Loading...
HomeMy WebLinkAboutContract 42788-CO1 (2), , City of Fort Worth Change Order Request Project Name! Cromwell Marine Creek Client Project #( s)j P227 541200 20728004 7883 ! City Sec# .__4_27_88 ____ __, Project Description! Bridge , Paving, and Sewer Improvements Contractor! Conatser Construction City Project Mgr.! Michael Perkins Dept. TPW Original Contract Amount $1 ,138,957.75 Extras to Date Credits to Date Pending Change Orders (in M&C Process) Contract Cost to Date $1 ,138,957.75 IAmount of Proposed Change Order $201,189.50 Revised Contract Amount $1 ,340,147.25 Original Funds Available for Change Orders $66 ,920 .00 Remaining Funds Available for this CO $66,920 .00 Additional Funding (if necessary) $134 ,269.50 69 1~ Change Order # Date City Inspector Jerry Taliaferro Totals $1 ,138,957 .75 $1 ,138,957.75 $201,189.50 $1,340 ,147 .25 $66,920.00 $66 ,920.00 $134 ,269 .50 CHANGE ORDERS to DATE (INCLUDING THIS ONE} AS % OF ORIGINAL CONTRACT MAX ALLOWABLE CONTRACT AMOUNT (ORIGINAL CONTRACT COST+ 25%} 17.66% $1,423 ,697.19 JUSTIFICATION (REASONS) FOR CHANGE ORDER 10/8/2012 Contract Time (CD) 294 294 30 324 This change order is required due to insufficient quantities in the bid documents for Fill Material-Borrow, Concrete RipRap , and Flaired Concrete Headwalls. The additional length of 18-inch and 36-inch Drilled Shaft was required to provide the minimum penetration of 8-feet into gray limestone as required by the plans . This change order also ~~letion for Temporary Retaining Walls. It was determined during construction that the temporary retain ing walls would not be ~~R 1' ,a~~" ~ I ooOOOOoo!r..o""' ff JJ.l o~~~ -~!:8 iz ~ .t:t O.~o o0 v~ ijgi g ~ ~ io lJf.J1 ~ * 00 00 .t:I Ooo oooooS .t:f ?'!.,-,1.EX ~~'°'Q' "I.~ \l.\j."\l.'li).""'" OFFICIAL RECORD CITY SECRETARY FT. WORTH, TX It is understood and agreed that the acceptance of this Change Order by the contractor constitutes an accord and satisfaction and represents payment in full (both time and money) for all costs arising out of, or incidental to, the above Change Order. M&C Number j c.-1...,,0 l i2 M&C Date Approved ! 1 i -11&· 12..- 0 1-·1 1-u Ai9 :44 I N FORT WORTH ----.--- Project Name Cromwell Marine Creek Client Project# P227 541200 207280047883 City of Fort Worth Change Order Additions Project Description Bridge , Paving , and Sewer Improvements Contractor Conatser Construction City Sec# Change Orde r # 1 Date 10/8/2012 City Project Mgr. Michael Perkins City Inspector Jerry Taliaferro ADDITIONS 111:.M uc:;:,1..,trn"' 1 IUN Ul:.J-'I lJty Unit Unit vOSt !S t-'av1ng & urainage Improvements : t-111 Matena1-t::Sorrow I l"'VV 1z,oo.::.uu l.,;Y :j,14 .UL 1 Bridge Improvements : Concrete RipRap -Install fPW bJ.UU l.,;Y $225.UL 'L t::Sridge Improvements : Bridge-Dr111ea ::snaft -Install ( 18" Drilled ::snaft) fPW 18.bU ,.., $65 .UL 3 Bridge Improvements: Bridge-Drilled ::snaft -Install lJti" Drilled ::snaft) fPW 18.UU ,.., :j>Z!SJ .UL ti'l.'l.l.,; Paving & Drainage Improvements : 24-mch Flaired Concrete Headwall fPW 2.UU EA $3 ,ZUU .UL OLJI.., Paving & Drainage Improvements : Jo-inch Fla1red Concrete Headwall fPW 1.UU EA $5 ,'l.UU.UL TPW Sub Total Add1t1ons Change Order Additions Page 2 of 4 42788 1ota1 :j)l lb , I .::o .UU :j,11 ,l:IZb .UU :j)l ,.::u.::.bU .)O ,Ul:14 .UU .)0,4UU .UU .)o ,.::uu .uu $205 ,549 .50 ~'l.Ub ,549 .bU FORT WORTH ---...,...