department
to whom delivery.was made. Such receipt shall Ike dvddenee that the Documentation was received
by the City. Failure tb comply shall render the bid nonresponsive.
• The water and sanitary:sewer;work must be performed by:a.contractor that is pre-qualified by the
Water Department.at the time of the bid opening. A general contractor, who is not pre-qualified:by
the Water Department, must employ the services of a: sub-contractor who is. pre-qualified. -The-
procedure for pre-qualification is outlined in the"Special Instructions to Bidders(Water—Sewer)".
The:Managing Department for this project Is the Department of Engineering.
For additional Information concerning this proJegk..please,contact David Mathieseri,. P.E, Project
Manager at..the offces of J. B: Davies, Inc., (817) 870-0i?56 or RichardArgomaniz,-.p:.E, Project.
Manager at the.Cityof FortW- orth,(817)392-8651..
A: rebid p , conference will tie held on Wednesdajr; May 14.2d08 at 11:00 a.m.,in.the:Department.ctf
Transportation.and Public blocks Conference Room, Room 270;.2nd Floor, City Municipal:B:UIiding,.•
10l)0 Tlirockmorton.Street, Fort Worth, Texas. Bidders° are encouraged to review the ptaris and
specifications:prior io the pre-bid conference..
DALE A. FISSELER; P.E..
CITY MANAGER
MARTY HENDRIX
CITY SECRETARY
'r A DOUGLAS:,RADEMAKER P.E., DIRECTOR
DEPARTMENT OF ENGINEERING
` By: t•- tCLI
F Dena:Iohnson, P.E.M nager, Engineering Services
Advertising Dates:
Aorfi 24.2008
j.11Nay:,2008
a11i
2006 PREVAILING WAGE RATES
CONSTRUCTION INDUSTRY
_ AC Mechanic $21.69 Plumber $20.43
AC Mechanic Helper $12.0D Plumber Helper $14.90
Acoustical Ceiling Mechanic $15.24 Reinforcing Steel Setter $10.00
Bricklayer/Stone Mason $19.12 Roofer $14.00
Bricklayer/Stone Mason Helper $10.10 Roofer Helper $10.00
Carpenter $16.23 Sheet Metal Worker $16.96
Carpenter Helper $11.91 Sheet Metal Worker Helper $12.31
Concrete Finisher $13.49 Sprinkler System Installer $18.00
Concrete Form Builder $13.12 Sprinkler System Installer Helper $9.00
.� Drywall Mechanic $14.62 Steel Worker Structural $17.43
Drywall Hel r $10.91 Concrete Pump $20.50
Cranes Clamsheet,Backhoe,Derrick,DLine
Drywall Taper $13.00 Shovel $17.76
Drywall Taper Helper $9,00 Forklift $12.63
Electrician(Journeyman) $20.20 Front End Loader $10,50
Electrician Helper $14.43 Truck Driver $14.91
Electronic Technician $19.86 Welder $16.06
Electrons[Technician Helper I $1Z.00 Welder Helper $9.75
Floor Layer(Resilient) $20.00
.� Floor Layer Helper $13.00
Glazier $18.OD
.� Glazier Helper $13.00
Insulator $14.78
Insulator Helper $11,25
Laborer Common $10,27
Laborer Skilled $13.18
Lather $16.10
Painter $14.83
Painter Helper $8.00
Pipefitter $18.85
Y Pi efitter Helper $12.83
Plasterer $17.25
Plasterer Het r $12.25
mo
(f) reasonable hours for inspection by the City. The provisions of the Audit section
of these contract documents shall pertain to this inspection.
_. (g) Eay Estimates. With each partial payment estimate or payroll period,whichever
is less;the contractor shall submit an affidavit stating that the contractor has
complied with the requirements of Chapter 2258, Texas Government Code.
(h) Postingof f Wage Rates. The contractor shall post the prevailing wage rates in a
conspicuous place at the site of the project at all times.
(i) Subcontractor Compliance. The contractor shall include in its subcontracts
and/or shall otherwise require all of its subcontractors to comply with paragraphs
(a)through(g)above.
SPECIAL INSTRUCTION TO BIDDERS
(TRANSPORTATION AND PUBLIC WORKS)
1. BID SECURITY: Cashier's check or an acceptable bidder's bond payable to the City of
Fort Worth, in an amount of not less than five(5%)per cent of the total of the bid submitted
must accompany the bid, and is subject to forfeit in the event the successful bidder fails to
execute the contract documents within ten(10)days after the contract has been awarded.
To be an acceptable surety on the bid bond, the surety must be authorized to do business in
the state of Texas. In addition, the surety must (1) hold a certificate of authority from the
United States secretary of the treasury to qualify as a surety on obligations permitted or
required under federal law; or (2) have obtained reinsurance for any liability in excess of
$100,000 from a reinsurer that is authorized and admitted as a reinsurer in the state of Texas
and is the holder of a certificate of authority from the United States secretary of the treasury
to qualify as a surety on obligations permitted or required under federal law. Satisfactory
proof of any such reinsurance shall be provided to the City upon request. The City, in its
sole discretion,will determine the adequacy of the proof required herein.
2. PAYMENT, PERFORMANCE AND MAINTENANCE BONDS: The successful bidder
entering into a contract for the work will be required to give the City surety in a sum equal to
the amount of the contract awarded. In this connection, the successful bidder shall be
required to furnish a performance bond and a payment bond, both in a sum equal to the
amount of the contract awarded. The form of the bond shall be as herein provided and the
surety shall be acceptable to the City. All bonds furnished hereunder shall meet the
requirements of Chapter 2253,Texas Government Code.
In order for a surety to be acceptable to the City, the surety must (1) hold a certificate of
authority from the United States secretary of the treasury to qualify as a surety on obligations
permitted or required under federal law; or(2) have obtained reinsurance for any liability in
excess of$100,000 from a reinsurer that is authorized and admitted as a reinsurer in the state
of Texas and is the holder of a certificate of authority from the United States secretary of the.
treasury to qualify as a surety on obligations permitted or required under federal law.
Satisfactory proof of any such reinsurance shall be provided to the City upon request. The
City,in its sole discretion,will determine the adequacy of the proof required herein.
The City will accept no sureties who are in default or delinquent on any bonds or who have
an interest in any litigation against the City. Should any surety on the contract be determined
unsatisfactory at any time by the City,notice will be given to the contractor to that effect and
the contractor shall immediately provide a new surety satisfactory to the City.
If the contract amount is in excess of$25,000, a Payment Bond shall be executed, in the
amount of the contract, solely for the protection of all claimants supplying labor and
materials in the prosecution of the work.
If the contract amount is in excess of$100,000, a Performance Bond shall be executed, in
the amount of the contract conditioned on the faithful performance of the work in accordance
10/27/04 1
_ with the plans, specifications, and contract documents. Said bond shall solely be for the
protection of the City of Fort Worth.
All contracts shall require a Maintenance Bond in the amount of one hundred percent
(100%) of the original contract amount to guarantee the work for a period of two(2) years
after the date of acceptance of the project from defects in workmanship and/or material.
3. LIOUIDATED DAMAGES: The Contractor's attention is called to Part 1, Item 8,
paragraph 8.6,of the"General Provisions"of the Standard Specifications for Construction of
the City of Fort Worth, Texas, concerning liquidated damages for late completion of
projects.
4. AMBIGUITY:In case of ambiguity or lack of clearness in stating prices in the proposal,the
City reserves the right to adopt the most advantageous construction thereof to the City or to
reject the proposal.
5. EMPLOYMENT: All bidders will be required to comply with City Ordinance No. 7278 as
amended by City Ordinance No.7400 (Fort Worth City Code Section 13-A-21 through 13-a-
29)prohibiting discrimination in employment practices.
6. WAGE RATES: Section 8.8 of the Standard Specifications for Street and Storm Drain
Construction is deleted and replaced with the following:
(a) The contractor shall comply with all requirements of Chapter 2258, Texas Government
_ Code, including the payment of not less than the rates determined by the City Council of the
City of Fort Worth to be the prevailing wage rates in accordance with Chapter 2258, Texas
Government Code. Such prevailing wage rates are included in these contract documents.
(b) The contractor shall,for a period of three(3)years following the date of acceptance
of the work, maintain records that show (i) the name and occupation of each worker
employed by the contractor in the construction of the work provided for in this contract; and
(ii) the actual per diem wages paid.to each worker. These records shall be open at all
reasonable hours for inspection by the City. The provisions of the special provision titled
"Right to Audit"pertain to this inspection.
(c) The contractor shall include in its subcontracts and/or shall otherwise.require all of
its subcontractors to comply with paragraphs(a)and(b)above.
(d) With each partial payment estimate or payroll period, whichever is less, an affidavit
stating that the contractor has complied with the requirements of Chapter 2258, Texas
Government Code.
(e) The contractor shall post the prevailing wage rates in a conspicuous place at the site
of the project at all times.
Section 8.9 of the Standard Specifications for Street and Storm Drain Construction is hereby
deleted.
10/27/04 2
7. FINANCIAL STATEMENT:A current certified financial statement may be required by the
Department of Engineering if required for use by the CITY OF FORT WORTH in
determining the successful bidder. This statement, if required, is to be prepared by an
independent Public Accountant holding a valid permit issued by an appropriate State
Licensing Agency.
8. INSURANCE: Within ten(10)days of receipt of notice of award of contract,the Contractor
must provide, along with executed contract documents and appropriate bonds, proof of
insurance for Worker's Compensation and Comprehensive General Liability(Bodily Injury-
$500,000 each person, $1,000,000 each occurrence ($2,000,000 aggregate limit); Property
Damage - $250,000 each occurrence). The City reserves the right to request any other
insurance coverage as may be required by each individual project.
,. 9. ADDITIONAL INSURANCE REQUIREMENTS:
a. The City, its officers,employees and servants shall be endorsed as an additional insured
on Contractor's insurance policies excepting employer's liability insurance coverage under
Contractor`s workers'compensation insurance policy.
b. Certificates of insurance shall be delivered to the City of Fort Worth, contract
administrator in the respective department as specified in the bid documents, 1000
Throckmorton Street, Fort Worth, TX 76102, prior to commencement of work on the
contracted project.
c. Any failure on part of the City to request required insurance documentation shall not
constitute a waiver of the insurance requirements specified herein.
d. Each insurance policy shall be endorsed to provide the City a minimum thirty days notice
of cancellation,non-renewal,and/or material change in policy terms or coverage. A ten days
notice shall be acceptable in the event of non-payment of premium.
e. Insurers must be authorized to do business in the State of Texas and have a current A.M.
Best rating of A:VII or equivalent measure of financial strength and solvency.
f. Deductible limits, or self-funded retention limits, on each policy must not exceed
$10,000.00 per occurrence unless otherwise approved by the City.
g. Other than worker's compensation insurance, in lieu of traditional insurance, City may
consider alternative coverage or risk treatment measures through insurance pools or risk
retention groups.The City must approve in writing any alternative coverage.
h. Workers'compensation insurance policy(s) covering employees employed on the project
shall be endorsed with a waiver of subrogation providing rights of recovery in favor of the
City.
i. City shall not be responsible for the direct payment of insurance premium costs for
contractor's insurance.
j. Contractor's insurance policies shall each be endorsed to provide that such insurance is
primary protection and any self-funded or commercial coverage maintained by City shall not
be called upon to contribute to loss recovery.
10/27/04 3
Now
k. In the course of the project, Contractor shall report, in a timely manner, to City's
officially designated contract administrator any known loss occurrence which could give rise
to a liability claim or lawsuit or which could result in a property loss.
Contractor's liability shall not be limited to the specified amounts of insurance required
herein.
m. Upon the request of City, Contractor shall provide complete copies of all insurance
policies required by these contract documents.
10. NONRESIDENT BIDDERS: Pursuant to Article 601g, Texas Revised Civil Statutes, the
City of Fort Worth will not award this contract to a non resident bidder unless the
nonresident's bid is lower than the lowest bid submitted by a responsible Texas resident
bidder by the same amount that a Texas resident bidder would be required to underbid a
nonresident bidder to obtain a comparable contract in the state in which the nonresident's
principal place of business is located.
"Nonresident bidder" means a bidder whose principal place of business is not in this state,
but excludes a contractor whose ultimate parent company or majority owner has its principal
place of business in this state.
"Texas resident bidder"means a bidder whose principal place of business is in this state,and
includes a contractor whose ultimate parent company or majority owner has its principal
place of business in this state.
This provision does not apply if this contract involves federal funds.
The appropriate blanks of the Proposal must be filled out by all non resident bidders in order
for its bid to meet specifications. The failure of a nonresident contractor to do so will
automatically disqualify that bidder.
I L MINORITY AND WOMEN BUSINESS ENTERPRISES: In accordance with City of
_ Fort Worth Ordinance No. 15530,the City of Fort Worth has goals for the participation of
minority business enterprises and women business enterprises in City contracts. A copy of
the Ordinance can be obtained from the Office of the City Secretary. The bidder shall submit
the MBE/WBE UTILIZATION FORM SUBCONTRACTOR/SUPPLIER UTILIZATION
FORM, PRIME CONTRACTOR WAIVER FORM, and/or the GOOD FAITH EFFORT
FORM ("with Documentation") and/or the JOINT VENTURE FORM as appropriate. The
Documentation must be received by the managing department no later than 5:00 p.m., five
(5)City business days after the bid opening date. The bidder shall obtain a receipt from the
appropriate employee of the managing department to whom delivery was made. Such receipt
shall be evidence that the documentation was received by the City. Failure to comply shall
render the bid non-responsive.
Upon request, Contractor agrees to provide the Owner complete and accurate information
regarding actual work performed by a minority business enterprise (MBE) and/or women
business enterprise(WBE)on the contract and payment thereof. Contractor further agrees to
10/27/04 4
permit any audit and/or examination of any books, records or files in its possession that will
substantiate the actual work performed by an MBE and/or WBE. The misrepresentation of
facts (other than a negligent misrepresentation) and/or commission of fraud by the
Contractor will be grounds for termination of the contract and/or initiating action under
appropriate Federal, State or local laws or ordinances relating to false statements. Further,
any such misrepresentation facts (other than a negligent misrepresentation) and/or
commission of fraud will result in the Contractor being determined to be irresponsible and
barred from participating in City work for a period of time of not less that three(3)years.
12. AWARD OF CONTRACT: Contract will be awarded to the lowest responsive bidder. The
City reserves the right to reject any and/or all bids and waive any and/or all irregularities.
No bid may be withdrawn until the expiration of ninety(90)days from the date the M/WBE
UTILIZATION FORM, PRIME CONTRACTOR WAIVER FORM, GOOD FAITH
EFFORT FORM, and/or the JOINT VENTURE FORM("Documentation")as appropriate is
received by the City. The award of contract, if made, will be within ninety (90) days after
this documentation is received, but in no case will the award be made until all the
responsibility of the bidder to whom it is proposed to award the contract has been verified.
13. PAYMENT; The Contractor will receive full payment (minus retainage) from the .City for
all work for each pay period. Payment of the remaining amount shall be made with the final
payment,and upon acceptance of the project.
14. ADDENDA: Bidders are responsible for obtaining all addenda to the contract documents
prior to the bid receipt time and acknowledging them at the time of bid receipt. Information
regarding the status of addenda may be obtained by contacting the Plans Desk of the
Department of Engineering Construction Division at (817) 392-7910. Bids that so not
acknowledge all applicable addenda may be rejected as non-responsive.
15. CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW:
A.Workers Compensation Insurance Coverage
a.Definitions:
Certificate of coverage ("certificate"). A copy of a certificate of insurance, a
certificate of authority to self-insure issued by the commission, or a coverage
agreement (TWCC-81, TWCC-82, TWCC-83, or TWCC-84), showing statutory
worker's compensation insurance coverage for the person's or entity's employees
providing services on a project,for the duration of the project.
Duration of the project-includes the time from the beginning of the work on the
project until the contractor's/person's work on the project has been completed and
accepted by the governmental entity.
Persons providing services on the project("subcontractor" in 9406.096)-includes all
persons or entities performing all or part of the services the contractor has
undertaken to perform on the project, regardless of whether that person contracted
directly with the contractor and regardless of whether that person has employees.
This includes, without limitation, independent contractors, subcontractors, leasing
companies, motor carriers, owner-operators, employees of any such entity, or
10/27/04 5
employees of any entity that furnishes persons to provide services on the project.
"Services" include, without limitation, providing, hauling, or delivering equipment
or materials, or providing labor,transportation, or toner services related to a project.
"Services"does not include activities unrelated to the project,such as food/beverage
vendors,office supply deliveries,and delivery of portable toilets.
b. The contractor shall provided coverage, based on proper reporting of
classification codes and payroll amounts and filing of any coverage agreements,
which meets the statutory requirements of Texas Labor Code, Section 401.011
(44) or all employees of the contractor providing services on the project, for the
duration of the project.
c. The Contractor must provide a certificate of coverage to the governmental entity
prior to being awarded the contract.
d. If the coverage period shown on the contractor's current certificate of coverage
ends during the duration of the project, the contractor must, prior to the end of
the coverage period, file a new certificate of coverage with the governmental
entity showing that coverage has been extended.
e. The contractor shall obtain from each person providing services on a project,and
provide to the governmental entity:
(1) a certificate of coverage, prior to that person beginning work on the project,
4 so the governmental entity will have on file certificates of coverage showing
coverage for all persons providing services on the project;and
(2) no later than seven days after receipt by the contractor, a new certificate of
coverage showing extension of coverage, if the coverage period shown on
the current certificate of coverage ends during the duration of the project.
£ The contractor shall retain all required certificates of coverage for the duration
of the project and for one year thereafter
g. The contractor shall notify the governmental entity in writing by certified mail or
personal delivery, within ten (10) days after the contractor knew or should have
known, of any change that materially affects the provision of coverage of any
person providing services on the project.
h. The contractor shall post on each project site a notice, in the text, form and
manner prescribed by the Texas Worker's Compensation Commission,
informing all persons providing services on the project that they are required to
be covered, and stating how a person may verify coverage and report lack of
coverage.
.. I. The contractor shall contractually require each person with whom it contracts to
provide services on a project,to:
(1) provide coverage, based on proper reporting on classification codes and
F payroll amounts and filing of any coverage agreements, which meets the
10/27/04 6
statutory requirements of Texas labor Code, Section 401.011 (44) for all of
its employees providing services on the project, for the duration of the
project;
(2) provide to the contractor,prior to that person beginning work on the project,
a certificate of coverage showing that coverage is being provided for all
employees of the person providing services on the project,for the duration of
the project;
(3) provide the contractor, prior to the end of the coverage period, a new
certificate of coverage showing extension of coverage, if the coverage period
shown on the current certificate of coverage ends during the duration of the
project;
(4) obtain from each other person with whom, it contracts, and provide to the
contractor:
(a) a certificate of coverage, prior to the other person beginning work on
the project;and
(b) a new certificate of coverage showing extension of coverage, prior to
the end of the coverage period, if the coverage period shown on the
current certificate of coverage ends during the duration of the project;
(5) retain all required certificates of coverage on file for the duration of the
project and for one year thereafter.
(6) notify the governmental entity in wiring by certified mail or personal
delivery, within ten(10) days after the person knew or should have known,
of any change that materially affects the provision of coverage of any person
providing services on the project;and
(7) contractually require each person with whom it contracts, to perform as
required by paragraphs (1) - (7), with the certificates of coverage to be
provided to the person for whom they are providing services.
j. By signing this contract or providing or causing to be provided a certificate of
coverage, the contractor is representing to the governmental entity that all
employees of the contractor who will provide services on the project will be
covered by worker's compensation coverage for the duration of the project, that
the coverage will be based on proper reporting of classification codes and
payroll amounts, and that all coverage agreements will be filed with the
appropriate insurance carrier or, in the case of a self insured, with the
commission's Division of Self-Insurance Regulation. Providing false or
misleading information may subject the contractor to administrative, criminal,
civil penalties or other civil actions.
k. The contractor's failure to comply with any of these provisions is a breach of
contract by the contractor does not remedy the breach within ten days after
receipt of notice of breach from the governmental entity.
10/27/04 7
B. The contractor shall post a notice on each project site informing all persons providing
services on the project that they are required to be covered, and stating how a person may
verify current coverage and report failure to provide coverage. This notice does not satisfy
other posting requirements imposed by the Texas Worker's Compensation Act or other
Texas Worker's Compensation Commission rules. This notice must be printed with a title in
at least 30-point bold type and text in at least 19-point normal type, and shall be in both
English and Spanish and any other language common to the worker population. The text for
the notices shall be the following text,without any additional words or changes:
"REQUIRED WORKER'S COMPENSATION COVERAGE"
The law requires that each person working on this site or providing services related to this
construction project must be covered by worker" compensation insurance. This includes
•• persons providing, hauling or delivering equipment or materials, or providing labor or
transportation or other service related to the project, regardless of the identity of their
employer or status as an employee".
Call the Texas Worker's Compensation Commission at 512-440-3789 to receive information
on the legal requirement for coverage, to verify whether your employer has provided the
required coverage,or to report an employer's failure to provide coverage".
16. NON-DISCREVIINATION: The contractor shall not discriminate against any person or
persons because of sex, race, religion, color,-or national origin and shall comply with the
provisions of City Ordinance 7278, as amended by City Ordinance 7400 (Fort Worth City
Code Sections 13A-21 through 13A-29),prohibiting discrimination in employment practices.
17. AGE DISCRIMINATION: In accordance with the policy ("Policy') of the Executive
Branch of the federal government,contractor covenants that neither it nor any of its officers,
members, agents, or employees, while engaged in performing this contract, shall, in
connection with the employment, advancement or discharge of employees or in connection
with the terms, conditions or privileges of their employment, discriminate against person
because of their age except on the basis of a bona fide occupational qualification, retirement
plan or statutory requirement.
Contractor further covenants that neither it nor its officers, members, agents, or employees,
or person acting on their behalf, shall specify, in solicitations or advertisements for
employees to work on this Contract, a maximum age limit for such employment unless the
specified maximum age limit is based upon a bona fide occupational qualification,retirement
plan or statutory requirement.
Contractor warrants it will fully comply with the Policy and will defend, indemnify and hold
City harmless against any and all claims or allegations asserted by third parties against City
arising out of Contractor's alleged failure to comply with the above referenced Policy
concerning age discrimination in the performance of this Contract.
18. DISCRIMINATION DUE TO DISABILITY: In accordance with the provisions of the
Americans with Disabilities Act of 1990 ("ADA"), Contractor warrants that it will not
unlawfully discriminate on the basis of disability in the provision of services to the general
public, nor in the availability, terms and/or conditions of employment for applicants for
employment with, or current employees of Contractor. Contractor warrants it will fully
10/27/04 g
comply with ADA's provisions and any other applicable federal state and local laws
concerning disability and will defend indemnify and hold City harmless against any claims or
allegations asserted by third parties against City arising out of Contractor's alleged failure to
comply with the above-referenced laws concerning disability discrimination in the
performance of this Contract.
19. PROGRESS PAYMENTS, FINAL PAYMENT, PROJECT ACCEPTANCE AND
WARRANTY:
a. The contractor will receive full payment (less retainage) from the city for each pay
period.
b. Payment of the retainage will be included with the final payment after acceptance of the
project as being complete.
c. The project shall be deemed complete and accepted by the City as of the date the final
punch list has been completed, as evidenced by a written statement signed by the
contractor and the City.
_ d. The warranty period shall begin as of the date that the final punch list has been
completed.
e. Bills Paid Affidavit and Consent of Surety shall be required prior to final payment
becoming due and payable.
f. In the event that the Bills Paid Affidavit and Consent of Surety have been delivered to
the city and there is a dispute regarding (i) final quantities, or (ii) liquidated damages,
City shall make a progress payment in the amount that city deems due and payable.
g. In the event of a dispute regarding either final quantities or liquidated damages, the
parties shall attempt to resolve the differences within 30 calendar days.
10/27/04 9
SPECIAL INSTRUCTIONS TO BIDDERS
l) PI-.EQUALIFICATION REQUIREMENTS: All contractors submitting bids are required to be
prequalified by the Fort Worth Water Department prior to submitting bids. This prequalification
process will establish a bid limit based on a technical evaluation and financial analysis of the
contractor. It is the bidder's responsibility to submit the following documentation:a current financial
statement,an acceptable experience record,an acceptable equipment schedule and any other documents
the Department may deem necessary,to the Director of the Water Department at least seven(7)
calendar days prior to the date of the opening of bids.
a) The financial statement required shall have been prepared by an independent certified public
.� accountant or an independent public accountant holding a valid permit issued by an appropriate
State licensing agency and shall have been so prepared as to reflect the financial status to the
submitting company. This statement must be current and not more than one(I)year old. In the
case that a bidding date falls within the time a new statement is being prepared,the previous
statement shall be updated by proper verification.
b) For an experience record to be considered to be acceptable for a given project,it must reflect the
experience of the firm seeking qualification in work of both the same nature and technical level as
that of the project for which bids are to be received.
c) The Director of the Water Department shall be the sole judge as to the acceptability for financial
qualification to bid on any Fort Worth Water Department project.
d) Bids received in excess of the bid limit shall be considered non-responsive and will be rejected as
such.
e) The City,in its sole discretion,may reject any bid for failure to demonstrate experience and/or
expertise.
f) Any proposals submitted by a non-prequalified bidder shall be returned unopened,and if
inadvertently opened,shall not be considered.
g) The City will attempt to notify prospective bidders whose qualifications(financial or experience)
are not deemed to be appropriate to the nature and/or magnitude of the project on which bids are to
be received. Failure to notify shall not be a waiver of any necessary prequalification.
2. BID SECURITY: A cashier's check,or an acceptable bidder's bond,payable to the City of Fort
Worth,in an amount of not less than five(S%)percent of the largest possible total of the bid submitted
must accompany the bid,and is subject to forfeiture in the event the successful bidder fails to execute
the Contract Documents within ten(10)days after the contract has been awarded To be an acceptable
surety on the bid bond,the surety must be authorized to do business in the state of Texas. In addition,
the surety must(1)hold a certificate of authority from the Untied States secretary of the treasury to
qualify as a surety on obligations permitted or required under federal law,or(2)have obtained
reinsurance for any liability in excess of$100,000 from a reinsurer that is authorized and admitted as a
reinsurer in the state of Texas and is the holder of a certificate of authority from the Untied States
secretary of the treasury to qualify as a surety on obligations permitted or required under federal law.
Satisfactory proof of any such reinsurance shall be provided to the City upon request. The City,in its
sole discretion,will determine the adequacy of the proof required herein.
3. BONDS: A performance bond,a payment bond,and a maintenance bond each for one hundred
(100%)percent of the contract price will be required,Reference C 3-3.7.
4. WAGE RATES:
Section C3-3.13 of the General Conditions is deleted and replaced with the following:
09/10/04 1
(a) The contractor shall comply with all requirements of Chapter 2258,Texas Government Code,
including the payment of not less than the rates determined by the City Council of the City of Fort
Worth to be the prevailing wage rates in accordance with Chapter 2258,Texas Government Code.
Such prevailing wage rates are included in these contract documents.
(b) The contractor shall,for a period of three(3)years following.the date of acceptance of the work,
maintain records that show(i)the name and occupation of each worker employed by the contractor in
the construction of the work provided for in this contract;and(U)the actual per diem wages paid to
each worker. These records shall be open at all reasonable hours for inspection by the City. The
provisions of Right to Audit,under paragraph L of Section C 1:Supplementary Conditions To Part C—
General Conditions,pertain to this inspection.
(c) The contractor shall include in its subcontracts and/or shall otherwise require all of its
,�p subcontractors to comply with paragraphs(a)and(b)above.
(d) With each partial payment estimate or payroll period,whichever is less,an affidavit stating that the
contractor has complied with the requirements of Chapter 2258,Texas Government Code.
The contractor shall post the prevailing wage rates in a conspicuous place at the site of the project at all
times.
5. AMBIGUITY: In the case of ambiguity or lack of clearness in stating prices in the Proposal,the City
reserves the right to adopt the most advantageous construction thereof to the City or to reject the
_ Proposal.
6. BIDDER LICENSE: Bidder must be a licensed Contractor in the State of Texas.
7. NONRESIDENT BIDDERS: Pursuant to Article 601g,Texas Revised Civil Statutes,the City of Fort
Worth will not award this contract to a nonresident bidder unless the nonresidents bid is lower than the
lowest bid submitted by a responsible Texas resident bidder by the same amount that a Texas resident
bidder would be required to underbid a nonresident bidder to obtain a comparable contract in the state
in which the nonresident's principal place of business in located.
"Nonresident bidder"means a bidder whose principal place of business is not in this state,but excludes
a contractor whose ultimate parent company or majority owner has its principal place of business in this
state.
This provision does not apply if this contract involves federal funds.
The appropriate blanks of the Proposal must be filled out by all nonresident bidders in order for the bid
to meet specifications. The failure of a nonresident contractor to do so will automatically disqualify
that bidder.
8. PAYMENT: If the bid amount is$25,000.00 or less,the contract amount shall be paid within forty-
five(45)calendar days after completion and acceptance by the City.
9. AGE: In accordance with the policy("Policy")of the Executive Branch of the Federal Government,
Contractor covenants that neither it nor any of its officers,members,agents employees,program
participants or subcontractors,while engaged in performing this contract,shall,in connection with the
employment,advancement or discharge of employees or in connection with the terms,conditions or
privileges of their employment,discriminate against persons because of their age except on the bases of
a bona fide occupational qualification,retirement plan or statutory requirement.
09/10/04 2
_ Contractor further covenants that neither it nor its officers,members,agents,employees,
subcontractors,program participants,or persons acting on their behalf,shall specify,in solicitations or
advertisements for employees to work on this contract,a maximum age limit for such employment
unless the specified maximum age limit is based upon a bona fide occupational qualification,retirement
plan or statutory requirements.
Contractor warrants it will fully comply with the policy and will defend,indemnify and hold City
harmless against any claims or allegations asserted by third parties or subcontractor against City arising
out of Contractor's and/or its subcontractors'alleged failure to comply with the above referenced Policy
concerning age discrimination in the performance of this agreement.
10. DISABILITY: In accordance with the provisions of the Americans With Disabilities Act of 1990
("ADA"),Contractor warrants that it and any and all of its subcontractors will not unlawfully
discriminate on the basis of disability in the provision of services to the general public,nor in the
availability,terms and/or conditions of employment for applicants for employment with,or employees
of Contractor or any of its subcontractors. Contractor warrants it will filly comply with ADA's
provisions and any other applicable federal,state and local laws concerning disability and will defend,
indemnify and hold City harmless against any claims or allegations asserted by third parties or
subcontractors against City arising out of Contractor's and/or its subcontractors'alleged failure to
comply with the above referenced laws concerning disability discrimination in the performance of this
agreement.
11. MINORITY AND WOMEN BUSINESS ENTERPRISES: In accord with City of Fort Worth
Ordinance No. 15530,the City of Fort Worth has goals for the participation of minority business
enterprises and women business enterprises in City contracts. A copy of the Ordinance can be obtained
from the Office of the City Secretary.The bidder shall submit the MBE/WBE UTILIZATION FORM,
SUBCONTRACTOR/SUPPLIER UTILIZATION FORM,PRIME CONTRACTOR WAIVER FORM
and/or the GOOD FAITH EFFORT FORM("with Documentation")and/or the JOINT VENTURE
FORM as appropriate. The Documentation must be received by the managing department no later than
5:00 pm.,five(5)City business days after the bid opening date. The bidder shall obtain a receipt from
the appropriate employee of the managing department to whom delivery was made. Such receipt shall
_ be evidence that the documentation was received by the City. Failure to comply shall render the bid
non-responsive.
Upon request,Contractor agrees to provide the Owner complete and accurate information regarding
actual work performed by a Minority Business Enterprise(MBE)and/or women business enterprise
(WBE)on the contract and payment thereof Contractor frther agrees to permit any audit and/or
examination of any books,records or files in its possession that will substantiate the actual work
performed by an MBE and/or WBE. The misrepresentation of facts(other than a negligent
misrepresentation)and/or commission of fraud by the Contractor will be grounds for termination of the
contract and/or initiating action under appropriate Federal, State or local laws or ordinances relating to
false statements. Further,any such misrepresentation of facts(other than a negligent misrepresentation)
and/or commission of fraud will result in the Contractor being determined to be irresponsible and
barred from participating in City work for a period of time of not less than three(3)years.
12. FINAL PAYMENT,ACCEPTANCE AND WARRANTY:
a. The contractor will receive full payment(less retainage)from the city for each pay period.
b. Payment of the retainage will be included with the final payment after acceptance of the project as
being complete.
C. The project shall be deemed complete and accepted by the City as of the date the final punch list
has been completed,as evidenced by a written statement signed by the contractor and the City.
09/10/04 3
_ d. The warranty period shall begin as of the date that the final punch list has been completed
e. Bills Paid Affidavit and Consent of Surety shall be required prior to final payment becoming due
and payable.
f. In the event that the Bills Paid Affidavit and Consent of Surety have been delivered to the city and
there is a dispute regarding(i)final quantities,or(ii)liquidated damages,city shall make a
progress payment in the amount that city deems due and payable.
g. In the event of a dispute regarding either final quantities or liquidated damages,the parties shall
attempt to resolve the differences within 30 calendar days.
F
F
09/10/04 4
PROPOSAL
TO: Mr. Dale A. Fisseler,P.E.
City Manager
Fort Worth, Texas
T FOR: LOST CREEK PHASE 2 DRAINAGE IMPROVEMENTS FOR:
LOST CREEK ADDITION—FROM BLUE CREEK COURT SOUTH TO MARY'S
T CREEK
LOST CREEK ADDITION—FROM BEN CREEK COURT SOUTH TO GOLF
COURSE
WESTPOINT ADDITION—FROM POWDERHORN ROAD TO PARK JUST SOUTH
OF LITTLE VALLEY ROAD
DOE NO. 4744
Pursuant to the foregoing"Notice to Bidders",the undersigned has thoroughly examined the plans,
specifications and the site,understands the amount of work to be done,and hereby proposes to do all the
work and furnish all labor,equipment,and materials necessary to complete all the work as provided in the
plans and specifications,and subject to the inspection and approval of the Department of Engineering
Director of the City of Fort Worth.Upon acceptance of this proposal by the City Council,the bidder is
bound to execute a contract and furnish Performance and Payment Bond approved by the City of Fort
Worth for performing and completing said work within the time stated and for the following sums,to-wit:
UNIT II:DRAINAGE IMPROVEMENTS
Furnish and install,including all appurtenant work,complete in place,the following items: (SC.-##refers
_ to specifically related items of the Special Provisions of these Specifications and Contract Documents,all
applicable General Specification and Special Provisions apply):
SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT
BID
SC.69 1. 4 EA. Project Designation Sign
BID— TWO HUNDRED FIFTY Dollars&
.. 00504 NO Cents Per EA. $2�00 $1000.000
SC.70 2. 1 LS. Utility Adjustment
BID— FOUR THOUSAND Dollars&
00414 Cents Per LS. $4 0, 00.00 $4 00.00
SC.54 3. 216 LF. Remove Existing Curb and Gutter
BID— T 1x1C Dollars&
00424 YN-O Cents Per LF. $ -t70 $ y 3oZ.cc
SC.46 4. 181 LF. Concrete Curb or Curb and Gutter Including
SC 91 LAydovp Curb
BID— Dollars&
00425 Cents Per LF. $ 01H.00
SC.53 5. 720 SF. Remove Existing Concrete Driveway,
SC 91 Sidewalk,Leadwalk
BID— _ C Ke Dollars&
00402 WO Cents Per SF.
Proposal Page 1 of 6
SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT
BID
SC.61 6. 3 EA. Remove/Salvage/Reconstruct Existing
BID- Brick Mailbox
00407 Dollars&
BID- NA-0 Cents Per EA. $ 4M. $ 1:aoo.00
00408
SC.95 7. 1 EA. Remove Existing 10-Foot Inlet Top
BID- E ;1n '�. e1 Dollars&
00846 ttiD Cents Per EA. $ %00.00 $�•C
SC.95 8. 1 EA. Remove Existing,20-_F000t Inlet Top
BID-
Dollars
00846 Per EA. & $ 12CO-M $ to
SC.55 9. 1 EA. Remove Existing I 0-Foot Inlet
BID-- Dollars&
00102 WV.-C Cents Per EA. $ scV. $ %Cacti
SC.66 10. 1 EA. Standard 10-Foot Curb Inlet
BID- Dollars&
00106 Cents Per EA. 01C EO $
SC.66 11. 1 EA. Standard 15-Foot Curb Inlet
BID- Dollars&
_ 00107 i/t y Cents Per EA. $3tKy' $ Mrc-
SC.66 12. 1 EA. Standard 20-Foot Curb Inlet
BID- ¢ Dollars&
00108 I&D Cents Per EA. $5cw.00 $�_
SC.95 13. 1 EA. Standard 10-Foot Curb Iplet Top
BID- .L, Dollars&
00846 Q ti,o Cents Per EA.
SC.95 14. 1 EA. Standard 20-Foot Curb Vet Top
BID- 4A&mAa Dollars&
00846 J y buQ Cents Per EA.
$ 3LIC0. $ 3�Lz�•
SC.96 15. 2 EA. Connect Proposed Storm Drain Main to
BID- Existing Storm Drain Inlet
00121 Dollars&
Cents Per EA. $5O•co $ DO.fr
SC.96 16. 1 EA. Connect Existing Storm Drain Main to
BID- Proposed Storm Drain Inlet
00121 Dollars&
Cents Per EA. $ S0.00 $ 50.cr
SC.97 17. 63 SF. 4-Inch Reinforced Concrete Sidewalks,
SC 91 Lead walks-
BID- Dollars& $ $.OD $ _50g,D
00527 Cents Per SF.
Proposal Page 2 of 6
SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT
BID
SC.56 18. 792 SF. 6-Inch Reinforced Concrete Standard
SC 91 Driveway Approach Pavement
BID— �p�_ Dolbns& $ .rJO $
00404 Cents Per SF.
SC.94 19. 2 EA. Storm Drain Concrete Manhole Collar
SC 91 Dollars&
BID— V-0 Cents Per EA. $3M.00 $ ISO•tE)
00197
SC.94 20. 2 EA. Sanitary Sewer Concr to Manhole Collar
SC 91 L Dollars&
BID— k.o Cents Per EA. $
00197
SC.66 21. 1 EA. Standard 4'Storm DrW4 Manhole
BID— ..�. Dollars&
00118 1,.o Cents Per EA.
SC.66 22. 1 EA. Standard 5' Storm Drain anhole
BID— Dollars&
00115 V�uy Cents Per EA. $ D.OD $a DD.
SC.100 23. 48 LF. Proposed 24-Inch Class III RCP Storm
BID— Dr in
00082 Dollars& $l 0.DO $loa tjD.O
C is Per LF.
SC.100 24. 121 LF. Proposed 30-Inch Class III RCP Storm
BID— Drain
00083 Vk lents Per
& $ 145.VV. $175�5•
LF.
SC.99 25. 103 LF. Proposed 3'x 2' Class III RC Box Storm
BID— Sewer
00870 Dollars& $,23 5•ca $2 4�
Vt-0 is Per LF.
SC.99 26. 307 LF. Proposed 3'x 3'Class III RC Box Storm
BID— Sewer
00871 Aw A4 j -"�g Dollars& $�1,3•CV $ 80 D
Un T Cements Per LF.
SC.98 27. 134 LF, Proposed 30"High Density Polethylene
BID— Pi e
00293 - ollars& $ tj G1.00 $.23
l; nts Per LF.
SC.100 28. 3 EA Propos 30-Inch 22030"RCP Bend
BID— Dollars&
00121 Leo Cents Per EA. $ 50.00 $ Sc. DO
SC.100 29. 1 EA Proposec136-Inch 22*30"RCP Bend
BID— �� Dollars&
00121 �. Cents Per EA. $ 50•co $ �0•
r.
Proposal Page 3 of 6
SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT
BID
SC.67 30. 825 CY. Trench Excavation and Backfill for Storm
BID- Drains
00101 '�&••o Dollars&
U-40 Cents Per CY. $ •DO $ 16,5D.
SC.101 31. 674 LF. Trench Safety System for Trenches
BID- Greater Than Five Feet Deep
00372 O 1tis Dollars&
K.o Cents Per LF. $ 1.00 $ to714-CC
SC.51 32. 388 SY. Permanent Pavement Repair Per Fig.
SC 91 2000-413
BID- and Fig 4 HMAC.
00450 3 Dollars& $ .DO $3oL42L.o
1% Cents Per SY.
SC.105 33. 80 CY. 12"Rock Rip Rap Protection
BID- A.;�_ Dollars&
0094 w Cents Per CY. $ 305.00 $ asoo-co
- SC.106 34. 72 SY. Gabions and Gabion Mattresses
BID- L...: . _ Dollars&
0067 J —cents Per SY.
SC.71 35. 75 CY. Topsoil
BID- SS Dollars&
00147 No Cents Per CY. $ 16.00 $ 1200.00
SC.102 36. 4 EA. Remove Concrete Headwall
_ BID- '•'y��L^-' Dollars&
0070 vw Cents Per EA. $ laDO•D0 $ 2 0w.00
SC.103 37. 9 CY. Type`B'Modified Reinforced Concrete
BID- Headwall
0069 Dollars&
�.O G is Per CY. $1050.00 $ 5 q w.
SC.59 38. 63 LF. Protect/Remove/Salvage/Reconstruct
BID- Existing Iron Fence/Stone and Mortar
00126 Wall
'•' BID- cT.... Dollars& $ 20.00 $ 13 t D.oc
00127 � Cents Per LF.
SC.107 39. 2 EA. 8"Diameter Waterline Adjustment to
SC.108 Avoid Storm Drain conflict Per Each
BID- Location to Include All Fittings and
00414 Concrete Encasemen
Dollars& $?500-t>0 $ Sabo.
'• 14 V We Cents Per EA.
SC.108 40. 1 LS. Furnish and Lay 2-Inch Pipe for
BID- Te orary atgr Services.
00768 R,o Dollars&
1-0 v Cents Per LS. $ 256.DO $ :1 So•
Proposal Page 4 of 6
..
SPEC PAY APPROX. DESCRIPTION OF ITEMS WITH BID UNIT TOTAL
ITEM ITEM QUANTITY PRICES WRITTEN IN WORDS PRICE AMOUNT
BID
SC.104 41. 30 CY. Class`A'3000 psi Concrete for
_ BID— Miscellaneous Placement as Directed by
00544 the En ineer
_ Dollars& $ jo.00 $ geo.co
Cents Per CY.
SC.104 42. 30 CY. Class`D' 1500 psi Concrete for
BID— Miscellaneous Placement as Directed by
00544 the Engineer
T i,,...� Dollars& OO $
U_C, Cents Per CY.
SC.92 43. 1 LS. Traffic Control Plan
BID— Dollars&
00181 1i►0 Cents Per LS. $ 15D0 OD $ 5� oo•00
SC.109 44. 230 SY. Sodding,
BID- Dollars&
00137 Cents Per SY. $ It-Do $ 1940.D
SC 110 45. 10 CY. Flowable Fill.
BID— 1��+., �,,..Q� Dollars&
00544 V� Cents Per CY.
$ 45.00 $ qso.
SC 108 46. l EA. Relocate Water Meter Box.Include
BID— Service Line to 'ap
00549 _ Dollars&
BID- k-v Cents Per EA. $ moo•aD $ :5oo•ocj
00759
v
l'{7. TOTAL BID: $
W�.
GRAND TOTAL AMOUNT BID: $ -2 I0 5, y 10
GRAND TOTAL AMOUNNT BID IN WRITING$
V
Proposal Page 5 of 6
This contract is issued by an organization which qualifies for exemption pursuant to the provision of
Article 20.04(F)of the Texas Limited Sales,Excise and Use Tax Act. All equipment and
materials not consumed by or incorporated into the project construction are subject to State sales
taxes under House Bill 11,enacted August 15, 1991.
The Contractor shall comply with City Ordinance 7278,as amended by City Ordinance 7400(Fort
Worth City Code Sections 13-A-21 through 13-A-29),prohibiting discrimination in employment
practices.
(Complete A or B below,as applicable:)
A.The principal place of business of our company is in the State of
Nonresident bidders in the State of ,our principal
place of business,are required to be percent lower than resident bidders
- by state law. A copy of the statute is attached.
Non resident bidders in the State of ,our principal
place of business,are not required to underbid resident bidders.
+ B.The principal place of business of our company or our parent company or
majority owner is in the State of Texas.
LM
The undersigned agrees to complete all work covered by these contract documents within Sixty
(60)Working Days from and after the date for commencing work as set forth in the written Work
Order to be issuedby the Owner and to pay not less than the"Prevailing Wage Rates for Street,
Drainage and Utility Construction"as established by the City of Fort Worth,Texas.
Within ten(10)days of receipt of notice of acceptance of this bid,the undersigned will execute the
formal contract and will deliver an approved Surety Bond for the faithful performance of this
contract. The attached dg sit check in the sum of
S Dollars 4M
Is to be forfeited in the event the contract and bond are not executed
within the time set forth,as liquidated damages for delay and additional work caused thereby.
(Uwe), acknowledge receipt of the following addenda to the plans and specifications,all of the
provisions and requirements of which have been taken into consideration in preparation of the
foregoing bid:
Addendum No. 1(Initials) Addendum No.3(Initials)
Addendum No.2(Initials) Addend (Initials)
RespectfuIl ubmitted: agmsto Co"waucrtowl�k,n G.
By
Address em I SoUTRWCS-r ELM
5eN 1 00 i<,t�c lei S a
(SEAL) Telephone $11—73$—'s 1 p p
Date -5 lazk Io$
Proposal Page 6 of 6
Statement of Materials and Other Charges
MATERIAL INCORPORATED INTO THE PROJECT: $ I Sg IZ'%I .y 0
ALL OTHER CHARGES: $ ��� . l8'1 . 60
*TOTAL: $ 2 to 5 i 4 tag _o a
'This total must agree with the total figure shown in Part B-Proposal, TOTAL AMOUNT BID for this UNIT
in the bound contract.
For Purposes of complying with the Texas Tax Code,the Contractor agrees that the charges for any
material incorporated into the project in excess of the estimated quantity provided for herein will be no
less than the invoice price for such material to the Contractor.
NOTE: ONLY THE COPY OF THIS FORM IN THE BOUND CONTRACT IS TO BE FILLED OUT.
7
VENDOR COMPLIANCE TO STATE LAW
The 1985 Session of the Texas Legislature passed House Bill 620 relative to the award of contracts to
nonresident bidders. This law provides that,in order to be awarded a contract as low bidder,nonresident
bidders(out-of-State contractors whose corporate offices or principal place of business are outside of the
State of Texas)bid projects for construction,improvements,supplies or services in Texas at an amount
lower than the lowest Texas resident bidder by the same amount that a Texas resident bidder would be
required too underbid a nonresident bidder in order to obtain a comparable contract in the State in which
the nonresident's principal place of business is located. The appropriate blanks in Section A must be filled
out by all out-of-State or nonresident bidders in order for your bid to meet specifications. The failure of
■ out-of-State or nonresident contractors to do so will automatically disqualify that bidder. Resident bidders
must check the box in Section B.
A. Nonresident vendors in (give State),our principal place of business,are required to
be percent lower than resident bidders by State law. A copy of the Statute is attached.
Nonresident vendors in (give State),our principal place of business,are not
required to underbid resident bidders.
B. Our principal place of business or corporate offices are in the State of Texas.
BIDDER:
?XAR 14SC.D CoW.tMu c_-rte N,1 r c- By: otatZl�S
(PleasCpi
ML Sarrmwayr QLVD Signature
&,yBemt< 1 C 7i0 l 3 a Title: S l ZJ 1=1i"T'
City State Zip (Please print)
THIS FORM MUST BE RETURNED WITH YOUR.QUOTATION
' I 07-03-08 Al 0 :
+ ATTACHMENT IA
Page 1 of 4
Fo R r WORTH City of Fort worth
Subcontractors/Suppliers Utilization Form
PRIME COMPANY NAME: Check applicable block to describe prime
Burnsco Construction, Inc.
PROJECT NAME: I
M/W/DBE NON-M/W/DBE
Host Creek Phase 2 Drainage Improvements for: BID DATE
+ Blue Creek Ct, Ben Creek Ct, & Powderhorn Rd May 22,, 20081I�
City's MlwBE Project Goal: Prime's M/WBEC
Project Utilization: C 2 0 0 5 41097 Nti U 8 0 0 0 8 7
20 % 20 % 83 U l
r
Identify all subcontractors/suppliers you will use on this project
Failure to complete this form, in its entirety with requested documentation, and received by the Managing
Department on or before 5:00 p.m. five (5) City business days after bid opening, exclusive of bid opening date,
will result in the bid being considered non-responsive to bid specifications.
The undersigned Offeror agrees to enter into a formal agreement with the MMBE firm(s) listed in this
utilization schedule, conditioned upon execution of a contract with the City of Fort Worth. The intentional
and/or knowing misrepresentation of facts is grounds for consideration of disqualification and will result in the
bid being considered non-responsive to bid specifications
M/WBEs listed toward meeting the project goal must be located in the nine (9) county marketplace or
currently doing business in the marketplace at the time of bid. Marketplace is the geographic area of Tarrant,
Parker,Johnson,Collin, Dallas, Denton, Ellis, Kaufman and Rockwall counties.
Identify each Tier level. Tier is the level of subcontracting below the prime contractor, i.e., a direct
+ payment from the prime contractor to a subcontractor is considered 1"tier, a payment by a subcontractor to
its supplier is considered 2"d tier
ALL M/WBEs MUST BE CERTIFIED BEFORE CONTRACT AWARD.
Certification means those firms, located or doing business at the time of bid opening within the Marketplace,that have
been determined to be bonafide minority or women businesses by the North Central Texas Regional Certification
Agency(NCTRCA), or the Texas Department of Transportation (TX DOT), highway division. Disadvantaged Business
Enterprise(DBE)is synonymous with Minority/Women Business Enterprise(MMIBE).
If hauling services are utilized, the prime will be given credit as long as the M/WBE listed owns and
+ operates at least one fully licensed and operational truck to be used on the contract. The M/WBE may lease
trucks from another M/WBE firm, including M/WBE owner-operators, and receive full M/WBE credit. The
M/WBE may lease trucks from non-M/ BEs, including owner-operators, but will only receive credit for the
fees and commissions earned by the M/WBE as outlined in the lease agreement.
..
Rev.5/30/03
I �
.� I ATTACHMENT IA
FORT IVORTH Page 2 of 4
y Primes are required to identify ALL subcontractors/suppliers, regardless of status;i.e., Minority,Women and non-M/WBEs.
Please list M/WBE firms first,use additional sheets if necessary.
_ Certification N
(check one)
SUBCONTRACTORISUPPLIER
T N T Detail Detail
Company Name i C X M Subcontracting Work Supplies Purchased Dollar Amount
Address e M W T D W
Telephone/Fax r B B R o 8
E E C T E
A
Trucking & Const.
Co. of TX, Inc. X Hauling by
P.O. Box 951 Dumptruck $10, 000. 00
Keene, TX 76059 1
' 817-558-0525
817-645-6441
Trucking & Const.
Co. of TX, Inc. X Aggregates $9, 500. 00
P.O. Box 951
Keene, TX 76059 1
817-558-0525
817-645-6441
Cowtown Redi Mix
Concrete X Ready Mix
P.O. Box 162327 1 Concrete $9, 000. 00
Fort Worth, TX 76151
817-759-1919
817-759-1716
Ricochet Fuel
Distributors, Inc. 1 X Fuel
1201 Royal Pkwy $5000.00
Euless, TX 76040
817-268-5910
817-282-7497
Perkins ConstructiDr
3721 Huntwick Dr.
Ft. Worth, TX 76123 Asphalt
817-346-7140 Paving $12000 . 00
817-263-9621 1 X
Axis Contracting
P.O. Box 360715 1 X Concrete
Da1la89xTX 75336 Pavintjg $8949. 00
.. 972-557-3672
972-557-3740
'� Rev.5/30/03
07-03-08 Al 0 : 09 IN ATTACHMENT IA
FORT WORTH Page 3 of 4
' Primes are required to identify/L subcontractors/suppliers, regardless of status;i.e.,Minority,Women and non-M/WBEs.
Please list M/WBE firms first,use additional sheets if necessary.
Certification N
o
SUBCONTRACTOWSUPPLIER T (check one)
Company Name i N T Detail Detail
Address e M w C X M Subcontracting Work Supplies Purchased Dollar Amount
- Telephone/Fax r g B T o e
E E C T E
A
Act Pipe & Supply
2585 NE 28th St. 1 X PVC Pipe $3200. 00
Ft. Worth TX 76111
817-831 -1663
- 817-831 -1903
Hanson
1000 N Macarthur 1 X Concrete
Grand Prairie, TX Pipe $33100. 00
75050
972-260-3455
972-260-3633
r
"' Rev.5130103
ATTACHMENT 1A
FOR1_ ��TH 07-03-08 A10 : 09 IN Page 4of4
� T
Total Dollar Amount of M/WBE Subcontractors/Suppliers $ 54,449 .00
Total Dollar Amount of Non-M/WBE Subcontractors/Suppliers $ 36, 300 . 00
TOTAL DOLLAR AMOUNT OF ALL SUBCONTRACTORS/SUPPLIERS $ 90, 749. 00
The Contractor will not make additions, deletions, or substitutions to this certified list without the prior approval
of the Minority and Women Business Enterprise Office Manager or designee through the submittal of a
Request for Approval of Change/Addition. Any unjustified change or deletion shall be a material breach of
contract and may result in debarment in accord with the procedures outlined in the ordinance. The contractor
shall submit a detailed explanation of how the requested change/addition or deletion will affect the committed
M/WBE goal. If the detail explanation is not submitted, it will affect the final compliance determination.
By affixing a signature to this form, the Offeror further agrees to provide, directly to the City upon request,
.. complete and accurate information regarding actual work performed by all subcontractors, including
M/W/DBE(s) arrangements submitted with the bid. The Offeror also agrees to allow an audit and/or
examination of any books, records and files held by their company. The bidder agrees to allow the
transmission of interviews with owners, principals, officers, employees and applicable
subcontractors/suppliers/contractors participating on the contract that will substantiate the actual work
performed by the M/W/DBE(s) on this contract, by an authorized officer or employee of the City. Any
intentional and/or knowing misrepresentation of facts will be grounds for terminating the contract or debarment
from City work for a period of not less than three (3) years and for initiating action under Federal, State or
Local laws concerning false statements. Any failure to comply with this ordinance and create a material
breach of contract may result in a determination of an irresponsible Offeror and barred from participating in
City work for a period of time not less than one(1)year.
John Burns
Authorized I
ignature Printed Signature
President Ab Grantges
Title Contact NamdTitie(it different)
Burnsco Construction, Inc. 817-738-3200 / 738-3203
n Company Name Telephone and/or Fax
6331 Southwest Blvd burnscoinc2@aol.com
Address E-mail Address
Benbrook, TX 76132 July 2, 2008
Clty/Btawilp Date
r
"r Rev.5/30/03
ATTACHMENT 1C
Page 1 of 3
FORT WORTH
�----�•..�..�--- City of Fart Worth
J5-29-08 Al . .
Good Faith Effort Form
PRIME COMPANY NAME: Check applicable block to describe
Surnsco Construction, Inc, prime
TMIW/DBE NON-MNV/DBE
PROJECT NAME: Ix
Lost Creek Phase 2 Drainage Improvements for:Blue Creek Court,Ben Creek Court and BID DATE
Powderhorn Road
City's M/WBE Project Goal: PROJECT NUMBER
20% C200 541200 2032800087 83
Ifyou have fa�ledto secure MNVBE particiation and you have subcontracting anrllar suppler opporEuart�es or if ydyr
DBE partic�patioi is.less than:the GI#y's project goal,you.'Must compiete:th�s form
If the bidder's method of compliance with the M/WBE goal is based upon demonstration of a
"good faith effort", the bidder will have the burden of correctly and accurately preparing and
" submitting the documentation required by the City. Compliance with each item, 1 thru 6 below,
shall satisfy the Good Faith Effort requirement absent proof of fraud, intentional and/or knowing
misrepresentation the facts or intentional discrimination by the bidder.
failurc�fo complete this ftlrrri, �n Its, entirety with`support�ngdocumentatton, and recelvecl ksy the
Mar:agmg Department:onr before 5 00 p m five i5} CEty buslnessays after bid opening1 exclusive of
bid»peeing tlate, nrlll,result in the:bid being consldereclron'r s ons>veo b�d::specifcaton�
P
I J Please list each and every subcontracting and/or supplier opportunity] for the completion of this
project, regardless of whether it is to be provided by a MNVBE or non-MIWBE. (DO NOT LIST NAMES
OF FIRMS) On Combined Projects, list each subcontracting and or supplier opportunity through the
2" tier.
(Use additional sheets, ff necessary)
List of Subcontracting Opportunities List of Supplier Opportunities
Barricades Rebar
Erosion Control
Hauling by Dumptruek Fuel
Concrete (Redi-Mix)
ATTACHMENT1C
Page 2 of 3
2.) Obtain a current(not more than three(3) months old from the bid open date) list of M/WBE
subcontractors and/or suppliers from the City's M/WBE Office.
Yes Date of Listing 3 / 5 / 2 0 0 8
No
3.) Did you solicit bids from M/WBE firms,within the subcontracting and/or supplier areas previously
listed, at least ten calendar days prior to bid opening by mail, exclusive of the day the bids are
opened?
X Yes (If yes,attach M/WBE mail listing to include name of firm and address and a dated copy of letter mailed.)
No
4.) Did you solicit bids from M/WBE firms,within the subcontracting and/or supplier areas previously
listed, at least ten calendar days prior to bid opening by telephone,exclusive of the day the bids are
opened?
X Yes (If yes,attach list to include name of M/WBE firm,person contacted,phone number and date and time of contact.)
No
NOTE: A facsimile may be used to comply with either 3 or 4, but may not be used for both. If a facsimile
is used, attach the fax confirmation, which is to provide M/WBE name, date, time, fax number and
documentation faxed.
NOTE: If the list of MfWBEs for a particular subcontracting/supplier opportunity is ten (10) or less, the
bidder must contact the entire list to be in compliance with questions 3 and 4. If the list of M/WBEs for a
particular subcontracting/supplier opportunity is ten (10) or more, the bidder must contact at least two-
thirds (2/3) of the list within such area of opportunity, but not less than ten to be in compliance with
questions 3 and 4.
5.) Did you provide plans and specifications to potential M/WBEs or information regarding the location of
plans and specifications in order to assist the M/WBEs?
X Yes
No
6.) Submit documentation if M/WBE quotes were rejected. The documentation submitted should be in
the forms of an affidavit, include a detailed explanation of why the M/WBE was rejected and any
supporting documentation the bidder wishes to be considered by the City. In the event of a bona fide
dispute concerning quotes, the bidder will provide for confidential in-camera access to and
inspection of any relevant documentation by City personnel.
_ Please use additional sheets, if necessary,and attach.
Company Name Telephone Contact Person Sco a of Work Reason for Re ection
omas ReyesJessie Hau ing by Not iow bidder
Truckin 631 -2711 alas uez Dumptruck
Ornelas & 214 Manuel Ornelas Hauling by Not low bidder
Dum truck
Ted Alvarez 972 Ted Alvarez Hauling by Not low bidder
T u kin
Trucking and 817 Cindy Cornish Aggregat89 Not low bidder
e�
Rev.05/30/03
ATTACHMENT 1C
Page 3 of 3
ADDITIONAL INFORMATION:
Please provide additional information you feel will further explain your good and honest efforts to obtain
M/WBE participation on this project.
Burnsco Construction will be utilizing the following MWBE firms:
Trucking & Construction - Hauling by Dumptruck - $8, 000.00
Cowtown Redi-Mix - Redi-mix Concrete - $4, 500. 00
Ricochet Fuel - Offroad Diesel - $5, 000. 00
For a total of $17, 500. 00, appuoximately 6. 6% of contract.
The bidder further agrees to provide, directly to the City upon request, complete and
accurate information regarding actual work performed on this contract, the payment
thereof and any proposed changes to the original arrangements submitted with this bid.
The bidder also agrees to allow an audit and/or examination of any books, records and
files held by their company that will substantiate the actual work performed on this
contract, by an authorized officer or employee of the City.
Any intentional and/or knowing misrepresentation of facts will be grounds for
terminating the contract or debarment from City work for a period of not less than three
(3) years and for initiating action under Federal, State or Local laws concerning false
statements. Any failure to comply with this ordinance and creates a material breach of
contract may result in a determination of an irresponsible offeror and barred from
participating in City work for a period of time not less than one (1) year.
The undersigned certifies that the information provided and the M/WBE(s) listed
was/were contacted in good faith. It is understood that any M/WBE(s) listed in
nc nt 1 C will be contacted and the reasons for not using them will be verified by
he City' L
E Office.
John Burns
AuthorizYN gnature Printed Signature
Presidehtt Ab Grantges - Project Manager
Title Contact Name and Title(if different)
Burnsco Construction, Inc. 817-738-3200 / 817-738-3203
Company Name Phone Number Fax Number
6331 Southwest Blvd. burnscoinc2@aol.com
Address Email Address
Benbrook, TX 76132 5/28/2008
City/State/Zip Date
.� Rev.05/30/03
SPECIAL PROVISIONS FOR
STREET AND STORM DRAIN IMPROVEMENTS
Table of Centex&
1. SCOPE OF WORK...................................................................................................................................SP4
2. AWARD OF CONTRACT.................................................................................. ..........................SP4
3. PRECONSTRUCTION CONFERENCE..................................................................................................SP4
4. EXAMINATION OF SITE ......................................................................................................................SP-4
5. BID SUBMITTAL....................................................................................................................................SP-5
6. WATER FOR CONSTRUCTION............................................................................................................SP-5
7. SANITARY FACILITIES FOR WORKERS......................................... ..................SP-5
8. PAYMENT................................................................................................................................................SP-5
9. SUBSIDIARY WORK..............................................................................................................................SP-5
10. LEGAL RELATIONS AND RESPONSIBILITIES
TOTHE PUBLIC......................................................................................................................................SP-5
11. WAGE RATES.........................................................................................................................................SP-5
12. EXISTING UIILITIES.............................................................................................................................SP-6
13. PARKWAY CONSTRUCTION...............................................................................................................SP-6
14. MATERIAL,STORAGE...........................................................................................................................SP-7
15. PROTECTION OF EXISTING UTILITIES
AND IMPROVEMENTS..........................................................................................................................SP-7
16. INCREASE OR DECREASE IN QUANTITIES......................................................................................SP-7
17. CONTRACTORS RESPONSIBILITY FOR DAMAGE CLAIMS..........................................................SP-7
18. EQUAL EMPLOYMENT PROVISIONS................................................................................................SP-8
19. MINORITY AND WOMENS BUSINESS ENTERPRISE
(M/WBE)COMPLIANCE.......................................................................................................................SP-8
20. FINAL CLEAN UP...................................................................................................................................SP-9
21. CONTRACTOR'S COMPLIANCE WITH WORKER'S
COMPENSATIONLAW..........................................................................................................................SP-9
22. SUBSTITUTIONS.................................................................................................................................SP-12
23. MECHANICS AND MATERIALSMEN'S LIEN................................»................................................SP-12
24. WORK ORDER DELAY
25. WORKING DAYS ..................................................................................................................................SR 12
26. RIGHT TO ABANDON...........................................................................................................................SP 12
27. CONSTRUCTION SPECIFICATIONS..................................................................................................SP-12.
28. MAINTENANCE STATEMENT ............................................................................................................SP-12
29. DELAYS ...................................................................................................................................SP-13
30. DETOURS AND BARRICADES ............................................................................................................SP-13
31. DISPOSAL OF SPOHAILL MATERIAL ..............................................................................................SP-13
32. QUALITY CONTROL TESTING ...........................................................................................................SP-13
33. PROPERTY ACCESS..............................................................................................................................SP-14
34. SAFETY RESTRICTIONS-WORK NEAR HIGH VOLTAGE LINES ...............................................SP-14
35. WATER DEPARTMENT PRE-QUA.LIFICATIONS .............................................................................SP-14
36. RIGHT TO AUDIT ..................................................................................................................................SP-15
37. CONSTRUCTION STAKES ...................................................................................................................SP-15
38. LOCATION OF NEW WALKS AND DRIVEWAYS ..........................................................................SP-15
39. EARLY WARNING SYSTEM FOR CONSTRUCTION.........................................................................SP-15
40. AIR POLLUTION WATCH DAYS.....................................................................................I............4.4...SP-16
05/27/05 Sp-1
SPECIAL PROVISIONS FOR
STREET AND STORM DRAIN IMPROVEMENTS
Table of Contents
CONSTRUCTION ITEMS:
41. PAY ITEM-UNCLASSIFIED STREET EXCAVATION.......................
42. PAY ITEM-6"REINFORCED CONCRETE PAVEMENT...................................................................SP-17
43. PAY ITEM-SILICONE JOINT SEALING.............................................................................................SP-17
44. PAY ITEM-7"CONCRETE CURB....»..................................................................................................SP-21
45. PAY ITEM-RETAINING WALL.................. .......................................................................................SP-21
46. PAY ITEM-REPLACE EXISTING CURB AND GUTTER..................................................................SP-21
' 47. PAY ITEM-HMAC TRANSITION........ ............................................................................................SP-21
48. PAY ITEM-6"PIPE SUBDRAIN...........................................................................................................SP 21
49. PAY ITEM-TRENCH SAFETY.............................................................................................................SP 22
50. PAY ITEM-8"THICK LIME STABILIZED SUBGRADE AND CEMENT FOR SUBGRADE
STABILIZATION................................................................................................................SP 22
51. PAY ITEM-6-HMAC PAVEMENT(FIGA)(THICKNESS TOLERANCES AND HMAC TESTING
PROCEDURES)...................................................... .........................................................SP 22
52. PAY ITEM-CONCRETE FLAT WORK(CURB,CURB&GUTTER,SIDEWALKS,
�.. LEADWALKS,WHEELCHAIR RAMPS AND DRIVEWAYS)......:................................SP-23
53. PAY ITEM-REMOVE EXISTING CONCRETE SIDEWALK,DRIVEWAYS,STEPS,
LEADWALKS AND WHEELCHAIR RAMPS..................................................................SP-23
54. PAY ITEM-REMOVE EXISTING CURB AND GUTTER...................................................................SP-24
55. PAY ITEM-REMOVE EXISTING CURB INLET...................... SP-24
...........................................................