-- Project Name Cromwell Marine Creek Client Project# P227 541200 20728004 7883 City of Fort Worth Change Order Deletions Project Description Bridge , Paving, and Sewer Improvements Contractor Conatser Construction City Sec# Change Order # 1 Date 10/8/2012 City Project Mgr . Michael Perkins City Inspector Jerry Taliaferro DELETIONS 111:.M Ut:::>vKII"' I IUN Ut:I"' I I.J.{'f Unit unit c.;ost 1/ ~nage Improvements: M::it:. 1-<etammg wa11 -install ( I emp . 1-<etammg Wall) I l"'VV !>4!>.UU ::ii-$Ii.VU TPW Sub l otal Deletions Change Order Deletions Page 3 of 4 42788 Total $4 ,Jt:>U .UU $4 ,360.00 $4 ,JoU .UU M/WBE Breakdown for this Change Order MWBE Sub Type of Service Amount for this CO Robert Granados Provide Haul-Off $24,500.00 Total $24,500.00 Previous Change Orders CO# DATE AMOUNT Total $0.00 -~ City of Fort Worth, Texas Mayor and Council Communication COUNCIL ACTION: Approved on 12/18/2012 DATE: Tuesday, December 18 , 2012 REFERENCE NO.: **C-26020 LOG NAME: 20SW_CROMWELL MARINE CREEK BRIDGE SUBJECT: Authorize Execution of Change Order No. 1 to City Secretary Contract No. 47288 with Conatser Construction TX , LP, in the Amount of $201 ,189 .50 for a Total Contract Amount of $1,340,147.25 for the Cromwell Marine Creek Bridge , Paving and Sewer Improvements Project (COUNCIL DISTRICT 7) RECOMMENDATION: It is recommended that the City Council authorize the execution of Change Order No. 1 to City Secretary Contract No . 47288 with Conatser Construction TX , LP , in the amount of $201 ,189.50 thereby revising the total contract amount to $1 ,340,147.25. DISCUSSION: On September 27 , 2011 , (M&C C-25198) the City Council authorized the award of a contract to Conatser Construction TX, LP , (Conatser) for this project. This change order is required primarily due to insufficient quantities in the bid documents for Fill Material , Concrete RipRap, and Concrete Headwalls . Also there were some small quantity adjustments , both additive and deductive , on work items for which it is not practical to determine precise measurements for the bidding process . The net effect of the proposed Change Order is as follows: Original Contract Amount Proposed Change Order No. 1 Revised Contract Amount AMOUNT $ 1,138,957.75 $ 201, 189.50 $ 1,340,147 .25 Costs for the implementation of Change Order No. 1 will be funded by the Stormwater Capital Projects Bond Fund. Conatser Construction TX, LP , is in compliance with the City's M/WBE Ordinance by committing to an additional 12 percent M/WBE participation on this Change Order No. 1. This project is located in COUNCIL DISTRICT 7 , Mapsco 47A. FISCAL INFORMATION/ CERTIFICATION: The Financial Management Services Director certifies that funds are available in the current capital budget, as appropriated, of the Stormwater Capital Projects Bond Fund . .. TO Fund/Account/Centers CERTIFICATIONS: Submitted for City Manager's Office by: Originating Department Head: Additional Information Contact: ATTACHMENTS FROM Fund/Account/Centers P227 541200 20728004 7883 Fernando Costa (6122) Douglas W . Wiersig (7801) Michael Perkins (2748) 1. 00478 Cromwell Marine Creek MWBE.pdf (CFW Internal) 2. 00478 Cromwell Marine Creek Map.pdf (Public) 3. FAR-00478-00008-C01.pdf (CFW Internal) 4. P227 485249 99901 pdf.pdf (CFW Internal) $201,189.50