56. PAY ITEM-6"REINFORCED CONCRETE DRIVEWAY...................................................................SP-24
57. PAY ITEM-REMOVE AND CONSTRUCT CONCRETE STEPS........................................................SP-24
58. PAY ITEM-4' STANDARD CONCRETE SIDEWALK,LEADWALK AND
WHEELCHAIR RAMP.......................................................................................................SP-24
p+ 59. PAY ITEM-REMOVE AND REPLACE FENCE...................................................................................SP-24
_ 60. PAY ITEM-STANDARD T'CURB AND 18"GUTTER......................................................................SP-25
61. PAY ITEM-REMOVE AND RECONSTRUCT MAILBOXES/MISCELLANEOUS
62. PAY ITEM-BORROW .................................................................................SP-25
63. PAY ITEM-CEMENT STABILIZATION..............................................................................................SP-25
64. PAY ITEM-CEMENT .........................................................................................................................SP-25
65. PAY ITEM-NEW 7"CONCRETE VALLEY GUTTER........................................................................SP 25
66. PAY ITEM-STORM DRAIN INLETS AND MANHOLES...................................................................SP 25
67. PAY ITEM-TRENCH EXCAVATION AND BACKFILL
FOR STORM DRAIN.....................................»..................................................................SP-26
68. PAY ITEM-STORM WATER POLLUTION PREVENTION(FOR DISTURBED AREAS
EQUAL TO OR GREATER THAN 1 ACRE)....................................................................SP-26
69. PRE BID ITEM-PROJECT DESIGNATION SIGN...............................................................................SP-27
70. PRE BID ITEM-UTILITY ADJUSTMENT...........................................................................................SP-28
71. PRE BID ITEM-TOP SOIL..................................................................................................................SP-28
72. PRE BID ITEM-ADJUST WATER VALVE BOX............................................:...................................SP-28
73. PRE BID ITEM-MANHOLE ADJUSTMENT......a...............................................................................SP-28
74. PRE BID ITEM-ADJUST WATER METER BOX................................................................................SP-28
75. NON-PAY ITEM-CLEARING AND GRUBBING................................................................................SP 29
76. NON-PAY ITEM- SPRINKLING FOR DUST CONTROL...................................................................SP-29
77. NON-PAY ITEM- PROTECTION OF TREES,PLANTS AND SOILS................................................SP-29
78. NON-PAY ITEM-CONCRETE COLORED SURFACE.......................................................................SP-29
05/27/05 SP-2
SPECIAL PROVISIONS FOR
STREET AND STORM DRAIN IMPROVEMENTS
Table of Contents
79. NON-PAY ITEM-PROJECT CLEAN-UP..............................................................................................SP 29
80. NON-PAY ITEM-PROJECT SCHEDULE............................................................................................SP-30
81. NON-PAY ITEM-NOTIFICATION OF RESIDENTS...................................„.....................................SP 30
82. NON-PAY ITEM-PUBLIC NOTIFICATION PRIOR TO BEGINNING CONSTRUCTION..............SP-30
83. NON-PAY ITEM-PRE-CONSTRUCTION NEIGHBORHOOD MEETING........................................SP-30
84. NON-PAY ITEM-WASHED ROCK.....................................................................................................SP-31
85. NON-PAY ITEM-SAWCUT OF EXISTING CONCRETE...................................................................SP-31
86. NON-PAY ITEM-LOCATION AND EXPOSURE OF MANHOLES
AND WATER VALVES..........................................................................................SP-31
87. NON-PAY ITEM-TIE-IN INTO STORM DRAIN STRUCTURE........................................................SP-31
88. NON-PAY ITEM- SPRINKLER HEAD ADJUSTMENT......................................................................SP-31
89. NON-PAY ITEM-FEE FOR STREET USE PERMITS AND RE-INSPECTIONS..............................SP-32
90. NON PAY ITEM-TEMPORARY EROSION,SEDIMENT AND WATER
POLLUTION CONTROL(FOR DISTURBED AREAS LESS THAN 1 ACRE)....SP-32
91. NON PAY ITEM-`GREEN'CEMENT POLICY .................................................................................SP-33
92. NON PAY ITEM-TRAFFIC CONTROL ......................................................................................„......SP-33
93. NON PAY ITEM-PROTECTION OF ADJACENT STRUCTURES....................................................SP-34
94. PAY ITEM-CONCRETE MANHOLE COLLARS................................................................................SP-34
95. PAY ITEM-REMOVE AND REPLACE EXISTING INLET TOPS.....................................................SP-34
96. PAY ITEM-CONNECT TO EXISTING/PROPOSED STORM DRAIN INLET OR
STORMDRAIN MAIN....................................................................................................SP-35
97. PAY ITEM-4"REINFORCED CONCRETE SIDEWALK,LEADWALK,
OR DRIVEWAY PAVEMET............ ..............................................................................SP-35
98. PAY ITEM-30"HIGH DENSITY POLETHYLENE PIPE(HDPE) ....................................................SP-35
99. PAY ITEM-3X2,3X3 REINFORCED CONCRETE BOX SECTIONS...............................................SP-35
100. PAY ITEM-24"AND 30"DIAMETER CLASS III RCP STORM DRAINS........................................SP-35
101. PAY ITEM-TRENCH SAFETY SYSTEM FOR TRENCHES GREATER THAN 5 FEET DEEP......SP-36
102. PAY ITEM-REMOVE CONCRETE HEADWALL...............................................................„.............SP-36
103. PAY ITEM-TYPE B MODIFIED REINFORCED CONCRETE HEADWALL...................................SP-36
104. PAY ITEM-MISCELLANEOUS PLACEMENT OF MATERIAL.......................................................SP-36
105. PAY ITEM-ROCK RIP RAP SLOPE PROTECTION..........................................................................SP-37
106. PAY ITEM-GABIONS AND GABION MATTRESSES......................................................................SP-37
107. PAY ITEM-8"DIAMETER WATERLINE ADJUSTMENT TO AVOID CONFLICT WITH
STORM DRAIN PER EACH LOCATION........................................................................SP 39
108. PAY ITEM-INSTALLATION OF WATER FACILITIES....................................................................SP-39
109. PAY ITEM-SODDING.......................................................................................................„..................SP-44
110. PAY ITEM-FLOWABLE FILL ............................................................................................................SP-44
05/27/05 SP-3
SPECIAL PROVISIONS
FOR
STREET AND STORM DRAIN IMPROVEMENTS
FOR: LOST CREEK PHASE 2 DRAINAGE IMPROVEMENTS: BLUE CREEK COURT, BEN
CREEK COURT AND POWDERHORN ROAD
LOST CREEK ADDITION—FROM BLUE CREEK COURT SOUTH TO MARY'S CREEK
LOST CREEK ADDITION—FROM BEN CREEK COURT SOUTH TO GOLF COURSE
WEST POINT ADDITION—FROM POWDERHORN ROAD TO PARK JUST SOUTH OF
LITTLE VALLEY ROAD
Project No.C200-641200 203280008787
D.O.E. NO. 4744
1. SCOPE OF WORK: The work covered by these plans and specifications consist of the following:
Reconstruction of Storm Drainage Improvements and all other miscellaneous items of
construction to be performed as outlined in the plans and specifications which are necessary to
satisfactorily complete the work.
2. AWARD OF CONTRACT: Submission of Bid: Lost Creek Unit 11: Drainage Improvements. If the
Contractor submits a bid on Unit 11 and has the lowest responsive proposal price, the Contractor
will be the apparent successful bidder for this project. Bidders are hereby informed that the
Director of the Department of Engineering reserves the right to evaluate and recommend to the
City Council the best bid that is considered to be in the best interest of the City.
3. PRECONSTRUCTION CONFERENCE: The successful Contractor, Engineer, and City shall meet
at the call of the City for a preconstruction conference before any of its work begins on this project.
At this time, details of sequencing of the work, contact individuals for each party, request for
survey, and pay requests will be covered. Prior to the meeting, the Contractor shall prepare
schedules showing the sequencing and progress of their work and its effect on others. A final
composite schedule will be prepared during this conference to allow an orderly sequence of project
construction. As used herein, the term "Engineer" shall mean the design engineer who prepared
and sealed the plans, specifications and contract documents for this project.
4. EXAMINATION OF SITE: It shall be the responsibility of the prospective bidder to visit the project
site and make such examinations and explorations as may be necessary to determine all
conditions that may affect construction of this project. Particular attention should be given to
methods of providing ingress and egress to adjacent private and public properties, procedures for
protecting existing improvements and disposition of all materials to be removed. Proper
consideration should be given to these details during preparation of the Proposal and all unusual
conditions that may give rise to later contingencies should be brought to the attention of the City
prior to the submission of the Proposal.
During the construction of this project, it is required that all parkways be excavated and shaped
including bar ditches at the same time the roadway is excavated. Excess excavation will be
disposed of at locations approved by the Engineer.
During construction of this project,the Contractor shall comply with present zoning requirements of
the City of Fort Worth in the use of vacant property for storage purposes.
05/27/05 SP-4
5. BID SUBMITTAL: Bidders shall not separate, detach or remove any portion, segment or sheets
from the contract documents at any time. Failure to bid or fully execute contract without retaining
contract documents intact may be grounds for designating bids as "non-responsive" and rejecting
bids as appropriate and as determined by the Director of the Department of Engineering.
6. WATER FOR CONSTRUCTION: Water for construction will be furnished by the Contractor at his
own expense.
7. SANITARY FACILITIES FOR WORKERS: The Contractor shall provide all necessary
conveniences for the use of workers at the project site. Specific attention is directed to this
equipment.
8. PAYMENT: The Contractor shall receive full payment from the City for all the work based on unit
prices bid on the proposal and specified in the plans and specifications and approved by the
Engineer per actual field measurement.
9. SUBSIDIARY WORK Any and all work specifically governed by documentary requirement for the
projects, such as conditions imposed by the Plans, the General Contract Documents or these
special Contract Documents, in which no specific item for bid has been provided for In the
Proposal, shall be considered as a subsidiary item or work,the cost of which shall be included in
the price bid in the Proposal for each bid item, including but not limited to surface restoration
cleanup and relocation of mailboxes.
All objectionable matter required to be removed from within the right-of-way and not particularly
described under these specifications shall be covered by Item No. 102"Clearing and Grubbing"
_ and shall be subsidiary to the other items of the contract.
10. LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC: The Contractor's particular
attention is directed to the requirements of Item 7, "Legal Relations and Responsibilities to the
Public°of the"Standard Specifications for Street and Storm Drain Construction".
11. WAGE RATES:
Compliance with and Enforcement of Prevailing Wage Laws
Duty to pay Prevailing Wage Rates.
The contractor shall comply with all requirements of Chapter 2258, Texas Government Code(Chapter
2258), including the payment of not less than the rates determined by the City Council of the City of
Fort Worth to be the prevailing wage rates in accordance with Chapter 2258. Such prevailing wage
rates are included in these contract documents.
Penalty for Violation.
A contractor or any subcontractor who does not pay the prevailing wage shall, upon demand made by
the City, pay to the City$60 for each worker employed for each calendar day or part of the day that the
worker is paid less than the prevailing wage rates stipulated in these contract documents. This penalty
shall be retained by the City to offset its administrative costs, pursuant to Texas Government Code
2258.023.
Complaints of Violations and City Determination of Good Cause.
On receipt of information, including a complaint by a worker, concerning an alleged violation of
2258.023, Texas Government Code, by a contractor or subcontractor, the City shall make an initial
determination, before the 31st day after the date the City receives the information, as to whether good
cause exists to believe that the violation occurred. The City shall notify In writing the contractor or
subcontractor and any affected worker of its initial determination. Upon the City's determination that
05/27/05 SP-5
there is good cause to believe the contractor or subcontractor has violated Chapter 2258, the City shall
— retain the full amounts claimed by the claimant or claimants as the difference between wages paid and
wages due under the prevailing wage rates, such amounts being subtracted from successive progress
payments pending a final determination of the violation.
Arbitration Required if Violation Not Resolved.
An issue relating to an alleged violation of Section 2258.023, Texas Government Code, including a
penalty owed to the City or an affected worker, shall be submitted to binding arbitration in accordance
with the Texas General Arbitration Act (Article 224 et seq., Revised Statutes) if the contractor or
subcontractor and any affected worker do not resolve the issue by agreement before the 15th day after
the date the City makes its initial determination pursuant to paragraph (c) above. If the persons
required to arbitrate under this section do not agree on an arbitrator before the 11th day after the date
that arbitration is required, a district court shall appoint an arbitrator on the petition of any of the
persons. The City is not a party in the arbitration. The decision and award of the arbitrator is final and
binding on all parties and may be enforced in any court of competent jurisdiction.
Records to be Maintained.
The contractor and each subcontractor shall, for a period of three (3) years following the date of
acceptance of the work, maintain records that show (i) the name and occupation of each worker
employed by the contractor in the construction of the work provided for in this contract, and (11) the
actual per diem wages paid to each worker. The records shall be open at all reasonable hours for
inspection by the City. The provisions of the Audit section of these contract documents shall pertain to
this inspection.
_ Pay Estimates.
With each partial payment estimate or payroll period, whichever is less, the contractor shall submit an
affidavit stating that the contractor has complied with the requirements of Chapter 2258, Texas
Government Code.
Posting of Wage Rates.
The contractor shall post the prevailing wage rates in a conspicuous place at the site of the project at
all times.
Subcontractor Compliance.
The contractor shall include In its subcontracts and/or shall otherwise require all of its subcontractors to
comply with paragraphs(a)through (g)above.
_ (Wage rates are attached at the end of this section.)
12. EXISTING UTILITIES: The locations and dimensions shown on the plans relative to existing
utilities are based on the best information available. It shall be the Contractor's responsibility to
verify location of adjacent and/or conflicting utilities sufficiently In advance of construction in order
that he may negotiate such local adjustments as are necessary in the construction process in order
to provide adequate clearance. The Contractor shall take all necessary precautions in order to
protect all services encountered.
Any damage to utilities and any losses to the utility City due to disruption of service resulting from
the Contractor's operations shall be at the Contractor's expense.
13. PARKWAY CONSTRUCTION: During the construction of this project, it will be required that all
parkways be excavated and shaped at the same time the roadway is excavated. Excess
excavation will be disposed of at locations approved by the Director of the Department of
Engineering.
05/27/05 SP-6
U. MATERIAL STORAGE: Material shall not be stored on private property unless the Contractor has
obtained permission from the property owner and/or City.
15. PROTECTION OF EXISTING UTILITIES AND IMPROVEMENTS: The Contractor shall take
adequate measures to protect all existing structures, improvements and utilities, which may be
encountered.
The utility lines and conduits shown on the plans are for information only and are not guaranteed
by the City or the Engineer to be accurate as to extent, location and depth, they are shown on the
plans as the best information available at the time of design, from the Owners of the utilities
involved and from evidences found on the ground.
16. INCREASE OR DECREASE IN QUANTITIES: The quantities shown in the Proposal are
approximate. It is the Contractor's sole responsibility to verify all the minor pay item quantities prior
to submitting a bid. No additional compensation shall be paid to Contractor for errors in the
do quantities. Final payment will be based upon field measurements. The City reserves the right to
alter the quantities of the work to be performed or to extend or shorten the improvements at any
time when and as found to be necessary, and the Contractor shall perform the work as altered,
increased or decreased at the unit prices as established in the contract documents. No allowance
will be made for any changes in anticipated profits or shall such changes be considered as waiving
or invalidating any conditions or provisions of the Contract Documents.
Variations in quantities of storm drain pipes in depth categories shall be interpreted herein as
applying to the overall quantities of storm drain pipe in each pipe size but not to the various depth
categories.
17. CONTRACTOR'S RESPONSIBILITY FOR DAMAGE CLAIMS: Contractor Covenants and agrees
to indemnify City's Engineer and Architect, and their personnel at the project site for Contractor's
sole negligence. In addition, Contractor covenants and agrees to indemnify, hold harmless and
defend, at its own expense, the City, its officers, servants and employees, from and against any
and all claims or suits for property loss, property damage, personal injury, including death, arising
out of, or alleged to arise out of, the work and services to be performed hereunder by Contractor,
its officers, agents, employees, subcontractors, licensees or invitees, whether or not any such
Injury, damage or death is caused, in whole or in part, by the negligence or alleged
negligence of City, Its officers, servants, or employees. Contractor likewise covenants and
agrees to indemnify and hold harmless the City from and against any and all injuries to City's
officers, servants and employees and any damage, loss or destruction to property of the City
arising from the performance of any of the terms and conditions of this Contract, whether or not
any such Injury or damage Is caused in whole or in part by the negligence or alleged
negligence of City,Its officers, servants or employees.
In the event City receives a written claim for damages against the Contractor or its subcontractors
prior to final payment, final payment shall not be made until Contractor either (a) submits to City
satisfactory evidence that the claim has been settled and/or a release from the claimant involved,
or(b) provides City with a letter from Contractor's liability insurance carrier that the claim has been
referred to the insurance carrier.
The Director may, if deemed appropriate, refuse to accept bids on other City of Fort Worth public
work from a Contractor against whom a claim for damages is outstanding as a result of work
performed under a City Contract.
U. EQUAL EMPLOYMENT PROVISIONS: Contractor shall comply with City Ordinance Number 7278
as amended by City Ordinance Number 7400(Fort Worth City Code Sections 13-A-21 through 12-
A-29) prohibiting discrimination in employments practices.
05/27/05 SP-7
The Contractor shall post the required notice to that effect on the project site, and at his request,
will be provided by assistance by the City of Fort Worth's Equal Employment Officer who will refer
any qualified applicant he may have on file in his office to the Contractor. Appropriate notices may
be acquired from the Equal Employment Officer.
19. MINORITY AND WOMEN BUSINESS ENTERPRISE(M/WBE)COMPLIANCE: In accordance
with City of Fort Worth Ordinance No. 15530,the City has goals for the participation of minority
business enterprises and women business enterprises in City contracts. The Ordinance is
— incorporated in these specifications by reference. A copy of the Ordinance may be obtained from
the Office of the City Secretary. Failure to comply with the ordinance shall be a material breach of
contract.
M/WBE UTILIZATION FORM, M/WBE GOALS WAIVER FORM AND GOOD FAITH EFFORT
FORM,as applicable, must be submitted within fine(5)city business days after bid opening.
Failure to comply shall render the bid non-responsive.
Upon request, Contractor agrees to provide the City complete and accurate information regarding
actual work performed by a Minority or Women Business Enterprise(M/WBE)on the contract and
payment thereof. Contractor further agrees to permit an audit and/or examination of any books,
records or files in its possession that will substantiate the actual work performed by an MBE and/or
WBE. The misrepresentation of acts(other than a negligent misrepresentation) and/or the
commission fraud by the Contractor will be grounds for termination of the contract and/or initiating
action under appropriate federal, state, or local laws or ordinances relating to false statement.
Further, any such misrepresentation (other than a negligent misrepresentation)and/or commission
of fraud will result in the Contractor being determined to be irresponsible and barred from
participating in City work for a period of time not less than three years.
The City will consider the Contractor's performance regarding its M/WBE program in the evaluation
of bids. Failure to comply with the City's M/WBE Ordinance,or to demonstrate"good faith effort",
shall result in a bid being rendered non-responsive to specifications.
Contractor shall provide copies of subcontracts or co-signed letters of intent with approved M/WBE
subcontractors prior to issuance of the Notice to Proceed. Contractor shall also provide monthly
reports on utilization of the subcontractors to the City's M/WBE office.
The Contractor may count first and second tier subcontractors and/or suppliers toward meeting the
goals. The Contractor may count toward its goal a portion of the total dollar amount of the contract
with a joint venture equal to the percentage of the M/WBE participation in the joint venture for a
clearly defined portion of the work to be performed. All M/WBE Contractors used in meeting the
goals must be certified prior to the award of the Contract. The M/WBE Contractor(s)must be
certified by either the North Central Texas Regional Certification Agency(NCTRCA)or Texas
Department of Transportation (TxDOT), Highway Division and must be located in the nine(9)
county marketplace or currently doing business in the marketplace at time of bid. The Contractor
shall contact all such M/WBE subcontractors or suppliers prior to listing them on the M/WBE
utifation or good faith effort forms as applicable. Failure to contact the listed M/WBE
subcontractor or supplier prior to bid opening may result in the rejection of bid as non-responsive.
Whenever a change order affects the work of an MM/BE subcontractor or supplier,the M/WBE
shall be given an opportunity to perform the work. Whenever a change order exceeds 10%of the
original contract, the M/WBE coordinator shall determine the goals applicable to the work to be
performed under the change order
During the term of the contract the contract shall:
1. Make no unjustified changes or deletions in its M/WBE participation commitments
submitted with or subsequent to the bid, and,
05/27/05 SP-8
2. If substantial subcontracting and/or substantial supplier opportunities arise during the
term of the contract which the Contractor had represented he would perform with his
forces, the Contractor shall notify the City before subcontracts or purchase orders are
let, and shall be required to comply with modifications to goals as determined by the
City, and,
3. Submit a REQUEST FOR APPROVAL OF CHANGE FORM, if the Contractor desires
to change or delete any of the M/WBE subcontractors or suppliers. Justification for
change may be granted for the following:
a. Failure of Subcontractor to provide evidence of coverage by Worker's
Compensation Insurance.
b. Failure of Subcontractor to provide required general liability of other insurance.
C. Failure of Subcontractor to execute a standard subcontract form in the amount
of the proposal used by the Contractor in preparing his M/WBE Participation plan.
d. Default by the M/WBE subcontractor or supplier in the performance of the
subcontractor.
Within ten (10)days after final payment from the City,the Contractor shall provide the
M/WBE Office with documentation to reflect final participation of each subcontractor
and supplier used on the project, inclusive of M/WBEs.
20. FINAL CLEAN-UP: Final cleanup work shall be done for this project as soon as the paving and
curb and gutter has been completed. No more than seven days shall elapse after completion of
construction before the roadway and R.OW. is cleaned up to the satisfaction of the Engineer. The
Contractor shall make a final cleanup of all parts of the work before acceptance by the City or its
representative. This cleanup shall include removal of all objectionable rocks, pieces of asphalt or
concrete and other construction materials, and in general preparing the site of the work in an
orderly manner and appearance.
21. CONTRACTOR COMPLIANCE WITH WORKER'S COMPENSATION LAW:
A. Workers Compensation Insurance Coverage
a. DEFINITIONS:
b. Certification of coverage("Certificate"). A copy of a certificate of insurance, a certificate of
authority to self-insure issued by the commission, or a coverage agreement(TWCC-81,TWCC-
82, TWCC-83, OR TWCC-84), showing statutory workers'compensation insurance coverage for
the person's or entity's employees providing services on a project, for the duration of the project.
Duration of the project-includes the time from the beginning of the work on the project until the
•• Contractor'stperson's work on the project has been completed and accepted by the
governmental entity.
Persons providing services on the project ("subcontractor" in §406.096)-includes all persons or
entities performing all or part of the services the Contractor has undertaken to perform on the
project, regardless of whether that person contracted directly with the Contractor and regardless
of whether, that person has employees. This includes, without limitation, independent
Contractors, subcontractors, leasing companies, motor carriers, City-operators, employees of
any such entity, or employees of any entity which furnishes persons to provide services on the
project "Services" include, without limitation, providing, hauling, or delivering equipment or
materials, or providing labor, transportation, or other services related to a project. "Services"
does not Include activities unrelated to the project, such as food/beverage vendors, office supply
deliveries, and delivery of portable toilets.
The Contractor shall provide coverage, based on proper reporting of classification codes and
payroll amounts and filing of any coverage agreements, which meets the statutory requirements
05/27/05 SP-9
of Texas Labor Code, Section 401.011(44) or all employees of the Contractor providing services
on the project,for the duration of the project.
c. The Contractor must provide a certificate of coverage to the governmental entity prior to being
awarded the contract.
d. If the coverage period shown on the Contractor's current certificate of coverage ends during the
duration of the project, the Contractor must, prior to the end of the coverage period, file a new
— certificate of coverage with the governmental entity showing that coverage has been extended.
e. The Contractor shall obtain from each person providing services on a project, and provide to the
governmental entity:
(1) a certificate of coverage, prior to that person beginning work on the project, so
the governmental entity will have on file certificates of coverage showing
coverage for all persons providing services on the project;and
(2) no later than seven days after receipt by the Contractor, a new certificate of
coverage showing extension of coverage, if the coverage period shown on the
current certificate of coverage ends during the duration of the project.
f. The Contractor shall retain all required certificates of coverage for the duration of the project and
for one year thereafter.
g. The Contractor shall notify the governmental entity in writing by certified mail or personal delivery,
within ten (10) days after the Contractor knew or should have known, or any change that
materially affects the provision of coverage of any person providing services on the project.
h. The Contractor shall post on each project site a notice, in the text, form and manner prescribed by
the Texas Worker's Compensation, informing all persons providing services on the project that
they are required to be covered, and stating how a person may verify coverage and report lack of
coverage.
I. The Contractor shall contractually require each person with whom it contracts to provide services
on a project, to:
(1) provide coverage, based on proper reporting on classification codes and
payroll amounts and filing of any coverage agreements, which meets the
statutory requirements of Texas Labor Code, Section 401.011(44) for all of its
employees providing services on the project,for the duration of the project;
(2) provide to the Contractor, prior to that person beginning work on the project, a
certificate of coverage showing that coverage is being provided for all
employees of the person providing services on the project, for the duration of
the project;
(3) provide the Contractor, prior to the end of the coverage period, a new
certificate of coverage showing extension of coverage, if the coverage period
shown on the current certificate of coverage ends during the duration of the
project;
(4) obtain form each other person with whom it contracts, and provide to the
Contractor:
(a) a certificate of coverage, prior to the other person beginning work on
the project; and
05/27/06 SP-10
(b) a new certificate of coverage showing extension of coverage, prior to
the end of the coverage period, If the coverage period shown on the
current certificate of coverage ends during the duration of the project;
(c) retain all required certificates of coverage on file for the duration of the
project and for one year thereafter.
(d) notify the governmental entity in writing by certified mail or personal
delivery, within ten (10) days after the person knew or should have
known, of any change that materially affects the provision of coverage
of any person providing services on the project; and
(e) contractually require each person with whom it contracts, to perform
as required by paragraphs (1)-(7), with the certificates of coverage to
be provided to the person for whom they are providing services.
J. By signing this contract or providing or causing to be provided a certificate of
coverage, the Contractor is representing to the governmental entity that all employees
of the Contractor who will provide services on the project will be covered by worker's
compensation coverage for the duration of the project, that the coverage will be based
on proper reporting of classification codes and payroll amounts, and that all coverage
agreements will be tiled with appropriate insurance carrier or, in the case of a self-
insured, with the commission's Division of Self-insurance Regulation. Providing false
or misleading information may subject the Contractor to administrative, criminal, civil
penalties or other civil actions.
k. The Contractor's failure to comply with any of these provisions is a breach of contract
by the Contractor which entities the governmental entity to declare the contract void if
the Contractor does not remedy the breach within ten day after receipt of notice of
breach from the governmental entity.
B. The Contractor shall post a notice on each project site informing all persons providing
services on the project that they are required to be covered, and stating how a person
may verify current coverage and report failure to provide coverage. This notice does
not satisfy other posting requirements imposed by the Texas Worker's Compensation
Act or other Texas Worker's Commission rules. This notice must be printed with a title
In at least 30 point bold type and text in at least 19 point normal type, and shall be in
both English and Spanish and any other language common to the Worker population.
The text for the notices shall be the following text, without any addltional words or
changes:
"REQUIRED WORKER'S COMPENSATION COVERAGE
The law requires that each person working on this site or providing services related to
this construction project must be covered by worker's compensation insurance. This
includes persons providing, hauling, or delivering equipment or materials, or providing
labor or transportation or other service related to the project, regardless of the identify
of their employer or status as an employee."
Cali the Texas Worker's Compensation Commission at 512-440-3789 to receive
information on the legal requirement for coverage, to verify whether your employer has
provided the required coverage, or to report an employer's failure to provide
coverage".
05/27/05 SP-11
22. SUBSTITUTIONS: The specifications for materials set out the minimum standard of quality that
the City believes necessary to procure a satisfactory project. No substitutions will be permitted
until the Contractor has received written permission of the Engineer to make a substitution for the
material that has been specified. Where the term "or equal", or"or approved equal" is used, it Is
understood that if a material, product, or piece of equipment bearing the name so used is
furnished, it will be approvable, as the particular trade name was used for the purpose of
establishing a standard of quality acceptable to the City. If a product of any other name Is
proposed substitutes is procured by the Contractor. Where the term "or equal", or "approved
equal" is not used in the specifications, this does not necessarily exclude alternative items or
material or equipment which may accomplish the Intended purpose. However, the Contractor shall
have the full responsibility of providing that the proposed substitution is, in fact, equal, and the
Engineer, as the representative of the City, shall be the sole judge of the acceptability of
substitutions. The provisions of the sub-section as related to "substitutions" shall be applicable to
all sections of these specifications.
23. MECHANICS AND MATERIALMEN'S LIEN: The Contractor shall be required to execute a release
of mechanics and materialmen's liens upon receipt of payment.
24. WORK ORDER DELAY: All utilities and right-of-way are expected to be clear and easements
and/or permits obtained on this project within sixty (60) days of advertisement of this project. The
work order for subject project will not be issued until all utilities, right-of-ways, easements and/or
permits are cleared or obtained. The Contractor shall not hold the City of Fort Worth responsible
for any delay in issuing the work order for this Contract.
25. WORKING DAYS: The Contractor agrees to complete the Contract within the allotted number of
working days.
26. RIGHT TO ABANDON: The City reserves the right to abandon, without obligation to the
Contractor, any part of the project or the entire project at any time before the Contractor begins any
construction work authorized by the City.
27. CONSTRUCTION SPECIFICATIONS: This contract and project are governed by the two following
published specifications, except as modified by these Special Provisions:
STANDARD SPECIFICATIONS FOR STREET AND STORM DRAIN CONSTRUCTION
CITY OF FORT WORTH
STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION
NORTH CENTRAL TEXAS
A copy of either of these specifications may be purchased at the Office of the Department of
Engineering, 1000 Throckmorton Street, 2"d Floor, Municipal Buliding, Fort Worth, Texas 76102.
The specifications applicable to each pay item are indicated in the call-out for the pay item by the
Engineer. If not shown, then applicable published specifications in either of these documents may
be followed at the discretion of the Contractor. General Provisions shall be those of the Fort Worth
document rather than Division 1 of the North Central Texas document.
28. MAINTENANCE STATEMENT: The Contractor shall be responsible for defects in this project due
to faulty materials and workmanship, or both, for a.period of two (2) years from date of final
acceptance of this project and will be required to replace at his expense any part or all of the
project which becomes defective due to these causes.
29. DELAYS: The Contractor shall receive no compensation for delays or hindrances to the work,
except when direct and unavoidable extra cost to the Contractor is caused by the failure of the City
w.
05/27/05 SP-12
to provide information or material, if any, which is to be furnished by the City. When such extra
compensation is claimed a written statement thereof shall be presented by the Contractor to the
Director of the Department of Engineering and if by him found correct shall be approved and
referred by him to the Council for final approval or disapproval; and the action thereon by the
Council shall be final and binding. If delay is caused by specific orders given by the Engineers to
stop work or by the performance of extra work or by the failure of the City to provide material or
necessary instructions for carrying on the work, then such delay will entitle the Contractor to an
equivalent extension of time, his application for which shall, however, be subject to the approval of
the City Council; and no such extension of time shall release the Contractor or the surety on his
performance bond form all his obligations hereunder which shall remain in full force until the
discharge of the contract.
30. DETOURS AND BARRICADES: The Contractor shall prosecute his work in such a manner as to
create a minimum of interruption to traffic and pedestrian facilities and to the flow of vehicular and
pedestrian traffic within the project area. Contractor shall protect construction as required by
Engineer by providing barricades.
Barricades, warning and detour signs shall conform to the Standard Specifications "Barriers and
_ Warning and/or Detour Signs," Item 524 and/or as shown on the plans.
Construction signing and barricades shall conform with "1980 Texas Manual on Uniform Traffic
Control Devices,Vol. No. 1."
31. DISPOSAL OF SPOIL/FILL MATERIAL: Prior to the disposing of any spoil/fill material, the
Contractor shall advise the Director of the Department of Engineering acting as the City of Fort
Worth's Flood Plain Administrator("Administrator"), of the location of all sites where the Contractor
intends to dispose of such material. Contractor shall not dispose of such material until the
proposed sites have been determined by the Administrator to meet the requirements of the Flood
Plain Ordinance of the City of Fort Worth (Ordinance No. 10056). All disposal sites must be
approved by the Administrator to ensure the filling is not occurring within a flood plain without a
permit A flood plain permit can be issued upon approval of necessary engineering studies. No fill
permit is required if disposal sites are not in a flood plain. Approval of the Contractor's disposal
sites shall be evidenced by a letter signed by the Administrator stating that the site is not in a
known flood plain or by a Flood Plain fill Permit authorizing fill within the flood plain. Any expenses
associated with obtaining the fill permit, including any necessary engineering studies, shall be at
the Contractor's expense. In the event that the Contractor disposes of spoil/fill materials at a site
without a fill permit or a letter from the administrator approving the disposal site, upon notification
by the Director of Engineering, Contractor shall remove the spoil/fill material at its expense and
dispose of such materials in accordance with the Ordinance of the City and this section.
32. QUALITY CONTROL TESTING:
(a) The Contractor shall furnish, at its own expense, certifications by a private laboratory for all
materials proposed to be used on the project, including a mix design for any asphaltic and/or
Portland cement concrete to be used and gradation analysis for sand and crushed stone to be
used along with the name of the pit from which the material was taken. The Contractor shall
provide manufacturer's certifications for all manufactured items to be used in the project and
will bear any expense related thereto.
(b) Tests of the design concrete mix shall be made by the Contractor's laboratory at least nine
days prior to the placing of concrete using the same aggregate, cement and mortar which are
to be used later in the concrete. The Contractor shall provide a certified copy of the test
results to the City.
(c) Quality control testing of on site material on this project will be performed by the City at its own
expense. Any retesting required as a result of failure of the material to meet project
05/27/05 SP-13
specifications will be at the expense of the Contractor and will be billed at commercial rates as
determined by the City. The failure of the City to make any tests of materials shall In no way
relieve the Contractor of its responsibility to furnish materials and equipment conforming to the
requirements of the contract.
(d) Not less than 24 hours notice shall be provided to the City by the Contractor for operations
requiring testing. The Contractor shall provide access and trench safety system (If required)
for the site to be tested and any work effort involved is deemed to be included In the unit price
for the item being tested.
(e) The Contractor shall provide a copy of the trip ticket for each load of fill material delivered to
the job site. The ticket shall specify the name of the pit supplying the fill material.
33. PROPERTY ACCESS: Access to adjacent property shall be maintained at all times unless
otherwise directed by the Engineer.
34. SAFETY RESTRICTIONS-WORK NEAR HIGH VOLTAGE LINES:
_ The following procedures will be followed regarding the subject item on this contract:
(a) A warning sign not less than five inches by seven inches, painted yellow with black letters that
are legible at twelve feet shall be placed inside and outside vehicles such as cranes, derricks,
.. power shovels, drilling rigs, pile drivers, hoisting equipment or similar apparatus. The warning
sign shall read as follows:
"WARNING—UNLAWFUL TO OPERATE THIS EQUIPMENT WITHIN SIX FEET OF HIGH
VOLTAGE LINES."
(b) Equipment that may be operated within ten feet of high voltage lines shall have an insulating
cage-type of guard about the boom or arm, except back hoes or dippers and insulator links on
the lift hood connections.
(c) When necessary to work within six feet of high voltage electric lines, notification shall be given
the power company (TU Electric Service Company) which will erect temporary mechanical
barriers, de-energize the line or raise or lower the line. The work done by the power company
shall not be at the expense of the City of Fort Worth. The notifying department shall maintain
an accurate log of all such calls to TU Electric Service Company and shall record action taken
in each case.
(d) The Contractor is required to make arrangements with the TU Electric Service Company for
the temporary relocation or raising of high voltage lines at the Contractor's sole cost and
expense.
(e) No person shall work within six feet of a high voltage line without protection having been taken
as outlined in Paragraph (c).
35. WATER DEPARTMENT PRE-QUALIFICATIONS: Any Contractor performing any work on Fort
Worth water or sanitary sewer facilities must be pre-qualified with the Water Department to
perform such work in accordance with procedures described in the current Fort Worth Water
Department General Specifications which general specifications shall govern performance of all
such work.
36. RIGHT TO AUDIT:
(a) Contractor agrees that the City shall, until the expiration of three (3) years after final payment
under this contract have access to and the right to examine and photocopy any directly
05/27/05 SP-14
pertinent books, documents, papers and records of the Contractor involving transactions
relating to this contract. Contractor agrees that the City shall have access during normal
working hours to all necessary Contractor facilities and shall be provided adequate and
appropriate workspace in order to conduct audits in compliance with the provisions of this
-
section. The City shall give Contractor reasonable advance notice of Intended audits.
(b) Contractor further agrees to include in all its subcontracts hereunder a provision to the effect
that the subcontractor agrees that the City shall, under the expiration of three (3) years after
final payment under the subcontract, have access to and the right to examine and photocopy
any directly pertinent books, documents, papers and records of such subcontractor involving
transactions to the subcontract and further, that City shall have access during normal working
hours to all subcontractor facilities and shall be provided adequate and appropriate work space
in order to conduct audits in compliance with the provisions of this article together with
subsection (c ) hereof. City shall give subcontractor reasonable advance notice of intended
audits.
(c) Contractor and subcontractor agree to photocopy such documents as may be requested by the
City. The City agrees to reimburse Contractor for the cost of copies at the rate published in the
_ Texas Administrative Code in effect as of the time copying is performed.
37. CONSTRUCTION STAKES:
The City, through its Surveyor or agent, will provide to the Contractor construction stakes or other
customary methods of markings as may be found consistent with professional practice to establish
line and grade for roadway and utility construction and centerlines and benchmarks for bridgework.
These stakes shall be set sufficiently in advance to avoid delay whenever practical. One set of
stakes shall be set for all utility construction (water, sanitary sewer, drainage, etc.), one set of
excavation/or stabilization stakes, and one set of stakes for curb and gutter and/or paving. It shall
be the sole responsibility of the Contractor to preserve, maintain,transfer, etc., all stakes furnished
until completion of the construction phase of the project for which they were furnished.
If, in the opinion of the Engineer, a sufficient number of stakes or markings provided by the City
have been lost, destroyed, or disturbed, that the proper prosecution and control of the work
contracted for in the Contract Documents cannot take place, then the Contractor shall replace
such stakes or markings as required. An individual registered by the Texas Board of Professional
Land Surveying as a Registered Professional Land Surveyor shall replace these stakes, at the
Contactor's expense. No claims for delay due to a lack of replacement of construction stakes will
-
be accepted, and time will continue to be charged in accordance with the Contract Documents.
38. LOCATION OF NEW WALKS AND DRIVEWAYS:
The Contractor will make every effort to protect existing trees within the parkway, with the approval
of the engineer the Contractor may re-locate proposed new driveways and walks around existing
trees to minimize damage to trees.
39. EARLY WARNING SYSTEM FOR CONSTRUCTION: Time is of the essence in the completion of
this contract. In order to insure that the Contractor is responsive when notified of unsatisfactory
performance and/or of failure to maintain the contract schedule, the following process shall be
applicable:
The work progress on all construction projects will be closely monitored. On a bi-monthly basis the
percentage of work completed will be compared to the percentage of time charged to the contract.
If the amount of work performed by the Contractor is less than the percentage of time allowed by
20% or more (example: 10% of the work completed in 30% of the stated contract time as may be
amended by change order), the following proactive measures will be taken:
1. A letter will be mailed to the Contractor by certified mail, return receipt requested
demanding that, within 10 days from the date that the letter is received, it provide
05/27/05 SP-15
sufficient equipment, materials and labor to ensure completion of the work within the
contract time. In the event the Contractor receives such a letter, the Contractor shall
provide to the City an updated schedule showing how the project will be completed
within the contract time.
2. The Project Manager and the Directors of the Department of Engineering, Water
Department, and Department of Transportation and Public Works will be made aware
of the situation. If necessary, the City Manager's Office and the appropriate city council
members may also be informed.
3. Any notice that may, in the City's sole discretion, be required to be provided to
interested individuals will distributed by the Engineering Department's Public
Information Officer.
4. Upon receipt of the Contractor's response, the appropriate City departments and -
directors will be notified. The Engineering Department's Public Information Officer will,
if necessary, then forward updated notices to the interested individuals.
5. If the Contractor fails to provide an acceptable schedule or fails to perform
satisfactorily a second time prior to the completion of the contract, the bonding
company will be notified appropriately.
40. AIR POLLUTION WATCH DAYS: The Contractor shall be required to observe the following
guidelines relating to working on City construction sites on days designated as "AIR POLLUTION
WATCH DAYS". Typically, the OZONE SEASON, within the Metroplex area, runs from May 1,
through OCTOBER 31, with 6:00 a.m. - 10:00 a.m. being critical BECAUSE EMISSIONS FROM
THIS TIME PERIOD HAVE ENOUGH TIME TO BAKE IN THE HOT ATMOSPHERE THAT LEADS
TO EARLY AFTERNOON OZONE FORMATION.
The Texas Commission on Environmental Quality (TCEQ), in coordination with the National
Weather Service, will issue the Air Pollution Watch by 3:00 p.m. on the afternoon prior to the
WATCH day. On designated Air Pollution Watch Days, the Contractor shall bear the responsibility
of being aware that such days have been designated Air Pollution Watch Days and as such shall
not begin work until 10:00 a.m. whenever construction phasing requires the use of motorized
equipment for periods in excess of 1 hour. However, the Contractor may begin work prior to 10:00
a.m. If use of motorized equipment is less than 1 hour, or if equipment is new and certified by EPA
as "Law Emitting", or equipment burns Ultra Low Sulfur Diesel (ULSD), diesel emulsions, or
alternative fuels such as CNG.
If the Contractor is unable to perform continuous work for a period of at least seven hours between
the hours of 7:00 a.m. - 6:00 p.m., on a designated Air Pollution Watch Day, that day will be
considered as a weather day and added onto the allowable weather days of a given month.
CONSTRUCTION
41. PAY ITEM- UNCLASSIFIED STREET EXCAVATION:
See Standard Specifications item No. 106, "Unclassified Street Excavation" for specifications
governing this item.
Removal of existing penetration or asphalt pavement shall be included in this item.
05/27/05 SP-16
Operations necessary to windrow existing gravel base in order to lower or raise subgrade shall be
-� considered as subsidiary to this item and no additional compensation shall be given as such.
During the construction of this project, it is required that all parkways be excavated and shaped at
the same time the roadway is excavated. Excess excavation will be disposed of at locations
approved by the engineer.
The intention of the City is to pay only the plan quantity without measurement. Should either
contracting party be able to show an error in the quantities exceeding 10 percent, then actual
quantities will be paid for at the unit prices bid. The party requesting the payment of actual rather
than plan quantities is responsible for bearing any survey and/or measurement costs necessary to
verify the actual quantities.
42. PAY ITEM- 6" REINFORCED CONCRETE PAVEMENT:
(a) All applicable provisions of standard Specifications Item 314"Concrete Pavement,"shall apply.
The Contractor shall use a six (6) sack concrete mix for all hand placement in the
intersections. The unit price bid per square yard shall be full payment for all labor, material,
equipment and incidentals necessary to complete the work.
(b) Once an evaluation of the pavement is made to determine whether the crack is due to distress
or minor shrinkage, the following policy will apply:
(1) When the crack is minor and due to shrinkage (cosmetic), then no further treatment
will be needed.
(2) If the crack is due to distress (structural), the failed pavement must be removed and
replaced a minimum of 5 feet. In no case should the remaining portion of the panel be
less than 5 feet wide after repairing the failed panel.
(3) Any crack within 12 inches of any joint must be removed and replaced a minimum of 5
feet to prevent future spalling of the pavement.
(c) All concrete pavement not placed by hand shall be placed using a fully automated paving
machine as approved by the Construction Engineer. Screeds will not be allowed except if
approved by the Construction Engineer.
43. PAY ITEM-SILICONE JOINT SEALING FOR CONCRETE PAVEMENT:
CITY OF FORT WORTH,TEXAS
TRANSPORTATION AND PUBLIC WORKS DEPARTMENT
SPECIFICATION
for
SILICONE JOINT SEALING
(Revision 1, October 18, 1989)
(Revision 2, May 12, 1994)
1. SCOPE
This specification for silicone joint sealing Portland Cement Concrete pavement and
.. curbs shall supersede Item 314.2. (11)"Joint Sealing Materials"of STANDARD
SPECIFICATIONS FOR STREET AND STORM DRAIN CONSTRUCTION-
CITY OF FORT WORTH, and Item 2.210"Joint Sealing" of STANDARD
SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION-NORTH TEXAS
COUNCIL OF GOVERNMENTS.
2. MATERIALS
2.1 The silicone joint sealant shall meet Federal Specification TT-S-001543A for
05/27/05 SP-17
Class A sealant except as modified by the test requirements of this specification.
Before the Installation of the joint sealant, the Contractor shall furnish the
Engineer certification by an independent testing laboratory that the silicone joint
sealant meet these requirements.
2.2 The manufacturer of the silicone joint sealant shall have a minimum two-year
demonstrated, documented successful field performance with Portland Cement
Concrete pavement silicone joint sealant systems. Verifiable documentation shall
be submitted to the Engineer. Acetic acid cure sealants shall not be accepted.
The silicone sealant shall be cold applied.
_ 2.3 Self-Leveling Silicone Joint Sealant
The joint sealant shall be Dow Coming 890-SL self-leveling silicone joint sealant
as manufactured by Dow Corning Corporation, Midland, MI 48686-0994, or an
approved equal.
Self-Leveling Silicone Joint Sealant
Test Method Test Requirement
AS SUPPLIED
**** Non Volatile Content, % min. 96 to 99
MILS-8802 Extrusion Rate, grams/minute 275 to 550
ASTM D 1475 Specific Gravity 1.206 to 1.340
Skin-Over Time, minutes max. 60
Cure Time, days 14 to 21
Full Adhesion,days 14 to 21
AS CURED-AFTER
21 DAYS AT 25C
ASTM D 412, Die C Mod. Elongation, %min. 1400
ASTM D 3583 Modulus @ 150% Elongation, psi max. 9
(Sect. 14 Mod.)
ASTM C 719 Movement, 10 cycles @+100/-50% No Failure
_ ASTM D 3583 Adhesion to Concrete, % Elongation min. 600
(Sect. 14 Mod.)
ASTM D 3583 Adhesion to Asphalt, % Elongation min. 600
.� (Sect. 14 Mod.)
2.4 The joint filler sop shall be of a closed cell expanded polyethylene foam backer
• rod and polyethylene bond breaker tape of sufficient size to provide a tight seal.
The back rod and breaker tape shall be installed in the saw-cut joint to prevent
the joint sealant from flowing to the bottom of the joint. The backer rod and
breaker tape shall be compatible with the silicone joint sealant and no bond or
reaction shall occur between them. Reference is made to the"Construction
Detail'sheet for the various joint details with their respective dimensions.
T- 3. TIME OF APPLICATION
05/27/05 SPA 8
On newly constructed Portland Cement Concrete pavement,the joints shall be
initially saw cut to the required depth with the proper joint spacing as shown on
the"Construction Detail"sheet or as directed by the Engineer within 12 hours of
the pavement placement. (Note that for the"dummy"joints, the initial 1/4 inch
width "green"saw-cut and the"reservoiru saw cut are identical and should be
part of the same saw cutting operation. Immediately after the saw cutting
pressure washing shall be applied to flush the concrete slurry from the freshly
saw out joints.) The pavement shall be allowed to cure for a minimum of seven
(7)days. Then the saw cuts for the joint sealant reservoir shall be made, the
joint cleaned, and the joint sealant installed. During the application of the joint
sealant, the weather shall not be inclement and the temperature shall be 40F(4C)
and rising.
4. EQUIPMENT
4.1 All necessary equipment shall be furnished by the Contractor. The Contractor
shall keep his equipment in a satisfactory working condition and shall be
inspected by the Engineer prior to the beginning of the work. The minimum
_ requirements for construction equipment shall be as follows:
4.2 Concrete Saw:The sawing equipment shall be adequate in size and power to
complete the joint sawing to the required dimensions.
4.3 High Pressure Water Pump:The high pressure cold water pumping system shall
be capable of delivering a sufficient pressure and volume of water to thoroughly
flush the concrete slurry from the saw-cut joint.
4.4 Air Compressors:The delivered compressed air shall have a pressure in excess
of 90 psi and 120 cfm. There shall be suitable reaps for the removal of all free
water and oil from the compressed air. The blow-tube shall fir into the saw-cut
joint.
4.5 Extrusion Pump:The output shall be capable of supplying a sufficient volume of
sealant to the joint.
4.6 Injection Tool:This mechanical device shall apply the sealant uniformly into the
joint.
4.7 Sandblaster:The design shall be for commercial use with air compressors as
specified in Paragraph 5.4.
4.8 Backer Rod Roller and Tooling Instrument:These devices shall be clean and free
of contamination. They shall be compatible with the join depth and width
requirements.
5. CONSTRUCTION METHODS
�. 5.1 General: The joint reservoir saw cutting, cleaning, bond breaker installation, and
joint sealant placement shall be performed in a continuous sequence of
operations
5.2 Sawing Joints:The joints shall be saw-cut to the width and depth as shown on
the"Construction Detail"sheet. The faces of the joints shall be uniform in width
and depth along the full length of the joint
5.3 Cleaning Joints: Immediately after sawing, the resulting concrete slurry shall be
05/27/06 SP-19
completely removed from the joint and adjacent area by flushing with high
pressure water. The water flushing shall be done In one-direction to prevent
joint contamination.
When the Contractor elects to saw the joint by the dry method, flushing the joint
with high pressure water may be deleted. The dust resulting from the sawing
shall be removed from the joint by using compressed air. (Paragraph Rev. 1,
October 18, 1989)
After complete drying,the joints shall be sandblasted. The nozzle shall be
attached to a mechanical aiming device so that the sand blast will be directed at
an angle of 45 degrees and at a distance of one to two inches from the face of
the joint. Both joint faces shall be sandblasted in separate, one directional
passes. Upon the termination of the sandblasting, the joints shall be blown-out
using compressed air. The blow tube shall fit into the joints.
The blown joint shall be checked for residual dust or other contamination. If
any dust or contamination is found,the sandblasting and blowing shall be
repeated until the joint is cleaned. Solvents will not be permitted to remove
stains and contamination.
Immediately upon cleaning,the bond breaker and sealant shall be placed in the
joint. Open, cleaned joints shall not be left unsealed overnight.
Bond Breaker Rod and Tape:The bond breaker rod and tae shall be installed in
the cleaned joint prior to the application of the joint sealant in a manner that will
produce the required dimensions.
5.4 Joint Sealant: Upon placement of the bond breaker rod and tape,the joint
sealant shall be applied using the mechanical injection tool. The joint sealant
application shall not be permitted when the air and pavement temperature is less
than 40F (4C). Joints shall not be sealed unless they are clean and dry.
Unsatisfactorily sealed joints shall be refilled. Excess sealant left on the
pavement surface shall be removed and discarded and shall not be used to seal
the joints.
The pavement surface shall present a clean final condition.
Traffic shall not be allowed on the fresh sealant until it becomes tack-free.
Approval of Joints:A representative of the sealant manufacturer shall be present
at the job site at the beginning of the final cleaning and sealing of the joints. He
shall demonstrate to the Contractor and the Engineer the acceptable method for
sealant installation. The manufacturer's representative shall approve the clean,
dry joints before the sealing operation commences.
6. WARRANTY
The Contractor shall provide the Engineer a manufacturer's written guarantee on all
joint sealing materials. The manufacturer shall agree to provide any replacement
material free of charge to the City. Also, the Contractor shall provide the Engineer a
written warranty on all sealed joints. The Contractor shall agree to replace any failed
joints at no cost to the City. Both warranties shall be for two years after final
acceptance of the completed work by the Engineer.
05/27/05 SP-20
7. BASIS OF PAYMENT
Payment will be made at the Contract bid item unit price bid per linear foot(L.F.)as
provided in"MEASUREMENT°for"SILICONE JOINT SEALING",which price of
shall be full compensation for furnishing all materials and for all preparation, delivery,
and application of those sealing materials and for all labor, equipment, tools and
incidentals necessary to complete the silicone joint sealing in conformity with the plans
and these specifications.
44. PAY ITEM-THIS ITEM INTENTIONALLY OMITTED:
45. PAY ITEM- RETAINING WALL:
This item will consist of placing retaining walls in locations and at heights determined by the engineer in
the field. All applicable section of City of Fort Worth Standard Specification item 518 shall apply except
as follows:
Retaining wall shall be constructed per City of Fort Worth Construction Standard Drawing No. S-M13
"Retaining Wall With Sidewalk"where applicable.
All existing brick and/or stone retaining walls not significantly impacted by proposed grade changes will
be protected. Replacement of retaining walls not Impacted by proposed grade changes will be at the
expense of the Contractor.
46. PAY ITEM-REPLACE EXIST. CURB AND GUTTER:
This item is included for the purpose and removing and replacing existing curb and gutter in transition
areas as determined by the Engineer in the field. The proposed curb and gutter will be of the same
dimensions as the existing curb and gutter to be removed. Quantities for this pay item are
approximate and are given only to establish a unit price for the work
The price bid per linear foot for"REPLACE EXIST. CURB AND GUTTER" as shown in the Proposal
will be full payment for materials including all labor, equipment, tools and incidentals necessary to
complete the work.
47. PAY ITEM-HMAC TRANSITION:
This item will consist of the furnishing and placing at varying thicknesses an HMAC surface in transition
areas where indicated on the plans, as specified in these specifications and at other locations as may
be directed by the Engineer.
This item shall be governed by all applicable provisions of Standard,Specifications Item 312.
The price bid per ton HMAC Transition as shown in the Proposal will be full payment for materials
including all labor,equipment,tools and incidentals necessary to complete the work.
48. PAY ITEM- THIS ITEM INTENTIONALLY OMITTED:
49. PAY ITEM- TRENCH SAFETY:
Description: This item will consist of the basic requirements which the Contractor must comply with in
order to provide for the safety and health of workers in a trench. The Contractor shall develop, design
and implement the trench excavation safety protection system. The Contractor shall bear the sole
responsibility for the adequacy of the trench safety system and providing "a safe place to work"for the
workman.
The trench excavation safety protection system shall be used for all trench excavations deeper than
five (5) feet. The Excavating and Trenching Operation Manual of the Occupational Safety and Health
Administration, U.S. Department of Labor, shall be the minimum governing requirement of this item
05/27/05 SP-21
and is hereby made a part of this specification. The Contractor shall, in addition, comply with all other
applicable Federal, State and local rules, regulations and ordinances.
Measurement and Payment: All methods used for trench excavation safety protection shall be
measured by the linear foot of trench and paid at the unit price in the Proposal, which shall be total
compensation for furnishing design, materials, tools, labor, equipment and incidentals necessary,
including removal of the system.
Trench depth for payment purposes for Trench Safety Systems is the vertical depth as measured from
the top of the existing ground to the bottom of the pipe.
50. PAY ITEM - 8" THICK LIME STABILIZED SUBGRADE & CEMENT FOR SUBGRADE
STABILIZATION:
See Standard Specifications Item No. 210, "Lime Treatment (Material Manipulation)" and Specification
Item No. 212, "Hydrated Lime and Lime Slurry' for specifications governing this item. Quantities for
this pay item are approximate and are given only to establish a unit price for the work.
The price bid per square yard for"8"THICK LIME STABILIZED SUBGRADE"as shown in the Proposal
will be full payment for all labor, equipment, tools and incidentals necessary to complete the work. The
price bid per ton for "LIME FOR SUBGRADE STABILIZATION" as shown in the Proposal will be full
payment for materials necessary to complete the work.
51. PAY ITEM - 8" H.M.A.C. (FIG. 4) PAVEMENT (Thickness Tolerances and HMAC Testing
Procedures):
The base course shall be a 3" deep Type"B"course placed in one lift. The surface course shall be a
3"deep Type°D"course placed in one lift.
All provisions of Standard Specification No. 312.7 'Construction Tolerance' shall apply except as
modified herein:
1) After completion of each asphalt paving course, core tests will be made to determine compliance
with the contract specifications. The hot-mix asphaltic concrete pavement will be core drilled by
the City of Fort Worth. The thickness of the asphaltic surface will be determined by measurement
cores taken at locations determined by the Engineer. The thickness of individual cores will be
determined by averaging at least three (3) measurements. If the core measurements indicate a
deficiency, the length of the area of such deficient thickness shall be determined by additional
cores taken along the length of the pavement in each direction until cores are obtained which are
at least of specified thickness. The width of such area shall not be less than '/ of the roadway
width.
2) When the thickness of the base course (as determined from core samples) is more than 15%
deficient of the plan thickness, the Contractor shall remove and replace the deficient area at his
own expense. if the thickness is less than 15% deficient, the Contractor shall make up the
difference in the base thickness with surface course material.
3) The surface course must be the plan thickness. This does not include surface course material
used to make up deficiencies in the base course as described in item 2).
4 •
4) The overall thickness of asphaltic concrete pavement must be a minimum of the plan thickness.
Deficient areas (as determined in item 1)found to be less than the plan thickness will be removed
and replaced at the Contractor's expense.
5) No additional payment over the contract price will be made for any hot-mix asphaltic concrete
course of a thickness exceeding that required by the plans and specifications.
6) HMAC Testing Procedure:
05/27/05 SP-22
The Contractor is required to submit a Mix Design for both Type "B" and "D" asphalt that will be
used for each project This should be submitted at the Pre-Construction Conference. This design
shall not be more than two (2)years old. Upon submittal of the design mix a Marshal (Proctor)will
be calculated, if one has not been previously calculated, for the use during density testing. For
ow type"B"asphalt a maximum of 20% rap may be used. No Rap may be used in type"D"
Upon approval of an asphalt mix design and the calculation of the Marshal(proctor)the Contractor
is approved for placement of the asphalt The Contractor shall contact the City Laboratory,through
the inspector, at least 24 hours in advance of the asphalt placement to schedule a technician to
assist in the monitoring of the number of passes by a roller to establish a rolling pattern that will
provide the required densities. The required Density for Type"B" and for Type"D"asphalt will be
91% of the calculated Marshal (proctor). A Troxler Thin Layer Gauge will be used for all asphalt
testing.
After a rolling pattern is established, densities should be taken at locations not more than 300 feet
apart. The above requirement applies to both Type "B" and "D" asphalt. Densities on type "B"
must be done before Type"D"asphalt is applied.
Cores to determine thickness of Type "B" asphalt must be taken before Type "D" asphalt is
applied. Upon completion of the application of Type"D" asphalt additional cores must be taken to
determine the applied thickness.
52. PAY ITEM - CONCRETE FLAT WORK(CURB. CURB& GUTTER, SIDEWALKS, LEADWALKS,
WHEELCHAIR RAMPS AND DRIVEWAYS):
Concrete flatwork is defined as curb, curb and gutter, sidewalks, leadwalks, wheelchair ramps and
driveways as shown in the plans. This provision governs the sequence of work related to concrete
flatwork and shall be considered a supplement to the specifications governing each specific item.
Required backfilling and finished grading adjacent to flatwork shall be completed in order for the
fiatwork to be accepted and measured as completed.
No payment will be made for flatwork until the pay item has been completed, which includes backfilling
and finished grading.
53. PAY ITEM—REMOVE EXISTING CONCRETE SIDEWALK, DRIVEWAYS, STEPS, LEADWALKS
AND WHEEL CHAIR RAMPS:
This item includes removal of existing concrete sidewalks, driveways, steps, leadwalks and wheelchair
ramps at location shown on the plans or as designed by the Engineer. See Standard Specification No.
104"Removing Old Concrete", for Specifications governing this item.
54. PAY ITEM—REMOVE EXISTING CURB AND GUTTER:
Where shown on the plans or where designated by the Engineer, existing curb and or gutter and
existing laid down curb shall be removed and disposed of In a manner satisfactory to the Engineer.
_ Measurement will be by the linear foot for curb and gutter, laydown curb removed, and for all labor,
tools, and incidentals necessary to complete the job.
55. PAY ITEM—REMOVE EXISTING CURB INLET:
This item shall include all labor, materials, and equipment necessary to remove and dispose of the
existing Inlet; and removal of connecting of the existing inlet RCCP lead pipe as shown on the Plans
and as directed by the Engineer.
06/27/05 SP-23
56. PAY ITEM—6"THICK REINFORCED CONCRETE DRIVEWAY:
See Standard Specification Item No. 504, "Concrete Sidewalks and Driveways" for specifications
governing this item as well as details S-S5 and S-S5A.
The price bid per square foot for"6"THICK REINFORCED CONCRETE DRIVEWAY" as shown in the
Proposal will be full payment for materials including all labor, equipment, tools and incidentals
necessary to complete the work.
57. PAY ITEM—THIS ITEM INTENTIONALLY OMITTED:
68. PAY ITEM—4'STANDARD CONCRETE SIDEWALK LEADWALK AND WHEELCHAIR RAMP:
All applicable provisions of standard Specifications Item 104 "Removing Old Concrete" and Item 504
"Concrete Sidewalk Driveways"shall apply except as herein modified.
The Contractor shall construct standard concrete wheelchair ramps as shown on the enclosed details,
or as directed by the Engineer.
The Contractor shall not remove any regulatory sign, instruction sign, street name and sign or other
sign which has been erected by the City. The Contractor shall contact Signs and Marking Division,
TPW(Phone 871-7738).
All concrete flared surfaces shall be colored with LITHOCHROME color hardener as manufactured by
L.M. Scofield Company or equal. The color hardener shall be brick red color and dry-shake type, and
shall be used in accordance with manufacturers' instructions.
"Contractor shall provide a colored sample concrete panel of one foot by one foot by three inches
dimension, or other dimension approved by the Engineer, meeting the aforementioned specification.
The sample, upon approval by the Engineer, shall be the acceptable standard to be applied for all
construction covered in the scope of this pay item.
The method of application shall be by screen, sifter, sieve or other means in order to provide for a
uniform color distribution."
_ 59. PAY ITEM—REMOVE AND REPLACE FENCE:
This item shall include the removal and reconstruction of the existing fence at the locations shown on
the plans or where deemed necessary by the Engineer. The Contractor shall exercise caution in
removing and salvaging the materials so they may be used in reconstructing the fence. Their
constructed fence shall be equal in every way, or superior, to the fence removed. The Contractor shall
be responsible for keeping livestock within the fenced areas during construction operation and while
removing and relocating the fence, and for any damage or injury sustained by persons, livestock or
property on account of any act of omission, neglect or misconduct of his agents, employees, or
subcontractors. The unit price per linear foot shown on the Proposal shall be full compensation for all
materials, labor, equipments, tools and incidentals necessary to complete the work.
60. PAY ITEM—THIS ITEM INTENTIONALLY OMITTED:
61, PAY ITEM—REMOVE AND RECONSTRUCT MAILBOXES/MISCELLANEOUS:
This item includes the removal and reconstruction of existing mailboxes, brick walls, flowerbed trim
and miscellaneous items within the right of way which may be damaged or removed during
construction. When possible, the Contractor shall salvage existing materials for reuse in the
replacement or repair of damaged or removed items. Items which are to be repaired or reconstructed
05/27/05 SP 24
should look architecturally the same In material and appearance and should be reconstructed or
repaired in a better or new condition.
All applicable provisions of City of Fort Worth Construction Standards shall apply.
62. PAY ITEM—BORROW:
The non-expansive earth fill should consist of soil materials with a liquid limit of 35 or less, a plasticity
Index between 8 and 20, a minimum of 35 percent passing the No. 200 sieve, a minimum of 85
percent passing the No. 4 sieve, and which are free of organics or other deleterious materials. When
compacted to the recommended moisture and density, the material should have a maximum free swell
value of 0.5 percent and a maximum hydraulic conductivity (permeability) of 1 E-05 cm/sec, as
determined by laboratory testing of remolded specimens of the actual materials proposed for the non-
expansive earth fill.
63. PAY ITEM—CEMENT STABILZATION:
All applicable provisions of Item 214, 'Portland Cement Treatment shall apply.
64. PAY ITEM—CEMENT:
All applicable provisions of Item 214, 'Portland Cement Treatment shall apply.
65. PAY ITEM—THIS ITEM INTENTIONALLY OMITTED:
66. PAY ITEM—STORM DRAIN INLETS AND MANHOLES:
An alternative method of construction for these items will be "Pre-Cast" manholes and inlets. If the
Contractor desires to use this method, he must submit details for the construction to the Transportation
and Public Works Department for review and approval if said details are acceptable. The Pre-Cast
construction must be equal or superior to the strength requirements for this item as set out in Standard
Specification Item 444, "Manholes and Inlets" and said construction shall be in compliance with all
other requirements of Standard Specification Item 444 where applicable. Manholes shall be
constructed in accordance with Standard Specifications Drawing No. S-SD 7.
A trench safety system shall be used for all excavations of all depths as required in Standard
Specification Item 400. The Excavating and Trenching Operation Manual of Occupational Safety and
Health Administration, U.S. Department of Labor, Subpart P shall be the minimum governing
requirement of the item and is hereby made a part of this item and payment for the trench safety
system shall be included in the unit prices bid for the items involving trenching in this contract.
67. PAY ITEM—TRENCH EXCAVATION AND BACKFILL FOR STORM DRAIN:
Work under this item Includes all the proposed excavation and backfill in the project area and the
necessary fill area. Payment will be made for the quantity of earth excavated/backfilled. The placing
of fill shall be subsidiary to the trench excavation/backfill price. Excess material which is obtained from
excavating the trench shall be used for fill placement subject to the provisions of item 114 of the City of
Fort Worth Standard Specifications.
All excavated material which is unacceptable as fill material shall become the property of .the
Contractor to be hauled off the site and disposed of properly. Unacceptable material shall be, but not
— limited to: rocks, concrete, asphalt, debris, etc. The cost for removal and disposal of unacceptable
material shall be subsidiary to the unit prices.
88. PAY ITEM-STORM WATER POLLUTION PREVENTION (FOR DISTURBED AREAS EQUAL TO
OR GREATER THAN 1 ACRE):
05/27/05 SP-25
PERMIT: As defined by Texas Commission on Environmental Quality (TCEQ) regulations, a Texas
Pollutant Discharge Elimination System (TPDES) General Construction Permit is required for all
construction activities that result In the disturbance of one to five acres (Small Construction Activity) or
five or more acres of total land (Large Construction Activity). The Contractor is defined as an"operator"
by state regulations and is required to obtain a permit. Information concerning the permit can be
obtained through the Internet at http://www.tnrec.state,bc.ustpermitting/water
perm/wwperm/construct.html. Soil stabilization and structural practices have been selected and
designed in accordance with North Central Texas Council of Governments Best Management
Practices and Erosion Control Manual for Construction Activities (BMP Manual). This manual can be
obtained through the Internet at www.dfwstormwater.com/runoff.html. Not all of the structural controls
discussed in the BMP Manual will necessarily apply to this project. Best Management Practices are
construction management techniques that, if properly utilized, can minimize the need for physical
controls and possible reduce costs.The methods of control shall result in minimum sediment retention
of not less than 70%.
NOTICE OF INTENT(NOI): If the project will result in a total land disturbance equal to or greater than
5 acres, the Contractor shall sign at the pre-construction meeting a TCEQ Notice of Intent(NOI) form
prepared by the engineer. It serves as a notification to the TCEQ of construction activity as well as a
commitment that the Contractor understands the requirements of the permit for storm water
discharges from construction activities and that measures will be taken to implement and maintain
storm water pollution prevention at the site. The NOI shall be submitted to the TCEQ at least 48 hours
a
prior to the Contractor moving on site and shall include the required$100 application fee.
The NOI shall be mailed to:
Texas Commission on Environmental Quality
Storm Water&General Permits Team; MC-228
P.O. Box 13087
Austin, TX 78711-3087
A copy of the NOI shall be sent to:
City of Fort Worth
Department of Environmental Management
5000 MLK Freeway
Fort Worth, TX 76119
NOTICE OF TERMINATION (NOT): For all sites that qualify as Large Construction Activity, the
Contractor shall sign, prior to final payment, a TCEQ Notice of Termination (NOT) form prepared by
the engineer. It serves as a notice that the site is no longer subject to the requirement of the permit.
The NOT should be mailed to:
Texas Commission on Environmental Quality
Storm Water&General Permits Team; MC-228
P.O. Box 13087
Austin, TX 78711-3087
STORM WATER POLLUTION PREVENTION PLAN (SWPPP): A document consisting of an erosion
control and toxic waste management plan and a narrative defining site parameters and techniques to
be employed to reduce the release of sediment and pollution from the construction site. Five of the
project SWPPP's are available for viewing at the plans desk of the Department of Engineering. The
selected Contractor shall be provided with three copies of the SWPPP after award of contract, along
— with unbounded copies of all forms to be submitted to the Texas Commission on Environmental
Quality.
LARGE CONSTRUCTION ACTIVITY -- DISTURBED AREA EQUAL TO OR GREATER THAN 5
ACRES: A Notice of Intent (NOI) form shall be completed and submitted to the TCEQ including
05/27/05 SP-26
payment of the TCEQ required fee. A SWPPP that meets all TCEQ requirements prepared by the
_. Engineer shall be prepared and implemented at least 48 hours before the commencement of
construction activities. The SWPPP shall be incorporated into in the contract documents. The
Contractor shall submit a schedule for implementation of the SWPPP. Deviations from the plan must
be submitted to the engineer for approval. The SWPPP is not warranted to meet all the conditions of
the permit since the actual construction activities may vary from those anticipated during the
preparation of the SWPPP. Modifications may be required to fully conform to the requirements of the
Permit. The Contractor must keep a copy of the most current SWPPP at the construction site. Any
alterations to the SWPPP proposed by the Contractor must be prepared and submitted by the
Contractor to the engineer for review and approval. A Notice of Termination (NOT) form shall be
submitted within 30 days after final stabilization has been achieved on all portions of the site that is the
responsibility of the permittee, or, when another permitted operator assumes control over all areas of
the site that have not been finally stabilized.
SMALL CONSTRUCTION ACTIVITY - DISTURBED AREA EQUAL TO OR GREATER THAN ONE
ACRE BUT LESS THAN FIVE ACRES: Submission of a NOI form is not required. However, a TCEQ
Site Notice form must be completed and posted at the site. A copy of the completed Site Notice must
be sent to the City of Fort Worth Department of Environmental Management at the address listed
above. A SWPPP, prepared as described above, shall be implemented at least 48 hours before the
-� commencement of construction activities. The SWPPP must include descriptions of control measures
necessary to prevent and control soil erosion, sedimentation and water pollution and will be included in
the contract documents. The control measures shall be installed and maintained throughout the
construction to assure effective and continuous water pollution control. The controls may include, but
not be limited to, silt fences, straw bale dikes, rock berms, diversion dikes, interceptor swales,
sediment traps and basins, pipe slope drain, inlet protection, stabilized construction entrances,
seeding, sodding, mulching, soil retention blankets, or other structural or non-structural storm water
pollution controls. The method of control shall result in a minimum sediment retention of 70% as
defined by the NCTCOG "BMP Manual." Deviations from the proposed control measures must be
submitted to the engineer for approval.
PAYMENT FOR SWPPP IMPLEMENTATION: Payment shall be made per lump sum as shown on
the proposal as full compensation for all items contained in the project SWPPP.
.� FOR DISTURBED AREAS LESS THAN 1 ACRE, SPECIAL PROVISION 23 - 40 SHALL BE
APPLICABLE.
69. PRE BID ITEM-PROJECT DESIGNATION SIGN:
The Contractor shall construct and install two (4) Project Designation Signs and it will be the
responsibility of the Contractor to maintain the signs in a presentable condition at all times on each
project under construction. Maintenance will include painting and repairs as directed by the Engineer,
it will be the responsibility of the Contractor to have the individual project signs lettered and painted in
accordance with the enclosed detail. The quality of the paint, painting and lettering on the signs shall
be approved by the Engineer. The height and arrangement of the lettering shall be in accordance with
the enclosed detail. The sign shall be constructed of Y4* fir plywood, grade A-C (exterior) or better.
These signs shall be installed on barricades or as directed by the Engineer and in place at the project
site upon commencement of construction.
The work, which includes the painting of the signs,_ installing and removing the signs, fumishing the
materials, supports and connections to the support and maintenance shall be to the satisfaction of the
Engineer.
The unit price bid per each will be full payment for materials including all labor, equipment, tools and
incidentals necessary to complete the work.
70. PRE BID ITEM—UTILITY ADJUSTMENT:
05/27/05 SP-27
This item is included for the basic purpose of establishing a contract price which will be comparable to
the final cost of making necessary adjustments required due to street improvements to water, sanitary
sewer and natural gas service lines and appurtenances where such service lines and appurtenances
are the property owner's responsibility to maintain. An arbitrary figure has been placed In the Proposal;
however, this does not guarantee any payment for utility adjustments, neither does it confine utility
adjustments to the amount shown in the Proposal. It shall be the"Contractor' responsibility to provide
the services of a licensed plumber to make the utility adjustments determined necessary by the
Engineer. No payment will be made for utility adjustments except those adjustments determined
necessary by the Engineer. Should the Contractor damage service lines due to his negligence, where
such lines would not have required adjustment or repair otherwise, the lines shall be repaired and
adjusted by the Contractor at the Contractor's expense. The payment to the Contractor for utility
adjustments shall be the actual cost of the adjustments plus ten percent (10%) to cover the cost of
bond and overhead incurred by the Contractor in handling the utility adjustments.
71. PRE BID ITEM- TOP SOIL:
The proposed quantities shown are calculated to provide topsoil 4 to 6 inches in depth (compacted)
over the parkway area and do not include deeper than design depth behind the curb. The pay item is
intended to pay for topsoil that must be imported where suitable material is either not available on the
job or cannot reasonably be stored on-site. Payment will be made on the basis of loose truck volume
(full truck with sideboards up) tickets and material must meet City of Fort Worth standards for topsoil.
Only the volume imported will be paid for and may be substantially less than the proposal quantifies
listed.
72. PRE BID ITEM- ADJUST WATER VALVE BOX:
Contractor will be responsible for adjusting water valve boxes to match new pavement grade. The
water valves themselves will be adjusted by City of Fort Worth Water Department forces.
The unit price bid will be full payment for materials including all labor, equipment, tools and incidentals
necessary to complete the work.
73. PRE BID ITEM- MANHOLE ADJUSTMENT;
This item shall include adjusting the tops of existing and/or proposed manholes to match proposed
grade as shown on the plans or as directed by the Engineer. Standard Specification Item No.450 shall
apply except as follows:
Included as part of this pay item shall be the application of a cold-applied preformed flexible
butyl rubber or plastic sealing compound for sealing interior and/or exterior joints on concrete
manhole sections as per current City Water Department Special Conditions.
74. PRE BID ITEM- ADJUST WATER METER BOX:
This item shall Include raising or lowering an existing meter box to the parkway grade specified. No
_ payment will be made for existing boxes,which are within 0.1'of specified parkway grade.
The unit price bid will be full payment for materials including all labor, equipment, tools and incidentals
necessary to complete the work.
75. NON-PAY ITEM - CLEARING AND GRUBBING:
All objectionable items within the limits of this project and not otherwise provided for shall be removed
under this item In accordance with Standard Specification Item 102, "Clearing and Grubbing."
However, no direct payment will be made for this item and it shall be considered incidental to this
contract.
76._NON-PAY ITEM-SPRINKLING FOR DUST CONTROL:
All applicable provisions of Standard Specifications Item 200, "Sprinkling for Dust Control" shall apply.
However, no direct payment will be made for this item and it shall be considered incidental to this
contract.
05/27/05 SP-28
77. NON-PAY ITEM-PROTECTION OF TREES, PLANTS AND SOIL:
All property along and adjacent to the Contractor's operations including lawns, yards, shrubs, trees,
etc. shall be preserved or restored after completion of the work to a condition equal or better than
existed prior to start of work.
By ordinance, the Contractor must obtain a permit from the City Forester before any work (trimming,
removal or root pruning) can be done on trees or shrubs growing on public property including street
rights-of-way and designated alleys. This permit can be obtained by calling the Forestry Office at 871- .
5738. All tree work shall be in compliance with pruning standards for Class II Pruning as described by
the National Arborist Association. A copy of these standards can be provided by calling the above
number. Any damage to public trees due to negligence by the Contractor shall be assessed using the
current formula for Shade Tree Evaluation as defined by the International Society of Arboriculture.
Payment for negligent damage to public trees shall be made to the City of Fort Worth and may be
withheld from funds due to the Contractor by the City.
To prevent the spread of the Oak Wilt fungus, all wounds on Live Oak and Red Oak trees shall be
immediately sealed using a commercial pruning paint. This is the only instance when pruning paint is
recommended.
78. NON-PAY ITEM- CONCRETE COLORED SURFACE:
Concrete wheelchair ramp surfaces, excluding the side slopes and curb, shall be colored with
LITHOCHROME color hardener or equal. A brick red color, a dry-shake hardener manufactured by
L.M. Scofield Company or equal, shall be used in accordance with manufacturers instructions.
Contractor shall provide a sample concrete panel of one foot by one foot by three inches dimension, or
other dimension approved by the Engineer, meeting the aforementioned specifications. The sample,
upon approval of the Engineer, shall be the acceptable standard to be applied for all construction
covered in the scope of this Non-Pay Item. No direct payment will be made for this item and it shall be
considered incidental to this contract.
The method of application shall be by screen, sifter, sieve, or other means in order to provide for a
uniform color distribution.
79. NON-PAY ITEM- PROJECT CLEAN-UP:
The Contractor shall be aware that keeping the project site in a neat and orderly condition is
considered an integral part of the contracted work and as such shall be considered subsidiary to the
appropriate bid items. Clean up work shall be done as directed by the Engineer as the work
progresses or as needed. If, in the opinion of the Engineer it is necessary, clean up shall be done on a
daily basis. Clean up work shall include, but not be limited to:
Sweeping the street clean of dirt or debris
• Storing excess material in appropriate and organized manner
Keeping trash of any kind off of residents' property
If the Engineer does not feel that the jobsite has been kept in an orderly condition,on the next estimate
payment (and all subsequent payments until completed) of the appropriate bid item(s) will be reduced
by 25%.
Final cleanup work shall be done for this project as soon as the paving and curb and gutter has been
constructed. No more than seven days shall elapse after completion of construction before the
roadway and right-of-way is cleaned up to the satisfaction of the Engineer.
80. NON-PAY ITEM- PROJECT SCHEDULE:
Contractor shall be responsible for producing a project schedule at the pre-construction conference.
This schedule shall detail all phases of construction, including project clean up, and allow the
Contractor to complete the work in the allotted time. Contractor will not move on to the jobsite nor will
work begin until said schedule has been received and approval secured from the Construction
Engineer. However, contract time will start even if the project schedule has not been turned in. Project
05/27/05 SP-29
schedule will be updated and resubmitted at the end of every estimating period. All costs involved with
producing and maintaining the project schedule shall be considered subsidiary to this contract.
81. NON-PAY ITEM- NOTIFICATION OF RESIDENTS:
In order to cut down on the number of complaints from residents due to the dust generated when saw-
cutting joints in concrete pavement, the Contractor shall notify residents, in writing, at least 48 hours in
advance of saw-cutting joints during the construction of paving projects.
All costs involved with providing such written notice shall be considered subsidiary to this contract.
82. NON-PAY ITEM- PUBLIC NOTIFICATION PRIOR TO BEGINNING CONSTRUCTION:
Prior to beginning construction on any block In the project, the Contractor shall, on a block by block
basis, prepare and deliver a notice or flyer of the pending construction to the front door of each
residence or business that will be Impacted by construction. The notice shall be prepared as follows:
The notification notice or flyer shall be posted seven (7) days prior to beginning any construction
activity on each block in the project area. The flyer shall be prepared on the Contractor's letterhead and
shalt include the following information: Name of Project, DOE No., Scope of Project (i.e. type of
construction activity), actual construction duration within the block, the name of the Contractor's
foreman and his phone number, the name of the City's inspector and his phone number and the City's
after-hours phone number.A sample of the 'pre-construction notification'flyer is attached.
The Contractor shall submit a schedule showing the construction start and finish time for each block of
the project to the inspector. in addition, a copy of the flyer shall be delivered to the City Inspector for his
review prior to being distributed. The Contractor will not be allowed to begin construction on any block
until the flyer is delivered to all residents of the block. An electronic version of the sample flyer can be
obtained from the construction office at 871-8306.
All work involved with the pre-construction notification flyer shall be considered subsidiary to the
contract price and no additional compensation shall be made.
83. NON-PAY ITEM —PRE-CONSTRUCTION NEIGHBORHOOD MEETING:
After the pre-construction conference has been held but before construction is allowed to begin on this
project a public meeting will be held at a location to be determined by the Engineer. The Contractor,
Inspector, and project manager shall meet with all affected residents and present the projected
schedule, including construction start date, and answer any construction related questions. Every
effort will be made to schedule the neighborhood meeting within the two weeks following the pre-
construction conference but in no case will construction be allowed to begin until this meeting Is
held.
84. NON-PAY ITEM- WASHED ROCK:
All washed rock used for embedment or backfill or as otherwise directed by the Engineer shall washed,
crushed stone and shall meet the following gradation and abrasion: (Actual washing not required if
gradation is met)
Sieve Size % Retained
1" 0-10
1/2" 40-75
3/8" 55-90
#4 90-100
~' #8 95-100
Los Angeles Abrasion Test: 50% Maximum wear per A.S.T.M. Designation C-131.
85. NON-PAY ITEM—SAWCUT OF EXISTING CONCRETE:
05/27/05 SP-30
When existing concrete or H.M.A.C. is cut, such cuts shall be made with a concrete saw. The
.. Contractor may break out curb and gutter to the nearest joint if he chooses. All sawing shall be
subsidiary to the unit cost of the respective item.
86. NON PAY ITEM— LOCATION AND EXPOSURE OF MANHOLES AND WATER VALVES:
The Contractor shall be responsible for locating and marking all previously exposed manholes and
water valves in each street of this contract before the recycling process commences for a particular
street.
The Contractor shall attempt to include the construction engineer(if he is available) in the observation
and marking activity. In any event a street shall be completely marked a minimum to two (2) working
days before recycling begins on any street. Marking the curbs with paint is a recommended procedure.
It shall be the Contractor's responsibility to notify the utility companies that he has commenced work on
the project. As the recycling is completed (within the same day) the Contractor shall locate the
i covered manholes and valves and expose them for later adjustment. Upon completion of a street the
Contractor shall notify the utilities of this completion and indicate that start of the next one in order for
the utilities to adjust facilities accordingly. The following are utility contact persons:
Company Telephone Number Contact Person
Southwestern Bell Telephone (817)338-6275 "Hot Line"
Texas Utilities (817)336-9411 ext.2121 Mr. Roy Kruger
Lone Star (817)336-8381 ext. 372 Mr. Jim Bennett
Of course, under the terms of this contract, the Contractor shall complete adjustment of the storm
drain and Water Department facilities, one traffic lane at a time within five (5) working days after
completing the laying of proposed H.M.A.C. overlay adjacent to said facilities.
Any deviation from the above procedure and allotted working days may result in the shut down of the
recycling operation by the Construction Engineer.
The Contractor shall be responsible for all materials, equipment and labor to perform a most accurate
job and all costs to the Contractor shall be figured subsidiary to this contract.
87. NON PAY ITEM—TIE IN INTO STORM DRAIN STRUCTURE: The cost for making lateral tie-ins
to the storm drain structure shall be subsidiary to the bid price for the respective lines.
88. NON PAY ITEM—SPRINKLER HEAD ADJUSTMENT: The adjustment and/or relocation of
sprinkler heads encountered shall be paid for under utility adjustment in the proposal section. No other
compensation will be provided.
89. NON PAY ITEM-FEE FOR STREET USE PERMITS AND RE-INSPECTIONS: A fee for street
use permits is in effect. In addition, a separate fee for re-inspections for parkway construction, such as
driveways,sidewalks, etc.,will be required. The fees are as follows:
The street permit fee is$50.00 per permit with payment due at the time of permit application.
A re-inspection fee of $25.00 will be assessed when work for which an inspection called for is
incomplete. Payment is due prior to the City performing re-inspection.
Payment by the Contractor for all street use permits and re-inspections shall be considered subsidiary
to the contract cost and no additional compensation shall be made.
_ 90. NON PAY ITEM-TEMPORARY EROSION SEDIMENT AND WATER POLLUTION CONTROL
(FOR DISTURBED AREAS LESS THAN 1 ACRE):
05/27/05 SP-31
A. DESCRIPTION: This item shall consist of temporary soil erosion sediment and water pollution
control measures deemed necessary by the Engineer for the duration of the contract. These control
measures shall at no time be used as a substitute for the permanent control measure unless otherwise
directed by the engineer and they shall not include measures taken by the CONTRACTOR to control
conditions created by his construction operations. The temporary measures shall include dikes,
dames, berms, sediment basins, fiber mats, jute netting, temporary seeding, straw mulch, asphalt
mulch, plastic liners, rubble liners, baled-hay retards, dikes, slope drains and other devices.
B. CONSTRUCTION REQUIRMENTS: The Engineer has the authority to define erodible earth
and the authority to limit the surface are of erodible-earth material exposed by preparing right-of-way,
clearing and grubbing, the surface area of erodible-earth material exposed by excavation, borrow and
to direct the CONTRACTOR to provide temporary pollution-control measures to prevent contamination
of adjacent streams, other water course, lakes, ponds or other areas of water impoundment. Such
work may involve the construction of temporary berms, dikes, dams, sediment basins, slope drains
and use of temporary mulches, mats, seeding or other control devices or methods directed by the
Engineer as necessary to control soil erosion. Temporary pollution-control measures shall be used to
prevent or correct erosion that may develop during construction prior to installation of permanent
pollution control features, but are not associated with permanent control features on the project. The
Engineer will limit the area of preparing right-of-way, clearing and grubbing, excavation and borrow to
be proportional to the CONTRACTOR'S capability and progress in keeping the finish grading,
mulching, seeding, and other such permanent pollution-control measures current in accordance with
the accepted schedule. Should seasonal conditions make such limitations unrealistic, temporary soil-
erosion-control measures shall be performed as directed by the Engineer.
1. Waste or disposal areas and construction roads shall be located and constructed
6P in a manner that will minimize the amount of sediment entering streams.
2. Frequent fordings of live streams will not be permitted; therefore, temporary
bridges or other structures shall be used wherever an appreciable number of
stream crossing are necessary. Unless otherwise approved in writing by the
Engineer, mechanized equipment shall not be operated in live streams.
3. When work areas or material sources are located in or adjacent to live streams,
such areas shall be separated from the stream by a dike or other barrier to keep
sediment from entering a flowing stream. Care shall be taken during the
construction and removal of such barriers to minimize the muddying of a stream.
4. All waterways shall be cleared as soon as practicable of false work, piling, debris
or other obstructions placed during construction operations that are not part of the
finished work.
5. The Contractor shall take sufficient precautions to prevent pollution of streams,
M lakes and reservoirs with fuels, oils, bitumens, calcium chloride or other harmful
materials. He shall conduct and schedule his operations so as to avoid or
Fminimize siltation of streams, takes and reservoirs and to avoid interference with
movement of migratory fish.
E. SUBMITTAL: Prior to the start of the applicable construction, the Contractor shall submit for
F approval his schedules for accomplishment of soil-erosion-control work and his plan to keep the area
of erodible-earth material to a minimum. He shall also submit for acceptance his proposed method of
soil-erosion control on construction and haul roads and material sources and his plan for disposal of
F waste materials. No work shall be started until the soil-erosion control schedules and methods of
operations have been reviewed and approved by the Engineer.
05/27/05 SP-32
F
F. MEASUREMENT AND PAYMENT: All work, materials and equipment necessary to provide
temporary erosion control shall be considered subsidiary to the contract and no extra pay will be given
for this work.
91. NON PAY ITEM — 'GREEN' CEMENT POLICY: All cement utilized for this project shall be
procured from a kiln utilizing a dry kiln process that does not produce an excess 1.71b of NOx
emissions per ton of clinker produced. Cement from wet kiln process plants shall also be
acceptable if the cement manufacturer certifies that it meets the NOx emission requirements as
stated above. In cases where cement meeting the above requirement is not available, and where
cement from a non-compliant source must be utilized, the contractor shall furnish good faith effort
documentation in form of letters from two North Texas cement suppliers who use the Dry Kiln
Process stating that no stock of 'green' cement available for the contractor at that time. These
letters must be dated no later that the bid opening date of the project. All related costs for
complying with the 'Green Cement Policy shall be considered subsidiary to the applicable project
pay items.
The contractor shall submit the 'Green Cement Policy Compliance Statement at the time of the
pre-Construction conference. A copy of the Compliance Statement Is attached at the end of the
Special Conditions. Failure to comply with the 'Green' Cement policy shall be grounds for rejecting
the bid as nonresponsive.
92. NON PAY ITEM -TRAFFIC CONTROL: The Contractor will be required to obtain a 'Street Use
.. Permit" prior to starting work. Unless otherwise included as a part of the Construction documents,
the Contractor shall submit a traffic control plan (duly sealed, signed and dated by a Registered
4 Professional Engineer In the state of Texas), to the City Traffic Engineer[Tel (817)392-87701 at or
before the preconstruction conference.Although work will not begin until the traffic control plan has
been reviewed and approved, the Contractor's time will begin in accordance with the timeframe
mutually established in the 'Notice to Proceed' issued to the Contractor. The traffic control plan
shall be consistent with the provisions set forth in the "Latest Edition Texas Manual on Uniform
Traffic Control Devices for Streets and Highways" issued under the authority of the"State of Texas
Uniform Act Regulating Traffic on Highways," codified as Article 6701d Vernon's Civil Statutes,
F pertinent sections being Section Nos.27, 29, 30 and 31.
The Contractor will not remove any regulatory sign, instructional sign, street name sign or other sign,
which has been erected by the City. If it is determined that a sign must be removed to permit required
construction, the Contractor shall contact the Transportation and Public Works Department, Signs and
Markings Division, (Phone Number 871-7738)to remove the sign. In the case of regulatory signs, the
M Contractor must replace the permanent sign with a temporary sign meeting the requirements of the
above-referenced manual and such temporary sign must be installed prior to the removal of the
permanent sign. If the temporary sign is not installed correctly or if it does not meet the required
specifications, the permanent sign shall be left in place until the temporary sign requirements are met.
I!< When construction work is completed to the extent that the permanent sign can be reinstalled, the
Contractor shall again contact the Signs and Markings Division to reinstall the permanent sign and
F shall leave his temporary sign in place until such reinstallation is completed.
Work shall not be performed on certain locations/streets during "peak traffic periods" as determination
by the City Traffic Engineer and in accordance with the applicable provision of the "City of Fort Worth
Traffic Control Handbook for Construction and Maintenance Work Areas."
The lump sum pay item for traffic control shall cover design, and / or installation and maintenance of
Fm the traffic control plans.
93. NON PAY ITEM— PROTECTION OF ADJACENT STRUCTURES: Contractor is advised that the
storm drain construction will be performed in close proximity to several structures. Contractor is
F required to take all necessary steps to protect the integrity of the structures. Any measures taken to
05/27/05 SP-33
protect structures shall be considered subsidiary to other pay items and no additional payment will be
.. made to the Contractor. Furthermore, collapse Insurance must be provided as part of comprehensive
general liability insurance and shall be shown on the insurance certificate.
Where the stability of adjoining buildings, walls, or other structures is endangered by excavation
operations, Contractor shall provide support systems such as shoring, bracing, or underpinning to
ensure the stability of such structures, as designed by contractor's engineer. The city has not designed
such support systems, it being the contractor's responsibility to obtain such design as necessary as
determined by the contractor in its sole discretion.
Do not excavate below the level of the base or footing of any foundation or retaining wall if it could
pose a hazard without a determination by a registered professional engineer retained by the contractor
that the structure is sufficiently removed from the excavation so as to be unaffected by the excavation
activity, or that such excavation work will not pose a hazard to employees. Such determination by a
professional engineer shall NOT relieve the contractor of responsibility for the safety of or damage to
structures
94. PAY ITEM—CONCRETE MANHOLE COLLARS: Standard Specification Item No.444,"Manholes
and Inlets" shall govern this Item except as modified here in. Concrete manholes collars shall be
constructed at locations designated on plans in accordance to Figure S - SD 16"Reinforced Concrete
Collar Detail". Removal and disposal of existing concrete collar shall be included in this pay item—no
additional compensation will be awarded. Contractor shall dispose of concrete and other debris at a
location approved by the Engineer. Measurement will be by per each as shown in the proposal and will
be full compensation for removal and disposal of existing concrete collar, construction of concrete
collar and for all labor, tools, materials and incidentals (including saw-cutting where required or as
directed)necessary to complete the work.
95. PAY ITEM — REMOVE AND REPLACE EXISTING INLET TOPS: Standard Specifications Item
No. 452, "Removing Old Structures" shall govern this Item except as modified here in. No blasting
shall be allowed. Where shown on the plans or where designated by the Engineer, existing curb inlet
tops shall be removed and disposed of in a manner satisfactory to the Engineer. This item shall consist
of the removal and disposal of the existing inlet top a minimum of 18 inches or as required, whichever
is greater, and constructing a new inlet top to the proposed lines and grade shown on the plans. The
contractor shall maintain the existing reinforcing steel to be used as dowels for the new construction. A
concrete bonding agent shall be applied to the joint. Measurement will be per each inlet top.removed
and replaced as shown on the proposal and shall be full compensation for the removal, reconstruction
and disposal of the curb inlet top; including all labor, tools, and incidentals(including saw-cutting where
required or as directed)necessary to complete the work
A trench safety system shall be used for all excavations of all depths. The excavating and trenching
Operation Manual of Occupational Safety and Health Administration, U.S. Department of Labor;
Subpart P shall be the minimum governing requirement of the item and Is hereby made a part of this
Item and hereby made part of this specification. However no direct payment will be made for this item
and payment for trench safety system(s) shall be included in the unit prices bid for the items involving
trenching in this contract.
96. PAY ITEM — CONNECT TO EXISTING/PROPOSED STORM DRAIN INLET OR STORM DRAIN
MAIN: The Contractor shall determine the exact location, elevation, configuration and angulations of
existing storm sewer inlet, pipe or box culvert prior to manufacturing of the connecting piece. Any
differences in locations, elevation, configuration, and or angulations of existing lines between the
contract drawings and what may be encountered in the said work shall be considered as incidental to
construction.
The cost of removing any existing concrete plug or cutting into the existing inlet, pipe or box culvert
shall be included in the cost of connection. All cost incurred shall be included in the unit price bid for
the appropriate connection.
05/27/05 SP-34
97. PAY ITEM — 4" REINFORCED CONCRETE SIDEWALK. LEADWALK OR DRIVEWAY
PAVEMENT: The applicable provisions of Standard Specification Item 504 shall govern this item.
Sidewalks and lead walks shall be constructed with 3000#concrete on a two inch sand cushion. Place
one-half inch preformed bituminous expansion joints at junctions with existing work and at intervals not
to exceed 50 feet, or as directed by the Engineer. The unit price bid per square foot shall prevail
regardless of the actual final amount required and shall be full compensation for furnishing all material,
labor, and incidentals required to complete the work. The thickness of the proposed concrete shall be
based on the thickness shown on the plans and as specified in the bid items of the proposal.
98. PAY ITEM — 30" HIGH DENSITY POLETHYLENE PIPE (HDPE): Construction shall be governed
according to City Standards for HDPE Pipe and City of Fort Worth Construction Standards. The unit
price bid per Llnear Foot and shall be full compensation for the furnishing of all materials to install the
30" HDPE to the lines and grades shown on the plans or as directed by the Engineer, including
embedment, castings, fittings, storm sewer connection, labor, equipment, tools, and other incidentals
necessary to complete the work. Refer to the HDPE Installatlon detall in the detail section of this
document.
A trench safety system shall be used for all excavations of all depths. The Excavating and Trenching
Operation Manual of Occupational Safety and Health Administration, U.S. Department of Labor;
Subpart P shall be the minimum governing requirement of the item and is hereby made a part of this
item and hereby made a part of this specification. However, no direct payment will be made for this
item and payment for the trench safety system(s) shall be included in the unit prices bid for the items
F� involving trenching in this contract.
99. PAY ITEM—3X2 3X3 REINFORCED CONCRETE BOX SECTIONS: This item shall be governed
by the applicable provisions of Standard Specification Item 441 "Precast Reinforced Concrete Box
Sections". The unit price bid per Linear Foot and shall be full compensation for the furnishing of all
materials to install the 3X2, and 3X3 Reinforced Concrete Box Sections to the lines and grades shown
M on the plans or as directed by the Engineer, including embedment, castings, fittings, storm sewer
connection, labor, equipment, tools, and other incidentals necessary to complete the work.
A trench safety system shall be used for all excavations of all depths. The Excavating and Trenching
Operation Manual of Occupational Safety and Health Administration, U.S. Department of Labor;
Subpart P shall be the minimum governing requirement of the item and is hereby made a part of this
Rem and hereby made a part of this specification. However, no direct payment will be made for this
Rem and payment for the trench safety system(s) shall be included in the unit prices bid for the items
Involving trenching in this contract.
100. PAY ITEM—24" 27° AND 30" DIAMETER CLASS Ill RCP STORM DRAINS: This item shall be
governed by the applicable provisions of Standard Specification Item 440"Reinforced Concrete Culvert
Pipe". The unit price bid shall be full compensation for the furnishing of all materials to install the 24",
27" or 30" Diameter Class III Reinforced Concrete Pipe to the lines and grades shown on the plans or
as directed by the Engineer, including embedment, castings, fittings, storm sewer connection, labor,
equipment, tools, and other incidentals necessary to complete the work.
A trench safety system shall be used for all excavations of all depths. The Excavating and Trenching
Operation Manual of Occupational Safety and Health Administration, U.S. Department of Labor,
Subpart P shall be the minimum governing requirement of the item and is hereby made a part of this
M item and hereby made a part of this specification. However, no direct payment will be made for this
item and payment for the trench safety system(s) shall be included in the unit prices bid for the items
Involving trenching in this contract.
101. PAY ITEM —TRENCH SAFETY SYSTEM FOR TRENCHES GREATER THAN 5 FEET DEEP:
Description: This item will consist of the basic requirements that the contractor must comply with in
order to provide for the safety and health of workers in a trench and the protection of adjacent homes,
05/27/05 SP-35
structures and property. The contractor shall develop, design and Implement the trench excavation
safety protection system. The contractor shall bear the sole responsibility for the adequacy of the
trench safety system and providing "a safe place to work" for the workman and the protection of
adjacent homes, structures and property.
The trench excavation safety protection system shall be used for all trench excavations deeper than
five (6) feet. The Excavating and Trenching Operation Manual of the Occupational Safety and Health
Administration, U.S. Department of Labor, shall be the minimum governing requirement of this item
and is hereby made a part of this specification. The contractor shall, In addition, comply with all other
applicable Federal, State and local rules, regulations and ordinances.
The contractor shall, in addition, when working near homes, structures and property provide for the
protection of the homes, structures and property and shall at their expense be responsible for and
complete any repair needed due to damage caused by their activates.
Measurement and Payment: All methods used for trench excavation safety protection shall be
measured by the linear foot of trench and paid at the unit price in the Proposal, which shall be total
compensation for furnishing design, materials, tools, labor, equipment and incidentals necessary,
including removal of the system.
102. PAY ITEM — REMOVE CONCRETE HEADWALL: See Standard Specifications Item No. 452,
"Removing Old Structures" except as modified here in. Where designated on plans or where directed
by the Engineer, existing concrete headwall shall be removed and disposed of in a manner satisfactory
to the Engineer. No blasting shall be allowed. Measurement will be per cubic yard as shown on the
proposal and shall be full compensation for the removal and disposal of the concrete headwall;
including all labor,tools and incidentals necessary to complete the work.
103. PAY ITEM —TYPE B MODIFIED REINFORCED CONCRETE HEADWALL: Except as modified
herein, Standard Specifications for Street and Storm Drain Construction Item 410 "Concrete
Structures" shall govern this item constructed in accordance with Standard Specifications Drawing No.
S-SD 13A. The unit price bid per cubic yard for"Type 'B' Modified Reinforced Concrete Headwall"
F shall include the removal and disposal of the existing °concrete headwall wing" and includes any
demolition dowelling Into existing headwall or complete headwall replacement as required.
104. PAY ITEM - MISCELLANEOUS PLACEMENT OF MATERIAL: Material has been allocated
under various bid items in the Proposal to establish unit prices for miscellaneous placement of
material. These materials shall be used only when directed by the Engineer, depending on field
conditions. Payment for miscellaneous placement of material will be made for only that amount of
material used, measured to the nearest one-tenth unit. Payment for miscellaneous placement of
material shall be in accordance with the General Contract Documents regardless of the actual amount
used for the project.
} 105. PAY ITEM — ROCK RIP RAP PROTECTION: The contractor shall install rock riprap to line the
outfall channel as shown on plans. Construction shall be governed according to City Standards for
rock riprap and City of Fort Worth Construction Standards.
RIPRAP MATERIAL: Stone for riprap shall be durable and of a suitable quality to insure permanence in
the structure. It shall be free from cracks, seams and other defects that would tend to increase
deterioration. Rock shall be grade per the following prescribed limits:
Rock size Diameter %Smaller
30" 100
24" 65-90
18" 45-55
12" 0-20
05/27/05 SP-36
Filter Fabric Blanket: Approved Manufacturers
Supac—Heavey Grade 8NP(UV)
Trevira 011/280
Amoco 4553
Or Equal Heavy Grade as approved by Engineer
Measurement will be per Square Yard as shown on the proposal and shall be full compensation for all
materials, labor, tools,and incidentals necessary to complete the work.
106. PAY ITEM—GABIONS AND GABION MATTRESSES: Material Specifications:
• Mesh type: Flexible hexagonal woven wire mesh of 80mm opening size
• Mesh wire: Steel wire to ASTM A 975 2.7mm and PVC coated to 3.7 mm
w • Detail Reinforced selvages: All mesh edges shall be reinforced with galvanized PVC
.. coated selvage wire of 3.4 mm core and 4.4 mm overall.
• Protective Coating: Mesh wire to be galvanized to Style 1 or be galvanized to Style 3 with
a bonded grey PVC coating of mean wall thickness of 0.5mm
• Gabion Cells: TX TX 1'
• Rock Gradation: At least 85% of the rock particles, by weight, shall be within the
predominant rock size range. Use rocks that are between 4 to 8 in. for gabions and
between 3 to 6 in.for gabion mattresses.
Table 1
Minimum Panel-to-Panel Connection Strength
_ Application Strength Ib/ft
Gabions, galvanized 1,400
Gabions, PVC-coated 1,200
F Gabion mattress, galvanized and PVC-coated 700
The contractor shall install gabions to line the outfall channel as shown on plans. Construction shall be
governed according to City Standards for gabions and City of Fort Worth Construction Standards.
Furnish woven wire gabions and gabion mattresses in accordance with ASTM A 975. Furnish
producer or supplier certification that wire baskets, stiffeners, lacing wire, and spiral connectors
conform to applicable ASTM specification.
Provide filler rock consisting of clean, hard, durable rock that does not contain shale, caliches, or other
soft particles. Rock appearing to contain such particles will be tested for soundness. Provide Type 2
filter fabric when required in accordance with DMS-6200. Filter filler material should consist of hard,
durable, clean sand or gravel with a max particle size of 3/8 in. w�
Foundation Preparation: Excavate the foundation to the extent shown on the plans or as directed. it
F
Remove all loose or otherwise unsuitable materials. Carefully backfill all depressions to grade with
suitable materials from adjacent required excavation or another approved source, and compact the
backfill to a density at least equal to that of the adjacent foundation. Remove any buried debris ri
protruding from the foundation that will impede the proper installation and final appearance of the
gabion or gabion mattress, and carefully backfill and compact voids as specified above. Immediately
before gabion placement, have the Engineer inspect the prepared foundation surface.
F
Filter Placement: When filter material is required, spread it uniformly on the prepared foundation
surface to the slopes, lines, and grades indicated on the plans. Do not place filter material by methods 4�4
that tend to segregate particle sizes. Repair all damage to the foundation surface that occurs during 4!
filter placement before proceeding with the work. Compaction of the filter material is not required, but i
finishes the material to present a reasonably even surface,without mounds or windrows.
05/27/05 SP-37
A
1411
Filter Fabric Placement: When filter fabric is required, place it as shown on the plans. Any defects,
rips, holes, flaws, or damage to the material may be cause for rejection. Place the material with the
long axis parallel to the centerline of the structure, highway, or dam. Place securing pins in the lapped
longitudinal joints, spaced on approximately 10-ft. centers. Keep the fabric material free of tension,
stress, folds, wrinkles, or creases. Lap the material at least 3 ft. along the longitudinal joint of material,
or lap the joints 1 ft. and sew them. Lap the ends of rolls at joints by at least 3 ft. Repair torn or
punctured fabric by placing a layer of fabric over the damaged area, overlapping at least 3 ft. beyond
the damaged area in all directions. Place securing pins through both strips of material at lapped joints
at approximately the midpoint of the overlap. Place additional securing pins as necessary to hold filter
fabric in position. Store filter fabric out of direct sunlight. After placing filter fabric, cover as soon as
possible but within 3 days.
Assembly and Installation: If PVC wire coating is specified, do not place PVC-coated materials
unless the ambient temperature and the temperature of the coated wire are at least 15°F above the
brittleness temperature of the PVC. Assemble empty gabion or gabion mattress units individually, and
place them on the approved surface to the lines and grades shown on the plans with the sides, ends,
and diaphragms erected to ensure that all creases are in the correct position, the tops of all sides are
level, and all sides that are to remain exposed are straight and plumb. Fill the basket units after
transporting them to their final position in the work. Place the front row of gabion or gablon mattress
units first and successively construct units toward the top of the slope or the back of the structure.
Place the initial line of basket units on the prepared surface, and partially fill them to provide anchorage
against deformation and displacement during subsequent filling operations. Stretch and hold empty
basket units as necessary to remove kinks and provide a uniform alignment. Before filling, connect all
adjoining empty gabion or gabion mattress units with lacing, wire spiral binders, or approved fasteners
along the perimeter of their contact surface to obtain a monolithic structure. If lacing wire is used,
provide continuous stitching with alternating single and double loops at intervals of no more than 5 in.
Securely fasten all lacing wire terminals. Provide connections meeting the joint strength requirements
of Table 1. These requirements apply to all connections including attachment of end panels,
diaphragms, and lids. Join twisted wire baskets through selvage-to-selvage or selvage-to-edge wire
connection; do not use mesh-to-mesh or selvage-to-mesh wire connection except where baskets are
offset or stacked, in which case join each mesh opening where mesh wire meets selvage or edge wire.
Carefully fill the basket units with stone, using hand placement to avoid damaging wire coating, to
ensure as few voids as possible between the stones and to maintain alignment. Machine placement of
stone will be allowed if approved by the Engineer. Correct excessive deformation and bulging of the
mesh before further filling. To avoid localized deformation, fill the basket units in a row in stages
consisting of maximum 12-in. courses; do not at any time fill a cell to a depth exceeding 1 ft. more than
its adjoining cell. Do not drop stones into the basket units from a height greater than 36 in. For gablon
units more than 2 ft. high, place 2 uniformly spaced internal connecting wires between each stone layer
In all front and side gablon units, connecting the back and the front faces of the compartments. Loop
connecting wires or preformed stiffeners around 2 twisted wire mesh openings or a welded wire joint at
each basket face, and securely twist the wire terminals to prevent loosening. Along all exposed faces,
carefully place the outer layer of stone and arrange it by hand to ensure a neat and compact
appearance. Overfill the last layer of stone uniformly by 1 to 2 in. for gabions and 1 in. for gabion
mattresses to compensate for future settlement in rock while still allowing for the proper closing of the
lid and providing an even surface with a uniform appearance. Make final adjustments for compaction
and surface tolerance by hand. Stretch lids tight over the stone fill, using an approved lid-closing tool,
until the lid meets the perimeter edges of the front and end panels. Do not use crowbars or other
single-point leverage bars for lid closing. Close the lid tightly along all edges, ends, and internal-cell
diaphragms with spiral binders or lacing wire or with other wire fasteners if approved. Ensure that all
projections or wire ends are turned into the baskets. Where shown on the plans or directed or where a.
complete gabion or gabion mattress unit cannot be installed because of space limitations, cut the
basket unit and fold and wire it together to suit site conditions. Fold the mesh back and neatly wire it to
an adjacent basket face. Complete the assembling, installation, filling, lid closing, and lacing of the
reshaped gabion or gabion mattress units in accordance with this Section.
05/27/05 SP-38
Measurement will be by the Cubic Yard of stone-filled gabions. Gabon mattresses will be measured in
place by the Square Yard of surface area or by the Cubic Yard. The price bid is full compensation for
wire baskets, stone fill, lacing and fasteners,filter fabric,filter material, excavation, grading and backfill,
materials, tools, equipment, labor, and incidentals. Filter fabric and filter material, if used, will not be
paid for directly but will be considered subsidiary to this Item.
107. PAY ITEM —8" DIAMETER WATERLINE ADJUSTMENT TO AVOID CONFLICT WITH STORM
DRAIN: The locations of potential grade conflicts with the proposed stormdrain have been shown on
the stormdrain construction plans. Waterline relocation shall comply with the WATERLINE
ADJUSTMENT DETAIL as shown on the construction plans DETAIL sheet. Waterline construction
and materials shall comply with Fort Worth Water Department's General Contract Documents and
Specifications, effective July 1, 1978, with the latest revisions. The unit price bid for"8-Inch Diameter
Waterline Adjustment to shall include all pipe, fittings, blocking, encasement, materials, excavation,
backfill, equipment, labor and work necessary to adjust waterlines at each stormdrain location where
the waterline elevation conflicts with the proposed storm drain or lead pipes.
108. PAY ITEM—INSTALLATION OF WATER FACILITIES:
108.1 Polyvinyl Chloride(PVC)Water Pipe
POLYVINYL Chloride Plastic Water Pipe and fittings on this Project shall be in accordance with the
material standard contained in the General Contract Documents. Payment for work such as backfill,
bedding, blocking, detectable tapes and all other associated appurtenant required, shall be included in
the linear foot price bid of the appropriate BID 1TEM(S).
108.2 Blocking
Concrete blocking on this Project will necessarily be required as shown on the Plans and shall be
installed in accordance with the General Contract Documents. All valves shall have concrete blocking
provided for supporting. No separate payment will be made for any of the work involved for the item
and all costs incurred will be considered to be included in the linear foot bid price of the pipe or the bid
price of the valve.
" 108.3 Type of Casing Pipe
1.WATER:
The casing pipe for open cut and bored or tunneled section shall be AWWA C-200 Fabricated
Electrically Welded Steel Water Pipe, and shall conform to the provisions of E1-15, E1-5 and E1-9 in
Material Specifications of General Contract Documents and Specifications for Water Department
Projects. The steel casing pipe shall be supplied as follows:
For the inside and outside of casing pipe, coal-tar protective coating in accordance with the
requirements of Sec. 2.2 and related sections in AWWA C-203.
Touch-up after field welds shall provide coating equal to those specified above.
C. Minimum thickness for casing pipe used shall be 0.375 inch.
Stainless Steel Casing Spacers (centering style) such as manufactured by Cascade Waterworks
Manufacturing Company or an approved equal shall be used on all non-concrete pipes when Installed
In casing. Installation shall be as recommended by the manufacturer.
2.SEWER:
Boring used on this project shall be in accordance with the material standard E1-15 and Construction
standard E2-15 as per Fig. 110 of the General Contract Documents.
3. PAYMENT:
Payment for all materials, labor, equipment, excavation, concrete grout, backfill, and incidental work
shall be included in the unit price bid per foot.
108.4 Tie-Ins
05/27/05 SP-39
F 7
The Contractor shall be responsible for making tie-ins to the existing water mains. It shall be the
responsibility of the Contractor to verify the exact location and elevation of the existing line tie-ins. And
any differences in locations and elevation of existing line tie-ins between the contract drawings and
what may be encountered in the field shall be considered as incidental to construction. The cost of
making tie-ins to existing water or sanitary sewer mains shall be included in the linear foot bid price of
the pipe.
108.5 Connection of Existing Mains
The Contractor shall determine the exact location, elevation, configuration and angulation of existing
water or sanitary sewer lines prior to manufacturing of the connecting piece. Any differences in
locations, elevation, configuration, and or angulation of existing lines between the contract drawings
and what may be encountered in the said work shall be considered as incidental to construction.
Where it is required to shut down existing mains in order to make proposed connections, such down
time shall be coordinated with the Engineer, and all efforts shall be made to keep this down time to a
minimum, In case of shutting down an existing main, the Contractor shall notify the Manager,
Construction Services, Phone 871-7813, at least 48-hours prior to the required shut down time. The
Contractor's attention is directed to Paragraph C5-5.15 INTERRUPTION OF SERVICE, Page C5-5(5),
PART C - GENERAL CONDITIONS OF THE WATER DEPARTMENT GENERAL CONTRACT
DOCUMENTS AND GENERAL SPECIFICATIONS. The Contractor shall notify the customer both
personally and in writing as to the location,time,and schedule of the service interruption.
The cost of removing any existing concrete blocking shall be included in the cost of connection.
Unless bid separately all cost incurred shall be included in the linear foot price bid for the appropriate
pipe size.
108.6 Valve Cut-Ins
It may be necessary to cut-in gate valves to isolate the water main from which the extension and/or
iF replacement is to be connected. This may require closing valves in other lines and putting consumers
out of service for that period of time necessary to cut in the new valve; the work must be expedited to
the utmost and all such cut-ins must be coordinated with the engineer in charge of inspection. All
consumers shall be individually advised prior to the shut out and advised of the approximate length of
F time they may be without service.
Payment for work such as backfill, bedding, fittings, blocking and all other associated appurtenants
required, shall be included in the price of the appropriate bid items.
F
108.7 Water Services
The relocation, replacement, or reconnection of water services will be required as shown on the plans,
and/or as described in these Special Contract Documents in addition to those located in the field and
identified by the Engineer.
All service's shall be constructed by the contractor utilizing approved factory manufactured tap saddles
(when required) and corporation stops, type K copper water tubing, curb stops with lock wings, meter
boxes, and if required approved manufactured service branches. All materials used shall be as
specified in the Material Standards(E1-17&E1-18)contained in the General Contract Documents.
All water services to be replaced shall be installed at a minimum depth of 36 inches below final grade.
All existing 3/4-inch water service lines which are to be replaced shall be replaced with 1-inch Type K
copper, 1-inch diameter tap saddle when required, and 1-inch corporation from the main line to the
meter box.
All services which are to be replaced or relocated shall be installed with the service main tap and
service line being in line with the service meter unless otherwise directed by the Engineer.
05/27/05 SP-40
A minimum of 24 hours advance notice shall be given when service interruption will be required as
specified In Section C5-5.15 INTERRUPTION OF SERVICE.
All water service meters shall be removed, tagged, and collected by the contractor for pickup by the
Water Department for reconditioning or replacement. After installation of the water service in the
proposed location and receipt of a meter from the project inspector the contractor shall install the
meter. The meter box shall be reset as necessary to be flush with existing ground or as otherwise
Ih directed by the Engineer. All such work on the outlet side of the service meter shall be performed by a
licensed plumber.
1. WATER SERVICE REPLACEMENTS: Water service replacement or relocation is required when
the existing service is lead or is too shallow to avoid breakage during street reconstruction. The
contractor shall replace the existing service line with Type K copper from the main to the meter, curb
stop with lock wings, and corporation stop.
Payment for all work and materials such as backfill, fittings, type K copper tubing, curb stop with lock
wings, service line adjustment, and any relocation of up to 12-inches from center line existing meter
location to center line proposed meter location shall be included in the Linear Foot price bid for Copper
Service Line from Main to five (5) feet behind Meter. Any vertical adjustment of customer service line
Within the 5 foot area shall be subsidiary to the service installation.
Payment for all work and materials such as tap saddle(if required), corporation stops, and fittings shall
be included in the price bid for Service Taps to Main.
i 2. WATER SERVICE RECONNECTION: Water service reconnection Is required when the existing
service is copper and at adequate depth to avoid breakage during street reconstruction. The
contractor shall adjust the existing water service line as required for reconnection and furnish a new
tap with corporation stop. The contractor will be paid for one (1) Service Tap to Main for each service
F reconnected plus for any copper service line used in excess of five (5) feet from Main to five (5) feet
behind the Meter.
3. WATER SERVICE METER AND METER BOX RELOCATIONS: When the replacement and
relocation of a water service and meter box is required and the location of the meter and meter box is
moved more than twelve(12) inches, as measured from the center line of the existing meter to location
to the center line of the proposed meter location, separate payment will be allowed for the relocation of
service meter and meter box. Centerline is defined by a line extended from the service tap through the
meter. Only relocations made perpendicular to this centerline will be paid for separately. Relocations
made along the centerline will be paid of in feet of copper service line.
When relocation of service meter and meter box is required, payment for all work and materials such
as backfill, fittings, five (5) feet of type K copper service and all materials, labor, and equipment used
by and for the licensed plumber shall be included in the price bid for the service meter relocation. All
other costs will be included in other appropriate bid item(s).
This item will also be used to pay for all service meter and meter box relocations as required by the
Engineer when the service line is not being replaced. Adjustment of only the meter box and customer
service line within 5 feet distance behind the meter will not justify separate payment at any time.
Locations with multiple service branches will be paid for as one service meter and meter box
relocation.
4. NEW SERVICE: When new services are required the contractor shall install tap saddle (when
required), corporation stop,type K copper service line, curb stop with lock wings, and meter box.
Payment for all work and materials such as backfill, fittings, type K copper tubing, and curb stop with
_ lock wings shall be included in the Linear Foot price bid for Service Line from Main to Meter five (5)
feet behind the meter.
h 05/27/05 SP-41
F
Payment for all work and materials such as tap saddle, corporation stops, and fittings shall be Included
in the price bid for Service Taps to Mains.
Payment for all work and materials such as furnishing and setting new meter box shall be included in
the price bid for furnish and set meter box.
5. MULTIPLE SERVICE BRANCHES: When multiple service branches are required the contractor
shall furnish approved factory manufactured branches.
Payment for multiple service branches will include furnishing and installing the multiple service branch
only and all other cost will be included in other appropriate bid item(s).
6. MULTIPLE STREET SERVICE LINES TO SINGLE SERVICE METER: Any multiple service lines
with taps servicing a single service meter encountered during construction shall be replaced with one
service line that is applicable for the size of the existing service meter and approved by the Engineer.
Payment shall be made at the unit bid price in the appropriate bid item(s).
108.8 2-Inch Temporary Service Line
The 2-inch temporary service main and 3/4-inch service lines shall be installed to provide temporary
water service to all buildings that will necessarily be required to have severed water service during said
work. The contractor shall be responsible for coordinating the schedule of the temporary service
connections and permanent service reconnections with the building owners and the Engineer in order
that the work be performed in an expeditious manner. Severed water service must be reconnected
within 2 hours of discontinuance of service.
A 2-inch tapping saddle and 2-inch corporation stop or 24nch gate valve with an appropriate fire
hydrant adapter fitting shall be required at the temporary service point of connection to the City water
supply. The 2-inch temporary service main and 3/4-inch service lines shall be installed in accordance
to the attached figures 1, 2 and 3. 2" temporary service line shall be cleaned and sterilized by using
chlorine gas or chlorinated lime(HTH)prior to installation.
In order to accurately measure the amount of water used during construction, the Contractor will install
.. a fire hydrant meter for all temporary service lines. Water used during construction for flushing new
mains that cannot be metered from a hydrant will be estimated as accurately as possible. At the pre-
construction conference the contractor will advise the inspector of the number of meters that will be
needed along with the locations where they will be used. The inspector will deliver the hydrant meters
to the locations. After installation, the contractor will take full responsibility for the meters until such
time as the contractor returns those meters to the inspector. Any damage to the meters will be the
sole responsibility of the contractor. The Water Department Meter Shop will evaluate the condition of
the meters upon return and if repairs are needed the contractor will receive an invoice for those
repairs. The issued meter Is for this specific project and location only. Any water that the contractor
may need for personal use will require a separate hydrant meter obtained by the Contractor, at their
cost,from the Water Department.
The out-of-service meters shall be removed, tagged and collected by the Contractor for delivery to the
Water Department Meter Shop for reconditioning or replacement. Upon restoring permanent service,
the Contractor shall re-Install the meters at the correct location. The meter box shall be reset as
necessary to be flush with the existing ground or as otherwise directed by the Engineer.
The temporary service layout shall have a minimum available flow rate of 5 GPM at a dynamic
pressure of 35 PSI per service tap. This criteria shall be used by the Contractor to determine the length
of temporary service allowed, number of service taps and number of feed points.
When the temporary service is required for more than one location the 2-inch temporary service pipes,
3/4-inch service lines and the 2-inch meter shall be moved to the next successive project location.
05/27/05 SP-42
Payment for work such as fittings, 3/4-inch service lines, asphalt, barricades, all service connections,
removal of temporary services and all other associated appurtenants required, shall be Included in the
appropriate bid item.
108.9 Adjust Manholes, and Vaults(Utility Cut)
Contractor will be responsible for adjusting water valve boxes, manholes and vaults to match new
pavement grade. The unit price bid will be full payment for materials including all labor, equipment,
tools and incidentals necessary to complete the work.
108.10 Adjust Water Valve Boxes
Contractor will be responsible for adjusting water valve boxes to match new pavement grade. The
water valves themselves will be adjusted, if necessary, by City of Fort Worth Water Department forces.
Prior to the beginning of work,the Contractor shall make an inventory of the condition of existing water
valve boxes. The Construction Engineer will field verify this inventory and provide the Contractor
replacements for broken valve boxes. The contractor shall replace the valve boxes which are
_ damaged during construction at no cost to the City.
The unit price bid per each will be full compensation for all labor, materials, equipment, tools, and
incidentals necessary to complete the work.
108.11 Purging and Sterilization of Water Lines
Before being placed into service all newly constructed water lines shall be purged and sterilized in
accordance with E2-24 of the General Contract Documents and Specifications except as modified
herein. The Contractor will furnish all water for INITIAL cleaning and sterilization of water lines. All
materials for construction of the project, including appropriately sized "pipe cleaning pigs", chlorine gas
or chlorinated lime (HTH)shall be furnished by the Contractor. Chlorinated lime(HTH)shall be used in
sufficient quantities to provide a chlorine residual of fifty(50) PPM. The residual of free chlorine shall
be measured after 24 hours and shall not be less than 10 parts per million of free chlorine. Chlorinated
water shall be disposed of in the sanitary sewer system. Should a sanitary sewer not be available,
chlorinated water shall be"de-chlorinated" prior to disposal. The line may not be placed in service until
two successive sets of samples,taken 24 hours apart, have met the established standards of purity.
Purging and sterilization of the water lines shall be considered as incidental to the project and all costs
incurred will be considered to be included in the linear foot bid price of the pipe.
108.12 Work Near Pressure Plane Boundaries
M Contractor shall take note that the water line to be replaced under this contract may cross or may be In
close proximity to an existing pressure plane boundary. Care shall be taken to ensure all "pressure
plane" valves Installed are installed closed and no cross connections are made between pressure
M planes
108.13 Water Sample Station
GENERAL:
All water sampling station installations will be per attached Figure 34 or as required in large water
meter vaults as per Figure 33 unless otherwise directed by the Engineer.
The appropriate water sampling station will be furnished to the Contractor free of charge; however, the
Contractor will be required to pick up this item at the Field Operations Warehouse.
PAYMENT FOR FIGURE 34 INSTALLATIONS: Payment for all work and materials necessary for the
installation of the 3/4-inch type K copper service line will be shall be
Included in the price bid for copper Service Line from Main to Meter.
05/27/05 SP-43
The appropriate water sampling station will be furnished to the Contractor free of charge; however, the
Contractor will be required to pick up this item at the Field Operations Warehouse.
PAYMENT FOR FIGURE 34 INSTALLATIONS: Payment for all work and materials necessary for the
installation of the 3/4-inch type K copper service line will be shall be
Included in the price bid for copper Service Line from Main to Meter.
Payment for all work and materials necessary for the installation tap saddle (if required), corporation
stops, and fittings shall be included in the price bid for Service Taps to Main.
Payment for all work and materials necessary for the installation of the sampling station, concrete
support block, curb stop, fittings, and an incidental 5-feet of type K copper service line which are
required to provide a complete and functional water sampling station shall be included in the price bid
for Water Sample Stations,
PAYMENT FOR FIGURE 33 INSTALLATIONS: Payment for all work and materials necessary for the
Installation tap saddle, gate valve, and fittings shall be included in the price bid for Service Taps to
Main.
Payment for all work and materials necessary for the installation of the sampling station, modification
to the vault, fittings, and all type K copper service line which are required to provide a complete and
functional water sampling station shall be included in the price bid for Water Sample Stations.
108.14 Ductile Iron and Gray Iron Fittings
Reference Part E2 Construction Specifications, Section E2-7 Installing Cast Iron Pipe, fittings, and
Specials, Sub section E2-7.11 Cast Iron Fittings:
E2-7.11 DUCTILE-IRON AND GRAY-IRON FITTINGS: All ductile-iron and gray-iron fittings shall be
furnished with cement mortar lining as stated in Section E1-7. The price bid for waterline adjustment
will include the price per ton of fittings shall be payment in full for all fittings, joint accessories,
polyethylene wrapping, horizontal concrete blocking, vertical tie-down concrete blocking, and concrete
cradle necessary for construction as designed.
All ductile-iron and gray-iron fittings, valves and specials shall be wrapped with polyethylene wrapping
conforming to Material Specification E1-13 and Construction Specification E2-13. Wrapping shall
precede horizontal concrete blocking, vertical tie-down concrete blocking, and concrete cradle.
Payment for the polyethylene wrapping, horizontal concrete blocking, vertical tie-down concrete
blocking, and concrete cradle shall be included In bid items for vales and fittings and no other
payments will be allowed.
109. PAY ITEM — SODDING: Except as modified herein, Standard Specifications for Construction
Item 118°Sodding" shall govern this item. Sodding shall be installed as directed by the Engineer. The
unit price bid of Nine(9) Dollars per Square Yard of Sodding will be full compensation for all materials,
labor,tools, and incidentals necessary to complete the work.
110. PAY ITEM-FLOWABLE FILL:
A. Description
This item governs the use of Ready-Mix Flowable Fill, sometimes known as Controlled Density Fill
(CDF), as an alternative to compacted soil. It is sometimes used for bedding, encasement, and
closures for tanks and pipes. It is also used for general backfill in trenches and abutments. Flowable
fill is always less than 2500 psi in ultimate strength and may be designed to be less than 150 psi where
future excavation is probable.
05/27/05 SP-44
Flowable fill will normally consist of Portland cement,flyash, sand, fine rock,and water in various
mixtures depending on the design strength of the mixture. It may contain high volumes of entrained air
to act as a strength capping agent and/or to improve flowability. Ready-Mix flowable fill or Controlled
Density Fill is prepared at the batch plant. Slump is designed for 10"to 12"and will generally be self
leveling. It should not require vibration after placement.
B. Materials
A. Portland Cement meeting ASTM C-150
B. Aggregates meeting the requirements of ASTM C-33
C. Sand or fine aggregate meeting the City of Ft.Worth Sped#406
D. Fyyash, Class C or F, meeting the requirements of ASTM C-618
.E. Admixture
(1) Mineral admixtures will be pozzolanic materials used in the standard ready mix.
(2) Chemical admixtures shall be in liquid or powder form used in standard ready-mix
concrete production unless specifically designed for flowable fill. Permissible types of
admixtures are:
a. High air generators specifically designed for Flowable Fill to lower unit weights,
reduce shrinkage and subsidence, and control compressive strength.
b. Air entraining admixtures conforming to ASTM C-260.
c. High range water reducers conforming to ASTM C494,Type F or G.
d. Accelerating admixtures conforming to ASTM C-494, Type C.
1. Non chloride, non corrosive accelerators will be used where metals are
present in concrete or embedded members.
2. Calcium chloride
C. Mixtures
The Contractor shall gain the engineer's approval for use of Ready-Mix Flowable Fill mixture. The
examples of various types listed below are for information only and should be confirmed by trial
batches. The various categories of Ready Mix Flowable Fill are as follows:
Type 1 Very flowable(non-excavatable)
Type 1 E Very flowable(excavatable)
Type 2 Flowable(non-excavatable)
_ Type 2E Flowable(excavatable)
Type 1 mixes will contain a minimum of 250 lbs. of Class C or Class F flyash or high air(25%plus)and
F will be self leveling. They are intended for use in permanent installations such as fill under structures.
They are capable of moving long distances and filling small areas. Type 1 mixes are not suitable for
bedding of pipe.
Sample Type 1 Mix
Cement 50lbs,
Fly Ash 250 lbs.
F Sand 2700 lbs.
Water 60lbs.
Type 2 mixes are used where size and distance do not require the very flowable characteristics of Type
1. They are intended for permanent installations such as thick fill under structures. They typically
contain less flyash and/or air unless the excavatable feature is required.
Type 1 E and 2E mixes(excavatable mixes)shall be hand tool excavatable and shall meet the following
requirements:
Time 28 day 90 Day
Compressive Strength 30-60 psi 100 psi Max
Air 22-30 percent
In the absence of prior strength data, mixes shall contain a minimum of 50 lbs. cement, 160 lbs, flyash,
F and shall have a plastic unit weight of 90-115 per cubic foot.
05/27/05 SP-45
D. Execution
1). Contractor shall secure site during the placement and curing period for the Flowable Fill
using stations, lights, fences, steel plates, etc. as required.
2). Contractor s supplier will,pretest all pump applications prior to day of placement with
actual equipment. Flowable Fill shall be batched at the concrete plant and hauled to job sites in ready-
mix trucks with continuous agitating drums shall agitate mixture. Entrained air shall be added as per
manufacturer's instructions. -
3). Tanks, pipes, and all other members to be encased in Flowable Fill shall be temporarily
secured in place to prevent displacement by the Flowable Fill mixture during the Flowable Fill
placement. Should the pipe or structure move either horizontally or vertically,the flowable fill and the
structure shall immediately be removed and the pipe or structure re-laid to proper line and grade. To
reduce hydrostatic pressure and limit displacement potential, Contractor may use a high air generator
In the Flowable Fill mixture to lower unit weights.
4). The height of free fall of the flowable fill shall not exceed four feet or as directed by the
Engineer. The use of a vibrator will not be required. After the flowable fill has been placed, it shall not
be covered or subjected to additional loads for 24 hours. Curing will not be required.
E. Basis of Payment
The basis of payment for Ready-Mix Flowable Fill shall be by the cubic yard of material in
place where specified for use by an item in the proposal. The unit prices bid for this type of material
shall prevail regardless of the actual amount used for the project. Where the Contractor opts to use
flowable fill in lieu of granular backfill specified,the price shall be considered subsidiary to the various
bid items in the contract.
05/27/05 SP-46
(To be printed on Contractor's Letterhead)
Date:
DOE No: 4744
PROJECT NAME: Water/Sanitary Sewer and Paving/Storm Drain Improvements for:
LOST CREEK PHASE 2 DRAINAGE 1 WROVEMENTS
MAPSCO LOCATION:
LIMITS OF CONST.:
LOST CREEK ADDITION-FROM BLUE CREEK COURT SOUTH TO MARY'S CREEK
LOST CREEK ADDITION—FROM BEN CREEK COURT SOUTH TO GOLF COURSE
WEST POINT ADDITION--FROM POWDERHORN ROAD TO PARK JUST SOUTH OF
LITTLE VALLEY ROAD_
EKQJECT NO.C200 541200 203280008783.FILE NO. SD-0135
Estimated Duration of Construction on your Street: days
THIS IS TO INFORM YOU THAT UNDER A CONTRACT WITH THE
M CITY OF FORT WORTH, OUR COMPANY WILL < REPLACE WATER
_ AND/OR SEWER LINES - RECONSTRUCT THE STREET> ON OR
AROUND YOUR PROPERTY.
CONSTRUCTION WILL BEGIN APPROXIMATELY SEVEN DAYS
FROM THE DATE OF THIS NOTICE.
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY
OR ANY OTHER ISSUE, PLEASE CALL:
Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.>
OR
Mr. <CITY INSPECTOR> AT<TELEPHONE NO.>
AFTER 4:30 PM OR ON WEEKENDS, PLEASE CALL 871-7970
PLEASE KEEP THIS FLYER HANDY WHEN YOU CALL.
05/27/06 SP-47
(To be printed on Contractor's Letterhead)
Date:
DOE No:DOE PROJECT NO. 4744
PROJECT NAME:LOST CREEK PHASE 2 DRAINAGE IMPROVEMENTS
MAPSCO LOCATION:
LIMITS OF CONST.:
LOST CREEK ADDITION-FROM BLUE CREEK COURT SOUTH TO MARY'S
CREEK
LOST CREEK ADDITION—,FROM BEN CREEK COURT SOUTH TO GOLF COURSE
WESTPOINT ADDITION—POWDERHORN ROAD TO PARK JUST SOUTH OF
LITTLE VALLY ROAD
PROJECT NO.C200 541200 203280008783,FILE No. SD-0135 ,
Estimated Duration of Construction on your Street: days
**NOTICE**
Construction only three days away
DEAR RESIDENT,
AS A FOLLOW UP TO OUR PREVIOUS FLYER DATED ,
THIS IS TO INFORM YOU THAT CONSTRUCTION ON THE
ABOVE MENTIONED PROJECT IN YOUR NEIGHBORHOOD
WILL BEGIN IN THREE DAYS FROM THE DATE OF THIS
NOTICE.
IF YOU HAVE QUESTIONS ABOUT ACCESS, SECURITY, SAFETY
OR ANY OTHER ISSUE, PLEASE CALL IMMEDIATELY:
Mr. <CONTRACTOR'S SUPERINTENDENT> AT <TELEPHONE NO.>
OR
Mr. <CITY INSPECTOR>AT <I'ELEPHONE NO.>
PLEASE DEEP THIS FLYER HANDY WHEN YOU CALL.
GREEN CEMENT POLICY COMPLIANCE STATEMENT
(To be furnished by the Contractor to the City at the time of bid opening)
(Submit separate forms for each supplier!retailer)
This goes to certify that the cement used for this project meets the
following criteria:
❑ The cement was manufactured in a kiln utilizing the dry process
(list source below) that met the emission standard of 1.71b or
less of NQx /ton of clinker released into the atmosphere.
❑ The cement meets ASTM C-150 requirements
Source of Cement:
Name of Concrete Supplier
Name of Plant(Kiln) & Address
Name of Manufacturer
CONTRACTOR SUPPLIER
Name Name
.. Title Title
Company Company
Phone Number Phone Number
CITY OF FORT WORTH
CORRUGATED DUAL WALL HDPE PIPE TRENCH INSTALLATION DETAIL
NOTES:
1. BEDDING AND BACKFlLL MATERIAL: PIPE EMBEDMENT SHALL
BE CRUSHED STONE OR ROCK, CRUSHED GRAVEL OR
GROUND SURFACE CRUSHED CONCRETE, 100X PASSING 1-4 INCH SIEVE, S 10%
PASSING No. 4 SIEVE AND < 5X PASSING No. 200 SIEVE,
.A
NON-PLASTIC EQUAL TO NORTH CENTRAL TEXAS COUNCIL OF
y, GOVERNMENTS AGGREGATE GRADE 4 OR CITY OF FORT WORTH
f.i . SPECIFICATION 402.2
2. FOUNDATION: WHERE THE TRENCH BOTTOM IS UNSTABLE,
THE CONTRACTOR SHALL EXCAVATED TO A DEPTH REQUIRED BY
THE ENGINEER AND REPLACE WITH A FOUNDATION OF BEDDING
AND BACKFlLL MATERIAL. AS AN ALTERNATIVE AND AT THE
DISCRETION OF THE ENGINEER, THE TRENCH BOTTOM MAY BE
FINAL BACKFlLL STABILIZED USING A WOVEN GEOTEXTILE FABRIC.
UNDISTURBED 3. BEDDING: UNLESS OTHERWISE SPECIFIED BY THE ENGINEER,
EARTH MINIMUM BEDDING THICKNESS SHALL BE 6-INCHES.
4. HAUNCHING AND INITIAI_ BACKFlLL: FOR PIPE DIAMETER
36-INCH AND LARGER, EMBEDMENT MATERIALS SHOULD BE
WORKED UNDER THE HAUNCHES BY HAND. INITIAL BACKFlLL
HDPE PIPE Q SHALL EXTEND 12-INCHES ABOVE THE TOP OF THE PIPE.
o , INITIAL BACKFILL, S. MINIMUM TRENCH WIDTHS
6' ABOVE TOP OF PIPE NOMINAL PIPE SIZE TRENCH WIDTH TRENCH WIDTH EACH
DISTANCE j OUTSIDE OF PAVEMENT, (INCHES) (INCHES) SIDE OF PIPE(INCHES)
TO SIDEWALL 12' ABOVE TOP OF PIPE 15 34 8
UNDER PAVEMENT, 18 39 9
24 48 10
HAUNCHING, TO 30 66 15
SPRINGLINE OF PIPE 36 78 18
BEDDING MATERIAL 42 83 18
48 89 18
54 96 18
FOUNDATION 60 102 18
6. MINIMUM COVER: MINIMUM RECOMMENDED DEPTHS OF
MIN, TRENCH WIDTH COVER FOR VARIOUS LIVE LOADING CONDITIONS ARE
SUMMARIZED IN THE FOLLOWING TABLE UNLESS OTHERWISE
NOTED, ALL DIMENSIONS ARE TAKEN FROM THE TOP OF THE
PIPE TO GROUND SURFACE
SURFACE LIVE LOAD CONDITION MINIMUM RECOMMENDED COVER (INCHES)
TYPICAL TRENCH CROSS-SECTION H25 (FLEXIBLE PAVEMENT) 12, 24* FOR 54 & 60 INCH DIAMETER PIP
N.T.S.) H25 (RIGID PAVEMENT) 12, 24 FOR 54 & 80 INCH DIAMETER PIPE
ESO RAILWAY 24
HEAVY CONSTRUCTION 48
*TOP OF PIPE TO BOTTOM OF BITUMINOUS PAVEMENT SECTION
7. CORRUGATED HDPE PIPE WITH SMOOTH INNER WALL SHALL
MEET THE REQUIREMENTS OF AASHTO M294, TYPE S AND ASTM
F2306.
C,'•Documents and Settings'-Joe Babconec`Desktop`_W Instoll 10-05,dwg
► - '__ a !RrTi
TYPE "C" BACKFILL
�— . s'•:rSfi w�.-..:s`•, _ SEE .SPEC. Ei--2.4
MINIMUM 6" INITIAL- G.C.D_
BACKFILL COVERT SAND MATERIAL EMBEDMENT
INITIAL BACKFILL
SEE SPEC. EI—2.3 G.C.D.
MINIMUM 60
------
EMBEDMENT ��� ►I i.1��F E II
�..•_._ __..... WA R.: 5I -S. 1R._�-Q_.. ND_-INCLU ..L
DING- 2.r .
J�pa �I I I II
'TYPE "C" BACKFILL
i J SEE SPEC. E1--2.4
MINIMUM 6" INITIAL
BACKFILL COVER: CRUSHED STONE OR SAND
WATER — 6
SEWER — 12" I— I '" "� ' I� 5EE SPEC` E1 2.4(b) OR
STORM DRAIN — 12" t I— Ii El—2 3 G.C.D.
CRUSHED STONE.
f INIMUM 8'--- I — -TILL SEE SPEC. E1-2.3
EMBEDMENT G,C.D.
WATER: SIZES 16" AND LARGER
SEWER- ALL SIZES
STORM Qj 6ft ALL SIZES
SANb GRADATION
THAN 109b PASSING ►�ATEBIAL �.CIFICATIQNS
LESS E200 SIEVE THE EMBEDMENT AND BACKFILL DETAILS PROVIDED ON THIS .
SHEET SHALL REPLACE APPROPRIATE PROVISIONS OF BOTH THE:
•P.I. = 10 OR LESS E1-2.4(b) AND E1—Z3 OF THE G.C.D. AND STD. SPEC. ITEM 402
OF THE, TPW STANDARD SPECIFICATIONS FOR STREET & STORM
DRAIN CONSTRUCTION. ALL OTHER PROVISIONS-OF THESE ITEMS
SHALL APPLY.
CRUSHED STONE SR DA AT4QN
SIEVE SIZE RETAINED
1" 0-10
40-75
55-90'
#4 90-100
8 95—•100
FoRTWORTH
CITY OF FORT WORTH,TEXAS DATE: 08-2007
WATER, SEWER, & STORM DRAIN
EMBEDMENT AND BACKFILL DETAILS WTR-034
COLLAR CONFIGURATION— COLLAR CONFIGURATION
FOR PAVED AREA FOR UNPAVED AREA
4'-0'
Y: •t. . i�a't ��0•:••a r
ri CLASS 'A' s� ,• t � I ^ J •� ,�� . :• �
3000 PSI ,��� \ '�' •'+��
C )CONCRETE
8-#4 REBARS TYP. -;• '•�::::� �• :.;";; '.;,f;; ;;': `'•�''-
GRADE RINGS %7 CHAMFER (TYP.)
•; „. r :y.< GROUND
r.a'2: 7;•2 .- SUB'a. • <:?
• ;?�rAs ,•. ;, ..: .
CASE 1 CASE 2 +',:{ •;��.� CONCRETE COLLAR
HEIGHT VARIES
6•'v E `t (8" MIN.. 24" MAX.)
RAM-NEK ? '
s CASE 1 -
•1w.X•
COLLAR SHALL EXTEND TO
TOP OF 2:27 CONCRETE ,.;.•
(REBAR REQUIRED)
CASE 2
COLLAR SHALL EXTEND 3"
W BELOW BOTTOM OF LOWEST O REBAR SHALL BE
GRADE RING PLACED 3" MIN. FROM
(REBAR REQUIRED) SE-Q110N A-A TOP AND BOTTOM OF
CONCRETE COLLAR.
.� E1-20, E1-21 MATERIAL
E2-20, E2-21 CONSTRUCTION
(JRTWQ CITY OF FORT WORTH,TEXAS DATE: 08-2007
MANHOLE CONCRETE COLLAR SAN-009
TRENCH REPAIR LIMITS
EXISTING EXISTING
HMAC PAVEMENT HMAC PAVEMENT
SAW CUF SAW cvr
f i NEW HMAC
. . �:
8" MIN
2:27 CONCRETE'• `f
' �. ; s: 4.r• EXISTING BASE
Zks (IF ANY) EXISTING CURB
EXISTING CURB 12, , k„ 12
& GUTTER. �/� �� `:C•�- /I`i
DITCH WALL
/ BACKFILL MATERIAL
�`/ �• a� /\�/' (SEE NOTE #3)
\ ��-
1 PIPE
ol
TRENCH REPAIR W/PERMANENT HMAC PAVEMENT AND NON-REINFORCED CONCRETE BASE
TYPICAL SECTION
NOTES:
1. PLACE A MIN. OF 2" HMAC SURFACE COURSE (TYPE "0" MIX) TO MATCH EXISTING HMAC PAVEMENT GRADE AS SHOWN.
2, PLACE A MIN. OF 8" 2:27 CONCRETE AS SHOWN.
3.FLOWABLE FILL MAY BE REQUIRED TO BACKFILL ALL TRENCHES IN DOWNTOWN STREETS AND IS
OPTIONAL IN OTHER AREAS. IF FLOWABLE FILL IS REQUIRED, A SEPERATE PAY ITEM WILL BE PROVIDED 4. ALL CONSTRUCTION MUST BE IN ACCORDANCE
FOR SUCH. FOR STORM DRAIN INSTALLATION, BACKFILL SHALL MEET SPECIFIED ITEM 402 OF THE WITH THE CITY OF FORT WORTH STANDARD
STANDARD SPECIFICATIONS FOR STREET AND STORM DRAIN CONSTRUCTION, CITY OF FORT WORTH. SPECIFICATIONS FOR STREET AND STORM
FOR WATER OR SANITARY SEWER INSTALLATION,BACKFILL SHALL BE PER FIGURE A. DRAIN CONSTRUCTION.
REV. 05/2006
oRTYVORz CITY OF FORT WORTH, TEXAS DATA; .•09/2005
PERMANENT ASPHALT PAVEMENT REPAIR
MTH NON-REINFORCED CONCRETE BASE 2000-1 A
T:B W:GENE[tAL CONS"ILV i'1QN`N=S
1. Contractor is responsible for.maintaining.water and sewer connections�n:working ordier at all,times.In no case.stroll
services be allowed to remain out of service ovemight,
2. Contractor shall become familiar with the terms and conditions set:fourtti in.tempaora y construcubn'easements.
Ingress'and egress is allowed on private property in order to.access:temporary.construction easements.:In:the areas::
where no construction easements are available,contractor shall limit'activities to vv. .ft ft.existing utAity Basemen
3. brltractor,shap verily the elevatlon,configuration and location of existing-lines p r,to*construction:Such verification
shall..be conskered subsddlary to the cost.of't.e.project'and.not additional ctirmpensatian wilt be allowed.
4;_ The-contractor shall remove from the project area all surplus material.This shall beincidental.and not a separate.pay
item:Surplus materials-from excavation including dirt,i adhcrete;trash;etc.,strati be property disposed of°att she
approved by the city inspector.
5. The contractor shall preserve and protect or remove and replace(with.prior approval of affected property owner)any
trees,'stikubs,.hedges;landscaping:etc., In or near proposed constructior area.:This work shall be considered
incidental and not a separate pay item;
.6:. All-gr'ass areas'damaged by construction shall receive 4"of_topsoil a W solid soddiing..Contractor shall remove and
Teplace existing topsoil whenever possible.
7, The.contractor shatremove all fences interfering.with construction..operation::witiim::roe,andfor easements removed
fences shall be replaced with new fence or undamaged original fencing with pricrbpproval of property owner
8. The contractor shall make-necessary provision for.the support ion of all.:utiliityp'1es,gas;mains,telephone
cables,sanitary sewer lines,electric cabdes,,drainage pipes;.ublityservices,;and aii.:ather.utilities and the structures:
tth above and below ground during constniction.The corifractor:is liable for all damages done to.such existing
facilities as a result of the contractor's operations:
9.. Contractor shall submit written request to.the engineer for approval of all areasto be used..for staging,mobiliiation;
eq:uiprnent,and material storage acid general'project construction management._Request shall be submitted to the
engineer vAhin five(5)days of n6666 ta.proceed::
10., Contractor shall be.responsibte for maintaining genera[safety.at and.:adjacent.of the..projeet ar,4:including:the :.
personal safety of the construction crew and genemal public and the.safety of�pubtic and private propehy:
11. AN barricades,warning:signs, tight.devices;ek :turthe gultlarice.and pro
tectton;of:traff1c arid;pedesblians must
conform to the installation shown on the 1980 Texas Manualof UnJfbrrn T ControI Dei+.ioes,:as currently
amended.by the Texas State Department of Highways and public Transportations
12. The con' cl or is responsible for keeping streets and sidewalks_adjacent to the project free,of mud and debris from
the construction
13. Two-way trafrrc°Must be maintained,at all times.One lane of traffic around constnrction operations in progress with
adequate safeguards wilt tie acceptable', unless otherwise directed by the engineer.
14. Cor ractom shall have utdli Companies locate and mark all underground facilities before beginning•excavatlon.
.. 15. Tire:contractor shall clean'up and restore the area of operations to a condition as good as or better than that which
=existed prior to the.praject.
16. The contractor is responsible for maintaining the existing storm dram system until the proposed-system is in service
iri po case should ithe contractor leave the existing storm sewer out of service where runoff would cause damage to
adjacent homeowners.
17. Vertical deflections and pipe Mqp6s.1or existing utilities.shown on plans Were obtained from record drawings'and
have not been field verified..Som6 pipe.slopes were adjusted to.match surveyed manhole flow-lines.Rim elevations
:lons
and horizd6tal locations Ofekisti.ng manho,,s were determined.from field
d survey's:
No"uiprh6nt or material.shall bedepopliedon private property without written permissionfrorn the prope.rtyowners.
If the contractor places'Ox :09terial'in the area without written. permission,he will be responsible for all damages
resulting from such f1h and he ihill remove tine materialat..his own cost,if the'engineer so di(ects,
19. The'lo.cation of driv steps,and retairilngWall,etc:,and aD water,sanftRry*sewer,storm sewer.telleph9n
..qf gas.
6t:
ion utiftes shown on these prate locations shah be.verified electric,and cable.televis ese plans.are approximate.Acc.
the time of construction after consultationw th rt h . ....
i prope...y,oWnus acid respective q.. COM'Pantes,
20..The contractor shall co'n:s.trpct a*lt*'draina..g".psys..W...i..systems from.V...o'M' **he*. doWnstr'ean end to allo.wd6rtinued storm.drain service;de,
if.the contractor choosesto construct the system otherwise, Propos construction
pre-6onstructl6n meeting
21'..The contractor's personnel.shall wear idL-.ntJfytn:g..:dq'thin9 or hats at all times.
22. Cdnstiuctlon activities shall tie'limited to the hours of 8:00 O,fn..to 6:00 p.m.unless 6potoved or directed by the
engineer.
23.-Th6adjijstment:eindlorrelocaUop.9f,'sprinkler head*eiico tdted�hii[lbepaid'fb*r under miscellaneous ublity
. ....... .... . ......
iidjustment Y'
ofthisl:i�MMU6
pa"ifirn in the proposal toe.section and contract documents..
EASEMENTS
2004 CIP LOST CREEK AND POWDERHORN DRAINAGE IMPROVEMENTS
DOE#4744
PARCEL#
3809 BEN CREEK CT
LOT-7,BLOCK 8,LOST CREEK ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
Ihat the undersigned, hereinafter referred to as "Grantor", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block I Lot 2, Lost Creek Addition,
as shown on the deed recorded in Instrument No. D206058682, Tarrant County Deed
Records, a/k/a 3809 Ben Creek Ct, Fort Worth, Tarrant County, Texas, hereinafter
referred to as the "Property", for the purpose of constructing drainage improvements.
Upon execution of this agreement, Grantor will grant Grantee and its contractor's access
to the Property for the purpose stated herein, until such time as the project is completed
and approved by the Grantee,at which time the above described temporary right of entry
�. becomes void
Ihis Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above_
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right oflntry.
EXECUTED this the day of es.. 200 .
GRANTOR: Horace L.and Billie Flowers
Horace L.Flowers
Billie Flowers
MWORARY WHI OF ENTRY
Rav 6/2Q07
we
H
2004 CIP LOST CREEK DRAINAGE IMPROVEMENTS
PARCEL #10
DOE# 4744
11913 BLUE CREEK DRIVE
LOT 37,BLOCK 3,LOST CREEK ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL,BY THESE PRESENTS
COUNTY OF TARRANT , §
That the undersigned, hereinafter referred to as "Grantor"" does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 3,Lot 37,Lost Creek Addition,
11913 Blue Creek Dr.,Fort Worth, Tarrant County, Texas,hereinafter referred to as the
"Property",for the purpose of installation of storm drain improvements. Upon execution
of this agreement, Grantor will grant Grantee and its contractor's access to the Property
for the purpose stated herein,until such time as the project is completed and approved by
the Grantee, at which time the above described temporary right of entry becomes void_
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of'Entxy
EXECUTED this the day of 2005,
GRANTOR:
(Please Print) ( ignature)
2004 CIP LOST CREEK DRAINAGE E%UROVEMENTS
PARCEL #11
DOE# 4744
3809 BEN CREEK CT.
LOT 7,BLOCK 8,LOST CREEK ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS
COUNTY OlF TARRANT §
That the undersigned, hereinafter referred to as "Grantor", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 8,Lot 7, Lost Creek Addition,
3809 Ben Creek Ct., Fort Worth, Tarrant County, Texas, hereinafter referred to as the
"Property",for the purpose of installation of'storm drain improvements. Upon execution
- of this agreement, Grantor will grant Grantee and its contractor's access to the Property
for the purpose stated herein,until such time as the project is completed and approved by
the Grantee,at which time the above described temporary right of entry becomes void.
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or contractors to access the aforementioned property,
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular; the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of Entry.
EXECUTED this the—.--day of Ve V'2005.
i
GRANTOR:
w �,
4 lease Print) tore
AN
2004 CIP LOST CREEK DRAINAGE IlVIPROVEMENTS
PARCEL #12
DOE# 4744
3805 BEN CREEK CT.
LOT 8,BLOCK 8,LOST CREEK ADDITION
CITY OF FORT WORTH
TEMWORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
That the undersigned, hereinafter referred to as "Grantor", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
— temporary right of entry onto property described as Block 8, Lot 8, Lost Creek Addition,
3805 Ben Creek Ct., Fort Worth, Tarrant County, Texas, hereinafter referred to as the
"Property", for the purpose of installation of storm drain improvements.. Upon execution
of this agreement, Grantor will grant Grantee and its contractor's access to the Property
for the purpose stated herein,until such time as the project is completed and approved by
the Grantee,at which time the above described tempoiary right of entry becomes void.
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of Entry.
EXECUTED this the ' day of AJo(;ynber ,2005.
GRANTOR:
k CRAMW,CA.,1u.A.,?r-vdec RNA
(Please Print) (Signature) JkMA J 61y
Nov. 16. 2005 11:49AM Bruce A Bollinger MD No 4426 P 3
2004 C1P LOST CREEK DRAINAGE WRO'VEMENTS
PARCEL #13
DOE# 47d4
3810 BEN CREEK CT.
LOT 7,BLOCK 7,LOST CREEKADDMON
CITY OF FART WORTH
TEMPQBARY_RIGUT OF ENTRY
STATE OF TEXAS §
§ XNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
That the undersigned,hereinafter referred to as"Grant'oi", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Qmntec" a
temporary right of entry onto property described as Block 7,Lot 7,Lost Creek Addition,
3810 Ben Creek Ct., Fort'Worth, Tarrant Comity. Texas, hereinafter refeeired to as the
"Property'".for the purpose of installation of storm drain improvements. Upon execution
of this fit, Orator-will grant Grantee and its contractor's access to the Property
from the purpose stated herein,until such time as the project is completed and approved by
the Grantee,at which time the above dwenInA temporary right of carry becomes void.
This Right of Entry shall include the tight of Grantee and its employees, agents,
t+ resa�ntadves,or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of cntry► togetimer with all and
singular,the rights and appuMn►owes thereto,anywise belonging unto the said Grant,
is successors and assigns,for the purposes set foxth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of Ert►try.
EXECUTED this the J �%y of 2005.
GRANTOR:
lca�Print) (8 gnatur�e) ���
s
2004 CIP LOST CREEK AND POWDER.HORN DRAINAGE IMPROVEMENTS
PARCEL #15
DOE# 4744
10162 LITTLE VALLEY RD.
LOT 4,BLOCK 40,WESTPOINT ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
That the undersigned, hereinafter referred to as "Grantor", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 40, Lot 4, Westpoint Addition,
10162 Little Valley Rd.,Fort Worth,Tarrant County, Texas,hereinafter referred to as the
"Property",for the purpose of installation of storm drain improvements. Upon execution
of this agreement, Grantor will grant Grantee and its contractor's access to the Property
for the purpose stated herein,until such time as the project is completed and approved by
the Grantee,at which time the above described temporary right of entry becomes void.
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of Entry.
EXECUTED this the—� . day of/�gZ$m b�.(` ,2005.
GRANTOR:
too �A
(Please Print) (Signature)
2004 CIP LOST CREEK AND POWDERHORN DRAINAGE EUPROVEMENTS
PARCEL #16
DOE# 47"
10154 POWDERHORN RD.
LOT 5,BLOCK 40,WESTPOI T ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
— § KNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
That the undersigned, hereinafter referred to as "Grantor", does by these presents giant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 40, Lot 5,Westpoint Addition,
10154 Powderhorn Rd_,Fort Worth, Tarrant County,Texas,hereinafter refereed to as the
"Property'; for the purpose of storm drain installation and driveway construction. Upon
execution of this agreement, Grantor will grant Grantee and its contrutor's access to the
Property for the purpose stated herein, until such time as the project is completed and
approved by the Grantee, at which time the above described temporary right of entry
becomes void.
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or contractors to access the aforementioned property.
rO HAVE AND TO HOLD the above described right of entry, together with all and
singular;the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under-this Right of Entry.
EXECUTED this the_10 day of_AQ4JAbaL,2005.
GRANTOR:
-,R
vZ
h2al
(Please Print) (Signature)
2004 CIP LOSI CREEK AND POWDERHORN DRAINAGE 11"ROVEMENIS
DOE#4744
PARCEL#17
10158 POWDERHORN RD.
LOT-b,BLOCK-40,WESTPOINT ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
Ihat the undersigned, hereinafter referred to as "Grantor", does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 40 Lot 6, We&Voint Addition,
as shown on the deed recorded in Instrument No. D20512697 Tarrant County Deed
Records and plat recorded in Volume 388=123, Page 68 Tarrant County Plat Records
a/k/a 10158 Powder Horn Rd, Fort.Worth, Tarrant County, Texas, hereinafter referred to
as the "Property", for the purpose of installation of storm drain improvements. Upon
execution of this agreement, Grantor will grant Grantee and its contractor's access to the
i` Property for the purpose stated herein, until such time as the project is completed and
approved by the Grantee, at which time the above described temporary right of entry
becomes void-
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or-contractors to access the aforementioned property.
IO HAVE AND TO HOLD the above described right of entry, together with all and
singular, the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above_
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right
yof Entry
EXECUTED this the day of lR., 200_
TOR:Kelly&Charles James
IJ
e a e
(PIease Pr' / ignature)
rEMPOURY RIGHT OF ENTRY
Rev W007
2004 CWLOSI CREEK AND POWDERHORN DRAINAGE IMPROVEMENTS
DOE#4744
PARCEL#IS
10162 POWDERHORN RD.
•- LOT-7,BLOCK 40,WESTPOINT ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
Ihat the undersigned, hereinafter referred to as "Grantor", does by these presents giant
_ and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 40 Lot 7 WesMoint Addition,
as shown on the deed recorded in Instrument No. D207064804 Tarrant County Deed
Records and plat recorded in Volume 8- 223, Page 68. Iarrant County Plat Records
a/k/a_10162 Powder Horn Rd, Fort North,Tarrant County, Texas, hereinafter referred to
as the "Property", for the purpose of installation of storm drain improvements. Upon
execution of this agreement, Grantor will grant Grantee and its contractor's access to the
Property for the purpose stated herein, until such time as the project is completed and
approved by the Grantee, at which time the above described temporary right of entry
becomes void,
This Right of Entry shall include the right of Grantee and its employees, agents,
representatives,or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular,the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns,for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
.. accessing the Property under this Right of Entry,
EXECUTED this the day of Q tip ,200_1.
GRANIOR: Elysium Enterprises,LP,a Texas limited liability company
MKI Anderson Management,Inc.,a Iexas corporation
`Ym „d
Mario Anderson
rEMPORARY RIGHT OF ENTRY
Rev N2007
2004 CIP LOST CREEK DRAINAGE IMPROVEMENTS
PARCEL # 21
DOE# 4744
11912 BLUE CREEK DRIVE
LOTS 31A&32,BLOCK 3,LOST CREEK ADDITION
CITY OF FORT WORTH
TEMPORARY RIGHT OF ENTRY
STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS
COUNTY OF TARRANT §
That the undersigned, hereinafter referred to as "Grantor"; does by these presents grant
and convey to the City of Fort Worth, TX, herein after referred to as "Grantee" a
temporary right of entry onto property described as Block 3,Lots 3IA& 32, Lost Cheek
Addition, 11912 Blue Creek Dr.,Fort Worth, Tarrant County,Texas,hereinafter referred
to as the"ProperW', for the purpose of installation of storm drain improvements. Upon
execution of this agreement, Grantor will grant Grantee and its contractor's access to the
Property for the purpose stated herein, until such time as the project is completed and
approved by the Grantee, at which time the above described temporary right of entry
becomes void.
This Right of Entry shall include the right of Grantee and its employees, agerrts,
representatives,or contractors to access the aforementioned property.
TO HAVE AND TO HOLD the above described right of entry, together with all and
singular,the rights and appurtenances thereto, anywise belonging unto the said Grantee,
is successors and assigns, for the purposes set forth above.
Grantee shall restore the Property to the condition it was in immediately prior to
accessing the Property under this Right of Entry.
EXECUTED this the day of o V )2005.
GRANTOR:
(Please Print) igna e
,_....,_.�.._..3. ..,.�.
COPY ARA#
2004 CIP LOST CREEK DRAINAGE IMPROVEMENTS �{
Parcel#27 �� o
Doe#4744 sv ��
TRACT 6 OF J. BURLESON SURVEY,ABSTRACT 78 �-- ka
STATE OF TEXAS § —+
§ KNOW ALL MEN BY THESE PRESENTS ra
COUNTY OF TARRANT §
CITY OF FORT WORTH
PERMANENT DRAINAGE FACILITY EASEMENT(Pipe)
AND TEMPORARY CONSTRUCTION EASEMENT
DATE:
GRANTOR: SOMERSET-LOST CREEK GOLF, LTD.
GRANTOR'S MAILING ADDRESS (including County):
4101 LOST CREEK BLVD, ALEDO,TARRANT COUNTY,TX 76008
GRANTEE: CITY OF FORT WORTH
GRANTEE'S MAILING ADDRESS (including County):
1000 THORCKMORTON ST.
FORT WORTH,TARRANT COUNTY,TX 76102
CONSIDERATION: Ten Dollars ($10.00) and other good and .valuable consideration, the
receipt and sufficiency of which is hereby acknowledged.
PROPERTY: Being a portion of the J. Burleson Survey, Abstract 78,Tarrant County, Texas,as
recorded in Volume 6587, Page 233, Deed Records, Tarrant County, Texas, and being more
particularly described in the Permanent Drainage Easement (Pipe), in Exhibits`A" and "B", and
the Temporary Construction Easement in Exhibits"C°and"D".
Grantor, for the consideration paid to Grantor and other good and valuable consideration,
hereby grants, sells, and conveys to Grantee, its successors and assigns, an exclusive,
perpetual easement for the construction, operation, maintenance, replacement, upgrade, and
�+ repair of a Permanent Drainage Facility, hereafter referred to as 'Facility". The Facility includes
all incidental underground and aboveground attachments, equipment and appurtenances,
Including, but not limited to manholes, pipelines, Junction boxes, inlets, flumes, headwalls,
wingwalls, slope pavement, gabions, rock rip-rap and other erosion.control measures in, upon,
under and across a portion of the Property and more fully described in Exhibits "A" and "B"
PERMANENT DRAINAGE FACILITY EASEMENT(P")AND TEMPORARY CONSTRUCTION EASEMENT
Rev.712006
r
attached hereto and incorporated herein for all pertinent purposes, together with the right and
privilege at any and all times to enter Properly, or any part thereof, for the purpose of
constructing, operating, maintaining, replacing, upgrading, and repairing said Facility; and a
temporary construction easement, as described in Exhibits "G" and "D', attached hereto and
made a part hereof, to use In connection with the construction of said Facility, said temporary
construction easement to expire upon completion of construction and acceptance by Grantee of
said Facility,
In no event shall Grantor(1) use the Property in any manner which interferes in any material way
or is inconsistent with the rights granted hereunder, or (11) erect or permit to be erected within
the easement property a permanent structure or building, including, but not limited to,
monument sign, pole sign, billboard, brick or masonry fences or walls or other structures that
require a building permit, or any structure not requiring a building permit but which may threaten
the structural integrity or capacity of the storm drain and its appurtenances. However, Grantor
shall be permitted to install and maintain driveways and parking lots across the easement.
Grantee shall be obligated to restore the surface of the Property at Grantee's sole cost and
expense, Including the restoration of any sidewalks, driveways, or similar surface improvements
located upon or adjacent to the Easement which may have been removed, relocated, altered,
damaged, or destroyed as a result of the Grantee's use of the easement granted hereunder
provided, however,that Grantee shall not be obligated to restore or replace irrigation systems or `
other improvements installed in violation of the provisions and intended use of this Easement
TO HAVE AND TO HOLD the above-described permanent easement, together with all and
singular the rights and appurtenances thereto in anyway belonging unto Grantee, and Grantee's
successors and assigns forever, and Grantor does hereby bind itself and its successor and
assigns to warrant and forever defend all and singular the easement unto Grantee, its
successor and assigns, against every person whomsoever lawfully claiming or to claim the
same, or any part thereof..
= TO HAVE AND TO HOLD the above described temporary construction easement,together with,
all and singular, the rights and appurtenances thereto In anyway belonging unto Grantee, and
Grantee's successors and assigns until the completion of construction and acceptance by
Grantee. Grantor hereby bind themselves, their heirs, successors, and assigns, to warrant and
defend, all and singular, said easement unto Grantee, its successors and assigns, against every
person whomsoever lawfully claiming or to claim the same, or any part thereof.
When the context requires, singular nouns and pronouns include the plural,
See Addendum attached hereto and incorporated herein by reference, in the event of a eonfTct
between the Addendum and this easement, the provisions of the Addendum shall control.
[SIGNATURES APPEAR ON THE FOLLOWING PAGE]
PERMANENT DRAINAGE FACILITY EASEMENT(Pipe)AND TEMPORARY CONSTRUCTION EASEMENT
Rev 712006
GRANTOR: Somerset-Lost Creek Golf, Ltd. GRANTEE: Cifiy Fort Worth
a Texas limited partnership
By: Somerset-Lost Creek Management, L.L.C.
a Texas limited liability company
,.- - Marc A ,Assistant City Manager
APPROVED AS TO FORM AND LEGALITY
t
on Bouterie,Vice President'
Assistant City Attorney
M& C: DATE AV'Z 'y 20 7
AGENT DOE '
PERMANENT DRAINAGE FACILITY EASEMENT(Pipe)ANDTEMPORARY CONSTRUCTION EASEMENT
Rev 712M
ACKNOWLEDGEMENT
STATE OF TEXAS §
COUNTY OF TARRANT §
BEFORE ME, the undersigned authority, a Notary Public in and for the State of Texas,
on this day personally appeared ;e , known to me to be the
same person whose name is subscribed to the foregoing instrument, and acknowledged to me
that the same was the act of and that he/she executed
the same as the act of said for the purposes
and consideration therein expressed and in the capacity therein stated_
GIVEN UNDER MY HAND AND SEAL OF OFFICE this 29.PX day of
20g.
emy
wIWE F.INGRAMNotary PublicSTATE OF TEXAS Notary Public in and for th COMM.gxp.04105=10
ACKNOWLEDGEMENT
STATE OF TEXAS §
COUNTY OF TARRANT §
BEFORE ME, the undersigned authority, a Notary Public in and for the State of
Texas, on this day personally appeared Marc A. Ott, Assistant City Manager of the City of Fort
Worth, known to me to be the same person whose name is subscribed to the foregoing
instrument, and acknowledged to me that the same was the act of the City of Fort Worth and
that he/she executed the same as the act of the City of Fort Worth for the purposes and
consideration therein expressed and in the capacity therein stated,
GIVEN UNDER MY HAND AND SEAL OF OFFICE this oe day of
20 O�7
, .<.
£ Ia�e �� ee Notary Public in and forte State of Texas
PERMANENT DRAINAGE FACILITY EASEMENT(Pipe)AND TEMPORARY CONSTRUCTION EASEMENT
Rev.7=06
ADDENDUM
This Addendum to the foregoing City of Fort Worth Permanent Drainage Facility Easement and
Temporary Construction Easement(the"Easement')modifies the Easement as follows:
Notwithstanding any provision in the.Easement to the contrary:
1. Grantee agrees to remit to Grantor the amount of$2,500.00 to replace trees removed to
_ accommodate the new headwall for the drainage outlet
2.. Grantee agrees to reimburse Grantor the amount of$2,000.00 for the construction of a
temporary Tee Box. The temporary Tee Box is necessary so that construction crews
will not be in danger of being struck by flying golf balls.
3. Grantee agrees to reimburse Grantor the amount of$1,244.00 for the installation of two
12 inch pipes beneath Grantors' cart path to accommodate the increased flow of water
as a result of Improvements to Grantees'facility,
GRANTOR: Somerset-Lost Creek Golf, Ltd. GRANTEE: of Fort Worth
a Texas limited partnership
By: Somerset-Lost Creek Management, L.L.C.
a Texas limited liability company 16"-/� -
Marc k Ott,Assistant City Manager
4"on
APPROVED AS TO FORM AND LEGALITY
erie,Vice PresidentAWk
Assistant City Att ey
PERMANENT DRAINAGE FACILITY EASEMENT(Pipe)AND TEMPORARY CONSTRUCTION EASEMENT
Rear Vrnos
PARCEL 27
FEZ IT "All
SITUATED in the City of Fort Worth,in Iarrant County, Texas and being a tract of land on
and across a portion of a tract of land in the J.Burleson Survey Abstract 78,as conveyed to
Somerset-Lost Creek Golf,ltd,(Lost Creek tract)by deed as recorded in Volume 6587,Page
233 of the Deed Records of Tarrant County being more patticularly described by metes and
bounds as follows:
BEGINNING at a point in a northerly line of said Lost Creek tract at the southwest coiner
of Lot 8,Block 8 of Lost Creek Addition an addition to the City of Fort Worth as recorded in
-- Volume 388-115,Page 97 of the Plat Records of Tarrant County, Iexas;
THENCE,S 81020'43"E_,along a northerly lane of'said Lost Creek tract and along the south
line of said Block 8,a distance of 25.0 feet;
THENCE,S.89917"W.,a distance of'36.0 feet;
THENCE,N. 81020'43"W.,a distance of'50.0 feet;
THENCE,N.8039'17"E_,a distance of 36.0 feet to a point in a northerly line of said Lost
Creek tract and the south line of said Block 8;
THENCE,S_81°20'43"E. along a northerly line of said Lost Creek tract and the south line of
said Block 8,a distance of 25.0 feet to the POINT OF BEGINNING and containing
1,800.0 square feet of land-
J.B..Davies,Inc.
Fort Worth, Texas
.January 7,2005 /
YQF
r Q '
L _ � d
BLOCK 8
! LOST CREEK ADDN,
1 VOL. 388--115, PG, 97
! ! a P,R,T.C,T.
LOT 7 !
. ! o
� w
LOT 8
! !
d ! w
o !
POINT OF BEGINNING
FOR DESCRIPTION OF EXHIBIT A
VOL. 17396, PG. 430 D.R.T.C. 25 °,
_ _
OWNER: SOMERSET--LOST CREEK cap`; ;�;;. 25•,Q-, le
0'43"�
GOLF, LTD.
4101 LOST CREEK BLVD.
ALEDO TX. 76008 '.
PARCEL 27 STORM DRAIN
EXHIBIT "A"
' M IMPROVEMENTS
Go
PROPOSED PERMANENT N81'43"`yy'
DRAINAGE EASEMENT '0
1800 SF
J. BURL.ESON SURVEY A--78
DRAWING SHOWING PARCEL 27 5s
EXHIBIT "T DRAWING OF EXHIBIT '°A"
50.0' BY 36.0' STORM DRAIN EASEMENT ACROSS ...0. ?.....�:5.11I .
....q- -.-.. . ....y-....
TRACT 5 OF THE J. BURLESON SURVEY ABSTRACT No. 78
AS DESCRIBED IN VOLUME 17396, PAGE 430.OF THE `. � S�co
DEED RECORDS OF TARRANT COUNTY. TEXAS
0 20 40
.T. B. DAWC , INC. ZMAGM and smvmiw
3018 SE LOOP 820
MRT WO= TEW 76.140 HORIZONTAL SCALE: 1" = 20'
817-335-3154
PARCEL 27
EXHIBIT "C"
TEMPORARY CONSTRUCTION EASEMENT
SITUATED IN THE City of Fort Worth, Tarrant County, Texas and being
a tract of land on the and across a portion of a tract of land in the J.
Burleson Survey Abstract Now 78 , as described in the deed to Somerset-
Lost Creek Golf, Ltd. (Lost Creek Tract) recorded in Volume 17396, Page
430 of the Deed Records of Tarrant County, Texas, being more
particularly described as follows:
BEGINNING at a point in the northerly line of the said Lost Creek tract,
being S8I*20'43"E, 25.Oft from the southwest corner of Lot 8 Block 8,
Lost Creek Addition an addition in the City of Fart Worth, Tarrant
County, Texas, as shown by plat recorded in Volume 388-115, Page 97 of
the Deed Records of Tarrant County, Texas;
THENCE S81°20'43"E, 15.Oft;
THENCE S8 -39'17"W, 60.Ofk.;
THENCE N81°20'43"W, 80.Oft.;
THENCE N8°39'1rE, 60..Oft. to a point in the said northerly line of the
Lost Creek tract;
THENCE S81°20'43"E, 15.Oft to a the northwest corner of the Permanent
Drainage Easement as described in Exhibit A herein;
THENCE S8°39'17"W, 36.Oft.;
THENCE S81°20'43"E, 50.Oft.;
THENCE N8°39'17"E, 36.Oft. to the place of beginning and containing
2998 square feet of land..
J. B. Davies, Inc.
Fort Worth, Texas
October 26, 2007
'•" in.H.
" ,13,DAV I'':$III
,..,.A.. .,.4368 y
�pE.sSt r{
l��AS1l9v��0
1� BLACK 8
r
! r4
LOT 7 r v LOST CREEK ANN,
r ac VOL. 388-115, PG, 97
JPiR*T.C,T&
} ! LOT 8
IL
VOL. 17396. PG. 430 D.R.T C.
+` OWNER: SOMERSET—LOST CREEK kk :
GOLF. LTD. . $12O'43,.
4101 LOST CREEK BLVD. p `"�--E
ALEDO TX. 76008 p co
PROPOSED
DRAINAGE ANENTf o `tea
0 SEMENT t: Q,
4369
QRco
ARY'
•SiiAV�^t r ONttR :• Go
4EN 7
PARCEL 27 81 P
W 80
DRAWING SHOWING PARCEL 27 ��
EXHIBIT "D" DRAWING OF EXHIBIT "C„
TEMPORARY CONSTRUCTION EASEMENT FOR TRACT 5
OF J. BURLESON SURVEY ABSTRACT No. 713
AS DESCRIBED IN VOLUME 17396• WAGE 430 OF THE
DEED RECORDS OF TARRANT COUNTY_ TEXAS
J• 0 20 40
.T B. DA M.
8016 SE LOOP 820
.� I' BT WO= 7=8 76140 HORIZONTAL SCALE: 1" — 20'
BIT-9s6-3t1s4
Fyst 1►Pwr
a44tr F'�s{jl�.l��ior
4 r
■PA iF
P i
CITY OF FT WORTH
900 MONROE ST N.
#302
FT WORTH TX 76102
Submi4ter. CITY OF FORT WORTH/REAL PROPERTY-001 ZCFVI
SUZANNE HENDERSON
TARRANT COUNTY CLERK
TARRANT COUNTY COURTHOUSE
100 WEST WEATHERFORD
FORT WORTH,TX 76196-0401
DO NOT DESTROY
WARNING - THIS IS PART OF THE OFFICIAL RECORD,
Filed For Registration: 11129/200711:35 AM
Instrument#: D207423697
E 10 PGS $48.00
By:
III11111111111111111111111111111IIIII1111111111111111111IN
D207423697
ANY PROVISION WHICH RESTRICTS THE SALE, RENTAL OR USE
OF THE DESCRIBED REAL PROPERTY BECAUSE OF COLOR OR
RACE IS INVALID AND UNENFORCEABLE UNDER FEDERAL LAW.
Printed by: ap
�.
ACORD,. CERTIFICATE OF LIABILITY INSURANCE DA12/18/08Y)
PRODUCER
Aon Risk Services southwest, inc. THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY
Dallas TX Office AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER.THIS
ci tyPl ace center East CERTIFICATE DOES NOT AMEND,EXTEND OR ALTER THE
2711 North Haskell Avenue COVERAGE AFFORDED BY THE POLICIES BELOW.
suite 800
Dallas TX 75204 USA INSURERS AFFORDING COVERAGE
PHONE•(214) 989-0000 FAX-(214) 989-2530
INSURED INSURER A: Hartford ins co of the Midwest
Burnsco Construction, inc. INSURERB: Illinois National insurance co
6331 southwest Blvd.
Benbrook TX 76132 USA INSURERC: Hartford casualty insurance co L
a:
INSURERD: Hartford underwriters ins. Co. `•"
a
r a
INSURER E: 'L
r
COVERAGES This Certificate is not intended.to specify all endorsements,coverages,terms,conditions and exclusions of the policies shown. SIR May App y c
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED,NOTWITHSTANDING L
ANY REQUIREMENT,TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY
PERTAIN,THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,EXCLUSIONS AND CONDITIONS OF SUCH POLICIES
AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS LIMITS SHOWN ARE AS REQUESTED
INSR POLICY EFFECTIVE POLICY EXPIRATION
LTR TYPE OF INSURANCE POLICY NUMBER LIMITS N
DATE(MM\DMYY) DATE(MM\DMYY) pc
N
D GENERAL LIABILITY 46 C QT1165 06/20/08 06/20/09 EACH OCCURRENCE $1,000,000Lr
COMMERCIAL GENERAL LIABILITY O
X COMMERCIAL GENERAL LIABILITY FIRE DAMAGE(Any one fire) $300,OOO m
CLAIMS MADE X❑OCCUR MED EXP(Any one person) $10,000 O
n
X Per Project Aggregate PERSONAL&ADV INJURY $1,000,000
X Contractual Liabilitv GENERAL AGGREGATE $2,000,000
GEN'L AGGREGATE LIMIT APPLIES PER
PRO- PRODUCTS-COMP/OP AGG $2,OOO,OOO
a POLICY E JECT LOC 'Z
a
a
A 46 UEN QT1166 06/20/08 06/20/09 a
AUTOMOBILE LIABILITY COMBINED SINGLE LIMIT
X ANY AUTO BUSINESS AUTOMOBILE (Ea accident) $1,000,000
� a
ALL OWNED AUTOS BODILY INJURY
SCHEDULED AUTOS (Per person)
X HIRED AUTOS BODILY INJURY
M10 NON OWNED AUTOS (Per accident)
PROPERTY DAMAGE
(Per accident)
No GARAGE LIABILITY AUTO ONLY-EA ACCIDENT
ANY AUTO OTHER THAN EA ACC
AUTO ONLY
AGG
B EXCESS LIABILITY BE 7227337 06/20/08 06 20 09 EACH OCCURRENCE $15,000,000
UMBRELLA LIABILITY
OCCUR ❑ CLAIMS MADE AGGREGATE $15,000,000
DEDUCTIBLE
X RETENTION $10,000
C WORKERS COMPENSATION AND 46 WE QT1164 06/20/08 06/20/09 X WC STATU-I OTH-
EMPLOYERS'LIABILITY WORKERS' COMPENSATION TO Y LIMITS ER
E.L.EACH ACCIDENT $1,000,000 0
E.L.DISEASE-POLICY LIMIT $1,000,000
E.L.DISEASE-EA EMPLOYEE $1,000,000
C.
OTHER
DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES/EXCLUSIONS ADDED BY ENDORSEMENT/SPECIAL PROVISIONS
Re: Lost Creek Phase 2 Drainage improvements for Ben Creek Court, Blue Creek Court, and Powderhorn Road; DOE W_
Project NO: 4744, TPw Project No. c200 541200 2032800087 83, City Of Fort worth, Texas.
The City, its officers, employees, and servants shall be named as an additional insured, on a primary and non
CERTIFICATE HOLDER CANCELLATION
X�
.. City Of Fort worth SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION '�rl
1000 Throckmorton street DATE THEREOF,THE ISSUING COMPANY WILL ENDEAVOR TO MAIL fir.
Fort worth TX 76102 USA 30 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, C!
BUT FAILURE TO DO SO SHALL IMPOSE NO OBLIGATION OR LIABILITY
OF ANY KIND UPON THE COMPANY,ITS AGENTS OR REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE ���JJ �Q �p -o
c�4'ossc7�cLfr�cw��sw
ACORD 25-5 7/97 ACORD CORPORATION 1 888 -
Attachment to ACORD Certificate for Burnsco construction, inc.
The terms,conditions and provisions noted below are hereby attached to the captioned certificate as additional description of the coverage
afforded by the insurer(s).This attachment does not contain all terms,conditions,coverages or exclusions contained in the policy.
INSURER
INSURED
Burnsco construction, Inc. INSURER
6331 southwest Blvd.
Benbrook TX 76132 USA INSURER
INSURER
INSURER
ADDITIONAL POLICIES If a policy below does not include limit information,refer to the corresponding policy on the ACORD
certificate form for policy limits
POLICY POLICY
INSR TYPE OF INSURANCE POLICY NUMBER EFFECTIVE EXPIRATION LIMITS
LTR POLICY DESCRIPTION DATE DATE
r
DESCRIPTION OF OPERATIONS/LOCATIONS/VEHICLES/EXCLUSIONS ADDED BY ENDORSEMENT/SPECIAL PROVISIONS
contributory basis, for all coverages except workers` compensation J waiver of subrogation in favor of
do the additional insured with regard to all certified coverages.
W
ar
Certificate No: 570032054282
■
CONTRACTOR COMPLIANCE WITH
WORKERS' COMPENSATION LAW
Pursuant to V.T.C.A. Labor Code §406.96 (2000), as amended, Contractor certifies that it
provides workers' compensation insurance coverage for all of its employees employed on City
of Fort Worth Department of Engineering No.4744 and City of Fort Worth Project No. C200-
203280008783.
CO A OR
_ Bufnsco C nstruction Inc.
Name: ,ol.tiw, '1JL*kp .
Title: Ik a 51 c-ey'. '
Date: �2�tz p S
STATE OF TEXAS §
COUNTY OF TARRANT §
Before me, the undersigned authority, on this day personally appeared
Y fie ►:;,�3 known to me to be the person whose name is subscribed to the
foregoing instrument, and acknowledged to me that he executed the same as the act and deed
of Bumsco Construction, Inc.for the purposes and consideration therein expressed and in the
capacity therein stated. C�
Given Under My Hand and Seal of Office thisday 20 �0
Notary Pub in and for the State of Texas
r MAW F RM"LL
My CoMMIM ►EXPk*6
SepA�+r►b91 28,2010
EQUIPMENT SCHEDULE
List of Equipment owned by Bidder that is in serviceable condition
and available for use:
Portions of work Bidder proposes to sublet in case of Award of
Contracts including amount and type:
EXPERIENCE RECORD
List of projects your organization has successful) completed:
Amount Of Contract Type of Work Date Accepted Name and Address of Owner
Award
List of projects your organization is now engaged in completing:
Amount Of Contract Type of Anticipated Name and Address of Owner
Award Work Date of
Completion
List Surety Bonds in force on above incomplete work:
Date of Contract Award Type of Work Amount of Name and Address of
Bond Bond Surety
Bond No. 6581471
- PERFORMANCE BOND
THE STATE OF TEXAS §
KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
Safeco Insurance Company
That we (1) Buroxo Construction. Inc. as Principal herein, and (2) of America a
corporation organized under the laws of the State of(3)Washington , and who is authorized to issue surety
bonds in the State of Texas, Surety herein, are held and firmly bound unto the City of Fort Worth, a municipal
corporation located in Tarrant and Denton Counties,Texas,Obligee herein,in the sum of.
Two Hundred Sixty-five Thousand Four Hundred Sixty-nine and oo/100»»»,»....,»...».»»».
($265,469,00)Dollars for the payment of which sum we bind ourselves,our heirs,executors,administrators,
successors and assigns,jointly and severally,firmly by these presents.
WHEREAS, Principal has entered into a certain contract with the Obligee dated the 9th of December,
2008 a copy of which is attached hereto and made a part hereof,for the constriction of:
Laat Crcek Phase 2 Drainf M 1wyMyp enty
NOW THEREFORE, the condition of this obligation is such, if the said Principle shall faithfully perform
the work in accordance with the plans, specifications, and contract documents and shall fully indemnify and hold
harmless the Obligee from all costs and damages which Obligee may suffer by reason of Principal's default, and
reimburse and repay Obligee for all outlay and expense that Obligee may incur in making good such default, then
this obligation shall be void;otherwise, to remain in full force and effect.
PROVIDED, HOWEVER, that this bond is executed pursuant to Chapter 2253 of the Texas Government
Code, as amended, and all liabilities on this bond shall be determined in accordance with the provisions of such
statute,to the same extent as if it were copied at length herein.
IN WITNESS WHEREOF, the duly authorized representatives of the Principal and the Surety have
executed this instrument.
SIGNED and SE D this 9*of December,2008.
ATTEST:
t — Burn o Const coon Inc.
(Principal) cre ry PR' CIPAL
ff Morton. BY:
Secretary Title: Joh Burns, President
(SEAL) 6331 Southwest Blvd.
Benbrook.TX 76132
(Address)
Safeco Insurancg Company of America
Wi as t
6331 Southwest Blvd., Benbrook, TX 76132
Address BY:
no -in-fact)( )
Lisa M. Bont 5
(Suzy)Secretary Safeco Plaza
Seattle, WA 98185 _
(Address)
(SEAL) NOTE: Date of Bond must not be
prior to date of Contract
(1) Correct Name of Contractor
(2) Correct name of Surety
(3) State of incorporation of Surety
Telephone number of surety must be stated.
In addition,an original copy of Power of
Attorney shall be attached to Bond by
Attorney-in-Fact.
The date of bond shall not be prior to date of
Contract.
Witness as to urety
2711 N. Haskell Avenue#800, Dallas, TX 75204
(Address)
Bond No. 6581471
PAYMENT BOND
THE STATE OF TEXAS §
§ KNOW ALL BY THESE PRESENTS:
COUNTY OF TARRANT §
Safeco Insurance Company
That we,(1)Burnsco Construction,Inc.,as Principal herein,and(2) of America
a corporation organized and existing under the laws of the State of(3) Washington as simty, are
-, held and firmly bound unto the City of Fort Worth,a municipal corporation located in Tarrant and Denton Counties,
Texas, Obligee herein, in the amount of Two Hundred Sixty-five Thousand Four Hundred Sixty-nine and
no/100-.-»...----..--..» Dollars ($265,469,00) for the payment whereof, the said Principal and Surety bind
themselves and their heirs,executors, administrators,successors and assigns,jointly and severally, firmly by these
presents:
WHEREAS,the Principal has entered into a certain written contract with the Obligee dated the 9th day of
December, 2008,which contract is hereby referred to and made a part hereof as if fully and to the same extent as if
copied at length,for the following project:
Lost Creek Phase 2 Drainaee Improvements
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal
shall faithfidly make payment to each and every claimant(as defined in Chapter 2253,Texas Government Code, as
amended)supplying labor or materials in the prosecution of the work under the contract,then this obligation shall be
void;otherwise,to remain in full force and effect.
PROVIDED, HOWEVER, that this bond is executed pursuant to Chapter 2253 of the Texas Government
Code, as amended, and all liabilities on this bond shall be determined in accordance with the provisions of said
statute,to the same extent as if it were copied at length herein.
IN WITNESS WHEREOF, the duty authorized representatives of the Principal and the Surety have
executed this instrument.
SIGNED and SEALED this 9th day of,December2008.
Bu o struction. Inc.,
PRI CIPAL
ATTEST: By:.
` Name: Jo n Burns
(Princ:ipaq -
�'' Jeff Morton Title: President
Je
(S E L) SecretaryAddress: 6331 Southwest Blvd.
Benbrook.TX 76132
Witness asio Prin&Qpi
Safeco Insurance Company of America
SUR TY
ATTEST: By:
Name: Lisa M. Bonnot
Secretary Attomey in Fact
(S E A L) Address: Safeco Plaza
Seattle, WA 9818B
� l
V iiriess as to &irely Telephone Number: 206/473-3799
NOTE: (1) Correct name of Principal (Contractor).
(2) Correct name of Surety.
(3) State of incorporation of Surety
Telephone number of surety must be stated. In addition, an original copy of
Power of Attomey shall be attached to Bond by the Attomey-in-Fact.
The date of bond shall not be prior to date of Contract.
Bond No. 6581471
MAINTENANCE BOND
THE STATE OF TEXAS §
COUNTY OF TARRANT §
Safeco Insurance Company
That Burnsco Construction, Inc. ("Contractor"), as principal, and of America
a corporation organized under the laws of the State of Washington , ("Surety"), do hereby
acknowledge themselves to be held and bound to pay unto the City of Fort Worth, a Municipal
Corporation chartered by virtue of Constitution and laws of the State of Texas, ("City") in Tarrant
County, Texas, the sum of Two Hundred Sixty-five Thousand Four Hundred Sixty-nine and
no/100.................................................................................................................................... Dollars
($265,469.00), lawful money of the United States, for payment of which sum well and truly be made
unto said City and its successors, said Contractor and Surety do hereby bind themselves, their heirs,
executors, administrators, assigns and successors,jointly and severally.
This obligation is conditioned, however, that:
WHEREAS, said Contractor has this day entered into a written Contract with the City of Fort
Worth, dated the 9th of December, 2008, a copy of which is hereto attached and made a part hereof,
for the performance of the following described public improvements:
Lost Creek Phase 2 Drainane Improvements
the same being referred to herein and in said contract as the Work and being designated as project
number(s) C200-203280008783 and said contract, including all of the specifications, conditions,
addenda, change orders and written instruments referred to therein as Contract Documents being
incorporated herein and being made a part hereof; and,
WHEREAS, in said Contract, Contractor binds itself to use such materials and to so construct
the work that it will remain in good repair and condition for and during a period of after the date of the
final acceptance of the work by the City; and
WHEREAS, said Contractor binds itself to maintain said work in good repair and
condition for said term of Two (2)years; and
WHEREAS, said Contractor binds itself to repair or reconstruct the Work in whole or in
part at any time within said period, if in the opinion of the Director of the City of Fort Worth
Department of Engineering, it be necessary; and,
WHEREAS, said Contractor binds itself, upon receiving notice of the need therefore to
repair or reconstruct said Work as herein provided.
NOW THEREFORE, if said Contractor shall keep and perform its said agreement to
maintain, repair or reconstruct said Work in accordance with all the terms and conditions of said
Contract, these presents shall be null and void, and have no force or effect. Otherwise, this
Bond shall be and remain in full force and effect, and the City shall have and recover from
Contractor and Surety damages in the premises as prescribed by said Contract.
This obligation shall be a continuing one and successive recoveries may be had hereon
for successive breaches until the full amount hereof is exhausted.
IN WITNESS WHEREOF,this instrument is executed in 8 counterparts, each of which
shall be deemed an original, this 9th day of December, A.D.2008.
ATTEST: Bumsco Construction, Inc.
(SEAL) Contractor �
By:
Secret Name: J n Burns
eff Morton
Secretary Title: President
ATTEST: Safeco Insurance Company of America
IS E A L) Surety
,V�- - By:
Secretary t4ame: Lisa M. B not
Title: Attorney-in-fact
Safeco Plaza
Seattle, WA 98185
Address
+
Safeco Insurance Company of America
POWER General Insurance Company of America
Safeco Plaza
OF ATTORNEY Seattle,WA 98185
KNOW ALL BY THESE PRESENTS: No. 3698
That SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF AMERICA, each a
Washington corporation,does each hereby appoint
*******************LISA M.BONNOT;DON E.CORNELL;CHRISTINE DAVIS;ROBBI MORALES;LUKE J.NOLAN,JR.;
+ RICARDO J.REYNA;JERRY P.ROSE;Dallas,Texas****************************"**"******************************
its true and lawful attorney(s)-in-fact,with full authority to execute on its behalf fidelity and surety bonds or undertakings and other
documents of a similar character issued in the course of its business,and to bind the respective company thereby.
IN WITNESS WHEREOF, SAFECO INSURANCE COMPANY OF AMERICA and GENERAL INSURANCE COMPANY OF
AMERICA have each executed and attested these presents
this 13th November 2008
+ day of
Edmund C.Kenealy.Secretary Timothy A.Mikolajewski,Vice President
CERTIFICATE -
Extract from the By-Laws of SAFECO INSURANCE COMPANY OF AMERICA
+ and of GENERAL INSURANCE COMPANY OF AMERICA:
"Article V,Section 13.-FIDELITY AND SURETY BONDS...the President,any Vice President,the Secretary,and any Assistant Vice
President appointed for that purpose by the officer in charge of surety operations,shall each have authority to appoint individuals as
attorneys-in-fact or under other appropriate titles with authority to execute on behalf of the company fidelity and surety bonds and
other documents of similar character issued by the company in the course of its business...On any instrument making or evidencing
such appointment, the signatures may be affixed by facsimile. On any instrument conferring such authority or on any bond or
undertaking of the company, the seal, or a facsimile thereof, may be impressed or affixed or in any other manner reproduced;
provided,however,that the seal shall not be necessary to the validity of any such instrument or undertaking."
+ Extract from a Resolution of the Board of Directors of SAFECO INSURANCE COMPANY OF AMERICA
and of GENERAL INSURANCE COMPANY OF AMERICA adopted July 28,1970.
"On any certificate executed by the Secretary or an assistant secretary of the Company setting out,
(i) The provisions of Article V,Section 13 of the By-Laws,and
+ (ii) A copy of the power-of-attorney appointment,executed pursuant thereto,and
(iii) Certifying that said power-of-attorney appointment is in full force and effect,
the signature of the certifying officer may be by facsimile,and the seal of the Company may be a facsimile thereof."
I,Edmund C.Kenealy Secretary of SAFECO INSURANCE COMPANY OF AMERICA and of GENERAL INSURANCE
+ COMPANY OF AMERICA,do hereby certify that the foregoing extracts of the By-Laws and of a Resolution of the Board of Directors
of these corporations,and of a Power of Attorney issued pursuant thereto,are true and correct,and that both the By-Laws,the Resolution
and the Power of Attorney are still in full force and effect.
IN WITNESS WHEREOF,I have hereunto set my hand and affixed the facsimile seal of said corporation
this 9th day of December 2008
CRORATf
SEAL W SEAL
A
tat'
trF�wAswti�d d(waSti�° Edmund C.Kenealy,Secretary
r Safeco®and the Safeco logo are registered trademarks of Safeco Corporation.
S-0974/DS 10/08 WEB PDF
r
Figure: 28 TAG§1.601(a)(3)
1 IMPORTANT NOTICE AVISO IMPORTANTE
To obtain information or make a complaint: Para obtener informacion o para someter una
queja:
2 You may contact Home Office Surety at Usted puede contactar a servicio de la oficina
(206)473-3799. principal de Safeco Surety al: 206-473-3799.
3 You may call (company)'s toll-free telephone Usted puede Ilamar al numeeo de telefono
number for information or to make a complaint gratis de (company)'s para informacion o para
at: someter una queja al:
(800)472-5357 Surety Option #7 (800)472-5357 Surety Opcion De#7
---4�75[r may also wMe tb-S L5-d`"--- - UsTedTambien puede-escn6ir_a Safeco
Insurance Company at: Insurance Company:
Safeco Plaza Safeco Plaza
Seattle,WA 98185-0001 Seattle,WA 98185-0001
5 You may contact the Texas Department of Puede comunicarse con el Departamento de
Insurance to obtain information on companies, Seguros de Texas para obtener information
coverages, rights or complaints at: acerca de companias, coberturas, derechos o
quejas al:
(800) 252-3439 (800) 252-3439
6 You may write the Texas Department of Puede escribir al Departamento de Seguros de
Insurance: Texas:
P.O. Box 149104 P.O. Box 149104
Austin,TX 78714-9104 Austin, TX 78714-9104
Fax: (512)475-1771 Fax: (512)475-1771
Web: http://www.tdi.state.tx.us Web: http://www,tdi.state.tx.us
E-mail: ConsumerProtection@tdi.state.tx.us E-mail:ConsumerProtection@tdi.state.tx.us
Y 7 PREMIUM OR CLAIM DISPUTES: DISPUTAS SOBRE PRIMAS O RECLAMOS:
Should you have a dispute concerning your Si tiene una disputa concerniente a su prima o
premium or about a claim you should contact the a un reclamo, debe comunicarse con el
(agent) (company) (agent or the company) (agente) (la compania) (agente o la compania)
first. If the dispute is not resolved,you may primero. Si no se resuelve la disputa,puede
contact the Texas Department of Insurance. entonces comunicarse con el departamento
(TDI).
8 ATTACH THIS NOTICE TO YOUR POLICY: UNA ESTE AVISO A SU POLIZA: Este aviso
This notice is for information only and does not es solo para proposito de information y no se
' become a part or condition of the attached convierte en parte o condition del documento
document. adjunto.
4 3
CITY OF FORT WORTH TEXAS
CONTRACT
THE STATE OF TEXAS
KNOW ALL BY THESE PRESENTS
.. COUNTY OF TARRANT
This agreement made and entered into this the 9th day of December A.D.,2008 by and between
the CITY OF FORT WORTH,a municipal corporation of Tarrant County,Texas,organized and existing
— under and by virtue of a special charter adopted by the qualified voters within said City on the 11'h day of
December, A.D. 1924, under the authority(vested in said voters by the "Home Rule" provision) of the
Constitution of Texas, and in accordance with a resolution duly passed at a regular meeting of the City
Council of said city,and the City of Fort Worth being hereinafter termed Owner,Bur nsco Construction,
Inc.,HEREINAFTER CALLED Contractor.
.. WTTNESSETH: That said parties have agreed as follows:
1.
That for and in consideration of the payments and agreements hereinafter mentioned to be made
and performed by the Owner, and under the conditions expressed in the bond bearing even date herewith,
the said Contractor hereby agrees with the said Owner to commence and complete the construction of
certain improvements described as follows:
.. Lost Credo Phase 2 Drainage Improvements
2.
That the work herein contemplated shall consist of furnishing as an independent contractor all
labor, tools, appliances and materials necessary for the construction and completion of said project in
x accordance with the Plans and Specifications and Contract Documents prepared by the Department of
Engineering for the Transportation and Public Works Department of the City of Fort Worth adopted by
the City Council of the City of Fort Worth, which Plans and Specifications and Contract Documents are
.. hereto attached and made a part of this contract the same as if written herein.
3.
The Contractor hereby agrees and binds himself to commence the construction of said work
within ten(10)days after being notified in writing to do so by the Department of Engineering of the City
.. of Fort Worth.
4.
The Contractor hereby agrees to prosecute said work with reasonable diligence after the
commencement thereof and to fully complete and finish the same ready for the inspection and approval of
the Department of Engineering of the City of Fort Worth and the City Council of the City of Fort Worth
within a period of 60 working days.
If the Contractor should fail to complete the work as set forth in the Plans and Specifications and Contract
_ Documents within the time so stipulated, plus any additional time allowed as provided in the General
Conditions, there shall be deducted from any monies due or which may thereafter become due him, the
sum of$210 Per calendar day, not as a penalty but as liquidated damages,the Contractor and his Surety
shall be liable to the Owner for such deficiency.
5.
Should the Contractor fail to begin the work herein provided for within the time herein fixed or to
carry on and complete the same according to the true meaning of the intent and terms of said Plans,
Specifications and Contract Documents, then the Owner shall have the right to either demand the surety
s to take over the work and complete same in accordance with the Contract Documents or to take charge of
and complete the work in such a manner as it may deem proper,and if in the completion thereof,the cost
to the said City shall exceed the contract price or prices set forth in the said plans and specifications made
a part hereof,the Contractor and/or its Surety shall pay said City on demand in writing, setting forth and
specifying an itemized statement of the total cost thereof,said excess cost.
.• 6
Contractor covenants and agrees to indemnify City's Engineer and Architect, and their personnel at the
n project site for Contractor's sole negligence. In addition,Contractor covenants and agrees to indemnify,
hold harmless and defend, at its own expense,the Owner, its officers, servants and employees, from and
against any and all claims or suits for property loss, property damage, personal injury, including death,
arising out of, or alleged to arise out of, the work and services to be performed hereunder by Contractor,
its officers, agents, employees, subcontractors, licensees or invitees whether or not any such injury,
damage or death is caused, in whole or in part, by the negligence or alleged negligence of
Owner, its officers, servants, or employees._Contractor likewise covenants and agrees to indemnify
and hold harmless the Owner from and against any and all injuries to Owner's officers, servants and
employees and any damage, loss or destruction to property of the Owner arising from the performance of
any of the terms and conditions of this Contract,whether or not any such injury or damage is caused
in whole or in part by the negligence or alleged negligence of Owner, its officers, servants or
employees..
In the event Owner receives a written claim for damages against the Contractor or its subcontractors prior
to final payment, final payment shall not be made until Contractor either (a) submits to Owner
satisfactory evidence that the claim has been settled and/or a release from the claimant involved, or (b)
provides Owner with a letter from Contractor's liability insurance carrier that the claim has been referred
to the insurance carrier.
_ The Director may, if he deems it appropriate, refuse to accept bids on other City of Fort Worth public
work from a Contractor against whom a claim for damages is outstanding as a result of work performed
under a City Contract.
7.
The Contractor agrees, on the execution of this Contract, and before beginning work, to make,
execute and deliver to said City of Fort Worth good and sufficient surety bonds for the faithful
,� performance of the terms and stipulations of the Contract and for the payment to all claimants for labor
and/or materials furnished in the prosecution of the work, such bonds being as provided and required in
Article 5160 of the Revised Civil Statutes of Texas, as amended, in the form included in the Contract
Documents, and such bonds shall be for 100 percent of the total contract price, and said surety shall be a
surety company duly and legally authorized to do business in the State of Texas, and acceptable to the
City Council of the City of Fort Worth.
8.
Said City agrees and binds itself to pay, and the said Contractor agrees to receive, for all of the
aforesaid work, and for all additions thereto or deductions therefrom, the price shown on the Proposal
submitted by the successful bidder hereto attached and made a part hereof. Payment will be made in
monthly installments upon actual work completed by contractor and accepted by the Owner and receipt of
., invoice from the Contractor. The agreed upon total contract amount(includinglexcluding)alternates
shall be Two Hundred 5:., -five Thousand Four Hundred Sixty-nine and
no/100.. ..Dollars,($265,469.00).
9.
It is further agreed that the performance of this Contract, either in whole or in part, shall not be
sublet or assigned to anyone else by said Contractor without the written consent of the Director of the
Department of Engineering.
10.
The Contractor agrees to pay at least the minimum wage per hour for all labor as the same is
classified, promulgated and set out by the City of Fort Worth, Texas,a copy of which is attached hereto
and made a part hereof the same as if it were copied verbatim herein.
11.
It is mutually agreed and understood that this agreement is made and entered into by the parties
hereto with references to the existing Charter and Ordinances of the City of Fort Worth and the laws of
the State of Texas with references to and governing all matters affecting this Contract,and the Contractor
agrees to fully comply with all the provisions of the same.
IN WITNESS THEREOF, the City of Fort Worth has caused this instrument to be signed in 8
counterparts in its name and on its behalf by the City Manager and attested by its Secretary, with the
corporate seal of the City of Fort Worth attached. The Contractor has executed this instrument through its
duly authorized officers in 8 counterparts with its corporate seal attached.
Done in Fort Worth,Texas,this the 9th day of December.A.D.,2008.
APPROVAL RECOMMENDED: CITY OF FORT WORTH
DIRECTOR,DEP OF
+� TRANSPORTATIONIPUBLIC WORKS FERNANDO COSTA,ASST CITY MANAGER
-2 ATTEST: _
SEc�
Burnsco Con ru ion, Inc.Jeff Morton
6331 Southwest Blvd. Secretary
Benbrook,TX 76132
CONTRACTOR
CITY SECRETARY
(SEAL)
BY: k�
Contract Authorizatiou
iNwsi=r-%>T' la 69
TITLE Date
APPROVED AS TO FORM AND
�p33/ �r,e3vD gRoamevc T5c LEGALITY:
ADDRESS 76r (K60,V11,
�3z
l !
ASST. L
November 1960
Revised May 1986
Revised September 1992
® RID
� E
4